Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 687-688 OF 2021
MAHARASHTRA STATE ELECTRICITY
DISTRIBUTION COMPANY LIMITED ...APPELLANT(S)
VERSUS
ADANI POWER MAHARASHTRA
LIMITED AND OTHERS ...RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. The present appeals challenge the judgment and order
th
dated 5 October 2020 passed by the Appellate Tribunal for
Electricity (hereinafter referred to as ‘APTEL’), in cross
appeals being Appeal No. 340 of 2019, filed by Maharashtra
State Electricity Distribution Company Limited (hereinafter
referred to as ‘MSEDCL’), the appellant herein, and Appeal
No. 354 of 2019, filed by Adani Power Maharashtra Limited
Signature Not Verified
(hereinafter referred to as ‘APML’), respondent No. 1 herein,
Digitally signed by
Narendra Prasad
Date: 2023.04.20
11:59:44 IST
Reason:
th
thereby challenging the order dated 6 September 2019,
1
passed by Maharashtra Electricity Regulatory Commission
(hereinafter referred to as ‘MERC’).
2. APML and MSEDCL had entered into four long term
Power Project Agreements (hereinafter referred to as ‘PPA’)
th
dated (a) 8 September, 2008 for 1230 MW (hereinafter
st
referred to as ‘1230 MW PPA’); (b) 21 March, 2010 for 1200
th
MW (hereinafter referred to as ‘1200 MW PPA’); (c) 9 August,
2010 for 120 MW (hereinafter referred to as ‘120 MW PPA’)
th
and (d)16 February, 2013 for 440 MW (hereinafter referred
to as ‘440 MW PPA’), pursuant to the competitive bidding
process conducted by MSEDCL.
3. Prior to the signing of the PPAs between the parties,
APML had applied to the Ministry of Coal, Government of
India (for short, “MoC”) for allotment of Lohara Coal Blocks
th th
on 10 January 2007. Thereafter, on 6 November 2007, the
MoC issued a Letter of Allocation (LoA) to APML conveying
the allocation of Lohara (West) and Lohara Extension (E) Coal
rd
Blocks as the allocated source of fuel. Subsequently, on 23
November 2007, APML applied to the Standing Linkage
Committee (Long-Term) (hereinafter referred to as “SLC (LT)”)
2
for grant of coal linkage for balance capacity to cover the coal
requirement of Units 1, 2 and 3 of the Tiroda Thermal Power
Station (TPS).
th
4. On 27 December 2007, the Government of
Maharashtra issued a statutory Notification under Section 38
(V) of the Wild Life (Protection) Act, 1972, classifying 625.82
sq. km. of the Tadoba National Park and Andheri Wildlife
Sanctuary as a Critical Tiger Habitat (CTH). It is pertinent to
note that, at this point in time, the area demarcating the
CTH, did not include the area of Lohara Coal Blocks and as
such, there were no restrictions on coal mining in the
allotted mining lease area. As per the revised Request for
st
Proposal (RFP), the bid deadline was 21 February 2008 and
th
the cut-off date was 14 February 2008, being seven days
before the deadline. APML submitted its bid for supply of
1320 MW Power to MSEDCL, wherein it specified that the
fuel source for a portion of the contracted capacity, viz. 800
MW capacity out of 1320 MW, would be the Lohara Coal
th
Blocks. A copy of the MoC’s allocation letter dated 6
3
November 2007 was appended to the bid, as per the bid
requirements.
st
5. Thereafter, on 21 February 2008, i.e., seven days after
the bid cut-off date, the Conservator of the Tadoba Andheri
Tiger Reserve (for short, “TATR”) approved the constitution of
an Expert Committee for the creation of a Buffer Zone
surrounding the core area of TATR under Section 38(V) of the
Wildlife (Protection) Act.
6. Twenty-four days after the bid cut-off date, the
Conservator, TATR submitted a proposal to the Chief
Conservator of Forest, Maharashtra for creation of the
aforesaid Buffer Zone. During the pendency of this proposal,
the Ministry of Environment, Forests and Climate Change,
Government of India (for short, “MoEF”), in exercise of its
powers in terms of Regulation 7 of MoEF’s Notification dated
th
14 September 2006, granted the Terms of Reference (ToR),
to APML for mining in the Lohara Coal Blocks, on the basis
of the recommendation made by the Expert Appraisal
st
Committee, MoEF (for short, “EAC”) in its 21 Meeting.
4
7. Thereafter, the 1320 MW PPA was executed between the
th
parties on 8 September 2008, for supply of the contracted
capacity from Units 2 and 3 of the Tiroda TPS. In pursuance
of APML’s application for coal linkage, the SLC(LT) issued a
th
Letter of Assurance (LoA) dated 12 November 2008,
authorising the coal linkage sought, whilst at the same time,
acknowledging that the Lohara Coal Blocks catered to the
requirement for generation of a portion of APML’s contracted
capacity, i.e. 800 MW to MSEDCL.
th
8. In the meanwhile, on 8 October 2008, the Conservator,
TATR submitted a revised proposal for creating the aforesaid
Buffer Zone, which, for the first time, included the mining
lease area of about 176 hectares of the Lohara Coal Blocks.
These proposals were discussed in a meeting of the EAC,
where an area of 1067.21 sq. km. was proposed to be the
th
Buffer Zone of TATR. Thereafter, in its 59 Meeting held on
24-25 November 2009, the EAC decided to withdraw the ToR
issued to the Lohara Coal Blocks since the proposed mining
lease areas were falling in the proposed Buffer Zone, which
included a tiger corridor in the midst of a rich forest.
5
th
Thereafter, vide notification dated 5 May 2010, the
Government of Maharashtra notified 1101.7 sq. km. as the
Buffer Zone of TATR.
9. Since the Lohara Coal Blocks could not be utilized to
meet the requirements under the 1320 MW PPA, APML first
informed MSEDCL of its inability to supply power, vide letter
nd
dated 22 May 2010 and, thereafter, issued a termination
th
notice to MSEDCL dated 16 February 2011 due to the
occurrence of force majeure, on account of cancellation of
Lohara Coal Blocks, in terms of Article 12 of the 1320 MW
PPA.
nd
10. On 22 May 2010, APML informed MSEDCL regarding
its inability to supply power under the PPA from Units II and
III at the PPA-agreed tariff due to cancellation of Lohara Coal
th
Blocks. On 14 June 2010, APML also informed MSEDCL
regarding the occurrence of a force majeure event in terms of
Article 12 of the PPA. Consequently, a termination notice
th
dated 16 February 2011was issued to MSEDCL.
th
11. On 17 July 2012, APML filed a petition, being Case No.
68 of 2012 before MERC, claiming ‘Change in Law’ and ‘ force
6
majeure’ reliefs on account of cancellation of Lohara Coal
st
Blocks. On 21 August 2013, MERC passed an order in the
said petition directing for a meeting of the Expert Committee
to be constituted to evaluate the impact of withdrawal of the
ToR on Units II and III of Tiroda TPS and determine a
compensatory charge to be paid to APML. MERC also
worked out an interim relief at Rs.3.124 per KWH, which
would be applicable only for sale of power above the initial
520 MW from the date of commercial operation. However,
the claim of APML’s with regard to force majeure was rejected
by the said order.
st
12. Being aggrieved by the said order dated 21 August
2013, M/s Prayas Energy Group, the consumer
representative (hereinafter referred to as “Prayas”) filed an
appeal being Appeal No. 296 of 2013 challenging the order
passed by MERC. A cross-appeal also came to be filed by
APML being Appeal No. 241 of 2016 challenging the rejection
of plea of force majeure .
st
13. In pursuance of the order passed by MERC dated 21
August 2013, the Government of Maharashtra constituted a
7
th
High-Level Expert Committee on 9 December 2013. The
th
said High-Level Expert Committee filed its report on 17
February 2014 recommending grant of compensatory tariff to
APML for 800 MW capacity which was entirely dependent on
coal from Lohara Coal Blocks.
th
14. On 17 February 2014, MoC cancelled and deallocated
Lohara Coal Blocks on the ground that Environmental
Clearance (EC) and Forest Clearance (FC) were not given to
th
the said coal blocks. Vide order dated 5 May 2014, MERC,
in Suo Motu Case No. 63 of 2014, devised a mechanism for
calculating the compensatory fuel charges payable to APML
by MSEDCL. The said order was challenged by MSEDCL and
Prayas in Appeal No. 166 of 2014 and Appeal No. 218 of
2014 respectively.
th
15. On 25 August 2014, this Court, in its judgment in the
case of Manohar Lal Sharma v. The Principal Secretary
1
and Others , held the allocation of coal blocks made by the
th
Screening Committee from 14 July 1993 onwards to be
th
illegal. On 16 April 2015, Ministry of Power (for short,
“MoP”) issued a policy direction under Section 107 of the
1 (2014) 9 SCC 516
8
Electricity Act, 2003 to treat allocation of coal block under
Coal Mine (Special Provisions) Ordinance, 2014 as a ‘Change
th
in Law’ event. On 28 January 2016, the MoP notified the
revised Tariff Policy.
th
16. On 11 May 2016, APTEL partly allowed Appeal No. 296
of 2013 filed by Prayas setting aside the order of MERC dated
st
21 August 2013, except on the issue of ToR cancellation not
th
being a force majeure event. Vide the said order dated 11
May 2016, APTEL also allowed the appeals filed by MSEDCL
th
and Prayas against the MERC’s order dated 5 May 2014.
APTEL held that MERC cannot exercise regulatory powers,
thereby setting aside the award of compensatory fuel charge
to APML by MERC in exercise of its regulatory power.
APTEL, however, kept the force majeure issue open for the
decision on the issue of withdrawal of ToR.
th
17. In the meantime, on 11 April 2017, this Court
delivered a judgment in the case of Energy Watchdog v.
2
Central Electricity Regulatory Commission and Others ,
wherein the Court held that change in policies of the
Government affecting availability of domestic coal to the
2 (2017) 14 SCC 80
9
generating companies qualifies as a ‘Change in Law’ event as
st
defined in the PPAs. Consequently, vide order dated 31 May
2019, APTEL allowed the appeal filed by APML being Appeal
No. 241 of 2016 and set aside the order of the MERC dated
st
21 August 2013 and remanded the matter to MERC for
fresh consideration in the light of judgment of this Court in
the case of Energy Watchdog (supra).
18. Being aggrieved thereby, MSEDCL preferred an appeal,
being Appeal No. 340 of 2019, on the ground that MERC
erred in declaring the event of deallocation of Lohara Coal
Blocks as ‘Change in Law’ event under the PPA. APML
preferred a cross-appeal, being Appeal No. 354 of 2019, on
the ground that, while granting relief on account of ‘Change
in Law’, MERC had adopted an erroneous methodology which
does not restore it to the same economic position as if no
‘Change in Law’ had occurred.
19. The APTEL framed the following issues for
consideration:
(1) “Whether MERC was justified in declaring the
event of de-allocation of the Lohara Coal
Blocks as a change in law event?
10
(2) Whether MERC was justified in considering
the landed cost of linkage coal as the basis for
computing change in law compensation to
Adani when Lohara Coal Blocks were the bid-
identified source of coal?
(3) Whether MERC was justified in pegging the
carrying cost to the rate specified in prevalent
Multi Year Tariff ("MYT") Regulations?
(4) Whether MERC was justified in restricting the
change in law relief to the difference between
100% assurance in New Coal Distribution
Policy ("NCDP"), 2007 and 75% assurance
under the SHAKTI Policy based on the Fuel
Supply Agreement ("FSA") dated 29.03.2018
being signed under the SHAKTI Policy?
Whether MERC was justified in linking NCDP
(5)
2007 with allotment of the Lohara Coal
Blocks?
Whether deallocation of the Lohara Coal
(6)
Blocks was a foreseeable risk for Adani and
whether the same has any implication on
change in law relief allowed to Adani?
(7) Whether MERC adopted the correct
methodology regarding Station Heat Rate
("SHR") and Gross Calorific Value ("GCV') in
the Impugned Order while computing the
change in law relief allowed to Adani? Whether
such methodology adheres to the principle of
restitution?”
20. The APTEL, vide the impugned judgment and order
th
dated 5 October 2020, answered the issues as under:
“14.1 Issue No.1:- We hold that the Appellant was
affected by change in law on account of the
de-allocation of Lohara Coal Blocks.
11
Accordingly, the impugned order is
upheld on this issue.
14.2 Issue No.2:- We hold that the Appellant is
entitled to be paid Lohara Coal cost
including transportation cost as base while
computing the compensations for the
change in law events. The issue is decided
in favour of the Appellant.
14.3 Issue No.3:- As the Appellant itself had
sought the carrying cost at the rate
prescribed in the MYT Tariff Regulations in
its petition before the State Commission, we
see no reason to interfere with the
impugned order on this issue. Hence, the
Appellant cannot raise its claim contrary to
what has been sought before the State
Commission. The issue is decided against
the Appellant.
14.4 Issue No.4:- ln line with our judgment
dated 28.9.2020 in A.No.116 of 2019 &
batch, we hold that findings in the
impugned order relating to the issue of
restricting the quantum of shortfall in
domestic coal to a maximum of 25% are
against the principles of restitution under
the change in law provisions of the PPA.
The issue is decided in favour of the
Appellant.
14.5 Issue No.5:- Since this issue was not
pressed during the proceedings, we do not
find it necessary to return a finding on this
issue. No decision required.
14.6 Issue No.6:- We hold that the Appellant’s
rights and obligation in the PPA cannot be
thwarted based on omissions on part of
Government instrumentalities and hence,
the de-allocation of the Lohara Coal Blocks
was not a feaseable risk for the Appellant.
The issue is decided in favour of the
Appellant.
12
14.7 Issue No.7:- In line with our judgment
dated 28.9.2020 in A.No.116 of 2019 &
batch, we hold that the change in law
compensation shall be calculated based on
the SHR specified in the MERC MYT
Regulations, 2011 or the actual SHR
whichever is lower and actual GCV of coal
as received at the plant site. The issue is
decided in favour of the Appellant.”
21. Consequently, the APTEL allowed the appeal filed by
APML, while rejecting the appeal preferred by MSEDCL.
Aggrieved thereby, MSEDCL has preferred the present
appeals.
22. We have heard Shri M.G. Ramchandran, learned Senior
Counsel appearing on behalf of the appellant-MSEDCL and
Shri Sajjan Poovayya, learned Senior Counsel appearing on
behalf of respondent No. 1–APML.
23. Shri Ramchandran submitted that both the MERC and
APTEL have grossly erred in holding the deallocation of
Lohara Coal Blocks to be a ‘Change in Law’ event. It is
submitted that deallocation of coal blocks is a matter
between APML and Coal India Limited (for short, “CIL”) and
the MSEDCL has nothing to do with the same. It is further
submitted that any change to clearances/consents cannot be
13
regarded as ‘Change in Law’. It is submitted that Clause
4.1.1 of the PPA devolves an obligation and responsibility on
APML to obtain and maintain all consents required under the
PPA and, as such, mere deallocation of Lohara Coal Blocks
could not be treated as ‘Change in Law’. It is further
submitted that in Case-1 bidding, the arrangement of fuel
was the responsibility of the bidder and, as such, APTEL is
not concerned as to from what sources APML would obtain
the coal. It is further submitted that as per the PPA, it was
APML’s sole responsibility to transport the coal and, as such,
APTEL erred in granting compensation by factoring the
additional cost of transportation.
24. As against this, Shri Poovayya submitted that, as
consistently held by this Court in the cases of Energy
Watchdog (supra), Adani Rajasthan and Maharashtra
State Electricity Distribution Company Limited v. Adani
3
Power Maharashtra Limited and Others [“ MSEDCL v.
APML and Others ”, for short], since the deallocation of
Lohara Coal Blocks was on account of inclusion of the said
area into Buffer Zone of TATR vide notification of Government
3 2023 SCC OnLine SC 233
14
th
of Maharashtra dated 5 May 2010, which was much after
the cut-off date, both MERC and APTEL have correctly held
that the said event would amount to ‘Change in Law’. It is
submitted that the bid of the appellant was submitted on the
basis that Lohara Coal Blocks was allotted to it. However,
much after the cut-off date, on account of the notification
issued by the State of Maharashtra, the coal block was
deallocated and, as such, APML was required to obtain the
coal from other sources which incurred additional costs.
25. Shri Poovayya further submitted that in view of the
judgment of this Court in the case of Tata Power Company
Limited Transmission v. Maharashtra Electricity
4
Regulatory Commission and MSEDCL v. APML and
Others (supra), an interference in the concurrent findings of
fact would not be warranted.
26. It is further submitted by Shri Poovayya that the Bank
Guarantee furnished by APML was also returned by CIL,
finding no fault on the part of APML thereby fortifying its
claim for Change in Law benefit.
4 2022 SCC OnLine SC 1615
15
27. It is further submitted by Shri Poovayya that MSEDCL
was a part of the Expert Committee, which was constituted
st
by the MERC vide its order dated 21 August 2013. Having
participated in the said meeting in which the Expert
Committee held that APML was entitled for compensation on
account of deallocation of Lohara Coal Blocks, it does not lie
in the mouth of MSEDCL to contend that APML is not
entitled to ‘Change in Law’ compensation.
th
28. Out of the seven issues framed by APTEL, the 5 issue
was not pressed before the APTEL.
29. When we heard this batch of Electricity appeals, it was
agreed between all the parties that this Court should first
decide Civil Appeal No. 684 of 2021 ( MSEDCL v. APML and
Others (supra)) and Civil Appeal No. 6927 of 2021
( Maharashtra State Electricity Distribution Company
Limited v. GMR Warora Energy Ltd. and Others )
inasmuch as three of the issues involved in all the appeals in
the batch were common. It was submitted that those two
appeals could be decided by deciding the three common
issues. However, insofar as the other appeals are concerned,
16
it was submitted that, in addition to the three common
issues, certain additional issues were also involved and it was
agreed that after those two appeals are decided, the other
appeals should be heard for considering these additional
issues.
30. The said three common issues are thus:
(i) Whether ‘Change in Law’ relief on account of NCDP
2013 should be on ‘actuals’ viz. as against 100% of
normative coal requirement assured in terms of
NCDP 2007 OR restricted to trigger levels in NCDP
2013 viz. 65%, 65%, 67% and 75% of Assured Coal
Quantity (ACQ)?
(ii) Whether for computing ‘Change in Law’ relief, the
operating parameters be considered on ‘actuals’
OR as per technical information submitted in bid?
(iii) Whether ‘Change in Law’ relief compensation is to
st
be granted from 1 April 2013 (start of Financial
st
Year) or 31 July 2013 (date of NCDP 2013)?
17
31. After extensively hearing all the learned counsel for the
rd
parties, vide the judgment and order dated 3 March 2023 in
the case of MSEDCL v. APML and Others (supra), this Court
decided those two appeals after considering the aforesaid
three issues.
32. The first issue was answered by this Court, holding that
the ‘Change in Law’ relief for domestic coal shortfall should
be on ‘actuals’ i.e. as against 100% of normative coal
requirement assured in terms of NCDP, 2007. Insofar as the
second issue is concerned, it was held that the Station Heat
Rate (“SHR” for short) and Auxiliary consumption should be
considered as per the Regulations or actuals, whichever is
lower. The third issue was answered holding that the Start
st
date for the ‘Change in Law’ event for the NCDP, 2013 is 1
April 2013.
33. As such, Issue No. 4 with regard to compensation for
shortfall of domestic coal on account of ‘Change in Law’ on
account of amendment to the SHAKTI Policy stands covered
rd
by our judgment dated 3 March 2023 in the case of
MSEDCL v. APML and Others (supra).
18
34. Insofar as the issue with regard to SHAKTI Policy is
concerned, the same is considered by us in our judgments of
even date, in Civil Appeal Nos. 677-678 of 2021 and Civil
Appeal No. 5684 of 2021, holding therein that the
restitutionary principle, as has been applied by this Court on
account of ‘Change in Law’, will also be applicable on
account of change occurring due to introduction of SHAKTI
Policy. As such, no interference would be warranted with the
findings of APTEL on Issue No. 4 in light of the view taken by
us in the aforesaid three judgments.
35.
Insofar as Issue No. 3 is concerned, a perusal of the
impugned judgment and order would reveal that MSEDCL
itself had sought the carrying cost prescribed in the MYT
Tariff Regulations before the State Commission. We,
therefore, find that APTEL has rightly held that MSEDCL
could not be permitted to raise its claim contrary to what was
sought before the State Commission. As such, interference
would not be warranted with the said issue also.
36. Insofar as Issue No. 7 is concerned, in the judgment of
this Court in the case of MSEDCL v. APML and Others
19
(supra), we have already held that ‘Change in Law’
compensation shall be calculated based on the SHR specified
in the MERC MYT Regulations or the actual SHR whichever
is lower.
| 37. This Court, in the case of MSEDCL v. APML and Others<br>(supra), after considering the relevant provisions under the<br>Electricity Act, 2003 with regard to constitution of various<br>expert bodies like the CEA, CERC and the learned APTEL,<br>has held that these bodies are bodies consisting of experts in<br>the fei ld. After considering various judgments on the issue,<br>this Court observed thus: | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| “ | 123. | Recently, the Constitution Bench of this | ||||||||||||||||
| Court in the case of | Vivek Narayan | |||||||||||||||||
| Sharma | v. | Union of India | has held that the | |||||||||||||||
| Courts should be slow in interfering with the | ||||||||||||||||||
| decisions taken by the experts in the fei ld and | ||||||||||||||||||
| unless it is found that the expert bodies have | ||||||||||||||||||
| failed to take into consideration the mandatory | ||||||||||||||||||
| statutory provisions or the decisions taken are | ||||||||||||||||||
| based on extraneous considerations or they | ||||||||||||||||||
| are | ex facie | arbitrary and illegal, it will not be | ||||||||||||||||
| appropriate for this Court to substitute its | ||||||||||||||||||
| views with that of the expert bodies.” | ||||||||||||||||||
38. In the case of MSEDCL v. APML and Others (supra), we
have upheld the view taken by CERC as well as APTEL,
20
holding that the actual GCV of coal ‘as received’ at the plant
site has to be taken into consideration. As such, no
interference would be warranted with regard to the said issue
also.
39. The other three issues, in our view, are interlinked. We
find that the only issue that is required to be considered is as
to whether deallocation of Lohara Coal Blocks would amount
to ‘Change in Law’ and as to whether APML would be entitled
to restitution on account of the same.
40. Insofar as the said issue is concerned, the same is
concurrently held in favour of APML by both the MERC and
the APTEL, thereby declaring the event of deallocation of
Lohara Coal Blocks as ‘Change in Law’. Unless the said
issue is found to be perverse or in ignorance of the
mandatory statutory provisions or is based on extraneous
considerations, it will not be permissible for this Court to
interfere with the same.
41. We will, therefore, have to examine the concurrent
findings of MERC as well as APTEL, guided by these factors.
21
42. It will be relevant to refer to the definition of ‘Law’ as
found in Article 1.1 of the PPA, which reads thus:
""Law” - means, in relation to this Agreement,
all laws including Electricity Law in force in
India and any statute, ordinance, regulation,
Notification or code, rule. or any interpretation
of any of them by an Indian Governmental
Instrumentality and having force of law and
shall further include all applicable rules.
regulations. orders. Notifications by an
Indian Governmental Instrumentality
pursuant to or under any of them and shall
include all rules. regulations. decisions and
orders of the CERC and the MERC
.
“Indian Governmental Instrumentality" means
the GOI, Government of Maharashtra and any
ministry or, department of or, board, agency or
other regulatory or quasi-judicial authority
controlled by GOI or Government of States
where the Procurer and Project are located and
includes the CERC and MERC."
[ Emphasis supplied ]
43. A perusal of the said definition would reveal that any
order or notification, rule or regulation by an Indian
Governmental Instrumentality would constitute ‘Law’. It
cannot be disputed that Government of Maharashtra,
Government of India and various statutory authorities would
fall under the term ‘Governmental Instrumentalities’.
44. It cannot be disputed that in the present case, the cut-
th
off date under the PPA was 14 August 2008. It is to be
22
noted that the power to notify a Tiger Reserve as a Buffer
Zone is vested with the State Government under Section 38V
of the Wildlife (Protection) Act. For consideration and
creation of Buffer Zone, three statutory requirements have to
be complied with, which are thus:
(i) “an Expert Committee must be
constituted for identifying and
establishing a Buffer Zone;
Gram Sabha should be consulted
(ii)
before any such notification and
the identification and establishment of
(iii)
a Buffer Zone shall be based on
scientific and objective criteria.”
45. From the material placed on record, it is clear that prior
th
to 14 August 2008, the area where Lohara Coal Block is
situated was not even proposed to be notified as a Buffer
st
Zone. It is only seven days after the cut-off date, i.e., 21
February 2008, that the Chief Conservator, Forests gave
approval for constitution of an Expert Committee for creating
th
the Buffer Zone surrounding the core area. Thereafter, on 7
March 2008, the Conservator, TATR submitted the proposed
23
demarcation to the Chief Conservator of Forest for creating
the Buffer Zone surrounding the core area of TATR. The
consultation of the Gram Sabha happened only between May
2008 and November 2008, i.e., much after the cut-off date.
th
Subsequently, on 8 October 2008, the Conservator, TATR
submitted the revised proposal for Buffer Zone to TATR.
After numerous other deliberations, including the one with
National Tiger Conservation Authority (NTCA), the
th
Government of Maharashtra issued a notification on 5 May
2010 notifying 1101.7711 sq. km. as the Buffer Zone of
th
TATR. As such, the notification dated 5 May 2010, which
included the area where Lohara Coal Blocks were situated,
will have to be construed to be a ‘Change in Law’. It is only
because of issuance of the said notification, the coal block,
which would have otherwise been available to APML, was not
available to it.
46. It is further clear from the record that MoC had
th
allocated Lohara Coal Blocks vide allocation letter dated 6
November 2007 and MoEF granted the ToR for Lohara Coal
th
Blocks on 16 May 2008 pursuant to EAC’s recommendation
24
th
in the meeting dated 28 April 2008. A perusal of the said
th
letter of MoC dated 6 November 2007 would clearly reveal
that allocation of Lohara West and Lohara Extension Coal
Block to APML has been specifically made to meet the coal
requirements of their 1000 MW power plant in District
Gondia, Maharashtra. It is, thus, clear that the bid
submitted by the appellant on the cut-off date was on the
basis of the assurance that the coal would be available to it
th
from Lohara Coal Blocks. Had the notification dated 5 May
2010 not been issued, APML could have utilized the coal
from Lohara Coal Blocks which was allotted to it by MoC.
Apart from that, it is to be noted that MSEDCL was a part of
the Expert Committee which was constituted by MERC vide
st
its order dated 21 August 2013. Having participated in the
proceedings of the meeting of the Expert Committee,
MSEDCL cannot be permitted to take a stand contrary to the
decision of the said Expert Committee.
47. It is further to be noted that deallocation of Lohara
Coal Blocks was not on account of any fault of APML and
25
this is recognized by CIL itself, inasmuch as it has returned
the Bank Guarantee which was furnished by APML.
48. We find that no interference would be warranted with
the concurrent findings of MERC and APTEL that
deallocation of Lohara Coal Blocks would amount to ‘Change
in Law’ event as defined under the PPA.
49. Insofar as methodology is concerned, APTEL has
referred to the report of the Expert Committee appointed by
MERC, which recommended determination of the price of
coal from Lohara Coal Blocks using “transfer pricing method”
which is one of the commonly used methods. It has accepted
the report of the Expert Committee which provided a
reasonable methodology to arrive at the cost of mining from
Lohara Coal Blocks. It will be relevant to refer to the
following paragraphs of the impugned judgment and order:
“8.9 We also observe that MSEDCL ought not
to cast aspersions on such use of methodology
of transfer pricing to deduce/determine the
coal cost. Expert Committee Report was
furnished after carrying out a detailed exercise
of analysing all relevant technical, commercial,
and financial aspects through a consultative
process. The Expert Committee had also
appointed external industry experts i.e. legal
consultant, financial experts and independent
26
auditors. Admittedly, the Expert Committee
took cognizance of view of all the stakeholders
(including MSEDCL) and it is not the case of
MSEDCL that it was not heard before
submission of the Report to MERC. In fact, we
are mindful of the fact that the cover letter
submitted to MERC records MSEDCL
representative being one of the members which
submitted the Report. As such, we see no
reason why the recommendations of the
Expert Committee cannot be relied upon.
8.10 It is also not a case where MSEDCL
produced any document to contradict such
determination of Lohara coal cost by Expert
Committee. We therefore hold that MERC
ought to have conducted a prudence check to
arrive at a conclusion regarding the
correctness of the figures so
derived/determined towards coal costs by the
Expert Committee. Prudence check, however,
does not mean taking linkage coal cost as the
base to grant or determine change in law
compensation to Adani. The MERC clearly fell
in error on this issue.
8.11 The MERC's erroneous approach erodes
the restitutionary principle enshrined under
Article 13 of the PPA. In fact, Adani submitted
that the Lohara coal cost cross-subsidizes fuel
cost from Linkage portion, which has also been
noted by the Expert Committee in its Report,
but ignored by MERC. MSEDCL has not
disputed this fact.
8.12 The Expert Committee Report further
notes that based on the said cost parameters,
Adani had arrived at two different bid streams
for each of the fuel source (i.e. captive coal and
linkage coal). The overall bid numbers were
based on a weighted average of the individual
bid streams. Observing thus, in Chapter 7, the
Expert Committee suggested MERC to
27
consider the Lohara coal cost to be considered
as the base for restituting Adani. Expert
Committee gave the following rationale for the
recommended methodology:
"7.1 ... The company had entered
into a PPA based on the assurance
of one of the instrumentality of GoI
to provide the coal mine. Therefore,
other instrumentality of a state
government may need to consider
the fact of subsequent non-
availability of coal mine. This fact
has been acknowledged by
MERC….”
8.13 We are in agreement with this rationale.
This rationale conforms to the Tribunal's
findings in the judgment dated 14.09.2019
(Appeal No 202 of 2018 & 305 of 2018) (Adani
Rajasthan judgment) wherein it was held that:
"11.13. The purpose of change in
law relief/compensation is to restore
the affected party to the same
economic position as if the change
in law had not occurred. In the
instant case, this would involve
compensating Adani Rajasthan for
the cost incurred in purchasing
alternate coal to meet the non-
availability of domestic coal
promised under the NCDP 2007.
The MoP letter of 31.07.2013 as well
as the Revised Tariff Policy of 2016
support the principle of
compensation to the generators for
the additional cost incurred in
procuring alternate coal. The
methodology proposed by Adani
Rajasthan prima facie appears to be
consistent with the principle/basis
of compensation for shortfall/non-
28
availability of domestic coal given by
the MoP and we do not find any
reason to interfere with the same."
8.13 In the aforesaid case, the principle which
was considered by us is that to restore the
affected party to the same economic position
as prevailing at the time of bid submission, the
affected party shall be compensated for any
additional cost incurred in procuring alternate
coal to mitigate the nonavailability/shortfall of
coal from the bid-identified source. Since the
bid identified source of coal in the aforesaid
case was linkage coal, the compensation
allowed by the Tribunal was the difference
between alternate coal cost and linkage coal
cost. The formula for such computation is:
Compensation = A - B [where 'A' is cost of
alternate coal and 'B' is cost of coal from the
bid-identified source of fuel i.e. linkage coal.]
Here, we find it important to note that the
methodology approved in Adani Rajasthan
Judgment has not been interfered with by the
Hon'ble Supreme Court in its order dated
31.08.2020 in Jaipur Vidyut Vitran Nigam v.
Adani Power Rajasthan Limited and Anr. (Civil
Appeal No. 8625-8626 of 2019).
8.14 Applying the same ratio as held in Adani
Rajasthan Judgment, the formula for
compensation for non-availability of coal from
Lohara Coal Blocks should have been
Compensation = A - B [where, 'A' is cost of
alternate coal and 'B' is cost of coal from the
bid-identified source of fuel i.e. Lohara Coal
Blocks.] Considering linkage coal cost as base
will not restitute Adani to the same economic
position as if no change in law had occurred
and thus runs contrary to the mandate laid
down by the Energy Watchdog Judgment, the
29
Uttar Haryana Judgment and the revised Tariff
Policy 2016.
8.15 Adani further prayed before to direct
MSEDCL that in so far as the costs incurred
towards transportation of coal from the Lohara
Coal Blocks to Tiroda TPS is concerned the
same may be considered based on applicable
Railway Freight with applicable taxes and
duties, while determining the landed cost of
coal from the Lohara Coal Blocks. We are in
agreement with this contention. It is no longer
res integra that landed cost of coal includes
transportation costs. Supreme Court's
judgment in Nabha Power Ltd. vs. Punjab State
Power Corp. Ltd. (2018) 11 SCC 508 is locus
classicus on the subject wherein it was held
that landed costs cannot exclude
transportation costs viz.:-
"64. We fail to appreciate as to how
these costs can be excluded, as the
transportation costs to the project
site have to be compensated to the
appellant. It is not qualified by the
methodology of transfer, i.e.,
railways or road. It is also a matter
of necessity, since the railway siding
had not reached the project site due
to some complications in acquisition
of land. It is really the
transportation cost from point to
point which would be involved and
the mere mention in the RFP under
project related activity/milestone
about Railway siding and the
Railway lines from nearby station to
site cannot imply that the Railways
is the only mode of transportation
when the siding has not been made,
30
albeit on account of land acquisition
problems."
8.16 We, therefore, hold that MSEDCL ought
to pay Lohara coal cost as base (including
transportation costs) while compensating
Adani for the change in law events. This issue
is decided accordingly and the Impugned
Order on this issue is set aside.”
50. It could thus be seen that the finding of APTEL is based
on the report of the Expert Committee, which was ignored by
MERC. The Expert Committee had found that APML had
entered into a PPA based on the assurance of an
instrumentality of the Government of India that coal would
be provided to it from the Lohara Coal Blocks. However, on
account of the reasons that have been elaborately discussed,
Lohara Coal Blocks, which was allocated to APML, came to
be deallocated for no fault on the part of APML. It is to be
noted that the Expert Committee, while arriving at its
finding, had also appointed external industry experts, i.e.
legal consultant, financial experts and independent auditors.
It is worthwhile to mention that one of the Members of the
said Expert Committee was a representative of MSEDCL.
What has been granted under the said methodology is the
31
additional cost of transport which APML would be required to
incur for transporting the coal from other locations on
account of deallocation of Lohara Coal Blocks. We, therefore,
find no reason to interfere with the said finding with regard
to methodology of arriving at the compensation payable on
account of ‘Change in Law’ event.
51. The appeals are, therefore found to be without merit
and, as such, are dismissed.
52. Pending application(s), if any, shall stand disposed of.
No costs.
…..….......................J.
[B.R. GAVAI]
…….........................J.
[VIKRAM NATH]
NEW DELHI;
APRIL 20, 2023.
32