UTPAL TREHAN vs. DLF HOME DEVELOPERS LTD.

Case Type: Civil Appeal

Date of Judgment: 11-07-2022

Preview image for UTPAL TREHAN vs. DLF HOME DEVELOPERS LTD.

Full Judgment Text

REPORTABLE                            IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION  CIVIL APPEAL NO. 4690 OF 2022 (Arising out of SLP (C) NO.19226 OF 2021) UTPAL TREHAN   .... APPELLANT(S) VERSUS DLF HOME DEVELOPERS LTD.        .... RESPONDENT(S) WITH CIVIL APPEAL NOS. 4691­4692 OF 2022 (Arising out of SLP (C) NOS.5871­5872 OF 2022)      J U D G M E N T ANIRUDDHA BOSE, J. Leave   is   granted   on   the   limited   question   which   was formulated by this Court at the time of issue of notices, by the rd order passed on 3  January 2022 in SLP (C) No.19226 of 2021. So far as SLP (C) Nos.5871­5872 of 2022 are concerned, leave is granted on the point on which the appellants thereof had Signature Not Verified Digitally signed by Rajni Mukhi Date: 2022.07.11 18:49:20 IST Reason: th confined their grievances, recorded in our order passed on 19 1 April,   2022.   We   shall   refer   to   these   points   later   in   this judgment.   The   controversy   which   we   shall   address   in   this judgment revolves around the quantum of compensation that the appellant in SLP (C) No.19226 of 2021 (now appeal) would be entitled to receive because of delay in delivery of possession of a flat as also the appellant’s obligation to pay maintenance charges in respect thereof.  The specific disputes giving rise to these appeals relate to 2. rd an Apartment Buyers’ Agreement, executed on 3   December, 2008 between Utpal Trehan (whom we shall henceforth refer to as “allottee”) and DLF Home Developers Limited (we shall refer to   them   as   the   “builder”)   for   purchase   of   a   flat,   within   a complex named New Town Heights in Sector­91, Gurgaon (now Gurugram),   Haryana.   This   was   booked   by   the   allottee   on depositing a sum of Rs.5 lakhs in March 2008. The allotment th letter was issued on 16  April 2008, and allocation was made of Apartment No. GBD­153 along with its parking.   As per the Apartment Buyers’ Agreement, the area of the flat was to be 1760 square feet (super area). The consideration amount was Rs.45,12,000/­,   to   be   paid   as   per   instalment   payment  plan 2 forming   part   of   the   Agreement.   The   stipulation   relating   to possession of the flat is contained in Clauses 11 and 17 of the said   Agreement.     A   copy   of   the   draft   Agreement   has   been annexed to the allottee’s paper book. In substance, the time for possession has been stipulated to be within 36 months from the   date   of   execution   of   the   Agreement   subject   to   certain qualifications   and   exceptions   incorporated   in   the   Agreement itself. This date of delivery of possession, along with the effects thereof, underwent certain changes, as there was delay on the part of the builders in getting certain regulatory clearance. Mr. Pinaki Mishra, learned Senior Advocate has appeared for the builder and the allottee has appeared in person before us. 3.   The facts forming genesis of the grievances of the allottee have   been   summarised   in   the   decision   of   the   National Consumer   Dispute   Redressal   Commission   (“National rd Commission”)   delivered   on   23   July   2021,   which   is   under appeal before us. We quote below the relevant passages from this decision:­ 12.   ….. The allotment letter dated 16.04.2008 and Annexure­3   to   the   Apartment   Buyer’s   Agreement dated 03.12.2008 provided a "Time Linked Payment Plan”   under   which   95%   of   the   sale   consideration 3 (including Rs. 5,00,000/­ of booking amount) had to be paid in 11 instalments starting from 29.05.2008 and   ending   on   29.06.2010.   Vide   Clause­12   of   the Allotment Letter dated 16.04.2008 and Clause­11 of Apartment Buyer's Agreement dated 03.12.2008, the possession had to be handed over within 36 months from the date of agreement. Environment Clearance Certificate was delayed as such the builder could not start construction till May, 2009, i.e. more than one year from booking. In such circumstances, the builder through letter dated 26.03.2009, amended the terms of the agreement and the payment of the instalments were   changed   as   “construction   Linked   Payment Plan”.  The   builder   has   simultaneously   provided various benefits to the buyers, i.e. Advance Payment Rebate in the shape of interest at the rate of 13% p.a. on the amount in excess of 35% of sale price as on 26.03.2009, 5% discount of basic sale price, increase of   approximately   5%   area   and   compensation   for delayed possession @ Rs.10/­ per Sq. ft. per month from   the   date   of   expected   possession   till   actual possession and Timely Payment Rebate, equivalent to 10% basic sale price. Letter dated 23.06.2009 and statement of account dated 10.06.2013 prove that the benefits of (i) Rs.9059/­ as Advance Payment Rebate, (ii) Rs. 1,98,000/­ as 5% discount of basic sale price and (iii) increase of 5% area have been given to the complainant.    The complainant argued that “Timely Payment 13. Rebate” and “compensation for delay in possession” had not been given in statement of the account dated 10.06.2013,  for which he was entitled. The builder has denied the Timely Payment Rebate on the ground that   in   spite   of   service   of   demand   letter   dated 29.12.2011, the amount due was not deposited till last date i.e. 18.01.2012, rather it was deposited on 27.01.2012 (without including the amount of interest accrued   on   it   in   the   meantime).   As   the   time   was essence   of   contract   and   this   instalment   was   not deposited in time as such the complainant was not entitled for Timely Payment Rebate.” (quoted verbatim from paperbook) 4 We   shall   discuss   separately   the   position   of   the   respective parties as regards obligation of the allottee to pay maintenance charges. 4. The allottee had approached the Delhi State Consumer Disputes Redressal Commission (“State Commission”), in the month of May 2015, after the builder had raised additional demands under different heads. As per the allottee, the total sum,   as   demanded,   added   upto   Rs.9   lakhs   approximately. Otherwise, the allottee claims to have had cleared the requisite instalments.  At that point of time, the main complaint of the allottee   was   of   being   deprived   of   certain   payment   related benefits on being offered possession of the flat.  He was being denied these benefits, since as per the builder, the allottee had made default in payment within the due date on demand of the developer of the ensuing instalment. As would be apparent from the said passages of the decision under appeal, the builder’s th contention   is   that   by   a   notice   of   29   December   2011,   the th allottee was to pay the next instalment by 18  January 2012, th but   this   was   paid   on   27   January   2012.   The   builder   thus alleged nine days’ delay. The allottee’s stand on this count, on 5 th the other hand, was that he had not received the notice of 29 nd December 2011, but on receiving a reminder on 22  January th 2012, he cleared the dues on 27  January of that year. 5. The delivery and payment stipulations were modified on account of delay in getting environmental clearance and these modifications, as made by the builder, has been summarised in the   passage   quoted   above   from   the   National   Commission decision. So, we are avoiding a repeat of these modification terms in this judgment. 6. Before the State Commission, the allottee prayed for the following reliefs:­ “4. …….   i.   Give the possession of the said flat at the earliest. ii.  Pay an amount of Rs. 10,00,000/­ as compensation for causing mental trauma and agony to complainant due to delay in giving the possession. iii.   Also pay additional delayed possession rent  @ Rs. 15/­ sq. ft. till the possession is offered to complainant. iv.   Further   waive   of   the   undue/unjustifiable   demand already raised towards the final dues settlement. v.  To pay Rs. 50,000/­ towards the expenses incurred by the complainants towards telephonic communications and personal visits made to OP since 2006.  6 vi.  To pay a sum of Rs. 75,000/­ towards the payment of litigation expenses.” (quoted verbatim from paperbook) During   pendency   of   the   proceeding   before   the   State 7. Commission, an application was filed by the builder to bring on record   certain   subsequent   events.   What   was   sought   to   be brought   on   record   included   crediting   to   the   allottee compensation for delayed possession of Rs.4,22,816/­, Timely Payment Rebate of Rs.4,02,076/­ and interest of Rs.14,082/­. This application also highlighted that certain sum of money was already credited to the allottee’s account under the head of Early Payment Rebate. This application also showed the liability of   the   complainant   (i.e.   the   allottee)   of   Rs.3,16,899/­   as maintenance   charges,   Rs.96,000/­   as   IBM   charges   and Rs.14,18,203/­   as   holding   charges.   The   said   application appears   to   have   been   filed   subsequent   to   an   attempt   at mediation   while   the   dispute   was   pending   before   the   State Commission. 8. The State Commission found that there was deficiency in service and the complaint was allowed in following terms:­ 7 “20. ……  i.  OP shall issue fresh offer of possession of the apartment in question i.e. GBD­153, New Town Heights in Sector­91, Gurgaon to the complainant and shall handover the possession of the apartment to the complainant within a period of 06 weeks.  ii.  OP shall also execute the sale deed/conveyance deed and get it registered in the name of the complainant on payment of stamp duty, registration charges and  other incidental charges, if any, by the complainant, within a period of one month thereafter. OP shall pay to the complainant the delayed compensation @ Rs. 10/­ per sq. ft. per month for the delayed period from the agreed date of possession i.e. March, 2011 till the date   of   fresh   offer   of   possession   after   adjusting   the delayed compensation already paid to the complainant.” (quoted verbatim from paperbook) 9. On the question of maintenance charges, however, the State Commission went against the allottee, holding : ­ 19.   As   regards   payment   of   Rs   3,16,899/­   towards maintenance charges, and Rs.14,18,204/­ toward holding charges @ Rs. 10 per square feet till 11.10.2018, as is stated in the aforesaid handing over the cheque issued earlier a new cheque can be issued against the same.  As   on   date,   the   complainant   is   liable   to   make   the following payment as per the agreement: i. Maintenance charges (till 30.09.2018) – Rs.3,16,899. ii. IBMS (Interest Bearing Maintenance Security) – Rs. 96,000/­ iii.   Holding   Charges   (@   Rs.   10/­   per   sq.   ft.   till 11.10.2018) – Rs.14,18,203/­. However, upon suggestions from this Hon’ble Commission, the   opposite   party   shall   consider   waiving   the   holding charges accruing day by day and hence, nothing remains payable to the opposite party. The maintenance security and the maintenance charges incurred towards upkeep of the   multi­storey   building   as   mentioned   above   shall   be payable   to   the   Condominium   Association   who   are maintaining   the   property   inquestion   since   the   date   the 8 property   was   ready   for   possession   and   was conveyed/offered to the complainant.” (quoted verbatim from paperbook) One of the critical issues which was examined by the 10. State Commission was as to whether there was any delay in payment   of   instalment   by   the   allottee   upon   demand   being made.   This question arose as the builder had denied certain benefits to the appellant which would have accrued to him if timely   payment   of   instalments   was   made   on   demand.   The th builder alleged that the demand in this case was made on 29 th December 2011 requiring the allottee to make payment by 18 January 2012. As we have already discussed, the allottee took th the   plea   that   the   letter   of   29   December   2011   was   never th received by him and when he received a reminder letter of 19 nd January 2012 on 22  January 2012, he made the payment on th 27   January   2012,   factoring   in   certain   holidays   which intervened.   The   State   Commission   examined   this   issue   and gave   a   finding   on   fact   that   the   material   on   record   did   not th establish that the demand notice of 29   December 2011 was served   on   any   adult   family   member/known   person   of   the allottee and that the developer had failed to prove service of 9 demand notice upon the allottee. The State Commission thus held   that   the   allottee  could   not   be   deprived   of   the   benefits th outlined   in   the   builder’s   letter   of   26   March   2009   on   the allegation of failure to pay instalment within due date.  11. The appeal of the allottee to the National Commission was mainly against the finding given by the State Commission on maintenance charges. The builder questioned legality of that part of the decision of the State Commission under which they were directed to issue fresh offer of possession and payment of delayed compensation. 12. The   National   Commission   partly   allowed   both   the appeals, inter­alia holding:­  “In view of aforementioned discussions First Appeal No. 1530 of 2019 is partly allowed and First Appeal No. 1638 of 2019 is partly allowed. DLF Home Developers Ltd., (the builder) is directed to (i) offer possession of the apartment in   dispute   to   the   complainant   afresh   and   hand   over possession to the complainant within 6 weeks and execute the sale/conveyance deed in his name, within one month thereafter, on payment of stamp duty, registration charges and other incidental legal charges, (ii) pay compensation for delay in possession, i.e interest @ Rs. 6%­ per annum on the sale price deposited by him for the delayed period from July, 2013 till the date of fresh offer of possession, adjusting   “Early   Payment   Rebate”   of   Rs.95,136/­   as mentioned in statement of account dated 10.06.2013 and (iii) pay “Timely Payment Rebate” i.e 10% of basic sale price.   The   builder   is   entitled   to   realise/adjust   the Maintenance charges, from the date of issue of Occupation 10 Certificate   and   cost   of   increased   area   (i.e.   the   area increasing to 5% of the increased area). The builder shall pay a cost of Rs.50,000/­ to the complainant to meet out his litigation and other expenses.” (quoted verbatim from paperbook) 13. So far as the allotee’s appeal is concerned, (arising out of SLP (C) No.19226 of 2021) at the time of issue of notice, this Court had passed the following order:­ “Heard petitioner in person.  Issue   notice   limited   to   the   question   of   maintenance charges as provided for by NCDRC in the concluding part of the order impugned. Notice may be made returnable in four weeks. Dasti service in addition to order in process permitted.”   In the appeal filed by the builder, at the stage of issue of 14. notice on the petition for special leave to appeal, it was recorded th in   our   order   of   19   April   2022   that   the   learned   counsel appearing   for   the   petitioner,   (i.e.,   the   builder)   essentially confined   his   submissions   to  the   grievance  of   the   petitioner­ developer   in   regard   to   the   directions   by   the   National Commission and the State Commission for making ‘a fresh offer of possession’. We have indicated earlier in this judgment that we are granting leave restricted to these two questions only. 15. We shall first deal with the question of directions to pay to the builder maintenance charges. In the definition Clause 11 and Clauses 19, 20 and 39 of the Apartment Buyer’s Agreement rd dated 3  December 2008, it has been specified:­ “Definitions ……   means   DHDL   or   association   of Maintenance   Agency" allottees   or   such   other   agency/body   to   whom   the maintenance of the Said Building/Said Complex (including common areas and facilities) is handed over by DHDL and who shall be responsible for providing the maintenance services within the Said Building /Said Complex and who shall be entitled to collect the Maintenance Charges.” “19.  Maintenance   of   the   Said   Building/Said Complex/Said Apartment In order to provide necessary maintenance services, upon the completion of the Said Building/ Said Complex the maintenance of the Said Building/Said Complex may be handed over to the association of Apartment allottees or such   other   agency/   body/   company/   association   of condominium. The Allottee agrees to execute Maintenance Agreement (draft given in Annexure VII to this Agreement) with   the   Maintenance   Agency   or   any   other   nominee/ agency or other body/ association of Apartment owners as may   be   appointed   by   DHDL   from   time   to   time   for   the maintenance   and   upkeep   of   the   Said   Land/the   Said Building/the Said Complex. This Agreement shall not be deemed to be executed till the same is signed by all the parties. The Allottee further undertakes to abide by the terms and conditions of the Maintenance Agreement and to pay promptly all the demands, bills} charges as may be raised   by   the   Maintenance   Agency   from   time   to   time. DHDL reserves the right to change, modify, amend, impose additional conditions in the Maintenance Agreement at the time of its final execution. The Maintenance Charges shall become   applicable/   payable   from   the   date   DHDL   has received the occupation certificate/the date of allotment whichever is later. It is further clarified that DHDL may at its sole discretion hand over the maintenance of the Said Building/   Said   Complex   to   anybody/association   of Apartment   owners   of   the   Said   Building/Said   Complex including   but   not   limited   to   any   body/   association   of condominium of the Said Building/ Said Complex, as the case may be, at any time before/ after the construction of 12 the Said Building/ Said Complex is complete either for each   building   or   for   the   entire   Said   Complex   and   the Allottee specifically gives his consent to this proposal. It is further   specifically   clarified   that   the   draft   Maintenance Agreement, set out in Annexure VII to this Agreement is merely  an  indicative   Agreement  that   is  proposed   to  be entered into with the Allottee for maintenance and upkeep of the Said Building/ Said Complex, however, if at any time,   after   having   taken   over   the   Said   Building/   Said Complex,   the   said   association   of   Apartment   owners/ condominium of association decides to modify, alter, add, delete any one or more of the terms and conditions of the Maintenance Agreement, the Allottee shall not have any objection to the same and shall execute the Maintenance Agreement as may be required by the Maintenance Agency or   association   of   Apartment   owners   or   association   of condominium or its nominees or assigns. 20. Fixation of total Maintenance Charges The   total   Maintenance   Charges   shall   be   more elaborately described in the Maintenance Agreement (draft given in Annexure VII). The Maintenance Charges shall be levied from the date of occupation certificate or the date of allotment, whichever is later and the Allottee undertakes to pay the same promptly. It is agreed by the Allottee that the payment of Maintenance Charges will be applicable whether or not the possession ofSaid Apartment is taken by   the   Allottee.   The   Maintenance   Charges   shall   be recovered on such estimated basis which may also include the overhead cost on monthly/quarterly intervals as may be   decided   by   the   Maintenance   Agency   and   adjusted against   the   actual   audited   expenses   as   determined   at every end of the financial year and any surplus/deficit thereof   shall   be   carried   forward   and   adjusted   in   the maintenance bills of the subsequent financial year. The estimates of the Maintenance Agency shall be final and binding   on   the   Allottee.   The   Allottee   agrees   and undertakes to pay the maintenance bills on or before due date as intimated by the Maintenance Agency. …… 39. Association of apartment owners The Allottee agrees and undertakes to join association/ society   of   apartment   owners   as   may   be   formed   by DHDL/Company on behalf of Apartment owners and to pay any fees, subscription charges thereof and to complete such documentation and formalities as may be deemed necessary by DHDL/ Company for this purpose.” 13 (quoted verbatim from paperbook) 16. Annexure VII to that Agreement appears at Page 185 of the paperbook in SLP (C) No. 19226 of 2021, which is in the form   of   a   draft.   The   actual   copies   of   the   Agreements,   if executed, have not been annexed to the paperbooks filed in either of these two appeals. No material has otherwise been produced   before   us   to   show   if   the   Maintenance   Agreement (Annexure VII to the main Agreement) was executed or not. Be that   as   it   may,   even   if   we   proceed   on   the   basis   that   the maintenance Agreement is applicable, the same constitutes a tripartite Agreement involving the builder, New Town Heights Condominium   Association,   a   registered   society   and   the purchaser. This is in the format of a standard form Agreement with several portions thereof left blank. In the counter affidavit of the builder, it has been stated that the maintenance charges are   not   paid   to   them   but   to   the   statutory   condominium association   of   allotees   who   actually   renders   maintenance services   recovered   from   each   allotee.   That  association   to  us appears to be an independent body and there is nothing on record   to   demonstrate   that   such   association   is   an   agent   of 14 either   the   builder   or   the   purchasers.   In   Clause   39   of   the Apartment   Buyers’   Agreement,   there   is   hint   that   such   an Association might be formed by the builder but no particular of its formation, or for that matter, its existence have been shown before us at the time of hearing.  17. The definition of Maintenance Agency means “DHDL (the builder) or association of allottees or such other agency…….” but the conjunction “or” as has been applied in the definition clause   ought   to   mean   in   the   alternative   and   this   definition cannot be construed to infer that even after handing over the maintenance work to an association, the builder shall continue to   remain   as   a   maintenance   agency   entitled   to   collect maintenance charges. The clause relating to fixation of total maintenance charges only specifies the obligation of an allottee to pay such charges and the substantive Agreement specifies again that the maintenance charges would be payable to the maintenance agency.  18. In   so   far   as   the   subject   dispute   is   concerned,   the builder’s case, as stated above, is that the maintenance agency is to receive the maintenance charges but no specific case has 15 been made out that the builder themselves are carrying on the maintenance work, which could have brought them within the definition of maintenance agency under the main Agreement. In such circumstances, we are unable to appreciate as to how, in dealing with the allotees’ complaint against the builder, the two statutory   fora   passed   orders   which   effectively   required   the allotee to make over payment as maintenance charges to a third party, the association in this case. We have already observed that   from   the   materials   on   record,   no   principal­agent relationship has been established between the builder and the association as regards the Maintenance Agreement entitling the builder to claim and receive maintenance charges. The builder, at best, is facilitator in organising a maintenance agency. The overall obligation of a flat buyer to pay maintenance charges may be derived from interpretation of clause 20 of the main Agreement. But without any claim from the entity, who are to render maintenance services and charge for the same, in our opinion, the two statutory fora ought not to have directed the allottee to make payment of maintenance charges. The National and the State Commissions, in our opinion, have committed error in directing the allotee to make payment of maintenance 16 charges, which ought to have been paid to the association when there   was   no   claim   from   the   association   in   the   first   place. Secondly, nothing has been brought to our notice from which it could be inferred that the builder had the authority to represent the   association   for   collecting   maintenance   charges.   On   the other hand, as we have already indicated, the builder’s own case is that the maintenance charges ought to be paid to the association.   The   latter   (i.e.,   the   association)   has   not   been impleaded as a party at any stage of these proceedings. Nor they have prosecuted any claim. 19. We must point out here that from the two orders of the State and the National Commissions, we do not find that the point on right of the builder to claim maintenance charges was specifically   discussed.   In   the   complaint   before   the   State Commission, point was taken that in absence of delivery of possession, charging for maintenance by the association was unjustified but the principle which we have discussed in the preceding three paragraphs are purely legal issues and goes to the   root   of   the   dispute   relating   to   payment   of   maintenance charges. Moreover, question of law formulated in paragraph 2D 17 of   the   allottee’s   special   leave   petition   (now   appeal),   in   our opinion, is broad enough to cover this issue. While determining rights of parties on a question of law which emerges from the pleadings and crystallises for adjudication, we cannot ignore answering that question. For otherwise, an incorrect principle of law may have to be laid down on account of failure of the litigants in raising it in clear terms. Moreover, the nature of the dispute having originated from a consumers’ grievance, the role of the Court has to be beyond just being an adjudicatory forum in   an   adversarial   cause,   and   must   have   an   element   of proactivity in public interest.  Having returned a specific finding on this point, we do not consider it necessary to deal with the allottee’s   contention   that   claim   of   maintenance   charge   was unjustified in absence of possession of the subject­flat being delivered to them.  20. Now we shall turn to the legality of the decision under appeal issuing direction upon the builder to make payment of delayed   compensation.   The   provision   relating   to   delayed compensation   is   contained   in   Clause   17   of   the   main Agreement:­  18 “17. Failure to deliver possession : Remedy to DHDL: The   Allottee   agrees   that   if   the   construction   and development of the Said Complex is abandoned or DHDL is unable to give possession within thirty six (36)   months   from   the   date   of   execution   of   this Agreement   or   such   extended   periods   as   permitted under   this   Agreement,   DHDL   shall   be   entitled   to terminate this Agreement whereupon DHDL's liability shall be limited to the refund of the amounts paid by the Allottee with simple interest @ 6% per annum for the period such amounts were lying with DHDL and DHDL shall not be liable to pay other compensation whatsoever.  However,   DHDL   may,   at   its   sole   option   and discretion, decide not to terminate this Agreement in which   event   DHDL   agrees   to   pay   only   to   the Allottee(s) and not to anyone else and only in cases other than those provided in Clauses 14, 15, 16 and 50 and subject to the Allottee not being in default under any term of this Agreement, compensation @ Rs.   5/­   per   sq.   ft.   of   the   Super   Area   of   the   Said Apartment  per month for the period of such delay beyond   thirty   six   (36)   months   or   such   extended periods   as   permitted   under   this   Agreement.   The adjustment of such compensation shall be done only at the time of conveyancing the Said Apartment to the Allottee   first   named   in   this   Agreement   and   not earlier.” (quoted verbatim from paperbook) As there was delay in obtaining regulatory clearance for 21. the   project,   the   builder   themselves   had   made   certain modifications in the terms of the Agreement, providing certain benefits   to   the   flat   buyers.   This   was   done   by   the th communication   dated   26   March   2009   (at   page   223   of   the 19 paper book in the allottee’s appeal). The relevant portion of this communication reads:­ “As   far   as   "New   Town   Heights"   is   concerned,   we would   like,   to   mention   here   that   the   necessary Building Plan Approvals for all the sectors of “New Town Heights” have been received. As you know, we are a highly compliant organisation, and we would like to start construction only after we have received the final Environment Clearance, which is awaited. As soon as we receive the same, we shall commence the construction. However, to allay any fear that you might   have   as   far   as   the   handing   over   period   is concerned,   we   hereby   revise   the   Compensation Clause No. 17 of the Agreement to Sell, to the extent of doubling the Compensation payable to Rs. 10/­ psft per month, as against Rs. 5 /­ psft per month, that was applicable earlier. Similarly, if the customer delays   in   taking   over   the   possession   once   the possession is offered by the Company, he/she shall also be liable to pay Holding Charges at the same rate,   ie.,   Rs.   10/­   psft   per   month,   for   the   delay involved in taking over the possession.  We stand behind our promised date of delivery as 3 years, as we have already communicated earlier. We have amended this clause to "3 Years from the date of   booking"  instead   of   '3   years   from   the   date   of Agreement', which was the earlier commitment.” (quoted verbatim from paperbook) The   direction   of   the   State   Commission   on   delayed compensation has already been quoted in this judgment. The National Commission, however, modified this directive, which has   also   been   quoted   in   the   earlier   paragraph.   This modification has been questioned by the allotee.  20 Paragraphs   15   and   16   of   the   National   Commission’s 22. decision disclose the reasoning for modifying the directive of the State   Commission   upon   the   builder   to   pay   delayed compensation. Such modification is as regards the quantum of compensation   and   the   relevant   part   of   the   National Commission’s order is reproduced below:­  15.   So   far   as   the   compensation   for   delayed possession   is   concerned,   the   complainant   has accepted part of the benefits given under the letter dated 26.03.2009 and is claiming remaining benefits. By this letter, mode of payment of the instalments were   changed   as   “construction   Linked   Payment Plan”. The construction was started in May, 2009. After adjusting the amount till March, 2009 and the benefits given by the letter dated 26.03.2009, on it, the   complainant   was   asked   to   deposit   instalment some time in 2010. Demand notice dated 16.03.2012, shows that Terrace Floor Slab was completed at that time   and   demand   notice   dated   18.06.2012   shows that the builder had applied for issue of Occupation Certificate, which has  been issued  on 28.02.2013. Thereafter,   final   accounts   of   the   buyers   were prepared and possession was offered through letter dated   10.06.2013.   Due   to   delay   in   starting construction   payment   schedule   of   the   instalments was changed and to mete out suffering of the buyers, various   benefits   were   provided.   Delay   in   offering possession had occurred as construction could not be started   for   more   than   one   year   of   booking.   lf   the buyers were required to payment instalments on later dates than the dates fixed in the agreement, then how it can be expected that the possession could be given   within   three   years   of   the   agreement.   In   the circumstances, the builder was justified in not giving compensation   for   delayed   possession   in   the statement of account dated 10.06.2013. 21 16. However, as we found that the complainant was entitled   for   "Timely   Payment   Rebate”   as   such statement   of   the   account   dated   10.06.2013   and demand   on   its   basis   was   illegal.   In   such circumstances we direct the builder to pay 6% p.a. interest on the amount deposited by the complainant toward basic sale price, as compensation for delay in possession   from   July   2013   till   date   of   offer   of possession as directed by Supreme Court in  Wg. Cdr. Arifur Rahman Khan Vs. DLF Southern Homes Pvt. Ltd., (2020) 16 SCC 512. (quoted verbatim from paperbook) 23. We are, however, unable to accept this reasoning. So far as start of the running time for quantifying delayed payment of compensation from March 2013 is concerned, we find that the builder themselves had modified the relevant clause by their letter dated 26th March 2009, amending the starting date for computing delayed payment of compensation from end of three years from the date of Agreement to three years from the date of booking. Thus, the date of booking in the case of the allottee being March 2008, the State Commission had rightly directed payment of delayed compensation from March 2011.  24. Mr. Mishra has urged that the entire responsibility for delivery of possession of the flat should not fall on his clients as the allottee himself could have applied before the adjudicatory forum for possession thereof subject to outcome of the case. 22 But   this   argument   in   our   view   is   fallacious.   The   dispute between   the   parties   primarily   arose   as   the   builder   denied substantial   benefits   to   the   allottee   for   nine   days’   delay   in clearing instalment. This allegation of delay has been rejected by the Consumer Fora and their concurrent finding is that no proper demand was made for payment of such instalment. Mr. Mishra has, in his submissions, emphasised on the “offer for th possession” letter dated 10  June 2013 and his submission is that obligation to pay delayed payment compensation cannot go beyond that date. The builder’s case is that they cannot be held responsible if the allottee does not take possession of the flat, when offered. A copy of this letter has been annexed at page 235 of the builder’s paperbook. On a plain reading of this letter, we find that the builder offered physical possession only on remitting of payments as per statement of accounts, which was for a sum of Rs.9,00,382/­ and on furnishing an undertaking. The National Commission found that the statement of account th dated 10  June 2013 and demand on that basis was illegal. As the offer for possession was conditional on settling of accounts and,   as   the   accounts   reflected   illegal   demand,   the   builder cannot argue that there was a valid offer for possession under 23 th the letter dated 10   June 2013. In this background, in the event the allottee wanted proper adjudication of his rights and liabilities before asking for interim possession of the flat which would have had carried with it unspecified obligations, no fault can be found in such conduct of the allotee. 25. Reliance   has   been   placed   on   the   judgments   of   two coordinate Benches of this Court in the cases of   DLF Homes Panchkula Pvt. Ltd. vs D.S. Dhanda and Ors.  [(2020) 16 SCC 318] and  DLF Home Developers Ltd. And Another vs Capital Greens Flat Buyers Association & Ors.  [(2020] SCC Online SC 1125] in support of the argument of the builder that “Delay Compensation” could be awarded only upto the date of offer of possession.  But in this case, we have already held that there was   no   valid   offer   for   possession.     In   the   case   reported   in [(2020) 16 SCC 318], interest was directed to be paid by way of compensation on deposited amount from the promised date of possession to the actual date of handing over possession, and the coordinate Bench directed, inter­alia, payment of interest at the rate of 9% per annum for a period of two months from the date of offer for possession.  In the case of  Capital Greens Flat 24 (supra),   interest   was   awarded   as Buyers   Association   compensation for delay in delivery of possession.   The latter judgment was delivered in the special circumstances of that case.     We   accept   the   argument   advanced   on   behalf   of   the builder   that   time   for   payment   of   compensation   for   delayed payment   shall   stop   running   from   the   date   of   offer   for possession.     But   in   this   case,   there   was   no   valid   offer   for possession.  Mr. Mishra also sought to bring to our notice the proposals   made   in   course   of   mediation   proceeding.     But mediation obviously failed between the parties and we cannot refer to what transpired during the process of mediation while adjudicating the right of the parties in an appeal.  The   ratio   of   the   judgment   in   the   case   of   26. Wing Commander Arifur  Rahman Khan and Aleya Sultana and Others vs DLF Southern Homes Pvt. Ltd. and Others  [(2020) 16 SCC 512] does not apply in the facts of the present case. The aforesaid   decision   was   rendered   in   a   context   in   which   a coordinate Bench of this Court found the Agreement involved in that   case   was   lopsided,   giving   unjustified   advantage   to   the 25 builder.   The   relevant   paragraph   from   the   judgment   is reproduced below:­
“25.The only issue which then falls for
determination is whether the flat buyers in these
circumstances are constrained by the stipulation
contained in Clause 14 of ABA providing
compensation for delay @ Rs 5 per square feet per
month. In assessing the legal position, it is necessary
to record that the ABA is clearly one­sided. Where a
flat purchaser pays the instalments that are due in
terms of the agreement with a delay, Clause 39(a)
stipulates that the developer would “at its sole option
and discretion” waive a breach by the allottee of
failing to make payments in accordance with the
schedule, subject to the condition that the allottee
would be charged interest @ 15 per cent per month
for the first ninety days and thereafter at an
additional penal interest of 3% p.a. In other words, a
delay on the part of the flat buyer attracts interest @
18% p.a. beyond ninety days. On the other hand,
where a developer delays in handing over possession
the flat buyer is restricted to receiving interest at Rs 5
per square feet per month under Clause 14 (which in
the submission of Mr Prashant Bhushan works out to
1­1.5% interest p.a.). Would the condition which has
been prescribed in Clause 14 continue to bind the flat
purchaser indefinitely irrespective of the length of the
delay? The agreement stipulates thirty­six months as
the date for the handing over of possession.
Evidently, the terms of the agreement have been
drafted by the developer. They do not maintain a
level platform as between the developer and
purchaser. The stringency of the terms which bind the
purchaser are not mirrored by the obligations for
meeting timelines by the developer. The agreement
does not reflect an even bargain.”
27. So   far   as   the   present   appeals   are   concerned,   the quantum of delayed compensation has been enhanced by the 26 builder themselves, along with provision for enhancement with respect to the delay in payment if made by the allottee in taking possession.   In   such   circumstances,   we   do   not   think   the National   Commission   ought   to   have   had   deviated   from   the modified   contractual   terms   contained   in   the   communication th dated 26   March 2009 and replace the said terms with 6% interest per annum from July 2013 till the date of fresh offer of possession was made. In our opinion, on the point of payment of delayed compensation, the State Commission’s view was the right view.  28. Now comes the question as to which date shall be treated to be the date for fresh offer of possession. Both the fora have directed the builder to issue fresh offer of possession as per the dates specified in the order.   The directions of the State and National Commissions were not to operate with retrospective th effect, from 10  June 2013. The argument of the builder is that a possession offer letter was issued on that date. This letter showed   certain   sum   of   balance   and   also   included   certain demands on account of cost of increase in apartment size area, further EDC and IDC charges, stamp duty charges, etc. Some 27 rebates were also denied to the allottee on account of delay in payment of instalment by nine days, which we have discussed in the preceding paragraphs of this judgment. In an application th th dated 15  November 2018, which was filed on 7  January 2019 before the State Commission, the builder admitted their fault in not providing any compensation for delayed payment in the th aforesaid   letter   of   10   June   2013   and   prayed   that   the complainant (i.e., the allottee) be directed to pay excess amount as specified in the said application and take possession of the apartment. The State Commission found that, as per the said application,   the   builders   had   admitted   wrong   calculation   in settling the credits in the account of the allottee. In fact, the builders then had given the credit for a sum of Rs.2,40,210/­ and issued a cheque for the said sum, which the allottee did not   encash.   Such   conduct   on   the   part   of   the   allottee   was justified   as   the   dispute   was   still   pending   before   the   State Commission. The State Commission found deficiency of service on   the   part   of   the   builder   by   sending   wrong   statement   of accounts along with the letter of possession and as per the finding of the State Commission, the allottee was deprived in taking possession of the flat, which was offered, because of 28 these factors. The National Commission did not take a contrary view and in fact came to a finding that the statement of account th dated 10   June 2013 and demand on that basis was illegal. These findings arrived by the two fora were on appreciation of evidence and we do not find any perversity in such finding. So, th the letter of 10  June 2013 cannot be treated as a valid offer letter. (i)   We,   accordingly,   hold   the   finding   of   the   National 29. Commission as also the State Commission that the allottee would   be   required   to   pay   maintenance   charges   as erroneous   and   that   part   of   the   findings   of   the   two Commissions are set aside.   (ii)   The entity to whom such charge is due has not raised any claim. In such circumstances, direction to the allottee to   pay   maintenance   charges   was   not   warranted   as   the entity entitled to receive such charges is not a party to these proceedings. Such directions assume the character of declaration   of   liability   or   obligation   of   the   allottee   in absence of the admitted claimant, who had not brought any action or staked their claim in any other manner through 29 these proceedings. Such declaratory relief cannot be given in vacuum.  (iii) We sustain the order of the National Commission as also the State Commission that fresh offer of possession ought to be issued. We extend the time for issuing such offer of possession by a period of eight weeks from this date.   Execution   of   Deed   shall   be   effected   within   the aforesaid period. (iv) We modify the direction of National Commission relating to payment of delayed compensation and while restoring the   directions   of   the   State   Commission,   we   direct   that delayed   compensation   be   paid   at   the   rate   of   Rs.10   per square feet per month for the entire period from March 2011 till the date on which the fresh offer of possession is issued.  (v) The delayed possession compensation shall be paid to the   allottee   after   adjusting   the   delayed   compensation already paid. The early payment rebate of Rs.95,136/­ shall also   be   adjusted,   as   has   been   directed   by   the   National 30 Commission. The said sum was mentioned in the statement th of account dated 10  June 2013.  (vi) We retain the order as to costs to be paid to the allottee quantified by the National Commission as Rs.50,000/­.  30. Both the appeals are disposed of in the above terms. We, however,   make   it   clear   that   in   this   judgment,   we   have addressed only the two questions on which leave is granted. Rest of the findings or directions of the National Commission shall remain undisturbed.  31. Connected applications, if any, shall stand disposed of, without any order as to costs.  ………………………………., J. (DINESH MAHESHWARI) ………………………………., J. (ANIRUDDHA BOSE) NEW DELHI; th 11  JULY 2022 31