Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1854 OF 2007
M/s. Gayatri Project Ltd.
….Appellant(s)
Versus
M/s. Sai Krishna Construction .…
Respondent(s)
O R D E R
This appeal is filed against the order passed by the High
JUDGMENT
Court in an application under Section 11(5) and (6) of the
Arbitration and Conciliation Act, 1996 (for short the ‘Act’)
directing that the matter be referred to arbitration by a former
Judge of the Andhra Pradesh High Court.
The respondent moved the aforesaid application on the
basis that it is a partnership firm, carrying on business of civil
works relating to irrigation structures. The Irrigation
Page 1
2
Department of Government of Andhra Pradesh had given the
work to the appellant herein. Thus, the appellant was the main
contractor and respondent was the sub-contractor working
| llant. The | works in |
|---|
lining and structures form KMs 156.650 to KMs 170-00 of
Package ICB-10’ in Kurnool District of Andhra Pradesh. The
appellant identified the respondent as a suitable agency for
execution of the work and entrusted the work to the
respondent as a sub-contractor. After due negotiations, an
agreement dated 29.1.2001 was entered into between the
parties. The agreement inter alia provides various terms and
conditions including the nature of work to be executed by the
respondent, security deposits, penalties leviable, commission
JUDGMENT
to which the appellant would be entitled to, method of
payment for the work undertaken, taxes and Government
levies. The agreement also contained an arbitration clause
which reads as under:-
“All disputes relating to the original contract shall
be properly referred and correspond by the work
contractor. However, the settlement of disputes and
consequential awards shall be to the account of
principal contractor and work contractor. All
disputes relating to the work contract under this
agreement shall be mutually settled between the
Page 2
3
work contractor and the principal contractor. In case
of any differences, the same will be decided by a
sole arbitrator appointed by the principal contractor
and work contractor.”
| of th<br>shall be | e agre<br>taken fo |
|---|
month. Payment shall be released as and when principal
contractor received payment from the Department, duly
deducting the commission and other recoveries as mentioned
in Clause 6 above. Final payment shall be released
after completion of the work satisfactorily. Clause 5 provided
that the work contractor (sub-contractor) shall be paid the
balance amount after deducting certain amounts from the
gross amount of running account bills. Relevant part of clause
5 is as under:-
JUDGMENT
"The work contractor shall be paid the balance
amount after deducting the following from the gross
amount of running account bills.
i. a. Earth work excavation in bed and slopes
including sectioning and leveling @ 14% (Fourteen
percent only) of Agreement rate.
b. Filling bed and slopes with CNS soils as directed
and as per specifications @ 17% (Seventeen percent
only) of Agreement rates.
ii. Sales Tax/Turnover Tax
iii. Income Tax in the running account bills.
Page 3
4
iv. Value of materials etc., if any, supplied by the
department or by the principal contractor and hire
charges of machinery given.
v. Any other recoveries affected by the department
in the account bills.
| ment fur | ther pro |
|---|
shall be released after completion of the work satisfactorily.
The respondent claims that it has executed the work to
the satisfaction of the appellant and the State Government.
The appellant having received all the amounts from the
Government of Andhra Pradesh failed to make corresponding
payments to the respondent after deducting commission as
stipulated under the agreement. The respondent, therefore,
approached and tried to persuade the appellant to make the
payment of the outstanding amount after the completion of
the entire work. However, the appellant failed to pay. Since
JUDGMENT
the amounts were not paid by the appellant, the respondent
served a Claim Notice on 6.5.2004 demanding the payment of
Rs.1,01,27,776/-. On 17.8.2004, the Appellant sent a reply to
the aforesaid notice not only disputing the various claims but
also raising a counter claim in the amount of Rs.32,12,950/-.
The appellant claimed that the accounts had been reconciled.
The parties had signed a full and final settlement document on
Page 4
5
6.6.2003, under which the respondent acknowledged the
receipt of certain amounts. The balance of Rs.17,32,843/- was
to be paid in two or three instalments before 30.6.2003. After
| entire pa | yment, |
|---|
of the reply with the counter-claim, the respondent sent a
further reply reiterating its claim and also disputing the
counter claim of the appellant as being frivolous and false. The
respondent in the aforesaid reply also stated that unless the
entire claim is satisfied, it will seek the remedy by way of
arbitration. In spite of the above, the appellant still made
efforts to settle the entire dispute but without any useful
results.
Instead of accepting the full and final settlement dated
JUDGMENT
6.6.2003, the respondent, in fact, raised a further claim for the
amount of Rs.25,50,048/- towards the value of HSD oil supply
and exemption of excise duties and sales tax which had been
availed by the appellant. A claim in this regard was sent to the
appellant on 30-5-2006. According to the respondent, the total
claim finally comes to Rs.1,26,77,824/- with interest accrued
thereon at 18% per annum from 6-5-2004. The appellant on
Page 5
6
24.6.2004 denied the aforesaid claim. The dispute not having
been resolved, the respondent served a legal notice on the
appellant dated 19.6.2006. The appellant again denied the
| ondent th | ereafter |
|---|
a reply to the application disputing and denying the claims of
the appellant. The appellant stated that the application for
appointment of Arbitrator is liable to be dismissed. It was
pleaded that Agreement dated, 29.1.2001 which contains the
arbitration clause has been superseded by the full and final
settlement agreement dated 6.6.2003. It was further the case
of the appellant that the respondent having received the entire
amount in terms of the "full and final settlement" dated 6-
6-2003 is estopped from filing the application under Section 11
JUDGMENT
(5) and (6) of the Arbitration Act. According to the Appellant,
since the entire dispute had been settled, no reference could
be made to arbitration. The appellant had also pleaded that
the respondent had failed to disclose that the parties had
entered into a full and final settlement on 6-6-2003. The plea
was also raised to the effect that invocation of the arbitration
on 9-6-2006 is time barred as the cause of action for filing the
Page 6
7
application arose on 6-6-2003 when the "full and final
settlement" was entered into between the parties.
It was also the case of the appellant that the works
| e respond | ent not b |
|---|
Consequently, the appellant had to rectify the defects and
incur extra expenses. These were liable to the deducted from
the amount claimed by the respondent. It is also the claim of
the appellant that since the works had not been satisfactorily
completed, the agreement itself was terminated on 16-11-
2001. The appellant had also pleaded that pursuant to the
Settlement dated 6-6-2003, the respondent had received a
sum of Rs.16 lakhs. Therefore, there is no arbitrable dispute
which can be referred to arbitration. It is also the case of the
JUDGMENT
appellant that he has actually suffered a loss as it has incurred
an expenditure of Rs.32,13,950/- in rectification of the works
which were unsatisfactorily performed by the respondent. The
appellant also claims that in order to maintain cordial
relations, it had entered into a "full and final settlement" with
the respondent with regard to the entire claims of the sub-
contractor.
Page 7
8
Upon examination of the entire factual as well as the
legal position, the High Court has allowed the application
under Section 11 (5) and (6) of the Act. This Appeal has been
| e aforesai | d Judgme |
|---|
Mr. Arun Kathpalia, learned Advocate appearing for the
appellant relied heavily on the "full and final settlement" and
submitted that the settlement has been duly signed by a
representative of the respondent. Therefore, the respondent
cannot now be permitted to submit that there was no "full and
final settlement". He further submitted that once there was
"full and final settlement", no arbitrable dispute remains which
could have been referred to the Arbitrator. To make good his
submissions, Mr. Kathpalia submitted that the respondent had
JUDGMENT
been negligent in the performance of the works which were
entrusted to the sub-contractor. This had ultimately led to the
termination of the Agreement on 16-11-2001. In fact, the
appellant had incurred huge amount of expenses in rectifying
the defects in the works executed by the respondent. Mr.
Kathpalia relied on clauses 5 and 6 of the Agreement and
submitted that the appellant was entitled to be compensated
Page 8
9
for the rectification work which had to be performed to the
satisfaction of the Andhra Pradesh Government. Learned
counsel also submitted that the respondent would be entitled
| ment onl | y upon s |
|---|
dispute between the parties and to maintain a cordial
relationship, the parties have entered into a voluntary
settlement on 6-6-2003 which is evidenced by the signatures
appended on the same by the Manager of the respondent sub-
contractor. In such circumstances, learned counsel submitted
that there was no arbitrable dispute which could have been
left to the Arbitrator and, therefore, the judgment of the High
Court allowing the application under Section 11 (5) and (6) of
the Act is erroneous. He further submitted that in case the
JUDGMENT
respondent intend to challenge the validity of the binding
nature of the settlement, the dispute cannot be left to the
Arbitrator. The settlement would form an independent contract
which can only be nullified in appropriate proceedings being
taken by the respondent.
In support of the submissions, the learned counsel relied
1
on Nathani Steels Ltd. v s. Associated Constructions . Mr.
1
1995 Supp (3) SCC 324
Page 9
10
Kathpalia relied on the observations made in paragraph 3 of
the judgment. The learned Counsel submits that the judgment
of the High Court is erroneous and has to be set aside.
| other ha | nd, Mr. |
|---|
final settlement" of the amounts which were due to the
respondent from the appellant. He further submits that the
respondent had executed all the works which were entrusted
to his client to the full satisfaction of the appellant. The claim
and counter claim now made by the appellant is totally false
and without any basis. The respondent is disputing each and
every claim made by the appellant. Learned counsel further
submitted that the alleged settlement dated 6-6-2003 is a
unilateral document. There is no agreement between the
JUDGMENT
parties for a final settlement. The document has been only
received and the Manager has signed only to indicate that the
letter has been received. There have been no negotiations
between the parties prior to the issuance of letter dated 6-6-
2003. He submits that the judgment relied upon by Mr.
Kathpalia is not applicable in the facts of this case. In fact,
according to him, the matter is squarely covered by the
Page 10
11
judgment of this Court in National Insurance Company
2
Limited vs. Boghara Polyfab Private Limited . Learned
counsel has relied on paragraphs 33, 34 and 35 of the
| pointed o | ut that in |
|---|
(supra) and distinguished the same. Relying upon the
aforesaid judgment, the learned counsel submits that the
appeal deserves to be dismissed.
Learned counsel further submitted that the receipt of a
sum of Rs.16 lakhs subsequent to the letter dated 6-6-2003
does not signify the acceptance by the respondent of the
aforesaid letter as a "full and final settlement". According to
the learned counsel, in fact, the claim of the respondent was
for over Rs.10,00,000/- and, therefore, the amounts which
JUDGMENT
were received by the respondent were only in part payment of
the amount due.
We have considered the submissions made by the
learned Counsel for the parties.
In our opinion, the question as to whether letter dated 6-
6-2003 would constitute a "full and final settlement" would
2
(2009) 1 SCC 267
Page 11
12
have to be determined on proper appreciation of the evidence
led by the parties. It is, in our opinion, open to two
interpretations. Which of the two interpretations is ultimately
| ave to be | decided |
|---|
that if the alleged settlement is to be doubted, it cannot be
doubted before the Arbitrator. It must be remembered that the
appellant is relying on the alleged settlement by way of
defence. The respondent has not accepted the same. Nor has
the respondent denied the execution of the document. The
respondent has also not claimed that the full and final
settlement was signed under coercion, undue influence, fraud,
misrepresentation or mistake. Furthermore, the appellant had
not made a claim on the basis of the settlement. It would have
JUDGMENT
been different, if the appellant had made a claim on the basis
of settlement which was denied by the respondent by one or
more of the defences, as noticed above. In such
circumstances, following the judgment in Nathani's case
(supra), it would have to be held that the settlement can only
be challenged in "proper proceedings". But these observations
Page 12
13
would be applicable only if there was a clear cut acceptance
by the parties that there was a "full and final settlement".
In fact, the matter would be squarely covered against the
| e ratio of | the judg |
|---|
the cases which were earlier considered in Nathani's Steel
(supra) and observed as follows:-
"33. Nathani Steels related to a dispute on account
of non-completion of the contract. The Court found
that the said dispute was settled by and between
the parties as per deed dated 20.12.1980 signed by
both parties. The deed referred to the prior
discussions between the parties and recorded the
amicable settlement of the disputes and differences
between the parties in the presence of the Architect
on the terms and conditions set out in clauses 1 to 8
thereof. In view of it, the Court rejected the
contention of the contractor that the settlement was
liable to be set aside on the ground of mistake. A
three-Judge Bench of this Court, after referring to
the decisions in P.K. Ramaiah and Nay Bharat
Builders, held thus: (SCC p.326, para 3)
JUDGMENT
“3…….. that once the parties have arrived at a
settlement in respect of any dispute or difference
arising under a contract and that dispute or the
difference is amicable settled by way of a final
settlement by and between the parties, unless that
settlement is set aside in proper proceedings, it cannot
lie in the mouth of one of the parties to the settlement
to spurn it on the ground that it was a mistake and
proceed to invoke the Arbitration clause. If this is
permitted the sanctity of contract, the settlement also
being a contract, would be wholly lost and it would be
open to one party to take the benefit under the
settlement and then to question the same on the
ground of mistake without having the settlement set
Page 13
14
aside. In the circumstances, we think that in the
instant case since the dispute or difference was finally
settled and payments were made as per the
settlement, it was not open to the respondent
unilaterally to treat the settlement as non est and
proceed to invoke the Arbitration clause."
| requires<br>nd Natha | to be n<br>ni Steel |
|---|
36. In Damodar Valley Corporation, the question that
arose for consideration of this Court was as follows:
(SCC p. 144 para 4)
''where one of the parties refers a dispute or
disputes to arbitration and the other party
takes a plea that there was a final settlement
of all claims, is the Court, on an application
under Sections 9(b) and 33 of the Act, entitled
to enquire into the truth and validity of the
averment as to whether there was or was not a
final settlement on the ground that if that was
proved it would bar a reference to the
arbitration inasmuch as the arbitration clause
itself would perish."
JUDGMENT
In that case the question arose with reference
to a claim by the supplier. The purchaser required
the supplier to furnish a full and final receipt. But
the supplier did not give such a receipt. Even
though there was no discharge voucher, the
purchaser contended that the payments made by it
were in full and final settlement of the bills. This
Court rejected that contention and held that the
question whether there has been a settlement of all
Page 14
15
| o' or 'in c<br>ere is an<br>anding t | onnectio<br>arbitrat<br>he plea t |
|---|
and final settlement by the Respondent which has been relied
upon by the appellant, the issue clearly had to be left to the
Arbitrator to be adjudicated.
In view of the above, we find no merit in the appeal and
the same is accordingly dismissed.
JUDGMENT
Before we part with this matter, we would request the
learned Arbitrator to conclude the Arbitration Proceedings as
expeditiously as possible since the matter was referred long
back as this would be in the interest of justice.
..….….
…………………………..J.
(SURINDER SINGH NIJJAR)
Page 15
16
…...…………………………………J
(RANJANA PRAKASH
DESAI)
NEW DELHI,
NOVEMBER 28, 2013.
JUDGMENT
Page 16