Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 10014 of 1995
PETITIONER:
U.P. STATE ELECTRICITY BOARD
Vs.
RESPONDENT:
M/S SEARSOLE CHEMICALS LIMITED
DATE OF JUDGMENT: 21/02/2001
BENCH:
S. Rajendra Babu & S.N. Phukan.
JUDGMENT:
J U D G M E N T
RAJENDRA BABU, J. :
L...I...T.......T.......T.......T.......T.......T.......T..J
An agreement was entered into between the appellant and
the respondent for supply of electrical energy and by virtue
of clause 1 of the agreement, the supply of electrical
energy shall be in form of a three-phase alternating
current at a pressure of approximately 400 Volts between
phases, a frequency of approximately 80 cycles per second
and a power not exceeding 744.12 KVA and the supply shall be
available continuously during the 24 hours of each day and
throughout the whole period of this agreement, provided
always that the supplier shall not be responsible for
damages or otherwise on account of accidental interruption
of supply or stoppage or deficiency of energy caused by any
order or direction issued by the Government of Uttar Pradesh
or resulting from fire, flood, tempest or any accident or
from any strike or lock out of workman or from any other
cause beyond the control of the supplier, but the supplier
shall make every effort to restore the supply as soon as
possible. On the ground that disputes arose between the
appellant and the respondent, the matter was referred to the
arbitration as provided in the agreement. The respondent in
the claim statement made various claims for refund of the
amounts paid under various bills and for various losses
suffered on account of various acts of commission and
omission of the appellant, details of which are set out
therein. By their written statement the appellant refuted
the various claims of the respondent.
On April 6, 1990 the arbitrators made an award for a sum
of Rs. 1,74,338.98 by way of refund, while in regard to
losses suffered on account of interruption in the power
supply as a result of the negligence and acts of omission
and commission by the appellant a sum of Rs. 24,00,000 was
awarded with interest at 12% with effect from 12.11.1986 up
to the date of the award and interest @ 6% per annum from
the date of the award till the date of payment. In the
Court of the Civil Judge the award was filed. Over-ruling
the objections of the appellant, the Civil Judge made a
decree in terms of the award against which an appeal was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
preferred to the High Court and which appeal having been
dismissed, this appeal by special leave is filed.
Shri Ranjit Kumar, the learned Senior Advocate appearing
for the appellant, submitted that the award made by the
arbitrators is not within the scope of the agreement entered
into between the parties inasmuch as the claim for damages
would arise except in the circumstances arising in the
proviso to clause 1 of the terms of agreement, to which we
have adverted to at the very outset. Damages would not
arise on account of interruptions, stoppage and deficiency
caused by (i) accident, or (ii) by any order or direction
issued by the Government of Uttar Pradesh, or (iii)
resulting from fire, flood, tempest or any accident or from
any strike or lock out of workman or from any other cause
beyond the control of the supplier. Thus the principal
contention addressed before us is that there is a guarantee
of supply of electricity for 24 hours of a day but under the
circumstances set out in the proviso supply could be
interrupted without liability of paying damages and this
aspect was not considered by the arbitrators. When this
point was raised before the High Court, the High Court
noticed the finding of the arbitrators that all log books
were not made available and even where they were made
available by the appellant were not complete and even did
not give any reasons and, where they contained reasons, the
same were not tenable. While recording findings in respect
of issues Nos. 1 and 2 after assessing the evidence, the
arbitrators came to this conclusion. Before us the extracts
of the logbooks have been produced and the reasons noted
therein, for instance, are Tripping, Shut down, Grid
failure, Break down. The respondent wrote to the appellant
seeking for clarification regarding the interruption in the
power supply and there was no response to such
correspondence at all. Taking this circumstance into
consideration and after going through the documents produced
by the parties, it was noticed by the arbitrators as follows
:-
The opposite party failed to produce log books for the
period 6.12.1978 to 3.12.1980 and also admitted vide their
letter dated 4.7.1987 that these log books were not
traceable. In these circumstances we are of the opinion
that had the opposite party filed the said log books it
would have gone against them. The opposite party has not
filed the best evidence available. Besides, the log books
which the opposite party produced, did not give any reasons
or where reasons were given, they were untenable.
Shri Ranjit Kumar very strenuously contended that the
relevant documents have been placed before the arbitrators
and stated that except in regard to one station for some
period, rest of the documents of the log books had been made
available. However, as noticed by us, there were reasons
set out in the log books or, as noticed earlier, those
reasons, in the opinion of the arbitrators, were either not
relevant or where they were relevant, they were untenable.
Therefore, the view taken by the arbitrators cannot be
characterised as not emanating from the agreement and falls
squarely within the excepted part of the proviso to clause 1
of the agreement. When the arbitrators have applied their
mind to the pleadings, the evidence adduced before them and
the terms of the contract, we do not think, it is within our
scope to re-appraise the matter as if this were an appeal,
and it is clear that where two views are possible in this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
case there is no such scope the view taken by the
arbitrators would prevail.
Shri Ranjit Kumar further pointed out that the
interruptions in the power supply, if any, were on account
of the Uttar Pradesh Electricity (Regulation of Supply
Distribution, Consumption and Use) Order issued from time to
time and, therefore, if there is any power cut effect at any
time or staggering of the power supply, it was the result of
such order which falls within the scope of the proviso to
clause 1 of the agreement. Clause 6 of the Order, which
regulated the supply, reads as follows :-
6. (i) In respect of electrical energy consumer by all
large and heavy power industrial consumers receiving power
at 33 KV and above from Uttar Pradesh State Electricity
Board, a cut of 33-1/3 per cent in their highest maximum
demand recorded in any month during the twelve months from
August, 1978 to July, 1979 shall be exercised :
Provided that where any such industrial consumer has his
own source of generation of energy which alone enables him
to obtain 66-2/3 per cent or more of his aforesaid highest
maximum demand then a cut of 100 per cent in the power
supplied by the Board shall be exercised.
(ii) All Arc Furnaces, Induction Furnaces, Rolling and
Re-Rolling mills receiving power below 33 KV from U.P.
State Electricity Board shall use energy for 10 hours only
every day during such hours as may be specified by the Board
from time to time anything contained in Clause 8(a)
notwithstanding.
(iii) All other continuous process industrial power
consumers (listed in Annexure 2) as well as Textile Mills
and non-continuous industrial power consumers having loads
above 110 BHP/100KVA/75 KW billed on large and heavy power
tariffs receiving power from the U.P. State Electricity
Board shall exercise 33.1/3 per cent cut in their highest
maximum demand recorded in any month during the twelve
months from August, 1978 to July, 1979:
Provided that any such consumer or Mill may for reasons
of technical difficulty instead of observing the aforesaid
cut avail supply for such 20 days in a month as may be
determined with the approval of the Executive Engineer
concerned and may observe block closure during the remaining
days of the month so, however, that consumption up to 5 per
cent of such highest maximum demand shall be allowed during
the block closure to meet the requirements of light, fan,
tube-well and repair workshops."
The log books should have indicated or other materials
should have been placed before the arbitrators to indicate
that the heavy power tariffs received from the U.P. State
Electricity Board should exercise 33.1/3 per cent cut in the
highest maximum demand recorded in any month during the 12
months from August 1978 to July 1979 and the manner in which
the same should be regulated. Whether that amount of
electricity was supplied to the respondent or not is also
not clear from the records. In the absence of such material
placed before the arbitrators, we cannot embark upon an
investigation on the basis of this order of the U.P.
Government.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
Therefore, we think, the High Court is justified in
having dismissed the appeal filed by the appellant, and we
do not think that there is any justification for us to
interfere with the award which was made the decree of the
civil court and in appeal affirmed by the High Court.
The appeal, therefore, stands dismissed. However, in
the circumstances of the case, the parties shall bear their
respective costs.
..J. @@
IIIIIIIIIIIIIIIIII
[
S. RAJENDRA BABU ]
.J. @@
IIIIIIIIIIIIIIIII
[
S. N. PHUKAN ]
FEBRUARY 21, 2001.