THE STATE OF HIMACHAL PRADESH vs. RAJIV

Case Type: Civil Appeal

Date of Judgment: 24-02-2023

Preview image for THE STATE OF HIMACHAL PRADESH vs. RAJIV

Full Judgment Text

1 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION   CIVIL APPEAL NOS. 1278 of 2023 State of Himachal Pradesh & Ors.         .. Appellants      Versus Rajiv and Anr.                .. Respondents J U D G M E N T M. R. Shah, J. 1. Feeling   aggrieved   and   dissatisfied   with   the   impugned judgment and order dated 01.10.2020 passed by the  High Court of Himachal Pradesh in CMP (M) No.1375 of 2019 in LPA No.50 of 2020 by which the Division Bench of the High Court has refused to condone the delay in preferring the LPA Signature Not Verified Digitally signed by R Natarajan Date: 2023.02.24 16:49:43 IST Reason: against the judgment and order passed by the learned Single 2 Judge             passed   in   CWP   No.771   of   2016,   the   State   of Himachal Pradesh has preferred the present appeal. 2. Though   the   present   appeal   is   against   the   impugned order passed by the Division Bench of the High Court refusing to   condone   the   delay   in   preferring   the   LPA,   instead   of remanding the matter to the Division Bench to decide the appeal on merits and to consider the legality and validity of the judgment and order passed by the Hon’ble Judge, we have heard   the   learned   counsel   appearing   on   behalf   of   the respective parties on merits against the judgment and order passed by the learned Single Judge. 2.1 That the respondents herein ­ original writ petitioners filed the writ petition before the learned Single Judge of the High Court being CWP No.771 of 2016 and prayed for the following reliefs: "(i)   That   the   respondents   may   be   directed   to produce entire record in connection with construction work of road from village Banuti to village Loharb in Tehsil and District Shimla along with entire record of the   remaining   portion   from   Loharb   to   Mauja   Pahal Tehsil   Sunni   showing   the   process   and   proceeding 3 which   were   started   for   acquisition   of   land   and   for payment of amount of compensation. (ii) That the respondent may be directed not to deprive   the   petitioners   of   their   property   without adopting due process of law and that they should act in accordance with law and make payment of amount of compensation as per provision law.  (iii) That in case the respondents are, not ready and   willing   to   start   and   complete   acquisition proceeding   and   make   payment   of   amount   of compensation in that event they may be directed to hand   over   the   physical   possession   of   the   land   in question to the petitioner and also they may be held liable   to   pay   use   and   occupation   charges   from   the period from 1996 to date. (iv)  Any other suitable relief as consider just and proper   under   the   facts   and   circumstances   of   the petition may kindly be granted to petitioners.” 2.2 It was the case on behalf of the original writ petitioners that the land in question was utilized by the State for the construction of Banuti to Pahal Road as far as back in the year 1996, however, till date, no compensation in view of the same has been paid to them.  The petition was opposed by the State by filing a reply contending   inter alia   that at the time when the road was constructed through the land of the writ petitioners, it was on their request and on the condition that they will not claim any compensation.  It was submitted that 4 however at that time no written document was executed in this respect.   It was submitted in the reply that due to this reason   the   construction   work   of   the   road   was   completed without acquisition proceedings by the State Government. It was   also   submitted   that   the   road   was   constructed   on  the demand of public of the area including the writ petitioners.  It was submitted that had there been any truth in the plea of the writ petitioners, the writ petitioners would have raised the objection during the long period of 20 years. 2.3 Having heard learned counsel appearing on behalf of the original writ petitioners as well as the State and taking into consideration the fact that some portion of the land of the writ petitioners has been utilized for the purpose of construction of the road and no compensation has been paid and the land has   been   used   without   acquiring   the   land   under   the provisions   of   the   Land   Acquisition   Act,   1894   (hereinafter referred   to   as   ‘the   Act,   1894’),   the   learned   Single   Judge allowed the writ petition and directed the appellants to initiate 5 the process for acquisition of the land of the writ petitioners in accordance with law. 2.4 Feeling aggrieved and dissatisfied with the judgment and order passed by the learned Single Judge, the State preferred the Letters Patent Appeal before the Division Bench of the High Court allowing the delay of 354 days in preferring the LPA.  By the impugned order the Division Bench of the High Court has refused to condone the delay and consequently has dismissed the LPA on the ground of limitation.   Hence, the present appeal. 3. Shri Abhimanyu Jhamba, learned counsel appearing on behalf of the State has vehemently submitted that in the facts and circumstances of the case, the learned Single Judge has materially   erred   in   directing   to   initiate   the   process   for acquisition of the land of the original writ petitioners in a writ petition which was filed after a period of 21 years from the date of the use of the land in question which was used for the construction of road. 6 3.1 It is submitted that before the learned Single Judge it was the specific case on behalf of the State that the land was used with the consent of the original writ petitioners and the same was done on the request of the writ petitioners and with condition that they will not claim compensation for the same. 3.2 Thus, the impugned judgment and order passed by the learned Single Judge has been assailed mainly on the ground of delay and laches.  4. Present appeal is vehemently opposed by Ms. Radhika Gautam, learned counsel appearing on behalf of the original writ petitioners. 4.1 It is   submitted  that  nothing  is  on  record  that  at the relevant time the original writ petitioners consented for the use of their land for construction of road without claiming compensation for the same. 4.2 It   is   vehemently   submitted   that   as   such   initially   a notification under Section 4 of the Act, 1894 was issued for acquisition   of   the   land   at   Village   Tikkari   on   17.05.1996, 7 however the notification so issued under Section 4 of the Act, 1894 was permitted to lapse. 4.3 It   is   submitted   that   thereafter   neither   the   fresh acquisition   proceedings   were   initiated   nor   even   the compensation with respect to the land used for construction of road has been paid. 4.4 It is submitted that the State on the ground of delay and laches cannot evade its legal responsibility towards those from whom private property has been expropriated.   Reliance is placed upon the recent decision of this Court in the case of Sukh Dutt Ratra and Anr. Vs. State of Himachal Pradesh and Ors., (2022) 7 SCC 505. 4.5 Relying   upon   the   aforesaid   decision,   it   is   further submitted that as observed and held by this Court in the said decision in absence of written consent to voluntarily give up their land, the land owners are entitled to the compensation in terms of law. 8 5. Having   heard   learned   counsel   appearing   for   the respective parties and in the facts and circumstances of the case and when the writ petition and the claim of the original writ petitioners to claim the compensation for the land used for construction of the road has been opposed by the State solely on the ground of delay and laches, we are of the opinion that   on   the   certain   conditions   which   shall   be   considered herein below the original writ petitioners – owners of the land used by the State for construction of the road shall be entitled to the compensation for their lands which have been used by the State without acquisition under the Act, 1894. 5.1 At   this   stage,   it   is   required   to   be   noted   that   in   the present case as such initially the Notification under Section 4 was issued for acquisition of the land at Village Tikkari on 17.05.1996.   However   thereafter   the   notification   so   issued under   Section   4   of   the   Act,   1894   was   permitted   to   lapse. Therefore,   17.05.1996   can   be   directed   to   be   treated   as   a deemed acquisition on that day and the original landowners may be awarded the  compensation considering the  market 9 price   as   on   17.05.1996,   however   with   all   other   statutory benefits excluding the interest from 17.05.1996 till the writ petition was filed before the High Court.  If the aforesaid order is passed in exercise of this Court’s extra ordinary jurisdiction under Articles 136 & 142 of the Constitution, the same can be said to be just and proper and doing the complete justice between the parties. 6. In view of the above and for the reasons stated above, present   appeal   stands   disposed   of   by   directing   that 17.05.1996   be   treated   as   the   deemed   date   of   acquisition under Section 4 of the Act, 1894 and the original owners/writ petitioners shall be entitled to the compensation considering the market price of the land in question used by the State for construction   of   the   road   as   on   17.05.1996.     However, considering the fact that there was a huge delay of 20 years in filing the writ petition before the High Court, we direct that though the original writ petitioners shall be entitled to all the statutory benefits which may be available under the Act, 1894 from 17.05.1996, however they shall not be entitled to any 10 interest under the Act, 1894 from 17.05.1996 to the date of filing of the writ petition. Now   the   State/appropriate   authority   to   calculate   the amount of compensation as above after giving an opportunity to the original writ petitioners to lead the evidence on the market price as on 17.05.1996 and thereafter to make the payment   of   compensation   as   above   within   a   period   of   2 months from the date of actual calculation of the amount of compensation.     However,   the   entire   exercise   shall   be completed within a period of six months from today. Present appeal stands allowed/disposed of in terms of the above. However,   in   the   facts   and   circumstances   of   the   case there shall be no order as to costs.    …………………………………J.             (M. R. SHAH) …………………………………J.     (C.T. RAVIKUMAR) New Delhi,  February  24, 2023