Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 9799 OF 2010
National Highways Authority of India …. Appellant
Vs.
M/s ITD Cementation India Limited …. Respondents
WITH
Civil Appeal No.9908/2011, Civil Appeal No. 9909/2011
Civil Appeal No.2488/2012, Civil Appeal No. 7066/2011
Civil Appeal No.3150/2012, Civil Appeal No. 686/2013
Civil Appeal No.4069/2013, Civil Appeal No. 5162/2012
Civil Appeal No.5661/2014, Civil Appeal No. 10586/2014
Civil Appeal No. 3913/15(@S.L.P. (C) No. 10014/2013)
Civil Appeal No.3914/15(@S.L.P. (C) No. 10701/2013)
Civil Appeal No.7373/2012 AND Civil Appeal No.6158/2013
JUDGMENT
JUDGMENT
Uday Umesh Lalit, J.
1. Leave granted in S.L.P (C) Nos. 10014 of 2013 and 10701 of
2013.
Page 1
2
A. Civil Appeal Nos. 9799 of 2010, 9908/2011, 9909/2011,
2488/2012, 7066/2011, 3150/2012, 686/2013, 4069/2013, 5162/2012
and 5661/2014, 10586/14, Civil Appeal @ from SLP © 10014/2013
and Civil Appeal @ from SLP © 10701 of 2013 :
| als by spec | ial leave r |
|---|
as such are being dealt with and considered by this common
judgment. The learned counsel for the parties agreed that Civil
Appeal No.9799 of 2010 be taken and was accordingly dealt with as
the lead case.
CIVIL APPEAL NO. 9799 OF 2010
3. Civil Appeal No. 9799 of 2010, by Special Leave seeks to
challenge the judgment and order dated 30.11.2007 passed by the
Division Bench of the High Court of Delhi at New Delhi in FAO (OS)
No.216 of 2007.
JUDGMENT
4. The dispute in question relates to the consequences of an
additional amount of royalty payable by the respondent as a result of
the notification for upward revision of royalty (Seignorage Fee as
named in Tamil Nadu) on minor minerals. This additional royalty was
imposed by the State of Tamil Nadu w.e.f. 01.11.2002. It is the plea
of the appellant that the additional amount of fee was not liable to be
Page 2
3
paid to the respondent in view of certain clauses in the contract which
provided for a formula of escalation, while according to the
respondent the full amount had to be compensated.
| awarded t | o the resp |
|---|
17.10.2001 for execution of work of widening of lanes and
rehabilitation of the existing two lane carriageway of
Vaniyambadi-Pallikonda section of NH-6 (from Km.49.00 to
Km.100.00). The total value of the contract was appropriately
Rs.183.71 crores. The parties adopted FIDIC form of Conditions of
Contract with some changes made which are called Conditions of
Particular Application (COPA, for short). In the invitation to tender
forming part of the contact under Clause 13.4 it was agreed between
the parties as under:
JUDGMENT
13.4. All duties, taxes and other levies payable by
the Contractor under the Contract, or for any other
cause, as of the date 28 days prior to the deadline
for submission of bids, shall be included in the
rates and prices and the total bid price submitted
by the bidder, and the evaluation and comparison
of bids by the Employer shall be made accordingly.
6. The aforesaid stipulation dealt with the impact and inclusion of
duties, taxes and other levies, as of the date 28 days prior to the
Page 3
4
deadline for submission of bids and clarified that the same shall stand
included in the rates and prices and the total bid price submitted by
the Contractor. Any subsequent variation in Prices on account of
| factors aft | er such dat |
|---|
70 to 70.8 of the COPA and the relevant parts thereof are quoted
hereunder:-
Clause 70: Changes in Cost and Legislation
Delete the text of Clause 70 in its entirety and
substitute, therefore the following clauses 70.1 to
70.8.
Sub-Clause 70.1 : Price Adjustment
The amount payable to the Contractor and valued
at base rates and prices pursuant to Sub-Clause
60.1 hereof shall be adjusted in respect of the rise
or fall in the indexed cost of labour, Contractor’s
equipment, Plant materials and other inputs to the
Work, by the addition or subtraction of the
amounts determined by the formulae prescribed in
this Clause.
JUDGMENT
Sub-Clause 70.2: Other Changes in Cost
To the extent that full compensation for any rise or
fall in the costs to the Contractor is not covered by
the provisions of this or other Clauses in the
Contract, the unit rates and, prices included in the
Contract shall be deemed to include amounts to
cover the contingency of such other rise or fall in
cost.
Sub-Clause 70.3 :Adjustment Formulae
Page 4
5
| te shall b<br>e price inc | e adjuste<br>rease or de |
|---|
a) Price adjustment shall apply for work
carried out within the stipulated time or extensions
granted by the Employer and shall not apply for
work carried out beyond the stipulated time. Price
adjustment for reasons attributable to the
Contractor, shall be paid in accordance with
Sub-Clause 70.6;
b) Following expressions and meanings are
assigned to the value of the work done during the
period under consideration:
RI= Total value of work done during the period
under consideration and payable in Indian Rupee
currency, it would include the value of materials on
which secured advance has been granted, if any,
during the period, less the value of materials in
respect of which the secured advance has been
recovered , if any, during the period. This will
exclude cost of work an items for which rates were
fixed under variation Clauses (51 and 52) for
which the escalation will be regulated as mutually
agreed at the time of fixation of rate.
JUDGMENT
To the extent that full compensation for any
rise or fall in indexed costs to the Contractor is not
covered by the provisions of this or other Clauses
in the Contract, the unit rates and prices included
in the Contract shall be deemed to be include
amount to cover the contingency of such other rise
or fall in costs.
Page 5
6
(c) Price adjustment for various inputs into the
works done shall be calculated as per formulae
given below:
| …………<br>………… | …<br>…… |
|---|
B) Variation of Price-General Materials
The Contract Price will be subjected to
adjustment on account of general variation of all
materials other than specifically provided in
Sub-Clause 70.5 hereinafter. The adjustment will
be made according to the formula given below:
V2=R1x (I-Io) x G
Io
Where,
V2= Variation in price on account of general variation of
prices of all materials other than specifically
provided in Sub-Clause 70.5 hereinafter.
Io = Base Cost Index corresponding to the Wholesale
Price in India (for all commodities) for the price
under consideration (Base 1993-94=100) released
by the economic advisor, Ministry of Industry,
Government of India, at the time specified in para
(E) hereinafter.
I= Current Cost Index corresponding to the Wholesale
JUDGMENT
Price in India (for all commodities ) for the price
under consideration (Base 1993-1994 =100)
released by the same agency at the time specified
in para (E) hereinafter.
G= Factor of 0.15 (zero point one five ) representing
component of all material other than specifically
provided elsewhere in the Contract Price.
R1= Value of the work done during the period under
consideration and payable in non-convertible
Page 6
7
Indian Rupee Currency at the base rates and prices
as applicable under the Contact.
C) Variation of Price –POL
| rice Adj | ustment |
|---|
……………..
……………
E) Base, Current and Provisional Indices
……………..
………………..
F) Price Adjustment
…………….
…………..
G) The Adjustable Amount
…………….
……………….
H) The Adjusted Amount
……………….
………………..
JUDGMENT
I) Adjustment after Completion
………………
……………..
Sub-Clause 70.4: Sources of Indices
The sources of indices shall be those as mentioned
in Sub-clause 70.3 of Section III Volume I of the
Bid documents.
Sub-Clause 70.5: Increase or Decrease of Price
of Specified Materials
Page 7
8
(i) Increase or decrease of price of specified
materials will be adjusted by either an addition to
or a deduction to or a deduction from the Contract
Prices. For the purpose of this Sub-Clause:
| e 2 of<br>nts and r | Section V<br>equired o |
|---|
“Basic Price” means the price for “Specified
materials” indicated in Schedule 2 of Section VII
of the Bidding Documents.
(ii) a) Adjustments to the Contract Price
for Bitumen
…………..
……………
b) Adjustment to the Contract Price for
Cement and Steel:
……………………….
……………………..
Sub-Clause 70.6: Limit of Price Adjustment
……………………..
……………………..
JUDGMENT
Sub-Clause 70.7: Exemption from Price
Adjustment
……………………
Sub-clause 70.8: Subsequent Legislation
If, after the date 28 days prior to the closing
date for submission of bids for the Contract there
are changes to any National or State Statute,
Ordinance, Decree or other Law or any regulation
or by-law of any local or other duly constituted
Page 8
9
| al or red<br>tion with th | uced cos<br>e Employ |
|---|
7. The Government of Tamilnadu by issuing a notification under
Section 15 of the Mines and Minerals (Regulation & Development)
Act, 1957 (hereinafter referred to as 1957 Act), increased the
JUDGMENT
seigniorage fee (which is synonymous with Royalty charges in other
States) on stone, sand and earth to the tune of nearly 30% with effect
st
from 1 November, 2002, i.e. after about one year from
commencement of the Work. The respondent requested for Price
Adjustment consequent to the increase in rates of Royalty under
Sub-Clause 70.8 of COPA vide letter dated 28.12.2002. The request
was rejected on 01.01.2003 on the ground that the increase in royalty
Page 9
1
charge cannot be paid separately as the same was already considered
under the Price Adjustment formula being paid for general materials
under Sub-Clause 70.3 of COPA. The matter was placed for
| the request | was fina |
|---|
relying on NHAI’s policy circular No.11041/21/02-Admn.III dated
01.09.2003.
8. It appears that in similar contracts with identical conditions
requests for payment of increased royalty under Sub-Clause 70.8 were
accepted and appropriate payments were made. However, during the
course of audit, the payment made by the NHAI towards increase in
Royalty charges was considered to be irregular by the Government
auditors on the ground that no such separate payment was required to
be made under Sub-clause 70.8 of COPA as payment was already
JUDGMENT
made under the Price Adjustment formula for price increase. In the
circumstances, the appellant on 03.09.2003 wrote to the Economic
Advisor, Ministry of Commerce and Industry, Government of India
seeking clarification and advice. Relevant portion of the letter dated
03.09.2003 is quoted hereunder:-
“Anand Bordia
Member (Finance) NATIONAL HIGHWAYS
Page 10
11
| ordia@nhai. | org |
|---|
D.O. NO.NHAI/11033/GM/2003-04 September 3, 2003
Dear Shri Nigam
Sub: Wholesale Price Index
1. NHAI was set up by the National Highways
Authority of India Act, 1988 to develop, maintain
and manage the national highways and any other
highways vested in, or entrusted to, it by the
Government.
2. Incidental to this function, for the
construction of highways, NHAI appoints highway
construction contractors, selected by a process of
competitive bidding. The bidding process involves
the bidder quoting his delivery cost for predefined
quantities of various inputs required for the
highway construction. Since the period of
execution is fairly long, to provide
protection/neutralize price related impacts to the
contractor/NHAI, certain mechanism has been
incorporated in the contract. For example, to cover
price impact arising out of or in consequence to
any Legislation is provided as under:
(a) Sub-Clause 70.8 Subsequent Legislation.
JUDGMENT
…………………
………………….
Page 11
1
3. We are enclosing herewith a copy of the
extracts of the Contract document detailing the
above provisos vide para 70.1 to 70.8
| se 70.8 on<br>Auditors | “Subseque<br>while au |
|---|
5. It is felt that if CAG interpretation is
accepted for implementation, the entire clause
“Subsequent Legislation” will be hit and made
entirely redundant as a tool to cover price risk.
6. CAG’s office has raised objection in a
specific case, details of which are narrated here
below:
JUDGMENT
……………………………
……………………………
7. All these payments were claimed by the
Contractor and paid by NHAI, as these arose on
account of Tax obligations under enactments made
or rates enhanced during the relevant period
thereby entitled under the clause for subsequent
legislations. We wish to stress the fact that these
were imposed and enhanced by the States of
Haryana and Rajasthan and relate to construction
Page 12
1
inputs which are not in the basket of items listed
for the consideration of WPI.
| into WP<br>were grant | I and W<br>ed and gi |
|---|
9. In view of the above, we will be grateful if
you could clarify the following:
(a) Will the WPI assessment include or deemed
to include such local factors as Octroi Entry Tax
and Royalty introduced/enhanced in one state etc.
on items mentioned in paragraph 6 of this letter
such as earth, morram, aggregate, sand, stones etc.
which it appears do not come under the items
considered to work out WPI.
JUDGMENT
(b) The WPI based compensation for price
changes will create an imbalanced structure
between two contractors, one operating within the
locality subject to a local impost and another in an
adjoining area outside such an impost, if CAG
auditors opinion is accepted. How can the WPI
mechanism be used by NHAI to create an
equitable structure?
You may recall that the Chairman NHAI Shri
Santosh Nautiyal had spoken to you about this
matter.
Page 13
1
Kind Regards,
Yours sincerely,
| awan Niga | m, |
|---|
9. The response from the Economic Advisor to the Government of
India was as under:
“Shrawan Nigam GOVERNMENT OF INDIA
Economic Advisor MINISTRY OF
COMMERCE
Tel:23012721 & INDUSTRY
Fax:23793502 UDYOG BHAWAN,
Economic Advisor to NEW DELHI-110001
the Government of India
th
27 November, 2003
D.O. No. Ec.Ad 11(1)/2003/WPD
JUDGMENT
Dear Shri Bordia,
Kindly refer to your D.O. Letter
No.NHAI/11033/GM/2003-04 dated the
September 3, 2004, seeking clarifications on
constituents of prices utilized for compilation of
Wholesale Price Index. I may mention in this
respect that in case of Minerals, ex-mine prices are
used for compilation of WPI. Ex-mine prices
correspond to Pit Mouth Value (PMV) of a mineral
i.e. sale value of mineral at pithead. In case sales
Page 14
1
| Royalty<br>d entry tax | but are n<br>. |
|---|
Since none of the items mentioned in your
letter, namely, Earth, Morram, Aggregate and Sand
are included in the Commodity Basket of WPI, it is
not possible to supply the Wholesale Price Indices
of these items. However, the WPI for ALL,
COMMODITIES and MINERALS from
December 1995 to July 2001 are being enclosed
for your appropriate use.
With regards,
Yours sincerely,
Sd/-
(Shrawan Nigam)
Shri Anand Bordia,
Member (Finance)
National Highway Authority of India,
Ministry of Road, Transport & Highways,
G-5&6, Sector-10, Dwarka,
NEW DELHI-110045.”
JUDGMENT
10. In the aforesaid circumstances the dispute between the parties
stood referred to Arbitral Tribunal. The respondent submitted its
Statement of Claim claiming under Sub Clause 70.8 of COPA an
st
amount of Rs.91,47,411/- allegedly due upto 31 January, 2005
towards reimbursement of increase in Royalty (Seigniorage fee) on
Page 15
1
minerals i.e. aggregate, sand and earth (the items in issue) along with
interest @ 12 per cent per annum compounded monthly on the sums
found due from the date they became due till realization.
| Tribunal | comprisi |
|---|
Engineers who had retired from Govt. service Departments above the
rank of Chief Engineer framed the following questions for
determination:
“1) Whether the increase in the rates of Royalty
has caused additional cost to the Claimant and
2) Whether the increase in cost because of
increase in the rates of Seigniorage Fee on
materials like aggregate, sand and earth has been
taken into account in the indexing of any inputs to
the Price Adjustment Formula in Sub-Clause
70.3(B) relating to the General Materials.”
After going through the pleadings and evidence the Arbitral
JUDGMENT
Tribunal unanimously found that the respondent had incurred
additional cost because of the change in rates of Seigniorage fee
pursuant to change in legislation and that the said increase in the rates
had not been taken into account in the indexing of any inputs to the
price adjustment formula in general materials and therefore the
Page 16
1
respondent would be entitled to be paid the additional cost incurred
by. It was held as under:
| vant Contr<br>sly consid | act provis<br>ered the r |
|---|
22. The other question now required to be
answered by us is whether the additional cost
because of change in the rates of Seigniorage fee
has been taken into account in the indexing of any
inputs to the Price Adjustment Formulae supra.
We have examined the basket of materials whose
cost variation is input in the estimation of the WPI.
The minor minerals like earth, sand and aggregate
used in highway construction works, do not find
place in this basket. We are prepared to concede
that the WPI is to an extent likely to indicate the
rise or fall in the prices of these minor minerals
also, but are not inclined to accept that the full
impact of the additional cost of these specific
materials because of a subsequent change in
legislation can be said to be taken care of in the
inputs to the WPI, especially when these materials
do not find place in the basket of materials for
JUDGMENT
Page 17
1
| act provisio<br>Sub-Clause | ns relatin<br>s 70.2 to |
|---|
23. We must state that but for the adult objection,
the Respondent NHAI itself was of the opinion
that this additional payment is admissible
separately. The reference by the NHAI to Mr.
Shravan Nigam, Economic Advisor, Ministry of
Commerce and Industry, GOI vide Ex. R/4 clearly
signifies this fact. The reply to this letter by Mr.
Shravan Nigam annexed with Ex. R/4 also does
not help us in arriving at any contrary conclusion.
Having answered the question, the Arbitral Tribunal rejected the
contention of the respondent that it was unnecessary for it to prove
JUDGMENT
actual incurring of such additional cost. The contention that the
respondent would be entitled to the difference in the royalty payable
on the material by a theoretical calculation based on the agreed
quantities, even without proving that any such additional cost had
been actually incurred was rejected. On the issue whether the
respondent had produced any evidence to substantiate its claim that
any such additional cost had been incurred, the Arbitral Tribunal
Page 18
1
found that the material placed on record was lacking in particulars and
as such the quantification of the impact of change in the rates of
royalty was left to be determined by the appellant.
| being aggri | eved by t |
|---|
published on 12.05.2006 filed OMP No.432 of 2006 in the High Court
of Delhi which was dismissed by a Single Judge of the High Court
vide judgment and order dated 14.05.2007. It was observed that the
Arbitral Tribunal had found that the minerals in question did not find
place in the basket of materials for working out the wholesale price
index i.e. WPI, that the WPI would be applicable uniformly in all the
States while the increase in Seigniorage Fee varied from State to
State. It was concluded that the view taken by the Tribunal did not
call for any interference. In the appeal, namely, FAO(OS) No.216 of
JUDGMENT
2007 preferred by the appellant, it was submitted that the
interpretation placed by the Arbitral Tribunal upon the provisions of
the agreement was erroneous and secondly that the award was
imperfect inasmuch as it left the question of quantification of the
amount undecided. While dealing with the first submission, the
Division Bench of the High Court observed:
Page 19
2
| al cost of t<br>he full imp | hose spec<br>act of the |
|---|
JUDGMENT
Page 20
2
The Division Bench however agreed with the appellant on the
second submission and remitted the matter to the Arbitral Tribunal on
the limited issue of quantification of the amount.
| by special | leave cha |
|---|
order passed by the Division Bench of the High Court, this Court at
the interim stage had directed the arbitration proceedings to continue
in terms of the order of the High Court. The Arbitral Tribunal by its
award dated 07.05.2010 quantified the sum that the respondent was
entitled to on account of increase in the rates at Rs.43,06,810/- and
awarded interest @ 12% p.a. from the date of publication till
realization. By order dated 15.11.2010 this Court directed the
appellant to deposit sum of Rs.46 lakhs, being the amount so
quantified. The amount has since then been deposited and stands
JUDGMENT
invested in a fixed deposit.
14. Mr. Parag P. Tripathi learned Senior Advocate assisted by Ms.
Monisha Handa, learned Advocate appeared for the appellant in the
lead case. Ms. Indu Malhotra, learned Senior Advocate and Ms.
Gunjan S. Jain, learned Advocate appeared for the appellants in the
companion matters. It was submitted by them that WPI is a general
Page 21
2
or representative index of prices of all commodities and as such it
would not and need not take all commodities into account. The
parties having agreed to go by WPI Index, that Index alone must be
| ve of the fa | ct whether |
|---|
question were taken into account specifically while arriving at such
Index. It was submitted that the award correctly observed in para 22
that “WPI is to an extent likely to indicate the rise or fall in the prices
of these other minerals also” though minor minerals in question did
not specifically find place in the commodity basket taken into
account while determining WPI. The reason why Arbitral Tribunal
was not inclined “to accept that the full impact of the additional cost
of these materials because of subsequent change in legislation can be
said to be taken care of by he inputs to the WPI” in the submission of
JUDGMENT
the learned counsel, was perverse. It was submitted that the
governing clause in the matter was Sub Clause 70.3 (B) and in terms
thereof, the respondent would at best be entitled to factor of 0.15 i.e.
15% and not the amount in entirety as claimed. It was contended that
the view taken by the Arbitral Tribunal ignored the provisions of Sub
Clauses 70.1 to 70.3(B) and exclusion in Sub Clause 70.8 and the
award so given in disregard of the terms of the contract stands vitiated
Page 22
2
being against public policy. Reference was placed on the decisions of
this Court in McDormott International Inc . v. Burn Standard Co.
1 2
Ltd. , ONGC Ltd . V. Western Geco International Ltd . and ONGC
3
Ltd. v. Saw Pipes .
15. Mr. George Thomas, learned Advocate appearing for the
respondent in the lead case and some companion matters submitted
that Sub-Clauses 70.1 to 70.7 of COPA deal with Price Adjustment in
respect of rise or fall in the indexed cost of various inputs to the work
due to market fluctuations while sub clause 70.8 specifically deals
with cases concerning change in price due to subsequent legislative
changes and that unlike the former category, in respect of cases in the
latter category the additional cost on account of changes in subsequent
legislation by virtue of sub clause 70.8 must be paid in full. Mr. P.H.
JUDGMENT
Parekh learned Senior Advocate appearing for respondent in Civil
Appeal No.4069 of 2013 and other companion matters, additionally
submitted that but for the audit objection, the appellant itself was of
the opinion that this additional payment was admissible separately.
Reliance was placed on the letter dated 03.09.2003 addressed by the
1
(2006) 11 SCC 181
2
(2014) 9 SCC 263
3
(2003) 5 SCC 705
Page 23
2
appellant to the Economic Advisor. Mr. Shyam Divan learned Senior
Advocate appearing for respondent in Civil Appeal No.9909 of 2011
submitted that both parties understood the terms of the Contract in a
| at the vie | w taken by |
|---|
affirmed by the Single Judge and the Division Bench on independent
assessment and such view being a plausible view no interference was
called for. Mr. Vinay Navare, learned Advocate appearing for
respondent in Civil Appeal No.3150 of 2012 and other learned
Counsel adopted the submissions.
16. Since it was argued that the Arbitral Tribunal disregarded the
material terms of the Contract while making its assessment and failed
to consider the impact of sub clauses 70.1 to 70.3 (B) and exclusion in
sub clause 70.8, the law on the point needs to be briefly adverted to.
JUDGMENT
In Mc Dermott International Vs. Burn Standard Co. Ltd . (Supra)
this Court held as under:-
“112. It is trite that the terms of the contract can be
express or implied. The conduct of the parties
would also be a relevant factor in the matter of
construction of a contract. The construction of the
contract agreement is within the jurisdiction of the
arbitrators having regard to the wide nature, scope
and ambit of the arbitration agreement and they
cannot be said to have misdirected themselves in
Page 24
2
| r to deter<br>ation of | mine, eve<br>a question |
|---|
113. Once, thus, it is held that the arbitrator had the
jurisdiction, no further question shall be raised and
the court will not exercise its jurisdiction unless it
is found that there exists any bar on the face of the
award.”
4
17. In Rashtriya Ispat Nigam Ltd . v. Dewan Chand Ram Saran , the
Court held:
“ 43 . In any case, assuming that Clause 9.3 was
capable of two interpretations, the view taken by
the arbitrator was clearly a possible if not a
plausible one. It is not possible to say that the
arbitrator had travelled outside his jurisdiction, or
that the view taken by him was against the terms of
contract. That being the position, the High Court
had no reason to interfere with the award and
substitute its view in place of the interpretation
accepted by the arbitrator.”
JUDGMENT
4
( 2012) 5 SCC 306
Page 25
2
5
18. In Sumitomo Heavy Industries Ltd. . v. ONGC , it was held the
Court held:
| greement w<br>one. One m | hich acco<br>ay at the |
|---|
JUDGMENT
6
19. In a recent decision in Associate Builders Vs. DDA while
discussing “the public policy of India” contained in Section 34(2) (b)
(ii) of the Arbitration Act, 1996 this Court dealt with each of the heads
contained in Saw Pipes Judgment (Supra) in the light of three distinct
5
(2010) 11 SCC 296
6
(2015) 3 SCC 49
Page 26
2
and fundamental juristic principles added in ONGC Ltd . Vs. Western
Geco. International Ltd. (Supra). “Patent-illegality” which is one of
the heads contained in Saw Pipes judgment (Supra) was then
| ote paras 4 | 2 to 42.3:- |
|---|
42. In the 1996 Act, this principle is substituted by
the ‘patent illegality’ principle which, in turn,
contains three sub heads:
42.1 (a) A contravention of the substantive law of
India would result in the death knell of an arbitral
award. This must be understood in the sense that
such illegality must go to the root of the matter and
cannot be of a trivial nature.This again is a really a
contravention of Section 28(1)(a) of the Act, which
reads as under:
“28. Rules applicable to substance of
dispute .—
(1) Where the place of arbitration is situated
in India,—
(a) in an arbitration other than an
international commercial arbitration, the
arbitral tribunal shall decide the dispute
submitted to arbitration in accordance with
the substantive law for the time being in
force in India;”
JUDGMENT
42.2 (b) a contravention of the Arbitration Act
itself would be regarded as a patent illegality- for
example if an arbitrator gives no reasons for an
award in contravention of section 31(3) of the Act,
such award will be liable to be set aside.
Page 27
2
42.3 (c) Equally, the third sub-head of patent
illegality is really a contravention of Section 28 (3)
of the Arbitration Act, which reads as under:
“28. Rules applicable to substance of
dispute .-
| ) -- (2) * | * * |
|---|
(3) In all case, the arbitral tribunal shall
decide in accordance with the terms of the
contract and shall take into account the
usages of the trade applicable to the
transaction.”
This last contravention must be understood with a
caveat. An arbitral tribunal must decide in
accordance with the terms of the contract, but if an
arbitrator construes a term of the contract in a
reasonable manner, it will not mean that the award
can be set aside on this ground. Construction of the
terms of a contract is primarily for an arbitrator to
decide unless the arbitrator construes the contract
in such a way that it could be said to be something
that no fair minded or reasonable person could do.
JUDGMENT
20. It is thus well settled that construction of the terms of a contract
is primarily for an arbitrator to decide. He is entitled to take the view
which he holds to be the correct one after considering the material
before him and after interpreting the provisions of the contract. The
court while considering challenge to an arbitral award does not sit in
appeal over the findings and decisions unless the arbitrator construes
Page 28
2
the contract in such a way that no fair minded or reasonable person
could do.
| award, as q | uoted abo |
|---|
impact of sub-clauses 70.1 to 70.7 and agrees with the contention that
the provision for cost escalation based on the agreed price adjustment
formulae falls in one compartment while the compensation for
additional cost resulting from a subsequent legislation falls in a
separate category. In other words, the contention that stands accepted
was, that the escalation in price premised on fluctuation in market
value of the inputs stands on one footing, while the additional cost
resulting form the impact of any statute, decree, ordinance, law etc as
referred to in sub-clause 70.8 stands on the other. Resultantly the
JUDGMENT
governing clauses in the instant case were held not to be sub-clauses
70.1 to 70.7 but the substantive part of sub-clause 70.8. The award
also considered whether minor minerals in question were or were not
included in the basket of materials whose cost variation was taken into
account as an input while arriving at WPI. It also considered that the
WPI is an index applicable uniformly in all states while the increase
Page 29
3
in Seigniorage Fee would vary from state to state. It further dealt with
the aspect that NHAI itself was of the opinion that the additional
impact as a result of subsequent legislation was admissible separately,
| ter dated 0 | 3.09.2003 |
|---|
the backdrop of the law laid down by this court, the construction of
the terms of the contract by the Arbitral Tribunal is completely
consistent with the principles laid down by this court. Upon
construing the terms and the material on record it concluded that the
instant matter would be covered by substantive part of Sub-Clause
70.8 of COPA. It also noted that NHAI itself was of such opinion.
The view so taken by the Arbitral Tribunal after considering the
material on record and the terms of the contract is certainly a possible
view, to say the least. We do not see any reason to interfere. The
JUDGMENT
Division Bench in our considered view, was completely right and
justified in dismissing the challenge.
22. We, therefore, dismiss Civil Appeal No. 9799 of 2010. The
decretal amount which stands deposited be made over to the
respondent along with the interest accrued thereon. No order as to
costs.
Page 30
3
Civil Appeal Nos. 9908/2011, 9909/2011, 2488/2012, 7066/2011,
3150/2012, 4069/2013, 5162/2012 and 5661/2014, 658/2013,
10586/14, Civil Appeal @ from SLP © 10014/2013 and Civil
Appeal @ from SLP © 10701 of 2013 :
| tters Natio | nal Highw |
|---|
appellant which had entered into contacts with respondents in each
appeal and the issue involved is identical that is to say the entitlement
of the concerned respondents to the additional amount payable as a
result of upward revision in royalty payable in respect of minor
minerals pursuant to subsequent legislation. The clauses in question
are identical and in all these matters the High Court, whose orders are
appealed against, had relied upon the judgment of the Division Bench
of the High Court of Delhi in FAO (OS) No.216 OF 2007, which was
under appeal in the lead matter i.e. Civil Appeal No. 9799 of 2010
JUDGMENT
24. Consequently, all these appeals are dismissed. The decretal
amount, if deposited, be made over to the respondents along with
interest accrued thereon. In some cases, money so deposited was
allowed to be withdrawn on furnishing of Bank Guarantees. The
Bank guarantees so furnished stand discharged. No order as to costs.
Page 31
3
B. CIVIL APPEAL NO. 7373 OF 2012 :
25. This appeal challenges the judgment and order dated
| y the High | Court of D |
|---|
497 of 2006. Unlike all the aforesaid cases, the clauses in question are
not identical and hence this matter is being dealt with separately.
26. The appellant awarded contract dated 30.08.2001 to the
respondent for the work of six laning of NH-7 from KM 539 to KM
556 in the State of Karnataka, Contract Package No. NS-24/KN.
Clause 13.3 of the contract pertained to Taxes and Other Levies which
is set out hereinbelow :
13.3 All duties, taxes and other levies payable by
the contractor under the contract, or for any other
cause shall be included in the rates, prices and total
Bid Price submitted by the bidder.
JUDGMENT
Clause 13.4 of the contract pertained to price adjustment and is
set out hereinbelow:
13.4 The rates and prices quoted by the bidder are
subject to adjustment during the performance of
the Contract in accordance with the provisions of
Clause 47 of the Conditions of Contract.
Page 32
3
Clause 32.1 of the contract pertaining to Early Warning was as
under:
| ances that<br>, increase t | may adver<br>he Contra |
|---|
32.2 The Contractor shall cooperate with the
Engineer in making and considering proposals for
how the effect of such an event or circumstance
can be avoided or reduced by anyone involved in
the work and in carrying out any resulting
instructions of the Engineer.
Clause 45 of the Contract pertaining to Tax was as follows:
45.1 The rates quoted by the Contractor shall be
deemed to be inclusive of the sales and the other
taxes the Contractor will have to pay for the
performance of this Contract. The Employer will
perform such duties in regard to the deduction of
such taxes at sources as per applicable law.
JUDGMENT
Clause 47 of the contract pertained to Price Adjustment and is
set out hereinbelow:
47Price Adjustment
This clause is applicable only for those projects
with completion period of more that one year.
Page 33
3
| price adjus | tment shal |
|---|
b)….
c) Following expressions and meanings are
assigned to the work done during each month:
R= Total value of work done during the month. It
would include the value of materials on which
secured advance has been granted, if any, during
the month less the value of materials in respect of
which the secured advance has been recovered, if
any during the month. It will exclude value for
works executed under variations for which price
adjustment will be worked separately based on the
terms mutually agreed.
JUDGMENT
47.2 To the extent that full compensation for any
rise or fall in costs to the contractor is not covered
by the provisions of this or other clauses in the
contract, the unit rates and prices included in the
contract shall be deemed to include amounts to
cover the contingency of such other rise fall in
costs.
Page 34
3
27. In this case the disputes which have arisen between the parties
were:
(i) With respect to a claim for reimbursement as a result of
| Cess” with | effect fro |
|---|
formal agreement was executed in 2001. The claim was subject matter
of Arbitral Award dated 13.11.2006 which was affirmed by Single
Judge and later by the Division Bench of the High Court vide
judgments dated 02.07.2008 and 17.08.2009 respectively. The
decision was accepted and the appellant paid to the respondent sum of
Rs. 28,49,503 of 28.07.2010. We are not concerned with this issue.
(ii) We are concerned with the claim for reimbursement arising
out of the enhancement of royalty payable in respect of minor
minerals with effect from 02.06.2003 pursuant to amendment in the
JUDGMENT
Karnataka Mine and Minerals Concession Rules, 1994. It was
contended by the respondent that the increase in royalty charges by
the legislation during the pendency of the contract could not have
been anticipated or foreseen and therefore the same falls within the
ambit of Clause 32.1 of the contract. The appellant submitted that in
terms of express provision in sub-clause 45.1, it was incumbent upon
the contractor to cover any such eventuality in respect of increase in
Page 35
3
taxes in the contract price itself at the time of bidding. Further, there
being no subsequent legislation clause in the contract, the parties were
clear that no additional cost would be awarded in case of rise of
| e in legisla | tion. The |
|---|
dated 18.06.2006, accepting the claim, awarded a sum of
Rs.40,95,881/- towards royalty upto 27.02.2006 with interest @ 12%.
This award was challenged by the Appellant by filing OMP No. 497
of 2006, which was dismissed by a Single Judge of the High Court on
27.04.2012 and that judgment is presently under challenge.
28. The award accepted that revision in royalty rates in respect of
minor minerals by Government of Karnataka being subsequent to the
contract would be covered under the expression ‘future events’ in
clause 32.1 entitling the respondent to raise a claim. It was observed
JUDGMENT
that there was no dispute between the parties that royalty was not
included in WPI and that in other contracts the reimbursement
towards additional costs incurred as a result of subsequent legislation
was granted by relying on Sub Clause 70.8 or similar clauses. The
High Court while affirming the view of the Arbitral Tribunal
additionally relied upon the fact that claim as regards reimbursement
Page 36
3
on account of ‘cess’ was accepted by a separate award relying on very
same submission, which view was affirmed by the High Court as
stated hereinabove.
| ne through | the rec |
|---|
submissions. The view that as a result of upward variation in the rates
of royalty pursuant to subsequent legislation, the matter would be
covered by clause 32.1 is certainly a plausible view. While quoting the
initial rates and prices, it would not have been in contemplation of a
party as to the framework of any revision in rates of royalty at a future
date. Clause 32.1 can be said to have covered such eventualities. We,
therefore, see no any error in the assessment and approach of the
Arbitral Tribunal. The High Court, in our view, was right in
dismissing the challenge. Consequently, this appeal fails and is
JUDGMENT
dismissed. The decretal amount deposited and invested in a fixed
deposit, pursuant to orders of this Court, was ordered to be released on
furnishing of a bank guarantee by the respondent. The bank guarantee
shall stand discharged. No order as to costs.
Page 37
3
C. Civil Appeal No.6158 of 2013
30.This appeal is directed against the judgment and order dated
| ing FAO ( | OS) No.30 |
|---|
31. On 22.03.1999 the appellant awarded contract to the respondent
for the work of four laning of NH24 from KM 27.643 to KM 48.638
and construction of Hapur Bypass at Ghaziabad, U.P. Clause 28.2 of
the contract entered into between the parties pertained to royalties,
which was as under:-
Royalties 28.2 Except where otherwise stated, the
Contractor shall pay all tonnage and other
royalties, rent and other payments or
compensation, if any, for getting stone, sand,
gravel, clay or other materials required for Works .
JUDGMENT
Clauses 70.1, 70.2 and 70.8 of Conditions of Particular
Application (COPA) were identical as found in Civil Appeal 979 of
2010, dealt with earlier and as such they are not repeated here.
32. According to the respondent after the commencement of work,
it was called upon vide letter dated 15.12.1999 by the District
Page 38
3
Authorities asking for payment of royalty on ordinary earth at the rate
of Rs.4/- per cubic meter. Though it tried to convince them that
ordinary earth was not a minor mineral and not liable to attract
| ties insist | ed on su |
|---|
respondent deposited the requisite sum and wrote to the appellant to
give appropriate benefit. The Government of India declared ordinary
earth as minor mineral by issuing Notification dated 03.02.2000 as per
Section 3 of 1957 Act.
33. The disputes between the parties were referred to the Arbitral
Tribunal. We are concerned in the present appeal with Claim No.8
which was for refund of Royalty on ordinary earth amounting to
Rs.70,65,039/- which was claimed on the ground that it was covered
by Sub Clause 70.8 COPA. It was observed by the Arbitral Tribunal
JUDGMENT
that after the commencement of 1957 Act it was not within the powers
of UP State Government to have framed UP State Rules of 1963 and
consequently such Rules were not binding on the Contractor. In its
view, the imposition of royalty by the Government of UP vide
notification dated 20.03.2001, being after the Central Government’s
notification dated 03.02.2000, for the first time validly created a
Page 39
4
liability to pay royalty. Any levy and collection prior to 03.02.2000
was without any legal sanction and therefore liable to be disregarded
and since the liability was validly created after the contract was
| er was cov | ered under |
|---|
34. The award dated 09.01.2012 thus accepted Claim No.8 in its
entirety. This award was challenged by the appellant by filing OMP
No.480 of 2012 in the High Court of Delhi, which was dismissed by a
Single Judge of the High Court vide his order dated 18.05.2012. The
matter was carried in appeal by the appellant by filing FAO (OS)
No.302 of 2012 before the Division Bench which was dismissed vide
judgment and order dated 13.02.2013. While granting special leave
to appeal this Court confined the matter to Claim No.8 alone and
directed the appellant to furnish bank guarantee in the sum of
JUDGMENT
Rs.70,65,039/-. The bank guarantee was accordingly furnished and is
kept alive.
35. In support of the appeal, Ms. Indu Malhotra, learned Senior
Advocate submitted that the royalty, at the time the contract was
entered into, was payable at the rate of Rs. 4 per cent and the
notification dated 20.03.2001 of the Government of UP maintained
Page 40
4
the same rate. The reasoning that prior to 03.02.2000 the State
Government lacked competence and as such valid impact occurred
for the first time vide notification dated 20.03.2001, in her submission
| ond the sco | pe of the |
|---|
Tribunal. On the other hand, it was submitted by the respondent that a
demand letter from the District Collector was without the support of
law and that the impost pursuant to notification of 20.3.2001 alone
was valid and legal and as such it being after the contract was entered
into, must qualify to be ‘subsequent legislation’.
36. The question, therefore, is whether Claim No.8 is covered by
Clause No.70.8 of COPA. In clause No.13.4 of the Invitation to
Tender it was clearly stipulated in the contract that all duties, taxes
and other levies payable by the contractor under the contract as of the
JUDGMENT
th
date 28 days prior to the deadline for submission of bid shall be
included in the rates and prices and the total bid price submitted by
the bidder. The State Government, as a matter of fact, was levying
royalty on ordinary earth and this situation was obtaining on such
date. If the State Government lacked power to levy and collect such
royalty prior to the notification dated 03.02.2000 whereby ordinary
Page 41
4
earth was brought under the definition of minor mineral, such ground
may certainly entitle a party to lay requisite challenge before an
appropriate forum. However, for the purposes of the contract such
| g levy mus | t be deem |
|---|
rates or prices quoted. By notification dated 20.03.2001, the same rate
was maintained and as such there was no change arising due to any
subsequent legislation. In our view the matter was therefore
completely outside the scope of Sub Clause 70.8 of COPA. The
Arbitral Tribunal ought to have confined itself to the terms of the
Contract and see if there was any variation for the purposes of
Sub-Clause 70.8 of COPA. It went beyond its powers in holding that
the existing levy as on the date the contract was entered into was
without any authority in law and as such the imposition by
JUDGMENT
notification dated 20.03.2001 created liability for the first time.
37. In our view, the Arbitral Tribunal went beyond the scope of the
contract and it clearly exceeded its jurisdiction. We, therefore, set
aside the award insofar as it allows Claim No. 8. Consequently, the
appeal stands allowed. At the interim stage, this Court had directed
the Appellant to deposit a sum of Rs.70,65,039/- which upon deposit
Page 42
4
was withdrawn by the Respondent on furnishing a bank guarantee.
The appellant is entitled to encash that bank guarantee to recover the
sum that was deposited. No order as to costs.
.……………………….J
(Dipak Misra)
………………………..J.
(Uday Umesh Lalit)
New Delhi,
April 24, 2015
JUDGMENT
Page 43