Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.179 of 2017
NABHA POWER LIMITED (NPL) ….Appellants
versus
PUNJAB STATE POWER
CORPORATION LIMITED (PSPCL) & ANR. ..…Respondents
J U D G M E N T
SANJAY KISHAN KAUL, J .
Facts:
1. The Punjab State Electricity Board (‘PSEB’) in the year 2009
conducted an international competitive bidding for selection of
developer through tariff based bidding process for procurement
of power on long term basis from a power station to be set up
at Village Nalash, Rajpura, District Patiala, Punjab. This
power station was envisaged as a Case-2 bid project (Case-2,
Signature Not Verified
Digitally signed by
SHASHI SAREEN
Date: 2017.11.11
11:07:05 IST
Reason:
CIVIL APPEAL No.179 of 2017 Page 1 of 63
Scenario-4) criteria by PSEB in terms of the competitive
bidding guidelines issued by the Government of India as per
Section 63 of the Electricity Act, 2003 (hereinafter referred to
as the ‘EA’).
2. The significance of the aforesaid is that Part-7 of the EA,
which contains the provisions for tariff, provides for tariff
regulations to be determined by the appropriate commission as
per guiding principles set out in the Section of the EA. The
tariff is determined under Section 62 of the EA. However in a
scenario such as the present case, the determination is as per
the provisions of Section 63 of the EA, which reads as under:
“ Section 63. Determination of tariff by bidding process. –
Notwithstanding anything contained in section 62, the
Appropriate Commission shall adopt the tariff if such tariff has
been determined through transparent process of bidding in
accordance with the guidelines issued by the Central
Government.”
3. In order to facilitate the implementation of the project the
PSEB incorporated Nabha Power Limited (‘NPL/Appellant’)
on 9.4.2007 as a special purpose vehicle (‘SPV’) for
implementation of the project and the successful bidder was to
acquire 100 per cent shareholding of the NPL and enter into a
CIVIL APPEAL No.179 of 2017 Page 2 of 63
25 year Power Purchase Agreement (‘PPA’) with PSEB.
4. It may be noticed for the purpose of completion of facts that
the first respondent, Punjab State Power Corporation Limited,
(‘PSPCL’) is the successor entity of the erstwhile PSEB
subsequent to the unbundling of PSEB in accordance with the
Punjab Power Sector Reforms Transfer Scheme, 2010, while
the second respondent is the Punjab State Electricity
Regulatory Commission (‘PSERC’).
5. On 10.6.2009, a Request for Qualification (‘RFQ’) and a
Request for Proposal (‘RFP’) inviting proposals to supply 1200
MW of power from the Rajpura Thermal Power Project was
issued. The RFQ specified that the following tasks had already
been completed:
“i. 1078 acres of land had been acquired.
ii. Environmental clearance had been obtained.
iii. Fuel arrangements had been tied up in the form of LoA
dated 11/18.12.2008.
iv. Water arrangement had been tied up.”
While the RFP specifically provided that:
CIVIL APPEAL No.179 of 2017 Page 3 of 63
“i. The source of primary fuel (coal) would be coal from SECL
since SECL had already issued the LoA.
ii. The Railways had given assurance for transportation of coal
from SECL over a distance of 1600 km.”
6. On the bidding document being issued on 16.9.2009, certain
queries and clarifications were raised by the prospective
bidders in terms of the bidding documents for which
clarifications were issued. The significant clarifications qua
the matter at hand, noticed even in the impugned order, are as
under:
“i. SECL would supply Grade ‘F’ coal from Korba/Raigarh
field, with GCV of 3900 Kcal/kg to 4260 Kcal/kg, Ash Content
of 35% to 40%, total inherent moisture of 5% to 6%, Volatile
matter of 24% to 32%, fixed carbon of 32% to 37% and
Sulphur content of 0.05%.
ii. On a specific query of whether the coal to be supplied would
be washed coal or unwashed coal, it was clarified that washing
of coal was to be arranged by the successful bidder.
iii. In response to the queries raised by the bidders,
clarifications on the model PPA were also issued on
17.09.2009. On the question of the costs associated with fuel
supply, transportation and unloading being pass through, it was
clarified that tariff payment will be in accordance with
Schedule VII of the PPA.”
7. On the bidding process being completed, M/s. L&T Power
CIVIL APPEAL No.179 of 2017 Page 4 of 63
Development Limited (‘L&T PDL’) was declared as the
successful bidder and a Letter of Intent was issued on
19.11.2009. Thereafter on 18.1.2010, a Share Purchase
Agreement (‘SPA’) was entered into between PSEB and L&T
PDL, transferring 100 per cent of the shares of NPL to L&T
PDL. Simultaneously the PPA was entered into between PSEB
and NPL. The contractual obligation began of the respective
parties.
8. In the course of the contractual obligations, various issues
arose, some of which were resolved. However, in respect of
the amounts payable to the appellant, the controversy
commenced, and remained right from the first invoice. It is the
case of the appellant, that the first respondent made deductions
from the amount due and payable under the invoices, on the
following accounts:
“i. Component of the cost of purchasing coal comprising
washing related costs including washery charges and cost of
coal towards loss of quantity on account of washing (yield
loss);
ii. Consideration of mid-point of GCV of ROM coal on
equilibrated GCV basis (‘EGCV’) to calculate energy charges;
CIVIL APPEAL No.179 of 2017 Page 5 of 63
iii. Denial of road transportation cost – at the plant-end and at
the mine-end.
iv. Denial of Liaising charges, denial of Transit and handling
losses and denial of Third party coal testing charges; and
v. Non-payment of Capacity Charges for the period from
20.02.2014 to 03.03.2014 when the availability was declared
on non-linkage (alternate) coal.”
9. The aforesaid gave rise to a cause for the appellant to file
Petition No.52 of 2014 under Section 86(1)(b) & (f) of the EA
before the State Commission seeking relief on account of
wrongful deduction of certain components of monthly tariff by
the first respondent. The State Commission, post admission,
dismissed this petition vide order dated 1.2.2016. The
appellant, thus, filed Appeal No.64 of 2016 before the
Appellate Tribunal (‘AT’). The appeal was, however, rejected
vide order dated 14.12.2016 on most grounds except the
non-payment of capacity charges allowed in favour of the
appellant. It may be noticed that in the course of the appeal
various questions of law were framed but ultimately the same
were restricted only to five issues.
CIVIL APPEAL No.179 of 2017 Page 6 of 63
10.
The dispute really is about the interpretation of the
provisions of the PPA dated 18.1.2010 and is, thus, one of pure
interpretation of the terms of the contract.
The plea of the Appellant:
11. Mr. Mukul Rohatgi, learned Senior Advocate, argued on
behalf of the appellant. Mr. Rohatgi contended that the
significant aspect is that the bidding process for the power
project was in terms of the “Guidelines for Determination of
Tariff by Bidding Process for Procurement of Power by
Distribution Licensees, 2005” (hereinafter referred to as the
‘Guidelines’), which have a statutory flavor under Section 63
of the EA. Para 2.2 read with para 3.2(i) of the Guidelines
envisages two routes of competitive bidding, Case-1 and
Case-2. The said paras read as under:
“2.2. The guidelines shall apply for procurement of base-load,
peak-load and seasonal power requirements through
competitive bidding, through the following mechanisms:
(i) Where the location, technology, or fuel is not specified
by the procurer (Case 1);
CIVIL APPEAL No.179 of 2017 Page 7 of 63
(ii) For hydro power projects, load center projects or other
location, specific projects with specific fuel allocation
such as captive mines available, which the procurer
intends to set up under tariff based bidding process
(Case-2).
However separate RFP shall be used for procuring base load or
peak load or seasonal load requirements as the case may be.”
…. …. …. …. ….
“3.2 (i) In order to ensure timely commencement of supply of
electricity being procured and to convince the bidders about
the irrevocable intention of the procurer, it is necessary that
various project preparatory activities are completed in time.
For long term procurement for projects for which
pre-identified sites are to be utilized (Case-2), the following
project preparatory activities should be completed by the
procurer, or authorized representative of the procurer,
simultaneously with bid process adhering to the milestones as
indicated below:
(i) Site identification and land acquisition: If land is
required to be acquired for the power station, the
notification under section 4 of the Land Acquisition Act,
1894 should have been issued before the publication of
RFQ. The notification under section 6 of the Land
Acquisition Act, 1894 should have been issued before the
issue of RFP. If the provisions of section 17 of the Land
Acquisition Act, 1894 regarding emergency have not been
applied, the Award under the Land Acquisition Act should
have been declared before the PPA becomes effective.
(ii) Environmental clearance for the power station: Rapid
Environmental Impact Assessment (EIA) report should be
available before the publication of RFQ. Requisite
proposal for the environmental clearance should have
CIVIL APPEAL No.179 of 2017 Page 8 of 63
been submitted before the concerned administrative
authority responsible for according final approval in the
Central/State Govt., as the case may be, before the issue
of RFP. Environmental clearance should have been
obtained before PPA becomes effective.
(iii) Forest Clearance (if applicable) for the land for the
power station: Requisite proposal for the forest clearance
should have been submitted before the concerned
administrative authority responsible for according final
approval in the Central/State Govt., as the case may be,
before the issue of RFP.
(iv) Fuel Arrangements: If fuel linkage or captive coal
mine(s) are to be provided, the same should be available
before the publication of RFQ. In case, bidders are
required to arrange fuel, the same should be clearly
specified in the RFQ.
(v) Water linkage: It should be available before the
publication of RFQ.
(vi) Requisite Hydrological, geological, meteorological
and seismological data necessary for preparation of
Detailed Project Report (DPR), where applicable. These
should be available before the issue of RFP. The bidder
shall be free to verify geological data through his own
sources as the geological risk would lie with the project
developer.
The project site shall be transferred to the successful bidder at
a price to be intimated at least 15 days before the due date for
submission of RFP bids.”
12. The essential difference between Case-1 and Case-2
procurement route is stated to be that a Case-2 is a ‘fuel
CIVIL APPEAL No.179 of 2017 Page 9 of 63
specific procurement’ having a ‘pre-identified site’ as in the
present case. It is in these circumstances that the first
respondent, being the procurer is stated to have arranged the
fuel linkage from SECL, Chhattisgarh and specified the site
location for the project near Village Nalash, Tehsil Rajpura,
Punjab. The bidder’s responsibility included design,
engineering, procurement, construction, testing,
commissioning, financing, operation and maintenance of the
power station. Even under the Case-2 model, there are stated
to be five scenarios, and the bid parameters of each scenario is
stated to be different – the present one being scenario 4. This
is stated to be significant inasmuch as an all-inclusive
fixed/capped energy charge was not a bidding parameter, and
the energy charges were designed to vary in accordance with
the actual cost of coal, and the actual quality of coal. The
appellant, as bidder, is thus stated to have taken the risk only of
one component of the energy charge formula, being the
efficiency of the project, and not with respect to other two
components, i.e., cost of coal and Gross Calorific Value
CIVIL APPEAL No.179 of 2017 Page 10 of 63
(‘GCV’) of coal, including its constituents. This is the reason
stated for the relevant formula under Article 1.2.3 of Schedule
7 of the PPA, which will be discussed hereafter.
13. It is the case of the appellant that on 16.9.2009, prior to
the bid date, PSPCL disclosed the coal quality in its pre-bid
clarification. The project was located at a distance of more
than 1,000 kilometers from the SECL mine and the coal
arranged by the respondent contained more than 34 per cent
ash. The project, thus, came under the ambit of Ministry of
Environment and Forest (for short ‘MoEF’) Notification of
1997, making it mandatory for the coal to be washed for the
use of generation of electricity energy. PSPCL, also mandated
that washing of coal was to be arranged by the successful
bidder (pre-bid clarification). The query raised by the
appellant was as to whether the coal to be supplied for the
project, was washed coal or unwashed coal (query No.6). It is
the plea of the appellant that, thus, the reference to coal and
fuel in the PPA, including the energy charges formula, could
only refer to washed coal and thus the actual cost of
CIVIL APPEAL No.179 of 2017 Page 11 of 63
purchasing, transporting and unloading coal referred to in
Article 1.2.3 of Schedule 7 of the PPA, must refer to such
actual cost of washed coal. The PSPCL, however, took a
contrary stand that the term ‘washing’ is not part of the energy
charges formula, while the appellant sought to include – (A)
the actual cost of unwashed coal procured by NPL from SECL,
including the cost of coal lost in washing (around 20 per cent);
and (B) washing charges paid for getting the coal washed. The
appellant’s stand, thus, is that the clarification that the
successful bidder would have to arrange for washing of coal,
would not imply that the washing cost has to be fastened on to
the appellant, as in terms of the PPA, the energy charge
formula expressly provided for actual cost incurred, to be
reimbursed.
14. The significant contention of the appellant is that the
operation cost mentioned in clause 2.7.1.4(3) of the RFP only
referred to the cost towards operating and maintenance of
power plant, and cannot refer to any cost associated with the
cost of coal, which is a part of the energy charges.
CIVIL APPEAL No.179 of 2017 Page 12 of 63
15. The appellant also invoked the principle of ‘business
efficacy’ and the maxim ‘Reddendo Singula Singulis’ for
interpreting the terms of the PPA and the Energy Charges
Formula, as set out at Article 1.2.3 of Schedule 7 of the PPA.
16. The aforesaid is really the major and the first dispute inter
se the parties.
17. The second dispute relates to the GCV of the coal, and is
in a sense, linked to the first dispute. This is so as the PSPCL
2
takes into account the theoretical/Equilibrated GCV (‘EGCV’)
of unwashed coal at the mine-end rather than GCV of washed
coal on an As Received Basis (‘ARB’) at the project-end as
part of PCV n in the Energy Charges formula. The GCV of the
coal is stated to change significantly due to transportation by
rail over a period of 4 to 5 days, as coal contains moisture.
The critical stage is stated to be the measure of GCV when the
project coal reached the site (from the mine-end in
Chhattisgarh to the project-site at Rajpura) when it is stated to
be jointly sampled, tested and recorded by NPL and PSPCL.
This is stated to be obvious from the definition of PCV n . The
CIVIL APPEAL No.179 of 2017 Page 13 of 63
joint sampling done at the mines of SECL is only of unwashed
coal.
COAL
18. The formula, it is pleaded, of F
n is stated to refer to the
actual cost of transporting the coal to the project and the actual
cost of unloading at the project. The mere transfer of title of
unwashed coal, which cannot be used in generation of
electricity charges is, thus, pleaded not to imply delivery of
coal to the project.
19. On the same principle, there is a third aspect of the claim
of transportation cost of coal with respect to the first mile and
the last mile. The first mile is on account of the unwashed coal
from the mine to the washery, while the last mile is stated to
have been incurred for carriage of coal from the nearest
railway station to the project, on account of incomplete land
acquisition by the Government of Punjab on behalf of the
PSPCL. The transportation has to be reimbursed irrespective
of mode. In a Case-2 project, the risk towards land is not
assigned to the bidder but is of the PSPCL.
20. There are also certain other linked charges qua coal in the
CIVIL APPEAL No.179 of 2017 Page 14 of 63
context of transit and handling charges, third party testing
charges and liaising charges.
21. In the synopsis filed, the appellant has claimed even
interest on the disputed energy charges in view of Article
11.3.4 read with Article 11.6.8 requiring payment of
interest/late payment surcharge on the disputed component of
the monthly bill from the date on which such payment was
originally due against whom the dispute is settled/decided.
The absence of a separate prayer for the payment of interest, it
has been pleaded, cannot deny the appellant such benefit which
must enure in case of the appellant succeeding in the
adjudication. Also the appellant having been deprived of the
use of money, this deprivation cost should be compensated
with interest/damages. We may note at the end of such
submissions of the appellant, that along with certain synopsis,
some documents have been filed showing joint sampling in the
presence of NPL and PSPCL representatives for the coal
received at the project-site including coal received after
washing, to deny the plea of respondent No.1 that such
CIVIL APPEAL No.179 of 2017 Page 15 of 63
verification was being done only at the mine-site.
Plea of the First Respondent:
22. The first respondent through Mr. V. Giri, learned Senior
Advocate canvassed that any claim of the appellant relatable to
coal has to be considered in terms of Clause 1.2.3 of Schedule
7 of the PPA. In terms thereof, there are stated to be only three
distinct identifiable components of coal recognized for tariff:
(a) Purchase; (b) Transportation and (c) Unloading. Thus, until
and unless the claims squarely fall under one of these three
heads, the same cannot be included in the monthly energy
charges. It is not as if all costs relatable to coal handling from
the stage of procurement from SECL at the coal mine-site, up
to stage of firing in the boiler to generate electricity is to be
included. Had that been the intention, the stipulation would
have been of actual cost of coal used for generation of power.
23. The plea raised is that the cost of coal is payable to SECL,
which is provided on actual basis. It was abundantly clear that
the coal supplied would not be washed coal and the obligation
CIVIL APPEAL No.179 of 2017 Page 16 of 63
of washing was on the appellant. Such washing could have
been undertaken either by establishing a washery, or by
outsourcing the washing activity to a third party. Not only
washing, there were certain other essential activities to be
undertaken in relation to coal after the purchase of coal,
including sizing of coal, crushing of coal, sprinkling and
moisturisation of coal for stacking and storage, sorting of coal,
ash removal, removal of stones and other undesired contents,
demoisturisation of coal, pulverization of coal, etc. The
calculation formula, for monthly energy charges, is claimed to
provide for only the purchase price paid to SECL and not any
other expenditure incurred by the appellant.
24. The first respondent contends that the definition of the
term ‘fuel supply agreement’ refers to the agreement between
the appellant and the fuel supplier, i.e., SECL, and thus, the
transaction of purchase referred to in Clause 1.2.3 of Schedule
7 of the PPA is identifiable to the purchase in the definition of
the fuel supply agreement.
25. The attention of the Court was also invited to “Project
CIVIL APPEAL No.179 of 2017 Page 17 of 63
Documents”, which reads as under:
““Project Documents” mean
a) Construction Contracts;
b) Fuel Supply Agreements including the Fuel
Transportation Agreement;
c) O&M contracts;
d) RfP and RfP Project Documents; and
e) any other agreements designated in writing as such,
from time to time, jointly by the Procurer and the Seller;”
26. It is, thus, pleaded that there is no separate agreement for
‘washing’ included in this list of what constituted “Project
Documents.” The delivery point under the fuel supply
agreement is the loading end of the colliery whereafter the title
and risk of the coal is that of the appellant. Thus, the purchase
is complete.
27. The burden to obtain any clarification being on the
appellant, it was submitted that the clarification which they
actually sought was as to whether the coal to be supplied
would be washed or unwashed, to which a categorical answer
was given. Had the appellant any doubt about bearing the cost
CIVIL APPEAL No.179 of 2017 Page 18 of 63
for the washed coal, they could easily have raised a specific
query in that behalf. This is sought to be read along with
Clause 2.7.1.4 providing for the quoted tariff to be an ‘all
inclusive tariff’ with no exclusion allowed. Thus, the washing
of coal and other activities in relation thereto, are to be
included in the quoted tariff, which is as per unit tariff. The
relevant clause, in this regard, reads as under:
“2.7.1.4 The Bidder shall inter alia take into account the
following while preparing and submitting the financial Bid:
…. …. …. …. ….
3. The Quoted Tariff in Format 1 of Annexure 4 shall be
an all inclusive tariff and no exclusions shall be allowed.
The Bidder shall take into account all costs including
capital and operating costs, statutory taxes, duties, levies
while quoting such tariff. Availability of the inputs
necessary for generation of power should be ensured by
the Seller at the Project Site and all costs involved in
procuring the inputs (including statutory taxes, duties,
levies thereof) at the Project Site must be reflected in the
Quoted Tariff.”
…. …. …. …. ….
“6. The Bidders should factor the cost of the secondary
fuel into the Quoted Tariff and no separate reimbursement
shall be allowed on this account.”
28. The first respondent seeks to draw a distinction between
the purchase cost of fuel and the cost of usable fuel for the
contention that it is only the first one which is to be included.
CIVIL APPEAL No.179 of 2017 Page 19 of 63
29. On the second issue of GCV, the plea raised is that it is the
own case of the appellant itself that SECL is actually over
stating the GCV of coal actually supplied. Since the coal is to
be jointly analyzed and tested at the stage of delivery, it is not
understood how SECL is supplying inferior coal but billing for
superior coal. In any case, this is an issue to be raised with
SECL. The formula of energy charges in relation to GCV, is
using the expression the coal delivered “to the project.” This is
in contradistinction to the expression “to and at the project”
which is used in relation to the cost of coal. Thus, with these
two different expressions used, they obviously mean two
different things. In support of his proposition reliance is
placed on Life Corporation of India & Anr. vs. Dharam Vir
1
Anand , wherein it was observed as under:
“6. ….. In construing a particular Clause of the Contract it is
only reasonable to construe that the word and the terms used
therein must be given effect to. In other words one part of the
Contract cannot be made otiose by giving a meaning to the
policy of the contract. Then again when the same Clause of a
contract uses two different expressions, ordinarily those different
expressions conveying one and the same meaning.”
30. Qua the issue of road transportation charges, a reference
1
(1998) 7 SCC 348
CIVIL APPEAL No.179 of 2017 Page 20 of 63
has been made to the RFP where under the heading of
“Activities/Milestones to be completed before issue of RfP as
per Bidding guidelines” at serial No.3 only transportation
through Railways has been envisaged:
| Sl. No. | Project<br>Inputs/clearances | Parameters | Status of<br>activities/milestones |
|---|---|---|---|
| 3. | Fuel<br>Transportation | For Coal<br>approx.<br>1600 km | Railways have<br>given assurance for<br>transportation of<br>Coal from SECL. |
31. The land for the Railways siding was to be acquired by
the bidder (appellant) as per the requirement, and the
Government of Punjab was to facilitate the acquisition of land.
1078 acres of land was already acquired. The relevant extract
of the RFP is as under:
| B. Other Project Related Activities/Milestones | |||
|---|---|---|---|
| Sl. No. | Project<br>Inputs/clearance<br>s | Parameters | Status of<br>activities/milest<br>ones |
| 1. | Land | ||
| ii) Railway<br>sidings and rail<br>lines from<br>nearby station to<br>site | To be acquired<br>by Selected<br>Bidder as per<br>requirement.<br>Govt. of Punjab<br>will facilitate<br>acquisition of |
CIVIL APPEAL No.179 of 2017 Page 21 of 63
| land as desired<br>by the Selected<br>Bidder. |
|---|
32. The endeavour to get any other linked claim arising from
coal is also thus denied, as is the claim for interest, which was
not even claimed. It is added by providing a copy of the order
dated 7.6.2017 of the Commission dealing with the remand
proceedings, that since the claim for interest there has been
rejected now on the ground that there was no claim made
earlier, the submission sought to be made in respect of the
claim for interest is an attempt to get over the said defect. The
question of payment of interest arises only qua bills, which are
not in dispute, the relevant clause being, clause 11.3.4, as
under:
“11.3.4 In the event of delay in payment of a Monthly Bill
by the Procurer beyond it Due Date month billing, a Late
Payment Surcharge shall be payable by the Procurer to the Seller
at the rate of two (2) percent in excess of the applicable SBAR
per annum, on the amount of outstanding payment, calculated on
a day to day basis (and compounded with Monthly rest), for each
day of the delay.”
Legal Principles for interpretation of a commercial contract:
CIVIL APPEAL No.179 of 2017 Page 22 of 63
33.
The contours of the controversy show that we are really
concerned with the interpretation of the commercial contract
inter se the parties. Before analyzing the relevant clauses of
the contract including the Definition clause and formulae, we
consider it appropriate to set forth certain judicial
pronouncements relevant for determination of the issue.
34. To begin with we refer to the judgment of the Court of
2
Appeal in The Moorcock . Bowen, L.J., dealt with the implied
warranty on the part of the owners of the jetty, in respect of a
contract made for the use of the jetty to a ship, for discharge of
its cargo. The name of the ship was ‘The Moorcock’. It was
observed as under:
“ Bowen, L.J. : ….Now, an implied warranty, or, as it is called,
a covenant in law, as distinguished from an express contract or
an express warranty, really is in all cases founded on the
presumed intention of the parties, and upon reason. The
implication which the law draws from what must obviously have
been the intention of the parties, the law draws with the object of
giving efficacy to the transaction and preventing such a failure
of consideration as cannot have been within the contemplation
of either side; and I believe that if one were to take all the cases,
and they are many, of implied warranties or covenants in law, it
will be found that in all of them the law is raising an implication
from the presumed intention of the parties with the object of
giving to the transaction such efficacy as both parties must have
2
(1889) 14 PD 64
CIVIL APPEAL No.179 of 2017 Page 23 of 63
intended that at all events it should have. In business
transactions such as this, what the law desires to effect by the
implication is to give such business efficacy to the transaction as
must have been intended at all events by both parties who are
business men; not impose on one side all the perils of the
transaction, or to emancipate one side from the all chances of
failure, but to make each party promise in law as much, at all
events, as it must have been in the contemplation of both parties
that he should be responsible for in respect of those perils or
chances.” (Emphasis supplied)
35. The significant issue was the principle of ‘business
efficacy to the transactions’ which are intended at all events by
parties who are businessmen.
36. The aforesaid was, once again, relied upon in Shirlaw v.
3
Southern Foundries (1926) L.D. wherein MacKinnon, L.J.,
observed as under:
“I recognize that the right or duty of a Court to find the existence
of an implied term or implied terms in a written contract is a
matter to be exercised with care; and a Court is too often invited
to do so upon vague and uncertain grounds. Too often also such
an invitation is backed by the citation of a sentence or two from
the judgment of Bowen L.J. in The Moorcock (1939) 2 KB 206.
They are sentences from an extempore judgment as sound and
sensible as all the utterances of that great judge; but I fancy that
he would have been rather surprised if he could have foreseen
that these general remarks of his would come to be a favourite
citation of a supposed principle of law, and I even think that he
might sympathize with the occasional impatience of his
successors when The Moorcock (1939) 2 KB 206 is so often
flushed for them in that guise.
3
(1939) 2 KB 206
CIVIL APPEAL No.179 of 2017 Page 24 of 63
For my part, I think that there is a test that may be at least as
useful as such generalities. If I may quote from an essay which I
wrote some years ago, I then said: “Prima facie that which in
any contract is left to be implied and need not be expressed is
something so obvious that it goes without saying; so that, if,
while the parties were making their bargain, an officious
bystander were to suggest some express provision for it in their
agreement, they would testily suppress him with a common ‘Oh,
of course!’ ”
At least it is true, I think, that, if a term were never implied by a
judge unless it could pass that test, he could not be held to be
wrong.”
37. The aforesaid, thus, extended a word of caution while
applying The Moorcock test, by bringing forth “The Officious
Bystander Test” of ‘Oh, of course!’.
38. In Reigate vs. Union Manufacturing Co. (Ramsbottom)
4
Ltd. , Scrutton L.J., discussed the developments in respect of
these principles and observed as under:
“These principles, however, have been clearly established: The
first thing is to see what the parties have expressed in the
contract; and then an implied term is not to be added because the
Court thinks it would have been reasonable to have inserted it in
the contract. A term can only be implied if it is necessary in the
business sense to give efficacy to the contract; that is, if it is
such a term that it can confidently be said that if at the time the
contract was being negotiated some one had said to the parties,
“What will happen in such a case,” they would both have
replied, “Of course, so and so will happen; we did not trouble to
say that; it is too clear.” Unless the Court comes to some such
4
[1918] 1 K.B. 592
CIVIL APPEAL No.179 of 2017 Page 25 of 63
conclusion as that, it ought not to imply a term which the parties
themselves have not expressed.”
…. …. …. …. ….
“Is that a necessary implication? If this matter had been mooted
at the time when the contract was being negotiated, I expect that
the parties would at once have disagreed as to what the position
was. Unless we are satisfied that it is an implication which must
necessarily have been in the minds of both parties, we cannot
imply a term which they have not expressed, especially when I
see that they have thought sufficiently about the matter to
express two conditions on which the agreement is to be
determined, first, the obvious one on the death of the agent; and,
secondly, by six months' notice after the expiration of the seven
years.”
5
39. In Liverpool City Council vs. Irwin , Lord Denning M.R.,
observed as under:
“It is often said that the courts only imply a term in a contract
when it is reasonable and necessary to do so in order to give
business efficacy to the transaction: see The Moorcock (1889)
14 P.D. 64, 68. (Emphasis is put on the word “necessary”:
Reigate v. Union Manufacturing Co. (Ramsbottom) Ltd. [1918]
1 K.B. 592, 605.) Or when it is obvious that both parties must
have intended it: so obvious indeed that if an officious bystander
had asked them whether there was to be such a term, both would
have suppressed it testily: “Yes, of course”: see Shirlaw v.
Southern Foundries (1926) Ltd. [1939] 2 K.B. 206, 227.
Those expressions have been repeated so often that it is with
some trepidation that I venture to question them. I do so because
they do not truly represent the way in which the courts act. Let
me take some instances. There are stacks of them. Such as the
terms implied by the courts into a contract for the sale of goods
5
(1976) Q.B. 319
CIVIL APPEAL No.179 of 2017 Page 26 of 63
— Jones v. Just (1868) L.R. 3 Q.B. 197: or the hire of goods —
Asley Industrial Trust Ltd. v. Grimley [1963] 1 W.L.R. 584: into
a contract for work and materials —Young & Marten Ltd. v.
McManus Childs Ltd. [1969] 1 A.C. 454: or into a contract for
letting an unfurnished house — Hart v. Windsor (1843) 12 M. &
W. 68: or a furnished house — Collins v. Hopkins [1923] 2 K.B.
617: or into the carriage of a passenger by railway: see
Readhead v. Midland Railway Co. (1869) L.R. 4 Q.B. 379: or to
enter on premises: see Francis v. Cockrell (1870) L.R. 5 Q.B.
501: or to buy a house in course of erection: see Hancock v. B.
W. Brazier (Anerley) Ltd. [1966] 1 W.L.R. 1317.
If you read the discussion in those cases, you will see that in
none of them did the court ask: what did both parties intend? If
asked, each party would have said he never gave it a thought: or
the one would have intended something different from the other.
Nor did the court ask: Is it necessary to give business efficacy to
the transaction? If asked, the answer would have been: “It is
reasonable, but it is not necessary.” The judgments in all those
cases show that the courts implied a term according to whether
or not it was reasonable in all the circumstances to do so. Very
often it was conceded that there was some implied term. The
only question was: “What was the extent of it?” Such as, was it
an absolute warranty of fitness, or only a promise to use
reasonable care? That cannot be solved by inquiring what they
both intended, or into what was necessary. But only into what
was reasonable. This is to be decided as matter of law, not as
matter of fact. Lord Wright pulled the blinkers off our eyes when
he said in 1935 to the Holdsworth Club:
“The truth is that the court …. decides this question in
accordance with what seems to be just or reasonable in its eyes.
The judge finds in himself the criterion of what is reasonable.
The court is in this sense making a contract for the parties —
though it is almost blasphemy to say so.” (Lord Wright of
Durley, Legal Essays and Addresses (1939), p. 259.)
In 1956, Lord Radcliffe put it elegantly when he said of the
CIVIL APPEAL No.179 of 2017 Page 27 of 63
parties to an implied term:
“their actual persons should be allowed to rest in peace. In their
place there rises the figure of the fair and reasonable man. And
the spokesman of the fair and reasonable man, who represents
after all no more than the anthropomorphic conception of justice,
is and must be the court itself”: see Davis Contractors Ltd. v.
Fareham Urban District Council [1956] A.C. 696, 728.
In 1969, Lord Reid put it simply when he said: “… no warranty
ought to be implied in a contract unless it is in all the
circumstances reasonable,” see Young & Marten Ltd. v.
McManus Childs Ltd. [1969] 1 A.C. 454, 465: and Lord Upjohn
echoed it when he said, at p. 471, that the implied warranty was
“imposed by law.””
40. The aforesaid judgment was carried in appeal to the
House of Lords in Liverpool City Council vs. Irwin [H.L.
6
(E.)] . However, it was clarified that the touchstone for
interpreting commercial documents, cannot be ‘mere
reasonableness’ as Lord Denning had observed, but
‘necessity’ :
Edmund–Davies, L.J.,: “That set the Court of Appeal off on
considering in what circumstances a contractual term could be
implied, and that understandably but unfortunately led them to
The Moorcock , 14 P.D. 64. It had not been cited in Miller v.
Hancock but the Court of Appeal considered that it enshrined the
only possible basis for implying such a term as that contended
for by the tenants. It is right to say, furthermore, that such was
the only basis advanced on behalf of the tenants themselves at
6
(1976) 2 WLR 562
CIVIL APPEAL No.179 of 2017 Page 28 of 63
that time. The Court of Appeal accordingly proceeded to
consider whether, in the light of The Moorcock , such a term
could be implied in the tenancy agreement. Roskill L.J. (with
whom Ormrod L.J. agreed) said [1975] 3 W.L.R. 663, 677:
“I cannot agree … that it is open to us in the court at the
present day to imply a term because subjectively or
objectively we as individual judges think it would be
reasonable so to do. It must be necessary in order to make
the contract work as well as reasonable so to do, before
the court can write into a contract as a matter of
implication some term which the parties have themselves,
assumedly deliberately, omitted to do.”
Lord Denning M.R., on the other hand, “with some trepidation”
(p. 669) (which was understandable), took a different view and,
after referring to some out of the “stacks” of relevant cases, said,
at p. 670:
“…in none of them did the court ask: what did both
parties intend? If asked, each party would have said he
never gave it a thought: or the one would have intended
something different from the other. Nor did the court ask:
Is it necessary to give business efficacy to the transaction?
If asked, the answer would have been: ‘It is reasonable,
but it is not necessary.’ The judgments in all those cases
show that the courts implied a term according to whether
or not it was reasonable in all the circumstances to do so
…. This is to be decided as matter of law, not as matter of
fact.”
I have respectfully to say that I prefer the views of the majority
in the Court of Appeal. Bowen L.J. said in the well known
passage in The Moorcock, 14 P.D. 64, 68:
“In business transactions such as this, what the law desires
to effect by the implication is to give such business
efficacy to the transaction as must have been intended at
CIVIL APPEAL No.179 of 2017 Page 29 of 63
all events by both parties who are business men; … to
make each party promise in law as much, at all events, as
it must have been in the contemplation of both parties that
he should be responsible for …”
That is not to say, of course, that consideration of what is
reasonable plays no part in determining whether or not a term
should be implied. Thus, in Hamlyn & Co. v. Wood & Co.
[1891] 2 Q.B. 488, decided only two years after The Moorcock
(to which he had been a party), Lord Esher M.R. said, at p. 491:
“… the court has no right to imply in a written contract
any such stipulation, unless , on considering the terms of
the contract in a reasonable and business manner , an
implication necessarily arises that the parties must have
intended that the suggested stipulation should exist. It is
not enough to say that it would be a reasonable thing to
make such an implication. It must be a necessary
implication in the sense that I have mentioned.”
Bowen and Kay L.JJ., who had also been members of the
Moorcock court, delivered similar judgments. The touchstone is
always necessity and not merely reasonableness : see, for
example, the judgment of Scrutton L.J. in Reigate v. Union
Manufacturing Co. (Ramsbottom) Ltd. [1918] 1 K.B. 592, 605,
and in the case cited below by Roskill L.J., In re Comptoir
Commercial Anversois v. Power, Son and Co. [1920] 1 K.B.
868. 899.
But be the test that of necessity, (as I think, in common with
Roskill and Ormrod L.JJ.) or reasonableness, (as Lord Denning
M.R. thought), the exercise involved is that of ascertaining the
presumed intention of the parties. Whichever of these two tests
one applies to the facts of the instant case, in my judgment the
outcome would be the same for, in the words of Roskill L.J.
[1975] 3 W.L.R. 663, 677–678:
“… I find it absolutely impossible to believe that the
CIVIL APPEAL No.179 of 2017 Page 30 of 63
Liverpool City Council, if asked whether it was their
intention as well as that of their tenants of these flats that
any of the implied terms contended for by Mr. Godfrey
should be written into the contract, would have given an
affirmative answer. Their answers would clearly have
been ‘No.’” (Emphasis supplied)
41. In a sense, this was a turning around to what was observed
in The Moorcock (supra).
42. Lord Denning, M.R., in Shell U.K. Ltd. vs. Lostock
7
Garage Ltd. , once again, considered the law as to implied
terms and summarized it:
“This submission makes it necessary once again to consider the
law as to implied terms. I ventured with some trepidation to
suggest that terms implied by law could be brought within one
comprehensive category — in which the courts could imply a
term such as was just and reasonable in the circumstances: see
Greaves & Co. (Contractors) Ltd. v. Baynham Meikle &
Partners [1975] 1 W.L.R. 1095, 1099–1100; Liverpool City
Council v. Irwin [1976] Q.B. 319, 331–332. But, as I feared, the
House of Lords in Liverpool City Council v. Irwin [1976] 2
W.L.R. 562, have rejected it as quite unacceptable. As I read the
speeches, there are two broad categories of implied terms.
(i) The first category
The first category comprehends all those relationships which are
of common occurrence. Such as the relationship of seller and
buyer, owner and hirer, master and servant, landlord and tenant,
carrier by land or by sea, contractor for building works, and so
forth. In all those relationships the courts have imposed
7
(1976) 1 WLR 1187
CIVIL APPEAL No.179 of 2017 Page 31 of 63
obligations on one party or the other, saying they are “implied
terms.” These obligations are not founded on the intention of the
parties, actual or presumed, but on more general considerations:
see Luxor (Eastbourne) Ltd. v. Cooper [1941] A.C. 108, 137 by
Lord Wright; Lister v. Romford Ice and Cold Storage Co. Ltd.
[1957] A.C. 555, 576 by Viscount Simonds, and at p. 594 by
Lord Tucker (both of whom give interesting illustrations); and
Liverpool City Council v. Irwin [1976] 2 W.L.R. 562, 571 by
Lord Cross of Chelsea, and at p. 579 by Lord Edmund-Davies.
In such relationships the problem is not to be solved by asking
what did the parties intend? Or would they have unhesitatingly
agreed to it, if asked? It is to be solved by asking: has the law
already defined the obligation or the extent of it? If so, let it be
followed. If not, look to see what would be reasonable in the
general run of such cases: see by Lord Cross of Chelsea at p.
570H: and then say what the obligation shall be. The House in
Liverpool City Council v. Irwin [1976] 2 W.L.R. 562 went
through that very process. They examined the existing law of
landlord and tenant, in particular that relating to easements, to
see if it contained the solution to the problem: and, having found
that it did not, they imposed an obligation on the landlord to use
reasonable care. In these relationships the parties can exclude or
modify the obligation by express words; but unless they do so,
the obligation is a legal incident of the relationship which is
attached by the law itself and not by reason of any implied term.
Likewise, in the general law of contract, the legal effect of
frustration does not depend on an implied term. It does not
depend on the presumed intention of the parties, nor on what
they would have answered, if asked: but simply on what the
court itself declares to amount to a frustration: see Davis
Contractors Ltd. v. Fareham Urban District Council [1956] A.C.
696, 728 by Lord Radcliffe and The Eugenia [1964] 2 Q.B. 226,
238, 239.
(ii) The second category
CIVIL APPEAL No.179 of 2017 Page 32 of 63
The second category comprehends those cases which are not
within the first category. These are cases — not of common
occurrence — in which from the particular circumstances a term
is to be implied. In these cases the implication is based on an
intention imputed to the parties from their actual circumstances:
see Luxor (Eastbourne) Ltd. v. Cooper [1941] A.C. 108, 137 by
Lord Wright. Such an imputation is only to be made when it is
necessary to imply a term to give efficacy to the contract and
make it a workable agreement in such manner as the parties
would clearly have done if they had applied their mind to the
contingency which has arisen. These are the “officious
bystander” types of case: see Lister v. Romford Ice and Cold
Storage Co. Ltd. [1957] A.C. 555, 594, by Lord Tucker. In such
cases a term is not to be implied on the ground that it would be
reasonable: but only when it is necessary and can be formulated
with a sufficient degree of precision. This was the test applied by
the majority of this court in Liverpool City Council v. Irwin 1
[1976] Q.B. 319. and they were emphatically upheld by the
House on this point: see [1976] 2 W.L. R. 562, 571D–H by Lord
Cross of Chelsea; p. 578G–579A by Lord Edmund-Davies.
There is this point to be noted about Liverpool City Council v.
Irwin. In this court the argument was only about an implication
in the second category. In the House of Lords that argument was
not pursued. It was only the first category.
Into which of the two categories does the present case come? I
am tempted to say that a solus agreement between supplier and
buyer is of such common occurrence nowadays that it could be
put into the first category: so that the law could imply a term
based on general considerations. But I do not think this would be
found acceptable. Nor do I think the case can be brought within
the second category. If the Shell company had been asked at the
beginning: “Will you agree not to discriminate abnormally
against the buyer?” I think they would have declined. it might be
a reasonable term, but it is not a necessary term. Nor can it be
formulated with sufficient precision. On this point I agree with
Kerr J. It should be noticed that in the Esso case Mocatta J. also
CIVIL APPEAL No.179 of 2017 Page 33 of 63
refused to make such an implication: see [1966] 2 Q.B. 514,
536–541; and there was no appeal from his decision. In the
circumstances, I do not think any term can be implied.”
43. A parallel development in Australia arose out of a
judgment of the Lords of the Judicial Committee of the Privy
Council in the appeal preferred from the Full Court of the
Supreme Court of Victoria in B.P. Refinery (Westernport)
Proprietary Limited vs. The President Councillors and
8
Ratepayers of the Shire of Hastings . On the implication of
the terms of contraction five conditions were laid down and a
reference was, once again, made to the The Moorcock (supra),
Reigate vs. Union Manufacturing Co. (Ramsbottom) Ltd.
(supra) and Shirlaw v. Southern Foundries (supra) in the
following terms:
“40. Their Lordships do not think it necessary to review
exhaustively the authorities on the implication of a term in a
contract which the parties have not thought fit to express. In
their view, for a term to be implied, the following conditions
(which may overlap) must be satisfied: (1) it must be reasonable
and equitable; (2) it must be necessary to give business efficacy
to the contract, so that no term will be implied if the contract is
effective without it; (3) it must be so obvious that "it goes
without saying"; (4) it must be capable of clear expression; (5) it
must not contradict any express term of the contract.
8
[1977] UKPC 13
CIVIL APPEAL No.179 of 2017 Page 34 of 63
41. Their Lordships venture to cite only three passages - albeit
they are familiar to every student of this branch of the law. In
The Moorcock (19) Bowen LJ said:
"I believe if one were to take all the cases, and they are
many, of implied warranties or covenants in law, it will be
found bat in El of them the law is raising an implication
from the presumed intention of the parties with the object
of giving to the transaction such efficacy as both parties
must have intended that at all events it should have. In
business transactions such as this, what the law desires to
effect by the implication is to give such business efficacy
to the transaction as must have been intended at all events
by both parties who are business men.. . ."
It is because the implication of a term rests on the presumed
intention of the parties that the primary condition must be
satisfied that the term sought to be implied must be reasonable
and equitable. It is not to be imputed to a party that he is
assenting to an unexpressed term which will operate
unreasonably and inequitably against himself.
In Reigate v. Union Manufacturing Co. (20), Scrutton LJ said:
"A term can only be implied if it is necessary in the
business sense to give efficacy to the contract i.e., if it is
such a term that it can confidently be said that if at the
time the contract was being negotiated some one had said
to the parties, 'What will happen in such a case?', they
would both have replied: 'Of course, so and so will
happen; we did not trouble to say that; it is too clear."'
In Shirlaw v. Southern Foundries (1926) Ltd. (21), MacKinnon
LJ said:
"Prima facie that which in any contract is left to be
implied and need not be expressed is something so
obvious that it goes without saying; so that, if, while the
CIVIL APPEAL No.179 of 2017 Page 35 of 63
parties were making their bargain, an officious bystander
were to suggest some express provision for it in their
agreement, they would testily suppress him with a
common, 'Oh, of course.’"” (Emphasis supplied)
44. The next development, was in Investors Compensation
9
Scheme Ltd. vs. West Bromwich Building Society . Lord
Hoffmann, in his majority opinion, prefaced his explanation of
reasons with some general remarks about the principles which
contractual documents are nowadays construed – common
sense principles by which any serious utterance would be
interpreted in ordinary life. Almost all the old intellectual
baggage of ‘legal’ interpretation was observed to have been
discarded, and the principles summarized as follows:
“(1) Interpretation is the ascertainment of the meaning which the
document would convey to a reasonable person having all the
background knowledge which would reasonably have been
available to the parties in the situation in which they were at the
time of the contract.
(2) The background was famously referred to by Lord
Wilberforce as the “matrix of fact,” but this phrase is, if
anything, an understated description of what the background
may include. Subject to the requirement that it should have been
reasonably available to the parties and to the exception to be
mentioned next, it includes absolutely anything which would
have affected the way in which the language of the document
9
(1998) 1 All ER 98
CIVIL APPEAL No.179 of 2017 Page 36 of 63
would have been understood by a reasonable man.
(3) The law excludes from the admissible background the
previous negotiations of the parties and their declarations of
subjective intent. They are admissible only in an action for
rectification. The law makes this distinction for reasons of
practical policy and, in this respect only, legal interpretation
differs from the way we would interpret utterances in ordinary
life. The boundaries of this exception are in some respects
unclear. But this is not the occasion on which to explore them.
(4) The meaning which a document (or any other utterance)
would convey to a reasonable man is not the same thing as the
meaning of its words. The meaning of words is a matter of
dictionaries and grammars; the meaning of the document is what
the parties using those words against the relevant background
would reasonably have been understood to mean. The
background may not merely enable the reasonable man to
choose between the possible meanings of words which are
ambiguous but even (as occasionally happens in ordinary life) to
conclude that the parties must, for whatever reason, have used
the wrong words or syntax: see Mannai Investments Co. Ltd. v.
Eagle Star Life Assurance Co. Ltd. [1997] A.C. 749.
(5) The “rule” that words should be given their “natural and
ordinary meaning” reflects the common sense proposition that
we do not easily accept that people have made linguistic
mistakes, particularly in formal documents. On the other hand, if
one would nevertheless conclude from the background that
something must have gone wrong with the language, the law
does not require judges to attribute to the parties an intention
which they plainly could not have had. Lord Diplock made this
point more vigorously when he said in Antaios Compania
Naviera S.A. v. Salen Rederierna A.B. [1985] A.C. 191, 201:
“if detailed semantic and syntactical analysis of words in a
commercial contract is going to lead to a conclusion that
flouts business commonsense, it must be made to yield to
CIVIL APPEAL No.179 of 2017 Page 37 of 63
business commonsense.’”
45. Once again, Lord Hoffmann, now sitting on the Privy
Council, in Attorney General of Belize and Ors. vs. Belize
10
Telecom Ltd. and Anr. , dealt with the implied terms of the
contract in the context of the Articles of Association of a
company. It has been observed as under:
“16. Before discussing in greater detail the reasoning of the
Court of Appeal, the Board will make some general observations
about the process of implication. The court has no power to
improve upon the instrument which it is called upon to construe,
whether it be a contract, a statute or articles of association. It
cannot introduce terms to make it fairer or more reasonable. It is
concerned only to discover what the instrument means.
However, that meaning is not necessarily or always what the
authors or parties to the document would have intended. It is the
meaning which the instrument would convey to a reasonable
person having all the background knowledge which would
reasonably be available to the audience to whom the instrument
is addressed: see Investors Compensation Scheme Ltd v West
Bromwich Building Society [1998] 1 WLR 896 , 912–913. It is
this objective meaning which is conventionally called the
intention of the parties, or the intention of Parliament, or the
intention of whatever person or body was or is deemed to have
been the author of the instrument.
17. The question of implication arises when the instrument does
not expressly provide for what is to happen when some event
occurs. The most usual inference in such a case is that nothing is
to happen. If the parties had intended something to happen, the
instrument would have said so. Otherwise, the express
provisions of the instrument are to continue to operate
10
(2009) 1 WLR 1988
CIVIL APPEAL No.179 of 2017 Page 38 of 63
undisturbed. If the event has caused loss to one or other of the
parties, the loss lies where it falls.
18. In some cases, however, the reasonable addressee would
understand the instrument to mean something else. He would
consider that the only meaning consistent with the other
provisions of the instrument, read against the relevant
background, is that something is to happen. The event in
question is to affect the rights of the parties. The instrument may
not have expressly said so, but this is what it must mean. In such
a case, it is said that the court implies a term as to what will
happen if the event in question occurs. But the implication of the
term is not an addition to the instrument. It only spells out what
the instrument means.
19. The proposition that the implication of a term is an exercise
in the construction of the instrument as a whole is not only a
matter of logic (since a court has no power to alter what the
instrument means) but also well supported by authority. In
Trollope & Colls Ltd v North West Metropolitan Regional
Hospital Board [1973] 1 WLR 601 , 609 Lord Pearson, with
whom Lord Guest and Lord Diplock agreed, said:
“the court does not make a contract for the parties. The
court will not even improve the contract which the parties
have made for themselves, however desirable the
improvement might be. The court’s function is to interpret
and apply the contract which the parties have made for
themselves. If the express terms are perfectly clear and
free from ambiguity, there is no choice to be made
between different possible meanings: the clear terms must
be applied even if the court thinks some other terms
would have been more suitable. An unexpressed term can
be implied if and only if the court finds that the parties
must have intended that term to form part of their
contract: it is not enough for the court to find that such a
term would have been adopted by the parties as
reasonable men if it had been suggested to them: it must
CIVIL APPEAL No.179 of 2017 Page 39 of 63
have been a term that went without saying, a term
necessary to give business efficacy to the contract, a term
which, though tacit, formed part of the contract which the
parties made for themselves.”
20. More recently, in Equitable Life Assurance Society v Hyman
[2002] 1 AC 408 , 459, Lord Steyn said: “If a term is to be
implied, it could only be a term implied from the language of
[the instrument] read in its commercial setting.”
21. It follows that in every case in which it is said that some
provision ought to be implied in an instrument, the question for
the court is whether such a provision would spell out in express
words what the instrument, read against the relevant
background, would reasonably be understood to mean. It will be
noticed from Lord Pearson’s speech that this question can be
reformulated in various ways which a court may find helpful in
providing an answer—the implied term must “go without
saying”, it must be “necessary to give business efficacy to the
contract” and so on—but these are not in the Board’s opinion to
be treated as different or additional tests. There is only one
question: is that what the instrument, read as a whole against the
relevant background, would reasonably be understood to mean?
22. There are dangers in treating these alternative formulations
of the question as if they had a life of their own. Take, for
example, the question of whether the implied term is “necessary
to give business efficacy” to the contract. That formulation
serves to underline two important points. The first, conveyed by
the use of the word “business”, is that in considering what the
instrument would have meant to a reasonable person who had
knowledge of the relevant background, one assumes the notional
reader will take into account the practical consequences of
deciding that it means one thing or the other. In the case of an
instrument such as a commercial contract, he will consider
whether a different construction would frustrate the apparent
business purpose of the parties. That was the basis upon which
Equitable Life Assurance Society v Hyman [2002] 1 AC 408
CIVIL APPEAL No.179 of 2017 Page 40 of 63
was decided. The second, conveyed by the use of the word
“necessary”, is that it is not enough for a court to consider that
the implied term expresses what it would have been reasonable
for the parties to agree to. It must be satisfied that it is what the
contract actually means.
23. The danger lies, however, in detaching the phrase “necessary
to give business efficacy” from the basic process of construction
of the instrument. It is frequently the case that a contract may
work perfectly well in the sense that both parties can perform
their express obligations, but the consequences would contradict
what a reasonable person would understand the contract to
mean. Lord Steyn made this point in the Equitable Life case, at p
459, when he said that in that case an implication was necessary
“to give effect to the reasonable expectations of the parties”.
24. The same point had been made many years earlier by Bowen
LJ in his well known formulation in The Moorcock (1889) 14
PD 64, 68:
“In business transactions such as this, what the law desires
to effect by the implication is to give such business
efficacy to the transaction as must have been intended at
all events by both parties who are business men …”
25. Likewise, the requirement that the implied term must “go
without saying” is no more than another way of saying that,
although the instrument does not expressly say so, that is what a
reasonable person would understand it to mean. Any attempt to
make more of this requirement runs the risk of diverting
attention from the objectivity which informs the whole process
of construction into speculation about what the actual parties to
the contract or authors (or supposed authors) of the instrument
would have thought about the proposed implication. The
imaginary conversation with an officious bystander in Shirlaw v
Southern Foundries (1926) Ltd [1939] 2 KB 206 , 227 is
celebrated throughout the common law world. Like the phrase
“necessary to give business efficacy”, it vividly emphasises the
CIVIL APPEAL No.179 of 2017 Page 41 of 63
need for the court to be satisfied that the proposed implication
spells out what the contact would reasonably be understood to
mean. But it carries the danger of barren argument over how the
actual parties would have reacted to the proposed amendment.
That, in the Board’s opinion, is irrelevant. Likewise, it is not
necessary that the need for the implied term should be obvious
in the sense of being immediately apparent, even upon a
superficial consideration of the terms of the contract and the
relevant background. The need for an implied term not
infrequently arises when the draftsman of a complicated
instrument has omitted to make express provision for some
event because he has not fully thought through the contingencies
which might arise, even though it is obvious after a careful
consideration of the express terms and the background that only
one answer would be consistent with the rest of the instrument.
In such circumstances, the fact that the actual parties might have
said to the officious bystander “Could you please explain that
again?” does not matter.
26. In BP Refinery (Westernport) Pty Ltd v Shire of Hastings
(1977) 180 CLR 266 , 282–283 Lord Simon of Glaisdale, giving
the advice of the majority of the Board, said that it was “[not]
necessary to review exhaustively the authorities on the
implication of a term in a contract” but that the following
conditions (“which may overlap”) must be satisfied:
“(1) it must be reasonable and equitable; (2) it must be
necessary to give business efficacy to the contract, so that
no term will be implied if the contract is effective without
it; (3) it must be so obvious that ‘it goes without saying’
(4) it must be capable of clear expression; (5) it must not
contradict any express term of the contract.”
27. The Board considers that this list is best regarded, not as
series of independent tests which must each be surmounted, but
rather as a collection of different ways in which judges have
tried to express the central idea that the proposed implied term
must spell out what the contract actually means, or in which they
CIVIL APPEAL No.179 of 2017 Page 42 of 63
have explained why they did not think that it did so. The Board
has already discussed the significance of “necessary to give
business efficacy” and “goes without saying”. As for the other
formulations, the fact that the proposed implied term would be
inequitable or unreasonable, or contradict what the parties have
expressly said, or is incapable of clear expression, are all good
reasons for saying that a reasonable man would not have
understood that to be what the instrument meant.”
46. There were, once again, parallel developments in India
during this period in various High Courts but the views of this
Court can be found expression in M/s. Dhanrajamal
11
Gobindram vs. M/s. Shamji Kalidas and Co. :
“19. ….Commercial documents are sometimes expressed in
language which does not, on its face, bear a clear meaning. The
effort of Courts is to give a meaning, if possible. This was laid
down by the House of Lords in Hillas & Co. v. Arcos Ltd.
[(1932) All ER 494] , and the observations of Lord Wright
have become classic, and have been quoted with approval both
by the Judicial Committee and the House of Lords ever since.
The latest case of the House of Lords is Adamastos Shipping
Co. Ltd. v. Anglo-Saxon Petroleum Co. Ltd. [(1959) AC 133]
There, the clause was “This bill of lading”, whereas the
document to which it referred was a charter-party. Viscount
Simonds summarised at p. 158 all the rules applicable to
construction of commercial documents, and laid down that
effort should always be made to construe commercial
agreements broadly and one must not be astute to find defects
in them, or reject them as meaningless.”
47. In The Union of India vs. M/s. D.N. Revri & Co. and
11
(1961) 3 SCR 1020
CIVIL APPEAL No.179 of 2017 Page 43 of 63
12
Ors. , P.N. Bhagwati, J. (as he then was), speaking for the
Bench of two Judges said in para 7 as under:
“7. It must be remembered that a contract is a commercial
document between the parties and it must be interpreted in such
a manner as to give efficacy to the contract rather than to
invalidate it. It would not be right while interpreting a contract,
entered into between two lay parties, to apply strict rules of
construction which are ordinarily applicable to a conveyance and
other formal documents. The meaning of such a contract must be
gathered by adopting a common sense approach and it must not
be allowed to be thwarted by a narrow, pedantic and legalistic
interpretation…..”
48. Lastly in Satya Jain (Dead) Through LRs. and Ors. vs.
13
Anis Ahmed Rushdie (Dead) Through LRs. and Ors. ,
Ranjan Gogoi, J., elucidated the well established principles of
the classic test of business efficacy to achieve the result of
consequences intended by the parties acting as prudent
businessmen. It was opined as under:
“33. The principle of business efficacy is normally invoked to
read a term in an agreement or contract so as to achieve the
result or the consequence intended by the parties acting as
prudent businessmen. Business efficacy means the power to
produce intended results. The classic test of business efficacy
was proposed by Bowen, L.J. in Moorcock [(1889) LR 14 PD 64
(CA)] . This test requires that a term can only be implied if it is
necessary to give business efficacy to the contract to avoid such
12
(1976) 4 SCC 147
13
(2013) 8 SCC 131
CIVIL APPEAL No.179 of 2017 Page 44 of 63
a failure of consideration that the parties cannot as reasonable
businessmen have intended. But only the most limited term
should then be implied—the bare minimum to achieve this goal.
If the contract makes business sense without the term, the courts
will not imply the same. The following passage from the opinion
of Bowen, L.J. in Moorcock [(1889) LR 14 PD 64 (CA)] sums
up the position: (PD p. 68)
“… In business transactions such as this, what the law
desires to effect by the implication is to give such business
efficacy to the transaction as must have been intended at
all events by both parties who are businessmen; not to
impose on one side all the perils of the transaction, or to
emancipate one side from all the chances of failure, but to
make each party promise in law as much, at all events, as
it must have been in the contemplation of both parties that
he should be responsible for in respect of those perils or
chances.”
34. Though in an entirely different context, this Court in United
India Insurance Co. Ltd. v. Manubhai Dharmasinhbhai Gajera
[(2008) 10 SCC 404] had considered the circumstances when
reading an unexpressed term in an agreement would be justified
on the basis that such a term was always and obviously intended
by and between the parties thereto. Certain observations in this
regard expressed by courts in some foreign jurisdictions were
noticed by this Court in para 51 of the Report. As the same may
have application to the present case it would be useful to notice
the said observations: (SCC p. 434)
“51. … ‘… “Prima facie that which in any contract is left
to be implied and need not be expressed is something so
obvious that it goes without saying; so that, if, while the
parties were making their bargain, an officious bystander,
were to suggest some express provision for it in their
agreement, they would testily suppress him with a
common ‘Oh, of course!’” Shirlaw v. Southern Foundries
(1926) Ltd. [(1939) 2 KB 206 : (1939) 2 All ER 113 (CA)]
CIVIL APPEAL No.179 of 2017 Page 45 of 63
, KB p. 227.'
*
‘… An expressed term can be implied if and only if the
court finds that the parties must have intended that term to
form part of their contract: it is not enough for the court to
find that such a term would have been adopted by the
parties as reasonable men if it had been suggested to
them: it must have been a term that went without saying, a
term necessary to give business efficacy to the contract, a
term which, although tacit, formed part of the contract
which the parties made for themselves. Trollope and Colls
Ltd. v. North West Metropolitan Regl. Hospital Board
[(1973) 1 WLR 601 : (1973) 2 All ER 260 (HL)] , All ER
p. 268a-b.’”
35. The business efficacy test, therefore, should be applied only
in cases where the term that is sought to be read as implied is
such which could have been clearly intended by the parties at the
time of making of the agreement…..”
Our View:
49. We now proceed to apply the aforesaid principles which
have evolved for interpreting the terms of a commercial
contract in question. Parties indulging in commerce act in a
commercial sense. It is this ground rule which is the basis of
The Moorcock test of giving ‘business efficacy’ to the
transaction, as must have been intended at all events by both
business parties. The development of law saw the ‘five
condition test’ for an implied condition to be read into the
CIVIL APPEAL No.179 of 2017 Page 46 of 63
contract including the ‘business efficacy’ test. It also sought to
incorporate ‘The Officious Bystander Test’ [ Shirlaw vs.
Southern Foundries (supra)]. This test has been set out in
B.P. Refinery (Westernport) Proprietary Limited vs. The
President Councillors and Ratepayers of the Shire of
Hastings (supra) requiring the requisite conditions to be
satisfied: (1) reasonable and equitable; (2) necessary to give
business efficacy to the contract; (3) it goes without saying,
i.e., The Officious Bystander Test; (4) capable of clear
expression; and (5) must not contradict any express term of the
contract. The same penta-principles find reference also in
Investors Compensation Scheme Ltd. vs. West Bromwich
Building Society (supra) and Attorney General of Belize and
Ors. vs. Belize Telecom Ltd. and Anr. (supra). Needless to say
that the application of these principles would not be to
substitute this Court’s own view of the presumed
understanding of commercial terms by the parties if the terms
are explicit in their expression. The explicit terms of a contract
are always the final word with regards to the intention of the
CIVIL APPEAL No.179 of 2017 Page 47 of 63
parties. The multi-clause contract inter se the parties has, thus,
to be understood and interpreted in a manner that any view, on
a particular clause of the contract, should not do violence to
another part of the contract.
50. The pricing of the coal is, if one may say, the crux of the
problem. It is no doubt true, as contended by the first
respondent, that while submitting the financial bid, clause
2.7.1.4(3) of the RFP required the tariff to be quoted in
Format-1 of Annexure 4 to be an ‘all inclusive tariff’ and
provided that no exclusion shall be allowed. This clause has
already been extracted aforesaid. The bidder/appellant was,
thus, required to take into account all costs, including capital
and operational costs, statutory taxes, etc.. The same clause
also provides that the availability of inputs necessary for
generation of power should be ensured by the seller at the
‘Project Site’, which must be reflected in the quoted tariff. The
significant aspect is that the working of the contract is on the
basis of ‘Project Site’. It has to be, however, simultaneously
kept in mind that the present project is in the nature of a Case-2
CIVIL APPEAL No.179 of 2017 Page 48 of 63
project which provides for a fuel specific procurement, having
a pre-identified site.
51. The contract did not provide for a fixed energy charge, or
a periodic revision of that charge, as the formula for energy
charge was designed in such a manner that it would be
influenced by the actual cost of coal. Thus, the basis is the
actual cost incurred with regards to the coal. Of course, a major
controversy has arisen as to whether the cost of coal has to be
determined on the basis of the purchase price from SECL at the
‘mine-end’, when the property is supposed to pass to the
appellant, or whether it is the cost of coal to be used for the
plant as incurred by the appellant at site of the project, or the
‘project-end’.
52. Schedule 7 of the PPA provides for tariff payment and its
computation. The monthly energy charges form part of clause
th
1.2.3 of the 7 Schedule. This clause is extracted as under:
CIVIL APPEAL No.179 of 2017 Page 49 of 63
“ 1.2.3 Monthly Energy Charges
The Monthly Energy Charges for Month “m” shall be
calculated as under:
MEPn = AEOm x MEPn
Where:
AEOm is the Scheduled Energy during the month m (in
kWh)
Monthly Energy Charges
COAL
MEPn = NHR n x F
n
PCV n
where,
NHR n is the Net Heat Rate for the Contract Year in
which month “m” occurs expressed in
kCal/kwh and is equal to the Quoted Net
Heat Rate of the Contract Year in which
month “m” occurs, as provided in Schedule
11.
COAL
F
n is the weighted average actual cost to the
Seller of purchasing, transporting and
unloading the coal most recently supplied to
and at the Project before the beginning of
month “m” (expressed in Rs./MT in case of
domestic coal)
PCV n is the weighted average gross calorific value
of the coal most recently delivered to the
Project before the beginning of month “m”
expressed in kcal/kg.”
(emphasis supplied)
CIVIL APPEAL No.179 of 2017 Page 50 of 63
COAL
53. The variable component of ‘F
n ’ refers to the ‘actual’
cost to the seller/appellant of the three components, i.e., (a)
purchasing; (b) transporting; and (c) unloading the coal. The
first respondent is thus right that there may be different aspects
before the coal is used in the plant which are not required to be
reimbursed by the first respondent. The illustrations given by
the first respondent are of sizing of coal, crushing of coal,
sprinkling and moisturisation of coal for stacking and storage,
etc. being activities required to be undertaken prior to
generation. Thus, there is no hesitation in our concluding that
in view of the specific formula provided, only three aspects
relatable to coal would determine the particular co-efficient.
54. These three expressions are thereafter followed by the
stipulation that the coal has to be recently supplied “to and at
the project.” The question is, what is the meaning of this
expression? The word ‘to’ obviously would have reference to
transporting while the word ‘at’ would have relationship with
unloading since it would be ‘transporting to’ and ‘unloading
CIVIL APPEAL No.179 of 2017 Page 51 of 63
at’. Any other construction will fail to make grammatical
sense. Not only that, all the three, i.e., purchasing, transporting
and unloading, have a reference to “the Project.” Thus, the
COAL
definition of F
n is the weighted average actual cost incurred
by the appellant of purchasing the coal and transporting it to
the project site and thereafter unloading the coal at the project
site. The fact that the property in coal passed on to the
appellant vis-à-vis SECL, on delivery being taken at the
mine-end would not change the definition of coal pricing as is
required for the purposes of calculation of the tariff.
55.
Mr. Mukul Rohatgi, learned Senior Advocate, thus, rightly
took support of the maxim for interpretation, ‘ Reddendo
Singula Singulis ’ This principle is set out as under:
14
“ 387. Reddendo Singula Singulis principle
Where a complex sentence has more than one subject, and more
than one object, it may be the right construction to render each
to each , by reading the provision distributively and applying
each object to its appropriate subject. A similar principle applies
to verbs and their subjects, and to other parts of speech.”
56. In ‘Principles of Statutory Interpretation’ by Justice G.P.
14
Francis Bennion – Statutory Interpretation (Butterworths – 1984,
London); (Part XXII, pg. 842)
CIVIL APPEAL No.179 of 2017 Page 52 of 63
Singh (former Chief Justice, Madhya Pradesh High Court), it
has been expressed as under:
15
“ (e) Reddendo Singula Singulis
The rule may be stated from an Irish case in the following
words Where there are general words of description,
following an enumeration of particular things such general
words are to be construed distributively, reddendo singula
singulis; and if the general words will apply to some things
and not to others, the general words are to be applied to those
things to which they will, and not to those to which they will
16
not apply; that rule is beyond all controversy ". Thus, 'I
devise and 'bequeath' all my real and personal property to A'
will be construed, reddendo singula singulis by applying
'devise' to 'real' property and 'bequeath' to 'personal'
17
property and in the sentence: 'If any one shall draw or load
ant sword or gun' the word 'draw' is applied to 'sword' only
and the word 'load' to gun only, because it is impossible to
18
load a sword or draw a gun. ”
57. The aforesaid also refers to Koteswar Vittal Kamath v. K.
19
Rangappa Balia & Co. , which in turn has referred to the
Black’s Interpretation of Laws to define this expression as:
15
Principles of Statutory Interpretation by Justice G.P. Singh (former
Chief Justice M.P. High Court) Fourth Edition 1988
16
M’Neill v. Crommelin (1858) 9 Ir CLR 61 : 62 Digest, p. 672.
17
OSBORNE: Concise Law Dictionary, p. 269
18 th
WHARTON: Law Lexicon, 14 Edition, p. 850.
19
(1969) 1 SCC 255
CIVIL APPEAL No.179 of 2017 Page 53 of 63
“Where asentences in a statue contains several an tecedents
and several consequences, they are to be read distributively;
that is to say, each phrase or expression is to be referred to its
appropriate object.”
58. We have thus, also endeavoured to read the provision
distributively, by applying each object, to the appropriate
subject. Thus, the relevant preposition has been applied to the
relevant activity.
59. Once we obtain clarity on the aforesaid formula for
calculation of the energy charges, the prior activity of
‘washing’, before receiving the coal at the project site would
be part of the pricing of coal and cost of purchasing the same.
The appellant did seek to obtain clarity on the issue of the
quality of coal to be used, to which the first respondent did
answer that it would have to be ‘washed’ coal. In fact, this was
in conformity with the Notification issued by the MoEF since
the travel distance was more than 1,000 kilometers. The
reference to coal in the formula would, thus, be only a
reference to ‘washed’ coal and not to ‘unwashed’ coal.
60. The appellant has correctly sought to point out that the
CIVIL APPEAL No.179 of 2017 Page 54 of 63
manner in which the first respondent seeks to read the
definition is different from the actual definition by giving the
following illustration:
COAL
“ Actual definition in the PPA : F
n is the weighted average
actual cost to the Seller of purchasing, transporting and
unloading the coal most recently supplied to and at the
Project
COAL
PSPCL’s Interpretation : F
n is the weighted average actual
cost to the Seller of purchasing unwashed coal, transporting
washed and unloading the washed coal most recently
supplied to and at the Project”
61. The fact that the clarification made it clear that the
appellant had to “arrange” the washing of coal, did not imply
that the cost of washing the coal had to be borne by the
appellant, as the energy charge formula alone would have to be
referred to for the purposes of calculation of the coal price.
The operating cost in clause 2.7.1.4(3) of the RFP would refer
to the activities mentioned therein and the operation and
maintenance of the power plant which would not alter the
formula of the energy charges which contains the cost of coal.
The principle of ‘business efficacy’ would also require us to
read the ‘Monthly Energy Charges’ formula in a manner as
CIVIL APPEAL No.179 of 2017 Page 55 of 63
would be normally understood.
62. The plea of the first respondent that the fuel supply
agreement and the fuel transportation agreement are part of the
‘project documents’ which does not include the component of
‘washing’, does not hold much water for the reason that
‘washed’ coal is a necessity for the project as a quality
requirement for the formula envisaging the requisite quality of
coal to be obtained at the project site and, thus, including all
the relevant costs up to that quality. The mere term ‘coal’,
therefore, would have to mean ‘washed’ coal, as no other type
of coal could be used in the matter at hand.
63.
Now turning to the transportation cost, once again, what is
sought to be excluded is taking the coal for ‘washing’ as well
as the last mile to the project, on account of the Railway siding
not being located at the project site for a certain specified
period of time. It is for that period of time that the actual
transportation cost through road is sought to be recovered by
the appellant.
64. We fail to appreciate as to how these costs can be
CIVIL APPEAL No.179 of 2017 Page 56 of 63
excluded, as the transportation costs to the project site have to
be compensated to the appellant. It is not qualified by the
methodology of transfer, i.e., railways or road. It is also a
matter of necessity, since the railway siding had not reached
the project site due to some complications in acquisition of
land. It is really the transportation cost from point to point
which would be involved and the mere mention in the RFP
under project related activity/milestone about Railway siding
and the Railway lines from nearby station to site cannot imply
that the Railways is the only mode of transportation when the
siding has not been made, albeit on account of land acquisition
problems.
65. The plea of the first respondent that despite the absence of
rail siding, if the appellant proceeded to operate the plant, that
was their ‘business decision’, cannot be sustained for the
reason that the project was set up for obtaining electricity for
the first respondent and as a prudent business decision for both,
it would be required to operate the plant at the earliest. The
complication in obtaining land by the State Government,
CIVIL APPEAL No.179 of 2017 Page 57 of 63
cannot imply that the project should be on hold for two years,
causing loss to everyone and lack of availability of electricity.
Such a plea would be in defiance of the very object of the
setting up of the power plant.
66. Now turning to the other aspect of the GCV of the coal. If
the issue is one of SECL billing for higher Calorific Value
while actually supplying a low Calorific Value of coal, that
would be a matter between the appellant and the SECL and the
first respondent cannot be blamed for the same. That does not
take away from the application of the formula for energy
charge which provides for PCV n as the weighted average Gross
Calorific Value delivered to the project. This Calorific Value
of coal would have to be, thus, on the same parameter
determined at the project site.
67. On behalf of the first respondent an endeavour has been
made to make a distinction between ‘at the site’ and ‘to the
COAL
project’ in the definition of F
n and PCV n . However, this is
not of much assistance to the first respondent, in our view, as
delivery ‘to the project’ could only mean ‘at the site of the
project’. It cannot be at the mine site. In fact, this is a
CIVIL APPEAL No.179 of 2017 Page 58 of 63
fundamental issue where the first respondent seems to be
altering the basic concept of the formula by seeking to replace
the wordings in the formula relatable to the project-site to the
mine-site.
68. In view of our discussion we have no hesitation in
concluding that the point at which the Calorific Value of the
coal is to be measured is at the project-site. The plea of the
first respondent that there is no such methodology of
measuring the Calorific Value at the project-site is belied by
the sample reports of different financial years filed by the
appellant along with the synopsis, which itself referred to the
joint sampling and testing of the coal received and is duly
signed by both sides. It is surprising how such a bald denial
was made despite the position existing at the site. These
sample reports are for years 2014, 2015, 2016 and 2017.
69. We are, thus, of the view that the reading of the energy
formula leads to only one conclusion that all costs of coal up to
the point of the project site have to be included and the
Calorific Value of the coal has to be taken as at the project-site.
CIVIL APPEAL No.179 of 2017 Page 59 of 63
70.
We may notice that there are certain other essential costs
sought to be claimed by the appellant such as the transit and
handling losses, third party testing charges, liaising charges.
We have already held that the formula contains only three
elements and thus, the appellant cannot be permitted to plead
that any other element, other than those would also incidentally
form a part of the formula. In fact, such claims would be hit
by RFP clause 2.7.1.4(3) and the energy charges have to be
calculated only on the basis of the formula understood in a
business sense. Thus, these claims are rejected.
71.
Last but not the least is the claim for interest. It is
undisputed that no such claim has been laid so far, at any stage.
The appellant claims to rely upon clause 11.3.4 read with
clause 11.6.8. We have extracted the relevant clause aforesaid.
No doubt there is a provision for a late payment surcharge in
the event of delay in payment of a monthly bill but in the
present case it is not as if there are undisputed bills remaining
unpaid. There were serious disputes regarding the
interpretation of the contractual clauses itself. We do not think
CIVIL APPEAL No.179 of 2017 Page 60 of 63
that the present one is a fit case where the principle of
compensation for deprivation should enure for the benefit of
the appellant as a measure of restitution. More so as it has not
been claimed by them at any stage. It does appear that this
inclusion in the written synopsis does seem to arise as
canvassed by the learned Senior Advocate for the first
respondent on account of the Tribunal not finding favour with
such claim in the remand proceedings by reason of no claim
being laid towards the same. We are, thus, not inclined to
grant this claim.
72. We may, however, in the end, extend a word of caution. It
should certainly not be an endeavour of commercial courts to
look to implied terms of contract. In the current day and age,
making of contracts is a matter of high technical expertise with
legal brains from all sides involved in the process of drafting a
contract. It is even preceded by opportunities of seeking
clarifications and doubts so that the parties know what they are
getting into. Thus, normally a contract should be read as it
reads, as per its express terms. The implied terms is a concept,
CIVIL APPEAL No.179 of 2017 Page 61 of 63
which is necessitated only when the Penta-test referred to
aforesaid comes into play. There has to be a strict necessity for
it. In the present case, we have really only read the contract in
the manner it reads. We have not really read into it any
‘implied term’ but from the collection of clauses, come to a
conclusion as to what the contract says. The formula for
energy charges, to our mind, was quite clear. We have only
expounded it in accordance to its natural grammatical contour,
keeping in mind the nature of the contract.
Conclusion:
73. We, thus, partly allow the appeal to the extent that the
appellant is held entitled to the washing cost of coal, the
transportation from the mine site via washing of coal to the
project site inclusive of cost of road transportation for the
period where it was necessary. The Calorific Value of the coal
would have to be taken at the project site. All other claims in
appeal stand rejected. The amount payable to the appellant as
the consequences thereof be remitted within a period of three
(3) months from the date of this order, failing which it would
carry interest @ 12 per cent per annum (simple interest). No
CIVIL APPEAL No.179 of 2017 Page 62 of 63
costs.
..….….…………………….J.
(Rohinton Fali Nariman)
...……………………………J.
(Sanjay Kishan Kaul)
New Delhi.
October 05, 2017.
CIVIL APPEAL No.179 of 2017 Page 63 of 63