Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
CASE NO.:
Appeal (civil) 1687 of 1998
PETITIONER:
SIDDAPPA VASAPPA KURI AND ANR.
RESPONDENT:
SPECIAL LAND ACQUISITION OFFICER AND ANR.
DATE OF JUDGMENT: 16/10/2001
BENCH:
S.P. BHARUCHA & Y.K. SABHARWAL & BRIJESH KUMAR
JUDGMENT:
JUDGMENT
2001 Supp(4) SCR 236
The Judgment of the Court was delivered by
BHARUCHA, J. This appeal has been referred to a bench of three Judges by
reason of the contrary views taken by two banches of two learned Judges in
Special Tahsilar (LA), P. W.D. Schemes, Vijayawada, v. M.A. Jabbar, [1995]
2 SCC 142 on the one hand and in Asstt. Commr., Gadag Sub-Division, Gadag
\. Mathapathi Basavannewwa, [1995] 6 SCC 355 on the other. (The referral
order also makes a reference to State of H.P. v. Dharam Das, [1995] 5 SCC
683, but no reasoning can be discerned therein.)
We are required to consider the provisions of Section 23 (1A) of the Land
Acquisition Act, 1894 in the context of the following facts : Possession of
land bearing Survey No. 311/3, admeasuring 2 acres and 16 guntas, situated
at Village Hirenandi, Gokak Taluk, Belgaum District, Karnataka was taken by
the respondents from the appellants, who were the owners thereof, on 1st
June, 1977 for the purposes of the construction of an irrigation channel.
On 8th March, 1991, a notification was issued under Section 4(1) of the Act
in relation to the said land. It was followed by a notification under
Section 6. The provisions of Section 17 were thereafter applied. On 6th
February, 1993, an award was made and compensation was awarded to the
appellants at the rate of Rs. 10,000 per acre, on a reference made by the
appellants, the District Judge enhanced the compensation to Rs. 50,000 per
acre. The Land Acquisition officer and the State preferred appeals before
the High Court. Therein, com-pensation was reduced to Rs. 41,400 per acre.
The decree so passed was put in execution. Before the executing court the
question of additional compensa-tion under Section 23(1 A) arose. The
executing court granted to the appellants additional compensation under
Section 23(1A) from the date on which posses-sion of the land was taken,
namely, 1st June, 1977 to the date on which the Section 4 notification was
issued, namely, 8th March, 1991. The High Court, before whom a revision
petition was presented by the LAO, took the view that the appellants were
entitled to the additional compensation from the date of the Section 4
notification, namely, 8th March, 1991, to the date of the award, namely,
6th February, 1992. Against this order of the High Court this appeal has
been filed.
Section 23(1A) reads thus :
"23(1-A) In addition to the market-value of the land, as above provided,
the Court shall in every case award an amount calculated at the rate of
twelve per centum per annum on such market-value of the period commencing
on the from the date of the publication of the notification under Section
4, sub-section (1), in respect of such land to the date of the award of the
Collector or the date of taking possession of the land, whichever is
earlier.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
Explanation- In computing the period referred to in this sub-section, any
period or periods during which the proceedings for the acquisition of the
land were held up on account of any stay or injunc-tion by the order of any
court shall be excluded."
It is the contention of learned counsel for the appellants that the appel-
lants are entitled to compensation for the period 1st June, 1977 to 8th
March, 1991, i.e., from the date on which possession of the said land was
taken till the date of publication of the section 4(1) notification. He
finds sustenance for this contention in the decision of this Court in
Mathapathi Basavannewwa ’s case [1995] 6 SCC 355 where a similar contention
was upheld. The provisions of Section 23(1A) were analysed but, said the
Court, "strict construction leads to unjust result, hardship to the owner
and defeats legislative object." In its view, therefore, the expression
"whichever is earlier" in Section 23(1A) had to be construed in that
backdrop and the claimant was entitled to the additional amount from the
date of taking possession. Since advance possession was taken before the
publication of the notification under Section 4(1), "the claimants, by
necessary implication, are entitled to the payment of additional amount by
way of compensation from the date of taking over the possession for loss of
enjoyment of the land."
This Court in Special Tahsildar (LA), P. W.D. Schemes, Vijayawada v. M.A.
Jabbar, [1995] 2 SCC 142, quoted Section 23(1A) and said "In other words,
the owner of the land who has been deprived of the enjoyment of the land by
having been parted with possession, the Act intended that the owner be
compensated by awarding an additional amount calculated at the rate of 12
per centum per annum on the enhanced market value for the period between
the date of notification and the date of award or date of taking possession
of the land, whichever is earlier. Admittedly, possession having already
been taken on 15-2-1965, before publication of the notification under
Section 4(1) on 6-3-1980, the award of additional amount for the period
from 6-3-1980 to 30-9-1983, i.e., the date of making the award under
Section 11 is perfectly correct."
It is, as we see it, clear from Section 23(1A) that the starting point for
the purposes of calculating the amount to be awarded thereunder, at the
rate of 12 per centum per annum on the market value, is the date of
publication of the Section 4 notification. The terminal point for the
purpose is either the date of the award or the date of taking possession,
whichever is earlier. In the present case, possession of the land having
been taken prior to the publication of the Section 4 notification, that
terminal is not available. The only available terminal is the date of the
award. The High Court, therefore, was in no error in holding that the
appellants were entitled to the additional compensation under Section
23(1A) for the period 8th March, 1991 to 6th February, 1993.
Section 23(1A) admits of no meaning other than the meaning that we have
placed upon it. There is no room here for any construction other than that
given above. It is only where a provision is ambiguous that a construction
that leads to a result that is more just can be adopted. Having regard to
its clear terms, Section 23(1A) must receive the only construction it can
bear. We are of the view, therefore, that the law has been correctly laid
down in the decision in Special Tahsildar (LA), P.W.D. Schemes v. MA.
Jabbar, [1995] 2 SCC 142 and that it has not been correctly laid down in
Asstt. Commr., Godag Sub-Division v. Mathapathi Basavannewwa, [1995] 6 SCC
355 and, for that matter in State of H.P. v. Dharam Das, [1995] 5 SCC 683.
The appeal is dismissed. No order as to costs.