Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 30
PETITIONER:
INDIAN ALUMINUM COMPANY ETC.
Vs.
RESPONDENT:
KERALA STATE ELECTRICITY BOARD
DATE OF JUDGMENT23/07/1975
BENCH:
BHAGWATI, P.N.
BENCH:
BHAGWATI, P.N.
ALAGIRISWAMI, A.
GOSWAMI, P.K.
CITATION:
1975 AIR 1967 1976 SCR (1) 70
1975 SCC (2) 414
CITATOR INFO :
R 1976 SC 127 (12,14,16,17)
R 1976 SC2414 (33)
R 1982 SC 149 (1095)
D 1986 SC1126 (13,24,25,26,33,34,40,41,45,47
D 1988 SC1989 (12)
R 1989 SC 268 (12, TO, 17,27,28)
RF 1992 SC1033 (15)
RF 1992 SC2169 (12)
ACT:
Electrieity Supply Act (54 of 1948) Ss. 49, 57, 59 and
79(j)-Scope of.
Power of public authority to fetter its discretion-
scope of
Delegated legislation -No power to enhance charges in
Act-If delegate can d by . framing regulation
Interpretation of statutes-Marginal Note use of
HEADNOTE:
Under s. 49(1) and (2) of the Electricity Supply Act,
1948, the legislature has empowered the State Electricity
Board to frame uniform tariffs and has also Indicated the
factors to be taken into account in fixing uniform tariffs
Under. sub-s. (3), the Board may, in the special
circumstances mentioned therein, fix different tariffs for
the supply of electricity, but, in doing so, sub-s. (4)
directs that the Board is not to show undue preference to
any person. Under s. 59 the Board shall not, as far as
practicable carry on its operations at a loss and shall
adjust its charges accordingly from time to time.
Certain consumers of electricity had entered into
agreements for the supply of electricity for their
manufacturing purposes at specified rates for specified
periods . Some of the agreements were entered into with the
State Governments and the others with the State Electricity
Boards. In one of the agreements there was an arbitration
clause. On account of the increase in the operation and
maintenance cost, due to various causes which caused loss to
the State Electricity Boards, the Boards wanted to increase
the charges in all the cases. the consumers challenged the
competency of the Boards to do so by petitions in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 30
respective High Courts. The High Court sustained the Boards
claim, in some cases, under Ss. 49 and 59, and in others,
held that the Board was incompetent to do so. In the case of
the consumer where there was the arbitration clause, the
High Court refused to entertain the petition on account of
the clause.
In appeals to this Court by the aggrieved consumers
and the Boards
^
HELD: (1) The agreements with the State Governments
must also be treated as agreements entered into with ’the
Boards. Section 60 of the Act provides that all contracts
entered into by or with the State Government for any of the
purposes of the Act, shall be deemed to have been entered
into by or with the Board. One of the primary purposes of
the Supply Act is to provide For the supply of electricity.
An agreement for supply of electricity to a consumer is.
therefore, an agreement for one of the purposes of the
Supply Act and s. 60 has application to such an agreement.
[78G-H]
2(a) Fixation of special tariffs under s 49(3) can be
a unilateral Act on the part of the Board but more often it
would be the result of negotiations between the Board and
the consumer and hence a matter of agreement between them.
Therefore, the Board can, in exercise of the power conferred
under the sub-section, enter into an agreement with a
consumer stipulating for special tariff for supply of
electricity for a specific period of time. The agreements
for supply of electricity to the consumers must therefore be
regarded as having been entered into by the Boards in
exercise of the statutory power conferred under s. 49(3).
[81E-F. H-82B]
71
(b) When a public authority is entrusted by a statute
with a discretionary power to be exercised for the public
good, it cannot, when making a private contract in general
terms, fetter itself in the use of that power or in the
exercise of such discretion. This principle is attracted
when an attempt is made to fetter in advance the future
exercise of statutory powers otherwise than by ’the valid
exercise of a statutory power. Where a statutory power is
exercised to enter in o a stipulation with a third party
which fetters the future exercise of other statutory powers,
where such stipulation is made, not as part of a private
contract in general terms, but in exercise of a statutory
power. he exercise of the statutory power would not be held
to be invalid as a fetter on the future exercise of other
statutory powers. If it were so held, it would render the
statutory power meaningless and futile. Therefore, where a
stipulation in a contract is entered into by a public
authority in exercise of a statutory power, then, even
though such stipulation fetters the subsequent exercise of
the same statutory power or future exercise of another
statutory power it would he valid and the exercise of such
statutory power, would protanto stand restricted. The public
authority would not, in such a case. be free to denounce the
stipulation as a nullity and claim to exercise its
statutory power in disregard of it. except, where there is
an overriding statutory provision which, expressly or by
necessary implication, authorises the public authority to
set at naught in certain circumstances, a stipulation though
made in exercise of :1 statutory power. [82E-F; 83F-G; 84F-
G; 85A-C, E]
Ayer Harbour Trustees Oswald, 8 A.C. 623, York
Corporation v. Henry Leetham and Sons, [1924] 1 Ch. 557,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 30
Straffordshire & Warcestershire Canal Navigation v.
Birmingham Canal Navigation, 1866 L.R. I H.L. 254,
Southendon-Sen Corporation , v. Hodgson (Wickford) Ltd.
[1961] 2 All. E.R. 46, Southport Corporation v. Birkdale
District Electric Supply Co. [1925] 1 Ch. 794 Commissioners
of Crown Lands v. Page [1960] 2 All. E.R. 726 and Dowty .
Boulton v. Wolverhempton, Corporation, [1971] 2 All. E.R.
277, referred to.
(c) In the present ease, ‘the agreements were entered
into with the consumers in exercise of the statutory power
to fix special tariffs under s. 49(3) and therefore there
could be no question of such stipulation being void as
fettering or hindering the exercise of the statutory power
under that provision These stipulations did not divest the
Board of its statutory power or fetter or hinder its
exercise. In fact, they represented ’he exercise of the
statutory power Once the agreements were made containing the
stipulations they were binding as having been validly made
in exercise of the statutory power, and it was not competent
to the Board to override them. The Board could not enhance
the charges in breach of these stipulations, for that would
negate the existence of the statutory power in the Board
under s. 49(3 ) to fix the charges for a specific period
of time. [85E-86B]
(d) The Board was also not competent to enhance the
charges under the guise of fixing uniform tariffs because,
sub-s. (1) of s. 49 is subject to sub-s (3) and once special
tariffs were fixed under sub-s. (3) there could be no
question of fixing uniform tariffs applicable to the
consumer under sub-s. (1) . Such .. power could not be
exercised in derogation of the stipulation fixing special
tariffs under sub-s (3). [86B-C]
(e) If the stipulations as to charges were not binding
and the Board could enhance the charges unilaterally in
disregard of them the consumer would also be free to
repudiate the stipulations. ’the stipulations as to charges
are inseverable from the rest of the agreements and if
"these stipulations are disturbed and the charges are
revised unilaterally by the Board the agreements could no.
bind the consumer. [86C-E]
(f) Further, on the contention of the Board i would be
impossible for a consumer to enter into an agreement with
the Board for supply of electricity at a certain specified
rate. But ’that could not have been intended by the
legislature because, far from promoting the object of
electric development and industrial growth in the State it
would act as a regressive factor. [86E-F]
3 (a) A marginal note to a section cannot afford any
legitimate aid to the construction of the section but it can
be relied upon as indicating the drift
72
of the section to show what the section was dealing with.
The marginal note to s. 59 reads ’General Principles for
Board’s finance’. This shows that the section is intended to
do no more than to lay down general principles for the
finance of the Board. It merely enunciates certain
guidelines which the Board must follow in managing its
finance. [86H-87B]
(b) Under the section the Board is directed as far as
practicable not to carry on its operations at a loss and to
adjust its charges accordingly from time to time. The
legislature has deliberately and advisedly used the word as
far as practicable," because, since the Board is a statutory
authority charged with the general duty of promoting
coordinated development of general on supply and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 30
distribution of electricity within the State, with
particular reference to such development in areas not for
’the time being served or adequately served by any licensee,
it might suffer loss in carrying on its operations, as it
might have to give special tariffs to consumers in
undeveloped or sparsely developed areas, and sometimes to
industrial consumers for accelerating the to of industrial
growth, even though such special tariffs might not be
sufficient to meet the cost of generation, supply and
distribution of electricity. [87B-E]
(c) Where, by a stipulation validly made under s. 49(3)
the Board under a contractual obligation not to charge
anything more then a specified tariff it would not be
practicable for it to enhance its charges if it finds that
is is incurring operational loss. To do something contrary
to law in violation of a contractual obligation, can never
be regarded as ’practicable’. the Board can adjust its
charges under s. 59 only in so far as the law permits it to
do so, that. is, where it is not fettered by a contractual
stipulation from doing
(4) (a) Under s. 57 of the Act a Iciness can,
notwithstanding any agreement entered into with the
consumer, enhance the charges for sale of electricity in
order to earn a reasonable return by way of profit. The
difference in language between s. 59 and s. 57 shows that s.
59 does not confer any power on the Board to enhance the
charges for supply of electric y in disregard of a
contractual stipulation entered into under s. 49(3). [87G-
88C]
(b) The 6th Schedule of the Act is, by a fiction
enacted in s. 57, deemed to be incorporated in the licence e
of every licensee and it enables the Licensee to adjust its
charges for the sale of the electricity by enhancing them so
that it earns a reasonable return as profit; but the
definition of ’licensee’ in s. 2(6) does not include the
State Electricity Board. it has been expressly taken out of
the category of licensee for the purpose of the Supply Act.
[99C-E]
(5) (a) The cost is not the sole or only criterion for
fixing tariff. [87E-F]
Maharashtra State Electricity Board v. Kalyan Borough
Municipality [1968] 3 S.C.R. 137, followed.
(b) There may be certain consumers who may have to be
supplied electricity at special tariff less than the cost,
having regard to the geographical area or the nature or
purpose of the supply. That is why the adjustment of the
charges would have to be left to the discretion of the Board
to be made in such manner as it thinks fit, and since cost
is not the sole or only criterion for fixing tariff, the
Board would be free not to enhance the charges in case of
some consumers even though such charges may be less than
their costs. If that be so, it must follow, a fortiorari,
that there is nothing in s. 59 which requires the Board ’to
enhance the charges in a case where it has bound itself by a
contractual stipulation not to claim anything more than
certain specified charges. [88C-E]
(6) If the power to enhance the rates unilaterally in
derogation of the contractual stipulation does not reside in
any provision of the Supply Act it cannot be created by
regulations under s. 79(j) of the Act. Either this power can
be found in some provisions of the Supply Act or it is not
there at all. Regulations, in the nature of subordinate
legislation, cannot confer authority on the Board to
interfere with contractual rights and obligations unless the
73
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 30
power to make such regulations is vested in the Board by
some provision of the statute expressly or by necessary
implication. Therefore, it would not make any difference
whether or not the Board has made any regulations under .
79(j). [92H-93B]
(7) The arbitration clause provided that "any dispute
or difference arising between the consumer and the supplier
o, their respective electric engineers, as to the supply of
electrical energy hereunder or the pressure thereof as as
to the supplier or the consumer respectively to determine
the same or any question, matter thing arising hereunder
shall be referred to a single arbitrator who shall be
mutually agreed upon by both parties".
The claim of the Electricity Board to enhance the
charges under ss. 49 and 59 and the 6th Schedule to the
Supply Act, is not a question matter or thing arising under
the agreement is a claim founded on the provisions of the
Supply Act and such a claim falls outside the ambit of the
arbitration provision. [98E-H]
(8) (a) But since the Board also claimed that it has
the power to claim the additional levy under another clause
of the agreement, which provided that the. tariff and
conditions of supply mentioned in the agreement shall be
subject to any revision that may be made by the supplier.
The question whether the Board had power under that clause
to enhance the charges is a question arising under the
agreement. All the contentions raised by the consumer
against the claim of the Board are also covered by the
arbitration agreement, and therefore, there is no reason why
the consumer should not pursue he remedy of arbitration and
instead invoke the extraordinary jurisdiction of the High
Court under t. 226. [99F-100E]
(b) When an authority takes action which is within its
compence, it cannot be held to be invalid merely because it
purports to be made under a. wrong provision, if it can be
shown to be within its power under any other provision. The
Board claimed originally power under ss. 49 and 59 and the 6
h Schedule of the Supply Act, but if it has power under a
clause of the agreement, the enhancement could be justified
by reference to that power.
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeals Nos. 1457
& 1642 of 1971.
From the judgment and order dated 19th August, 1971 of
the Kerala High Court in O.P. Nos. 2827 & 1288 of 1970
respectively.
CIVIL APPEALS Nos. 1652-1654 of 1974.
Appeals by special leave from the judgment and order
dated the 27th March, 1974 of the Orissa High Court in
O.J.C. Nos. 357, 605 and 527 of 1971.
S. V. Gupte (In C.A. No. 1457/71) G. B. Pai (In C.A.
No. 1642/ 71) Ajay Ray and P. Mathai, (In C.A. No 1457/71)
O.C. Mathur K.J. John and J. B. DadachanJi, for the
appellants (In C.As. Nos. 1457 & 1642/71).
Lal Narain Sinha, Solicitor General (In C.A. No.
1457/71) A. G. Pudissery, for the respondents (In C. As.
Nos. 1457 & 1642/71).
Sumitra Chakravarty (In C.A. No. 1652/74) B.
Parthasarthy, for the appellants (In C.A. Nos. 1652/74).
A. K. Sen, B. Sen, Ranjit Mehanty, Ajay Ray, O. C.
Mathur, K J; John and J. B. Dadachanji, for the respondent
(In C.A. Nb.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 30
74
K. R. Chowdhary and K. Rajendra Chowdhry, for the
intervener. Andhra Pradesh Electricity Board.
G. L. Sanghi , P. V. Kapur and U. K. Khaitau, for the
applicatintervener-Ferro Alloys Corporation.
S. V. Gupte (In C.A. No. 1654174) and Vinoo Bhagal, for
the appellant (In C.As. Nos. 1653-1654/74).
The Judgment of the Court was delivered by
BHAGWATI, J.-The short but important question which
arises for determination in this appeal is whether a State
Electricity Board has power to enhance the rates for supply
of electricity notwithstanding an agreement binding it to
supply electricity at certain rates where it finds that the
contractual rates arc less than the cost of generation,
distribution and supply of electricity and in the result
there is loss to the State Electricity Board in its
operations? In order to appreciate how the question arises,
it is necessary to state a few facts giving rise to the
appeal.
The petitioner is a limited liability company which
carries on business of manufacturing aluminium. The
manufacture of aluminium involves three processes, viz.,
mining of bauxite ore, dressing it and converting it into
alumina and reduction of alumina into aluminium. The
petitioner carried on bauxite mining at the quarries in
Bihar and also set up its factory in Bihar for dressing
Bauxite ore and converting it into alumina. So far as the
process of reducing alumina into aluminium is concerned, it
involves the application of the method of electrolysis ill
which electrical energy is a primary raw material and,
therefore, the petitioner was anxious to set up a factory
for this purpose at a place where electric power would, be
cheap. The Government of the then native State of Travancore
offered to supply electric power to the petitioner at
reasonable rates for a long period of time if the petitioner
established its factory for reducing alumina into aluminium
within its territory. An agreement dated 30-7-41 was
accordingly entered into between the petitioner and the
Government of the State of Travancore for supply of
electrical energy at certain rates for period of 34 years
from 1-7-41 with an option of renewal in favour he
petitioner for a further period of 20 years. In view of this
agreement, the petitioner established a factory at Alupuram
near Alwaye fol. reducing alumina and converting it into
aluminium, though alumina for this purpose had to be brought
all the way from Bihar and the aluminium produced at the
factory had to be transported outside the State of
Travancore for the purpose of sale.
On the integration of the States of Travancore and
Cochin, a new state of Travancorc-Cochin was formed in 1948
and the agreement 30-7-41 (hereinafter referred to as the
Principal Agreement) was accepted by the new State as
binding upon it. The terms and conditions of supply of
electrical energy laid down in, the Principal Agreement
were, however, varied and modified by a supplemental
agreement (hereinafter referred to as the first
Supplemental Agreement) dated
75
16-8-1955 entered into between the petitioner and the State
of Travancore-Cochin on 1-1-1956 a new State of Kerala was
formed comprising inter alia the territories of the existing
State of Travancore Cochin, barring a small portion
transferred to the State of Madras under the States
Reorganisation Act 1956, and by reason of section 87 of that
Act, the Principal Agreement as modified by the First
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 30
Supplemental Agreement was deemed to have been made in the
exercise of executive power of the State of Kerala and all
rights and obligations under it became the rights and
obligations of the State of Kerala. The Kerala Government
thereafter by a Notification issued urbder section 5, sub-
section (1) of the Electricity Supply Act, 1948 (hereinafter
referred to as the Supply Act), constituted the Kerala State
Electricil. Board (hereinafter referred to as the Board)
with effect from 1-4-57. Section 60 of thc Supply Act
provides, inter alia that all the contracts entered into by
or with the State Government for any of the purposes ot the
Act before the firsl constitutionl of the Board shall be
deemed to have been entered into by or with the Board. The
Principal Agreeement as modified by the First Supplemental
Agreement was, therefore. deemed to have been entered into
with the petitioner by the Board. The terms and conditions
of agreement were subsequently modified under another
supplemental agreement (hereinafter referred to as the
Second Supplemental Agreement) dated 4-4-1963 entered into
between the petitioner and the Board. This modification did
not affect either the rates or the duration of the Principal
Agreement.
It appears that the petitioner required additional
electric power for expansion of the operations of its
alumina reducing factory and an agreement dated 30-3-1963
(hereinafter referred to as the Second Agreement) was,
therefore, entered into between the petitioner and the Board
whereby the Board agreed to supply to the petitioner from
1965 a total of 12500 Killowatts of electric power at the
rates and on the terms and conditions set out in the
agreement. The duration of this agreement was 25 years from
1-1-1965 with an option to the petitioner to renew it for a
further period of 25 years. Another agreement (hereinafter
referred to as the Third Agreement) was entered into between
the petitioner and the Board on 18-9-1965 for supply of
further 12500 k.w. Of electric power at certain rates for a
period of 25 years from 1-1-1966 with an option of renewal
in favour of the petitioner for a further period of 25 years
on the same terms and conditions.
Whilst these agreements were in force, the Board framed
the Kerala State Electricity Board (General Tariffs)
Regulations 1966 in exercise of the powers conferred under
section 79 (j) read with sections 49 and 59 of the Supply
Act. Regulation 4 empowered the Board to prescribe different
terms and conditions for different classes of consumers and
Regulation 6 provided that the Board may fix different
tariffs for different classes of services under various
heads. The Board was conferred power under Regulation 10 by
Notification or otherwise to fix special terms and
conditions fol. supply for special purposes and‘ under
Regulation 11 the Board could amend the terms and conditions
of supply from time to time. These Regulations were amended
by
76
the Board by making the Kerala Electricity Board (General
Tariffs) (Amendment) Regulations, 1969. By the amendment
Regulations 6 and 8 were substituted by a new Regulation 6
which empowered the Board to fix different tariffs for
different classes of services under the broad heads, low
tension supply, high tension supply and extra high tension
supply. Now it appears that since September 1965, when the
last revision of tariffs was made by the Board, there was a
steep rise in "prices of all commodities including plant and
equipment, construction materials, etc. salary and wages of
employees" thereby increasing the operation and maintenance
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 30
cost of the Board with the result that the Board found
itself in a position where it was working at a loss. Section
59 of the Supply Act enjoins the Board that "it shall not,
as far as possible, carry on its operations under this Act
at a loss and shall adjust its rates accordingly from time
to time". The Board, therefore, in exercise of the power
conferred under section 49 of the Supply Act and the
Regulations, "and other enabling provisions in the Statute",
issued an order dated 28-11-1969 called "Kerala State
Electricity Board Extra High Tension Tariff order 1969"
fixing the rates Or tariffs for supply of electric power to
all extra high tension consumers-a category which included
the petitioner. Clause (6) of this order provided that the
rates or tariffs fixed by it shall apply "to all extra high
tension consumers" notwithstanding anything to the contrary
contained in any agreement entered into with any extra high
tension consumer either by the Government or by the Board or
anything the tariff Regulations or Rules previously issued".
The result was that despite the Principal Agreement, the
Second Agreement and the Third Agreement, which were in
force, the Board claimed to be entitled to recover from the
petitioner the rates or tariffs fixed by this order. though
they were manifestly higher than the rates or tariff
stipulated in these respective agreements. The petitioner
thereupon filed a writ petition in the High Court of Kerala
challenging the validity of this order but the challenge
failed. The High Court sustained the order on the ground
that it was within the competence of the Board under
sections 49 and 59 of the Supply Act. This view is assailed
in the present appeal brought with certificate obtained from
the High Court. F
Before we proceed to consider the question which arises
for determination in this appeal, it will be convenient at
this stage to refer to a few relevant provisions of the
Supply Act for this is the statute with which we are
concerned in this appeal. The Supply Act, as its preamble
and long title show, is enacted "to provide for the
rationalisation of the production and supply of electricity
and generally for taking measures conducive to electrical
development". That is the object and purpose of the Statute
and this object and purpose is sought to be achieved by the
establishment of the Central Electricity Authority and State
Electricity Boards charted with certain functions, powers
and duties. Section 5 (1) provides that the State Government
shall, as soon as may he after the issue of the notification
under section 1(4) bringing into force the various
provisions of the Act, "constitute by notification in, the
official Gazette a State Electricity Board under such name
as shall ba specified in the notification". Chapter TV sets
77
out the powers and duties of the State Electricity Board.
Section 18, which is the first section in that chapter
enumerates duties, which also) represent the function, of
the State Electricity Board. It Says, to quote the words of
the section: "Subject to the provisions of this Act the
Board shall be charged with the general duty of promote the
coordinated development of the generation, supply and
distribution of electricity within the State in the most
efficient and economical manner, with particular reference
to such development in areas not for the time being served
or adequately served by any licensee, and without prejudice
to the generality of the foregoing provisions it shall be
the duty of the Board-(a) to prepare and carry out schemes
sanctioned under Chapter V; (b) to supply electricity to
owners of controlled stations and to licensees whose
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 30
stations are closed down under this Act; (c) to supply
electricity as soon as practicable to any other licensees or
persons requiring such supply and whom the Board may be
competent under this Act so to supply." Then follow other
sections in that Chapter which deal with the powers of the
State Electricity Board. They are not material and we need
not refer to them. Chapter V is headed "The Board’s Works
and Trading Procedure". It contains the fasciculus of
sections dealing with making of a scheme for all area "with
a view to rationalising the production and supply of
electricity‘’ in that area. Then there are other sections,
not relevant for our purpose, which speak of controlled
stations and generating stations, provide for supply of
electricity by the State Electricity Board to a licensee and
lay down the mode of fixation of grid tariff. Section 49
enacts a provision for sale of electricity by the State
Electricity Board to a person other than a licensee. It
reads:
"(1) Subject to the provisions of this Act and of
regulations, if any, made in this behalf the Board may
supply electricity to any person not being a licensee
upon such terms and conditions as the Board thinks fit
and may for the purposes of such supply frame uniform
tariffs.
(2) In fixing the uniform tariffs, the Board shall
have regard to all or any of the following factors,
namely-
(a) the nature of the supply and the purposes for
which it is required;
(b) the co-ordinated development of the supply
and distribution of electricity within the
State in the most efficient and economical
manner, with particular reference to such
development in areas not for the time being
served or adequately served by the licensee:
(c) the simplification and standardisation of
methods and rates of charges for such
supplies;
(d) the extension and cheapening of supplies of
electricity to sparsely developed areas.
(3) Nothing in the foregoing provisions of this
section shall derogate from the power of the Board, if
it considers
78
it necessary or expedient to fix difference tariffs for
the supply of electricity to any person not being a
licensee, having regard to the geographical position of
any area, the nature or the supply and purpose for
which supply is required and any other relevant
factors.
(4) In fixing the tariff and terms and conditions
for the supply of electricity, the Board shall not show
under preference to any person."
Chapter VI deals with "The Board’s Finance Accounts and
Audit’. the first section in this Chapter, which is
material, is section 59 which is in the following terms:
The Board shall not, as far as practicable and
after taking credit for any subventions from the State
Government under section 63, carry on its operations
under this Act at a loss, and shall adjust its charges
accordingly from time to time."
Then comes section 63 which provides inter alia that
"all contracts" contracts into by, with the State Government
for any of the purposes of this Act before the first
constitution of the Board shall be deemed to have been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 30
entered into by, with the Board". Lastly, section 63
empowers the State Government with the approval of the State
Legislature, from time to time to ’make subventions to the
Board for the purposes of this Act on such terms and
conditions as the State Government may determine".
Now, in the present case, as we have already seen,
there are three main agreements entered into by the
appellant for purchase of electricity. True, the Principal
Agreement, as modified by the First Supplemental Agreement,
was not entered into with the Board, but as pointed out
above, by reason of section 60 of the Supply Act, it must be
deemed to have been entered into by the appellant with the
Board and in view of the legal fiction, all the consequences
and incident must follow as if it were an agreement made
with the Board. The learned Solicitor General, appearing on
behalf of the Board. contested the applicability of section
60 on the ground that the Principal Agreement, as modified
by the First Supplemental Agreement, was not an agreement
entered into by the State Government "for any of the
purposes of this Act". but we do not think this contention
is sound. One of the primary purposes of the Supply Act is
to provide inter alia for the supply of electricity: in
fact, the Supply Act empowers the Board to supply
electricity to any person other than a licensee. An
agreement for supply of electricity to a consumer is.
therefore. plainly and indubitably an agreement for one of
the Purposes of the Supply Act and section 60 has clearly
application to such an agreement. The Principal Agreement,
as modified by the First Supplemental Agreement. must, there
fore, for all the purposes of the Supply Act be treated as
an agreement entered into with the Board. So far as the
second and the third agreements are concerned, there is no
question of invoking section
79
60, as they have been entered into by the appellant with the
Board from the very beginning. The question is whether the
Board is entire to override the supulation as to charges
contained in these agreements and enhance the charges by
unilateral action as it has purported to do.
The Board relied principally on two provisions of the
Supply Act, namely, section 49 and 59, in support of its
claim to increase the charges unnaterally despite the
stipulation as to charges contained in the three agreements.
Taking firstly its stand on section 49, the Board contended
that under this section the Legislature has entrusted to it
the power to fix charges-described in the section as
tariffs-for supply of electricity to any person other than a
licensee. Now this power is exercisable not once and for
all, but from Lime to time as action requires or
circumstances justify. It was urged that the exercise of
this power is conditioned by the statutory obligation of
"promoting the coordinated development of the generation,
supply and distribution of electricity within the State in
the most efficient and economical manner" and in order to
run its undertaking economically, that is without Joss the
Board is entitled to refix the charges in exercise of this
power indeed, it is statutorily bound to do so. In any
event, contended the Board, the powers and duties duties by
the Supply Act, the power to fix charges under section 49
being one of them, are for public good and they are intended
to further the object of promoting the production and supply
of electricity which is a matter of public utility and hence
in public interest. It is, therefore, not competent to the
Board to enter into a stipulation with the consumer binding
it not to charge anything more than a specific rate and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 30
thereby divest itself of the power to fix and refix charges
entrusted to it under section 49, or fetter or hinder its
future exercise. Such a stipulation is void and it does not,
ran the argument, stand in the way of the Board enhancing
unilaterally the charges for supply of electricity. This
argument was sought to be supported by the Board by relying
on two decisions of English courts, namely, Ayer Harbour
Trustees v. Oswald(1) and York Corporation) v. Henry Leetham
& Sons(2) Simulataneously section 59 was also invoked in aid
by the Board. It was pointed out that the opening words of
section 49(1) made the power to fix charges conferred on the
Board subject to section 59, and therefore, the mandate of
the Legislature contained in section 59 must prevail over
anything that is done by the Board in exercise of this
power. Section 59 enjoins that the Board shall not, as far
as practicable, carry on its operations at a S loss and
shall adjust its charges accordingly from time to time.
Notwithstanding the fixation of charges under section 49,
therefore, the Board is entitled to enhance the charges if
it finds that it is necessary to do so in order to avoid
operating at a loss. In any event, the Board cannot by
stipulation in a contract bind itself to refrain from
exercising the statutory power which it possesses under
section 59 to enhance the charges in case of operational
loss. The statutory power cannot be bartered away by a
contractual stimulation. If it were held permissible to the
Board to bind itself by a contractual stipulation not
80
to enhance the charges even though such charges result in
operational loss, public interest would suffer since the
production, distribution and supply of electricity would be
prejudicially affected and electrical development in the
State would receive a serious set back. On these two grounds
the Board urged that, since it was incurring loss in its
operations, it was entitled unilaterally to revise the
charges so as to avoid such loss, notwithstanding that under
the stipulation contained in the K three agreements it was
bound to supply electricity to the appellant at certain
fixed charges. Let us examine whether either of these two
grounds is well-founded.
Turning first to section 49, we may point out that
prior to its amendment by the Electricity (Supply) Amendment
Act, 1966, this section was in a different form. On an
interpretation of the unamended section the High Court of
Bombay took the view, in a case relating to the Kalyan
Municipality, that it did not give power to the Board to fix
uniform tariffs as to cast a higher burden on the consumer
in a compact area where the cost of supply was less than on
the consumers in a sparse area where the cost of supply was
more owing to higher distribution cost. This case was taken
in appeal by the Maharashtra State Electricity Board, but
before the appeal could be decided by this 1 Court, the
Parliament enacted the Amending Act substituting the present
section 49 for the old one with retrospective effect. The
appeal had, therefore, to be decided by reference to the
amended section 49 and having regard to that section, as
amended, this Court held that the Board had power to fix
uniform tariffs both for consumers in compact areas as well
as consumers in sparse areas. This Court, interpreting the
amended section 49, pointed out:-
"In s. 49 as it now stands, the Legislature has
empowered the Board to frame uniform tariffs and it has
also indicated the factors to be taken into account in
fixing uniform tariffs. These two aspects are contained
in sub-ss. (1) and (2). The Legislature has also made
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 30
it clear in sub-s. (3) that the Board, in the special
circumstances mentioned therein, has got power to fix
different tariffs for the supply of electricity. Sub-s.
(4) directs the Board not to show undue preference to
any person for fixing the tariffs and the term and
conditions for the supply of electricity. Though prima
facie it would appear that sub-s. (4) will govern sub-
ss. (1) to (3) in s. 49. the proper way to interpret
sub-s. (4) will be to read it along with sub-s. (3).
The question of the Board showing undue preference
to any Person in fixing the tariffs and terms and
conditions for supply of electricity will not arise
when the Board frames uniform tariffs under sub-ss. (1)
and (2). When the entire tariff is uniform for every
consumer, there is no question of any undue preference
as every customer will pay the same amount for the same
benefit received by him. Sub-s (3) of s. 49 recognises
the power of the Board to fix different
81
tariffs for the supply of electricity and it is really
here, if at all, that an occasion for any undue
preference being shown, may arise. Therefore, in our
opinion, sub-s. (4) will control the action of the
Board under sub-s. (3) of s. 49."
It would be seen that sub-s. (1) of s. 49 empowers the Board
to fix uniform tariffs. the fixation of uniform tariffs need
not necessarily be regionwise or areawise, nor need it be
only in respect of particular classes of consumers. There is
no limitation on the exercise of the power of fixing
uniforms tariffs save that certain factors are laid down in
sub-s. (2) of s. 49 which have to be taken into account by
the Board in fixing uniform tariffs. These factors guide and
control the exercise of the power of the Board. But, even
where uniform tariffs are fixed for a particular category of
consumers, the application of uniform tariffs to all
consumers falling within the category irrespective of their
distinctive features, may sometime defeat the object of
promotion of electrical development and industrial growth
and progress. There may arise individual cases there, there
regarded to special circumstances, it may be found necessary
to take departure from the uniform tariffs and to fix
special tariffs for them. Sub-s. (3) of s. 49, therefore,
provides that the Board shall have the power,. if it
considers it necessary or expedient to fix different tariffs
for the supply of electricity to any. person not being", ;
licensee, having regard to the geographical position of any
area, the nature of the supply and purpose for which supply
is required and any other relevant factors". This sub-
section confers power on the Board to fix special tariff for
a consumer if the geographical position of the area, the
nature of the supply, the purpose for which supply is
required and other relevant factors so warrant. Now,
fixation of special tariffs can be a unilateral act on the
part of the Board, but more often than not it would be the
result of negotiation between the Board and the consumer and
hence a matter of agreement between them. It would,
therefore, seem clear that the Board can, in exercise of the
power conferred under sub-s. (3) of s. 49, enter into an
agreement with a consumer stipulating for a special tariff
for supply of electricity for a specific period of time.
Such a stipulation would amount to fixing of special tariff
and it would clearly be in exercise of the power to fix
special tariff granted under subs. (3) of s. 49. Indeed, if
the power to fix special tariff through the modality of an
agreement with the consumer were not there in sub-s. (3) of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 30
s. 49. it cannot be found in any other provision of the
Supply Act and in such a case it would be impossible for the
Board to enter into any agreement with the consumer binding
itself to supply electricity at a special rate for a certain
period of time. Such an agreement would be wholly ultra the
power of the Board and the would cause considerable mischief
and inconvenience as no industry would be able to enter into
an agreement ensuring supply of electricity which would be
binding on the Board. Tariff is the most important element
in such agreement and if no binding stipulation can be made
in regard to tariff, the agreement itself would be
meaningless and would b no more than a mere rope of sand..
The power to enter into an agreement fixing. a special
tariff for supply of electricity for a specified period of
time is, therefore, relatable to sub-s. (3) of s. 49
82
and such an agreement entered into by the Board would b. in
exercise of the power under that sub-section. The three
agreements for supply of electricity to the appellant must,
in the circumstances be regarded as having been entered into
by the Board in exercise of the statutory power conferred
under sub-s. (3) of s. 49. Now, when the power to fix
special tariff for a consumer is given to the Board, the
possibility cannot be ruled out that the Board may in
exercising this power show undue preference to one consumer
as against the other. Sub-section (4) of s. 49 therefore,
provides a safeguard by enacting that in fixing tariff and
terms and conditions for the supply of electricity, the
Board shall not show any undue preference to any person.
This safeguard is obviously necessary only in cases where
special tariff is filed by the Board under sub-s. (3) of s.
49. When uniform tariffs are filed by the Board under sub-
ss. (1) and (2) of s. 49, there could be no question of the
Board showing undue preference to any one consumer against
another because every consumer falling within the category
would have to pay the same tariff for the same benefit
received by him. It is, therefore, obvious that sub-s. (4)
of s. 49 controls the action of the Board in fixing tariff
under sub-s. (3) of s. 49 and it has, no application where
uniform tariffs are fixed under sub-ss. (1) and (2) of s.
49.
Having analysed the provisions of s. 49, we may now
turn to consider the argument advanced on behalf of the
Board that a stipulation binding the Board not to charge
anything more than a specific rate would be void as it would
have the effect of divesting the Board of the power to fix
and refix charges entrusted to it under s. 49, or hindering
or fettering is future exercise. Now, if there is one
principle more well settled than any other, it is that when
a public authority is entrusted by statute with a
discretionary power to be exercised for the public good, it
cannot, when making a private contract in general terms,
fetter itself in the use of that power or in the exercise of
such discretion. There are a number of decisions which would
establish this principle beyond doubt. We may refer to a few
of them in order to appreciate the true scope and ambit of
this principle-what is its area of operation and what are
its limitation.
The first case where this principle was enunciated is
Ayr Harbour Trustees v. Oswald (supra). In this case the
Harbour Trustees, whose statutory power and duty were to
acquire land, to be used as need might arise for the
construction of works on the coast line of the Harbour,
sought to save money in respect of severence on the
compulsory acquisition of a particular owner’s land by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 30
offering him a perpetual covenant not to construct their
works on the land acquired, so as to cut off from access to
the waters of the Harbour, or otherwise to affect him
injuriously in respect of the land not taken but from which
the acquired land was severed. It was held that such a
covenant was ultra vires Lord Blackburn stated the principle
in these terms:
"I think that where the legislature confer powers
on any body to take lands compulsorily for a particular
purpose, it
83
is on the ground that the using of that land for that
purpose will be for the public good. Whether that body
be one which is seeking to make a profit for
shareholders, or, as in the present case, a body of
trustees acting solely for the public good, I think in
either case the powers conferred on the body empowered
to take the land compulsorily are intrusted to them,
and their successors, to be used for the furtherance of
that object which the legislature has thought
sufficiently for the public good to justify it in
intrusting them with such powers; and, consequently
that a contract purporting to bind them and their
successors not to use those powers is void."
This case was followed by Russell, J., in York
Corporation v. Henry Leetham & Sons Ltd. (supra). There, the
plaintiff-Corporation was entrusted by statute with the
control of navigation in part of the rivers ouse and Foss
with power to charge such tolls within limits, as the
Corporation deemed necessary to carry on the two navigations
in which the public had an interest. The Corporation made
two contracts with the defendants under which they agreed to
accept, in consideration of the right to nevigate the ouse a
regular annual payment of Rs.600/- per annum in place of the
authorised tolls. The contract in regard to navigation of
the Foss was on similar lines. It was held by Russell, J.,
that the contracts were ultra vires and void because under
them the Corporation had disabled itself, whatever emergency
might arise, from exercising its statutory powers to
increase tolls as from time to time might be necessary. The
learned Judge, after citing Ayr Harbour’s case (supra) and
another case(1) observed: "the same principle underlies many
other cases which show the incapacity of a body charged with
statutory powers for public purposes to divest itself of
such powers or to fetter itself in the use of such powers".
Finally Lord Parker, C. J., said in Southendon Sea
Corporation v. Hodgson (Wickford) Ltd.(2): "There is a long
line of cases to which we have not been specifically
referred which lay down that a public authority cannot by
contract fetter the exercise of its discretion."
The principle laid down in these cases is
unexceptionable and can not be doubted. But the question is:
does it apply in the present case We do not think so. The
principle is attracted when an attempt is made to fetter in
advance the future exercise of statutory powers otherwise
than by the valid exercise of a statutory power. The
covenant in Ayr Harbour’s case (supra) tied the hands of the
Harbour Trustees and prevented them from constructing works
on the land acquired, however necessary they might become
for the proper management of the undertaking and thus
fettered the Harbour Trustees in the exercise of the
statutory power entrusted to them by the Legislature for the
purpose of the undertaking. But this covenant was entered
into by the Harbour Trustees as a ’private contract’ with
the owner of the land acquired in order to save money in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 30
respect of
84
severence and not in exercise of a statutory power and hence
the principle was invoked to invalidate the covenant. So far
as York Corporation case (supra) is concerned, it came to be
severely criticised by Sargant, L.J., in Southport
Corporation v. Birkdale District Electric Supply Co. (1) and
the learned Lord Justice pointed out that the decision in
York Corporation’s case (supra) could hardly stand with the
judgment of the Court in Southport Corporation’s case
(supra). This criticism of the decision in York
Corporation’s case (supra) was adopted by Earl of Berkenhead
when the Southport Corporation case (supra) was taken in
appeal to the House of Lords. Lord Sumner also observed in
that case that he did not think that there was a true
analogy between Ayr Harbour’s case (supra) and York
Corporation’s case (supra). The House of Lords as well as
the Court of Appeal in the Southport Corporation’s case
(supra) seemed to be of the view that the York Corporation’s
case (supra) was wrongly decided. Of course, they did not
doubt the validity of the principle enunciated by Russell,
J., but questioned its applicability to the facts of the
York Corporation’s case (supra). They appeared to think that
the discharge of their statutory duties by the Harbour
Trustees would be facilitated rather than fettered by a
reasonable latitude of discretion in fixing tolls and both
ouse and Foss agreements must, therefore, be regarded as
having been entered into by the Harbour Trustees in exercise
of the statutory power of fixing tolls and hence they would
be valid. But they pointed out that there were certain
peculiar features in the York Corporation’s case (supra) on
which the actual decision of Russell, J., holding ouse and
Foss agreements to be void, could be sustained. The
discussion of these two cases shows that the principle that
a public authority cannot by contract fetter the exercise of
the statutory power, which is conferred upon it for the
public good, is limited in its application to those cases
where the attempt to do so is otherwise than by the valid
exercise of a statutory power.
The position is different where a statutory power, is
exercised to enter into a stipulation with a third party
which fetters the future l. exercise of other statutory
powers-where such stipulation is made not us part of
’private contract in general terms as Devlin L.J. calls it
in Commissioner of Crown Lands v. Page(2), but in exercise
of a statutory power. In such a case it is difficult to see
how the exercise of the statutory power could be held to be
invalid as a fetter on the future exercise of other
strututory powers. If it were so held it would render the
statutory power meaningless and futile. It would nullify the
existence of the statutory power and that would be contrary
to all canons of construction. If the statutory power is to
have any meaning. and content. the stipulation made in
exercise of the statutory power must be valid and binding
and it would, as pointed out by Pennycuick, VC. in Dowty
Boulton v. Wolverhampton Corporation(3), "exclude the
exercise of other statutory powers in respect
85
of the same subject-matter". To put it differently, where a
stipulation in a contract is entered into by a public
authority in exercise of a statutory power, then, even
though such stipulation fetters subsequent exercise of the
same statutory power or future exercise of another statutory
power, it would be valid and the exercise of such statutory
power would protanto stand restricted. That would follow on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 30
the principle of harmonious construction. The public
authority would not, in such a case, be free to denounce the
stipulation as a nullity and claim to exercise its statutory
power in disregard of it. If that were permissible, it would
mean that the stipulation has no binding force and the
public authority has no statutory power to enter into such
stipulation. But that would be plainly contradictory of the
premise on which the argument is based.
The distinction must always, therefore, be borne in
mind whether the stipulation by which the public authority
is alleged to have fettered in advance the future exercise
of the statutory power, is one which is entered into as part
of ’private contract in general terms’, or in exercise of a
statutory power. If it is the former, the stipulation would
he bad on the principle that a public authority cannot by
contract fetter the exercise of a statutory power which is
conferred upon it for the public good. But if it is the
latter, the stipulation being in exercise of a statutory
power would be valid and it would not be open to the public
authority to disregard the stipulation and exercise the
statutory power initiated or fettered by it. This last
statement, must, however, be qualified by making it clear
that a case may conceivably arise where there. may be an
overriding statutory provision which expressly or by
necessary implication authorises the public authority to set
at naught, in certain given circumstances, a stipulation
though made in exercise of a statutory power. Where there is
such a statutory provision, the stipulation would certainly
be bindings but. when the specified circumstances rise, the
public authority, would have the power to override the
stipulation and act in derogation of it. But that again
would be a matte of construction
Now, in the present case, as we have already pointed
out above, the stipulations as to charges contained in the
agreements entered into with the appellant were made in
exercise of the statutory power to fix special tariffs
conferred under sub-s. (3) of s. 49, and, therefore there
could be no question of such stipulations being void as
fettering or hindering the exercise of the statutory power
under that provision. These stipulations did not divest the
Board of this statutory power or fetter or hinder its
exercise in fact, they represented the exercise of this
statutory power. Once the agreements were made containing
these stipulations, it was not competent to the Board to
override these stipulations which were binding as having
been validly made in exercise of statutory power. The Board
could not enhance the charges in breach of these
stipulations. To hold that the Board could unilaterally
revise the charges notwithstanding these stipulations, would
negate the existence of statutory power in the Board under
86
words, the Board had no power to enter into such
stipulations. That would negate the existence of statutory
power in the Board under sub-s. (3) of s. 49 to fix the
charges for a specific period ox time, which would be
contrary to the plain meaning and intendment of the section.
The Board was also not competent to enhance the charges
under the guise of fixing uniform tariffs for all high
tension consumers, including the appellant, under subs (1)
of s. 49, because sub-s. (1) is, on its plain language,
subject to sub-s. (3) of s. 49 and once special tariffs were
fixed for the appellant under sub-s. (3) of s. 49, there
could be no question of fixing uniform tariffs applicable to
the appellant under sub-s. (1) of s. 49. The power to fix
uniform tariffs under Sub-s (1) of s. 49 could not be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 30
exercised in derogation of the stipulations fixing special
tariffs made under sub-s. (3) of s. 49 Moreover, if the
stipulations as to charges were not binding and the Board
could enhance the charges unilaterally in disregard of them,
it is difficult to see how the agreements, of which the
stipulations formed a term as well as consideration, could
be sustained. We can understand an argument that the whole
of the agreements were void But strangely, the claim of the
Board was that the appellant should be held to the
agreements, though, at the same time the Board should be
free to repudiate the stipulations which formed the
consideration or part of the consideration. That is a claim
which is highly illogical and we find it difficult to
appreciate it. The stipulations as to charges are
inseverable from the rest of the agreements and if these
stipulations are disturbed and the charges are revised
unilaterally by the Board, how could the agreements continue
to bind the appellant ? on the view contended on behalf of
the Board, it would be impossible for a consumer to enter
into an agreement with the Board for supply of electricity
at a certain specified tariff. That surely could not have
been intended by the Legislature. " Far from promoting the
object of electrical development and industrial growth in
the State it would act as a regressive factor. It may be
pointed out that the Board also did not contend that the
agreements entered into with the appellant were wholly void.
The attack was only against the validity of the stipulations
as to charges and that attack must. for reasons which we
have given, fail in so far as it is based on s. 49.
We then turn to consider the argument based on s. 59.
That section provides that the Board shall not, as far as
practicable and after taking credit for any subventions from
the State Government under section 63, carry on its
operations under the Act at a loss and shall adjust its
charges accordingly from time to time. The contention of the
Board was that since it was operating at a loss, it was
bound under s. 59 to readjust its charges in order to avoid
the loss and hence it was within its power to enhance the
charges notwithstanding the stipulations contained in the
agreements. This contention, plausible though it may seem at
first blush‘ is‘ on closer scrutiny not well founded. It
ignores the true object and purpose of the enactment of s.
59 and fails to give due effect to the words "as far as
practicable". The marginal note to s. 59 reads "General
Principles for Board’s Finance". It is true the marginal
note cannot
87
afford any legitimate aid to a construction of a section,
but it can certainly be relied upon as indicating the drift
of the section, or, to use the words of Collins M. R. in
Bushell v. Hammond(1) "to show I what the section was
dealing with’. It is apparent from the marginal note that s.
59 is intended to do no more than lay down general
principles for the finance of the Board. It merely
enunciates certain guidelines which the Board must follow in
managing its finance. The Board is directed, as far as
practicable, not to carry on its operations at a loss and to
adjust its charges accordingly from time to time. The
Legislature has deliberately and advisedly used the words
"as far as practicable" as the Legislature was well aware
that since the Board is a statutory authority charged with
the general duty of promoting the coordinated development of
generation, supply and distribution of electricity within
the State with particular reference to such development in
areas not for the time being served or adequately served by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 30
any licensee, it might run into loss in carrying on its
operations and it might not always be possible for it to
avoid carrying on its operations at a loss. Sometimes the
Board might have to give special tariffs to consumers in
undeveloped or sparsely developed areas and sometimes
special tariffs might have to be given to industrial
consumers with a view to accelerating the rate of industrial
growth and development, in the State even though such
special tariffs might not be sufficient to meet the cost of
generation, supply and distribution of electricity. The
Legislature, therefore, did not issue a rigid directive to
the Board that it shall on no account carry on its
operations at a loss, and if there is a loss for any reason
whatsoever, it shall adjust its charges so as to wipe off
such loss. But it merely administered a caution to the Board
that ’as far as practicable’ it shall not carry on its
operations at a loss, that is, if it is ’practicable’ for it
to avoid operating at a loss by adjusting its charges, it
should try to do so. That is why this Court pointed out in
Maharashtra State Electricity Board v. Kalyan Borough
Municipality (2) that cost is not the sole or only criterion
for fixing the tariff". Now obviously where, by a
stipulation validly made under sub-s. (3) of s. 49, the
Board is under a contractual obligation not to charge any
thing more than a specified tariff, it would not be
’practicable’ for it to enhance its charges, even if it
finds that it is incurring operational loss. To do something
contrary to law-in violation of a contractual obligation an
never be regarded as ’practicable’. Section 59 does not give
a charter to the: Board to enhance its charges in breach of
a contractual stipulation. The Board can adust its charges
under the section only in so far as the law permits it to do
so. If there is a contractual obligation which binds the
Board not to charge anything more than a certain tariff, the
Board cannot claim to override it under s. 59. It is
significant to note the difference in language between s. 59
on the one hand and s. 57 read with cl. (1) of the Sixth
Schedule on the other. Section 57 clearly and in so many
terms provides that the provisions of "any other law.
agreement or instrument applicable to the licensee" shall,
in relation to the licensee"., be void and of no effect in
so far as they are inconsistent with the
88
provisions of the Sixth Schedule and cl. (1) of the Sixth
Schedule provides that the licensee shall so adjust its
charges for the sale of electricity, whether by enhancing or
reducing them, that its clear profit in any year of account
shall not so far as possible, exceed the amount of
reasonable return. The licensee can, therefore,
notwithstanding any agreement entered into with the
consumer, enhance the charges for sale of electricity in
order to earn the amount of reasonable return by way of
clear profit. But no such language is to be found in s. 59
and, on the contrary, the words there used are "so far as
practicable". We do not, therefore, think that s. 59 confers
any power on the Board to enhance the charges for supply of
electricity in disregard of a contractual stipulation
entered into by it under sub-s. (3) of s. 49.
There is also one other circumstance which supports
this view. If under s. 59, charges have to be adjusted for
the purpose of avoiding operational loss, what is the basis
on which such adjustment would be made ? obviously it cannot
be on the basis of cost of production, distribution and
supply of electricity to each consumer or class of
consumers, for there may be certain consumers or classes of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 30
consumers who may have to be supplied electricity at special
tariff less than the cost, having regard to the geographical
area or the nature or purpose of the supply. That means that
the adjustment of the charges would have to he left to the
discretion of the Board to be made in such a manner as it
thinks fit and proper in the light of relevant circumstances
and since "cost is not the sole or only criterion for fixing
tariff", the Board would be free not to enhance the charges
in case of some consumers or classes of consumers even
though such charges may be less than the cost and in case of
others, enhance them even beyond the cost, provided, of
course, the relevant factors are taken into account and
there is no undue preference of one consumer as against
another. If that be so, it must follow a fortiorari that
there is nothing in s. 59 which requires the Board to
enhance the charges in a case where it has bound itself by a
contractual stipulation not to claim anything more than a
certain specified charges.
We are, therefore, of the view that the Board was not
entitled to enhance the charges in derogation of the
stipulation as to charges contained in the agreements with
the appellant and the notification dated 28th November, 1969
fixing tariff s for extra high tension consumers was not
enforceable against the appellant. We accordingly
issue a writ quashing and setting aside the notification
dated 28th November, 1969 in so far as it seeks to make the
tariffs specified in it applicable to the appellant and
declare that the Board is not entitled to claim from the
appellant anything more than the charges specified in the
agreements. We also issue a writ restraining the Board from
enforcing the notification dated 28th November, 1969 against
the appellant or claiming from the appellant anything more
than the
89
charges specified in the agreements. The appeal is
accordingly allowed. The 1st respondent will pay the costs
of the appeal to the appellant.
Civil Appeal No. 1642 of 1971
The facts and circumstances giving rise to the present
appeal are in material respects identical with those in
Indian Aluminum Company v. KeraIa Stat Electricity Board(1)
which we have disposed of by a judgment delivered this
morning The judgment in Indian Aluminum Company v. Kerala
State Electricity Board (supra) will, therefore. govern the
decision of the present appeal as well.
We accordingly issue a writ quashing and setting aside
the notification dated 28th November, 1969 in so far as it
seeks to make the tariffs specified in it applicable to the
appellant and declare that the Board is not entitled to
claim from the appellant anything more than the charges
specified in the agreement dated 26th October, 1964. We also
issue a writ restraining the Board from enforcing the
notification dated 28th November, 1969 against the appellant
or claiming from the appellant anything more than the
charges specified in the agreement dated 26th October, 1964.
The appeal is accordingly allowed. The 1st respondent will
pay the costs of the appeal to the appellant
Civil Appeal No. 1652 of 1974
This appeal, by special leave, is directed against the
order of the High Court of orissa allowing a writ petition
filed by the first respondent for quashing a Press note
dated 1st February, 1971 levying a coal surcharge at 0.62 p.
per unit of electricity supplied by the orissa State
Electricity Board to the 1st respondent. The writ petition
came to be filed by the 1st respondent in the following
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 30
circumstances
The 1st respondent is a limited liability company
carrying on business of manufacturing aluminum. It has
several factories at different places in the country where
it carries on one or the other processes involved in the
manufacture of aluminum. It was desirous of setting up
another factory and for that purpose it was looking for a
place where it would be able to secure at reasonable rates
electrical energy which is a primary raw material in the
method of electrolysis employed for the purpose of
converting alumina into aluminum. The State of orissa had,
about this time, commissioned hydro electric station at the
site of Hirakud Dam with a view to step up the production of
electricity and making it available for industrial purposes.
It offered to supply electricity to the 1st respondent at
reasonable rates if the respondent set up its factory at
Hirakud in the District of Sambhalpur within the territories
of the State. A. contract dated 3rd
90
June, 1957 was accordingly entered into between the 1st
respondent and the state of orissa for supply of
electricity at certain mutually agreed rates for a period of
25 years with an option or renewal In favour of the 1st
respondent for a further period of 25 years. In view of this
contract, the 1st respondent established a factory at
Hirakud for the manufacture of aluminum and the State of
orissa supplied electricity to the 1st respondent from the
Hirakud Hydro Power Station at the rates stipulated in the
contract. Some time after the factory of the 1st respondent
had been in production, it was found that additional
electric power was necessary for expansion of its
operations. Another contract dated 11th February, 1960 was,
therefore, entered into between the 1st respondent and the
State of orissa whereby the State agreed to supply to the
1st respondent additional electric power at the rates and on
the terms and conditions set out in this contract. The
duration of this contract was also coextensive with that of
the earlier contract. Thus there were two contracts between
the 1st respondent and the State of orissa under which the
State supplied electricity to the 1st respondent.
In or about 1962, the State Government, had by a
notification issued under s. 5, sub-s. (1) of the
Electricity (Supply) Act, 1948 (hereinafter referred to as
the Supply Act) constituted orissa State Electricity Board
(for shortness called the Board). Section 60 of the Supply
Act provides inter alia that "all contracts entered into by,
with the State Government for any of the purposes of this
Act before the first constitution of the Board shall be
deemed to have been entered into by, with the Board".
Therefore, as soon as the Board was constituted, the two
contracts, dated 3rd June, 1957 and 11th February, 1960 were
deemed to have been entered into by the 1st respondent with
the Board and for all the purposes of the Supply Act, they
were to be treated as contracts entered into with the Board.
The Board in its turn supplied electricity to the 1st
respondent from the Hirakud Hydro Power Station at the rates
and in accordance with the terms and conditions set out in
these contracts.
In 1968, the State Government set up a Thermal Power
Station at Talcher and the transmission lines from the,
Hirakud Hydro Power Station were integrated with those from
the Talcher Thermal Power Station. The Thermal Project was
thereafter in June 1970, transferred from the State
Government to the Board. Both the Hirakud Hydel Project and
the Thermal project were then operated by the Board. Now, in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 30
a thermal project, coal is an essential raw material as it
constitutes the fuel necessary for generation of electricity
and the cost of generation of electricity is, therefore,
directly linked with the price of coal. The Board, after it
had taken over the Talcher Thermal Project found that, owing
to steep rise in price of coal, the cost of generation of
electricity at Talcher Thermal Power Station had gone up
considerably and in order to off-set this rise in the cost
of generation, it was necessary to levy a coal surcharge on
consumers receiving electricity from the Talcher-Hirakud
Grid. The Board accordingly after obtaining the approval of
the Government decided
91
to levy a coal surcharge at the rate of 0.62 p. per unit of
the electricity supplied from the Talcher-Hirakud , Grid and
notified its decision in a Press note issued on 1st
February, 1971. The relevant part of Press note was in the
following terms:
Owing to steep rise in the price of coal which is
necessary for generation of thermal power at Talcher,
the cost of generation has gone up considerably and the
Board felt that the additional cost could be set only
by the levy of a coal surcharge on consumers receiving
power supply from Talcher-Hirakud Grid, as is levied by
other Electricity Boards who have Thermal Generation.
As per the pro visions of sections 49 and 59 and the
6th schedule of the Indian Electricity (Supply) Act,
1948, the levy of coal surcharge is permissible under
the aforesaid circumstances.
The quantum of coal surcharge is, however,
dependant on the rise or fall in the cost of coal
delivered at the Talcher Thermal Power Station and on
the basis of the present cost of coal supplied to the
Power Station the Board proposes to levy coal surcharge
at 0.62 paise per unit provisionally. This coal
surcharge will be in addition to the present tariff at
which the power is being supplied to the consumer fed
from the Talcher-Hirakud Grid and is also exclusive of
the Electricity Duty and other charges, if any levied
by Government from time to time. The coal surcharge
will, however, not apply to the consumers getting
supply of power from Diesel Power Stations run by the
Board.
The coal surcharge at the above mentioned rate of
0.62 paise per unit will be levied on all supplies of
energy from the Talcher-Hirakud Grid with effect from
1-2-1971. As the Machkund Power System is not
integrated with the Hirakud-Talcher Grid, consumers
receiving power from Machkund Power System are exempted
from the above levy for the present."
It would be seen that the Press Note excluded from the coal
surcharge consumers of electricity-supplied from diesel
power stations as also Machkund Power Station. The only
consumers subjected to the coal surcharge were those
receiving electricity from the Talcher Hirakud Grid. Relying
on the Press Note, the Board claimed to recover the coal
surcharge from the 1st respondent, but the 1st respondent
disputed this liability and filed writ petition No. 357 of
1971 in the High Court of Orissa challenging the validity of
the Press Note and praying for quashing the demand for coal
surcharge. The High Court allowed the writ petition and
quashed the decision of the Board to levy the coal surcharge
so far as the 1st respondent is concerned. The Board
thereupon brought the present appeal with. special leave
obtained from this Court.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 30
92
There were in the main three grounds on which the High
Court declared the levy of the coal surcharge invalid.
Firstly, the High Court held that since electricity to be
supplied to the 1st respondent under the two contracts was
to be from the Hirakud Hydro Power Station, rise ill the
price of coal, which is not an essential raw material in the
generation of hydro electric power, was irrelevant and that
the Board could not furnish any valid or legitimate reason
for applying coal surcharge to the 1st respondent. Secondly,
the High Court said that the levy of the coal surcharge
could not be justified under s. 49, as it was imposed only
on consumers of electricity from Grid and consumers of
electricity from diesel power station and Machkund Hydro
Power Station were not touched and it did not form part of a
measure to fix uniform tariffs. Section 59 also, according
to the High Court, did not help the Board. In the first
place, no positive material was placed before the High Court
by the Board which would show that the Board was running at
a loss and the coal surcharge had been levied for the
purpose of avoiding such loss and secondly, to quote the
words of the High Court, if the coal surcharge were imposed
to meet the purposes of section 59, there could have been no
"justification to exempt the consumers of energy from diesel
stations and Machkund Hydro Project" for ‘section 59 makes
provision for a comprehensive view of the matter and not
with reference to a particular undertaking of the Board"
Lastly, the High Court felt that no regulations having been
made under section 79(j) conferring power on the Board to
unilaterally revise the charges, it was not competent to the
Board to ignore the stipulation contained in the two
contracts and enhance the charges in violation of such
contractual stipulation. The High Court observed that if
regulations made under s. 79(j). conferred "unilateral power
on the Board of revising the tariffs, the position would be
very different": in such a case, "since regulations are law
and such law would provide for unilateral exercise of power,
agreements cannot stand in the way and deter the authority
of the law enabling unilateral exercise of power from being
so exercised’. The High Court accordingly quashed the
decision to levy the coal surcharge contained in the Press
Note and declared that the 1st respondent shall not be
subject to the coal surcharge on the basis of the Press
Note. the question is whether the view taken by the High
Court is correct.
We will take up the second and the third grounds
together for consideration. We do not think that the High
Court was right in saying that by making regulations under
section 79(j) the Board could confer upon itself power to
unilaterally revise the rate‘s for supply of electricity
Section 79(j) empowers the Board to make regulations not
inconsistent with the Supply Act to provide for principles
governing the supply of electricity by the Board to persons
other than the licenses under section 49". This power to
make regulations must obviously be exercised consistently
with the provisions of the Supply Act and the regulations
made in exercise of this power cannot go beyond the Supply
Act. If the power to enhance the rates unilaterally in
derogation of the contractual stipulation
93
does not reside in any provision of the Supply Act, it
cannot be created by regulations made under the Supply Act.
Either this power can be found in some provision of the
supply Act or it is not there at all. Regulations in the
nature of subordinate legislation cannot confer authority on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 30
the Board to interfere with the contractual rights and
obligations unless specific power to make such regulations
is vested in the Board by some provision in the Statute
expressly or by necessary implication. No such power is to
be found in section 79(j) or in any other provision of the
Supply Act. It does not, therefore, make any difference
whether regulations under section 79(j) were made or not, at
the date when the coal surcharge was levied. Even if they
were made, they could not have conferred authority on the
Board to unilaterally exonerate itself from the stipulation
con lined in the two contracts and enhance the rates
notwithstanding such contractual stipulation. The only
question could be whether the Board had any such authority
under ss. 49 and 59, these being the only two sections
relied on for the purpose of spelling out such authority in
the Board. This question stands concluded against the Board
by the decision given by us this morning in Indian Aluminium
Company v. Kerala State Electricity Board(1). We have
analysed the provisions of ss. 49 and 59 and held that on a
true interpretation, neither of these two sections confers
any authority on the Board to override a contractual
stipulation as to rates and to enhance the rates in
derogation of such contractual stipulation, even if it finds
that the rates stipulated in the contract are not sufficient
to meet the cost of production and supply of electricity and
it is incurring operational loss. This decision clearly
negatives the claim of the Board to enhance the rates by the
levy of coal surcharge under s. 49 or s. 59. The Board must
be held bound by the stipulation as to rates contained in
the two contracts solemnly entered into by the State of
orissa with the first respondent. On t his view it becomes
unnecessary to consider whether the levy of the coal
surcharge could not be justified under s. 49 because it was
imposed only on consumers of electricity from Talcher-
Hirakud Grid and not on the other consumers, and it did not
form part of a measure to fix uniform tariffs, or whether
there was any material before the High Court showing that
the Board was running its operations at a loss so as to
justify readjustment of the charges under s. 59. It is
immaterial to consider these questions because whatever view
be taken in regard to them. it is clear from our decision
that neither under s. 49 nor under s. 59 can the Board. even
if it is running at a loss, interfere with a contractual
stipulation as to rates solemnly agreed upon with the
consumer. It may readjust the rates in order to avoid the
operational loss, where it is not fettered by a contractual
stipulation from doing so. The High Court was therefore.
right in taking, the view that the Board was not entitled to
levy coal surcharge on the 1st respondent in enhancement of
the rates for supply of electricity stipulated in the two
contracts between the parties. We need not. On this view.
consider the first ground on which also the High Court held
the levy of coal surcharge to be invalid, namely, that
electricity to be supplied to the 1st
94
respondent under the two contracts was to be from Hirakud
Hydro Power Station and, therefore, rise in the price of
coal was irrelevant and it could not furnish any
justification for imposing coal surcharge on the 1st
respondent. We do not express any opinion on this point as
it is unnecessary to do so.
There is in the circumstances, no reason to interfere
with the decision of the High Court. We accordingly dismiss
the appeal with costs.
Civil Appeal No. 1653 of 1974
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 30
This appeal, by special leave, is brought against an
order of the High Court of orissa dismissing a writ petition
filed by the appellant for quashing a Press Note dated 1st
February, 1971 levying a coal surcharge at the rate of 0.62
p. per unit on electricity supplied by the orissa state
Electricity Board from the Talcher-Hirakud Grid. The writ
petition came to be filed by the appellant in the following
circumstances.
The appellant is a limited liability company carrying
on business of manufacture of board and paper. The appellant
wanted to set . up its factory at a place which would be
convenient from the point of view of availability of
facilities such as electric power The State of orissa had,
about this time commissioned Hydro Electric Station at the
site of Hirakud Dam with a view to stepping up the
production of electricity and making it available for
industrial purposes. It offered to supply electricity to the
appellant at reasonable rates as also to make other
facilities available to the appellant if the appellant set
up its factory at Chouadwar in Cuttack district. An
agreement dated 3rd December, 1960 was accordingly entered
into between the appellant and the State of orissa for
supply of electricity at certain mutually agreed rates and
on the terms and conditions set out in the agreement. Clause
(1) of the agreement provided that it shall be deemed to be
in force , for a period of five years from the date of
supply of Hydro Power, i.e. 1st February, 1958 and
thereafter shall so continue unless and until the same shall
be determined by either party giving to the other six
calendar months’ notice in writing of his intention to
terminate the agreement. It was common ground between the
parties that neither had given notice terminating the
agreement as contemplated in cl. (1) and in the
circumstances, the agreement continued to be in force.
Clauses (7), (14) and (22) specified the charges payable by
the appellant for the electricity supplied by the State
Electricity Board under the agreement Clause (13) provided
that "the tariff and conditions of supply mentioned in this
agreement shall be subject to any revision that may be made
by the supplier from time to time". Clause (23) laid down
the machinery of
95
arbitration. It said: "any dispute or difference arising
between the consumer and the supplier or their respective
Electrical Engineers IS to the supply of electrical energy
hereunder or the pressure thereof or as to the Supplier or
the Consumer respectively to determine the same or any
question, matter or thing arising hereunder shall be
referred to a single arbitrator who shall be mutually agreed
upon by both parties". And lastly, Clause (24) declared that
"the supply of electrical energy under this agreement shall
be subject to the provisions of all Acts of the Union
Parliament and the rules made thereunder and the special
orders of the Government of orissa for the time being in
force with reference to the supply of electrical energy from
the Hirakud Hydro Electric Station and the provisions of
such Acts of the Union Parliament and the rules made
thereunder and Special orders of the Government of Orissa
shall be deemed to be incorporated with and form part of
this agreement so far as they are not inconsistent
therewith". This last mentioned clause clearly posited that
under the agreement electricity was to be supplied by the
State from the Hirakud Hydro Electric Station a position
reinforced by the use of the words "Hydro Power" in cl. (1).
In view of this agreement, the appellant set up its factory
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 30
for manufacture of board and paper at Choudwar, a backward
area, even though it is situated far from the source of raw
materials and the consumer market and the State supplied
electricity to the appellant at the rates stipulated in the
agreement.
In or about 1962 the State Government, by a
notification issued under section 5, sub-section (1) of the
Electricity (Supply) Act, 1948 (hereinafter referred to as
the Supply Act) constituted the orissa State Electricity
Board (for shortness caned the Board). Section 60 of the
Supply Act provides inter alia that all contracts entered
into by, with the State Government for any of the purposes
of this Act before the first constitution of the Board shall
be deemed to have been entered into by, with the Board".
Therefore, as soon as the Board was constituted, the
agreement dated 3rd December, 1960 was deemed to have been
entered into by the appellant with the Board and for all the
purposes of the Supply Act it was to be treated as an
agreement entered into with the Board. The Board in its turn
supplied electricity to the appellant from the Hirakud Hydro
Power Station at the rates and in accordance with the terms
and conditions set out in the said agreement.
In 1968, the State Government set up a Thermal Power
Station at Talcher and the transmission lines from the
Hirakud Hydro Power Station were integrated with those from
the Talcher Thermal Power Station. The Thermal project,
thereafter in June 1970, was transferred from the State
Government to the Board. With the Hirakud Hydro Hydel
Project and the Talcher Thermal Project were then operated
by the Board. Now, in a thermal project coal is an essential
raw material as it constitutes the fuel necessary for
generation of electricity and the cost of generation of
electricity is, therefore, directly linked with the price of
coal. The Board, after it had taken over Talcher Thermal
Project, found that, owing to steep rise in the price of
coal,
96
the cost of generation of electricity at Talcher Thermal
Power Station had gone up considerably and in order to off-
set this rise in the cost of generation it was necessary to
levy a coal surcharge on consumers receiving electricity
from the Talcher-Hirakud Grid. The Board accordingly, after
obtaining the approval of the Government, decided to levy a
coal surcharge at the rate of 0.62 p. per unit of the
electricity supplied from the Talcher-Hirakud Grid and
notified its decision in a Press Note issued on 1st
February, 1971. The relevant part of the Press Note was in
the following terms:
"Owing to steep rise in the price of coal which is
necessary for generation of thermal power at Talcher,
the cost of generation has one up considerably and the
Board felt that the additional cost could be set only
by the levy of a coal surcharge on consumers receiving
power supply from Talcher- Hirakud Grid, as is levied
by other Electricity Boards who have Thermal
Generation. As per the provisions of Sections 49 and 59
and the 6th Schedule of the Indian Electricity (Supply)
Act, 1948, the levy of coal surcharge is permissible
under the aforesaid circumstances.
The quantum of coal surcharge is, however,
dependent on the rise or fall in the cost of coal
delivered at the Talcher Thermal Power Station and on
the basis of the present cost of coal supplied to the
Power Station the Board proposed to levy coal surcharge
at 0.62 paise per unit provisionally. ’This coal
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 30
surcharge will be in addition to the present tariff at
which the power is being supplied to the consumer fed
from the Talcher-Hirakud Grid and is also exclusive of
the Electricity Duty and other charges, if any, levied
by Government from time to time. The coal surcharge
will, however. not apply to the consumers getting
supply of power from Diesel Power Stations run by the
Board.
The coal surcharge at the above mentioned rate of
0.62 paise per unit will be levied on all supplies of
energy fro the Talcher-Hirakud Grid with effect from 1-
2-1971. As the Machkund Power System is not integrated
with the Hirakud-Talcher Grid, consumers receiving
power from Machkund Power System are exempted from the
above levy for the present."
It would be seen that the Press Note excluded from the coal
surcharge consumers of electricity supplied from Diesel
power stations as also Machkund Power Station. The only
consumers subjected to the coal surcharge were these
receiving electricity from the Talcher-Hirakud Grid. Relying
on the Press Note, the Board claimed to recover the coal
surcharge from the appellant, but the appellant disputed its
liability and filed Writ Petition No. 605 of 1971
challenging the validity of the Press note and praying for
quashing the demand for coal surcharge. H
There were various contentions raised on behalf of the
appellant in supports of the writ petition. Since, according
to the Press Note,
97
the coal surcharge was sought to be imposed by the Board
under sections 49 and 59 and the Sixth Schedule to the
Supply Act, the principal contention of the appellant was
directed towards showing that none of these provision
authorised the Board to levy the coal surcharge and thereby
enhance the rates for supply of electricity unilaterally, in
derogation of the stipulation as to rates contained in the
agreement. It was also urged on behalf of the appellant that
in any event the coal surcharge could not be levied on the
appellant, since electricity to be supplied to the appellant
under the agreement was to be, from the Hirakud Hydro Power
Station as clearly. indicated in cls. (1) and (2) of the
agreement and rise in the price of coal was, there fore,
irrelevant so far as the cost of supply of electricity to
the appellant was concerned. Even if the electric, supply
from the Talcher Thermal Power Station was integrated with
that from the Hirakud Hydro Power Station-a position
seriously disputed by the appellant it did not, according
to the appellant, make any difference to the position
because, in the first place, the Talcher Thermal Power
Station was not established and inter connected with the
Hirakud Hydro Power Station pursuant to any scheme under the
Supply Act, and secondly, there was sufficient electricity
generated in the Hirakud Hydro Power Station which would
meet the requirements of the appellant under the agreement
and it was not necessary for the Board to draw upon the
electricity generated at the Talcher Thermal Power Station
for the purpose of discharging its obligations under the
agreement. ’though the Press Note referred only to sections
49 and 59 and the Sixth Schedule to the Supply Act as the
source of the power to levy the coal surcharge, the Board
also sought to justify its claim by reference to cl. (13) of
the agreement and it, therefore became necessary for the
appellant to repel this contention of the Board. The
appellant urged that cl. (13) of the agreement could not
clothe the Board with the authority to levy the coal
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 30
surcharge, when it had no such authority under the
provisions of the Supply Act. It was also contented on
behalf of the appellant that, in any event, the power
conferred under cl. (13) of the agreement could not be
exercised by the Board arbitrarily or unreasonably, or on an
extraneous or irrelevant ground, and since electricity to be
supplied to the appellant under the agreement was to be T
from the Hirakud Hydro Power Station, levy of coal surcharge
on the appellant on the ground that there was steep rise in
the price of coal, when coal is not at all a necessary raw
material in the generation of Hydro electric power, was
arbitrary and unreasonable and, to say the least, founded on
a wholly irrelevant ground. The appellant also contended
that there was nothing to show that the cost of generation
of electricity at the Hirakud Hydro Power Station was more
than the f rates for the supply of electricity. stipulated
in the agreement. Even if the combined cost of generation of
electricity at the Hirakud Hydro Power Station and the
Talcher Thermal Power Station were taken into account, there
was no material said the appellant, to show that the rates
for the supply of electricity provided in the agreement were
not sufficient to meet the cost of generation so as to
justify revision of such rates under cl. (13) of the
agreement.
98
Though these contentions were pressed on behalf of the
appellant at the hearing of the Writ Petition, the Division
Bench of the High Court of orissa, which heard the writ
petition, declined to entertain the merits of these
contentions and dismissed the writ petition on a short
preliminary ground. That ground may be stated as follows in
the words of the Division Bench Clause 23 of the agreement
provides for arbitration in the event of any dispute arising
out of it. We are of the view that the petitioner must avail
of the specific remedy provided in the agreement, is so
advised, to resolve its dispute with the Board as in our
opinion, even if on an examination of the several
contentions advanced before us it turns out that adequate
power under the statute is wanting, the Board may yet
justify its action relying upon the contractual provision
Whether the levy is justified under the agreement is a
matter well within the scope of the arbitration proceeding.
If the petitioner disputed the levy in a civil action,
section 24 of the Arbitration Act, 1940, could have been
relied upon by the Board to divert the action to the
private forum chosen by the parties. The petitioner should
not be permitted to invoke our extraordinary jurisdiction",
and on this view the Division Bench dismissed the writ
petition without examination of the merits of the several
contentions". The appellant applied to the High Court for
leave to appeal to this Court, but the application was
refused and hence the appellant brought the present appeal
with special leave obtained from this Court.
It is apparent from the Press Note that when the Board
decided to levy the coal surcharge on the consumers
receiving electricity from the Talcher Hirakud Grid, it
claimed to do so under ss. 49 and 59 and the Sixth Schedule
to the Supply Act. We must, therefore, first examine whether
any of these provisions of the Supply Act empowered the
Board to levy the coal surcharge. We fail to see how the
machinery of arbitration contained in cl (23) of the
agreement can possibly cover such a question. The
arbitration agreement in that clause applies only in a
dispute or difference "as to the supply of electrical energy
hereunder or the pressure thereof or as to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 30
interpretation of this Agreement or the right of the
supplier or the consumer respectively to determine the same
or any other question matter or thing arising hereunder‘.
The question as to whether the Board had the power under
sections 49 and 59 and the Sixth Schedule to the Supply Act
to levy the coal surcharge is not a question, matter or
thing arising under the agreement It is a claim founded on
the provisions of the Supply Act to impose the coal
surcharge in addition to the rates payable by the appellant
to the Board under the agreement. Such a claim clearly falls
outside the ambit and coverage of the arbitration provision
contained in cl. (23) of the agreement. The arbitration
agreement cannot therefore, be regarded as a relevant factor
which should legitimately influence the discretion of the
Court in declining to entertain the writ petition on merits.
So we proceed to consider how far sections 49 and 59 and the
Sixth Schedule to the Supply Act could be regarded as
providing statutory authority to the Board to levy coal
surcharge on the appellant.
We have already had occasion to consider the true scope
and ambit of sections 49 and 59 of the Supply Act in Indian
Aluminium
99
Company v. Kerala State Electricity Board(1) in which we
have pronounced our judgment this morning. It is clear from
our judgment in that case that neither section 49 nor
section 59 confers any authority on the Board to enhance the
rates for supply of electricity where they are fixed under
stipulation made in an agreement. The Board has no authority
under either of these two sections to override a contractual
stipulation and enhance unilaterally the rates for the
supply of electricity. Now, the effect of the levy of coal
surcharge would be to enhance the rates for the supply of
electricity stipulated under the agreement. It would,
therefore, appear to be clear that the Board cannot claim to
justify the levy of coal surcharge on the appellant by
resort to sections 49 and 59. It is futile for the Board to
rely on either of these two sections. Equally futile is the
reliance placed by the Board on the Sixth Schedule to the
Supply Act. The Sixth Schedule is, by a fiction enacted in
section 57 deemed to be incorporated in the licence of every
licensee and if the Board were a licensee for the Purpose of
this section, the provisions of the Sixth Schedule would
also apply to it and it would be entitled under cl. (1) of
the Sixth Schedule to so adjust its charges for the sale of
electricity by enhancing them that its clear profit in any
year of account does not, as far as possible, exceed the
amount of reasonable return. But the definition of
’licensee’ given in section 2, sub section (6) says that
the provisions of section 26 of the Supply Act
notwithstanding, ’licensee’ does not include the Board. The
Board is therefore, by express enactment taken out of the
category of licensee for the purpose of the Supply Act.
Section 57 cannot, in the circumstances, have any
application to the Board and if that be so, the provision of
the Sixth Schedule cannot be invoked by the Board in support
of its claim to enhance the rates by the addition of the
coal surcharge.
But that does not put an end to the controversy between
the parties. It is true that in the Press Note the Board
relied only on sections 49 and 59 and the Sixth Schedule of
the Supply Act as the source of the power under which it
claimed to levy the coal surcharge and these provisions have
been found not to contain the power sought in them. But, if
there is one principle more well settled than any other, it
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 29 of 30
is that, when an authority takes action which is within its
competence, it cannot be held to be invalid, merely because
it purports to be made under a wrong provision, if it can be
shown to be within its power under any other provision. A
mere wrong description of the source of power a mere wrong
label cannot invalidate the action of an authority, if it is
otherwise within its power. The Board claimed that, in any
event, even if sections 49 and 59 and the Sixth Schedule to
the Supply Act could not be construed as authorising the
Board to enhance unilaterally the rates for supply of
electricity, the Board had the power under cl. (13) of the
agreement to levy the coal surcharge on the appellant and
the decision to levy the coal surcharge could be justified
by reference to this power. Now, if this claim of the Board
were well founded. it would afford a complete answer to the
challenge made on behalf of the appellant. But
100
the appellant raised various contentions in answer to this
plea based on cl, (13) of the agreement. We may have
referred to some of these contentions in an earlier part of
the judgment. It is here that the case of the appellant
founders on the rock of the preliminary objection. Clause
(23) of the agreement provides that any dispute or
difference relating to a question, thing or matter arising
under the agreement shall be referred to the arbitration of
a single arbitrator. Questions such as: whether the Board
had power under cl. (13) of the agreement to levy any coal
surcharge at all when no such power was conferred on it by
the Act, whether the action of the Board in levying the coal
surcharge on the appellant under cl. (13) of the agreement
was arbitrary and unreasonable or whether it was based on
extraneous and irrelevant considerations and whether, on the
facts and circumstances of the case, the Board was justified
under cl. (13) of the agreement to levy the coal surcharge
on the appellant, are plainly questions arising under the
agreement and they are covered by the arbitration provision
contained in cl. (23) of the agreement. All the contentions
raised by the appellant against the claim to justify the
levy of the coal surcharge by reference to cl. (13) of the
agreement would, therefore, seem to be covered by the
arbitration agreement and there is no reason why the
appellant should not pursue the remedy of arbitration which
it has solemnly accepted under cl. (23) of the agreement and
instead invoke the extraordinary jurisdiction of the High
Court under Art. 226 of the Constitution to determine
questions which really form the subject matter of the
arbitration agreement. We are, therefore, of the view that
the High Court was right in exercising its discretion
against entertaining the writ petition on merits, in so far
as it was directed against the validity of the levy of the
coat surcharge under cl. (13) of the agreement. The merits
of the contentions raised by the appellant would have to be
decided by arbitration as provided in cl. (23) of the
agreement.
We, therefore, dismiss the appeal, but, in the peculiar
circumstances of the case, make no order as to costs.
Civil Appeal No, 1654 of 1954.
This appeal, by special leave, is directed against the
order of the High Court of orissa dismissing Writ Petition
No. 527 of 1971 filed by the appellant against the orissa
State Electricity Board (hereinafter referred to as the
Board) Writ Petition No. 527 of 1971 challenged the vapidity
of the same Press Note dated 1st February, 1971 which also
formed the subject matter of challenge in Writ Petition No.
605 of 1971 leading to Civil Appeal No. 1653 of 1974. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 30 of 30
facts giving rise to Writ Petition No. 527 of 1971 are
identical with those of Writ Petition No. 605 of 1971
barring only the difference that whereas the appellant in
Writ Petition No. 605 of 1971 carried on the business of
manufacture of board and paper, the appellant in Writ
Petition No. 527 of 1971 carried on the business of running
a textile mill and while the agreement between the appellant
and the State of orissa for supply of electricity in Writ
Petition No. 605 of 1971 was
101
dated 8th December, 1960, the agreement in Writ Petition No.
527 of 1971 was dated 12th May, 1960. The material terms and
conditions of both the agreements were, however, the same.
The judgment given by us in Titagarh Paper Mills Co., Ltd.
v. Orissa State Electricity Board and Anr. (Civil Appeal
1653 of 1974) must also, therefore, govern the decision of
this appeal and whatever we have said in Titagarh Paper
Mills Co. Ltd. v. Orissa State Electricity Board and Anr.
(Civil Appeal 1653 of 1974) must apply equally in the
present case.
We, therefore, dismiss the appeal with no order as to
costs.
V.P.S. Appeals dismissed.
102