Full Judgment Text
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6097 OF 2008
(Arising out of SLP [C] No.21221 of 2006)
Kerala State Housing Board & Anr. … Appellant(s)
Vs.
Grace Joseph & Anr. … Respondent(s)
O R D E R
Leave granted. Heard both parties.
2. The appellant, Kerala State Housing Board (‘Board’ for
short) allotted a premises (land and building) to the
respondent in terms of agreement of sale dated 8.4.1992.
Clause (4) of the agreement fixed a sum of Rs.31260/- as
the tentative land value and tentative service charges (for
providing amenities). The said clause also fixed the
(final) cost of the structure as Rs.86992/-. Clause 10
enabled the Board to re-fix of the final price of the land
2
and service charges, on account of enhancement of
compensation for acquisition of the land and increase in
the cost of amenities. Clause 11 provided for the interest
payable on the difference between the tentative price and
the final price fixed. The said Clauses 10 & 11 are
extracted below :
“10. It is agreed that the Kerala State Housing Board
shall be entitled to re-fix the final price of the
land and service charges thereon taking into account
inter alia the enhanced compensation awarded by Courts
and Tribunals. The cost incurred by the Board or and
its predecessors in interest for prosecuting such
proceedings in courts and tribunals and also the
increased cost of development works and amenities
undertaken with respect to the scheme after a final
settlement of accounts in connection therewith.
It is agreed that the decision of the Board in fixing
the revised price of the land and service charges
shall be conclusive and final.
11. It is expressly agreed between the parties hereto
that after the finalization of the price of the land
and service charges by the Board the party of the
second part shall pay to the Board together with
interest at 15.5% and 13% per annum, the difference
between the tentative price fixed therefor and the
price finally fixed for both the land and service
charges by the Board, within thirty days of the date
of a registered notice demanding the payment thereof
or in such instalments such rate of interest to be
determined by the Board.”
Clause 12 provides that the allottee shall be entitled to
get a registered sale deed conveying the premises on
payment of all the amounts due in terms of the said
3
agreement and after complying with all the terms and
conditions of the said agreement.
3. It is stated that the respondent has paid the
tentative land value and tentative service charges
aggregating to Rs.31260/- as also the cost of structure
being Rs.86992/- by 1994 and secured possession of the
premises. More than a decade after the agreement, the Board
send a demand notice dated 7.1.2004 claiming Rs.13406/- as
the difference in building cost (with interest) and
Rs.163821/- as additional land value (with additional
development and LAR) in all Rs.177227/-.
4. Feeling aggrieved, the respondent approached the High
Court contending that no particulars of the increased cost
were furnished to her and that she was not liable to pay
the additional amount claimed by the Board. A learned
Single Judge of the Kerala High Court, by order dated
14.6.2005 disposed of the writ petition by directing the
appellant Board to furnish a detailed statement of account
(showing the actual cost and the interest) to the
respondent. Learned Single Judge also observed that if on
receiving the statement of account the respondent wanted to
4
dispute any part of the claim, she may have to approach the
civil court, as that was in the nature of a civil dispute.
5. The order of the learned Single Judge was challenged
by the respondent in a writ appeal before the Division
Bench. The Division Bench found that in so far as cost of
the structure, the sum of Rs.86992/- mentioned in the
agreement was not a tentative but final figure and neither
clause 10 nor clause 11 of the agreement enabled the Board
to make a claim for increase in the cost of construction.
The Division Bench was therefore of the view that increase
of Rs.13406/- claimed in regard to the cost of the
structure was unwarranted. In so far as the increase in
land cost and service charges, the Division Bench found
that the Land Acquisition Officer had made an award in
regard to the acquired land (where the project was
executed) on 25.11.1981 and the reference court had
enhanced the compensation by its award dated 5.12.1989. The
Division Bench held that as the said increase by the
Reference Court was more than two years prior to the
agreement, the said increase would have been already worked
into land cost and service charges shown as Rs.31260/-
under the agreement dated 8.4.1992. The Division Bench also
noted that the award of the Reference Court was not
5
challenged by the land owners and therefore, there was no
question of any increase after 8.4.1992; and that the award
of the Reference Court was challenged by the Board before
the High Court and the High Court had reduced the amount
awarded by the Reference Court and that had attained
finality. The Division Bench was therefore of the view that
there was no justification for demanding any increase in
cost towards land. It held that the increase in cost, if
any, that could be demanded was only in regard to the
development work and amenities. In view of its findings,
the Division Bench allowed the appeal, by its judgment
dated 22.6.2006, set aside the judgment of the learned
Single Judge and quashed the demand notice dated 7.1.2004.
It however left it open to the Board to make a fresh demand
only in regard to service charges (that is the increased
cost of development work and amenities undertaken in regard
to the scheme)after final settlement of account. The
Division Bench also directed that the title deed should be
issued to the respondent on execution of an undertaking
that she will pay the amount due towards increased cost of
development work and amenities. The Board sought review,
which was rejected on 13.10.2006.
6
6. The said judgment and order are challenged by the
Board in this appeal. The Board is not able to challenge
the quashing of the demand for Rs.13406/- towards extra
cost of structure, as the contract shows that Rs.86992/-
paid by the respondent was the final price and the contract
did not provide for any increase therein. In regard to the
land cost, the Board submitted that the sum of Rs.31260/-
shown as tentative land value and service charges in the
agreement dated 8.4.1992 did not take into account the
compensation enhancement granted under the award dated
5.12.1989 of the reference court as the said amount had not
been paid to the land-owners by then and, the final cost
was worked out after payment to the land-owners and after
the litigation ended. It was further submitted that the
Division Bench could not have assumed that the enhanced
land cost had been taken into account in the tentative
price shown in the agreement.
7. We find considerable force in the contention of the
appellant. The appeal filed against the award of the
Reference Court, by the Board, was pending till 1996 and
therefore the land price mentioned in the agreement dated
8.4.1992 could not be said to be final. We also find that
the Division Bench, before passing the impugned judgment,
7
did not secure the working sheets in regard to the price of
the land nor examined the accounts. The agreement (clause
10) specifically stated that the land price was tentative
and any increase demanded was payable. If the entire cost
of land including enhancement had already been taken into
account while fixing the cost of land mentioned in the
agreement, it would not have stated that the land price was
tentative and subject to increase in final settlement. The
fact that the cost of construction was shown as the final
price and the cost of land and development was shown as
tentative clearly demonstrate that the amount shown in the
agreement towards land cost and service charges was not the
final cost. The Division Bench could have at best directed
the Board to give actual calculation/break up of the
increased amount (as was directed by the learned Single
Judge). If the Division Bench did not want to refer the
parties to a civil court in the event of any part of the
calculation being disputed, it ought to have examined the
accounts, considered the objections of the respondent and
finally decided the issue. The direction issued by the High
Court in regard to the tentative service charge should
equally apply to the tentative land cost also.
8
8. We therefore allow this appeal in part and set aside
the judgment of the High Court in so far as it relates to
the cost of land and service charges. The matter is
remanded to the High Court with the following directions:
(a) The Board shall furnish to the respondent the
calculation-sheet in regard to Rs.177227/- claimed as
the increased cost of land and service charges (for
development and amenities) within two months from
today;
(b) If the respondent agrees with the calculation and pays
the amount, the Board shall execute the sale deed
within one month from the date of payment;
(c) If the respondent disputes the amount claimed by the
Board, either in regard to land cost or service
charges, she may file objections to the calculations
and the Division Bench shall decide the same.
(d) If there is any delay in the disposal by the High
Court, it is open to the respondent to furnish a bank
guarantee for the amount claimed by the Board, without
prejudice and obtain the sale deed.
(e) The quashing of the demand in respect of increase in
cost of construction is upheld.
9
……………………………………………………..J
[R. V. Raveendran]
…………………………………………………………J
[Lokeshwar Singh Panta]
New Delhi;
October 3, 2008.