Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
GANNON DUNKERLEY & CO. LTD.
Vs.
RESPONDENT:
UNION OF INDIA
DATE OF JUDGMENT:
28/10/1969
BENCH:
SHAH, J.C.
BENCH:
SHAH, J.C.
HEGDE, K.S.
CITATION:
1970 AIR 1433 1970 SCR (3) 47
1969 SCC (3) 667
CITATOR INFO :
R 1992 SC 111 (4)
ACT:
Limitation Act, 1908-Suit for payment at an additional rate
over contract rate in view of altered circumstances and
complex nature of work--Claim is not one for price of work
done nor for compensation or breach of contract--Therefore
Art. 56 and Art. 115 of First Schedule not applicable--Suit
governed by Art. 120--Commencement of period of imitation
under Article.
HEADNOTE:
The appellant-company filed a suit against the Union of
India demanding payment at an enhanced rate over the basic
rate stipulated in a construction contract with the Union of
India. The claim related to revision of rates due to the
complex nature and increase in the quantity of work and in
respect of work not covered by the, contract. The addi-
tional work was done at the request of the Engineer-in-
charge who under the terms of the contract was competent to
give instructions for work not covered by the terms of the
contract and fix the rate at which remuneration was to be
paid in respect of such work. The Union of India contended
that the claim was barred, by the law of limitation. The
trial court decreed the suit for the amount certified by the
Superintending Engineer. On appeal the High Court held that
the claim was governed either by Art. 56 or by Art. 115 of
the First Schedule, to the Limitation Act, 1908, and a suit,
more than three years of the date on which the work was done
and in any event of the, date on which the claim was
rejected, was barred. Allowing the appeal to this Court and
restoring the decree for the trial court,
HELD : (i) Article 56 of the First Schedule to the Indian
Limitation Act, 1908, prescribes a period of three years for
a suit for the price of the work done by the plaintiff for
the defendant at his request, where no time has been fixed
for payment, and the, period of limitation commences to run
from the date when the work is done. A suit is governed by
Art. 56 if it arises out of a contract to pay the price of
work done at the request of the defendant., The claim in the
present case is for payment at an additional rate over the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
stipulated ’rate in view of change in circumstances and not
for the, price of work done by the appellant, even though
the additional work was done :at the request of the
Engineer-incharge. [51 F]
(ii) Article 115- of the First Schedule to the
Limitation Act is a residuary article dealing with the claim
for compensation for the breach of any contract,
express orimplied, not in writing registered and, not
specially provided for in the first schedule. The period of
limitation in such cases is three years and it commences to
ran when the contract is broken, or where there are
successive breaches when the breach in respect of which the
suit is instituted occurs or where the breach is continuing
when it ceases. The suit filed by the appellant company is
not a suit for compensation for breach of’ contract express
or implied; it is: a suit for enhanced rate because of
change of circumstances, and in respect of work not covered
by the contract. The additional work directed by the
Engineer-in-charge when carried out May be deemed to be done
under the
48
terms of the contract; but the claim for enhanced rates does
not aris out of the contract : it is in any case not a claim
for compensation for beach of contract. [51 H]
(iii)The claim is, therefore, not covered by any specific
article under the First Schedule and must fall within the
terms of Art. 120. Under this Article the period of six
years commences to run when the right to sue accrues. There
is no right to sue until there is an accrual of the right
asserted in the suit and its infringement or at least a
clear and unequivocal threat to infringe the right by the
defendant against whom the suit is instituted. [52 C]
Bolo v. Kokao and Others, L.R. 87 I.A. 325, referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeals Nos. 258, and
2585 of 1966.
Appeals from the judgment and decrees dated January 19 1965
of the Patna High Court in First Appeals Nos. 190 and 21 of
1960.
H.R. Gokhale, G. L Sanghi, J. B. Dadachanji and Ravinde,
Narain, for the appellant (in both the appeals).
Jagdish Swarup, Solicitor-General, V. A. Seyid Muhammad, B.
D. Sharma and S. P. Nayar, for the respondent (in both the
appeals).
The Judgment of the Court was delivered by
Shah, J. The Government of India invited tenders for "rein
forced concrete work relating to the foundation and super
structure of the Fertilizer Factory building at Sindri" in
the State of Bihar. The tender submitted by the appellant
Company was accepted on November 22, 1947 and a formal
contract in that behalf was executed on November 26, 1948.
By cl. 12 of the contract, insofar as it is relevant, it was
provided :
"The Engineer-in-charge shall have power to
make any alterations in, omissions from,
additions to, or substitutions for, the
original specifications, drawings, designs and
instructions and the contractor shall be
bound to- carry out the work in accordance
with any instructions which may be given to
him and any altered, additional or substituted
work which the contractor may be directed to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
do in the manner above specified as part of
the work shall be carried out: by the
contractor on the same conditions in all
respects on which he agreed to do the main
work, and at the same rates as are specified
in that tender for the main work And if
the altered, additional or substituted work
includes any class of work, for which no rate
is specified in this contract then such class
of work shall
49
be carried out at the rates entered in the
current schedule of rates of the Hazaribagh
P.W.D. district which was in force at the time
of the acceptance of the contract minus/plus
the percentage which the total tendered amount
bears to the estimated cost of the entire work
put to tender, and if the altered, additional
or substituted work is not entered in the said
schedule of rates, then the contractor shall
within seven days of the date of his receipt
of the order to carry out the work inform the
Engineer-in-charge of the rate which it is his
intention to charge for such class of work,
and if the Engineer-incharge does not agree to
this rate he shall, by notice in writing, be
at liberty to cancel his order to carry out
such class of work provided that if the
contractor shall commence work or incur any
expenditure in regard thereto before the rates
shall have been determined then .... he shall
only be entitled to be paid in respect of the
work carried out or expenditure incurred
according to such rates as shall be fixed by
the Engineer-in-charge. In the event of a
dispute, the decision of the Superintending
Engineer of the Circle shall be final."
Clause 25 of the agreement provided, insofar
as it is relevant
"Except where otherwise provided in the
contract all questions and disputes relating
to the meaning of the specifications, designs,
drawings, and instructions, hereinbefore
mentioned and as to the qualify of workman-
ship, or materials used on the work, or as to
any other question, claim, right, matter or
thing whatsoever, in any way arising out of,
or relating to the contract, designs,
drawings, specifications, estimates,
instructions, orders or these conditions, or
otherwise concerning the works, or the
execution, or failure to execute the same,
whether arising during the progress of the
work or after the completion or abandonment
thereof shall be referred to a Superintending
Engineer to be nominated by the Chief Engineer
for arbitration in the manner provided by law
relating to arbitration
The Sindri Factory Buildings were to be constructed under
the, , advice and guidance of M/s. Chemic Construcetion,
Corporation of New York. That Firm made delay in supplying
the drawings and specifications which involved work of a
complicated nature not included in the original contract.
Time for completion of the work was on that account extended
till February 26, 1950.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
On September 20, 1950 the appellant Company made a demand
for payment at an enhanced rate of 421 % over the basic
50
rates stipulated under the original contract. This claim
was made on -five grounds :
1 . That there was a "substantial deviation"
in the nature of work of which the detailed
work drawings were supplied to the appellant
Company after the date of the contract. The
work involved was of a complex nature
requiring highly skilled labour, and that
additional labour and materials not covered by
the contract rates were required;
2. That there was "great increase in the
price of materials and labour on account of
undue prolongation of the period of work;"
3. That there was increase in the cost of
transportation on account of rise in the price
of petrol and increase in railway freight;
4. That the Government of India entered
into other contracts incidental to the
construction of the Sindri Factory at
substantially higher rates which directly
affected the cost of labour and materials of
the appellant Company who had to compete with
the other contractors;
5. That additional work ordered to be done
involved in many instances quantity of -work
several times the work set out in the
contract.
By his letter dated September 13, 1950, the Additional Chief
Engineer rejected the claim. In September 1954 the disputes
relating to the claim for rise in cost of material and
labour due to delay in supplying detailed work drawings, the
claim arising from rise in price of petrol and for increase
in the cost of material and labour due to other contractors
working on the site, were referred to arbitration, but not
the claims for revision of rates due to complex nature of
the work and increase in the quantity of work, The
arbitrator rejected the claims of the Company in respect -of
the matters which were referred.
Thereafter the appellant Company filed a suit on August 9,
1956, against the Union of India, for a decree for Rs.
3,62,674/9/6 being the amount claimed at the rate of 421%
above the contract rate, in the alternative, a decree for
Rs. 2,44,000/- being the amount claimed at the rate of 28.1%
above the contract rate as recommended by the Executive
Engineer, and in the -further ’alternative, a decree for Rs.
1,36,222/-at the rate of 18 17% above the contract rate as
certified by the Superintending Engineer. The Union of
India contended, inter alia, that the claim was barred by
the law of limitation.
51
The Trial Court held that the claim was not barred by the
law of limitation and decreed the claim for Rs. 1,36,222/-
as certified by the Superintending Engineer. Aginst the
decree passed by the Trial Court the appellant Company as
well as the Union of India appealed to the High Court.
Before the High Court, in support of the appeal only the
plea of limitation was pressed on behalf of the Union of
India. In the view of the High Court the claim was governed
either by Art. 56 or by Art. 115 of the First Schedule to
the Limitation Act, 1908, and the suit not having been filed
within three years of the date on which the work was done
and in any event of the date on, which the claim was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
rejected was barred. The appellant Company has appealed to
this Court with certificate.
The appellant Company had undertaken under the terms of the
contract to do specific construction work at "basic rates".
The Engineer-in-charge was by the terms of cl. 12 of the
agreement competent to give instructions for work not
covered by the terms of the contract, and it was provided
that remuneration shall be paid at the rate fixed by the
Engineer-in-charge for such additional work, and in case of
dispute the decision of the Superintending Engineer shall be
final. It is common ground that the claim made by the
appellant Company was not covered by the arbitration
agreement, and on that account it was not referred to the
arbitrator. The claim in suit related to the revision of
rates due to the complex nature of the work and due to
increase in the quantity of work and also grant of contracts
to other competing parties at substantially higher rates and
other related matters.
Article 56 of the First Schedule to the Indian Limitation
Act. 1908, prescribes a period of three years for a suit for
the price of work done by the plaintiff for the defendant at
his request, where no time has been fixed for payment, and
the period of limitation commences to run from the date when
the work is done. A suit is governed by Art. 56 if it
arises out of a contract to pay the price of work done at
the request of the defendant. The claim in ,the present
case is for payment at an additional rate over the
stipulated rate in view of change in circumstances, and not
for price of work done by the appellant Company. It is true
that additional work was done at the request of the
Engineer-in-charge, but the claim in suit was not for the
price of work done but. for enhanced rates in view of
altered circumstances.
Article 115 of the First Schedule to the Limitation Act is a
residuary article dealing with the claim for compensation
for the breach of any contract, express or implied, not in
writing registered and not specially provided for, in the
First Schedule. The period of limitation in such cases is
three years and it commences
52
to run when the contract is broken, or where there are
successive breaches when the breach in respect of which the
suit is instituted occurs, or where the breach is continuing
when it ceases. The suit filed by the appellant Company is
not a suit for compensation for breach of contract express
or implied : it is a suit for enhanced rate because of
change of circumstances, and in respect of work not covered
by the contract. The additional work directed by the
Engineer-in-charge when carried out may be deemed to be done
under the terms of the contract : but the claim for enhanced
rates does not arise out of the contract : it is in any case
not a claim for compensation for breach of contract.
The claim is therefore not covered by any specific article
under the First Schedule, and must fall within the terms of
Art. 120. The Solicitor-General appearing on behalf of the
Union of India contended that even if the claim falls within
the terms of Art. 120 of the Limitation Act, it was barred,
for, the appellant Company had in the suit made a claim for
work done more than six years before the institution of the
suit. Counsel submitted that under Art. 120 the period of
limitation commences to run from the date on which the
defendant obtains the benefit of the work done by the
plaintiff. But under Art. 120 of the Limitation Act the
period of six years for suits for which no period of
limitation is provided elsewhere in the Schedule commences
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
to run when the right to sue accrues. In our judgment, there
is no right to sue until there is an accrual of the right
asserted in the suit, and its infringement, or at least
clear and unequivocal threat to infringe that right by the
defendant against whom the suit is instituted : Bolo v.
Kokan and, Others(1).
The appeals are allowed and the decree passed by the Trial
Court is restored with costs in the High Court and in this
Court. One hearing fee. The appellant will be entitled to
intereston the amount decreed at the rate of 6% per annum
from the date of the suit till payment.
R.K.P.S.
Appeals allowed.
(1) L.R. 57 I.A. 325 at p. 331,
53