Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Arbitration Petition 17 of 2006
PETITIONER:
DHV BV
RESPONDENT:
TAHAL CONSULTING ENGINEERS LTD. & ORS.
DATE OF JUDGMENT: 12/09/2007
BENCH:
D.K. JAIN
JUDGMENT:
JUDGMENT
O R D E R
D.K. JAIN, J.:
1. This is a petition under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (for short \021the Act\022)
for the appointment of an Arbitrator for adjudication of
the disputes which are stated to have arisen between the
parties.
2. The petitioner M/s DHV Consultants BV (for short
\021DHV\022) is a foreign company registered in Netherlands,
providing consultancy and engineering group services in
aviation; spatial planning in environment, transportation
and water with expertise in water management and water
planning. Respondent No.1 - M/s Tahal Consulting
Engineers Limited (hereinafter referred to as \021Tahal\022) is
also a consultant foreign company based in Israel and
respondent No.2 is the Water Resources Organisation,
PWD, Government of Tamil Nadu (hereinafter referred to
as \021TNPWD\022).
3. The facts, relevant for the disposal of this petition,
are as follows:
On 1st December, 1997, an agreement (hereinafter
referred to as the \021main contract\022) was signed between
Tahal and TNPWD, with DHV and two other concerns,
namely, Lahmeyer International of Germany and
Consulting Engineering Services (India) Ltd., as sub-
consultants, for providing management consultancy and
technical assistance services for the Tamil Nadu Water
Resources Consolidation Project. Subsequently, in
March, 1998, a further sub-consultancy agreement
(hereinafter referred to as the \021sub-contract\022) was signed
between Tahal and DHV for providing services in respect
of the main contract, scope whereof was defined in the
conditions of both the said agreements.
4. As per clause 1.10 of the special conditions of the
main contract, TNPWD had agreed to bear the Income tax
liabilities on payments to be made by it to the consultant,
sub-consultants and their personnel. DHV was to receive
all the payments through Tahal, being the principal
consultant. The contract was duly performed and DHV
received all payments in respect of the invoices raised by
them for the services rendered. The last payment was
received some time in January, 2003 and the matter
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
rested there.
5. Some time in February, 2004, DHV received notices
from the Income Tax Department under Section 148 of
the Income Tax Act in respect of the assessment years
1997-98 to 2001-02, alleging non-payment of Income tax
on the remittances made by TNPWD in respect of the said
contract. They were required to submit their returns of
income for the said assessment years. Seemingly, DHV
objected to the said notices but later on submitted the
requisite returns of income, including therein the receipts
from TNPWD. According to DHV, on receipt of the said
notices they learnt that the respondents had defaulted in
making payment of applicable taxes on the payments
made by TNPWD to Tahal, which resulted in the creation
of additional Income tax demand of Rs.30,40,149/-
which they were forced to pay to avoid penal
consequences.
6. Having paid the said additional demand on 15th
March, 2005, DHV issued legal notices to Tahal and
TNPWD, asking them to settle the dispute amicably in
terms of clause 8.1 of the General Conditions of the main
contract, dated 1st December, 1997. However, both the
respondents denied their liability to reimburse the said
amount to DHV. On refusal of the respondents to settle
the controversy, on 21st April, 2005, DHV issued yet
another notice to the respondents demanding reference of
the disputes to sole arbitration in terms of clause 8.2 of
the main contract. Both the respondents refused to refer
the disputes to arbitration, necessitating the filing of the
present petition for the appointment of an Arbitrator.
7. Both Tahal and TNPWD have filed counter affidavits
resisting the petition. Tahal\022s objection is that : (i) the
main contract under which DHV had demanded
arbitration had expired almost four-five years prior to the
filing of the application and, therefore, there was no
existing arbitration agreement between the parties; (ii)
not being a technical matter, the alleged dispute did not
fall within the ambit of clause 8 of the General
Conditions of the Agreement (main contract) and (iii) at
no point of time Tahal was under any contractual
obligation relating to payment of taxes, such obligation
being solely and strictly that of TNPWD. TNPWD opposes
the petition mainly on the ground that: (i) DHV being a
sub-consultant has no locus standi to invoke the
arbitration agreement qua them as no payment was
received by DHV directly from TNPWD; (ii) the claim of
DHV is barred by limitation inasmuch as the main
contract was over on 31st March, 2002 and (iii) there was
no cause of action to file the petition because whatever
Income tax was to be deducted on payments to Tahal -
the principal consultant, was duly deposited with the
State Bank of India and requisite details were filed with
the Income tax department.
8. I have heard learned counsel for the parties. As
noted above, the objection of the respondents to the
appointment of Arbitrator is mainly two-fold viz. (i) after
the completion of the main contract in March/April, 2002
and on final payment on 30th January, 2003, the
contract came to an end and, therefore, there was no
valid arbitration agreement in existence and (ii) the claim
of the DHV is stale and barred by limitation.
9. In support of the proposition that the entire tax
obligation under the contract has been duly discharged,
learned counsel for the TNPWD invited my attention to
some correspondence with the Income tax authorities,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
wherein the rate at which Income tax was to be deducted
on payment under the contract has been indicated.
Learned counsel for the respondents further submitted
that in view of the decision of this Court in SBP & Co.
Vs. Patel Engineering Ltd. & Anr. , the issues raised
have to be adjudicated by me. Learned counsel for the
DHV, on the other hand, contended that the controversy
regarding the tax liability in terms of clause 1.10 cannot
be said to be stale because it arose only when DHV
received notice from the Income tax department in
February, 2004, requiring them to pay Income tax on the
amounts received from TNPWD. It is also submitted that
prior to the receipt of the said notices, DHV had no cause
to complain, having received full payments against the
invoices raised. It is, thus, pleaded that the cause of
action to ask for settlement of their claim arose only in
the month of February, 2004. Further, the stand of
learned counsel for the DHV is that issue of limitation is
not to be finally decided by me as the same is to be
conclusively decided by the Arbitrator under Section 16
of the Act.
10. Thus, the question for consideration before me is :
(i) whether after the completion of the contract in
March/April 2002, there is still an enforceable arbitration
agreement between the parties and (ii) whether the claim
made by DHV is stale and barred by limitation?
11. The controversy in regard to the nature of function
to be performed by the Chief Justice or his designate
under Section 11 of the Act has been set at rest by a
seven-Judge Bench decision of this Court in SBP\022s case
(supra). It has been held, per majority, that the function
performed by the CJ or his nominee under the said
Section is a judicial function. Defining as to what the CJ
or his designate is required to determine while dealing
with an application under Section 11 of the Act, P.K.
Balasubramanyan, J, speaking for the majority said:
\02339. It is necessary to define what exactly
the Chief Justice, approached with an
application under Section 11 of the Act,
is to decide at that stage. Obviously, he
has to decide his own jurisdiction in the
sense, whether the party making the
motion has approached the right High
Court. He has to decide whether there is
an arbitration agreement, as defined in
the Act and whether the person who has
made the request before him, is a party to
such an agreement. It is necessary to
indicate that he can also decide the
question whether the claim was a dead
one; or a long barred claim that was
sought to be resurrected and whether the
parties have concluded the transaction by
recording satisfaction of their mutual
rights and obligations or by receiving the
final payment without objection. It may
not be possible at that stage, to decide
whether a live claim made, is one which
comes within the purview of the
arbitration clause. It will be appropriate
to leave that question to be decided by
the arbitral tribunal on taking evidence,
along with the merits of the claims
involved in the arbitration. The Chief
Justice has to decide whether the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
applicant has satisfied the conditions for
appointing an arbitrator under Section
11(6) of the Act. For the purpose of taking
a decision on these aspects, the Chief
Justice can either proceed on the basis of
affidavits and the documents produced or
take such evidence or get such evidence
recorded, as may be necessary. We think
that adoption of this procedure in the
context of the Act would best serve the
purpose sought to be achieved by the Act
of expediting the process of arbitration,
without too many approaches to the
court at various stages of the proceedings
before the Arbitral Tribunal.\024
12. It is clear from the above extracted paragraph that
in order to set into motion the arbitral procedure, the CJ
or his designate has to decide the issues, if raised,
regarding territorial jurisdiction and existence of an
arbitration agreement between the parties. In addition
thereto, he can also decide the question whether the
claim was a dead one in the sense that the parties have
already concluded the transaction by recording
satisfaction of their mutual rights and obligations or have
recorded satisfaction regarding their financial claims.
Nevertheless, the Court made it clear that at that stage it
may not be possible to decide whether a live claim made,
is one which comes within the purview of the arbitration
clause and this question should be left to be decided by
the arbitral tribunal on taking evidence. It is, therefore,
plain that purely for the purpose of deciding whether the
arbitral procedure is to be set into motion or not, the CJ
or his designate has to examine and record his
satisfaction that an arbitration agreement exists between
the parties and that in respect of the agreement a live
issue, to be decided between the parties, still exists. On
being so satisfied, he may allow the application and
appoint an Arbitral Tribunal or a Sole Arbitrator, as the
case may be. However, if he finds and is convinced that
the claim is a dead one or is patently barred by time, he
may hold so and decline the request for appointment of
an Arbitrator.
13. Applying these principles on facts in hand, I am of
the opinion that the petition deserves to be allowed. In
this context, it would be appropriate to refer to clause
1.10 of the special conditions of the contract forming part
of the main contract, to which all the parties herein are
signatories. Insofar as it is relevant for our purpose, it
reads as under:
\0231.10 ... xxx\005\005xxx.....xxx
For Foreign Consultants/Personnel
The Client warrants that the client shall
pay on behalf of the Consultants and the
Personnel any taxes, duties, fees, levies
and other impositions imposed, under the
Applicable Law, on the consultants and
the Personnel in respect of:
(a) any payments whatsoever made to
the Consultants, Sub-Consultants
and the Personnel of either of them
(other than Indian Nationals or
Foreign Nationals now permanently
residing in India), in connection with
the carrying out of the Services;
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
(b) any equipment, materials and
supplies brought into India by the
Consultants or Sub-consultants for
the purpose of carrying out the
Services and which after having
been bought into such territories
will be subsequently withdrawn
therefrom by them;
(c) any equipment imported for the
purpose of carrying out the Services
and paid for out of funds provided
by the client and which is treated as
property of the client.
(d) Any property brought into India by
the Consultants, any sub-
consultants, the Personnel of either
of them (other than Indian nationals
or permanent residents of India), or
the eligible dependants of such
Personnel for their personal use and
which will subsequently be
withdrawn therefrom by them upon
their respective departure from
India, provided that:
(1) the consultants, sub-consultants
and personnel and their eligible
dependants, shall follow the usual
customs procedures of the
Government in importing property
into India; and
(2) If the consultants, sub-consultants
or personnel, or their eligible
dependants, do not withdraw but
dispose of any property in India
country upon which customs duties
and taxes have been exempted, the
consultants, sub-consultants or
personnel, as the case may be,
(i) shall bear all such customs duties
and taxes in conformity with the
regulations of the Government.
(ii) Shall reimburse them to the client if
they were paid by the client at the
time the property in question was
brought into the Government\022s
country.\024
14. Under the said clause, TNPWD, as a client had
taken upon itself the obligation to pay on behalf of the
consultants, sub-consultants and the personnel any
taxes, dues, fees, etc. imposed under the applicable law.
At the same time, it is significant to note that as per
clause (d) thereof, not only there is an obligation to pay
taxes etc. in certain situations, reimbursement of some of
the amounts by the consultants to the client, which the
client was compelled to pay, is also postulated.
Obviously, such a situation may arise and this clause
would be enforceable even after the expiry of the contract
on completion of the services and on the payments
having been made. Therefore, it cannot be laid as an
abstract proposition that whenever the contracted work
is completed, all the rights and obligations of the parties
under the contract, ipso facto, come to an end and the
arbitration agreement also perishes with the contract.
Each case is required to be considered on its own facts.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
In the instant case, though it is true that all the
payments were to be made by TNPWD to the consultants,
namely, Tahal, but the obligation to pay taxes was also in
respect of the payments which were to be received by the
sub-consultants, namely, DHV in terms of sub-clause (a).
Similarly, DHV as well as Tahal was under an obligation
to reimburse to TNPWD the amount, if any, paid by them
in terms of the aforenoted clause. Thus, it was the
performance of the contract that had come to an end, but
the contract is still in existence insofar as the dispute
arising under clause 1.10 thereof is concerned. I have,
therefore, no hesitation in rejecting the plea of learned
counsel for the TNPWD that DHV had no direct contract
with them insofar as the payments of taxes were
concerned, and, therefore, the dispute raised by them
could not fall within the ambit of arbitration agreement
between TNPWD \026 the client and Tahal \026 the consultant
or that on completion of the contract, the arbitration
clause in the main contract got extinct. In my opinion,
therefore, an enforceable arbitration agreement exists
between the parties.
15. Clause 8.2 of the main contract provides for the
right to arbitration and reads as follows:
\0238.2 Right to Arbitration
Any dispute between the parties as to
matters arising pursuant to this contract
which cannot be settled amicably within
thirty (30) days after receipt by one Party
of the other Party\022s request for such
amicable settlement, may be submitted
by either Party for arbitration in
accordance with the following provisions:
xxx\005xxx\005xxx\024
16. The arbitration agreement is in clear terms and
brings within its ambit any dispute between the parties
as to matters arising pursuant to the main contract
which cannot be settled amicably. Admittedly, the
liability to pay the taxes flows from the contract and not
otherwise. Having found that it was obligatory upon
TNPWD to discharge the tax liability in respect of the
payments made to the sub-consultants and DHV being a
signatory to the main contract, I am of the opinion that
claim made by DHV in respect of the Income tax dues
would fall within the ambit of the arbitration agreement
between the parties.
17. As regards the question as to whether the said
claim can be said to be stale in the sense that after the
last payment in January, 2003, none of the three parties
herein had any pending claims against each other insofar
as the payments under the main contract were
concerned, I am of the view that notwithstanding the fact
that payments against all the invoices raised by DHV
stood paid, in the light of the agreement between the
parties in terms of clause 1.10, subsequent creation of an
additional payment by the Income tax department in
respect of the payments made by TNPWD to DHV
through Tahal, has given rise to a live dispute requiring
settlement between the parties in terms of the arbitration
agreement. For the view I have taken, it is axiomatic that
prima facie, the claim made by DHV is not barred by
limitation.
18. For the aforesaid reasons the petition is allowed and
as prayed by learned counsel for the parties, instead of
constituting an Arbitral Tribunal, Justice P.K.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
Balasubramanyan, a former Judge of this Court, is
appointed as the Sole Arbitrator to adjudicate upon the
claims/disputes raised by DHV, subject to his consent
and such terms as he may deem fit and proper. Needless
to add that the learned Arbitrator shall deal with the
matter uninfluenced by any observation in this order on
the rival stands of the parties.
19. The Registry is directed to communicate this order
to the learned Arbitrator to enable him to enter upon the
Reference and decide the matter as expeditiously as
practicable. The petition stands disposed of with no
order as to costs.