Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 3113 of 2006
PETITIONER:
Orissa Hydro Power Corpn. Ltd
RESPONDENT:
Santwant Singh Gill (D) by Lrs. & Ors
DATE OF JUDGMENT: 24/07/2006
BENCH:
ARIJIT PASAYAT & LOKESHWAR SINGH PANTA
JUDGMENT:
J U D G M E N T
(Arising out of SLP (C) No. 17187 of 2003)
With
CIVIL APPEAL NO 3114 OF 2006
(Arising out of SLP ( C ) No. 16439 OF 2003)
ARIJIT PASAYAT, J.
Leave granted.
The appeal arising out of SLP(C) No.17187 of 2003 is
directed against the judgment rendered by a Division Bench of
the Orissa High Court in the First Appeal. The appeal relating
to SLP (C) No. 16439 of 2003 is against the order passed on a
review application filed by the appellant relating to the
connected first appeal.
The factual background in a nutshell is as follows :
An agreement bearing No. 21F2 of 1984-85 was executed
between the original respondent Santwant Singh Gill (who has
died in the mean time and is represented by his legal
representatives) and the Executive Engineer, Indravati Dam
Division for construction of Concrete-cum-Masonry work of
the Indravati Dam of Block No. 18 upto RI 625.5. Stipulated
dates of commencement of work and completion of work were
2.2.1985 and 1.5.1985 respectively. Since the respondent did
not complete the work and did not participate in the
measurement, by letter dated 6.1.1986 the respondent was
asked to accept the final measurements of the work done by
him. Subsequently the work was assigned to another
contractor. A writ petition was filed by the respondent
questioning the decision. High Court disposed of the matter
directing the authorities to consider the grievances. In
September, 1986 the respondent filed a suit in the Court of
Subordinate Judge, Jeypore being Money Suit No. 417 of 1986
claiming a sum of Rs.8,93,659.91/- with pendente-lite and
future interest @ 18% per annum. The defendants in the said
suit who are respondents No.2 to 4, herein i.e. State of Orissa,
the General Manager, Upper Indravati Project and the
Executive Engineer, Indravati Dam Division filed written
statement denying the claim, except for a sum of
Rs.94,006.40/- and prayed for dismissal of the suit. The
admitted amount was paid in November, 1987. The suit was
decreed on 20th March, 1991 for Rs.7,03,375.29/- along with
pendente- lite interest at the rate of 12% and future interest at
the rate of 9% p.a. on the principal amount of
Rs.6,51,077.29/-.
The respondents No.2 to 4 filed an appeal before the High
Court which was dismissed. Pursuant to the enforcement of
the Orissa Electricity Reforms Act, 1995 and Orissa Electricity
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
Reforms (Transfer of undertaking, assets, liabilities,
proceeding and personnel) Schemes Rules, 1997 framed
thereunder, the Upper Indravati Hydro Electric Project
alongwith all its circles and Divisions with all assets and
liabilities was transferred by the State Government to the
appellant with effect from 1.4.1996. Since the appellant was
not a party in the First Appeal, prayer for permission to file
SLP was made and has been granted, and that is how the
appeals have been filed. As noted above the High Court
dismissed the First Appeal and the application for review filed
by the appellant was rejected by the High Court on the ground
that no case for review was made out. At this juncture it is to
be noted that certain stands which were not highlighted in the
First Appeal were sought to be introduced by the appellant in
the review petition.
Learned counsel for the appellant-Corporation submitted
that basically two issues were considered by the High Court.
They related to (1) whether any extra work was undertaken by
the respondent and (2) whether damage on account of idle
labour was payable. State’s stand was that Clause 11 of the
Agreement clearly indicated that M-150 is purely an extra item
and as such the plaintiff i.e. present respondent would be
entitled to receive payment as per schedule of rate of 1982.
The High Court proceeded on the basis that though the work
in question is not stipulated in the agreement, it was known
to the parties concerned that there was a change in the design
and as given in the drawing (Exhibit N), the execution of M
150 grade concrete work was necessary. This according to
learned counsel for the appellant runs counter to the
observation of the High Court. The stand of the respondent
before the courts below was that the Executive Engineer had
assured payment as per agreement for M-200 grade concrete
work for which the agreement was executed and the work had
commenced. As there was no official communication in that
regard, the respondent informed the Executive Engineer to
allow him to commence the work and confirm the
arrangement.
Learned counsel for the appellant further submitted that
it has not been established that any assurance was given.
Even if it is conceded for the sake of argument that any
assurance was given, the same is clearly unauthorized and in
any event the respondent himself accepted that this was an
extra item of work and that the schedule of rates applicable in
1982 were applicable. Strong reliance was placed in this
regard on a letter purported to have been written on 30.9.1985
by the respondent.
The other item awarded which was questioned related to
payment for idle labour. It was submitted that the time period
for completion of work expired on 1.5.1985 and even if the
claim of the respondent that there was extension up to
2.7.1985 is accepted, the courts below were not justified in
granting compensation for idle labour up to 6.1.1986. It is
submitted that the High Court has not given practically any
reason, to uphold the award in respect of these items. So far
as the first item is concerned, the High Court merely observed
as follows:
"In view of what has been stated above, we are
inclined to concur with the finding of the
learned trial Judge that the plaintiff is entitled
to be paid for the M-150 grade concrete work
at the rate for M-200 grade concrete work."
Similarly, it was submitted that in regard to the claim
relating to idle labour the High Court did not even consider as
to the period by which the work was to be completed. If no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
extension of time was granted beyond 2.8.1985 which
according to the courts below was the last date by which the
work was to be completed, the appellant could not have been
directed to make payment for a period (a) from 26.2.1985 to
13.4.1985 and (b) from 3.7.1985 to 6.1.1986.
In response, learned counsel for the respondents
submitted that both the trial court and the High Court have
analysed the factual position and have worked out the
entitlement of the respondents and there is no infirmity so as
to warrant any interference.
We find that several relevant factors have not been
considered by the High Court; for example the effect of the
letter purported to have been written by the respondent-
Santwant Singh Gill. The relevant portion reads as follows :
"In the meantime, due to change in
design, I was asked to do plain concrete in
place of masonry. This item of work was not
contemplated in my agreement. However, I
have done the plain concrete at the schedule of
rate."
(Underlined for emphasis)
The High Court has not made any effort to find out as to
whether the work in question was extra work was and/or
covered by agreement. If it was covered by the agreement, the
question of assurance, if any, given as claimed is
inconsequential. If it was a part of agreement it was to be
covered by the rate stipulated. In that event there is no
question of any assurance having any role to play. This aspect
has also not been considered by the High Court.
Additionally, as rightly pointed out by the learned
counsel for the appellant, if work was to be completed by
2.8.1985 as claimed by the respondents, the question of any
payment being made for idle work beyond the said date does
not arise. This aspect was also required to be analysed by the
High Court which has not been done.
In the fitness of nature, therefore, the High Court should
re-examine the matter on the aforesaid two aspects and decide
the matter in accordance with law.
So far as the connected appeal is concerned we find that
the High Court rightly held that a case of review was not made
out on the grounds apart from those which we have dealt with
in the connected appeal. Since the basic issues relating to
alleged grievances were not placed for considered before the
High Court earlier there was no scope for entertaining a review
petition. The High Court had therefore rightly rejected the
review petition. The said appeal stands dismissed.
As noted above in the appeal relating to the First Appeal
before the High Court basic issues are to be examined and,
therefore, the re-consideration is to be limited to the two
issues indicated above.
The appeals are accordingly disposed of. No costs.