Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 6593-6594 of 2005
PETITIONER:
Union of India & Anr.
RESPONDENT:
M/s. V.S.Engineering (P) Ltd.
DATE OF JUDGMENT: 16/11/2006
BENCH:
A.K.MATHUR & LOKESHWAR SINGH PANTA
JUDGMENT:
J U D G M E N T
A.K.MATHUR,J
These appeals are directed against the judgment
and order passed by the High Court of Andhra Pradesh. By the
impugned order dated 27.4.2001 a batch of writ petitions were
disposed of including the one before us whereby the High
Court appointed arbitrator under Section 11 of the Arbitration
and Conciliation Act, 1996 (hereinafter to be referred to as ’the
Act’). In the present appeals, we are concerned with Writ
Petition No.2465 of 2001 [ Union of India & Anr. v.
M/s.V.S.Engineering (P) Ltd & Anr.]. So far as order dated
27.4.2001 passed by the Division Bench of the High Court is
concerned, all the issues raised in that order has already been
decided by this Court in the case of SBP & Co. v. Patel
Engineering Ltd. & Anr. [ (2005) 8 SCC 618] by a seven Judge
Bench of this Court. Therefore, no purpose will be served by
examining the validity of the order of the Division Bench of the
High Court challenged in this present appeal as all issues are
covered in the decision of SBP & Co. (supra), therefore this
appeal is accordingly disposed of in the light of the aforesaid
decision.
Brief facts giving rise to another appeal are that M/s.
V.S. Engineering Private Limited, Hyderabad was awarded the
work of supply and stacking of 50mm machine crushed stone
ballast at Nallapadu Depot and loading the same into
B.T.Wagons by Mechanical/ Manual means for a quantity of 1.8
lakh cum at the value of Rs.5,02,20,000/-. The agreement
No.GM/W/SC/93/2 providing payment of mobilization advance
and machinery and plant advance was executed by the
contractor on 19.4.1993. The completion period was 39
months as per the acceptance letter dated 27.1.1993. As per
the agreement the work was to be commenced from 26.4.1993
and completed by 26.4.1996 supplying the ballast at the rate
of 60,000 cum per annum. As the contractor could not
commence the work as per the tender conditions and supplied
only 88214 cum up to November, 1997 penalty for an amount
of Rs.1,01 crore was recovered from the running bills of the
contractor. The appellant did not agree to the request of the
contractor for waiver of penalty and rescheduling of supply.
Therefore, a dispute arose between the parties and the
contractor sought appointment of an arbitrator under clause
64 of the General Conditions of contract. In pursuance of the
contractor’s demand the Arbitral Tribunal was appointed to
adjudicate the contractor’s claim. The Arbitral Tribunal
initiated the proceedings and the contractor submitted his
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
claim statement before the Arbitral Tribunal. Subsequently,
the contractor filed an arbitration application No.60 of 1998
dated 16.10.1998 before the High Court of Andhra Pradesh at
Hyderabad under section 11 of the Act, seeking appointment
of an Arbitrator to resolve the dispute emanating from the
agreement dated 19.4.1993. The appellant- Union of India
contested the arbitration application filed by the respondent by
filing a counter and denying the allegations. It was pointed out
that it was wrong to say that the payment was not done for the
work done. It was alleged that the payment was made as per
the terms of the contract and there was no delay on the part of
the Railway. It was also contended that the request for
referring the dispute for arbitration has to be done in
accordance with Clauses 63 & 64 of the General Clauses of
Contract. As per Clause 63, on receipt of the application the
Railway had to notify the decisions on all matters including
the matters which came up under the caption excepted
matters. The respondent subsequently made a request for
referring the matter to Arbitral Tribunal, The General Manager
of the Railways as per Clause 64 of the General Conditions of
Contract accepted the request of the respondent for referring
the dispute to the Arbitral Tribunal and accordingly, a letter
was sent on 5.5.1998 furnishing four names of Railways
Officers out of which the respondent had to nominate up to
two names which was the requirement in accordance with
clause 64 (3) (a) (ii) of the General Conditions of Contract. The
respondent chose one name i.e. Shri R.N. Raghavan out of the
four names given to him and the dispute was referred to the
Arbitral Tribunal on 20.8.1998. Thereafter some other Railway
Official was appointed. Some claims were not referred to the
Arbitral Tribunal. Meanwhile, the contactor filed petition in the
High Court. The High Court on 28.11.2000 appointed
Mr.Justice Y.V.Narayana as Arbitrator to resolve the disputes
and referred all 14 claims and also fixed the fee at Rs.2 lac .
Aggrieved by the order dated 28.11.2000 passed in Civil
Miscellaneous Petition No.60 of 1998, the appellant filed a
writ petition before the High Court challenging the order of the
learned Single Judge appointing the Arbitrator before the
Division Bench. The Division Bench clubbed together large
number of matter including various issues pertaining to
Arbitration Act, 1996 & decided by its order dated 27.4.2001.
This order was also challenged by Union of India by filing the
present appeal. The Division Bench of the High Court by this
order disposed of Union of India’s appeal pertaining to this
subject matter and directed that in view of the peculiar facts
of this case that since General Manager of the Railway has
already constituted an Arbitral Tribunal, the appellant should
approach the learned Single Judge for modification/ recalling
the aforesaid order dated 28.11.2000. Pursuant to that the
appellant approached the learned Single Judge praying for
modification of the order. Learned Single Judge dismissed the
aforesaid application by order dated 21.2.2002. While
dismissing the application, learned Single Judge observed as
follows :
" As this court is of the opinion that the
Arbitral tribunal constituted by the General
Manager is impliedly set aside and the matters
referred are already withdrawn by referring the
same to the sole Arbitrator appointed by this
Court, the question of functioning of the
Arbitral Tribunal constituted by the General
Manager, Railways, does not arise."
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
Hence, aggrieved against this order the present Special Leave
Petition was filed and leave was granted. Hence both the
present appeals have come up before us for final disposal.
Learned Additional Solicitor General appearing for the
appellant- Union of India has pointed out that as per Clauses
63 & 64 of the General Conditions of Contract, this Court in
no uncertain terms has held that the Arbitral Tribunal has to
be constituted as per the General Conditions of Contract, the
High Court should not interfere under Section 11 of the Act
and the High Court should accept the Arbitral Tribunal
appointed by the General Manager, Railway. In this
connection, learned ASG invited our attention to a decision of
this Court directly bearing on the subject in Union of India &
Anr. v. M.P.Gupta [ (2004) 10 SCC 504] wherein a similar
question with regard to appointment of Arbitral Tribunal for
the Railways with reference to Clause 64 of the General
Conditions of Contract came up before this Court and this
Court held that where two gazetted railway officers are
appointed as the Arbitral Tribunal, the High Court should not
appoint a retired Judge of the High Court as a sole Arbitrator
and the appointment of sole arbitrator was set aside. The
conditions of Clauses 63 & 64 of the General Conditions of
Contract are almost analogous to the one we have in our hand.
In that case also relying on Clause 64 of the contract a three
Judge Bench presided over by the Chief Justice of India
observed as follows :
" In view of the express provision contained
therein that two gazetted railway officers shall
be appointed as arbitrators, Justice P.K.Bahri
could not be appointed by the High Court as the
sole arbitrator. On this short ground alone, the
judgment and order under challenge to the
extent it appoints Justice P.K.Bahri as sole
arbitrator is set aside. Within 30 days from
today, the appellants herein shall appoint two
gazetted railway officers as arbitrators. The two
newly appointed arbitrators shall enter into
reference within a period of another one month
and thereafter the arbitrators shall make their
award within a period of three months."
Earlier also in the case of Datar Switchgears Ltd. v. Tata
Finance Ltd & Anr. [ (2002) 8 SCC 151] their Lordships have
observed that the arbitrator should be appointed within thirty
days on demand being made by the other party and the
appointment could still be made but before the other party
moves the Court under Section 11 of the Act. It was observed
that once the other party moves the court the right to make
the appointment ceases to exist. In the present case as it
appears that the General Manager, Railway has already
appointed the arbitrator but despite this, learned Single Judge
has overruled the objection of the Union of India & appointed
learned Judge of the High Court as arbitrator.
As against this learned counsel appearing for the
respondent has invited our attention to a decision of this Court
in SBP & Co. v. Patel Engineering Ltd. & Anr. [ (2005) 8 SCC
618] in a Bench of seven Judges by majority has overruled the
earlier decision given in Konkar Railway Corporation Ltd. &
Anr. v. Rani Construction Pvt. Ltd. [ (2002) 2 SCC 388]. So far
as the case of SBP & Co. (supra) is concerned it cannot come
to the rescue of the respondent. Learned counsel for the
respondent invited our attention to paragraph 47 that this
judgment will have prospective following. But it did not lay
down that when as per agreement arbitrator is appointed then
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
Court should or should not interfere in the matter, whereas
this issue is covered by earlier judgment by this Court in the
case of Union of India v. M.P.Gupta (supra) by a three Judge
bench which is binding on us. Therefore, the decision in SBP
& Co. (supra) cannot be of any help to the respondent. It has
also been pointed out that the arbitration proceedings are
almost complete. But this Court has stayed the
pronouncement of the award. In the present case, in view of
the decision in M.P. Gupta (supra) a three Judge Bench has
clearly stated that whenever the agreement specifically
provided for appointment of two gazetted railway officers of
equal status as arbitrators by the General Manager, Railway,
then in that case the Court should give this latitude to the
General Manager to make appointment.
However, before parting with this case we may also
observe that Railways and Public institutions are very slow in
reacting to the request made by a contractor for appointment
of the arbitrator. Therefore, in case appointment is not made
in time on the request made by the contracting party. then in
that case the power of the High Court to appoint arbitrator
under Section 11 of the Act will not be denuded. We cannot
allow administrative authorities to sleep over the matter and
leave the citizens without any remedy. Authorities shall be
vigilant and their failure shall certainly give rise to cause to the
affected party. In case, the General Manager, Railway does not
appoint the arbitral tribunal after expiry of the notice of 30
days or before the party approaches the High Court, in that
case, the High Court will be fully justified in appointing
arbitrator under section 11 of the Act. It is the discretion of the
High Court that they can appoint any railway officer or they can
appoint any High Court Judge according to the given situation.
As a result of our above discussion, we allow these
appeals, set aside the orders of the High Court. We direct the
General Manager, Railway to appoint arbitral tribunal within a
period of 30 days from the date of receipt of a certified copy of
this order. The arbitral tribunal so appointed shall enter into
the matter and dispose of the arbitration proceedings as
expeditiously as possible. Consequently, the appointment of
Justice Y.V.Narayana as arbitrator is set aside. There would be
no order as to costs.