Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
CASE NO.:
Appeal (civil) 1280 of 2007
PETITIONER:
BOC India Ltd
RESPONDENT:
Bhagwati Oxygen Ltd
DATE OF JUDGMENT: 12/03/2007
BENCH:
Dr.AR.Lakshmanan & Tarun Chatterjee
JUDGMENT:
J U D G M E N T
(Arising out of S.L.P. [C] No. 13662/2005 )
TARUN CHATTERJEE,J.
Leave granted.
This is an appeal from a judgment of a Division
Bench of the Calcutta High Court dismissing an appeal
which was filed against the judgment of a learned Judge
refusing to accept the objection filed by the appellant
under Section 30 read with Section 33 of the Arbitration
Act, 1940 (hereinafter referred to as the "Act").
The brief facts of this appeal are as follow:
BOC Ltd. being the appellant herein and one
Nippon Sansa K.K. (NSKK) entered into an agreement in
order to facilitate the respondent to import components
for setting up a 25 tons per day Oxygen plant at
Ghatsila, Bihar (now in the State of Jharkhand). In the
month of April/May 1990 the appellant and the
respondent entered into a contract for erection,
installation and commission of the aforesaid plant at
Ghatsila, Jharkhand. On 5th June 1990 a tripartite
meeting between the representatives of the appellant
and the respondent and NSKK were held where the
letter of intent was signed and purchase orders were
issued by the respondent in favour of the appellant. The
respondent awarded a turnkey contract on 6th June,
1990 to the appellant for manufacture, supply, erection
and commission of the said plant. Vide letter dated 18th
December 1990, the respondent had agreed to pay
interest on margin money and reimburse the same to
the appellant. The appellant thereafter on 31st March
1992 raised final invoices and subsequently on 13th
April 1992 the respondent raised claims and sought
refund from the appellant. By a letter dated 9th March
1993 the appellant informed the respondent indicating
therein the interest payable by them to the respondent.
Finally, when the prior invoice and letter were not
responded to, on 13th September 1993 the respondent
again raised claims and sought refund from the
appellant. When the refund was not made by the
appellant, the respondent made an application under
Sections 8 and 33 of the Act for the appointment of an
arbitrator on 24th November 1995 in the High Court at
Calcutta.
In the meantime, on 21st September 1995 the High
Court directed the appellant to release the spares to the
respondent on payment of Rs. 10,19,000/- by them. A
lawyer was thereafter appointed as Arbitrator by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
consent of the parties and the said arbitrator
subsequently was replaced on 12th February, 1996 by
Late Arbitrator Shri P.K. Roy. On 29th July 2000, Late
Shri Roy had passed his award in favour of the
respondent for a sum of Rs. 24,92,165/- with an
interest of 12 per cent on the amount. However, the
counter claim of the appellant was rejected.
On 30th October, 2000, the appellant filed an
application for setting aside the award passed by the
arbitrator under Section 30 of the Act before the High
Court at Calcutta. In the said application, the appellant
raised objection to the effect that the award in question
suffered errors apparent on the face of it. It was alleged
that the arbitrator erred in awarding the claim of the
respondent for a sum of Rs. 17,95,710/- relating to
claim no. 9 although the learned arbitrator held issue
no. 4 in favour of the appellant. It was also alleged that
since the appellant had not realised any sum in excess
of Rs. 50 lacs against indigenous supply, the award of
the learned arbitrator to the effect that the respondent
was entitled to receive back from the appellant, the said
sum of Rs. 17,95,710/-, was not only erroneous on the
face of the award but also contradictory and
inconsistent with the findings of the arbitrator against
issue no. 4. It was further alleged by the appellant
under Section 30 of the Act that the learned arbitrator
committed error apparent on the face of the award and
had acted in excess of his jurisdiction by awarding the
aforesaid sum of Rs. 17,95,710/- in favour of the
respondent as the award was contrary to the findings
made by the learned arbitrator himself and therefore
was liable to be set aside. We are not dealing with the
other objections taken by the appellant in its objection
under Section 30 of the Act as noted herein after. A
learned Judge of the High Court by a detailed judgment
had rejected the objection filed under Section 30 of the
Act and had refused to set aside the award passed by
the arbitrator on the ground that on the materials on
record, the award was not liable to be set aside on such
grounds.
Feeling aggrieved by the judgment of the learned
Single Judge, the appellant filed an appeal before the
Division Bench of the High Court which was also
dismissed against which the present Special Leave
Petition was filed in respect of which leave has been
granted.
We have heard Mr. Soli J. Sorabjee, learned senior
counsel appearing for the appellant and Mr. Bhaskar P.
Gupta, learned senior counsel appearing for the
respondent. We have also considered the award passed
by the Sole Arbitrator Late Mr. P.K. Roy and the
objection raised against such award under Section 30 of
the Act and also the judgment of the learned Single
Judge as well as the Division Bench of the High Court
in detail.
Before we proceed further, as noted herein earlier,
we keep it on record that before the Division Bench of
the High Court, the appellant restricted his grounds for
setting aside the award in respect of Claim No.9 of the
statement of claim only and prayed for the same. Before
us, Mr. Sorabjee also restricted his submissions only in
respect of Claim No.9 of the statement of claim and also
prayed for setting aside the award restricted to Claim
No.9 only. In view of this stand taken by the appellant,
we need not dwell upon other questions and are
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
concentrating only on the issue raised before us by the
learned senior counsel appearing for the appellant.
As noted, we may reiterate that the respondent
placed Purchase Order (P.O.) dated 6th of June, 1990 to
the appellant for supply, installation and commissioning
of oxygen plant at a lump sum price of Rs.347.40 lacs.
This fixed price was, however, subject to variation only
in respect of imported components of supply on account
of exchange rate variation and customs duty variation.
This would be evident from clause 1.1 of the P.O. as
quoted herein after. It is not in dispute that the job was
completed in June/July, 1992.
Due to variation in exchange rate and also in
customs duty, the lump sum price of Rs.347.40 lacs
increased to Rs.4,62,60,543. The appellant submitted
its bill inclusive of taxes as per the contract and the
break up which is as follows:
" A. Annexure 1
Invoice No. 3224 Rs.4,62,60,543/-
B. Invoice dated 31.3.1992 Rs. 5,91,625/-
C. Taxes paid as per contract
(as mentioned in Invoice
No.3225 and 3227) Rs. 6,25,984/-
=============
Total Rs.4,74,78,152/-"
=============
As stated herein earlier, in view of the arbitration
clause accepted by the parties, the respondent had
raised a dispute after payment and the matter was
referred to arbitration. The respondent submitted its
claim before the arbitrator under 12 heads for a total
amount of Rs.1,79,76,716/-. The appellant also
submitted its counter claim. The sole arbitrator Late
Shri P.K.Roy passed an award on 29th of July, 2000, as
noted herein earlier and allowed the claim of the
respondent in respect of the following items:
"A. Claim No.1: Interest
on margin money Rs.1,80,000/-
B. Claim No.3: Bank charges
and interest Rs.3,10,932/-
C. Claim No.7: Refund
on REP Licence Rs. 35,000/-
D. Claim No.8 : Foreign Technician
fees, Air fare, hotel expenses Rs. 1,70,523/-
E.Claim No.9 Indigenous Supply Rs.17,95,710/-
===========
Rs.24,92,165/-"
===========
As noted herein earlier, the arbitrator, however,
dismissed all other claims of the respondent and also
the counter claim of the appellant.
Mr. Sorabjee contended that since the award in
question was contrary to the findings of the learned
arbitrator himself, the learned arbitrator in passing the
award had misconducted himself and accordingly the
award was arbitrary and liable to be set aside in respect
of claim No.9 of the respondent.
Mr. Sorabjee had drawn our attention to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
purchase order, which contained price for manufacture
and supply of plant and equipment comprising both
imported and indigenous components for installation,
erection and commissioning thereof. He had also drawn
our attention to the fact that a lump sum of Rs.379.49
lacs was fixed as a price for doing the job. The ’basis of
price’ is mentioned in Clause 1.1. of the contract
which is as follows :-
"Basis of price includes \026
1.1.1 -The value of the imported components will be
128.66 million YEN CIF Calcutta.
1.1.2 Customs duty @ 80% of CIF value based on
’Project Import".
1.1.3 Stevedoring, port handling, customs
clearance, inland transportation and transit
insurance from port to site @ 5% of CIF Value.
1.1.4 Exchange rate has been taken at 100 yen
Rs.10.9.
1.1.5 The price includes excise duty towards
supply wherever applicable as on date, but
does not include sales tax, entry tax, income
tax on foreign technicians and other Govt.
impositions, if any, which will be paid extra,
as applicable.
1.1.6 Any variation in 1.1 to 1.1.5 except 1.1.3
indicated above will be adjusted.
1.1.7 The premium of Rs.5 lakhs towards purchase
of REP Licences is the maximum amount
payable by us. Any decrease below RS.5
lakhs will be passed on to us.
1.1.8 The above price is also subject to ’General
Conditions of sale and installation of Plant
and Equipment’. In the event of any conflict
between the clauses, one mentioned herein
shall prevail. Where General Conditions are
not applicable, have been marked accordingly
and initiated by competent authority."
Clause 4 of the contract contains Terms of Payment.
Indigenous supply is included in clause 4.4 which reads
as following-
"Supply Portion - Rs.50 lacs.
10% advance against order.
10% advance within 3
months.
80% advance against proforma
invoice before dispatch.
4.5 For Erection and Rs.15 lakhs.
commissioning \026 10% advance against order
10% advance on opening of site
70% pro rata on monthly
basis.
10% on completion of erection
and commissioning."
In the statement of claim, as made by the
respondent, the value of projected imported components
worked out to Rs.264.44 lacs in the order shown below
:-
"(i) CIF value of JY 128.66 million Rs.1,40,23,940/-
(ii) Handling charges @ 5% of CIF- Rs. 7,01,198/-
(iii) Import Duty @ 80% (based on
Project Import) Rs.1,12,19,152/-
(iv) REP Licence premium Rs. 5,00,000/-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
=============
Total Rs.2,64,44,290/-"
=============
In the said statement of claim the total value of
the order worked out as imported components
(Rs.264.44 lacs) plus indigenous components (Rs.50
lacs) plus erection and commissioning (Rs.15 lacs)
comes to Rs.329.44 lacs. But the value was kept at
Rs.347.40 lacs, i.e., a cushion money of Rs.18 lacs
approximately was provided for securing the forward
cover for foreign exchange and other variations.
In paragraph 21 of the said statement of claim, the
respondent stated that under the aforesaid order, the
appellant was required to supply indigenous
components plants and machinery as set out in Clause
2.1.2 to 2.3.4 of the order for a sum of Rs.50 lacs. The
appellant further stated that the indigenous supply was
not subjected to variation as per the order. The
appellant contrary to and in breach of the said order
raised invoices for a sum of Rs.67,95,710/- against
indigenous supply and realized an excess amount of
Rs.17,95,710/- from the respondent. Therefore, the
respondent claimed refund of Rs.17,95,710/- from the
appellant.
According to Mr. Sorabjee, the learned Arbitrator
had misconducted himself in passing the award under
Section 30(1)(a) of the Act and thus the award was liable
to be set aside so far as Claim No.9 (Award No.9) of the
Arbitrator is concerned. According to Mr. Sorabjee, the
award in respect of Award No.9 is contrary to the
findings of the learned Arbitrator and liable to be set
aside as it amounted to judicial misconduct. As noted
herein earlier, purchase order dated 5th June, 1990
provided for a lump sum price of Rs.347.40 lacs subject
to variation of importation of the contract and exchange
rates. He further submitted that since price was a lump
sum amount no specific price could be allotted to a
particular item. He contended that the value of Rs.50
lacs and Rs.15 lacs mentioned against indigenous
supply under Clause 4.4 of the P.O. and against
erection and commissioning mentioned in Clause 4.5 of
the P.O. was not appearing as a component of price but
appearing as "terms of payment" (4.0 of P.O.).
Accordingly, Mr. Sorabjee sought to contend that the
Arbitrator had gone beyond his jurisdiction in awarding
Rs.50 lacs and Rs.15 lacs, mentioned against
indigenous supply and against erection and
commissioning, as the same was not appearing as
’component of price’. Therefore, he had misconducted
himself in awarding the amount in respect of Award
No.9 (Claim No. 9 of the Statement Of Claim). In
support of this contention, Mr. Sorabjee relied on a
decision of this Court in K.P. Poulose vs. State of
Kerala, [1975 (2) SCC 236]. Mr. Sorabjee particularly
relied on para 6 of the judgment and submitted that the
Arbitrator was guilty of legal misconduct as he had gone
beyond his jurisdiction to pass an award on Claim No.9.
This submission of Mr. Sorabjee was contested by
Mr. Bhaskar P. Gupta, learned Senior Counsel,
appearing on behalf of the respondent. Mr. Gupta
contended that considering the terms of the contract, it
cannot be said that the Arbitrator had acted beyond his
jurisdiction in passing the award in respect of Claim
No.9. So far as the decision of this Court, relied on by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
Mr. Sorabjee, is concerned, Mr. Gupta submitted that
this decision cannot be applied in the facts and
circumstances of the present case. In that decision,
according to Mr.Gupta documents produced before the
Arbitrator were contrary to the award passed. In this
connection, Mr. Gupta had also drawn our attention to
the fact that the arbitrator in that case had ignored two
very material documents resulting in miscarriage of
justice. If we read para 6 of this decision carefully we
will find that the principle which was laid down in the
decision was that an award could be set aside on the
ground that the arbitrator had misconducted himself
when it was found that the arbitrator on the face of the
record arrived at an inconsistent decision even on his
own finding or arrived at a decision by ignoring very
material documents which throw abundant light on the
controversy to help in arriving at a just and fair
decision. Keeping this principle in mind, this court held
that the arbitrator had misconducted the proceedings in
that case.
This is not the position in the present case. For
deciding this question, it would be necessary for us to
look into the P.O. Clause 4.0 contains "terms of
payment". Clause 4.4 of the P.O. contains the
indigenous supplies which clearly indicates Rs.50
lacs would be the advance at the rate of 10% against the
date of order within 30 days and 10% advance within
three months and 80% advance against proforma
invoice before dispatch. Clause 4.5 of the terms of
payment provides for erection and commissioning which
indicates Rs.15 lacs in respect of which 10% advance
against order, 10% advance on opening of site, 70% on
pro rata on monthly basis, 10% on completion of
erection and commissioning. The Arbitrator had taken
into consideration the claim of the respondent on
indigenous supplies. He had also taken into
consideration the total value of the contract which was
Rs.347.40 lacs.
A bare perusal of the award of the Arbitrator
would show that he had considered the figure of
17,95,710/- which is included in the lump sum
contract price as consideration payable to the
respondent for services rendered by it towards
importation of plants components. From the award it
will also be evident that in respect of the claim of
Rs.17,95,710/- against indigenous supply attention was
drawn to the works given in para 10 [a], 10 [b] and 10
[c] of the statement of claim. If we assign individual
value to the individual jobs, the total works out to
Rs.3,29,44,290/- leaving a balance of Rs.17,95,710/-.
The learned Arbitrator in his award also
considered that the break-up was an admitted position
which would appear from para 10[c] of the Statement of
Claim and the sum of Rs.17,95,710/-, the appellant
had recovered under the bill issued against indigenous
supply and the respondent paid the amount without
any objection. While the Arbitrator has considered the
fact that the appellant had realised the differential
amount of Rs.17,95,710/- from the respondent against
indigenous supply, it cannot be said to mean that the
value of indigenous supply had gone up from Rs.50 lacs
to Rs.67,95,710/- as according to the terms of the
contract the value of indigenous supply remained at
Rs.67,95,710/- and the appellant realised the
differential amount of Rs.17,95,710/- against
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
indigenous supply. Accordingly the Arbitrator was
justified in holding that the said sum of Rs.17,95,710/-
was on account of expenses that might have been
incurred by the respondent in executing the contract.
In the case of Trustees of the Port of Madras Vs.
Engineering Construction Corporation Ltd. [AIR 1995
SC 2423], while this Court dealing with a situation
when an award can be set aside under Section 30 of the
Arbitration Act
held as under:
"The above decisions make it clear that the
error apparent on the face of the award
contemplated by Section 16 (I) (c) as well as
Section 30(c) of the Arbitration Act is an error of
law apparent on the face of the award and not
an error of fact. It is equally clear that an error
of law on the face of the award means an error
of law which can be discovered from the award
itself or from a document actually incorporated
therein. A note of clarification may be
appended viz., where the parties choose to
refer a question of law as a separate and
distinct matter, then the Court cannot interfere
with the award even if the award lays down a
wrong proposition of law or decides the
question of law referred to it in an erroneous
fashion. Otherwise, the well settled position is
that an arbitrator "cannot ignore the law or
mis-apply it in order to do what he thinks is
just and reasonable." (See Thawardas Perumal
v. Union of India, (1955)’-) SCR 48: (AIR 1955
SC 468)."
In paragraph 20 of the said decision this Court
also held that the proposition that emerges is that in the
case of a reasoned award, the Court can interfere if the
award is based upon a proposition of law which is
unsound in law and that the erroneous proposition of
law must be established to have vitiated the decision. It
has also been held in that decision that the error of law
must appear from the award itself or from any
document or note incorporated in it or appended to it.
This Court also held that it was not permissible to travel
and consider materials not incorporated or appended to
the award. So far as the facts of the present case are
concerned, we do not think that the award of the
Arbitrator can at all be interfered with as the award was
not based upon either a proposition of law which is
unsound or an erroneous proposition of law was
established to have vitiated the decision. As noted
herein earlier, the Arbitrator had considered all aspects
of the matter including the terms of the contract and all
the materials on record and the statement of claim and
has come to a conclusion of fact. Such being the
position, we cannot but hold that the award was not
based upon a proposition of law which is unsound or an
error of law must have appeared from the award itself or
from any document or note incorporated in the award or
appended to it.
That apart, according to the Arbitrator, this figure
was nothing but a mark up which the parties agreed to
keep in the contract for rendering of service towards
importation of plant components from Japanese
supplies. The appellant had realized this difference
amount of Rs. 17 lacs from the respondent against
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
indigenous supplies. Therefore, it was not the case that
the arbitrator had misconducted himself in passing the
award by ignoring to consider material documents,
which had thrown light on the controversy raised by the
parties. As noted herein earlier, the arbitrator had
looked into the terms of the contract, arbitration clause
and the statement of claim of the respondent disputed
by the appellant. It was not the case that the arbitrator
had decided erroneously a question of law referred to
him but on consideration of the terms of contract and
statement of claim came to a conclusion that Claim No.
9 of the respondent should be awarded in its favour.
Such being the position, we do not find any reason to
interfere with the award of the arbitrator which was
passed on consideration of all material put on record.
In this view of the matter, it is not open to the
court to set aside the award on the ground that the
learned Arbitrator had, while continuing with the
proceeding, acted beyond his jurisdiction and violated
the contract while awarding Rs. 17,95,710/- in the form
of Award No.9. In our view, this cannot be said to have
an award, which is contrary to the contract entered into
by the parties. It is also not the case where the learned
Arbitrator had failed to consider material documents
produced by the parties for arriving at a right decision.
On the other hand as noted herein earlier, we are of the
considered view that the Learned Arbitrator had duly
considered the statement of claim and the terms and
conditions of the contract and the material documents
produced by the parties, which were available on record,
and came to a conclusion rightly in favour of the
respondent. The Learned Arbitrator also came to a
conclusion that the aforesaid figure of Rs. 17,95,710/-,
was included as lump sum contract price as
consideration payable to the respondent for service
rendered by them for importation of plants and
components. In any view of the matter, when the
Arbitrator had taken a plausible view on interpretation
of contract, it is not open to the court to set aside the
award on the ground that the Arbitrator had
misconducted himself in the proceedings and therefore,
the award was liable to be set aside.
In Indu Engineering and Textile Limited vs.
Delhi Development Authority [2001 (5) SCC 691] this
court laid down a principal when the court could set
aside an award in the exercise of its powers under
Section 30 of the Act. This court in the said decision
held that when a plausible view had been taken by the
arbitrator and unless the award of the arbitrator was
vitiated by a manifest error on the face of the award or
was wholly improbable or perverse, it was not open to
the court to interfere with the award within the
statutory interpretation set out in Section 30 of the Act.
That apart, the amount of Rs.17,95,710/- was
recovered by the appellant under the bill issued against
indigenous supplies and amount were paid without any
objection by the respondent. Such being the position we
are unable to agree with Mr. Sorabjee that the award
was liable to be set-aside on the aforesaid ground.
We, therefore, do not find any merit in this appeal.
The appeal is dismissed without any order as to costs.