Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 25
PETITIONER:
RAMJI DAYAWALA & SONS (P) LTD.
Vs.
RESPONDENT:
INVEST IMPORT
DATE OF JUDGMENT09/10/1980
BENCH:
DESAI, D.A.
BENCH:
DESAI, D.A.
SHINGAL, P.N.
CITATION:
1981 AIR 2085 1981 SCR (1) 899
1981 SCC (1) 80
CITATOR INFO :
R 1982 SC1302 (8)
D 1988 SC 30 (5)
R 1989 SC 818 (10,13)
ACT:
Arbitration Act 1940, S. 34; Code of Civil Procedure
1908. S. 15; Arbitration (Protocol and Convention) Act 1937,
S. 3; & Foreign Awards (Recognition & Enforcement) Act,S. 3-
Sub-contract between Indian firm and foreign firm-Sub-
contract incorporating an agreement to refer disputes to a
foreign arbitral tribunal-After execution of agreement
Indian firm repudiating the arbitration agreement-Suit for
recovery in High Court by Indian firm-Foreign firm
contesting that suit to be stayed on account of arbitration
clause in the agreement-Single Judge and Division Bench
deciding stay of suit necessary-Decision-Whether valid-power
of court to stay suit-Exercise of discretion by trial court-
Interference by appellate court.
HEADNOTE:
The appellant (plaintiff), a private limited company, a
labour contractor, entered into a sub-contract with the
respondent (defendant), a Yugoslavia based company which in
turn had entered into a contract with the State Electricity
Board for setting up a power station. The sub-contract dated
July 10, 1961 between the appellant and the respondent
incorporated an agreement to refer all the disputes arising
out of the sub-contract to arbitration by the International
Chamber of Commerce in Paris with the application of
Yugoslav materials and economical law. In carrying out the
work undertaken under the sub-contract,the appellant claimed
that it carried out some extra work for which it was
entitled to recover extra amounts from the respondent, and
as the claims were not satisfied or met with by the
respondent, the appellant filed a civil suit on the original
side of the High Court for recovery of the amount. On a
notice of motion taken out by the appellant, the High Court
granted an ad interim exparte injunction restraining the
respondent from withdrawing the money due to it from the
State Electricity Board.
Pursuant to service of the aforesaid notice of motion
the respondent moved an application under sec. 151 of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 25
Code of Civil Procedure, alleging in the petition for stay
that the disputes and differences that arose were in respect
of and/or relating to the sub-contract dated July 10, 1961
and in view of the subsisting agreement to refer disputes or
differences arising under or out of the sub-contract to
arbitration, the suit filed by the appellant should be
stayed. The appellant filed a counter-affidavit contending
that there was no concluded agreement between the parties to
refer all the disputes arising out of the subcontract to
arbitration and alleged that by letter dated July 10, 1961,
the very dated on which the sub-contract was entered into at
Belgrade, the Managing
900
Director of the appellant company informed the respondent
that he had objected to the arbitration clause in the
agreement. It was also averred that a cable was also sent by
the Managing Director on reaching Bombay on July 13, 1961
requiring that the clause regarding arbitration be deleted.
Second contention was that even if it is held that there is
a subsisting arbitration agreement, having regard to all the
circumstances of the case, the discretion should not be
exercised in favour of the defendant-respondent.
The Single Judge granted the petition of the respondent
and stayed further proceedings in the suit filed by the
appellant, and vacated the ad interim injunction granted in
favour of the appellant.
The appellant preferred two appeals. One against the
order of the single Judge granting stay of the suit of the
appellant and the other against the order vacating the ad
interim injunction. A Division Bench of the High Court
dismissed both the appeals by a common judgment holding that
there was a valid subsisting arbitration agreement between
the parties and that it was binding on both. It also held
that the claims made by the appellant in the suit arose out
of the sub-contract which included the arbitration agreement
and, therefore, the appellant must be bound by the bargain
undertaken by him. It negatived the appellant’s contention
that on the facts and circumstances of the case
discretionary relief of grant of stay of suit would cause
irreparable hardship and deny justice.
In appeal to this Court against the order of stay of
the suit granted by the High Court, it was contended on
behalf of the appellant: (1) there was no concluded
arbitration agreement between the parties to refer the
disputes arising out of the sub-contract dated July 10, 1961
to arbitration and, therefore, the suit cannot be stayed;
(2) even if the Court came to the conclusion that there was
such a subsisting arbitration agreement between the parties,
prayer for stay having been made under section 51 of the
Code of Civil Procedure and/or under section 34 of the
Arbitration Act, 1940, read with Section 151 CPC, the Court
should not enforce it in its discretionary jurisdiction as
it would result in miscarriage of justice; (3) in view of
the provisions contained in the Arbitration (Protocol and
Convention) Act, 1937 the Court could not invoke its
inherent jurisdiction under section 151 CPC and the Special
Act would not assist the respondent as the case was not
covered by its provisions. It was also contended that the
undermentioned circumstances when properly evaluated would
unmistakably indicate that the instant case is not a fit
case in which the Court should decline to adjudicate upon
the dispute brought to it by granting stay in favour of the
respondent. (1) The work under the special contract Ext. A
dated July 10, 1961 was executed and carried out in India
and the whole of the evidence both for and against the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 25
appellant in India,(2) the amount claimed in the suit is so
disproportionately small in relation to the huge cost of
arbitration to be held at Paris in France that forcing the
appellant to incur the cost to realise such a small sum
would be denial of justice, (3) restrictions on availability
of foreign exchange is a relevant consideration, a fact of
which the Court can take judicial notice, (4) the Court
should not render its assistance by granting stay to one who
insists on arbitration not as a matter of principle but with
a view to thwarting, stiffing or exhausting the other side,
and (5) in all cases of arbitration by a foreign arbitral
tribunal there is always a rider that in case of hardship or
injustice, Courts of the country of the party being forced
to go to foreign arbitral tribunal will protect him.
901
On behalf of the respondent it was contended that (1)
even if the court proceeds on the assumption that the
letter and the cable were received, it is not open to the
Court to look into the contents of the letter and the cable
because the contents were not proved, as the Managing
Director of the appellant company who was supposed to have
signed the letter and the cable had neither entered the
witness box nor filed his affidavit proving the contents
thereof, (2) that once the sub-contract was admittedly
signed and executed by the Managing Director of the
appellant company, subsequent attempt on behalf of the
appellant to repudiate a part of the contract would be of no
avail and the court cannot give effect to it except if the
novatio suggested by the appellant was unreservedly accepted
and agreed to by the respondent, and (3) when the motion is
addressed to the discretion of the court and the court has
exercised its discretion, the appellate Court should be slow
to interfere with the discretionary order and substitute its
own discretion in place of the discretion of the court
before which the motion was addressed.
Allowing the appeal,
^
HELD: 1. Both the learned Single Judge and the Division
Bench of the High Court were in error in granting stay of
the suit. The stay of the suit granted by the learned Single
Judge and affirmed by the Division Bench is vacated. The
suit should proceed further from the stage where it was
stayed. The trial court would give priority to it and
dispose it of as expeditiously as possible. [928G-H]
2. The sub-contract marked Ext. A had been signed both
by the Managing Director of the appellant company as well as
on behalf of the respondent company. The third paragraph of
Article 12 of sub-contract Ext. A recites an arbitration
agreement. The provision is for a reference of disputes
arising out of the sub-contract to foreign arbitral
tribunal, namely, the International Chamber of Commerce in
Paris. Such a clause spells out an arbitration agreement.
[908E-F]
3. (i) The Appellate Bench of the High Court held that
the letter and the cable were not received by the
respondent. This conclusion is not only contrary to evidence
on record but reached in utter disregard of the admission of
the Manager of the respondent. [910A-B]
(ii) The letter and the cable would show that the
arbitration agreement to refer disputes to a foreign
arbitral tribunal in the draft was not acceptable to the
appellant though the other terms were acceptable. The
appellant repudiated the arbitration agreement soon after
the agreement was signed when the Managing Director of the
appellant was in Belgrade and took the follow up action by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 25
sending a cable reiterating and repeating the objection
immediately after his return to India. After this specific
objection with regard to arbitration agreement in the sub-
contract, the respondent allowed the appellant to proceed
further with the implementation and execution of the sub-
contract, without controverting what the appellant had
stated in the letter and the cable. This unmistakably shows
that the respondent accepted the alteration as suggested by
the appellant in that the arbitration agreement was deemed
to have been deleted from the sub-contract Ext A. [910H;
911A-D]
4. If the truth of the facts stated in a document is in
issue, mere proof of the handwriting and execution of the
document would not furnish evidence of the truth of the
facts or contents of the document. The truth or otherwise
902
of the facts or contents so stated would have to be proved
by admissible evidence i.e. by the evidence of those persons
who can vouchsafe for the truth of the facts in issue.
[912B-C]
In the instant case the utter failure of the respondent
to reply to the letter and the cable controverting the
averments made therein unmistakably establish the truth of
the averments made in the letter. [912E]
5. In the facts of a given case acceptance of a
suggestion may be sub silentio reinforced by the subsequent
conduct. The general rule is that an offer is not accepted
by mere silence on the part of the offeree. There may,
however, be further facts which taken together with the
offeree’s silence constitute an acceptance. One such case is
where a part of the offer was disputed at the negotiation
stage and the original offeree communicated that fact to the
offerer showing that he understood the offer in a particular
sense. This communication will probably amount to a counter
offer in which case it may be that mere silence of the
original offerer will constitute his acceptance. [912G-H]
In the instant case, the conclusion is inescapable that
there was no concluded arbitration agreement between the
parties. [914E]
Halsburys Laws of England 4th Edn. vol. 9 para 251, R.
v. Fulhan, Hammersmith and Kensington Rent Tribunal, ex
parte Zerek, [1951] 1 All E. R. 482, Davies v. Sweet (1962)
2 W.L.R. 525, referred to.
6.(i) The High Court totally overlooked and ignored the
admission of receipt of letter and cable in paragraph 6 of
the affidavit. The High Court attached importance to the
denial of the receipt of the letter and the cable by the
employee of the respondent company in the oral evidence and
did not attach importance to the subsequent admission that
the manager of respondent company must have replied to the
letter and the cable. Admission, unless explained, furnishes
the best evidence. The High Court overlooked the material
evidence, drew impermissible inference and came to the
conclusion which on evidence is found utterly unsustainable.
[914G-H]
(ii) A finding of fact recorded by the High Court
overlooking the incontrovertible evidence which points to
the contrary and, therefore, utterly unsustainable cannot
come in the way of this Court reaching a correct conclusion
on facts and the examination of the evidence by this Court
cannot be impeded by a mere submission that this Court does
not interfere with finding of fact. [915A]
7. (i) Both the Courts practically overlooked the basic
difference in the approach which the Court will have to
adopt if the application is to be treated under section 34
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 25
of the Arbitration Act, 1940, or one under section 151
C.P.C. In any event, as the motion is at the discretion of
the Court and as both the parties have led evidence, the
burden of proof would assume secondary importance. [916F]
Michael Golodetz & Ors. v. Serajuddin and Co. [1964] 1
S.C.R. 19, referred to.
(ii) It is well settled that where the trial court has
a discretion in the matter, the appellate court would not
ordinarily substitute its discretion in place of the
discretion exercised by the trial court. It is equally well
settled that where the trial court ignoring the relevant
evidence, side tracking the
903
approach to be adopted in the matter and overlooking various
relevant considerations, has exercised its discretion one
way, the appellate court keeping in view the fundamental
principle can and ought to interfere because when it is said
that a matter is within the discretion of the court it is to
be exercised according to well established judicial
principles, according to reason and fair play, and not
according to whim and caprice. [917B-C]
Craies Statute Law 6th Edn. p. 273 R. v. Wilkes (770) 4
Barr 2527, referred to.
8. The Single Judge and the Division Bench completely
overlooked the well established principles in granting stay
of suit in a case where reliance is placed upon a subsisting
arbitration agreement. [917D]
9. When parties by contract agree to arrange for
settlement of their disputes by a Judge of their choice, by
procedure of arbitration voluntarily agreed upon, ordinarily
the court must hold the parties to their bargain. As a
corollary, if a party to a subsisting arbitration agreement
in breach or violation of the agreement to refer dispute to
arbitration approaches the Court, the Court would not lend
its assistance to such a party and by staying the suit
compel the party in breach to abide by its contract. When
the parties have agreed to an arbitration by a foreign
arbitral tribunal the case for stay would be stronger than
if there was a domestic arbitration agreement. However, it
is not an absolute rule. Granting or refusing to grant stay
is still a matter within the discretion of the court. How
discretion would be exercised in a given case would depend
upon various circumstances. [918D-F]
Bristol Corporation v. John Aird & Co. [1913] A.C. 241
at 257 and Owners of Cargo Ex "Athenee" v. Athenee Llyods’
List Law Reports, Easter Sittings 1922, Vol. XI, page 6,
referred to.
In the instant case the entire evidence both of the
appellant and the respondent is in this country; the
contract as a whole was executed and carried out in this
country; the claim as a whole arose in this country; the
appellant is a company incorporated in this country; and the
respondent is having its office in this country; and that
the respondent is not motivated by any principle to have the
decision of the foreign arbitral tribunal at Paris but the
principal object of respondent is merely to make it more
difficult, if not impossible, for the appellant to assert
the claim. The other vital considerations are, that the cost
of arbitration at Paris will be so disproportionately high
to the claim involved in adjudication that one would never
think of incurring such a huge cost to realise such a small
sum claimed, and the restriction on the availability of
foreign exchange. The sum total of all these well
established circumstances clearly indicate that the instant
suit is one in which when discretion is exercised on well
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 25
settled judicial considerations no court would grant stay
and the stay has to be refused. [925B-D]
Michael Golodetz & Ors. v. Serajuddin & Co. [1964] 1
S.C.R. 19, Bristol Corporation v. John Aird & Co. [1913]
A.C. 241 at 257, Owners of Cargo Ex "Athenee" v. Athenee
Llyods’ List Law Reports, Easter Sittings 1922, Vol. XI,
page 6, V/o Tractoroexport, Moscow v. M/s. Tarapore &
Company and Anr. [1970] 3 S.C.R. 53 and The Fehmarn [1957] 2
All E.R. 707, referred to.
10. Section 3 of the Arbitration (Protocol and
Convention) Act, 1937 is in pari materia with section 3 of
the Foreign Awards (Recognition and Enforcement) Act, 1961.
Section 3 of the 1937 Act would only be attracted if there
is a submission pursuant to an agreement to that effect.
[928B-C]
904
In the instant case while there is an agreement as
contemplated by First Schedule to the 1937 Act, there is no
submission made in pursuance of such agreement and,
therefore the application of the respondent could not have
been entertained under section 3 of the 1937 Act. [928D]
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 2407-
2408 of 1968.
From the Judgment and Order dated 1-12-1965 of the
Calcutta High Court in Appeal Nos. 110-111/64
P. K. Chatterjee and P. K. Mukherjee for the Appellant.
S. C. Majumdar, Arvind Kumar, S. Dasgupta, Mrs. L.
Arvind and Miss Karabi Banerji for the Respondent.
The Judgment of the Court was delivered by
DESAI, J.-Protracted, time consuming, exasperating and
atrociously expensive court trials impelled an alternative
mode of resolution of disputes between the parties:
arbitrate-don’t litigate. Arbitration being a mode of
resolution of disputes by a judge of the choice of the
parties was considered preferable to adjudication of
disputes by court. If expeditious, less expense resolution
of disputes by a judge of the choice of the parties was the
consummation devoutly to be wished through arbitration,
experience shows and this case illustrates that the hope is
wholly belied because in the words of Edmond Davis, J. in
Price v. Milner, these may be disastrous proceedings.
A petty labour contractor in search of its labour
charges in a paltry amount of Rs. 4,25,343.00 from a giant
foreign engineering and construction company which had
undertaken to erect a thermal power station at Barauni in
Bihar State under a contract dated February 27, 1960, with
Bihar State Electricity Board, filed a suit in the year 1963
which stands stayed without the slightest progress for the
last 17 years and with end nowhere in sight. Plaintiff
(appellant herein), a private limited company, a labour
contractor, entered into a sub-contract for erecting two
complete radiation type steam boilers as part of Thermal
power station at Barauni, with the defendant Invest-Import,
a Yugoslavia based company which in turn had entered into a
contract with the Bihar State Electricity Board for setting
up the power station. Plaintiff sub-contractor, pursuant to
the sub-contract dated July 10, 1961, had to supply skilled
labour, unskilled labour and apprentice labour, to carry out
the erection work and incidentally to do other things
provided in the sub-contract.
905
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 25
The contract also provided for employing extra labour force
as well as carrying out extra stipulated job for
installation, substantial alteration of design etc. as and
when desired and directed by the principal contractor,
respondent herein. In carrying out the work undertaken under
the sub-contract, the plaintiff claims that it carried out
some extra work for which it was entitled to recover Rs.
70,000 from the respondent. There were also other claims
made by the appellant which were not satisfied or met with
by the respondent with the result that the appellant filed
suit No. 1359/63 on the original side of the High Court at
Calcutta on August 1, 1963, to recover Rs. 4,25,343.00 from
the respondent. The split up of the total claim has been set
out in the particulars appended to para 16 of the plaint.
The appellant also annexed sub-contract between the
appellant and the respondent as Annexure ’A’ to the plaint.
On August 2, 1963, on a notice of motion taken out by the
appellant, a learned single judge of the High Court granted
an ad interim ex parte injunction restraining the respondent
from withdrawing the money due to it from the Bihar State
Electricity Board.
Pursuant to service of notice of motion taken out by
the appellant, on August 8, 1963, the respondent appeared
through one Ilija Kostantinovic, Manager of the respondent
company posted at its office at 36, Ganesh Chandra Avenue,
Calcutta, and moved an application purporting to be under s.
151 of the Code of Civil Procedure, contending, inter alia,
that the sub-contract between the appellant and the
respondent incorporates an agreement to refer all the
disputes arising out of the sub-contract to arbitration and,
therefore, the suit should be stayed. The clause spelling
out agreement to refer disputes to arbitration was
reproduced in the petition. It reads as under:
"Any mutual disputes should be settled in mutual
agreement, however, should they fail to reach an
agreement in the way, both contracting parties accept
the jurisdiction of the Arbitration by the
International Chamber of Commerce in Paris with
application of Yogoslav materials and economical law".
After setting out the background of disputes between
the parties, it was alleged in the petition for stay that in
the circumstances set out in the petition, disputes and
differences arose between the appellant and the respondent
out of or in respect of and/or relating to the sub-contract
dated July 10, 1961, and in view of the subsisting agreement
to refer disputes or differences arising under or out of the
sub-contract between the parties to arbitration, the suit
filed by the appellant should be stayed. It was also averred
that if the provisions of Arbitration Act did not apply the
Court should in
906
exercise of its inherent jurisdiction injunct the plaintiff
appellant from proceeding with the suit instituted by it.
There were further averments praying for vacating ad interim
injunction granted by the High Court which are no more
relevant. The respondent annexed to the petition for stay
the sub-contract between the parties dated July 10, 1961, as
also some correspondence that had ensued between the
parties.
Appellant filed a counter affidavit sworn by one
Bhikhubhai Gourishankar Joshi who described himself as
principal officer and constituted attorney of the appellant
company controverting the averments made by the respondent
in the petition seeking stay of the suit. The principal
contention taken in the counter affidavit was that there was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 25
no concluded agreement between the parties to refer all the
disputes arising out of the sub-contract to arbitration as
contended for and on behalf of the respondent. To
substantiate this contention letter dated July 10, 1961, the
very date on which the sub-contract was entered into between
the appellant and the respondent, sent by the Managing
Director of the appellant company as also a telegram sent by
the same person on July 13, 1961, were annexed to the
counter-affidavit.
Ilija Kostantinovic, Manager of the respondent company
at Calcutta filed an affidavit in rejoinder in which there
are certain averments which go to the root of the matter
and, therefore, they may better be extracted here. They read
as under:
"5. With reference to the allegations contained in
paragraph 4 of the said affidavit, I reiterate the
statements contained in paragraphs 3 and 4 of the
petition and I deny all allegations, which are contrary
thereto and/or inconsistent therewith.
6. With further reference to the allegations
contained in paragraph 4 of the said affidavit, I say
that after entering into the contract dated July 10,
1961, and after executing the same, the respondent
purported to send a letter to the petitioner seeking to
modify and/or delete the arbitration clause contained
in the contract dated July 10, 1961, and also purported
to send a cable to the petitioner. The petitioner never
agreed to the modification and/or deletion of the
arbitration clause as contained in the said contract or
to the alleged arbitration clause suggested by the
respondent".
The petition for stay was set down for recording
evidence. One Panich Stojan son of Nikola Panich, Project
Manager, Barauni Thermal Project, an employee of the
respondent company was examined on behalf of the respondent.
No. oral evidence was offered
907
on behalf of the appellant. The learned single judge by his
order dated January 10, 1964, granted the petition of the
respondent and stayed further proceedings in the suit filed
by the appellant. The learned judge also vacated the ad
interim injunction granted in favour of the appellant.
The appellant preferred two appeals being Civil Appeal
No. 110/64 against the order of the learned single judge
granting stay of the suit of the appellant and Civil Appeal
No. 111/64 against the order dated February 6, 1964,
vacating the interim injunction granted in favour of the
appellant. A Division Bench of the High Court disposed of
both the appeals by a common judgment dated December 1,
1965, dismissing both the appeals. While dismissing the
appeals the division bench held that there was a valid
subsisting arbitration agreement between the parties and it
was binding on both the parties. It was also held that the
claims made by the appellant in the suit arose out of the
sub-contract which included arbitration agreement and,
therefore, the plaintiff must be bound by the bargain
undertaken by him. The contention of the appellant that even
if there was a subsisting arbitration agreement, in the
facts and circumstances of the case discretionary relief of
granting stay of suit would cause irreparable hardship and
deny justice to the appellant was negatived.
Appellant then moved an application for a certificate
under 7 Article 133(1)(c) of the Constitution. The High
Court was of the opinion that the appeals did involve
substantial questions of law and the case was a fit one for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 25
appeal to the Supreme Court and accordingly granted a
certificate under Art. 133(1)(c). Appellant accordingly
preferred these two appeals by certificate.
At the commencement of hearing of the appeals Mr. P. K.
Chatterjee, learned counsel who appeared for the appellant
stated that by passage of time the prayer for injunction
restraining the respondent from recovering its claim from
Bihar State Electricity Board had become infructuous and
accordingly Civil Appeal No. 2408/68 which was against the
order vacating ad interim injunction granted by the High
Court and the dismissal of the appeal against that order was
not pressed. Therefore, Civil Appeal No. 2408/68 would stand
dismissed as having not been pressed.
Mr. Chatterjee in support of Civil Appeal No. 2407/68
canvassed four contentions before us. They are:
1. There is no concluded arbitration agreement
between the parties to refer the disputes arising
out of the sub-contract dated July 10, 1961, to
arbitration and, therefore, the suit cannot be
stayed;
908
2. Alternatively, even if the Court comes to the
conclusion that there is such a subsisting
arbitration agreement between the parties, prayer
for stay having been made under s. 151 of the Code
of Civil Procedure and/or under s. 34 of the
Arbitration Act, 1940, read with s. 151, C.P.C.,
the Court should not enforce it in its
discretionary jurisdiction in the facts and
circumstances of the case as it would result in
miscarriage of justice;
3. In view of the provisions contained in Arbitration
(Protocol and Convention) Act, 1937, the Court
could not invoke its inherent jurisdiction under
s. 151, C.P.C. and the special Act would not
assist the respondent because the present case is
not covered by the provisions of the Act;
4. This being a foreign arbitration, s. 34 of the
Arbitration Act, 1940, is not attracted and the
Court would have no jurisdiction to grant stay of
the suit filed by the appellant.
The first contention is that there is no concluded
arbitration agreement between the parties to refer the
disputes arising out of the sub-contract dated July 10,
1961, to arbitration and in the absence of a mutually agreed
arbitration agreement, the respondent is not entitled to a
stay of the suit filed by the appellant either under s. 34
of the Arbitration Act or under s. 34 read with s. 151 of
the Code of Civil Procedure. Undoubtedly, sub-contract
marked Ext. A has been signed both by the Managing Director
of the appellant company and by one Mr. Petrovije on behalf
of the respondent company. Third paragraph of Art. 12 of
sub-contract Ext. A recites an arbitration agreement. The
provision is for a reference of disputes arising out of the
sub-contract to foreign arbitral tribunal, namely, the
International Chamber of Commerce in Paris. Such a clause
has always been interpreted to spell out an arbitration
agreement. Respondent contends that admittedly the Managing
Director of the appellant company has signed sub-contract
Ext. A which incorporates arbitration agreement and the
appellant accepted the same and entered upon the work
entrusted to it under Ext. A and, therefore, it is not now
open to it to repudiate a part of the contract which
provides for reference of disputes arising out of the sub-
contract to arbitration of a foreign arbitral tribunal.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 25
Appellant countered by saying that the appellant accepted
the principal contract but not the agreement to refer the
dispute to foreign arbitral tribunal and that there are
tell-tale circumstances on record which would convincingly
establish that the parties were not ad idem with regard to
arbitration clause in Ext. A.
909
To recall, sub-contract Ext. A was signed by the
parties in Belgrade on July 10, 1961. Managing Director of
the appellant was in Belgrade on that day. On that very day
Managing Director sent a letter from Belgrade itself
addressed to the respondent at Belgrade, relevant portion of
which may be extracted:
"10th July 1961
"I have signed the contract of Barauni Thermal
Power Station work with you.
I have objected to the clause of Arbitration put
in there in agreement which was deleted from our
revised draft of agreement sent to you in advance.
Arbitration clause will be acceptable to us if
only arbitration to be done in India, according to the
rules and regulations and procedure of our country".
This letter was handed in to the respondent on the same day
on which Ext. A was signed and accepted by the parties and
it would imply that it must be soon after the signing
ceremony was over. Further, the Managing Director of the
appellant immediately on landing in Bombay on July 13, 1961,
sent a cable to the respondent which reads as under:
"Reached safely Bombay (stop) Reference to our
letter of 10th July 1961 regarding Arbitration clause
to be deleted from the contract document".
Three things emerge from a conjoint reading of the letter
and the cable that before sub-contract Ext. A was signed by
the parties at Belgrade, a draft of the intended sub-
contract was sent by the respondent to the appellant for its
approval and the Managing Director of the appellant had
raised a limited objection to the arbitration clause. On
behalf of the appellant it was suggested that there would be
no objection to the arbitration clause if arbitration was to
be done in India. But as the original draft submitted on
behalf of the respondent suggested arbitration by a foreign
arbitral tribunal stationed in Paris, the same was objected
to on behalf of the appellant and its amendment was sought.
Undoubtedly, Managing Director of appellant signed Ext. A
which incorporated the arbitration agreement as extracted
herein-before. But the letter referred to herein was handed
in presumably soon after the signing ceremony of subcontract
Ext. A was over and was followed by the cable which not only
referred to letter dated July 10, 1961, but also reiterated
and repeated the objection to the arbitration clause.
910
At one stage of the proceeding the respondent adopted a
position that neither the letter nor the cable were received
by it and they are not genuine documents. The appellate
Bench of the High Court held that the letter and the cable
were not received by the respondent. This conclusion is not
only contrary to evidence on record but is reached in utter
disregard of the admission of the Manager of the respondent.
Ilija Kostantinovic, Manager of the respondent company
stationed at Calcutta filed an affidavit in rejoinder. The
admissions are spelt out in paragraphs 5 and 6 of the
affidavit which are extracted hereinabove. In para 6 it is
in terms admitted that the appellant purported to send a
letter to the respondent seeking to modify and/or delete the
arbitration clause contained in the contract dated July 10,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 25
1961. and also purported to send a telegram to the
respondent. He further proceeded to state that the
respondent never agreed to the modification and/or deletion
of the arbitration clause. This unambiguous admission
unmistakably shows that the letter and the cable were
received by the respondent. Of course, again at a later
stage when Panich Stojan, Project Manager of the respondent
entered the witness box to give evidence in support of the
application for stay he was asked at Question No. 13 whether
he had any knowledge about the letter sent by the appellant
on July 10, 1961, relating to the arbitration clause
contained in the agreement. The answer was that the deponent
had not received any letter in his department. To question
No. 16 about the cable, the answer was that the respondent
had not received any cable also. In cross-examination when
he was confronted with the averments in paragraph 6 of the
affidavit of Ilija Kostantinovic, a nebulous answer was
given that Mr. Kostantinovic must have replied to the letter
and the telegram. And he admitted that Mr. Kostantinovic was
the Manager of the branch office of the respondent company
at Calcutta. Now, one employee, viz., the Manager of the
respondent company stationed at Calcutta in terms admitted
the receipt of the letter and the cable while the witness
who claimed to be present at the signing ceremony of the
sub-contract Ext. A was emphatic that the cable and the
letter were not received and gave an explanation with regard
to the averments of the affidavit which only show that truth
was otherwise. In the face of uncontroverted and unambiguous
admission in the affidavit of the Manager of the respondent
company one can without fear of contradiction assert that
the letter and the cable were received by the respondent.
The letter and the cable would show that the arbitration
agreement to refer disputes to a foreign arbitral in the
draft was not acceptable to the appellant though the other
terms were acceptable. The appellant repudiated the
arbitration agreement soon after the agreement was signed
when the Managing
911
Director of the appellant was in Belgrade and took the
follow up action by sending a cable reiterating and
repeating the objection immediately after his return to
India.
Now, once it is admitted and established that the
letter and the cable were received by the respondent,
ordinarily if the contents of the letter and cable are not
acceptable to respondent, a reply to that effect is
naturally expected. Contention is that respondent accepted
the change in arbitration clause proposed by the appellant
sub silentio coupled with the subsequent conduct. It is a
fact that the respondent did not write back saying that if
the arbitration agreement was not acceptable to the
appellant the sub-contract would not be acceptable as a
whole to the respondent. On the contrary, after a specific
objection only with regard to arbitration agreement in the
sub-contract Ext. A by the appellant, the respondent allowed
the appellant to proceed further with the implementation and
execution of the subcontract, without controverting what the
appellant had stated in the letter and the cable. This would
unmistakably show that the respondent accepted the
alteration as suggested by the appellant in that the
arbitration agreement was deemed to have been deleted from
the subcontract Ext. A. Add to this the circumstance that a
petty labour contractor could not have been expected to or
was not likely to agree to arbitration by a foreign arbitral
tribunal stationed in Paris because it would be beyond its
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 25
reach to seek relief by arbitration in a foreign country.
Incidentally it was urged by Mr. Majumdar that even if
the court proceeds on the assumption that the letter and the
cable were received, it is not open to this Court to look
into the contents of the letter and the cable because the
contents are not proved as the Managing Director of the
appellant company who is supposed to have signed the letter
and the cable has neither entered the witness box nor filed
his affidavit proving the contents thereof. Reliance was
placed on Judah v. Isolyne Bose. In that case a letter and
two telegrams were tendered in evidence and it was observed
that the contents of the letter and the telegram were not
the evidence of the facts stated therein. The question in
that case was whether the testatrix was so seriously ill as
would result in impairment of her testamentary capacity. To
substantiate the degree of illness, a letter and two
telegrams written by a nurse were tendered in evidence. The
question was whether in the absence of any independent
evidence about the testamentary capacity of the testatrix
the contents of the letter could be utilised to prove want
of testamentary capacity.
912
Obviously, in these circumstances the Privy Council observed
that the fact that a letter and two telegrams were sent by
itself would not prove the truth of the contents of the
letter and, therefore, the contents of the letter bearing on
the question of lack of testamentary capacity would not be
substantive evidence. Undoubtedly, mere proof of the
handwriting of a document would not tantamount to proof of
all the contents or the facts stated in the document. If the
truth of the facts stated in a document is in issue mere
proof of the handwriting and execution of the document would
not furnish evidence of the truth of the facts or contents
of the document. The truth or otherwise of the facts or
contents so stated would have to be proved by admissible
evidence, i.e. by the evidence of those persons who can
vouch safe for the truth of the facts in issue. But in this
case Bhikhubhai Gourishankar Joshi who filed an affidavit on
behalf of the appellant has referred to the averments in the
letter and the cable. He is a principal officer and
constituted attorney of the appellant company. Once the
receipt of the letter and the cable are admitted or proved
coupled with the fact that even after the dispute arose and
before the suit was filed, in the correspondence that ensued
between the parties, the respondent did not make any overt
or covert reference to the arbitration agreement and utter
failure of the respondent to reply to the letter and the
cable controverting the averments made therein would
unmistakably establish the truth of the averments made in
the letter. What is the effect of averments is a different
question altogether but the averments contained in the
letter and the cable are satisfactorily proved.
It was, however, contended that once sub-contract Ext.
A was admittedly signed and executed by the Managing
Director of the appellant company, subsequent attempt on
behalf of the appellant to repudiate a part of the contract
would be of no avail and the court cannot give effect to it
except if the novatio suggested by the appellant is
unreservedly accepted and agreed to by the respondent. In
the facts of a given case acceptance of a suggestion may be
silentio reinforced by the subsequent conduct. True it is
that the general rule is that an offer is not accepted by
mere silence on the part of the offeree. There may, however,
be further facts which taken together with the offeree’s
silence constitute an acceptance. One such case is where a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 25
part of the offer was disputed at the negotiation stage and
the original offeree communicated that fact to the offerer
showing that he understood the offer in a particular sense.
This communication will probably amount to a counter offer
in which case it may be that mere silence of the original
offerer will constitute his acceptance (see Halsbury’s Laws
of England, 4th Edn.,
913
Vol. 9, para 251). Where there is a mistake as to terms of a
document as in this case, amendment to the draft was
suggested and a counter offer was made, the signatory to the
original contract is not estopped by his signature from
denying that he intended to make an offer in the terms set
out in the document; to wit, the letter and the cable (Ibid.
para 295). It can, therefore, be stated that where the
contract is in a number of parts it is essential to the
validity of the contract that the contracting party should
either have assented to or taken to have assented to the
same thing in the same sense or as it is sometimes put,
there should be consensus ad idem. And from this it follows
that a party may be taken to have assented if he has so
conducted himself as to be estopped from denying that he has
so assented (Ibid, para 288). Even apart from this, it would
still be open to the party contending novatio to prove that
he had not accepted a part of the original agreement though
it has signed the agreement containing that part. It would
in this connection be advantageous to refer to R. v. Fulhan,
Hammersmith and Kensington Rent Tribunal, ex parte Zerek,
wherein an oral agreement was entered into between the
landlord and a tenant for lease of unfurnished premises at
weekly rent of 35s. The landlord subsequently refused to
grant the tenant possession unless he agreed to hire his
furniture to the landlord for one year at a rental of & 12
and to execute a document certifying, inter alia, that the
letting was a furnished letting at a rent of 35s. a week.
The tenant signed the document and entered into possession.
Later the tenant applied to a rent tribunal to fix a
reasonable rent for the premises as an unfurnished dwelling
house under the Landlord and Tenant (Rent Control) Act,
1949. The tribunal accepted the tenant’s evidence that the
premises were originally let unfurnished and came to the
conclusion that the document signed by the tenant did not
constitute a valid agreement and did not modify or replace
the earlier oral agreement and that the premises were not
bona fide let furnished. The tribunal reduced the rent to
15s. a week. On an application by the landlord for an order
of certiorary, motion for certiorary was refused and in so
doing the subsequent written agreement was ignored and the
previous oral agreement was accepted as genuine and binding.
It would, therefore, be inappropriate to say that because
the appellant has signed the sub-contract, every part of it
is accepted by him even though there is convincing evidence
pointing to the contrary. It was, however, said that a
subsequent negotiation
914
or a repudiation of part of the contract cannot in any
manner affect the concluded agreement. Reliance was placed
on Davies v. Sweet the pertinent observation at p. 529 being
as under:
"If there was originally a concluded bargain
between the parties, this could only be got rid of by
either (a) a mutual agreement to call off the sale, or
(b) an agreement for a variation of the terms of the
original contract. The mere fact that there have been
negotiations which prove to be abortive and do not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 25
result in an enforceable agreement does not destroy the
original contract: see Perry v. Suffields Ltd. (1916) 2
Ch. 187. C.A."
If on the evidence in this case it can be held that the sub-
contract Ext. A was concluded contract in respect of all
clauses of it including the arbitration agreement, a
subsequent repudiation of a part of it by a party to the
contract cannot affect the concluded agreement. But as
clearly pointed out hereinbefore an amendment was suggested
to the draft of the intended contract and immediately after
the signing ceremony a letter pointing out that part in
respect of which amendment was sought and not carried out
was not acceptable and it was followed by a cable it would
indicate that the parties were not consensus ad idem with
regard to a severable portion of contract and there was thus
lack of mutuality on the question of arbitration agreement.
Therefore, the conclusion is inescapable that there was no
concluded arbitration agreement between the parties. The
High Court rejected the contention of the appellant holding
that when the Managing Director of the appellant signed the
contract at Belgrade on July 10, 1961, the sub-contract
contained the arbitration agreement and his signature was
only less than half an inch away from the arbitration clause
and that he has not entered the witness box and offered
himself for cross-examination and that the respondent’s
contention that the letter and the cable were not received
appeared to be acceptable. The High Court totally overlooked
and ignored the admission of receipt of letter and cable in
paragraph 6 of the affidavit of Ilija Kostantinovic. The
High Court attached importance to the denial of the receipt
of the letter and the cable by Mr. Panich Stojan in his oral
evidence and did not attach importance to his subsequent
admission that Mr.
915
utterly unsustainable. A finding of fact recorded by the
High Court overlooking the incontrovertible evidence which
points to the contrary and, therefore, utterly unsustainable
cannot come in the way of this Court reaching a correct
conclusion on facts and the examination of the evidence by
this Court cannot be impeded by mere submission that this
Court does not interfere with finding of fact.
Assuming we are not right in reaching the conclusion
that there was no concluded arbitration agreement between
the parties and that the concurrent finding of fact recorded
by the learned single judge and the division bench of the
High Court in Letters Patent Appeal are binding on us, we
may now examine the contention of law whether in the facts
and circumstances of this case the High Court was right in
exercising its discretion in favour of the respondent by
granting stay of the suit filed by the appellant.
If the application for stay filed by the respondent
purported to be under s. 34 of the Arbitration Act, by a
catena of decisions it is well settled that granting of stay
of the suit is within the discretion of the Court. The
expression ’such authority may make an order staying the
proceedings’ clearly indicates that the Court has a
discretion whether to grant the stay and thereby compel the
parties to abide by the contract or the Court may refuse to
lend its assistance by undertaking to adjudicate the dispute
by refusing the stay. If the application is under s. 151,
C.P.C., undoubtedly the Court will still have a discretion
in exercise of its inherent jurisdiction to grant stay of
the suit or refuse the same but the approach of the Court
would be different. If s. 34 of the Arbitration Act, 1940,
is attracted, ordinarily the approach of the Court would be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 25
to see that people are held to their bargain. Therefore, the
party who in breach of arbitration agreement institutes an
action before the Court, the burden would be on such party
to prove why the stay should be refused. On the other hand,
if the application is under s. 151, C.P.C., invoking
inherent jurisdiction of the Court to grant stay, the burden
will be on the party seeking stay to establish facts for
exercise of discretion in favour of such party. In the
present case respondent who moved an application for stay of
suit instituted by the appellant founded its request for
stay on shifting sands in that at one stage it was stated
that the application was under s. 34 of the Arbitration Act,
at other stage it was stated that it was under s. 151,
C.P.C., and before us it was stated that it is under s. 3 of
the Arbitration (Protocol and Convention) Act, 1937, or
under the Foreign Awards (Recognition and Enforcement) Act,
1961. In the notice of motion taken out for stay of the suit
by the respondent
916
it was stated that the application purports to be under s.
151, C.P.C. There is no reference to s. 34 of the
Arbitration Act, 1940, in the body of the petition or in the
affidavit annexed to the petition. On the contrary, it was
stated in para 16 of the petition that if Arbitration Act,
1940 does not apply to the arbitration agreement relied upon
by the respondent, the Court may in exercise of its inherent
jurisdiction restrain the appellant from proceeding with the
suit. Learned single judge appears to have treated the
application to be under s. 34 of the Arbitration Act,
because in the last paragraph of his order he has stated
that the Arbitration Act applies even if the arbitration
agreement provides for reference to a foreign arbitral
tribunal. So saying, stay was granted which would imply that
the learned judge treated the application to be one under s.
34 of the Arbitration Act. While dealing with the contention
of the appellant that in view of the fact that arbitration
agreement refers to arbitration by a foreign arbitral
tribunal, Arbitration Act, 1940, is not attracted, the
Division Bench has assumed as was done in Michael Golodetz &
Ors. v. Serajuddin & Co., that the Arbitration Act, 1940,
invests in Court in India with authority to stay a legal
proceeding commenced by a party to an agreement against any
other party thereto in respect of any matter agreed to be
referred,, even when the agreement is to submit it to a
foreign arbitral tribunal. It further. however, held that
even if s. 34 is not attracted, the Court can in exercise of
the inherent jurisdiction for doing justice between the
parties, stay further proceeding of the suit which would
imply that the Court exercised its jurisdiction under s.
151, C.P.C. Both the Courts practically overlooked the basic
difference in the approach which the Court will have to
adopt if the application is to be treated under s. 34 of the
Arbitration Act, 1940, or one under s. 151, C.P.C. In any
event, as the motion is at the discretion of the Court and
as both the parties have led evidence, the burden of proof
would assume secondary importance.
The important question is whether the Court was
justified in the facts and circumstances of the case in
exercising its discretion in favour of the respondent.
Before examining this aspect, a minor contention raised by
Mr. Majumdar that when the motion is addressed to the
discretion of the Court and the Court has exercised its
discretion one way, the appellate Court should be slow to
interfere with the discretionary order and substitute its
own discretion in place of the discretion of the Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 25
before which the motion was addressed and as in this case
both the learned single judge and the
917
appellate bench have exercised the discretion in favour of
the respondent, in exercise of its extra-ordinary
jurisdiction this Court should not interfere with the same,
may be disposed of. It is well settled that where the trial
court has a discretion in the matter, the appellate court
would not ordinarily substitute its discretion in place of
the discretion exercised by the trial court. But it is
equally well settled that where the trial court ignoring the
relevant evidence, side tracking the approach to be adopted
in the matter and overlooking various relevant
considerations, has exercised its discretion one way, the
appellate court keeping in view the fundamental principle
can and ought to interfere because when it is said that a
matter is within the discretion of the court it is to be
exercised according to well established judicial principles,
according to reason and fairplay, and not according to him
and caprice. ’Discretion’, said Lord Mansfield in R. v.
Wilkes, ’when applied to a court of justice, means sound
discretion guided by law. It must be governed by rule, not
by humour; it must not be arbitrary, vague, and fanciful,
but legal and regular’ (see Craies on Statute Law, 6th End.,
p. 273). In the course of this judgment we would be
constrained to point out that both the learned single judge
and the judges of the Division Bench completely overlooked
the well established principles in granting stay of suit in
a case where reliance is placed upon a subsisting
arbitration agreement.
Mr. Chatterjee, learned counsel for the appellant
deduced the following circumstances from the evidence on
record which, when properly evaluated, would unmistakably
indicate that this is not a fit case in which the Court
should decline to adjudicate upon the dispute brought before
it by granting stay in favour of the respondent:
(i) The entire main contract including the work of
erecting the boilers entrusted to the appellant
under the sub-contract Ext. A, dated July 10,
1961, was executed and carried out in India and
the whole of the evidence both for and against the
appellant is in India;
(ii) The amount claimed in the suit is so
disproportionately small in relation to the huge
cost of arbitration to be held at Paris in France
that forcing the appellant to incur the costs to
realise a small sum would be denial of justice;
(iii)Restrictions on availability of foreign exchange
is a relevant consideration, a fact of which Court
can take judicial notice;
(iv) The Court should not lend its assistance by
granting the stay to one who insists on
arbitration not as a matter of
918
principle but with a view to thwarting, stiffing
or exhausting the other side;
(v) In all cases of arbitration by a foreign arbitral
tribunal there is always a rider that in case of
hardship or injustice Courts of the country of the
party being forced to go to foreign arbitral
tribunal will protect him.
We would analyse and examine each one of the circumstances
hereinabove extracted separately and evaluate their
cumulative impact on exercise of the judicial discretion one
way or the other. While so doing the observations of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 25
learned single judge and learned judges of the Division
Bench in granting stay of suit must receive serious
consideration.
When parties by contract agree to arrange for
settlement of their disputes by a judge of their choice, by
procedure of arbitration voluntarily agreed upon, ordinarily
the Court must hold the parties to their bargain. As a
corollary, if a party to a subsisting arbitration agreement
in breach or violation of the agreement to refer dispute to
arbitration approaches the Court, the Court would not lend
its assistance to such a party and by staying the suit
compel the party in breach to abide by its contract. When
the parties have agreed to an arbitration by a foreign
arbitral tribunal the case for stay would be stronger than
if there was a domestic arbitration agreement. This proceeds
on the assumption that parties not only sought and agreed
upon the forum for resolution of dispute but also the law
according to which the dispute would be resolved. However,
this is not an absolute rule. Granting or refusing to grant
stay is still a matter within the discretion of the Court.
How discretion would be exercised in a given case would
depend upon various circumstances. But to grant stay of the
suit is still a matter within the discretion of the Court.
In Bristol Corporation v. John Aird & Co., Moulton, L.J.
observed as under:
"But, my Lords, it must be remembered that these
arbitration clauses must be taken to have been inserted
with due regard to the existing law of the land, and
the law of the land as applicable to them is, as I have
said, that it does not prevent the parties coming to
the Court, but only gives to the Court the power to
refuse its assistance in proper cases. Therefore, to
say that if we refuse to stay an action we are not
carrying out the bargain between the parties does not
fairly describe the position. We are carrying out the
bargain between the parties,
919
because that bargain to substitute for the Courts of
the land a domestic tribunal was a bargain into which
was written, by reason of the existing legislation, the
condition that it should only be enforced if the Court
thought it a proper case for its being so enforced".
In Owners of Cargo Ex "Athenee" v. Athenee, the Court of
Appeal affirmed the extracted passage from Lord Moulton’s
judgment. In that case the action was brought by the
receivers of a part cargo of onions, which it was alleged
were damaged in course of carriage from Alexandria to Hull,
and the President of the Admirality Division declined to
stay the action. The Court of Appeal in the appeal at the
instance of the defendants declined to interfere with the
order refusing the stay on the ground that the balance of
convenience and the substantial advantage which the
plaintiffs have by suing in U.K. (and which they lose by not
being able to proceed in rem against this ship) and many
other advantages such as in respect of proof of loss, a
matter which any commercial tribunal would wish should be
decided, if possible, having regard to the evidence obtained
at the time by inspection of the vessel and so on, and in
these circumstances the arbitration clause in the contract
was not given effect to.
Reverting to the circumstances relied upon by the
appellant which are likely to influence the discretion of
the Court, the first submission is that the whole of the
principal contract including the subcontract was carried out
in India and the whole of the evidence both of the appellant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 25
and the respondent is in India and that this is a relevant
circumstance which must influence the judicial verdict.
Appellant has itemised his different claims in the plaint.
Broadly stated, it claims payment for extra work, difference
between agreed charges and the revised charges, loss
incurred on account of non-performance of a part of the
contract by the respondent, etc. In respect of most of the
claims the appellant will have to examine the men incharge
of the work, strength of labour force supplied by it and
this evidence would certainly be in India. Respondent had
set up its office at Calcutta and this office was
functioning even when the suit was instituted. Looking to
the various heads of claim by the appellant and the
correspondence between the parties prior to the suit it is
safe to conclude that the evidence of the respondent would
also be in India. Of course, as a remote possibility some
highly placed officers may have to be examined by the
respondent who may be in Yugoslavia. Mr. Majumdar learned
counsel for the respondents, however, urged that the
respondent has closed its office and all the books and
920
relevant documents have been taken to Belgrade and,
therefore, it is now too late in the day to say that the
evidence of the respondent is also in India. The Court is
required to consider the situation as on the date of
institution of the suit and unquestionably on the date of
institution of the suit office of the respondent at 36,
Ganesh Chandra Avenue, Calcutta, was functioning and within
7-8 days of the institution of the suit respondent appeared
in the suit through Ilija Kostantinovic, Manager of the
respondent stationed at Calcutta. Neither in the main
petition for stay nor in the affidavit in rejoinder it was
anywhere stated that the evidence of the respondent was not
in India. It was, however, urged that nearly a decade has
rolled by and that this Court should take into consideration
the change in circumstances on account of the passage of
time for which respondent is in no way responsible. Reliance
was placed on Pasupuleti Venkateswarlu v. The Motor &
General Traders. In that case an action was brought by the
landlord for recovering possession of certain premises from
the tenant. When the matter was pending in the High Court,
evidence was tendered to point out that since the
institution of the action in the trial court the landlord
has recovered another accommodation and that if the
subsequent development is taken into consideration landlord
has no present need of the accommodation in possession of
the tenant. The High Court admitted evidence on this point
and took into consideration the fact that the landlord has
since the institution of the suit obtained possession of
another accommodation and on this finding non-suited the
appellant. An objection was taken on behalf of the landlord
before this Court that the High Court was in error in taking
into consideration subsequent events and this contention was
negatived. In the very nature of action for eviction on the
ground of personal requirement, the Court has not only to be
satisfied that the requirement was present at the date of
institution of the action but continued to exist at the time
of decree and has to mould the decree accordingly. Even if
subsequent events as have a bearing on the contention
canvassed before the Court have to be taken into
consideration, there is no material on record to show that
the respondent has closed its office at Calcutta and that
the documents and books of accounts which may have to be
tendered in evidence have been taken to Yugoslavia. Save
this, Mr. Majumdar could not controvert the fact that the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 25
entire evidence both of the appellant and the respondent
which may be relevant for resolution of the dispute involved
in the suit is in this country, India. In Athenee (supra)
case the fact that the evidence was in U.K. was considered
as very relevant consideration for refusal to stay the suit.
In Michael
921
Golodetz & Ors. (Supra) the fact that all the evidence of
the parties was in India was accepted by this Court as a
relevant consideration for refusing to stay the suit.
The next circumstance relied upon is that the cost of
arbitration to be held at Paris would be so
disproportionately high to the amount claimed in the suit
that forcing the appellant to go to arbitration would be
denial of justice. This is self-evident. The claim in the
suit is Rs. 4,25,343. Now, just contemplate taking witnesses
and books of accounts to Paris for leading evidence before
the International Chamber of Commerce. The cost would
certainly be disproportionately high. One need not go into
the mathematical calculations for this obvious and self-
evident proposition.
The next circumstances relied upon is restriction on
availability of foreign exchange as a relevant
consideration. If witnesses are required to be taken to
Paris, if lawyers are to be engaged in Paris and if
documents are to be sent to Paris, all this would require
foreign exchange. Foreign exchange is a scarce and
controlled commodity. It can be obtained for prescribed
purpose. Both in the case of Michael Golodetz (Supra) and in
V/O Tractoroexport, Moscow v. M/s. Tarapore & Company and
Anr., this Court held that restriction on availability of
foreign exchange is a relevant consideration which should
enter into judicial verdict for exercising the discretion
one way or the other. The High Court in this connection
observed that if the Managing Director of the appellant
company could obtain foreign exchange for going to Belgrade
to sign the contract, why should it be assumed that he would
not get foreign exchange this time too to plead his cause -
a cause which owes its existence to the grant of foreign
exchange in 1961 ? This casual approach is none-too-
convincing. Foreign exchange for a visit for few days cannot
be equated with heavy requirement of foreign exchange for
engaging counsel, taking witnesses and transporting
documents from India to Paris so as to substantiate a claim
of Rs. 4,25,343. And the judicial approach is not whether
the appellant would get necessary foreign exchange but the
approach is should this valuable national asset of foreign
exchange be frittered away for resolving a petty matter
which can be conveniently resolved even in this country.
The next circumstance canvassed is that the Court
should not lend its assistance by granting the stay of the
suit to one who insists on arbitration not as a matter of
principle but with a view to thwarting, stifling or
exhausting the other side. Respondent insists that
922
by staying the suit the appellant should be forced to go to
arbitration if it desires to vindicate its claim. Is this
approach dictated by some principle or was the respondent
aware of the fact that looking to the quantum of claim the
appellant would not undertake the hazardous and expensive
adventure of going to foreign arbitration tribunal stationed
at Paris and that thereby the respondent would be able to
thwart or stifle the claim of the appellant ? If the relief
to be granted is discretionary, the approach of each party
persuading the Court to exercise the discretion one way or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 25
the other would be a vital and relevant consideration. The
respondent has anyhow either to appear before the Court in
India or a foreign arbitral tribunal in Paris. The
respondent is from Yugoslavia. Apart from this, the
respondent has an office at Calcutta and the responsible
officer like a Manager was stationed at Calcutta. The
correspondence between the parties prior to the institution
of the suit shows that the relevant documents were in India
on the basis of which certain replies were given by the
respondent to the claims advanced on behalf of the
appellant. But once the suit was filed, the respondent
insists that arbitration agreement should be given full
effect. Having regard to all the circumstances of the case
it appears crystal clear that the respondent is motivated to
seek stay neither to vindicate any principle nor to hold the
appellant to the bargain but to force the appellant to go to
Paris incurring disproportionately heavy cost or to give up
the claim. In Michael Golodetz (Supra) the fact that
arbitration in New York would proceed ex parte was viewed
with disfavour and stay was refused. Similarly, in The
Rehman, the principal object of the defendant was not to
achieve a trial in Russia but merely make it more difficult
to the plaintiffs to assert their claim, was emphasised
while refusing stay. In such a situation if there are other
weighty circumstances which indicate that the Court should
not lend its assistance to the respondent by staying the
suit, this aspect of the approach of the respondent would
reinforce the conclusion.
The next circumstance urged is that even where parties
have agreed to refer a dispute to foreign arbitral tribunal
it is always subject to a rider that the agreement is
subject to the law of the land, viz., that it does not
prevent the parties from coming to the court but only gives
to the Court the power to refuse its assistance in
appropriate cases. And enforcing the agreement would work
hardship or injustice, the Court would take it into
consideration before holding the parties to their bargain.
In The Rehman, a cargo was loaded at a Russian port by a
Russian shipper on board
923
the Rehman, a ship owned by a German Company. The cargo was,
by terms of the bill of lading, shipped in apparent good
order and condition and was to be delivered at the port of
London in like order and condition. The plaintiffs, an
English company, purchased the cargo and became the holders
of the bill of lading, thereby agreeing to be bound by its
terms, one of which was that all questions and disputes
should be determined in the U.S.S.R. At the Port of London
the cargo was discovered, according to the plaintiff, to be
contaminated and the damage was surveyed. The plaintiffs
issued a writ claiming against the defendants damages for
breach of the contract evidenced by the bill of lading. The
only matter for evidence, so far as the plaintiffs’ case was
concerned, that did not arise in England was the condition
of the goods when shipped, as regards which the bill of
lading contained the statement mentioned above. The
defendants moved to set aside the writ for want of
jurisdiction on the ground that by the contract the parties
had agreed that all disputes arising under it should be
judged in the U.S.S.R. and contended alternatively that all
proceedings should be stayed. Willmer, J. in Admirality
Division, held that where there is a provision in the
contract providing that disputes are to be referred to a
foreign tribunal prima facie the court will stay the
proceedings instituted in England in breach of such
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 25
agreement and will only allow them to proceed when satisfied
that it is just and proper to do so. That according to the
Court was the principle. After further holding that the
matter is in the discretion of the Court, stay was refused
on the ground that the plaintiffs were persons domiciled in
England, the claim arose in England, the damage sued for was
discovered in England, the cargo was surveyed in England,
and the damage was ascertained after the survey. The fact
that the entire evidence was in England was emphasised as a
relevant consideration. The Court also observed that from
the correspondence one is left with the suspicion that the
principal object of the defendants was not to achieve a
trial in Russia, but merely to make it more difficult for
the plaintiffs to assert their claim. On all these
considerations stay was refused. And this decision was
affirmed by the Court of Appeal in The Rehman Denning, L.
J., observed that the dispute is more closely connected with
England than with Russia. We cannot resist the temptation to
point out that the fact situation in the case before us is
almost similar, if not identical, to the one in The Rehman
(Supra).
The last circumstance relied upon is that in all cases
of arbitration by a foreign arbitral tribunal there is
always a rider that in
924
case of hardship or injustice Courts of the country of the
party being forced to go to foreign arbitral tribunal will
protect him. Ordinarily, the Court where the cause of action
has arisen would try to resolve the dispute brought before
it from the cause of action arising out of its jurisdiction.
If parties have agreed to another mode of resolution of
dispute, the Court may hold the parties to their bargain but
when the Court is deprived of the jurisdiction by an
agreement between the parties and if the Court is called
upon to enforce it, the matter will still be within the
discretion of the Court. As was stated in Bristol
Corporation (Supra) case when the Court refused to stay an
action it cannot be said that the Court is not carrying out
the bargain between the parties because that does not fairly
describe the position. The Court is carrying out the bargain
between the parties because the bargain to substitute for
the Courts of the land a domestic tribunal was bargain into
which was written, by reason of the existing legislation,
the condition that it should only be enforced if the Court
thought it a proper case for its being so enforced. And that
is where the discretion of the Court creeps in. Further,
Russel on Arbitration, 19th Edn., p. 194, neatly sums up the
relevant considerations for granting or refusing stay. It
reads :
"The principles established by the authorities
can, I think, be summarised as follows : (1) Where
plaintiffs sue in England in breach of an agreement to
refer disputes to a foreign Court, and the defendants
apply for a stay, the English court, assuming the claim
to be otherwise within its jurisdiction, is not bound
to grant a stay but has a discretion whether to do so
or not. (2) the discretion should be exercised by
granting a stay unless strong cause for not doing so is
shown. (3) The burden of proving such strong cause is
on the plaintiffs. (4) In exercising its discretion the
court should take into account all the circumstances of
the particular case. (5) In particular, but without
prejudice to (4), the following matters, where they
arise, may properly be regarded :- (a) In what country
the evidence on the issues of fact is situated, or more
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 25
readily available, and the effect of that on the
relative convenience and expense of trial as between
the English and foreign courts. (b) Whether the law of
the foreign court applies and, if so, whether it
differs from English law in any material respects. (c)
With what country either party is connected, and how
closely. (d) Whether the defendants genuinely desire
trial in the foreign country, or are only seeking
procedural advantages. (e) Whether the plaintiffs would
be prejudiced by having to sue in the foreign court
because they would: (i) be deprived of security for
their
925
claim; (ii) be unable to enforce any judgment obtained;
(iii) be faced with a time-bar not applicable in
England; or (iv) for political, racial, religious or
other reasons be unlikely to get a fair trial".
To sum up, the entire evidence both of the appellant
and the respondent is in this country; the contract as a
whole was executed and carried out in this country; the
claim as a whole arose in this country; the appellant is a
company incorporated in this country and the respondent is
having its office in this country; and that the respondent
is not motivated by any principle to have the decision of
the foreign arbitral tribunal at Paris but the principal
object of the respondent is merely to make it more
difficult, if not impossible, for the appellant to assert
the claim. Add to this two other vital considerations, viz.,
that the cost of arbitration at Paris will be so
disproportionately high to the claim involved in
adjudication that one would never think of incurring such a
huge cost to realise such a small sum claimed, and the
restriction on the availability of foreign exchange, another
vital relevant consideration. The sum total of all these
well established circumstances clearly indicate that this
was a suit in which when discretion is exercised on well
settled judicial considerations no court would grant stay
and the stay has to be refused.
And now to the approach of the appellate Bench of the
High Court relevant to the point. Says the Court :
"Here is a contract solemnly entered into between
the appellant, an Indian company, and the respondent, a
Yugoslav company, in aid of another contract entered
into between the latter and the State of Bihar through
its Electricity Board for erection of a thermal power
station at Barauni. What a valuable possession for the
nation such thermal power station means is plain to be
seen. We do not, Yugoslavs do, know the know-how, of
erecting a thermal power station. Hence they are here
on the role of collaborators to help us make such an
invaluable acquisition. And to get it built the
authorities spare from their none too adequate
resources the requisite foreign exchange for the
appellant’s managing director, Lalbhai, in order to
enable him to proceed to Belgrade with a view to
signing the contract, which he does, his signature
being "only one centimetre away" from the contract’s
arbitration clause".
Does it call for any comment or analysis that the division
bench completely misdirected itself while examining the
question of granting discretionary relief one way or the
other ? Does it disclose exercise
926
of discretion on sound judicial principles or the Court is
carried away by the considerations wholly extraneous and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 25
irrelevant? Yugoslavs did not undertake construction of
thermal power station actuated by any altruistic motive but
guided by sound business considerations. One who comes here
to earn by going into business need not be put on a
pedestal. The High Court overlooked the global competition
for obtaining international contracts and it is not a
philanthropic motive. The extracted passage clearly
indicates an approach not dictated by sound judicial
principles but considerations wholly extraneous to the issue
under discussion. It is in these circumstances that this
Court is constrained to interfere with the discretionary
relief granted in this case.
The next contention is that in view of the provisions
contained in Arbitration (Protocol and Convention) Act,
1937, (‘1937 Act’ for short), the Court could not invoke its
inherent jurisdiction under s. 151, C.P.C., and the special
Act would not assist the respondent because the present case
is not covered by the provisions of the Act. Mr. Majumdar
urged that the 1937 Act was enacted to give effect to the
protocol on arbitration clause set forth in the First
Schedule and to the convention on the execution of foreign
arbitral awards set forth in the Second Schedule as India
was a signatory to the protocol. Mr. Majumdar urged that
even if the application for stay is not entertainable under
s. 34 of the Arbitration Act on the ground that this is a
foreign arbitration to which Arbitration Act, 1940, will not
apply, nor could he invoke inherent jurisdiction of the
Court under s. 151 of the Code of Civil Procedure, yet the
application is maintainable under s. 3 of the 1937 Act.
Section reads as under:
"3. Notwithstanding anything contained in the
Arbitration Act X of 1940, or in the Code of Civil
Procedure, 1908, if any party to a submission made in
pursuance of an agreement to which the Protocol set
forth in the First Schedule as modified by the
reservation subject to which it was signed by India
applies, or any person claiming through or under him,
commences any legal proceeding in any court against any
other party to the submission or any person claiming
through or under him in respect of any matter agreed to
be referred, any party to such legal proceeding may, at
any time after appearance and before filing a written
statement or taking any other steps in the proceedings,
apply to the Court to stay the proceedings; and the
Court unless satisfied that the agreement or
arbitration has become inoperative or cannot proceed,
or that there is not in fact any dispute between the
parties with regard to the matter agreed to be
referred, shall make an order staying the proceedings".
927
India and Yugoslavia have ratified the protocol. The
question, however, is whether s. 3 is attracted in this
case. The important expression in s. 3 to be noted is: "if
any party to a submission made in pursuance of an
arbitration agreement to which the Protocol set forth in the
First Schedule as modified by the reservation subject to
which it was signed by India applies". This expression
postulates an agreement to which the protocol set forth in
the First Schedule as modified by the reservation subject to
which it was signed by India applies and a submission made
in pursuance of such agreement. Now, both India and
Yugoslavia have ratified the protocol modified by the
reservation subject to which it was signed by India. It may
be assumed that arbitration agreement between the parties to
this appeal is governed by the 1937 Act. Section 3 is,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 25
however, not attracted merely where an agreement as set
forth in the First Schedule is subsisting between the
parties but the next step ought to have been taken before
proceedings can be stayed in exercise of the power conferred
by s. 3, viz., submission made in pursuance of such an
agreement. A reference to s. 3 of the Foreign Awards
(Recognition & Enforcement) Act, 1961, (’1961 Act’ for
short), prior to its amendment by the Amending Act of 1973
and a decision of this Court interpreting the expression:
"if any party to a submission made in pursuance of an
agreement to which" would clearly establish that mere
existence of an agreement as envisaged by the First Schedule
would not attract s. 3 of the 1937 Act but it would only be
attracted where there is a submission pursuant to that
agreement. Section 3 of the 1961 Act prior to its amendment
in 1973 read as under:
"3. Stay of proceedings in respect of matter to be
referred to arbitration: Notwithstanding anything
contained in the Arbitration Act X of 1940 or in the
Code of Civil Procedure, 1908, if any party to a
submission made in pursuance of an agreement to which
the Convention set forth in the Schedule applies, or
any person claiming through or under him, commences any
legal proceedings in any Court against any other party
to the submission or any person claiming through or
under him in respect of any matter agreed to be
referred, any party to such legal proceedings may at
any time after appearance or before filing a written
statement or taking any other steps in the proceedings,
apply to the Court to stay the proceedings and the
Court, unless satisfied that the agreement is null and
void in-operative or incapable of being performed or
that there is not in fact any dispute between the
parties with regards to the matter agreed to be
referred, shall make an order staying the proceedings".
928
This section came in for interpretation in V/O Tractoro-
Export, Moscow. Interpreting this section this Court held as
under:
"But in the present case a suit is being tried in
the courts of this country which, for the reasons
already stated, cannot be stayed under section 3 of the
Act in the absence of an actual submission of the
disputes to the arbitral tribunal at Moscow prior to
the institution of the suit"
Section 3 of 1937 Act is in pari materia with s. 3 of
1961 Act. It, therefore, becomes crystal clear that s. 3 of
the 1937 Act would only be attracted if there is a
submission pursuant to an agreement to that effect. In fact,
the decision in V/O Tractoro-export, Moscow, (Supra) made it
necessary for the Parliament to amend s. 3 of the 1961 Act.
In this case we are concerned with s. 3 of the 1937 Act
which is not amended. It must, therefore, receive the same
interpretation which an identical provision received at the
hands of this Court. Viewed from that angle, in this case
while there is an agreement as contemplated by First
Schedule to 1937 Act, there is no submission made in
pursuance of such agreement and, therefore, the application
of the respondent could not have been entertained under s. 3
of the 1937 Act. As far as the 1961 Act is concerned, Mr.
Majumdar conceded that Yugoslavia has not ratified the
protocol pursuant to which 1961 Act was enacted and,
therefore, the respondent cannot maintain its application
under s. 3 of the 1961 Act.
The last submission is that this being an arbitration
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 25
agreement to refer a dispute to a foreign arbitral tribunal,
s. 34 of the Arbitration Act would not be applicable and
hence the application of the respondent for stay of the suit
is not maintainable. It is not necessary to examine this
contention on its merits because we have assumed for the
purpose of this appeal that s. 34 of the 1940 Act would be
attracted even where the agreement is to refer a dispute to
a foreign arbitral tribunal.
Having examined the matter from all angles it is clear
that both the learned single judge and the division bench of
the High Court were in error in granting stay of the suit in
this matter and, therefore, Civil Appeal No. 2407 of 1968 is
allowed and the stay of suit granted by the learned single
judge and affirmed by the division bench of the Calcutta
High Court is vacated. The suit should accordingly proceed
further from the stage where it was stayed. As the suit is a
very old one, we hope the trial court would give priority to
it and dispose it of as expeditiously as possible. The
appeal is allowed with costs throughout.
N.V.K. Appeal allowed.
929