Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
PETITIONER:
SARDAR MOHAR SINGH THROUGHPOWER OF ATTORNEY HOLDER, MANJIT S
Vs.
RESPONDENT:
MANGILAL @ MANGTYA
DATE OF JUDGMENT: 15/01/1997
BENCH:
K. RAMASWAMY, S. SAGHIR AHMAD, G.B. PATTANAIK
ACT:
HEADNOTE:
JUDGMENT:
O R D E R
Delay condoned.
This special leave petition arises from the judgment of
the learned Single Judge of the Madhya Pradesh High Court,
made on October 4, 1996 In Civil Revision No. 394/96. The
petitioner had entered into a contract with the respondent
for sale of agricultural land in Khasra No 52, 61, 73,74,79,
admeasuring 3-533, 0-166, 1-437, 0.384, 0.202 hectares and
also an agreement to sell dated July 7, 1977 in respect of
land situated in Village Khode, for a consideration of Rs.
25000/-. The respondent failed to perform his part of the
contract and, therefore, the petitioner filed a suit bearing
Civil Suit No. 9A/78 in the Court of ADJ, Mandleshwar. The
Trial Court granted a decree for specific performance on
November 18, 1987 directing the respondent to refund the
earnest money of Rs. 15000/- and also damages quantified in
the sum of Rs. 2,000/-, as agreed in the contract, within a
period of three months and in default to execute the sale
deed. The respondent filed applications rescind the decree
in execution and he sought
extension of time for compliance.
The executing Court by order dated March 15, 1996 allowed
the both the applications of the respondent and directed him
to deposit the amount within three days from that date. In
revision, the High Court, while upholding that order, has,
in addition to the direction of the lower court, directed
the respondent to deposit a further sum of Rs. 16000/- to
compensate the petitioner for loss of enjoyment of money.
Thus, this special leave petition.
Shri R.S. Suri, learned counsel for the petitioner
contended that in view of the inordinate delay of 7-1/2
years in making the application and in view of the finding
given by the execution Court that no proper explanation was
given by the respondent for the delay, the execution Court
as well as the High Court committed and error of law in
direction extension of time there being no proper
explanation. The High Court also was wrong in its conclusion
that the decree can be treated to be a priliminary decree
and, therefore, the direction can be granted in the final
decree. it is also contended that the Court has no power to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
extend time. We do not find force in any of these
contentions. It is seen that sub-section (1) of Section 28
of the Specific Relief Act, 1963 (for Short, the ’Act’)
gives right to the judgment debtor to file an application to
rescind the contract. It reads as under:
"Where in any suit a decree for
specific performance of a contract
for the sale or lease of immovable
property has been made and
purchaser of lessee does not,
within the period allowed by the
decree or such further period as
the Court may allow, pay the
purchase money or other sum which
the court has ordered him to pay,
the vendor or lessor may apply in
the same suit in which the decree
is made, to have the contract
rescinded and on such application
the Court may, by order, rescind
the contract either so far as
regards the party in default of
altogether, as the justice of the
case may require,"
From the language of sub-section (1) of Section 28, it
could be seen that the Court does not lose its Jurisdiction
after the grant of the decree for specific performance not
it becomes functus officio. The very fact that Section 28
itself gives power to grant order of rescission of the
decree would indicate that till the sale deed in executed in
execution of the decree, the trial Court retains its power
and jurisdiction to dear with the decree of specific
performance. It would also be clear that the Court has power
to enlarge the time in favour of the judgment- debtor to pay
the amount or to perform the conditions mentioned in the
decree for specific performance, in spite of a application
for rescission of the decree having been filed by the
judgment-debtor and rejected. In other words, the Court has
a discretion to extend time for compliance of the
conditional decree as mentioned in the decree for specific
performance, It is true that the respondent has not given
satisfactory explanation of every day’s delay. It is not,
unlike Section 5 of the Limitation Act, an application for
condonation of delay. it is one for extension of time. Under
these circumstances, the executing Court as well as the High
Court had exercised discretion and extended the time to
comply with the conditional decree, Accordingly, we do not
find any valid and justifiable reason to interfere with the
order passed by the High Court confirming the order of the
executing court when in particular the High Court has
further enhanced a sum of Rs. 16.000/- to compensate the
petitioner for loss of enjoyment of the money. The said
amount is given to the respondent in a sum of Rs. 16,000/-,
rightly for the reason that parties contracted for no-
performance of the contract. They quantified the damages at
Rs. 2,000/- for 8 years the Court has given Rs. 16,000/-
obviously in terms of the contract.
The special leave petition is dismissed.