Full Judgment Text
IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment delivered on: November 25, 2019
+ O.M.P.(I) (COMM.) 270/2019
IRB TUMKUR CHITRADURGA TOLLWAY LIMITED (EARLIER
KNOWN AS IRB TUMKUR CHITRADURGA TOLLWAY
PRIVATE LIMITED)
..... Petitioner
Through: Mr. Saurabh Kirpal, Mr. Parthiv
Goswami, Mr. Sarthak Sachdev,
Mr. Ishan Bisht, Mrs. Teresa.R. Daulat
and Mr. Mohnish Patkar, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI)
..... Respondent
Through: Mr. Sandeep Sethi, Sr. Adv. with
Mr. Ankur Mittal and Mr. Abhay
Gupta, Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
J U D G M E N T
V. KAMESWAR RAO, J
1. The present petition has been filed by the petitioner under
Section 9 of the Arbitration and Conciliation Act, 1996 („Act of
1996‟, in short) with the following prayers:
“It is therefore humbly prayed that this Hon'ble Court
may be pleased to:
A. Stay the operation and effect of the Letter dated 7th
August, 2019 of the Respondent whereby the
Respondent has purported to revoke / withdraw the
OMP (I) (COMM) 270/2019 Page 1 of 60
premium deferment scheme;
B. Restrain the Respondent from taking any coercive
action pursuant to such revocation of the premium
deferment scheme;
C. Grant ex parte ad interim orders in terms of
Prayer A above;
D. Pass such further or other orders as it may deem
fit and proper in the facts and circumstances of the
case.”
2. It is the case of the petitioner that it entered into a
Concession Agreement („CA‟, in short) with the respondent
NHAI for six (6) lanning of the Tumkur-Chitradurga section of
National Highway No.4 in the State of Karnataka and for
operating and maintaining the Project Highway for a period of 26
years on "Design Build Finance Operate Transfer Basis". In
terms of the CA, the petitioner is also required to pay a premium
of ` 140.40 Crores to the respondent, each year till the subsistence
of the agreement along with an annual increase at the rate of 5%.
In compliance with the terms of the CA, the petitioner executed
an Escrow Agreement with the State Bank of India.
3. It is the case of the petitioner that it executed all financing
documents with a consortium of Banks obtaining a Rupee Term
Loan of ` 831 Crores and declared financial closure as per the
terms of the CA. It is the case of the petitioner that the
respondent verified all the documents relating to financing and
declared financial closure having been achieved on March 03,
2011. It is averred that the petitioner converted a portion of the
OMP (I) (COMM) 270/2019 Page 2 of 60
rupee term loan to the extent of ` 300 Crores to an ECB loan i.e
fully convertible foreign currency loan. According to the
petitioner, the ECB agreement entitled the petitioner to hedge the
loan for a certain period, however the ECB loan was to be
converted into a Rupee Term Loan at the end of seven years at
which time the entire foreign losses was to be paid upfront to the
said ECB Bank. According to the petitioner, it submitted a copy
of the ECB Agreement to the respondent. It is averred that the
respondent submitted its comments on the ECB Agreement and
amendments to the main loan documents with the senior lenders
due to the ECB loan. It is averred that the respondent gave its
approval for amendments to the financing agreements. The final
approved financing agreements including the amendments carried
therein pursuant to the ECB loan, after due NOC from
respondent, were submitted to the respondent in compliance with
the terms of the CA. It is the case of the petitioner, in view of the
revenue shortfall across projects and in order to assist
concessionaires of such stressed projects, so that the project does
not suffer, the Central Government sanctioned a "Premium
Deferent Scheme" vide its Circular dated March 04, 2014 for all
such stressed projects in pursuance of Article 28 of the Model
CA. There under, the payment of premium to the extent of
shortfall in subsistence revenue was deferred and payable at a
later stage with interest.
4. According to the petitioner, in pursuance of the Central
Government premium deferment policy, the petitioner made an
application to the respondent for modification of terms of
OMP (I) (COMM) 270/2019 Page 3 of 60
premium payment under the CA, seeking deferment of premium.
It is their case that on June 06, 2014, the respondent sanctioned
and/or granted such approval for deferment of premium payment
to the extent of revenue shortfall as projected and agreed. Clause
3(b) therein provided for levy of interest at the time of payment
of the deferred premium amounts, at the rate of 2% above bank
rate per annum till payment. It is their case, that Clause 3(o)
provided for levy of penal interest of 2.5% per annum, if revenue
shortfall was less than more than 5% of projected revenue
shortfall, on such excess, till payment of additional premium to
offset the excess. According to the petitioner, a Supplementary
Agreement („SA‟, in short) to the CA, was entered into between
petitioner and respondent for deferment of premium in terms of
the sanction letter and the Central Government Scheme for
deferment of premium.
5. It is averred that the respondent vide its letter dated
February 24, 2015 by referring to clause 3(o) of the sanction
letter, requested the petitioner to undertake a review of the actual
revenue deficit for the financial year 2014-15 and if necessary
effect the required corrections and increase the premium
payment. It is averred that the petitioner vide its letter dated April
22, 2015 informed the respondent that upon evaluation of actual
revenue deficit for financial year 2014-15 it was seen that the
actual revenue deficit is higher that the projected revenue deficit.
The petitioner provided detailed calculations and submitted that
the penal interest under clause 3(o) was not applicable. It is the
case of the petitioner that the respondent vide its various letter
OMP (I) (COMM) 270/2019 Page 4 of 60
issued between September 2015 to May, 2016 requested the
petitioner to provide audited financial statements, certified
statements of month wise actual payment of interest and principle
to lenders, O&M expenses, premium paid, bank account
statements and various other documents with respect to expenses
for the financial year 2014-15 & 2015-16, which the petitioner
provided. It is averred that the respondent vide its letter dated
July 28, 2016, informed the petitioner that upon their review of
the actual data of the financial year 2014-15, it was seen that
allegedly the actual revenue deficit was lesser by more than 5%
of the projections. Therefore the respondent demanded that as per
clause 3(o) additional premium amounting to ` 12.74 Crore was
payable by the petitioner along with normal interest of bank rate
plus 2% and penal interest at 2.5%. The petitioner had, vide its
letter dated August 30, 2016, replied to the respondent reminding
the respondent that in calculating the alleged excess revenue the
respondent had not considered the foreign exchange losses which
formed a part of debt servicing and have to be paid in 2017 when
the ECB loan is converted into Rupee Term Loan and therefore
the alleged revenue excess was notional and in view thereof there
was no excess revenue as alleged. According to the petitioner,
the petitioner had through various correspondences repeatedly
explained to the respondent that in effect there was no excess
revenue and the notional revenue savings were ultimately to be
paid towards debt servicing in terms of the foreign losses at the
time of conversion of ECB loan to Rupee Term Loan.
6. It is the case of the petitioner, that it also highlighted
OMP (I) (COMM) 270/2019 Page 5 of 60
various provisions of the sanction letter, lenders
agreement/financing documents and the spirit of the Central
Government premium deferment scheme, wherein it was clear
that the purpose of the deferment scheme was to ensure that the
project revenue was first used for satisfaction of O&M expenses
and entire debt servicing. It was also clear that there was no
provision for compelling the petitioner to pay additional premium
at an earlier date and it is for such purpose that the deferment of
premium was given at the cost of a normal interest of 2% above
the bank rate and penal interest of 2.5%. However, the respondent
constantly insisted on the payment of the additional premium
along with normal interest and penal interest. In fact, it is the case
of the petitioner that it vide its letter dated January 24, 2017
reiterated that there was no revenue excess and the petitioner has
already paid the premium as payable under the sanction letter.
7. It is the case of the petitioner that it also reminded the
respondent that the toll revenues were even lower than the
projected revenues at the time of obtaining the deferment
sanction and therefore the respondent ought not to insist on such
payment of additional premium in contravention of the terms of
the agreement. However without prejudice to such contention the
petitioner offered to pay the penal interest at 2.5% of the alleged
excess. It is the case of the petitioner that it vide letter dated July
15, 2017 wrote to the respondent submitting an audited statement
of revenue shortfall for the project incorporating the foreign
exchange losses on ECB part of the debt for the year ending
March 31, 2016. Similar letter was also sent on November 16,
OMP (I) (COMM) 270/2019 Page 6 of 60
2017. It is also stated that the respondent vide its letter dated
February 16, 2018, inter-alia acknowledge the petitioner‟s
assurance to bear the penal interest at present and to pay the
purported excess premium along with interest as soon as the
project receives toll revenue in excess of the projected toll
revenue. However, the respondent demanded that such proposal
of the petitioner was under consideration at the respondent's
Headquarters and the petitioner should remit additional premium
for financial year 2015-16 along with interest & penalty. It is at
that stage that the petitioner vide its letter dated August 01, 2018
has invoked dispute resolution mechanism in terms of Article
44.2 of the CA for conciliation, in view of the dispute/difference
between the parties. The respondent vide various letters
constantly postponed the conciliation proceedings. Be that as it
may, the petitioner had addressed to the respondent that it has
paid the last tranche of the ECB facility by availing a Rupee
Term Loan on May 18, 2017 and the actual loss on repayment of
the entire foreign exchange loss on such conversion has been
paid. The petitioner submitted detailed statement wherein it was
evident that after factoring such losses the actual revenue
shortfall was higher than the revenue shortfall estimated in the
SA and therefore no additional premium was payable. In
response to the same, the respondent vide its letter dated
November 20, 2018 stated that allegedly ECB facility was not a
part of the financial package and NHAI has not granted any
approval for re-financing through ECB and again demanded
payment of additional premium for financial years 2014-2015
OMP (I) (COMM) 270/2019 Page 7 of 60
and 2015-2016, failing which it would consider revocation of
premium deferment and initiate action as per CA. Finally, vide
letter dated August 07, 2019, the respondent withdrew / revoked
the deferment premium and demanded that the petitioner remit
the entire balance outstanding premium as per the CA.
8. A reply has been filed by the respondent. At the outset,
the respondent has taken a preliminary objection about the
maintainability of the petition, inasmuch as the Arbitration clause
in the CA has no applicability to the SA and as such the petition
is not maintainable. In this regard, it is stated that the scheme of
premium deferment, which was extended by the Central
Government does not form part of CA but was extended on the
strength of a Supplementary Agreement, which did not have the
arbitration clause.
9. That apart, on merit, it is stated that under the CA dated
August 16, 2010, more particularly as per Article 26 thereof, the
petitioner is admittedly liable to pay premium to the respondent
authority. As per the provisions of Article 26.2.1 thereof, the
petitioner is liable to pay a premium in the form of additional
concession fee equivalent to 140.40 Crores commencing with
`
effect from the appointed date. The said premium is to be
increased on annual basis by an additional 5% amount as
compared to the immediately preceding years. The Premium
Deferment Scheme floated by the Government of India in the
year 2014, do not take away the fact that the NHAI is liable to
recover the premium from the Concessionaire, though under the
Deferment Scheme, based on the cash projections made by the
OMP (I) (COMM) 270/2019 Page 8 of 60
Concessionaire with respect to the traffic flow on annual basis, if
a particular project is falling in the category of "stressed" as per
the scheme, the premium deferment scheme has been permitted
subject to review of actual revenue deficit with projected deficit
at the end of every year and if the actual deficit is less than the
projected revenue deficit by more than 5% for payment of
additional concession fee. It is the case of the respondent that
before entering into the SA dated June 6, 2014, the
Concessionaire had made an application on March 25, 2014. In
order to assess the claim for deferring of premium, the
Concessionaire had made the assessment of following costs and
expenses:
a. operation and management outflows;
b. debt servicing;
c. tax payment, if any;
d. actual premium payable under the CA;
10. After adding up the aforesaid amounts, subsistence
revenue was arrived at. The subsistence revenue was thereafter
compared with the projected cash flows made by the
Concessionaire for the respective years at the end of each year,
for Concessionaire to arrive at the figure of revenue shortfall in
the year concerned. The Concessionaire i.e the petitioner, in its
application filed with NHAI on March 25, 2014 sought deferment
of this revenue shortfall through deferment of premium payable
as per CA. The respondent would submit that as per the
calculations circulated by the petitioner along with the
application dated March 25, 2014, debt servicing has been
OMP (I) (COMM) 270/2019 Page 9 of 60
divided into two parts, interest payment and principal payment.
The payment of interest has been captured in the calculations
furnished by the petitioner, which is related to calculating the
interest on the principal amounts at certain rate. The principal
amount repayment has been shown to be NIL initially, which
gradually increases over a period of time. According to the
respondent, the petitioner itself has only engulfed the amount of
interest payment and principal payment towards debt servicing.
There is not even an iota of whisper regarding so called foreign
losses on account of currency fluctuation. The petitioner had not
taken the foreign loss into account as a part of debt servicing,
while submitting the projections to NHAI. The petitioner has not
further explained, as to why such losses were not hedged by way
of obtaining appropriate hedging policy at the beginning itself.
As such, the SA signed on June 6, 2014 is not based upon and do
not take into account any foreign loss on account of currency
fluctuation, as part of debt servicing. Thus, the petitioner is not
entitled to claim any benefit on this count.
11. The respondent has further stated that for the financial
year 2014-15, the petitioner had given a figure of revenue
shortfall of ` 81.45 Crores, the same, apart from others, based
upon debt servicing amount of ` 95.57 Crores. However, when
the review was undertaken by NHAI as per clause 3(o) of the SA
dated June 6, 2014, it was found that as against the debt servicing
amount stated by the claimant to be at ` 95.57 Crores, the debt
serviced was actually only 81.52 Crores, thus lesser by an
`
amount of ` 14.05 Crores. At the same time, the total inflows
OMP (I) (COMM) 270/2019 Page 10 of 60
were projected at ` 185.46 Crores, however the actual collection
stated by the petitioner was to be ` 184.15 Crores. Thus, there is
a loss of ` 1.31 Crores. As a result, the revenue shortfall or
revenue deficit, which was originally projected at ` 81.45 Crores
was only ` 68.71 Crores, lesser by an amount of ` 12.74 Crores.
As a result, revenue deficit which was originally projected at a
different amount, was actually lesser by an amount of 12.74
`
Crores, thus triggering invocation of clause 3(o) of the SA dated
June 6, 2014. As per the said stipulation, if the revenue deficit at
the end of the year is lesser by more than 5% of the figures given
under the projections, the petitioner is liable to pay a penalty of
2.5% additional interest over and above the normal interest of
bank rate plus 2% on the said excess. It is the case of the
respondent that any amount recovered by the petitioner resulted
into less revenue deficit, then the projections originally made,
should be transferred to respondent. The amount so recovered or
reduced expense cannot be retained by the petitioner, as it will be
incomplete and absolute breach of the spirit of the contract and
the premium deferment. The premium has been deferred on the
touchstone that the project must be in stress, and as such, a one-
time benefit was granted to postpone payment of premiums by
arriving at the figure of revenue shortfall. But, if the revenue
shortfall is less than what was projected, so long as the premium
committed to respondent under the CA is not met out, the
petitioner has no authority to retain such additional amount, or
else it would amount to paying a premium to the petitioner for
making the wrong cash projections originally to its benefit. It is
OMP (I) (COMM) 270/2019 Page 11 of 60
the case of the respondent that the petitioner has failed to pay
reviewed premium amounting ` 12.74 Crores for the financial
year 2014-15 along with interest at the rate of the bank rate + 2%
and penal interest of 2.5% over and above the normal interest of
bank rate plus 2% despite several reminders.
12. Similarly, for the financial year 2015 - 16, there is the
difference of ` 4.24 Crores, which is liable to be paid to the
respondent along with interest and penal interest as above. For
Financial Year 2016 - 17, there is no shortfall. For financial year
2017 - 18, there is a difference of ` 46.78 Crores, which again is
liable to be paid to the respondent with interest and penal interest
as above. In total, the revenue amount additionally collected is
63.76 Crores, which is liable to be remitted to the respondent
`
forthwith, together with interest at the rate of bank rate +2% per
annum and additionally penal interest at the rate of 2.5% as
above. The total calculation results to a figure of
` 124,32,56,689/- as on August 31, 2019. In fact, it is the case of
the respondent vide letter dated January 24, 2017, admitted that it
is liable to pay penal interest together with interest as per clause
3(o) above. Therefore, the petitioner cannot be permitted to plead
or argue contrary to the contention of the said letter. The
petitioner had sought deferment of the additional amount
collected in the said letter, which was not permissible under the
CA or the Supplementary Agreement, therefore, the respondent
did not accept the same. It is also stated that the excess collected
by the petitioner vis-a-vis the projected revenue deficit cannot be
permitted to be retained by petitioner, or else it will have
OMP (I) (COMM) 270/2019 Page 12 of 60
cascading effect on other companies to whom similar scheme was
extended by respondent, apart from the fact that the same is in
violation of the terms of the SA and is nowhere provided. It is
also stated that the benefit of deferment of premium was made on
the understanding that the project is under stress, thus affecting
the ability of the petitioner to pay the premium under the CA as
per the schedule laid down therein. If any amounts collected by
the petitioner are permitted to be retained by it, it would directly
affect the ability of petitioner to pay the amount in future, where
already the premium payment amount are swelled up due to
deferment permitted in initial years. Such deferment of amount
collected in the pocket of petitioner, which is legally due to
respondent, would end up adding more stress to the project. The
petitioner, by attempting not to pay the said amount, is seeking to
defer the inevitable default. It is stated that an attempt on the part
of petitioner to retain the revenue collected the debt, despite
under an obligation to pay premium to respondent would amount
to causing loss to public exchequer, and conferring undue benefit
to the petitioner. The deferment permitted to petitioner earlier
was never on the understanding or basis that the petitioner be
permitted to retain certain amounts for itself. It is stated that
foreign loss on account of currency fluctuations, captured in the
accounts of petitioner on annual basis is not a debt servicing. It is
only an accounting entry to reflect the true nature of accounts as
on the financial year concerned. The foreign exchange loss so
captured is only notional, and is not the actual loss suffered,
inasmuch, the repayment of ECB loan is to be done over a period
OMP (I) (COMM) 270/2019 Page 13 of 60
of years. The notional amount which is captured in the accounts,
relates to foreign exchange loss or foreign exchange gain, on
account of currency fluctuations. Eventually, at the time when the
actual repayment is made, if the value of rupee has gone up vis-a-
vis the foreign currency, dollar in this case, the petitioner could
have gained instead of suffering loss. Therefore, the petitioner
ought to have taken this factor into account and hedged the same
by way of having an appropriate hedging policy. It is stated that
all banks and financial institutions funding any foreign currency
loan would insist on hedging, however it is not clear as to why
the same was not done by the petitioner in the instant case. If the
petitioner eventually decided to repay the said foreign currency
loans or convert them into rupee term loan, which resulted into
allegedly causing some foreign loss, the same cannot be
considered as a part of debt servicing as projected by the
petitioner at the time of seeking benefit of the scheme in
question, as the same were not taken into account at the time of
projection for availing premium deferment. Thus, foreign loss, if
any, has to be borne out by the petitioner independent of the
projected cash flows. In any case, no reserve can be permitted to
be created by the petitioner, while not making payment to
respondent mandated under the CA, by citing stress in the project
and the revenue shortfall was related to debt servicing, but does
not include any and every loss suffered by petitioner over a
period of years.
SUBMISSIONS ON BEHALF OF THE PETITIONER
13. Mr. Saurabh Kirpal, learned counsel for the petitioner
OMP (I) (COMM) 270/2019 Page 14 of 60
submitted that the CA dated August 16, 2010 executed between
the Petitioner and Respondent inter alia requires the Petitioner to
pay a premium of ` 140.40 Crores to the respondent each year till
the subsistence of the agreement along with an annual increase at
the rate of 5%. Article 44 provides for a dispute resolution
mechanism whereby the partiers first resolve the dispute through
conciliation as per Article 44.2, failing which Article 44.3
provides for arbitration. The premium obligation under the CA,
was agreed to be modified in accordance with a Circular dated
March 04, 2014 of the Central Government for deferment of
premium read with the petitioner‟s application dated March 25,
2014 and sanction letter dated June 06, 2014 issued by
respondent. Therefore, Supplement Agreement to the CA was
executed recording such modified terms of payment of premium
incorporating therein the terms of Sanction letter and Central
Government resolution / scheme. Recital Clause H of the
Supplemental Agreement recorded “Save and except provided in
this agreement, the Scheme and the letter of the Authority dated
June 06, 2014 the terms and conditions of the Concession
Agreement shall remain final and binding on the parties.” .
Therefore, it is submitted that the supplemental agreement dated
June 06, 2014 is an amendment / addendum to the CA and not a
separate agreement. Article 47.10 of the CA specifically requires
that any amendment or modification has to be carried out in
writing and therefore, there was a need to execute the
Supplemental Agreement. Thus, the arbitration agreement
contained at Clause 44 of the CA covers the disputes relating to
OMP (I) (COMM) 270/2019 Page 15 of 60
or arising out of the terms contained in the said Supplemental
Agreement to the CA. Both agreements, CA and Supplemental
Agreement to CA contain the Clause I stating that “this
agreement shall be subject to jurisdiction of Courts of Delhi”.
This does not negate Arbitration Agreement. In fact, he submitted
by participating in the Conciliation procedure as per Article 44.2
of the CA with respect to this dispute, the Respondent has acted
and accepted the same.
14. Without prejudice to the aforesaid, he submitted even
otherwise the arbitration agreement is incorporated by reference
in terms of Section 7(5) of the Act of 1996 as the Supplement
Agreement specifically refers to the CA. He would rely on the
judgment of the Supreme Court in the case of Alimenta S.A. vs.
National Agricultural Co-operative Marketing Federation of
India Ltd. and Anr., (1987) 1 SCC 615 , to contend that
arbitration clause of an earlier contract can by reference be
incorporated into a later contract provided it is not repugnant to
or inconsistent with the terms of the contract in which it is
incorporated.
15. He further submitted that the Petitioner has a prima facie
case, irreparable harm, loss, injury shall be caused to the
petitioner. According to him, as per the CA the Petitioner has
carried the work of construction and continues to operate and
maintain the Project, entirely at the petitioner‟s costs, including
payment of premium. There is no financial or other liability upon
the respondent for the project. To finance the Project the
Petitioner obtained a Rupee Terms Loan of ` 831 Crores from a
OMP (I) (COMM) 270/2019 Page 16 of 60
consortium of Banks which is approved by Respondent.
Subsequently, a portion of the said Rupee Term Loan to the
extent of ` 300 Crores was converted into an ECB loan (i.e. fully
convertible foreign currency loan) for a term of 7 years, which
requires that at the end of 7 years when the ECB loan is
converted into Rupee Term Loan all forex losses are payable
upfront to the Bank. The terms of the ECB agreement were also
known to Respondent as the documents were submitted to the
Respondent and it suggested some changes.
16. In 2013-2014 Central Government sanctioned a
“Premium Deferent Scheme” vide its Circular dated March 04,
2014 for all financially stressed projects. The Scheme is not a
special / extra contractual sanction but rather in terms of
contractual provisions contained in Article 28 of the Model CA –
Revenue Shortfall Loan. The intent of the scheme is that revenue
from the Project can be used first for satisfying the operation and
maintenance cost and debt servicing, so that main Project cost
required for running the Project are satisfied and the Project does
not suffer. Pertinently, during this entire time period of premium
deferment, the Concessionaire was not permitted to appropriate
for itself (i.e. take any profits) any toll revenues.
17. It is in line of such policy that the Petitioner made an
Application dated March 25, 2014 to Respondent for deferring
the payment of premium for specific years till 2024, after which
year i.e. from FY 2024-2025 till FY 2029-2030 all the deferred
premium along with interest @2% above bank rate would be paid
by the Petitioner in agreed tranches. Due to such deferment the
OMP (I) (COMM) 270/2019 Page 17 of 60
Petitioner is now liable to pay ` 1149 Crores as total premium
rather than the previous obligation of ` 405 Crores. Therefore,
again there is absolutely no loss to the Respondent, rather there is
profit as the interest is 2% higher than Bank rate.
18. He submitted, the Sanction letter incorporated in the
Supplemental Agreement, granting such Deferment, at Clause 1
crystallises the years for which premium would be deferred (i.e.
2014-2015 to 2023-2024), the amount of premium deferred for
these specified years and the amount of revised premium payable
during these years. After the year 2024 all these deferred
premium were payable to the Respondent with the agreed interest
as per the application and sanction letter. Clause 3 (b) of the
sanction letter provided that till the amounts of deferred premium
are repaid or recovered, the deferred amount shall at all times
carry an interest rate equal to 2% above bank rate per annum.
Clause 3 (h) provided that during the deferment period the
Petitioner was not entitled to any return on equity (i.e. the
Petitioner could not take any revenue for itself except for project
cost towards O & M expenses, debt servicing and payment of
premium.) Clause 3(o) provided that if the revenue deficit as
actually seen on review at the end of the year is lesser by more
than 5% of the figures projected the Petitioner will be liable to
pay a penalty of 2.5% additional interest over and above the
normal interest of Bank rate +2% on the said excess. It also
recorded that “however if the Petitioner effects the required
correction and increases the premium payment so as to have no
excess no such penalty would be payable”.
OMP (I) (COMM) 270/2019 Page 18 of 60
19. Thus, according to him it is evident from the plain
reading of the clauses, the Petitioner was entitled to pay the entire
deferred premium amounts only after FY 2024-2045 i.e. period of
deferment. In consideration whereof, the Petitioner was required
to pay interest on such deferred amounts @ 2% above bank
interest rate, along with the deferred premium amounts. Further,
in the event it was seen that there was any excess revenue during
any financial year, than the projections, then at the time of paying
such determined deferred premium amounts with interest @ 2%
above bank rate the petitioner was liable to pay additional interest
@ 2.5% over such revenue excess. Nowhere do the terms of the
agreement require / provide that in the event of such excess
revenue, Petitioner was liable to forthwith pay additional
premium. Clearly the liability that accrued upon determination of
such revenue excess (or shortfall in revenue deficit) was to bear
more interest over the total deferred premium (principal) and not
that additional premium was to be paid forthwith. However, if the
Petitioner chose to pay the additional premium so as to negate the
excess revenue of that year, then the penalty interest would not be
levied. Pertinently the payment of the additional premium amount
(which is a part of principal) would result in a reduction in the
total deferred premium to be paid with interest after 2024 and if
such additional premium is not paid then when the total deferred
premium is paid with normal interest the Petitioner would be
liable for additional interest, because there could be no change in
the total deferred premium amount payable. The only variable
was the applicable interest but as the nature of the scheme was
OMP (I) (COMM) 270/2019 Page 19 of 60
that this interest and the principal i.e. the deferred premium, was
not payable immediately (rather payable after 2024), no such
inference can be drawn that it was a contractual obligation to pay
the additional premium upfront, upon determination. This is a
commercial consideration by the Respondent in view of the
higher interest rates being paid to the Respondent. In fact the
Petitioner has duly paid all the agreed revised premium amounts
payable after the deferred premium amounts and by 2017-2018
the Petitioner paid a total of ` 462.15 Crores as revised premium
amount.
20. In view of the aforesaid, the demand of the Respondent
for payment of ` 12.54 Crores for 2014-2015 and ` 3.60 Crores for
2015-2016 along with normal interest and penalty interest in
terms of Clause 3(o) of the sanction letter for an alleged lesser
revenue shortfall/revenue excess, is in breach of the terms of the
contact. It is submitted that firstly there has been no shortfall in
revenue deficit in the financial years 2014-2015 and 2015-2016.
The Respondent has not considered forex losses which forms part
of Debt Servicing. The revenue savings / shortfall in revenue
deficit seen in 2014-2015 and 2015-2016 is only notional, as the
entire forex losses have been re-paid at the end of 7 years when
the ECB loan is repaid and converted into Rupee Term Loan.
Petitioner has borne forex losses to the tune of ` 111.83 Crores
and the same is certified by the Statutory Auditor, who itself
considers this as Debt. Article 48 of the CA defines Debt Service
as “the sum of all payments on account of principal, interest,
financing fees and charges due and payable in an Accounting
OMP (I) (COMM) 270/2019 Page 20 of 60
Year to the Senior Lenders under the Financing Agreements”. As
seen at pg.33 of the Petition, in 2017-2018 the Petitioner has paid
a total of ` 241.89 Crores towards Debt Servicing as against the
projected Debt servicing of 96.55 Crores as per the
`
supplemental agreement. Further, between the period 2014 to
2018 the Project has not been cash/revenue surplus i.e. it has
always been in revenue deficit. As against a projected Revenue
Shortfall of ` 238.38 Crores there has been an actual revenue
deficit of ` 422.87 Crores. Therefore, it is submitted that the
provisions of Clause 3 (o) of the Sanction letter are not invoked
as there is no shortfall in revenue deficit.
21. He stated, assuming without admitting that there is a
more than 5% shortfall in revenue deficit, even then as per the
plain language of Clause 3(o) there is no provision requiring the
Petitioner to upfront / forthwith pay the additional premium. In
fact as stated earlier, Clause 3(o) only contemplates that in such
event the Petitioner would be liable to pay additional interest as
penalty. It is submitted that when the scheme of deferment itself
requires that the principal (deferred premium amount) and the
interest (normal interest of 2% above bank rate) is to be paid only
after 10 years (2024) which is the period of deferment, then
Clause 3(o) can by no stretch of imagination be construed as a
liability of the Petitioner to pay additional premium and normal
interest and penalty interest forthwith or prior to the said 10 year
period. It is submitted that as per the principle of contra
proferentem, any ambiguity in the terms of the contract have to
interpreted against the interest of the party who drafted the
OMP (I) (COMM) 270/2019 Page 21 of 60
contract, which in the instant case is the Respondent. The
Petitioner‟s interpretation regarding operation of Clause 3 (o) of
the Deferment Sanction is both plausible and within the
framework of the „Scheme‟.
22. He submitted that while the contention whether these
amounts are a payable or not forms part of the dispute to be
decided by the arbitral tribunal, on one hand the Respondent is
refusing to appoint their arbitrator, on the other hand the
Respondent has by its Letter dated August 07, 2019 illegally
terminated / revoked / withdrawn the deferment scheme and has
by its letter dated August 14, 2018 called upon the Escrow Bank
to release an amount of ` 524,27,30,506/- (being the entire
amount of deferred premium along with normal interest and penal
interest) to be paid within 15 days of the Notice. It is submitted
that if such action on part of the Respondent is not stayed then the
Escrow Bank shall release the said amounts, even though
contractually the same are not payable and the arbitration invoked
by the Petitioner would frustrate. Further, the revenues from the
Project will not be sufficient to service the Operation and
Maintenance cost of the project and the project would turn NPA.
This would be contrary to the very principle of the Deferment
Scheme which was, to ensure that Operation and Maintenance
cost and Debt servicing are met and could lead to termination of
the CA itself. The claim of the Respondent is only a monetary
claim and is secured by the interest component secured in the
contract itself, as per Clause 3(o). Further, in the event that the
Petitioner for any reason, is unable to pay the amounts due to the
OMP (I) (COMM) 270/2019 Page 22 of 60
Respondent as per the Award, the Respondent has the contractual
right to terminate the CA and take over the Project assets (which
have been created by the Petitioner at its own cost) and collect
and appropriate toll thereon. In any event the Petitioner is a well-
established company and after having invested such huge
amounts in the construction of the Project and typing up debt
obligation, they will not renege from its obligations and leave the
project. Therefore, the petitioner seeks that reliefs sought herein
are granted.
SUBMISSIONS ON BEHALF OF THE RESPONDENT:
23. On the other hand, Mr. Sandeep Sethi, learned Senior
Counsel appearing for the respondent would submit that a CA
dated August 16, 2010 was entered between petitioner and
respondent for six-laning of the subject project highway from the
existing four lanes.
24. The Concessionaire was entitled to collect the toll from
the existing project highway. As per Article 26 of CA, the
petitioner is admittedly liable to pay premium (part of concession
fee as per article 26.22) to respondent Authority. As per Article
26.21, a premium of 140.40 annually in the form of additional
`
concession fee was payable by petitioner to respondent
commencing from appointed date. The said premium is to be
increased on annual basis by additional 5% amount as compared
to immediately preceding year. The Concession period under the
CA is 26 years.
25. Article 28 provides for revenue shortfall loan by NHAI.
As per the said article, if the realisable fee in any accounting year
OMP (I) (COMM) 270/2019 Page 23 of 60
fall short of subsistence revenue as a result of Indirect political
event, political event or Authority default, a provision for loan by
Authority to Concessionaire has been carved out. Article 44 is
the dispute resolution clause providing for arbitration.
26. Petitioner vide letter dated February 03, 2011 intimated to
NHAI that it has executed the Financing Agreements with its
lenders allegedly incorporating NHAI‟s comments. Vide the said
letter petitioner further declared that Financial Close for the
project in terms of Cl. 24.1.2 has been achieved. As per List of
Dates filed by petitioner, a Rupee Term Loan of ` 831 Crores
was availed by petitioner.
27. Vide letter dated April 01, 2011 NHAI declared that
petitioner has achieved Financial Close on March 03, 2011 with a
delay of 14 days as compared to stipulated time of 180 days (as
per clause 24.1.1) from date of CA under the CA. That on June
29, 2011 petitioner obtained Rupee Term Loan of 300 Crores
`
from ICICI Bank with a sublimit of ECB (External Commercial
Borrowing) loan i.e. foreign currency loan to the extent of USD
66.70 million. Unlike Rupee Term loan wherein petitioner has
sought NHAI‟s comments before executing the documents, no
comments or concurrence was sought before executing the ECB
agreement dated June 29, 2011.
28. That petitioner after having already executed the ECB
facility agreement dated June 29, 2011, vide letter dated August
18, 2011 (almost after 2 months of having entered into ECB
agreement on June 29, 2011) chose to intimate NHAI that
petitioner has availed financial assistance from ICICI bank
OMP (I) (COMM) 270/2019 Page 24 of 60
limited in the form of rupee facility of ` 300 crores with an ECB
sub-limit not exceeding USD 66,700,000/-, such that the
aggregate amount of loan commitments available to the Borrower
from existing lenders as well as ICICI Bank limited does not
exceed 831 crores.
`
29. He stated the letter dated August 18, 2011 in most
unambiguous terms and categorically stated that execution of the
new documents (including ECB agreement) would not have the
effect of imposing or increasing any financial liability or
obligation on NHAI. The relevant extract is reproduced herein
under:
“We hereby confirm that execution of the aforesaid new
documents would not have the effect of imposing or increasing
any financial liability or obligation on NHAI”
30. According to him, the petitioner was fully aware at the
relevant time that there may be currency fluctuation resulting into
forex gain or loss, however, petitioner made a categorical
statement in the above terms comforting the NHAI that the
entering into of ECB Agreement by petitioner will not add any
additional burden or obligation on NHAI.
31. That NHAI in response to letter dated August 08, 2011,
vide letter dated January 30, 2012 informed petitioner that
financial Consultant and Credible Management & Consultant
(Pvt.) Ltd. has examined the Term Loan Agreement and
Amendment to the Financing Agreement and has furnished their
comments in terms of Annexure A and Annexure B annexed with
the said letter. It was categorically stated that draft copies of the
OMP (I) (COMM) 270/2019 Page 25 of 60
agreement and amendments which is requirement of the Cl. 5.2
of CA have not been provided by petitioner.
32. That petitioner in response to letter dated January 30,
2012, vide its letter dated March 26, 2012 admitted that draft
copies of agreement were not submitted to NHAI. Petitioner
again reiterated that new agreements and amendments carried
out/executed does not increase the financial liability of NHAI.
He mentioned that response of petitioner against each of the
comments raised by NHAI vide letter dated January 30, 2012
would show that no changes/modifications to already executed
ECB agreements and other agreements was agreed upon by
petitioner for one or the other reason. Further, vide its letter dated
March 26, 2012 petitioner had sought concurrence of NHAI.
33. It is relevant to mention that no concurrence whatsoever
was ever accorded by NHAI vis-à-vis ECB agreement. The
reliance placed by petitioner on letter dated May 02, 2012 to
suggest that concurrence was provided is highly misplaced. A
perusal of the aforesaid letter would show that letter is related to
different transaction altogether i.e. 136 Crores from IDFC to
`
IIFCL whereas the ECB agreement was regarding ` 300 Crore
with ICICI Bank Limited Bahrain Branch. Hence, the contention
of the petitioner that NHAI have its approval to ECB agreement
is completely baseless. Not even a single document has been
placed before this Court to support the bald assertion that NHAI
has ever agreed or concurred for ECB transaction.
34. On March 04, 2014, Govt. of India floated Premium
Deferment Scheme. As per the said deferment scheme, if a
OMP (I) (COMM) 270/2019 Page 26 of 60
project fell in the category of „stressed‟ as per the defined criteria,
then in such case, the Concessionaire will be extended benefit of
determent of premium by a certain number of years. The scheme
provides for mode of implementation of said deferment scheme,
including the terms and conditions governing the implementation
thereof.
35. Clause 6(a) of the deferment scheme categorically
provides that the financial stress is only limited to premium
payment and “ not linked to any cash shortfall on account of any
O&M Expenses, debt servicing etc. ” The Concessionaire vide
letter dated March 25, 2014 applied for deferment of premium
under the aforesaid deferment scheme ( and not under the
concession agreement/or claiming any revenue shortfall loan
under article 28). Along with the said application, the Petitioner
made the assessment of following costs and expenses in order to
arrive at Subsistence Revenue:
i. Operation and management outflows
ii. Debt servicing
iii. Tax payment
iv. Actual premium payable under Cl.26.2.1
36. A perusal of the calculations made by the Concessionaire
itself (and forming part of the application dated March 25, 2014)
would reveal that the Concessionaire included only two
components as a part of debt servicing:
(a) Interest payment
( b) principal payment
No other component towards debt servicing was either
OMP (I) (COMM) 270/2019 Page 27 of 60
contemplated or reserved to be added in future, or proposed to
NHAI for consideration as a part of sanction, much less any forex
loss. Even otherwise, forex loss on a future date at best is an
operational loss, and is not part of debt servicing. Without
prejudice, the petitioner, in any case, never included the same as
a part of debt servicing.
37. Vide sanction letter dated June 06, 2014 a sanction was
provided and benefit of Deferred Premium Scheme was conferred
upon the petitioner relying upon the application dated March 25,
2014. Thus, the parties had never contemplated forex loss/gain as
a part of debt servicing. Pursuant thereto, a SA dated June 06,
2014 was also executed between petitioner and NHAI. It was
categorically stated in SA that terms and conditions envisaged in
the sanction letter dated June 06, 2014 would be binding on the
parties.
38. As per clause 3 (o) of sanction letter dated June 06, 2014
issued by NHAI, in case revenue deficit at the end of year is
lesser by more than 5% of the figures given under the projections
now being considered, petitioner would be liable to pay a penalty
of 2.5% additional interest over and above the normal interest of
bank rate + 2%, on the said excess. During review for the year
2014-15 as compared to deferment based on projected figure of `
81.45 Crore, the premium deferment based on actual figure
worked out less i.e. ` 68.71 Crore, thereby petitioner retaining `
12.74 Crore beyond its entitlement under the scheme. During
review for the year 2015-16 as compared to deferment based on
projected figure of 67.8 Crore, the premium deferment based on
`
OMP (I) (COMM) 270/2019 Page 28 of 60
actual figure worked out less i.e. ` 63.56 Crore, thereby retaining
` 4.24 Crore beyond its entitlement under the scheme.
39. Similarly, for the year 2017-18 as compared to deferment
based on projected figure of ` 36.28 Crore, the premium
deferment based on actual figure worked out in negative i.e.
` 10.75 Crore, thereby petitioner retaining ` 46.78 Crore beyond
its entitlement under the scheme.
40. Admittedly, petitioner retained the aforesaid amount,
despite, several correspondences by NHAI seeking demand of the
revenue shortfall, and did not even pay the penal interest, thus
committing default. Respondent was constrained to withdraw
benefit of the scheme vide letter dated August 07, 2019 under Cl.
3(p) and demanded the deferred premium and other amounts.
41. He submitted that deferment of premium is not
contemplated in the CA, as such, same has solely been granted to
petitioner based on the scheme floated by the Govt. of India on
March 04, 2014. It is relevant to mention that SA dated June 06,
2014 by way of which benefit of aforesaid deferment scheme was
conferred on the petitioner does not contained any arbitration
clause.
42. According to him, the petitioner in its attempt to bring the
present dispute within the scope of arbitration clause (Clause 44
of CA dated August 16, 2010) is trying to place reliance on
Article 28 of CA to suggest that Premium Deferment Scheme
was sanctioned to petitioner based on Article 28. The said
contention of the petitioner is completely misplaced.
43. According to Mr. Sethi, Article 28 does not contemplate
OMP (I) (COMM) 270/2019 Page 29 of 60
any premium Deferment rather it contemplates disbursement of
Revenue shortfall loan or Provisional Shortfall loan in case
Realisable Fee falls short of Subsistence Revenue due to
happening of Indirect Political Event, Political Event or an
Authority‟s Default. Importantly, it is neither the case of the
petitioner that any indirect political event, Political Event or
Authority‟s default has occurred nor NHAI has disbursed any
loan to the petitioner. The aforesaid facts clearly suggest non-
applicability of Article 28 in the present case.
44. The dispute resolution Clause 44 which limits its
applicability to disputes, differences or controversy of whatever
nature howsoever arising under or out of or in relation to the CA.
Evidently, the CA did not contemplate Premium Deferment (as
same was granted to the petitioner based on the Government of
India Scheme dated March 04, 2014) hence, the grant or
withdrawal of premium deferment scheme neither arises under or
out of or in relation to CA. Hence, the present dispute is not
arbitrable.
45. According to Mr. Sethi, the petitioner further seeks to rely
upon clause H of the Supplemental Agreement dated June 06,
2014 to assert that the arbitration clause is deemed to have been
incorporated by way of reference in the supplemental agreement.
He stated, Clause H provides as under:
“H. Save and except provided in this Agreement, the scheme and
the sanction letter of the Authority dated June 04=6, 2014 the
terms and conditions of Concessions Agreement shall remain
final and binding on parties.”
OMP (I) (COMM) 270/2019 Page 30 of 60
46. It is submitted that the only purpose of inserting clause H
is to deal with the binding nature of the scheme and the sanction
letter issued by the Authority on June 06, 2014. The intention of
the parties was not to incorporate the arbitration clause by way of
reference. It is submitted that the scheme is floated by the
Government of India, and is outside the scope of the original
contract entered i.e. CA into between the parties. The purpose of
scheme and the subsequent sanction letter and signing of SA was
merely limited to grant the benefit of said deferment scheme.
47. As a matter of fact, clause 3(p) of the sanction letter itself
deals with the default in compliance with the terms and
conditions of the sanction letter and entitlement of NHAI to
suspend or withhold or withdraw the facility of deferment of
premium and demand repayment of all outstanding liabilities
including interest accrued.
48. Learned counsel for the respondent seeks to rely on the
judgment of the Supreme Court in the case of M.R. Engineers
and Contractors Pvt. Ltd. v. Som Datt Builders Ltd., (2009) 7
SCC 696. He stated, the SA dated June 06, 2014 neither it
contains any arbitration clause not it makes reference to the
arbitration clause in the main agreement. As such, had there been
any intention to resolve dispute arising out of SA by way of
arbitration then there was no reason for parties not to have
mentioned the arbitration clause or not to have referred to
arbitration clause in the main agreement. On the contrary, clause
I of the SA makes a reference to the jurisdiction of Courts at
Delhi.
OMP (I) (COMM) 270/2019 Page 31 of 60
49. He submitted that the petitioner made an assertion that the
SA is not separately terminable, and it merely amends the terms
of the CA. It is submitted that the intention and purpose of
entering into a SA was to confer the benefit of deferment scheme
floated by the Government of India, which was outside the scope
of original contract i.e. the CA. It is with this intention, the SA
makes reference to the application dated March 25, 2014 and the
sanction dated March 6, 2014 as the basis of entering into the
supplementary agreement. He submitted that the intention of
parties was not to incorporate the arbitration clause 44 into the
supplementary agreement. This according to him fortified by the
fact that by way of letter dated August 7, 2019, the NHAI has
simplicitor withdrawn the benefit of deferment granted earlier.
The CA continues to govern the parties and is binding.
50. Once, the dispute in question is not arbitrable, a petition
Section 9 of the Act of 1996 is not maintainable.
51. Mr. Sethi also submitted, with the application dated
March 25, 2014 petitioner in order to assess the claim (amount)
for deferring of premium, had made the assessment of following
costs and expenses:
i. Operation and management outflows
ii. Debt servicing
iii. Tax payment
iv. Actual premium payable under Cl.26.2.1
52. After adding up the aforesaid amounts, Subsistence
Revenue was arrived at. The Subsistence Revenue was thereafter
compared to projected cash flow/inflow for respective year and
OMP (I) (COMM) 270/2019 Page 32 of 60
the difference between the two (Subsistence Revenue and Cash
inflow) was sought for premium deferment. As such, the amount
projected against each of the heads under costs and expenses
becomes significant, as the amounts are projected figures which
may vary from actual figures, NHAI contemplating the aforesaid
situation took care of it under Clause 3 (o) of its sanction letter
dated June 06, 2014.
53. As per Cl. 3(o) of sanction letter dated June 06, 2014
issued by NHAI, in case revenue deficit at the end of year is
lesser by more than 5% of the figures given under the projections
in letter of petitioner dated March 25, 2014, petitioner would be
liable to pay a penalty of 2.5% additional interest over and above
the normal interest of bank rate +2%, on the said excess. As per
the data, the actual figures against the projected figures, year-
wise are as under:
A. For the year 2014-15
Rs. In Crores
| Year 2014-15 | Projected figures taken<br>for deferment of premium | Actual figures<br>worked out | Difference |
|---|---|---|---|
| O & M | 8.81 | 8.81 | 0 |
| Debt Services | 95.57 | 81.52 | 14.05 |
| Premium Payable | 162.53 | 162.53 | 0 |
| Subsistence<br>revenue | 266.91 | 252.86 | 14.05 |
| Toll inflows | 185.46 | 184.15 | 1.31 |
| Revenue shortfall | 81.45 | 68.71 | 12.74 |
B. For the year 2015-16:
Rs. In Crores
OMP (I) (COMM) 270/2019 Page 33 of 60
| Year 2014-15 | Projected figures taken<br>for deferment of premium | Actual figures<br>worked out | Difference |
|---|---|---|---|
| O & M | 9.25 | 9.25 | 0 |
| Debt Services | 96.35 | 86.19 | 10.16 |
| Premium Payable | 170.66 | 170.66 | 0 |
| Subsistence<br>revenue | 276.26 | 266.1 | 10.16 |
| Toll inflows | 208.46 | 202.54 | 5.92 |
| Revenue shortfall | 67.8 | 63.56 | 4.24 |
C. For the year 2016-17: No shortfall
D. For the year 2017-18:
Rs. In Crores
| Year 2014-15 | Projected figures taken<br>for deferment of premium | Actual figures<br>worked out | Difference |
|---|---|---|---|
| O & M | 10.2 | 10.2 | 0 |
| Debt Services | 96.55 | 20.37 | 76.18 |
| Premium Payable | 188.15 | 188.15 | 0 |
| Subsistence<br>revenue | 294.9 | 218.72 | 76.18 |
| Toll inflows | 258.69 | 229.29 | -29.4 |
| Revenue shortfall | 36.21 | -10.57 | 46.78 |
Abstract Recovery of Premium based on review as per above
tables:
| Sl.No<br>. | Year | Premium amount to be recover (Rs.<br>in Crs.) |
| A | 2014-15 | 12.74 |
| B | 2015-16 | 4.24 |
| C | 2016-17 | 0 |
| D | 2017-18 | 46.78 |
| TOTAL | 63.76 |
OMP (I) (COMM) 270/2019 Page 34 of 60
54. He submitted that the excess amount is admittedly retained
by the petitioner. The only explanation being, that the petitioner
seeks to keep the same as reserves for meeting out future forex
losses. It is the case of the petitioner that aforesaid excess amount is
to be adjusted towards forex losses which may be incurred by it on
account of External Commercial Borrowing (ECB). According to
him on a perusal of the calculations made by the Concessionaire
itself (and forming part of the application dated March 25, 2014)
would reveal that the Concessionaire included only two components
as a part of debt servicing:
(a) Interest payment
( b) principal payment
No other component towards debt servicing was either contemplated
or reserved to be added in future, or proposed to NHAI for
consideration as a part of sanction. As such so called forex losses
were never included by petitioner while seeking benefit of premium
deferment scheme.
55. He stated even otherwise also, petitioner could not have
sought for any forex losses for the simple reason that petitioner vide
its letter dated August 18, 2011 categorically stated that execution of
the new documents (including ECB agreement) would not have the
effect of imposing or increasing any financial liability or obligation
on NHAI. The aforesaid stand was reiterated by petitioner vide its
letter dated March 26, 2012 wherein it again stated that new
agreements and amendments carried out does not increase the
financial liability of NHAI. Hence, attempt of petitioner to somehow
OMP (I) (COMM) 270/2019 Page 35 of 60
justify the retention of excess amount towards alleged forex losses is
completely misplaced and contrary to its own stand.
56. Importantly, as far Excess amount of ` 12.54 cores for FY
2014-15 is concerned as stated herein above by respondent, same has
been shown by petitioner in its own calculations as well (through in
its pleading petitioner seeks to explain it as notional revenue
savings).
57. Hence, once the excess amount of ` 12.54 crores is admitted,
which is more than 5% of the figures given under projection under
application dated March 25, 2014 by petitioner, clause 3(o) is
invoked. As such, the petitioner ought to have paid the excess
amount to NHAI along with penalty of 2.5% additional interest over
and above the normal interest of Bank rate +2% on the said excess.
Evidently, till date, petitioner has neither paid the penalty of 2.5%
additional interest over and above the normal interest of Bank rate
+2% on the said excess nor has it paid the excess amount.
58. He submitted that it is contended by the petitioner‟s counsel
that even if petitioner has retained the excess revenue, petitioner
would not be in default as long as he is ready and willing to pay
penalty of 2.5% additional interest over and above the normal
interest of Bank rate +2% on the said excess. It was also contended
by the petitioner‟ counsel that the terms of the sanction/SA does not
stipulate remittance of the excess amount or the interest or the penal
interest immediately.
59. In this regard, he submitted that non-payment of excess
amount and penalty by petitioner amounts to default. Evidently,
various demand letters have been made to the petitioner, however,
OMP (I) (COMM) 270/2019 Page 36 of 60
petitioner till date has neither chosen to pay the excess amount nor
the penalty+interest as per Cl.3(o). The interpretation given by
petitioner would virtually bring the entire deferment scheme to
standstill, and defeat its very purpose. Instead of deferment being a
temporary measure to rescue the stressed projects to tide over the
stressed situation, it becomes a measure for the concessionaire (who
is otherewise bound by CA to pay concession fee including the
premium), to retain in his own pocket for a certain number of year,
certain amounts of money, at the cost and expense of NHAI.
60. The very objective and basis of the deferment scheme is to
defer only that portion of revenue deficit, which is not earned or
collected in the concerned financial year by the concessionaire. The
concessionaire cannot argue that although it saved more in particular
financial year, yet it would retain the same in its own pocket, while
differing the otherwise payment already due and payable to NHAI.
61. The petitioner cannot further be permitted to argue that it is
willing to pay interest as well as penalty for pocketing such money at
the end of the deferred period (10 years in this case). Such an
interpretation would defeat the entire deferment scheme and would
open the doors to such unscrupulous concessionaire, to keep on
pocketing the revenue earned in a financial year, while asking the
NHAI to wait for 10 years to recover its premium alongwith interest
and penal interest.
62. He submitted, the repeated emphasis by Mr. Kirpal during
arguments, that the interest rate is a huge burden, is a farce. On the
contrary, the interpretation amounts to a soft unsecured loan to
petitioner on a meagre rate of interest. It is submitted that the
OMP (I) (COMM) 270/2019 Page 37 of 60
concessionaire cannot be permitted to pocket any excess money,
which is otherwise due and payable to NHAI as per the CA. The
deferment is not aimed at filling the coffers of concessionaire or
providing concessionaire a soft unsecured loan on a meagre rate of
interest, while keeping the NHAI at bay. Such interpretation is
absurd and would make the scheme itself unworkable.
63. The situation that stands today is that petitioner is enjoying
the excess amount without paying the penalty as contemplated under
clause 3(o). Hence, merely expressing its willingness to pay the
penalty (and that too belatedly in the year 2017) and not actually
paying anything to NHAI, the same does not exonerate petitioner
from being in default. He stated that for purposes of making its
submissions, respondent is referring to the excess amount of ` 12.54
Crores in FY 2014-15, as such, same submissions regarding the
excess the amount for other financial years may also be read
accordingly.
64. According to him as per clause 3(b) of sanction letter dated
June 06, 2014, the amounts of deferred premium are to be repaid or
recovered from the date such amounts are deferred with an interest
equal to 2% above the bank rate per annum. The Interest will be
compounded annually and calculated on the daily outstanding
balance of deferred premium. The aforesaid clause is applicable to
the deferred premium. However, the sanction letter under cl. 3(o)
vis-à-vis excess revenue envisages a penalty of 2.5% additional
interest over and above the normal interest of bank rate plus 2% on
the said excess.
65. The clause 3(o) suggests no other option but payment of
OMP (I) (COMM) 270/2019 Page 38 of 60
penal interest @2.5% over and above the bank rate +2% on the said
excess (alongwith the excess payment) in case petitioners fails to
increase the premium amount so as to have no excess by the end of
the relevant year. He submitted that the comparison between the two
clauses i.e. Cl. 3(b) and Cl. 3(o) is only with respect to additional
2.5% of interest. Hence, if the contention of Mr. Kirpal that
petitioner can retain the excess merely by assuring to pay the penalty
(and not even paying the penalty also) is assumed to be correct, then
it would result into petitioner retaining the excess amount for the
indefinite term at the meagre interest rate of 2.5% over the bank rate.
He submitted that petitioner would be more than happy to pay 2.5%
additional interest and enjoy crores of rupees which otherwise if he
would have borrowed from the market (bank/NBFCs/other lenders)
would not have come to it for less than 18-20% of interest that too he
would have been required to secure the aforesaid amount with some
security. He stated, it is amply clear that the contention of the
petitioner that it can retain the excess by merely paying the penalty
defies all the logic of commercial and current market situation.
Hence, the contention of the petitioner that it can retain the excess
amount by merely offering to pay additional rate of 2.5% interest
(and that too on a future date not clarified) is meritless.
66. He stated the provisions of penalty is with an objective to act
as a deterrent for concessionaire not to default in paying excess to
NHAI. It nowhere absolves the concessionaire of its inherent
liability to pay the premium or excess amounts. If in a particular
year, the concessionaire ends up not being in revenue deficit at all
and earns more than what was projected, as per the interpretation of
OMP (I) (COMM) 270/2019 Page 39 of 60
Concessionaire, it would be entitled to retain all the excess money in
its own pocket, while asking the NHAI to keep on waiting, despite
the fact that there may not be a revenue deficit at all. Such is not the
understating of the deferment scheme.
67. Hence, according to Mr. Sethi, petitioner being in default and
respondent is well within its right to withdraw the benefit of the
scheme under clause 3(p) of the sanction letter dated June 06, 2014.
III. FOREIGN EXCHANGE LOSS
68. He further submitted that the forex loss was neither
contemplated by Concessionaire in its application dated March 25,
2014 nor forming part of sanction dated June 06, 2014; the SA dated
June 06, 2014. Even otherwise, forex loss on account of currency
fluctuations, allegedly captured in the accounts of Concessionaire on
annual basis is not a debt servicing. It is only an accounting entry to
reflect the true nature of accounts of the Financial Year concerned.
The forex loss so captured is only notional, and is not the actual loss
suffered, inasmuch as the repayment of ECB loan is to be done over
a period of years. The notional amount which is captured in the
accounts, relates to forex loss or foreign exchange gain, on account
of currency fluctuations. Eventually, at the time when the actual
repayment is made, if the value of rupee has gone up vis-à-vis the
foreign currency, dollar in this case, the petitioner could have gained
instead of suffering loss.
69. He submitted, therefore, that the Concessionaire ought to
have taken this factor into account and hedged the same by way of
having an appropriate hedging policy. It is equally important to note
that over a period of years, all banks and financial institutions
OMP (I) (COMM) 270/2019 Page 40 of 60
funding any foreign currency loan would insist on hedging, however,
it is not clear whether petitioner has hedged its foreign currency loan
or not, further, if petitioner has not hedged it, it is not clear as to why
the same was not done by the Concessionaire in the instant case. If
the Concessionaire eventually decided to repay the said foreign
currency loans or convert them into rupee term loan, which resulted
into allegedly causing some forex loss, the same cannot be
considered as a part of debt servicing as projected by the
Concessionaire at the time of seeking benefit of the scheme in
question. Therefore, forex loss, if any, has to be borne out by the
Concessionaire independent of the projected cashflows. In any
case, no reserve can be permitted to be created by the
Concessionaire, while not making payment to NHAI mandated under
the CA, by citing stress in the project. It is submitted that the
revenue shortfall was related to debt servicing, but does not include
any and every loss suffered by Concessionaire over a period of years.
70. Respondent is not at all liable to extend any deferment
benefit for ECB losses as no prior approval was taken by the
petitioner for availing ECB loan and ECB loan is not a part of the
financial closure on the basis of which appointed date declared. The
financial closure was achieved by the petitioner on March 03, 2011.
Subsequently, the Concessionaire chose to avail a financial
assistance from ICICI bank limited by way of rupee loan was only a
sub-limit of the said rupee term loan facility.
71. The Concessionaire never sought approval from NHAI for
execution of ECB Facility Agreement, which was executed as early
as on June 29, 2011. A letter dated August 18, 2011 appears to have
OMP (I) (COMM) 270/2019 Page 41 of 60
been sent to NHAI for mere information and records. He submitted
that the said letter categorically made an assertion that the aforesaid
new documents will not have any increased financial liability or
obligation on NHAI. Relevant extract of the said letter is reproduced
as under:
“ we hereby confirm that the execution of the aforesaid new
documents would not have the effect of imposing or increasing any
financial liability or obligation on NHAI.”
72. This ECB Facility Agreement was executed between the
respective parties (not NHAI) to capture the sub-limit of rupee loan
facility of ` 300 Crores. Insofar as the rupee facility of ` 300 Crores
granted by ICICI bank is concerned, the lenders had amended the
original Common Rupee Loan Agreement dated February 03, 2011
amended on August 05, 2011 which has not been produced on
records by the Concessionaire.
73. The repayment clause 6 in the ECB Facility Agreement,
provides that the repayment is to be made in an equal semi-annual
installments in line with the repayment schedule of the rupee lenders
under the amended Common Rupee Loan Agreement. In other
words, the repayment was to continue alongside repayment of rupee
loan and the last payment was to be made on the date when the rupee
loan would have been closed. The Concessionaire has not placed
material on record to show the repayment schedule or under the
amended Common Rupee Loan Agreement. Despite having full
knowledge of the ECB Facility Agreement executed as earlier as on
2011, in the application filed by the Concessionaire on March 25,
2014 for seeking benefit of Deferment Scheme, no provision was
OMP (I) (COMM) 270/2019 Page 42 of 60
made towards forex loss. He submitted that the Concessionaire did
not do so, as it was fully aware that the debt servicing will not
include the component of forex loss, which is contingent liability in
nature.
74. Mr. Sethi submitted, after having signed the SA with open
eyes, and after having projected the cashflows including the debt
servicing based on certain understanding, which form the basis of
execution of Supplementary Agreement, the Concessionaire cannot
be permitted to take a U-turn and start adding more components
within the definition of debt servicing.
75. He submitted that an ECB Loan was preferred by the
petitioner by converting Indian currency loan of ` 300 Crores into
USD loan of 6.67 Crores USD and again reconvert the same into
rupee term loan at the end of 7 years and incurred forex losses and
appropriate the losses so occurred against revenue savings accruing
to them due to the hedging of the ECB Loan. He submitted that the
same is totally an unwarranted exercise of which NHAI is not a party
i.e., no approval was taken from NHAI for the same. The petitioner
also has not produced any approval from NHAI for such ECB loan.
IV. Clause 6(a) of the Deferment Scheme
76. Clause 6(a) of the deferment scheme categorically provides
that the financial stress is only limited to premium payment and
“ not linked to any cash shortfall on account of any O&M
Expenses, debt servicing etc.” Therefore, any stress that is adding to
the project on account of debt servicing, may be on a higher rate,
involving of commissions, on account of various charges etc. is
something which is not to be taken into account to capitulate the
OMP (I) (COMM) 270/2019 Page 43 of 60
financial stress.
77. The subsequent so called alleged forex loss, which is nothing
but a operational loss on account of a contingent liability, cannot be
taken into account to capitulate the financial stress in the project.
The concessionaire cannot be permitted to amend the terms of its
own application, and the subsequent sanction dated June 06, 2014
issued by NHAI to add forex loss as a part of debt service.
V. Relief of Mandatory Injunction
78. He submitted that the deferment granted, by its very nature,
is terminable. As per the original CA, the concessionaire was liable
to pay the premium as per Article 26 of the CA. The NHAI extended
the benefit of deferment of premium in view of the government
scheme in this regard, and the application of the concessionaire and
the subsequent sanction dated June 06, 2014 by the NHAI. The
NHAI has already withdrawn the said grant of deferment and has
called upon the concessionaire to repay the dues as per the CA.
79. By way of seeking interim relief before this Court, the
concessionaire is seeking relief in the nature of mandatory injunction
for a direction to NHAI to continue to grant the benefit of deferment
of premium. In other words, the same is in the nature of seeking
specific performance of deferment scheme, the benefits thereof is
already withdrawn. He submitted that the said relief would be hit by
Section 14 of the Specific Relief Act. In the first instance, the
benefit, by its very nature, is determinable. In any case, if the
concessionaire so feels, it can seek appropriate relief by way of
damages. It is submitted that the petitioner does not have any prima
facie case in its favour. The balance of convenience does not lie in
OMP (I) (COMM) 270/2019 Page 44 of 60
favour of petitioner. No irreparable loss or injury will be caused to
the petitioner if the reliefs sought for is not granted.
80. Having heard the learned counsel for the parties, the first and
foremost issue that arises for consideration is whether the dispute
between the parties is arbitrable under Article 44 of the CA. It was
the submission of Mr. Sethi that, SA is a separate agreement,
governing the deferment of the premium, never intended to be part of
CA. According to him, in the absence of arbitration clause in the SA
the petition is not maintainable.
81. When the CA was executed in the year 2010, the scheme of
Government of India for deferment of premium was not in existence.
It was notified on March 04, 2014. So clause 44 of the CA was
applicable to disputes, differences in relation to CA. But thereafter,
on an application of the petitioner for deferment of the premium
under the scheme was accepted by the NHAI, a SA was executed on
June 06, 2014. I may state here, that Article 47.10 of the CA
specifically requires that any amendment or modification has to be
carried out in writing, so accordingly, the SA was executed. As the
name suggest this SA is to the CA. The SA was necessitated because
the authority agreed with the request of the Concessionaire for
deferment of the premium which stipulation was not existing in the
CA. The following clauses of the SA are of some importance:
“H. Save and except provided in this agreement, the
Scheme and the sanction letter of the Authority dated
6/6/14 the terms and conditions of Concession
Agreement shall remain final and binding on parties.
I. This agreement shall be subject to jurisdiction of
OMP (I) (COMM) 270/2019 Page 45 of 60
Court of Delhi.
NOW THEREFORE, in consideration of the foregoing
and the respective covenants and agreements set forth in
the Concession Agreement dated 16/08/2010, the
Scheme and the letter of the Authority dated 06/06/2014
agreeing to the request of the Concessionaire for
deferment of premium, the receipt and sufficiency of
which is hereby acknowledged, and intending to be
legally bound hereby, the Parties enter into this
Supplementary Agreement to the aforesaid Concession
Agreement on this day.” (emphasis supplied)
82. Clause H stipulates the binding nature of the supplementary
agreement, the scheme, the sanction letter of the authority apart from
the terms and conditions of the CA. So, it follows even with the
execution of the supplementary agreement, the terms and conditions
of the CA, which includes clause 44, continued to be binding, on the
parties. The subsequent clause also clarifies the position that the SA
is to the CA. Hence, it is clear that the SA is part of the CA. Rightly
so, as per Article 26 of the CA, the petitioner was liable to pay the
premium to the respondent authority, but by the SA the payment of
premium has undergone a change.
83. In fact, I note that the sanction letter issued on June 06, 2014
vide clause 4 states that to evidence the deferment of premium and
attendant obligations thereunder, the Concessionaire shall execute a
SA to the CA and the sanction shall be subject to the signing of the
supplementary agreement. The effect of execution of SA is the
OMP (I) (COMM) 270/2019 Page 46 of 60
premium that is paid to the authority under Article 26.2 of the CA
shall get deferred in the manner stated in the SA, i.e., in accordance
with the scheme on terms and conditions conveyed vide letter dated
June 06, 2014. So, any dispute arising with regard to deferment of
premium shall be an issue arising in relation to CA, and as such
arbitrable under Article 44 of the CA. In fact, the above was the
understanding of the respondent as, I have been informed that the
parties resorted to conciliation proceeding under Article 44.2 of the
CA, which resulted in failure. The reliance placed by Mr. Sandeep
Sethi on the judgment of the Supreme Court in the case of M.R.
Engineers and Contractors Pvt. Ltd. (supra) is concerned, in the
said judgment the Supreme Court was concerned with the facts that
the Public Works Department, Government of Kerala entrusted the
work of “four-laning and strengthening of Alwaye-Vyttila and
Aroor-Cherthala and strengthening of Vyttila to Aroor section of NH
47-N2 and N3 packages” which included the work of “construction
of project directorate building for national highway four laning
project at Edapally, Cochin” to the respondent. The said contract
between the Public Works Department and the respondent contained
a provision for arbitration, as per Clause 67.3 of the general
conditions of the contract.
84. The appellant before the Supreme Court is a sub contractor
of the respondent. The respondent entrusted a part of the work
entrusted to it by the Public Works Department, namely,
“construction of project directorate building” to the appellant under
its work order dated May 04, 1994. The appellant alleges that it
informed the respondent that it executed certain extra items and
OMP (I) (COMM) 270/2019 Page 47 of 60
excess quantities of agreed items on the instructions of the Public
Works Department and requested the respondent to make a claim on
the Public Works Department in that behalf; that the respondent
accordingly made necessary claims in that behalf on the Public
Works Department; that the said claims, as also several other claims
of the respondent against the Public Works Department were referred
to arbitration and the arbitrator made an award dated August 18,
1999.
85. According to the appellant, the arbitrator awarded certain
amounts in regard to its claims put through the respondent and in
terms of the arrangement between the respondent and the appellant,
the respondent is liable to pay to the appellant, 80% of the amounts
awarded for such claims. The appellant, thereafter, lodged a claim
on the respondent by letter dated July 05, 2000, for payment of
` 65,11,341/-.
86. As the claim was not settled, the appellant sent a letter dated
December 06, 2000 seeking reference to the disputes to the
arbitration. As the respondent failed to comply, the appellant filed
an application under Section 11 of the Act. According to the
appellant, clause 67.3 of the general conditions of the contract
forming part of the contract between the Public Works Department
and the respondent, providing for arbitration, was imported into the
sub contract between the respondent and the appellants. The
appellant relies upon the term in the work order dated May 04, 1994
that the “sub-contract shall be carried out on the terms and conditions
as applicable to the main contract” to contend that the entire contract
between the department and the respondent, including clause 67.3
OMP (I) (COMM) 270/2019 Page 48 of 60
relating to arbitration, became a part and parcel of the contract
between the parties. The respondent denied the said claim and
contention.
87. The designate of the learned Chief Justice by order dated
January 31, 2003 rejected the application on the ground that the
arbitration clause was not incorporated by reference in the contract
between the respondent and the appellant.
88. The Supreme Court, on an interpretation of Section 7(5) of
the Act of 1996, has summarized its scope and intent in the following
manner:-
“24 (i) An arbitration clause in another document, would
get incorporated into a contract by reference, if the
following conditions are fulfilled : (i) The contract should
contain a clear reference to the documents containing
arbitration clause, (ii) the reference to the other
document should clearly indicate an intention to
incorporate the arbitration clause into the contract,
(iii) The arbitration clause should be appropriate, that is
capable of application in respect of disputes under the
contract and should not be repugnant to any term of the
contract.
(ii) When the parties enter into a contract, making a
general reference to another contract, such general
reference would not have the effect of incorporating the
arbitration clause from the referred document into the
contract between the parties. The arbitration clause from
another contract can be incorporated into the contract
OMP (I) (COMM) 270/2019 Page 49 of 60
(where such reference is made), only by a specific
reference to arbitration clause.
(iii) Where a contract between the parties provides that
the execution or performance of that contract shall be in
terms of another contract (which contains the terms and
conditions relating to performance and a provision for
settlement of disputes by arbitration), then, the terms of
the referred contract in regard to execution/performance
alone will apply, and not the arbitration agreement in the
referred contract, unless there is special reference to the
arbitration clause also.
(iv) Where the contract provides that the standard form of
terms and conditions of an independent Trade or
Professional Institution (as for example the Standard
Terms & Conditions of a Trade Association or Architects
Association) will bind them or apply to the contract,
such standard form of terms and conditions including any
provision for arbitration in such standard terms and
conditions, shall be deemed to be incorporated by
reference. Sometimes the contract may also say that the
parties are familiar with those terms and conditions or
that the parties have read and understood the said terms
and conditions.
(v) Where the contract between the parties stipulates that
the Conditions of Contract of one of the parties to the
contract shall form a part of their contract (as for
example the General Conditions of Contract of the
OMP (I) (COMM) 270/2019 Page 50 of 60
Government where Government is a party), the
arbitration clause forming part of such General
Conditions of contract will apply to the contract between
the parties.”
89. In the said case, the Supreme Court had come to a conclusion
that the arbitration clause between the PWD and the Som Datt
Builders has no applicability to the contract executed between the
parties before the Supreme Court which was a sub contract. Suffice
it would be to state that the facts in the judgment, as relied upon by
Mr. Sethi, are not similar to the one, which arise for consideration in
this case. Hence, the judgment is distinguishable and has no
applicability, more so, in view of my above conclusion.
90. Having said that, the question which arises for consideration
is whether the petitioner is entitled to relief it has sought for in this
petition.
91. It has been contended by Mr. Kirpal that the petitioner has a
prima facie case and irreparable loss shall cause to the petitioner if
the prayer as prayed for is not granted. The prayers made have
already been reflected above. The impugned order dated August 7,
2019 reads as under:
“Sir,
Please refer sanction letter cited under ref (i) above vide
which deferment of premium was sanctioned to the
Concessionaire.
2. As per clause 3 (o) of the approval letter review of
deferred premium was done and the Concessionaire was
requested to remit premium on the basis of review of
premium deferment amounting to Rs.12.74 Cr. for the
year 2014-15 & Rs.4.24 Cr. for the year 2015-16 along
with interest and penal interest.
OMP (I) (COMM) 270/2019 Page 51 of 60
4. Despite several reminders, the premium has not been
remitted by the Concessionaire, instead the
Concessionaire choose to raise the dispute and invoked
arbitration. The Competent Authority decided that the
dispute raised by the Concessionaire does not qualify
under Clause 44 of the Concession Agreement since the
facility of premium deferment is extended to the
Concessionaire under the special scheme of Central
Govt., “Policy of rationalization of premium quoted by
the Concessionaire in respect of highways project” (the
“Scheme”) to benefit highway projects under financial
stress. The above fact was communicated to the
Concessionaire vide NHAI letter cited under ref (ii)
above and requested to remit the demanded premium
amounting to Rs.12.74 Cr. for financial year 2014 -15,
Rs.4.24 Cr. for financial year 2015-16 along with interest
and penal interest at the earliest to avoid default as per
provision of Concession Agreement, failing which NHAI
will be considering revocation of premium deferment on
account of default in adhering to the terms and conditions
and may also initiate other action as per Concession
Agreement. However, the above demanded premium
has not been remitted by Concessionaire.
4. The Competent Authority has now decided to withdraw
the deferment of premium and the Concessionaire is
requested to remit the balance outstanding premium as
per Concession Agreement (including deferred premium)
along with interest as per provision of Concession
Agreement to avoid concession default.
This issue with the approval of Competent Authority.”
92. From the above, it is seen that the respondent has decided to
revoke the premium deferment scheme as sanctioned on account of
default of the petitioner to remit the demanded premium and
amounts of ` 12.74 Crores (for the financial year 2014-2015) and
` 4.24 (for the financial year 2015-2016) along with interest and
penal interest.
OMP (I) (COMM) 270/2019 Page 52 of 60
93. Further the question that would arise is whether the
petitioner is liable to pay amount of ` 12.74 Crores and ` 4.24 Crores
along with interest and penal interest and on failure to pay the same,
whether the respondents are within their right to revoke the
premium deferment scheme as sanctioned vide letter dated June 6,
2014. .
94. The submissions made by Mr. Kirpal can be noted as the
following:
A. The Scheme of Deferment is not a special / extra contractual
sanction, but rather in terms of Article 28 of the CA.
B.
The intent of the scheme is that revenue from the Project
can be used for satisfying the operation and maintenance
cost and debt servicing.
C. During this period, the concessioner is not permitted to
appropriate for itself any toll revenues.
D. The petitioner made an application for deferring the
payment of premium for the specific years till 2024 after
which year from 2024-2025 till financial year 2029-2030 all
the deferred premiums along with interest @ 2% bank rate
shall be paid by the petitioner in agreed tranches.
E. Clause 3(b) of the sanction letter provided that till the
amounts of deferred premiums are repaid or recovered, the
deferred amount shall at all times carry an interest rate equal
to 2% of the bank rate per annum.
F. Clause 3 (o) provided that if the revenue deficit as actually
seen on review at the end of the year is lesser than by more
than 5% of the figures projected, the petitioner will be liable
OMP (I) (COMM) 270/2019 Page 53 of 60
to pay a penalty of 2.5% additional interest over and above
the normal interest of bank rate + 2% on the said excess.
G. On a plain reading of the clauses, the petitioner was entitled
to pay the entire deferment premium amount on or after the
financial year 2024-2045, i.e., the period of deferment.
H. Nowhere do the terms of the agreement require / provide
that in the event of such excess revenue the petitioner was
liable to forthwith pay additional premium.
I. The liability that accrued about determination of such
revenue excess was to bear more interest over the total
deferred premium and no additional premium was to be paid
forthwith.
J. The payment of additional premium amount would result in
a reduction in the total deferred premium to be paid with
interest after 2024 and if such additional premium is not
paid, then when the total deferred premium is paid with
normal interest, the petitioner shall be liable for additional
interest because there could be no change in the total
deferred premium amount payable.
K. The nature of scheme is that the interest and the principal,
i.e., the deferred premium was not payable immediately and
no inference can be drawn that it was a contractual
obligation to pay additional premium upfront upon
determination.
L. The demand of the respondent for payment of ` 12.74 Crores
and ` 4.24 Crores along with normal interest and penal
interest in terms of Clause 3 (o) of the sanction letter being
OMP (I) (COMM) 270/2019 Page 54 of 60
alleged lesser revenue shortfall / revenue excess is in breach
of the terms of the contract.
M. The respondent has not considered the foreign exchange
losses which form part of the debt servicing.
N. Assuming that there is more than 5% shortfall in revenue
deficit even then as per the plain language of clause 3 (o),
there is no provision requiring the petitioner to upfront /
forthwith pay the additional premium.
O. When the scheme of deferment itself requires that the
principal and the interest is to be paid only after 10 years,
which is the period of deferment, then clause 3 (o) can by no
stretch of imagination be construed as a liability of the
petitioner to pay additional premium or normal interest and
penal interest forthwith or prior to the said 10 years period.
95. Similarly, the submissions made by Mr. Sethi in support of
the impugned order can be summed up as under:
A. Clause 6 (a) of the Deferment Scheme categorically
provides that the financial stress is only limited to premium
payment and not linked to any cash shortfall on account of
any O & M expenses, debt servicing etc.
B. The concessioner included only two components as par part
of debt servicing (a) interest payment and (b) principal
payment.
C. As per clause 3 (o) of the sanction letter, dated June 6, 2014,
issued by the NHAI in case of revenue deficit at the end of
the year is lesser by more than 5% of the figures given
under the projects now being considered, petitioner shall be
OMP (I) (COMM) 270/2019 Page 55 of 60
liable to pay penalty of 2.5% additional interest over and
above the normal interest of bank rate + 2% on the said
excess.
D. Admittedly, the petitioner retains the amount of ` 12.74
Crores and 4.24 Crores despite demand by the NHAI and
did not even pay the interest and penal interest thereon, thus
committed default.
E. The non-payment of excess amount, interest and penalty
interest by petitioner amounts to default.
F. The petitioner is enjoying the excess amount without paying
the penalty as contemplated in clause 3(o). Merely
expressing its willingness to pay the interest, penalty interest
and not actually paying anything, the same does not
exonerate the petitioner from being in default.
96. Having summed up the submissions made by the counsel for
the parties, this court having said that the dispute between the
parties is arbitrable is conscious of the fact that the issue which
falls for consideration is only a petition under Section 9 of the Act
of 1996 and the main issue needs to be decided by the Arbitral
Tribunal so constituted. But pending decision by the Arbitral
Tribunal, is the petitioner entitled to the relief as prayed for.
97. From the above, it is seen that both the parties have tried to
justify each other‟s stand. Surely, on a prima facie finding, this
Court can grant such relief, which will prevail till the matter is
decided by the Arbitral Tribunal.
98. The plea of Mr. Kirpal is primarily that the impugned order
has been passed by the respondents on failure on the part of the
OMP (I) (COMM) 270/2019 Page 56 of 60
petitioner to remit the amounts of ` 12.74 crores and ` 4.24 crores
with interest and penal interest.
99. The petitioner has contested the payments sought for on the
ground that they are payable before 2024-25.
100. On the other hand, the respondent has justified the claim of
the amounts by relying on Clause 3(o) of the sanctioned letter. In
fact, they have justified the impugned order on the ground of
failure on the part of the petitioner to pay the amounts by relying
upon Clause 3(p) of the sanctioned letter. Clause 3(o) of the
sanctioned letter reads as under:-
“3(o) If revenue deficit as actually seen on review at the
end of the year is lesser by more than 5% of the figures
given under the projections now being considered, the
concessionaire will be liable to pay a penalty of 2.5%
additional interest over and above the normal interest of
Bank Rate +2%, on the said excess. However if the
Concessionaires effects the required correction and
increases the premium payment so as to have no excess
by the end of the relevant year, no such penalty would be
imposed.”
101. From the perusal of the clause above, it is seen, if the
revenue deficit is lesser by more than 5% of the figures under the
projections at the end of the year “the concessionaire will be liable
to pay a penalty of 2.5% additional interest over and above the
normal interest of Bank Rate +2%, on the said excess.” Similarly,
Clause 3(p) of the sanctioned letter reads as under:-
OMP (I) (COMM) 270/2019 Page 57 of 60
“3(p) Nothing in this sanction shall be construed as
entitling the Concessionaire for any Termination
Payment in excess of what is provided for in the
Concession Agreement dated 16/08/2010. In the event of
any Default in the compliance to the terms and conditions
mentioned herein in this sanction letter, or in the
compliance the terms of concession as mentioned in the
Concession Agreement and the Supplementary
Agreement, NHAI shall be entitled, without prejudice to
its other rights and remedies under the Concession
Agreement, to suspend/ withhold or withdraw this facility
of deferment of premium and demand repayment of all
outstanding liabilities including interest accrued.”
102. From the perusal of Clause 3(p) as well, it is seen that in the
event of any default in compliance of the terms and conditions
mentioned in the sanctioned letter, the NHAI shall be entitled,
without prejudice to its other rights and remedies, under the
Concession Agreement, to suspend / withhold or withdraw this
facility of deferment of premium and demand repayment of all
outstanding liabilities including interest accrued.
103. It is the case of the petitioner that there is no revenue deficit.
The respondent has not considered foreign exchange losses which
form part of debt servicing. It is also its case that assuming that
there is a more than 5% shortfall in revenue deficit, even then
there is no provision requiring the petitioner to upfront / forthwith
pay the additional premium.
OMP (I) (COMM) 270/2019 Page 58 of 60
104. The pleas are unsustainable as clause 6(a) of the deferment
scheme provides that the financial stress is only limited to
premium payment and not linked to any cash shortfall on account
of any O and M expenses, debt servicing etc. Further on a
conjoint reading of Clauses 3(o) and 3(p), it is clear that if the
revenue deficit is less by more than 5% of the figures under the
projections at the end of the year , the consessioner is liable to pay
penalty of 2.5% additional interest over and above the normal
interest of bank rate + 2% on the said excess, which admittedly has
not been paid by the petitioner. Hence, the effect, as laid down in
Clause 3(p) of the sanctioned letter shall come into play. It
precisely for this reason that the impugned action has been taken
105. As stated above, the issue has to be decided through
Arbitration. Pending decision by the Arbitrator / Arbitral
Tribunal, I am of the view that by balancing the equities the only
order that can be passed is that the petitioner shall deposit with the
respondent the amounts of ` 12.74 Crores, ` 4.24 Crores and ` 46.78
Crores along with penalty interest of 2.5% and additional interest
of 2% over and above the normal interest of Bank rate within a
period of four weeks from today as stipulated in clause 3(o) of the
sanction letter. On such deposit the impugned communication
dated August 07, 2019 to the extent that the respondent has
withdrawn the facility of deferment payment shall remain stayed.
106. The amounts deposited by the petitioner shall be kept by the
NHAI in interest bearing FDRs so that the benefits thereof shall
enure to the successful party before the Arbitrator / Arbitral
Tribunal.
OMP (I) (COMM) 270/2019 Page 59 of 60
107. It is made clear that the aforesaid is a prima facie view and
shall be subject to the final adjudication by the Arbitrator / Arbitral
Tribunal.
108. The petition is disposed of.
109. No costs.
V. KAMESWAR RAO, J
/aky/jg
NOVEMBER 25, 2019
OMP (I) (COMM) 270/2019 Page 60 of 60