Full Judgment Text
1
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
ARBITRATION CASE © NO.22 OF 2013
ONGC Petro Additions Limited ..Applicant
| vers<br>mpany Lim | |
| us<br>ited, Ko |
| elim Industrial C | |
|---|---|
| JA | GDISH SINGH KHEHA |
J U D G M E N T
1. In spite of the fact, that notice in this case was
issued to the non-applicant, and the non-applicant-Daelim
Industrial Company Limited, Korea, was duly served, yet none
entered appearance on behalf of the non-applicant. Even though
the matter came to be adjourned on some dates, on account of
the absence of representation on behalf of the non-applicant,
under the belief that some one or the other would enter
appearance on its behalf. The hope entertained by this Court
JUDGMENT
was belied, in the sense, that none has entered appearance on
behalf of the non-applicant. Since the non-applicant was duly
served, this Court is left with no other alternative, but to
proceed with the case against the non-applicant, ex-parte.
2. We have heard learned counsel for the applicant.
3. The applicant ONGC Petro Additions Limited
(hereinafter referred to as the 'OPaL') issued a notice
inviting tenders, on 17.11.2009. By the aforesaid notice, the
applicant solicited bids for construction of a dedicated high
Page 1
2
density Poly Ethylene plant, for its Dahej Petrochemical
Complex. The pleadings in the present arbitration petition
reveal, that the non-applicant-Daelim Industrial Company
Limited, Korea, submitted its tender in response to the
aforesaid notice on 17.11.2009. According to the learned
counsel representing OpaL, in terms of the conditions depicted
in the notice inviting tenders, the bid documents submitted by
the tenderers could be accepted by the applicant finally, and
such acceptance, would result in a concluded and binding
contract. Insofar as the instant aspect of the matter is
concerned, reference was made to Clause 26 of the notice
inviting tender dated 17.11.2009. The same is being extracted
hereunder:
“Clause 26 of the Instructions to the Bidder of
the NIT dated 17.11.2009
26.0 Notification of Award:
26.1 Prior to the expiration of the period
of Bid Validity, the company shall notify the
successful Bidder in writing by registered letter
or by fax or by telex that their tender has been
accepted.
JUDGMENT
26.2 The above letter/ telex/ telefax of
acceptance shall construe that the Contract shall
be deemed to have been concluded. The
Notification of Award shall constitute a binding
contract between the successful bidder and the
Company.”
(emphasis is mine)
From a perusal of Clause 26.2, it clearly emerges, that the
acceptance of the bid by the applicant, would by itself,
Page 2
3
conclude the contract. Thereupon, the consequential
'notification of award', would be treated as a binding contract
between the bidder and the applicant. It also emerges from the
pleadings, that having accepted the bid furnished by the
non-applicant-Daelim Industrial Company Limited, Korea, the
applicant issued a 'notification of award' on 6.1.2011.
According to the learned counsel representing the applicant,
the above notification demonstrates, the factum of a concluded
contract between OPaL and the non-applicant; whereby Daelim
Industrial Company Limited, Korea, became bound by the bid
submitted by it, in response to the notice inviting tenders.
4. It is also necessary to reproduce herein, some other
clauses depicted in the 'notification of award' dated 6.1.2011,
which have a bearing on the determination of the present case.
In this behalf, clauses 8 to 12 of the 'notification of award'
are being extracted hereunder:
“8.0 M/S. Daelim Industrial Company Ltd. Shall
be required to sign a formal Contract with Opal
within 30 (thirty) days from the date of issue of
this NOA. This NOA shall constitute binding
Contract between M/S. Daelim Industrial Company
Ltd and Opal and shall be subject to all terms
and conditions of the Biddings Documents and
other documents mentioned in Para 1.0 above.
JUDGMENT
The date of commencement of activities under this
Contract shall be the date of issuance of this
NOA.
9.0 All other terms and conditions shall be as
per Bidding document No. MR/OW/MM/HDPE/15/2009,
subsequent Amendments and Documents issued
thereof as mentioned at Para 1.0 above.
10.0 Kick off meeting shall be held within 2
Page 3
4
weeks from the date of acceptance of this NOA.
Exact date/time and venue shall be communicated
shortly.
11.0 The effective date of Contract is the date
of this Notification of Award i.e. 06.01.2011.
12.0 Kindly acknowledge this Notification of
Award immediately.”
(emphasis is mine)
A perusal of clause 8.0 of the 'notification of award',
extracted hereinabove, reveals, that M/s Daelim Industrial
Company Limited, Korea, was required to sign a formal contract
with OpaL within 30 days, from the date of issue of
'notification of award'. A perusal of the same clause, further
leads to the inference, that the 'notification of award' would
constitute a binding contract between the applicant and the
non-applicant, and that, the terms and conditions expressed in
the bidding documents, would also constitute the conditions of
the contract. Furthermore, clause 8.0 also finalised the date
JUDGMENT
of commencement of activities under the contract, as the date
of issuance of the 'notification of award'. Learned counsel
for the applicant also invited the Court's attention to clause
10.0 of the 'notification of award' dated 6.1.2011, which
reveals, that the kick off meeting between the contracting
parties would be convened within two weeks from the date of
acceptance of the 'notification of award' by the
non-applicant-Daelim Industrial Company Limited, Korea.
5. In order to demonstrate the conclusion of the
contract, and also the acceptance of the 'notification of
Page 4
5
award' dated 6.1.2011, learned counsel for the applicant
invited this Court's attention to a communication dated
7.1.2011, addressed by the General Manager of the
non-applicant-Daelim Industrial Company Limited, Korea. An
extract of the aforesaid communication is being reproduced
hereunder:
“Sub:- Acknowledgment of Notification Award (NOA)
for Dedicated High Destiny Poly Ethylene Plant
(HDPE) for Dahej Petrochemical Complex against
Bidding Document No. MR/OW/MM/HDPE/15/2009
Dear Sir(s),
With reference to your Notification of Award
(NOA) dated Jan. 6, 2011 (Ref No.
OPAL/BDA/CTS/089/10-11), as per the clause 12.0
of the foregoing NOA, we, Daelim Industrial Co.,
Ltd, are pleased to hereby acknowledge the NOA.
As for the Kick Off Meeting, we respectfully
propose to invite you and hold the meeting in
Daelim Seoul Office from Jan. 25, 2011 to Jan.
27, 2011. We would like you to kindly confirm
the proposed meeting schedule, or otherwise,
inform us of your preferred date(s) and place for
the meeting.
JUDGMENT
Assuring you of our readiness to fulfill all
your requirements for this Project, we are
looking forward to accentuate our competency and
ability to provide you with success in this
Project.
Faithfully yours,
Sd/-
S.Y. Lee
General Manager,
Daelim Industrial Co., Ltd.”
(emphasis is mine)
Learned counsel for the applicant pointedly invited the Court's
attention, to the second paragraph of the aforesaid
Page 5
6
communication, and contended that, the non-applicant had
requested for the convening of the 'kick off meeting' from
25.1.2011 to 27.1.2011. It was the submission of the learned
counsel for the applicant, that the aforesaid 'kick off
meeting' could have been solicited by the non-applicant, only
on the acceptance of the 'notification of award' dated 6.1.2011
(as is clearly evident from clause 10 thereof).
6. Learned counsel then invited this Court's attention
to a message, addressed by the non-applicant-Daelim Industrial
Company Limited, Korea, to the applicant-OPaL on 22.1.2011,
wherein in compliance with clause 3.3, the non-applicant
submitted a scanned copy of the 'performance bank guarantee'.
The aforesaid message dated 22.1.2011 is also being extracted
hereunder:
“Message
(Jinho Shin) shinjh@daelim.co.k Sat, Jan 22, 2011
at 4.04 PM
JUDGMENT
To: sunilkumar upadhyay skuopal@gmail.com
Cc:”01(LESSY) Leesy@daelim.co.kr
(Park, Dong-Jib)”
djpark@daelim.co.kr ,“01
( Dongkjh0907@daelim.co.kr ,
jspark@daelim.co.kr
Dear Mr. Upadhyay,
As per the clause 3.3. “Performance Guarantee” in
General Conditions of Contract, we hereby submit
our scanned “Performance Bank Guarantee” as
enclosed.
The original copy is to be submitted in the
contact signing ceremony on Jan.27, 2011.
Sincerely,
Page 6
7
Jinho Shin
Jinho SHIN
Assistant Manager/Overseas Plant Business Team 1
DAELIM
17-7 Asiaone, Youngdungpo Ga, Yuido-Dong, Seoul,
150-010,
Korea.”
(emphasis is mine)
Based on the communication dated 7.1.2011, and the message
dated 22.1.2011, learned counsel for the applicant contended,
that the non-applicant-Daelim Industrial Company Limited,
Korea, had voluntarily accepted the contract. Based on the
above acceptance, the terms and conditions of the contract were
liable to be construed, in consonance with the 'notification of
award' dated 6.1.2011, read along with the bid documents.
7. There can be no doubt whatsoever, that the
submissions advanced by the learned counsel for the applicant
deserve acceptance, even though the terms and conditions,
especially clause 26 of the notice inviting tender dated
17.11.2009 reveals, that the acceptance of bid documents by the
JUDGMENT
applicant would constitute a concluded contract between the
parties. The communication dated 7.1.2011, and the message
dated 22.1.2011, fully affirm the above conclusion. The two
communications dated 7.1.2011 and 22.1.2011 leave no room for
any doubt, that the non-applicant consciously accepted the
'notification of award' dated 6.1.2011, and thereby, bound
itself to the terms and conditions of the contract. .
8. Despite the afore-stated concluded contract between
the parties, it seems, that the non-applicant-Daelim Industrial
Page 7
8
Company Limited, Korea, could not fulfill its obligations in
terms of the 'notification of award' dated 6.1.2011. It is
therefore, that the non-applicant addressed a letter dated
11.2.2011 to the applicant, wherein the non-applicant expressed
its regret in not being in a position to execute its
obligation, under the contract. The letter dated 11.2.2011 is
reproduced hereunder:
“Date: February 11, 2011
Ref: OBD-075
ONGC PETRO Additions LIMITED
th
VCCI Complex, 4 Floor, 73-GIDC Makarpura Road
Vandora -390010, India
Attention: Mr. Sunil Upadhyay, General manager
(MM)- Opal.
Subject: Tender No.: MR/OW/MM/HDPE/15/2009 –
Dedicated High Destiny Poly Ethylene Plant (HDPE)
for Dahej Petrochemical Complex at Dahej.
Dear Sirs,
Further to our email dated 8, 2011, we have been
intensively discussed with the licensor, Chevron
Philips Co., LP, in order to maintain our
partnership established for a success in the
subject project.
JUDGMENT
However, it is immensely regretful to inform you
that we are not in a position to enter into the
contract since we failed to resolve the unsettled
issues recently undergone with the licensor.
With much gratitude for your hospitality towards
us, we respectfully solicit your kind
understanding for our situation.
Faithfully yours,
Sd/-
S.Y.Lee
General Manager
Daelim Industrial Co., Ltd.”
(emphasis is mine)
Page 8
9
9. Consequent upon the default at the behest of the
non-applicant-Daelim Industrial Company Limited, Korea, in
executing the contract in compliance with the 'notification of
award' dated 6.1.2011, the applicant issued a legal/arbitration
notice, to the non-applicant-Daelim Industrial Company Limited,
Korea. While indicating the obligations which the non-applicant
had failed to fulfill, in consonance with the 'notification of
award' dated 6.1.2011, the legal/arbitration notice dated
26.11.2012 nominated Mr. Justice V.N. Khare, former Chief
Justice of India, as the applicant's nominee arbitrator, for
the resolution of the disputes raised in the legal/arbitration
notice. The law firm (R.S.Prabhu and company) which had issued
the above notice dated 26.11.2012, issued a further
communication to the non-applicant, on behalf of the
applicant-OPaL (in continuation of the legal/arbitration notice
dated 26.11.2012). It is not relevant, for the purpose of
disposal of the present controversy, to delineate the position
JUDGMENT
depicted in the latter communication.
10. In response to the legal/arbitration notice dated
26.11.2012 (issued on behalf of the applicant), the
non-applicant through its law firm (Kim and Chang) served a
reply dated 21.1.2013. Whilst denying the claims raised by the
applicant, against the non-applicant, as were set out in the
legal/arbitration notice dated 26.11.2012, the non-applicant
adopted the following expressed position in its reply:
“10. In addition to the reservation set out in
Page 9
10
paragraph 5 of this Response, Respondent denies
that the provisions of the Indian Arbitration and
Conciliation Act, 1996 should apply to this
arbitration or that the Chief Justice of India (or
any person or institution designated by him) has
the authority to appoint the third and presiding
arbitrator if any agreement cannot be reached
between the party-appointed arbitrators.
11. If an arbitration agreement does exist
between the parties, which is not admitted, the law
and rule governing the procedure of any arbitration
between the parties is the Singapore International
Arbitration Act (the “Act”) and the UNICITRAL Rules
respectively.
12. Therefore, subject to the reservation set
out in paragraph 5 of this Response and pursuant to
Articles 7.1 and 9.1 of the UNICITRAL Rules,
Respondent agrees to a three arbitrator arbitral
tribunal and nominates Mr. Peter Leaver QC as its
party appointed arbitrator. Mr. Leaver's details
are as follows:”
(emphasis is mine)
A perusal of paragraph 10 of the reply issued by the law firm,
on behalf of the non-applicant-Daelim Industrial Company
Limited, Korea, would reveal, that the non-applicant denied the
JUDGMENT
applicability of the provisions of the Indian Arbitration and
Conciliation Act, 1996. In fact, it was specifically pointed
out in paragraph 11 of the above reply, that the procedure for
settlement of disputes by way of arbitration between the
parties, would be regulated as per the Singapore International
Arbitration Act, and in consonance with the UNICITRAL Rules. In
paragraph 12, the non-applicant agreed to an arbitral
adjudication, by a three member arbitral tribunal. It is
therefore, that in response to the applicant having nominated
Justice V.N. Khare, former Chief Justice of India, the
Page 10
11
non-applicant-Daelim Industrial Company Limited, Korea,
nominated Mr. Peter Leaver, Q.C. to act as arbitrator on its
behalf.
11. It is not a matter of dispute, that the two nominated
arbitrators, were to appoint the presiding arbitrator, by
mutual consent. Despite mutual consultations, the two
nominated arbitrators, could not arrive at a concensus on the
name of the presiding arbitrator. It is therefore, that the
applicant approached this Court, requiring it to appoint the
presiding arbitrator under Section 11 of the Arbitration and
Conciliation Act, 1996.
12. Before the prayer made at the behest of the
applicant, under Section 11 of the Arbitration and Conciliation
Act, 1996, is accepted, it would be imperative for this Court
to conclude, that the provisions of the 1996 Act are indeed
applicable to the contract, executed between the rival parties.
It is therefore, that the Court required the learned counsel
JUDGMENT
for the applicant, to respond to the objections raised by the
law firm (Kim and Chang), through its communication dated
21.1.2013.
13. In response, learned counsel for the applicant
invited this Court's attention to clause 1.3 of the General
Conditions of Contract (Part-II) (as amended) of the notice
inviting tender, dated 17.11.2009. Clause 1.3 relied upon by
the learned counsel for the applicant is being reproduced
hereunder:
Page 11
12
“1.3 Laws/Arbitration:
1.3.1 Applicable Laws
| d sub | stantive) from time to |
|---|
1.3.2 Arbitration:
Except as otherwise provided elsewhere in the
contract if any dispute, difference, question or
disagreement arises between the parties hereto or
their respective representatives or assignees, at
any time in connection with construction, meaning,
operation, effect, interpretation or out of the
contract or breach thereof the same shall be
decided by an Arbitral Tribunal consisting of
three Arbitrators. Each party shall appoint one
Arbitrator and Arbitrators so appoined shall
appoint the third Arbitrator who will act as
Presiding Arbitrator.
In case a party fails to appoint an arbitrator
within 30 days from the receipt of the request to
do so by the other party or the two Arbitrators so
appointed fail to agree on the appointment of
third Arbitrator within 30 days from the date of
their appointment, upon request of a party, the
Chief Justice of India or any person or
institution designated by the him (in case of
International Commercial Arbitration) shall
appoint the Arbitrators/ Presiding Arbitrator. In
case of domestic contracts, the Chief Justice of
the High Court or any person or institution
designated by him within whose jurisdiction the
subject contract has been made, shall appoint the
arbitrator/ Presiding Arbitrator upon request of
one of the parties.”
JUDGMENT
(emphasis is mine)
Having perused the notice inviting tender, dated 17.11.2009,
and the 'notification of award' dated 6.1.2011, it is apparent,
that the terms and conditions in the notice inviting tender,
Page 12
13
were binding between the parties. A perusal of clause 1.3.1
“applicable laws” leaves no room for any doubt, for recording
an effective conclusion, that the parties had agreed, that all
questions or disputes arising between them, would be settled in
accordance with laws of India (both procedural and substantive)
in force, from time to time. Insofar as the instant aspect of
the matter is concerned, it is apparent, that the provisions of
the Indian Arbitration and Conciliation Act, 1996, lays down
the procedural, as well as, the substantive provisions,
relating to the settlement of arbitral disputes in India. It
is therefore not possible for this Court to accept, the
objections raised by the non-applicant-Daelim Industrial
Company Limited, Korea, in paragraph 10 of the reply filed on
behalf of the non-applicant through its law firm, expressing
that the provisions of the Indian Arbitration and Conciliation
Act, 1996 would not apply to the settlement of disputes arising
between the applicant and the non-applicant. Having so
JUDGMENT
concluded, the assertion made by the law firm (representing the
non-applicant) in paragraph 11, to the effect that the parties
would be bound by the provisions of the Singapore International
Arbitration Act, is liable to be rejected, and is accordingly
rejected.
14. It has already been recorded hereinabove, that
Justice V.N. Khare, former Chief Justice of India, was
nominated as arbitrator on behalf of the applicant, and Mr.
Peter Leaver Q.C. was nominated as arbitrator on behalf of the
Page 13
14
non-applicant. In terms of clause 1.3.2. of the General
Conditions of Contract (Part-II) (as amended) of the 'notice
inviting tender' dated 17.11.2009, the arbitrators nominated by
the rival parties, were to appoint the presiding arbitrator by
mutual consultation. Insofar as the present controversy is
concerned, even though there was mutual consultation between
the two nominated arbitrators, yet the same did not fructify
into the appointment of an agreed presiding arbitrator. It is
in the above circumstances, that the applicant approached this
Court, for appointing the presiding arbitrator, under Section
11 of the Indian Arbitration and Conciliation Act, 1996.
15. Having arrived at the conclusion, that there was a
binding contract between the parties, and further, that the
parties were to be governed by the provisions of the Indian
Arbitration and Conciliation Act, 1996, there remains no room
for any doubt, that in the absence of consensus between the
nominated arbitrators, this Court is obliged to appoint the
JUDGMENT
presiding arbitrator. Accordingly, Mr. Justice R.V.Raveendran,
a retired Judge of this Court, is appointed as the presiding
arbitrator, to settle the disputes raised by the applicant.
16. The presiding arbitrator shall be free to settle his
terms and conditions of engagement. He shall be forwarded a
copy of this order, by the Registry of this Court, without any
delay. The presiding arbitrator shall commence proceedings of
the arbitral tribunal comprising of himself, Mr. Justice V.N.
Khare and Mr. Peter Leaver Q.C., after consulting them, at the
Page 14
15
earliest.
17. It is necessary to record, that consequent upon a
request made by the non-applicant, it was agreed between the
parties, that the venue of the arbitral proceedings would be
Singapore. This position was conceded by the learned counsel
for the applicant. It is accordingly directed, that arbitral
proceedings shall, subject to a mutual consensus to the
contrary, be conducted at Singapore.
18. Disposed of in the above terms.
…......................J.
[JAGDISH SINGH KHEHAR]
NEW DELHI;
APRIL 07, 2015.
JUDGMENT
Page 15
16
ITEM NO.401 COURT NO.4 SECTION XVIA
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Before Hon'ble Mr.Justice Jagdish Singh Khehar
Arbitration Case (Civil) No(s).22/2013
ONGC PETRO ADDITIONS LTD. Applicant(s)
VERSUS
DAELIM INDUSTRIAL COMPANY LTD. KOREA Non-Applicant(s)
Date : 07/04/2015 This petition was called on for hearing
today.
For Petitioner(s) Mr. Tushar Mehta, ASG
Mr. Rajat Nair, Adv.
for Mr. K. R. Sasiprabhu,AOR
For Respondent(s)
UPON hearing the counsel the Court made the following
O R D E R
The arbitration case (c) no.22 of 2013 is disposed of
in terms of the signed judgment.
Having arrived at the conclusion, that there was a
binding contract between the parties, and further, that the
parties were to be governed by the provisions of the Indian
Arbitration and Conciliation Act, 1996, there remains no room
for any doubt, that in the absence of consensus between the
nominated arbitrators, this Court is obliged to appoint the
presiding arbitrator. Accordingly, Mr. Justice R.V.Raveendran,
a retired Judge of this Court, is appointed as the presiding
arbitrator, to settle the disputes raised by the applicant.
JUDGMENT
The presiding arbitrator shall be free to settle his
terms and conditions of engagement. He shall be forwarded a
copy of this order, by the Registry of this Court, without any
delay. The presiding arbitrator shall commence proceedings of
the arbitral tribunal comprising of himself, Mr. Justice V.N.
Khare and Mr. Peter Leaver Q.C., after consulting them, at the
earliest.
It is necessary to record, that consequent upon a request
made by the non-applicant, it was agreed between the parties,
that the venue of the arbitral proceedings would be Singapore.
Page 16
17
This position was conceded by the learned counsel for the
applicant. It is accordingly directed, that arbitral
proceedings shall, subject to a mutual consensus to the
contrary, be conducted at Singapore.
(Parveen Kr. Chawla) (Renu Diwan)
Court Master Court Master
[Signed Judgment is placed on the file]
JUDGMENT
Page 17