Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 4854 of 2000
PETITIONER:
Kerala State Science & Technology Museum
RESPONDENT:
Rambal Company & Ors
DATE OF JUDGMENT: 02/08/2006
BENCH:
ARIJIT PASAYAT & LOKESHWAR SINGH PANTA
JUDGMENT:
J U D G M E N T
WITH
CIVIL APPEAL NO. 3211 OF 2006
(Arising out of SLP (C) No. 7048/2001)
ARIJIT PASAYAT, J.
Challenge in these appeals is to the judgment of a
Division Bench of the Kerala High Court holding that
quantification of damages done and demanded from the
respondent No.1 cannot be legally sustained and accordingly
they were set aside. The writ petition was directed to be placed
before the Division Bench by a learned Single Judge. But the
question referred by learned Single Judge i.e. question of
limitation was left open to be adjudicated by the appropriate
authority in accordance with law.
The background facts in a nutshell are as follows :-
The respondent No.1 had entered into Ext. P1 agreement
with the appellant-Kerala State Science and Technology,
Thiruvananthapuram which is a society registered under the
Travancore Cochin Literary and Scientific Societies
Registration Act, 1995, on 16.05.1988 for the construction of
planetarium building of the Kerala State Science and
Technology Museum and allied Civil Works. Dispute having
arisen between the parties the agreement came to be
terminated by Ext. P2 termination notice dated 03.11.1989
issued by the appellant. Ext. P2 was followed by Ext. R1(c)
letter from the managing Partner of the respondent No.1
allegedly admitting the breach of contract. Suit notice dated
06.11.1990 issued by the appellant to the respondent No.1
which was replied by it as per Ext. P3 dated 31.12.1990
repudiating the alleged breach and raising a counter-claim.
According to the respondent No.1 there was a long silence
after Ext. P3 which was broken on 12.01.1998 on which date
it received Ext. P4 demand notice from the Deputy Tahsildar
(RR), Thiruvananthapuram under Section 34 of the Revenue
Recovery Act 1968 calling upon it to remit an amount of
Rs.22,10,303/- with future interest at the rate of 12% from
01.04.97. On receipt of Ext. P4 the respondent No.1 moved the
High Court with Arbitration Request No.2/98 under Section
11 of the Arbitration and Conciliation Act, 1996 for the
appointment of an arbitrator for resolution of all disputes and
differences between the parties concerning the performance of
the work under Ext. P1 agreement. The request was resisted
by the appellant contending, inter-alia, that there is no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
provision for arbitration in Ext. P1 agreement. It was also
contended that as per clause 54 of Ext P1 agreement, there is
a specific exclusion of resolution of disputes by arbitration and
the Civil Courts at Thiruvananthapurarn alone are clothed
with jurisdiction to resolve the disputes arising between the
parties out of Ext.P1 agreement. In other words, not only Ext.
P1 does not contain an arbitration clause, on the contrary,
Ext. P1 specifically rules out arbitration as a mode of
settlement of disputes or claims arising out of Ext. P1.
Accepting the said contentions the High Court rejected the
request. After the said order was passed by the High Court,
the respondent No.1 filed writ petition, being O.P. No.
22633/98 to quash Ext. P4 demand notice and for other
reliefs which came to be disposed of by judgment dated
17.11.98 directing the District Collector to consider and pass
orders on the representation preferred by the respondent No.1
within one month from the date of receipt of a copy of the
judgment. Pending issuance of orders by the District Collector
as aforesaid, the demand notice as evidenced by Ext. P4 was
stayed. As a sequel to the judgment, the District Collector
passed an order rejecting Ext. P8. Upon rejection of Ext.P8 by
District Collector’s order Ext.P4 was revived and the
respondent No.1 was called upon to pay the amount
mentioned therein being the loss suffered by the appellant in
re-arranging the work at the risk and cost of the respondent
No.1. It was at this stage, that the said respondent moved the
High Court by filing a writ petition praying for the issuance of
a writ of certiorari or any other appropriate writ, direction or
order quashing the order and Ext.P4 demand notice as illegal
and arbitrary and for the issuance of a writ of mandamus
declaring that revenue recovery proceedings may be initiated
against the respondent No.1 only after prior adjudication by a
court of law or any other independent judicial/quasi-judicial
body and other reliefs.
When the writ petition came up for hearing before learned
Single Judge, it was contended by the learned counsel for the
writ-petitioner that since breach of contract is not admitted, the
first respondent (present appellant), standing in the position of
another party to the contract, cannot unilaterally assess the
damage alleged to have sustained by it on account of the alleged
default on the part of the writ-petitioner. It was also contended
that the amount demanded as per Ext. P4 is time barred.
Further contention of the writ-petitioner was that since the
entire proceedings are barred, a time barred debt cannot be
recovered by recourse to revenue recovery proceedings. Stand of
the first respondent (present appellant) it is a society owned by
the State and, therefore, Article 112 of the Limitation Act, 1963
(in short the ’Limitation Act’) is applicable and in that view, the
demand raised is well within time. In view of the nature of the
contentions raised, learned Single Judge felt that the matter
should be placed before a Division Bench.
The Division Bench proceeded on the basis as if the main
question that arose for consideration was where a breach of
conditions of a contract is not admitted, whether is open for
the contractee to adjudicate upon the disputed question of
breach as well as to assess the damages arising from the
breach. Though the High Court take note of the fact that the
appellants placed reliance on the document Ex.RI (C) to
contend that there was admitted breach of contract which
resulted in termination of the contract, the respondent No.1
disputed the position and submitted that no breach of
contract can be spelt out as seen from the document Ex.P3.
High Court came to the conclusion that one of the contracting
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
parties cannot adjudicate upon a disputed question of breach
as well as assess the damage arising from the breach. It,
however, noted that the position would be different where
there is no dispute or there is consensus between the
contracting parties regarding breach of conditions. In such a
case an officer of the State even though a party to the contract
will be well within its right in assessing the damages in view of
the specific terms of clause 12 of the Contract.
In support of the appeals, learned counsel for the
appellants submitted that there was no dispute about breach
of contract. In fact, in the letter dated 14.2.1990 Ex.R1(C) it
was accepted that there was breach of contract. The relevant
portions of the document read as follows :
"We fully realize that the above demand
put forth by the then General Manger
Sreekumar asking for enhancement of rates is
against the spirit of the agreed contract and
that is why the museum and the Government
took the decision to rearrange the work
through some other agency at out risk and
cost.
We therefore, humbly request you to
kindly permit us to withdraw the company’s
letter referred above and offer the said work by
our company.
1. We are ready to complete the work
without any change in the rates for all
times of work that we have agreed
previously.
2. We are ready to complete the work in
all aspects without even giving us any
Mobilisation advance by the museum.
3. We request for an extension of 12
months time to complete the work in all
respects and we will strive our level best
to finish the same much in advance."
It was further submitted that before the learned Single
Judge it was not disputed that there was a breach of contract.
In fact, the only point urged before learned Single Judge
related to the question whether the claim was barred by time.
Stand was that a time barred demand cannot be enforced
through revenue recovery proceedings. That was the issue
which forms subject-matter of dispute and considering the
importance of that matter, learned single judge felt that the
matter should be heard by a Division Bench. It was submitted
that when a reference is made by learned Single Judge to the
Division Bench on a particular issue, the Division Bench
cannot travel beyond that issue and decide other matters.
In response, learned counsel for the respondent No.1
submitted that in fact there was no reference by learned Single
Judge, who only held that considering the importance of the
matter the case should be heard by a Division Bench. It is also
submitted that there was dispute regarding breach of
conditions of contract.
It is fairly well settled that when reference is made on a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
specific issued either by a learned Single Judge or Division
Bench to a larger Bench i.e. Division Bench or Full Bench or
Constitution Bench, as the case may be, the Larger Bench
cannot adjudicate upon an issue which is not the question
referred. (See: Kesho Nath Khurana v. Union of India and
Others [1981 (Supp.) SCC 38], Samaresh Chandra Bose v. The
District Magistrate, Burdwan and Others [1972 (2) SCC 476]
and K.C.P. Ltd. v. State Trading Corporation of India and
Another [1995 Supp. (3) SCC 466].
In the instant case, there was no reference to Division
Bench. Learned Single Judge felt that in view of the
contentions, a Division Bench should hear the case.
We find that before learned Single Judge there was
practically no dispute that there was breach of conditions of
contract. In fact learned Single Judge noted the position as
follows:
"The question of termination of contract with
effect from 25.11.1989 is not disputed.
Petitioner did not challenge the termination
order. As per the terms of the contract, if it is
re-tendered, the difference in the re-tender
amount and the loss suffered have to be paid
by the petitioner apart from the liquid
damages."
(Underlined for emphasis)
The learned Single Judge also noted that the main
contention of the writ petitioner was that the amount
demanded was time barred. Reference was made to Section
71 of the Kerala Revenue Recovery Act, 1968. Therefore, it was
contended before learned Single Judge that when the matter is
time barred even if the demand is correct it cannot be enforced
through revenue recovery proceedings. Stand of the appellants
on the contrary was that the society is owned by the State
and, therefore, Article 112 of the Limitation Act, 1963 is
applicable and the demand was raised within time.
Considering the rival submissions learned Single Judge
held that in view of the nature of contention the matter should
be heard by a Division Bench.
Unfortunately the Division Bench did not consider the
contentions which were raised before the learned Single
Judge. It also did not record any positive finding as to whether
the document relied upon by the appellant clearly established
admission of a breach of contract. The portion of the order of
learned Single Judge, quoted above, suggests that there was
no dispute when read in the context of the letter dated
14.2.1990.
As rightly contended by learned counsel for the appellant
the basic issue related to the question whether the demand
was barred by limitation. As noted above the Division Bench
of the High Court did not examine this question.
Above being the question we set aside the order of the
Division Bench and remit the matter back for fresh
consideration limiting the examination to the question whether
the demand by barred by limitation. Interim order dated
1.10.1999 shall be operative till the disposal of the matter by
the Division Bench. We make it clear that merely because
interim protection has been given that shall not be considered
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
to be expression of opinion on merits.
The appeals are disposed of accordingly. No costs.