Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. OF 2022
(Arising out of SLP(C) Nos. 15548-49 of 2021)
CENTRAL WAREHOUSING CORPORATION ...APPELLANT(S)
VERSUS
ADANI PORTS SPECIAL ECONOMIC
ZONE LIMITED (APSEZL) AND OTHERS ...RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. Leave granted.
th
2. The appeals challenge the judgment and order dated 30
June 2021 passed by the High Court of Gujarat at Ahmedabad
in Letters Patent Appeal (LPA) No. 22 of 2017 in Special Civil
Application (SCA) No. 184 of 2017 with SCA No. 5816 of 2017,
and Miscellaneous Civil Application No. 1 of 2021 in the above
Signature Not Verified
Digitally signed by
DEEPAK SINGH
Date: 2022.10.13
13:11:59 IST
Reason:
LPA, vide which the Division Bench of the High Court has
issued the following directions:
1
“(i) That Appellant – CWC is allowed three
months time from today either:-
(a) to seek and obtain approval as
a SEZ compliant Unit from the
competent authority under the SEZ
Act in respect of its Warehouse facility
situated in 34 acres of land in
question within SEZ Area developed
by Respondent – APSEZL;
or
(b) to obtain a waiver of the
conditions to comply with the
provisions of SEZ Act as a SEZ Unit
and the Competent Authority while
considering any such application of
CWC, if any filed by it, will provide
opportunity of hearing to both the
parties;
(ii) If CWC fails to get such approval as a SEZ
compliant Unit or waiver as aforesaid within
aforesaid period of three months, the
Respondent - APSEZL may acquire the land of
the same size of approximately 34 Acres
outside SEZ area as already identified and
selected by CWC, for the construction of a
Warehouse facility for the Appellant – CWC of
approximately same size as agreed between the
parties under Proposal Nos.1 and 2 in the
letter dated 9.3.2019 and affirmed by
subsequent correspondence and Board
Resolution dated 12.6.2019 of CWC and the
Affidavits of the parties filed in this Court.
Such acquisition of land and construction of
warehouse by the Respondent - APSEZL may
be completed within a period of one year after
the expiry of aforesaid period of three months
2
in Clause (i) above and same may be offered to
CWC to be occupied by the Appellant - CWC
on such terms and conditions in consonance
with the previous Agreement between the
parties vide Lease Agreement dated 2.6.2004
or under such mutually agreed terms as may
be agreed afresh between the parties.
(iii) Once the completed construction on the
land outside the SEZ Area, already identified
and selected by CWC, is offered to the
Appellant - CWC, the Appellant - CWC shall
vacate the existing premises of the
warehousing facility on the said 34 acres of
land situated within SEZ area within three
months of such communication of the
Respondent - APSEZL and the Appellant -
CWC shall be bound to hand over the peaceful
and vacant possession of existing warehousing
facility and land of 34 Acres in question to the
Respondent - APSEZL within such period of
three months of the communication of the
Respondent - APSEZL that new warehousing
facility on the land situated outside the SEZ
area is ready to be taken in possession and
occupied by CWC.
(iv) If the Appellant – CWC fails to hand over
the vacant and peaceful possession to the
Respondent, even thereafter, the Respondent -
APSEZL shall be free to approach this Court or
the concerned Development Commissioner or
the learned Single Judge or other authorities of
the State for appropriate execution of these
directions of this Court.
(v) That regarding Proposal No.3 about
underwriting of the future business loss of
CWC on the basis of published tariffs or
market tariffs or otherwise, the parties are left
3
free to make efforts for amicable settlement of
this issue between themselves with the help of
Development Commissioner or the Mediation
process under Section 89 of Civil Procedure
Code in the High Court annexed Mediation
Centre, where services of Senior Trained
Mediators can be made available to the parties
at the appropriate point of time.
(vi) For the aforesaid period of 18 months of
timeline involved in the aforesaid directions
namely, three months under Clause (i) and one
year or 12 months under Clause (ii) and three
months for handing over the vacant possession
under Clause (iii) aforesaid, the interim order
granted by the coordinate bench of this Court
on 11.1.2017 shall continue to operate
between both the parties.
(vii) That if the extension of the aforesaid time
period(s) becomes very necessary for
compelling reasons, both the parties shall be
at liberty to apply to the learned Single Judge
in the pending Writ Petition; being Special Civil
Application No.184 of 2017 and the learned
Single Judge keeping in view the conduct of
the applicant-party may grant such further
time as may be considered expedient and
necessary by the learned Single Judge.”
th
3. By an order dated 26 August 2021, the impugned
judgment and order came to be modified as under:
“3. In place of the words “already identified
and selected by CWC”, the following words will
be substituted in paragraph 33(ii) & (iii) of the
Judgment dated 30.06.2021:
4
“identified and proposed by the
Respondent APSEZL and finally
selected by CWC subject to the time-
frame prescribed in the present
Judgment.””
4. Being aggrieved by the aforesaid directions, the appellant-
Central Warehousing Corporation (for short, “CWC”) has
approached this Court.
5. The facts in brief giving rise to the present appeals are as
under:
The appellant-CWC was set up by the Government of India
in the year 1957 to provide support to the agricultural sector by
operating warehouses and Container Freight Stations across
the country. In the year 1962, the Warehousing Corporation
Act, 1962 (for short, “1962 Act”) came to be enacted. As such,
the appellant-CWC became a statutory Corporation under the
1962 Act. In the year 2000-2001, the Gujarat Maritime Board
(for short, “GMB”) executed a Lease and Possession Agreement,
thereby granting lease of an undeveloped land within New
Mundra Port Limits to Gujarat Adani Port Limited (for short,
“GAPL”). The said lease was granted for a period of 30 years.
5
Vide the said agreement, GMB also granted development rights
th
under a Concession Agreement dated 17 February 2001 to
GAPL to develop the port and other facilities.
nd
6. By an agreement dated 2 June 2004, GAPL sub-leased a
plot of land admeasuring about 34 acres to the appellant-CWC
for the purpose of setting up a warehouse to be used for storage
and handling of foodgrains, notified commodities and related
th
activities. The lease of the land was for a term up to 16
February 2031. After the said agreement was executed and the
possession of the said land was handed over to the appellant-
st
CWC on 1 October 2004, the appellant-CWC set up two
Godowns each with a capacity of 33,000 MT. The appellant-
CWC also made payments at the rate of Rs.603 per sq. metre,
i.e., about Rs.8.29 crores for the development of infrastructure
in the year 2005.
7. The Special Economic Zones Act, 2005 (for short, “SEZ
rd
Act”) came into force on 23 June 2005. The Special Economic
Zones Rules, 2006 (for short, “SEZ Rules”) were also notified on
th rd
10 February 2006. Vide notification dated 23 June 2006
6
issued by the Ministry of Commerce and Industry, Government
of India (for short, “Ministry of C & I), a vast area came to be
notified as a Special Economic Zone (for short, “SEZ”). The
th
appellant-CWC made a representation dated 10 April 2015 to
the Ministry of C & I for delineation/denotification of the said
34 acres of land from the SEZ. Till the year 2017, there was no
obstruction to the appellant-CWC in utilizing the said area.
th
8. A communication came to be addressed on 5 January
2017 by the respondent No.1-Adani Ports Special Economic
Zone Limited (hereinafter referred to as “APSEZL”) to the
appellant-CWC stating therein that, the appellant-CWC had
nd
violated Clause 4.2.3 of the agreement dated 2 June 2004,
which required the appellant-CWC to obtain and comply with
all approvals, consent and permits under the applicable law
pertaining to the sub-leased premises and activities proposed to
be carried out by the appellant-CWC. Vide the said
communication, the appellant-CWC was informed that APSEZL
has taken a decision of discontinuing the issuance of gate-
passes, and further that it would not permit the appellant-CWC
to continue the warehousing activities.
7
th
9. Being aggrieved by the communication dated 5 January
2017 and alleging that the same was causing obstruction in
free movement of vehicles and transportation of foodgrains etc.
to be stored at the warehousing facility, the appellant-CWC filed
the first writ petition being SCA No. 184 of 2017 before the
High Court. Since the learned Single Judge of the High Court
did not grant an interim relief while issuing notice, the
appellant-CWC filed LPA No. 22 of 2017. In the said LPA, vide
th
order dated 11 January 2017, the Division Bench of the High
Court had granted an ad-interim relief and directed the
respondents to allow the appellant-CWC to carry out the
activities of storing and transportation of its commodities to
and from the warehouse. The respondents were also directed to
issue gate passes for transportation till the next date of
hearing.
10. It further appears from the record that, in the meantime,
the request of the appellant-CWC for delineation/denotification
of the 34 acres of land in its possession from the SEZ area,
which was pending consideration, was considered by the
th
Ministry of C & I in its meeting held on 17 January 2017,
8
wherein it was decided to reject the said request of the
appellant-CWC to delineate/denotify the said land. The said
communication was communicated to the appellant-CWC on
th
25 January 2017. Being aggrieved thereby, the appellant-CWC
filed the second writ petition being SCA No. 5816 of 2017 before
the High Court.
11. It appears that thereafter, the said LPA came up for
hearing before the Division Bench on various occasions. It
further appears that there were also attempts to settle the
th
issues amicably. A perusal of the order dated 26 April 2019
passed by the Division Bench would reveal that an offer was
made by APSEZL that an equivalent plot of land outside the
limit of SEZ would be earmarked, whereupon a Godown of
similar size would be constructed at the expense of APSEZL
within a period of twelve months from the said date. Till then,
the appellant-CWC was to be permitted to carry on its activities
nd
as per the terms and conditions of the agreement dated 2
June 2004. The said proposal of APSEZL was placed before the
Board of Directors of the appellant-CWC (hereinafter referred to
9
th
as the “BoD”) on 12 June 2019. The BoD accepted the said
proposal in principle.
12. Thereafter, the matter was again listed before the Division
th
Bench on certain dates. On 28 January 2021, an adjournment
was again sought on behalf of the appellant-CWC to take
instructions from the Managing Director (for short, “MD”) of the
appellant-CWC. Vide order of the said date, the Division Bench
granted time as a last chance and the matter was directed to be
th th
posted on 9 February 2021. On 9 February 2021, the matter
th
was adjourned for 18 February 2021. Since both the parties
informed the High Court that the settlement is not possible, the
th
High Court directed the matter to be kept on 17 March 2021.
Thereafter, due to COVID, the matter could not be listed and
th
finally, it was listed on 30 June 2021, on which date the
impugned judgment and order was passed.
13. We have heard Shri Maninder Singh, learned Senior
Counsel appearing on behalf of the appellant-CWC and Shri
Shyam Divan, learned Senior Counsel appearing on behalf of
the respondents.
10
14. Shri Maninder Singh submitted that the Division Bench
has failed to take into consideration that the area admeasuring
34 acres in possession of the appellant-CWC could not have
been included in the SEZ areas. He submitted that as per Rule
7 of the SEZ Rules, the developer is required to furnish to the
Central Government, particulars required under sub-section (1)
of Section 4 with regard to the area referred to in sub-section
(2) or sub-section (4) of Section 3 of the SEZ Act. He submitted
that, along with the said information, the developer is also
required to submit a proof of legal right and possession and a
certificate from the State Government or the authorized agency
that the said area is free from all encumbrances. It is submitted
that, as per sub-rule (2) of Rule 7 of the SEZ Rules, the
identified area is required to be contiguous and vacant. He
submitted that APSEZL has suppressed the material fact that
the possession of the said area of 34 acres was not with it but
with the appellant-CWC. He submitted that, had this fact been
brought to the notice of the authorities, the area in possession
of the appellant-CWC could not have been included in the SEZ
areas.
11
15. Shri Maninder Singh submitted that from Clause 2.1 of
nd
the agreement dated 2 June 2004 itself, it is clear that the
warehousing infrastructure and the leased premises was
required to be set up by the appellant-CWC in accordance with
the plan as approved by APSEZL (then GAPL). It is submitted
that, in accordance with the said clause, the appellant-CWC
th
had submitted plans on 25 July 2006. The said plans were
duly approved by the then GAPL. It is submitted that, in
addition to the aforesaid, the then GAPL has itself been using
the warehousing facilities provided by the appellant-CWC from
the year 2006 onwards.
16. Shri Singh further submitted that the Ministry of
Consumer Affairs, Food and Public Distribution, Government of
India (hereinafter referred to as the “Ministry of CAF&PD”),
which is the controlling Ministry of the appellant-CWC, has also
been supporting the stand of the appellant-CWC. It is
submitted that however, the Ministry of C&I has been, on an
untenable ground, refusing the request of the appellant-CWC
for delineation/denotification of the land occupied by it. It is
submitted that, though the Ministry of C&I has taken a stand
12
in case of the appellant-CWC that there is no provision in the
SEZ Act and Rules which empowers the authorities to grant a
waiver as requested, the Ministry of CAF&PD, vide
th
communication dated 13 September 2013, has informed the
Chief Secretaries of all the States that in certain cases, such
request could be accepted. It is submitted that, not only this,
st th
but vide notifications dated 31 May 2013 and 4 July 2019,
certain areas have been delineated/denotified from the said
SEZ areas at the request of APSEZL. It is submitted that when
such a request could be allowed at the behest of APSEZL, there
is no rhyme or reason as to why the request of the appellant-
CWC could not be considered by the Ministry of C&I.
17. Shri Singh further submitted that the High Court has
totally erred in castigating the appellant-CWC. It is submitted
that the observations of the High Court that the appellant-CWC
was having an ego in the matter and was not reasonable are
totally unwarranted. He submitted that the impugned judgment
and order of the High Court is almost thrusting a part of the
settlement on the appellant-CWC. He submitted that the
relocation of the warehouse to a new location on rent as per the
13
published tariff of the appellant-CWC is not the solitary
decision of an individual. It is submitted that the BoD has
accepted the proposal for settlement on three conditions. As a
matter of fact, APSEZL itself had agreed on all the three
th
conditions vide its communication dated 9 March 2017.
th
However, it unilaterally, vide communication dated 10 June
rd
2019, resiled from the 3 condition. Though the High Court
has directed the appellant-CWC to abide by the first two
rd
conditions, it has failed to direct APSEZL to abide by the 3
condition.
18. Shri Singh submitted that the conduct of the Ministry of
C&I in rejecting the proposal of the appellant-CWC for
delineation/denotification of the said land from SEZ areas vide
th
its order dated 17 January 2017 is itself under a cloud of
doubt. He submitted that, in SCA No. 184 of 2017, the notice
th th
was issued on 10 January 2017 returnable on 17 January
2017. However, by the Minutes of the Meeting of the Ministry
of C&I passed on the very same day, the said proposal was
rejected. It is seen that the conduct of the Ministry of C&I in
14
deciding the matter on the very same day on which notice was
made returnable, speaks volumes of its conduct.
19. Shri Divan, on the contrary, submitted that insofar as the
writ petition being SCA No. 184 of 2017 is concerned, the same
is not at all tenable. He submitted that APSEZL is not a public
body and as such, a writ against it would not be tenable. It is
submitted that insofar as the second writ petition being SCA
No. 5816 of 2017 is concerned, no effective hearing has taken
place in the said proceedings. Shri Divan further submitted
that there is no challenge made by the appellant-CWC to the
rd
notification dated 23 June 2006. The said notification has
been issued in accordance with the provisions of the SEZ Act.
He submitted that the appellant-CWC, having not challenged
rd
the validity of the said notification dated 23 June 2006, no
relief could be granted in the said writ petition filed by it,
contrary to the statutory provisions.
th
20. Shri Divan submitted that, as early as on 26 March
2007, APSEZL had given the proposal to the appellant-CWC to
allot an equivalent plot at an alternative location. The said
15
rd
proposal was further reiterated by APSEZL on 23 May 2007.
st
Vide another communication dated 31 August 2007, APSEZL
has proposed to utilize the warehousing facility to be
constructed on the sub-leased area for a minimum period of
three years. However, the same was not positively responded to
by the appellant-CWC. As such, APSEZL was required to issue
th
a communication dated 5 January 2017 inasmuch as the
continuation of the warehousing facility was in contravention of
the SEZ Act.
21. Shri Divan submitted that a perusal of Rule 17 of the SEZ
Rules would reveal that a proposal has to be submitted for
approval to the Development Commissioner for setting up of a
Unit in SEZ. Under Rule 18 (2)(i) of the SEZ Rules, it is
required that the proposal meets with the positive net foreign
exchange earning requirement. Under Rule 19 of the SEZ
Rules, unless the proposal is approved by the Approval
Committee and unless the Development Commissioner issues a
letter of approval in Form G, no Unit can be established. Shri
Divan has submitted that sub-rule (v) of Rule 11 would make
the position clear. Shri Divan has further submitted that the
16
th
communication dated 13 September 2013 issued by the
Ministry of C&I clearly provides that a proposal for seeking
delineation/denotification cannot be considered unless such a
proposal has an unambiguous ‘No Objection Certificate’ from
the State Government concerned.
22. Shri Divan further submitted that in view of the provisions
of Section 51 of the SEZ Act, the provisions of the said Act will
have an overriding effect. He has further submitted that
various documents have been placed on record by the
appellant-CWC which were not placed before the High Court
and as such, the same cannot be taken into consideration.
23. Shri Divan further submitted that, as a matter of fact,
after the order was passed by the High Court, the appellant-
CWC had made a representation to the Development
th
Commissioner on 17 August 2021 requesting for
delineation/denotification of the plot in question. The same
has already been rejected by the Development Commissioner by
th
its order dated 7 September 2021. He therefore submitted
17
that, as a matter of fact, nothing survives in the present
proceedings.
24. Insofar as the contention of the appellant-CWC with
regard to non-compliance with the provisions of Rule 7 of the
SEZ Rules, it is submitted that the application was made by the
th
then GAPL under the old regime on 9 January 2004. The
th
same was approved on 12 February 2004. The notification
th
was issued on 5 July 2004. As such, the SEZ Act, which has
come into effect in the year 2005 and the SEZ Rules in the year
2006, would not be applicable. It is therefore submitted that
the arguments advanced on that behalf are without substance.
25. Shri Divan submitted that, though APSEZL was not duty
bound to provide an alternate site to the appellant-CWC, it
gratuitously agreed to give to the appellant-CWC an alternate
site of the same size. Not only that, it also agreed to construct
the Godowns of the same size as were in existence. As such,
the directions, which were issued are, in fact, for the benefit of
the appellant-CWC and there is no reason as to why the
appellant-CWC should have challenged the same. Shri Divan
18
relies on the judgments of this Court in the cases of
Krishnadevi Malchand Kamathia and Others v. Bombay
1
Environmental Action Group and Others and Ratnagiri
Nagar Parishad v. Gangaram Narayan Ambekar and
2
Others in support of the proposition that the appellant-CWC,
th
having not challenged the notification dated 5 July 2004, is
estopped from arguing contrary thereto.
26. In our considered view, the present case, rather than
being decided on law, requires to be decided on the factual
position as emerges from the record. It is not in dispute that,
after the land was leased to the then GAPL by the GMB in the
year 2000-2001, it entered into an agreement with the
nd
appellant-CWC on 2 June 2004 with regard to the area
admeasuring 34 acres. It is also not in dispute that the
appellant-CWC was put in possession of the said plot and has
constructed the warehouse on the same. It is also not in
dispute that after the construction of the warehouse, the
storage facilities were being utilized by the then GAPL.
1
(2011) 3 SCC 363
2
(2020) 7 SCC 275
19
However, it appears that in the year 2007, for the first time, the
then GAPL made a proposal for swapping the land and
construction of the warehouse on the swapped land. It further
appears that, though certain communications were addressed,
there was no hindrance on the operations of the appellant-CWC
th
till 5 January 2017. From a perusal of the communication
th
dated 5 January 2017, it is seen that the appellant-CWC was
restrained from continuing with the activities in the said
premises. It further states that the appellant-CWC would not
be able to get gate passes for the SEZ until the appellant-CWC
either (a) obtains a Letter of Approval (LOA) from Development
Commissioner (DC) as a SEZ Unit in compliance with the
provisions of SEZ Act/Rules; or, (b) obtains specific permission
from DC to carry out the activities of warehousing & stuffing
etc. in the said premises in the SEZ by waiving the requirement
of being approved as an SEZ-compliant Unit.
27. A perusal of the record would reveal that, immediately
th
after the said communication dated 5 January 2017 was
passed, the appellant-CWC filed SCA No. 184 of 2017. In the
th
said writ petition, vide order dated 10 January 2017, notice
20
th
was issued returnable on 17 January 2017. Since the interim
relief was not granted in the said writ petition, the appellant-
CWC preferred LPA No. 22 of 2017, wherein the Division Bench
th
has passed the order dated 11 January 2017, which reads
thus:
“4. In the communication dated 5th January
2007, reference is made to Rule 11(5) and Rule
11(7) of the SEZ Rules, applicability or
otherwise of the said Rules is a matter which is
required to be considered in the petition
pending before the learned single Judge. As it
is the case of the appellant that since 2005,
the appellantCorporation is using the leased
area after making constructions for storage
and for transportation of food grains, if
abruptly they are stopped from using the
same, public interest will suffer. In view of the
same, by way of ad-interim relief, the
respondents are directed to allow the
appellant-Corporation to carry out the activity
of storing and transportation of their
commodities in and from the warehouse. The
respondents are further directed to issue
necessary gate passes for transportation till
the next date of hearing.”
28. It appears that after the notice was issued in SCA No. 184
th
of 2017 which was returnable on 17 January 2017, a meeting
was held between the Development Commissioner, MD of the
appellant-CWC and the President of APSEZL. It will be relevant
21
th
to refer to the Minutes of the said Meeting dated 17 January
2017, which read thus:
“2. Explaining the background, DC, APSEZ
informed that in Dec 2002, CWC has entered into
MoU with APSEZ for two plots in the SEZ
measuring 40 acres and 34 acres. Lease agreement
for the plot for 34 acres, which is now in dispute,
was signed in June 2004. CWC took possession of
the same but did not get the agreement registered
with the Revenue authorities. He informed that
subsequently, on 23.06.2006, Mundra SEZL, now
APSEZL, was notified which included the 34 acres
with CWC. CWC constructed its warehouse on the
piece of land. In September 2008, DC, APSEZ
issued notice to CWC for non-compliance of
provisions of SEZ Act and Rules and requested
APSEZL to initiate action to exclude the plots with
CWC from SEZ limits. CWC, on 14.10.2008,
requested APSEZ Ltd. to initiate action to exclude
its both plots from the SEZ limits. Although EGoM,
in Oct 2008, had decided to delineate pre-existing
structures in the port area built prior to the
notification of 23.06.2006, the plot with CWC were
not delineated as perhaps the CWC Godown had
come up after 23.06.2006. He mentioned that CWC
is carrying out container stuffing in its Godown
which was against the provision of SEZ Act and
Rules. The developer, on 19.03.2015, asked CWC
to discontinue all activities from the Godown.
Thereafter, on 10.04.2015, CWC approached DoC
for delineating the warehouse from the SEZ. In Oct
2015, the developer offered an alternative site to
CWC, which was rejected by CWC. It was also
stated that on 05.01.2017, the developer wrote to
CWC to stop its operation and that CWC obtained a
stay against this letter from the Hon’ble High Court
of Gujarat.
22
3. The representatives from CWC informed that
they have entered into the agreement with APSEZL
in 2004 for a period of 30 years. APSEZ had not
informed CWC that the land in question was
included in the proposed SEZ which was notified in
June, 2006. It was also stated that since CWC had
made investment of Rs. 60 crores in construction of
the warehouse, the CVC had advised it that it
should not move out without proper arrangement.
It was also stated that presently MMTC was storing
26,000 tonnes of imported pulses as buffer stock for
the GoI. Since APSEZL had arbitrarily stopped this
storage and therefore CWC had to approach Hon’ble
High Court for stay. CWC representatives therefore
reiterated that since they are having an agreement
of 30 years lease from APSEZ, they are a Central
Government PSU, they have already invested more
than Rs. 60 cr. in warehouse and they are operating
peacefully, they should be allowed to do business
from the warehouse within the SEZ.
4. The representatives of APSEZL informed that as
per the agreement entered with the CWC, 30 year
agreement had to be registered within four months
without penalty and within 8 months with penalty.
CWC had not taken any action for getting the
agreement registered within the said period and
therefore the agreement had become null and void.
It was stated that APSEZ was willing to give
alternative plot to CWC for creating a new
warehouse and also that it had explored the
possibility of delineation and de-notification of the
area in possession with CWC. However the same
was not feasible.
5. It was made clear that there was no possibility of
any delineation as there was no provision in the
SEZ Act or SEZ Rules for such delineation. It was,
therefore, advised representatives of CWC to
amicably sort out the issue with APSEZL by either
23
becoming a SEZ Unit in the SEZ or become a do-
developer in the SEZ after ascertaining the
provisions and requirements under SEZ Unit Act,
2005 and SEZ Rules, 2006. If required, the matter
may be put up before the BoA for its consideration.”
29. It is to be noted that the appellant-CWC is a statutory
corporation. It cannot act as per the independent decisions of
any officer and has to act in accordance with the resolution of
the BoD.
30. In this background, it will be relevant to note that, as
early as in the year 2010, there was a complaint against one of
the Directors of the appellant-CWC before the Central Vigilance
Commission (for short, “CVC”). The CVC issued an office
th
memorandum on 12 January 2010. The relevant part of the
said office memorandum reads thus:
“2……
(i)……….
(ii) Further, it is observed that due to the
presence of CWC warehouse (a Central Govt.
PSU), various kinds of developmental activities
has been undertaken by the other related
Govt. undertaking like Railway etc. and due to
which the importance/value of the land/area
has now been greatly increased. By shifting
24
this warehouse to another place, M/s GAPL
will be unduly benefited and at the same time
CWC will not only loose business but also have
to struggle a fresh in creating the same kind of
infrastructure in the new location with the
help of other govt. agencies. In case in the
vicinity of the area presently occupied by CWC,
liquid cargo will be stored than even CWC can
possibly think of developing liquid cargo
storage facilities in the area presently occupied
which can be used by M/s GAPL and others.
Secondly, for the bulk cargo another location
as offered by M/s GAPL can be freshly
acquired by negotiating fresh terms &
conditions.
(iii) It is also requested to keep the
Commission posted regarding the future
developments in this regard.
3. Commission has further observed that there
may be vested interest in shifting of CWC
warehouse-apart from the cost involved and
possibility of loosing business by CWC, hence,
it will be desirable to have a close check on the
issue and monitor its progress/developments.”
31. The CVC has clearly observed that due to the presence of
CWC warehouse, various kinds of developmental activities have
been undertaken by other related government undertakings like
Railway etc. It has further been observed that by shifting the
warehouse to another place, GAPL will be unduly benefited and
25
at the same time, the appellant-CWC will not only lose business
but will also have to struggle afresh in creating the same kind
of infrastructure at the new location. The CVC further observed
that there could be a vested interest in shifting of the CWC
warehouse.
32. It is further to be noted that, though the Ministry of C&I
has been taking a stand that the delineation/denotification was
not permissible, another Ministry of the Union of India has
been taking a contrary stand. It will be relevant to refer to the
communication addressed by the Ministry of CAF&PD dated
st
31 July 2017, thereby specifying the stand to be taken on its
behalf, as thus:
“(i) With regard to non registration of the
agreement dated 02.06.2004 between GAPL
and CWC, it has been informed by CWC that
the land was physically banded over by GAPL
to CWC on 01.10.2004 and thereafter, CWC
started construction of warehouse on the land.
CWC has been paying lease rent and GAPL has
been accepting the same. Even GAPL has
stored its cargo in the godowns of CWC on the
same plot of land. Thus the lease has existed
by virtue of the actions taken by both the
parties. Moreover, GAPL has not denied
signing the agreement Hence, the agreement
cannot be treated as illegal.
26
(ii) With regard to obligations of CWC to obtain
and comply with all approvals, consents and
permits under the applicable law pertaining to
the sub-leased premises and activities and the
contention of APSEZL that CWC has failed to
obtain necessary approvals under SEZ Act, it
is informed that CWC has fulfilled its
obligations as per the agreement dated
02.06.2004 for warehousing activities. CWC
was not required to take any approval under
SEZ Act since the area became SEZ later and
CWC has no intention of becoming part of SEZ
and also since APSEZL has included the sub-
leased premises of CWC in the SEZ area by
suppressing the facts. APSEZL should have
included only those areas which it owned/
possessed at the time of submitting proposal
for notification of SEZ. APSEZL should not
have included the sub-leased premises of CWC
for notification of SEZ without the consent of
CWC, since CWC had already taken possession
of the plot on l.l0.2004 i.e. much before the
date of SEZ notification (23.06.2006). As per
SEZ rules (Annexure-6) having a contiguous
parcel of land is a primary requirement for the
developer to apply for notification of any area
as SEZ. It appears that APSEZL (formerly,
GAPL) have suppressed information regarding
the sub-leased premises, otherwise it would
have not got the approval for declaring the
area as SEZ. Thus, the whole contention of
APSEZL is based on suppression of facts.
(iii) With regard to the contention of APSEZL
that CWC has failed to obtain necessary
approvals under SEZ Act, it is further
intimated that it is the obligation of APSEZL as
the developer to de-lineate and de-notify the
sub-leased premises of CWC from SEZ area.
Since APSEZL did not take any action in this
27
regard, CWC took up the matter with Ministry
of Commerce on 10.04.2015 for de-lineation
and de-notification of its plots. The
Department of Food and Public Distribution
also took up this matter on behalf of CWC
before the Department of Commerce vide
letters dated 17.07.2015 and 17.06.2016.
(Annexure-2)
(iv) With regard to minutes of meeting held on
17.01.2017 in Department of Commerce,
wherein it has been stated that there was no
possibility of de-lineation as there was no
provision in SEZ Act and SEZ rules for such
de-lineation, the Department of Food and PD is
of the view that the stand of Department of
Commerce is not correct. In fact, there are
provisions for de-lineation/partial de-
notification of areas within SEZ which have
been circulated by Department of Commerce
vide letter No. D.J2/4S/2009-SEZ dated
13.09.2013 (Annexure-3). However, as per
these provisions, it is the responsibility of the
developer i.e. APSEZL to take action for such
de-lineation or partial de-notification. There is
precedent for such partial de-notification,
which has taken place in the SEZ at Jamnagar
on the initiative of the Developer (M/s Reliance
Industries) at that SEZ, as per newspaper
report in The Hindu Business Line published
on 18.01.2013(Annexure-4). Thus, it is
apparent that APSEZL first included the sub-
leased premises of CWC in SEZ by suppressing
the facts and now it is not taking action for de-
notification of the same premises.
Additional Point
APSEZL has not only suppressing the facts by
including CWC's premises in the SEZ Area, but
also has attempted several times to take
28
possession of CWC's plot by offering CWC
alternate land far away from Mundra port. The
value of CWC's plot has appreciated several
times due to development around it and the
alternate land is not only of low value but also
less suitable from business point of view for
CWC. CWC has not agreed to this proposal for
alternate land due to serious financial
implications. When the proposal of exchange of
land was being examined by the management
of CWC, a complaint was made against the
then Director (Finance) of CWC before the
Central Vigilance Commission (CVC). While
disposing of this complaint, CVC observed vide
OM No. 008/FUD/017170378 dated
12.01.2010 (Annexure-S) that "by shifting
CWC warehouses to another place, M/s GAPL
will be unduly benefited and at the same time
CWC will not only loose business but also have
to struggle a fresh in creating the same kind of
infrastructure in the new location with the
help of other govt. agencies". CVC has further
observed that "there may be vested interest in
shifting of CWC warehouse apart from the cost
involved and possibility of losing business by
CWC, hence, it will be desirable to have a close
check on the issue and monitor its
progress/developments". CVC has also
requested the Department of Food and PD to
keep the Commission posted regarding the
future developments in this regard. In view of
these observations of CVC, since CVC's
instructions are applicable to all Departments
of Govt. of India, it is responsibility of
Department of Commerce to accept the request
of CWC for de-notification of its premises.”
29
st
33. A perusal of the said communication dated 31 July 2017
would reveal that, as per the Ministry of CAF&PD, the
appellant-CWC has fulfilled its obligations as per the agreement
nd
dated 2 June 2004 for warehousing activities. It is also the
stand of the said Ministry that APSEZL has included the sub-
leased premises of the appellant-CWC in the SEZ areas by
suppressing the facts. It is stated that, since the appellant-
st
CWC has already taken possession of the plot on 1 August
rd
2004, i.e., much before the date of SEZ notification dated 23
June 2006, the said area could not have been included in the
SEZ areas. It is stated that, since it was the obligation of
APSEZL to take action to delineate/denotify the sub-leased
area, and since it has taken no such steps, the appellant-CWC
was required to take up the matter with the Ministry of C&I.
The said communication clearly states that the view of the
Ministry of C&I that there was no possibility of
delineation/denotification was not a correct stand. It is also
stated that there are also precedents of such partial
denotifications taking place. It has been stated that the value
of the plot of the appellant-CWC has appreciated several times
30
due to development around it and the alternate land is not only
of low value but also less suitable from a business point of
view. It is stated that the appellant-CWC has also not agreed to
this proposal for alternate land due to serious financial
implications. A reference has also been made to the office
th
memorandum of the CVC dated 12 January 2010 referred to
hereinabove.
34. It is further pertinent to note that, in the meantime, being
th
aggrieved by the Minutes of the Meeting dated 17 January
2017, the appellant-CWC had preferred the second writ petition
being SCA No. 5816 of 2017 before the High Court. The
prayers of the said writ petition read thus:
“(a) To issue a writ of certiorari or a writ, order
or direction in the nature of certiorari
quashing and setting aside the decision taken
by the Ministry of Commerce in a meeting held
on 17.01.2017, as communicated to the
petitioner Corporation under letter dated
25.01.2017, as being illegal, arbitrary and bad
in law;
(b) To issue a writ of mandamus, or a writ,
order or direction in the nature of mandamus
directing the Ministry of Commerce,
Government of India to consider the request of
31
the Corporation for denotifying the area of land
leased to it in the year 2004 and over which it
has constructed a warehouse in light of the
report of the Central Vigilance Commission,
correspondence exchanged between the
Corporation, Ministry of Consumer Affairs,
Food and Public Distribution and the
Developer, and in accordance with law;”
th
35. Vide order dated 26 April 2019 in SCA No. 5816 of 2017,
the same was directed to be placed along with LPA No. 22 of
2017.
36. It appears that during the pendency of the said LPA, there
were proposals and counter proposals. It is relevant to note that
th
a proposal was submitted by APSEZL on 9 March 2019. The
salient features of the said proposal read thus:
“APSEZ to offer alternate location in Non-
SEZ area of Mundra Industrial Estate is of
the same size i.e. approx. 34 acres.
APSEZ will construct the warehouse as per
the existing dimensions of the existing
warehouse after discussing the same with
you.
To give comfort to CWC, APSEZ is willing to
underwrite the revenue risk for CWC by
taking the warehouse at new location on
rent as per your published tariff for the
balance period of lease.”
32
37. The said proposal was put up for consideration before the
BoD. The BoD, in principle, accepted the said proposal on the
following conditions:
“(i) M/s. APSEZ may provide a suitable
alternative land of the same size as the
existing one as selected by CWC outside the
SEZ area at Mundra Port.
(ii) A godown of 66000 MT (as per existing)
may be created by M/s. APSEZ as per the
specification of CWC, within the period of
twelve (12) months .
(iii) M/s. APSEZ shall take the whole covered
space so created along with remaining open
area at CWC’s existing public tariff with 6%
annual escalation (compoundable) on
dedicated warehousing basis for entire period
of lease i.e. till 16.2.2031, underwriting the
business and other risks of the Corporation
and shall sign an agreement , giving suitable
amount of bank guarantee to this effect .”
38. It could thus be clear that APSEZL, in its proposal dated
th
9 March 2019, had agreed to underwrite the revenue risk of
the appellant-CWC by taking the warehouse to a new location
on rent as per the published tariff of the appellant-CWC for the
balance period of lease, and the same was accepted by the
appellant-CWC only with a rider that APSEZL shall sign an
33
agreement giving a suitable amount of bank guarantee to the
said effect.
39. However, after a period of almost three months, APSEZL
th
retracted from its proposal dated 9 March 2019 vide its
th
communication dated 10 June 2019, which reads thus:
“Dear Sir,
This has reference to our letter dated March
9, 2019 and your reply dated April 4, 2019 ,
subsequently our teams have been working
together for last 3 months in order to arrive at
a mutually beneficial solution.
With reference to our letter dated March
9,2019 wherein, along with offering an
alternate location for relocation of your
existing facility we had suggested to
underwrite the revenue risk for CWC for the
warehouse at new location on rent. We
would like to clarify that such underwriting
of revenue risk should be done based on
Market rates which can be mutually worked
out as the existing published tariff is too
high when compared to the market rates of
similar type of warehouses.
Further as discussed during the meeting with
your Director (M&CP), CWC we would like to
work out a One Time Settlement (OTS),
which we believe would be the most efficient
and quick resolution of this issue and we are
awaiting your proposal and response in this
regard.”
34
40. It could thus be seen that, though all the three conditions
th
as stated in the proposal of APSEZL dated 9 March 2019 were
th
accepted by the BoD in its meeting dated 12 June 2019, in the
rd
meantime, APSEZL unilaterally retracted from the 3 condition.
41. Vide the impugned judgment and order, the High Court
has, in fact, held that though the appellant-CWC was bound by
the first two conditions as agreed between the parties, the
rd
second respondent was not bound by the 3 condition as was
th
offered by APSEZL on 9 March 2019 and subsequently
th
retracted on 10 June 2019.
42. The Division Bench goes on to hold that, since there was a
consensus on the first two conditions and no consensus on the
rd
3 condition, the appellant-CWC was bound by the first two
rd
conditions and insofar as the 3 condition is concerned, it was
open for the parties to settle the same amicably between
themselves or through mediation. The Division Bench further
rd
observed that though APSEZL had initially proposed the 3
condition, it had immediately explained and clarified the same
35
th
in its next letter dated 10 June 2019. In the view of the High
Court, a period of three months is ‘immediate’.
43. We find the said approach of the Division Bench wholly
untenable.
44. We are of the view that the approach adopted by the
Division Bench was, in fact, forcing the appellant-CWC, which
is a statutory body, to accept the settlement. Vide order dated
th
28 January 2021, the Division Bench goes on to observe that
they were prima facie of the opinion that, while the first two
conditions taken by the appellant-CWC in its meeting dated
th rd
12 June 2019 appeared to be fair and reasonable, the 3
condition which also takes into account the future working
escalation, costs etc. does not appear to be fair and may
unnecessarily make the dispute linger on. After observing this
and granting a short accommodation to the counsel for the
appellant-CWC to take instructions from the MD of the
appellant-CWC, the Division Bench observed thus:
“9. We make it clear that any further delay in
their decision-making will not be allowed and if
the said settlement is not agreeable to the
appellant – Central Warehousing Corporation,
36
an Affidavit of the Managing Director of the
appellant – Central Warehousing Corporation
disclosing the reasons for the same may be
submitted, on which, appropriate orders may
be passed by this Court on next date.”
45. The High Court, in effect, forces the MD of the appellant-
CWC, which is a statutory body, to accept the first two
rd
conditions and leave the 3 condition to be settled mutually
th
through mediation. The offer given by APSEZL on 9 March
2019 was a composite one so also the acceptance thereof by the
appellant-CWC was a composite one. The acceptance of the
rd
first two conditions was also dependent upon the 3 condition.
If the High Court was so concerned about settlement of the
dispute, then, while compelling the appellant-CWC to accept
the first two conditions, it also ought to have compelled APSEZL
rd
to accept the 3 condition.
46. The Division Bench of the High Court, in paragraph (24),
observed thus:
“24. We are little surprised and also pained at
the reticent attitude of the Appellant - CWC, a
Central Government Undertaking to have an
insistent and persistent approach to remain
non-compliant with law and trying to exert
pressure on the private Respondent because of
37
its own status. We fail to understand how a
body corporate of the stature of CWC can have
any ‘Ego’ which is a vice of a human being and
a juristic person, of course managed by human
beings, can definitely have a better democratic
and consensual decision making process at its
top level. The CWC in the present case, is not
only in this spree of litigation against the
private Respondent - APSEZL but also against
its own parent, namely, the Central
Government challenging its action of not
agreeing with the CWC to exclude its existing
area of Warehouse from the SEZ Area, which
was allotted to the private Respondent -
APSEZL and is being developed by them in
accordance with the provisions of SEZ Act,
2005 and Rules made thereunder just because
under a sub-lease given by APSEZL to CWC, it
had already constructed a Warehouse there,
before a much larger area of more than 5000
Acres including that warehouse area of 34
Acres was declared as a SEZ area under the
special and overriding law.”
47. We find the said observations of the Division Bench totally
unwarranted. The High Court ought to have taken into
consideration that the appellant-CWC was a statutory body.
There are already observations made by the CVC as early as in
the year 2010 that the swapping of the warehousing facility
from the present site to a changed site would cause serious
financial implications and also that there could be various
38
vested interests involved. The CVC had also observed that
there was also a possibility of losing business. Further, the
Division Bench totally ignored the stand taken by the Ministry
of CAF&PD, which too had opposed such a swapping. Rather
than the High Court being surprised with the conduct of the
appellant-CWC, it is we who are surprised with the
observations made by the High Court. When an issue involved
the balancing of interests of a statutory Corporation and a
private company, the approach of the High Court ought to have
been a balanced one. The High Court ought to have taken into
consideration that, unless all the three conditions were
complied with, the interest of the appellant-CWC, which is a
statutory Corporation, could not have been safeguarded. If a
settlement was to be arrived at, unless the same was found to
be in the interest of both the parties, it could not have been
thrust upon a statutory Corporation to its detriment and to the
advantage of a private entity.
48. In any event, the writ petitions before the learned Single
Judge are very much pending. If the impugned order of the
High Court remains in force, there remains nothing to be
39
decided in the said writ petitions. The question as to whether
the first writ petition is tenable or not will be a question that
will have to be decided by the learned Single Judge.
Undisputedly, the second writ petition which seeks a relief
against the statutory authorities is very much tenable in law.
We are of the considered view that the best course available
with the Division Bench was to direct the learned Single Judge
to decide the petition on its merits.
49. We are therefore of the considered view that the impugned
th
judgment and order of the High Court dated 30 June 2021 is
not sustainable in law.
50. Before we part with the judgment, an important issue has
invited our concern. The stands taken by two ministries of the
Union of India are diagonally opposite to each other. On one
hand, the Ministry of C&I has held that the
delineation/denotification as sought by the appellant-CWC is
not permissible in law as could be seen from the Minutes of the
th
Meeting dated 17 January 2017. Not only that, after the order
passed by the High Court, the appellant-CWC had again
th
applied on 17 August 2021 for either delineating the area from
40
APSEZL or, in the alternate, to grant waiver/exemption to it
from complying with the conditions/obligations applicable to
SEZ Units. However, the specified officer of APSEZL, vide
th
communication dated 7 September 2021, has rejected the said
prayer on the ground that there is no provision in the SEZ Act
and Rules which empowers the authority to grant such a
waiver.
51. On the other hand, the Ministry of CAF&PD has taken a
stand that such a delineation/denotification is permissible in
law and has also stated that there are precedents for doing so.
The learned Senior Counsel for the appellant-CWC has also
placed on record certain notifications vide which certain areas
have been denotified at the instance of APSEZL. We do not
wish to dwell into that area inasmuch as it will have a direct
bearing on the second writ petition filed by the appellant-CWC.
We do not propose to prejudice the rights of either of the parties
by observing anything with regard to this. It is also a stand of
the Ministry of CAF&PD that shifting of the warehouses to the
alternate locations would be against the interest of the
appellant-CWC as well as public revenue.
41
52. We are of the considered view that it does not augur well
for the Union of India to speak in two contradictory voices. The
two departments of the Union of India cannot be permitted to
take stands which are diagonally opposite. We may gainfully
refer to the following observations made by a three-Judges
Bench of this Court in the case of Lloyd Electric and
Engineering Limited v. State of Himachal Pradesh and
3
Others :
| “14. The State Government cannot speak in | |
|---|---|
| two voices. Once the Cabinet takes a policy | |
| decision to extend its 2004 Industrial Policy in | |
| the matter of CST concession to the eligible | |
| units beyond 31-3-2009, up to 31-3-2013, and | |
| the Notification dated 29-5-2009, accordingly, | |
| having been issued by the Department | |
| concerned viz. Department of Industries, | |
| thereafter, the Excise and Taxation | |
| Department cannot take a different stand. | |
| What is given by the right hand cannot be | |
| taken by the left hand. The Government shall | |
| speak only in one voice. It has only one policy. | |
| The departments are to implement the | |
| government policy and not their own | |
| policy……” |
mechanism to ensure that whenever such conflicting stands are
3
(2016) 1 SCC 560
42
taken by different departments, they should be resolved at the
governmental level itself.
54. We, therefore, direct the Registry to furnish a copy of this
judgment to the learned Attorney General for India to use his
good offices and do the needful.
55. In the result, we pass the following order:
(i) The appeals are allowed;
th
(ii) The judgment and order dated 30 June 2021 passed
by the Division Bench of the High Court in LPA No. 22
of 2017 in SCA No. 184 of 2017 with SCA No. 5816 of
2017 is quashed and set aside;
(iii) The SCA Nos. 184 and 5816 of 2017 are remitted back
to the learned Single Judge of the High Court for
consideration afresh, to be decided as expeditiously as
possible and preferably within a period of six months
from the date of this judgment.
56. Until further orders are passed by the learned Single
th
Judge, the interim order dated 26 April 2019 passed by the
Division Bench in LPA No. 22 of 2017 shall continue to operate.
43
57. We clarify that our order would not come in the way of the
parties in arriving at a settlement which would be acceptable to
both the parties.
58. Pending application(s), if any, shall stand disposed of in
the above terms. No order as to costs.
…..….......................J.
[B.R. GAVAI]
…….......................J.
[C.T. RAVIKUMAR]
NEW DELHI;
OCTOBER 13, 2022.
44