Sulakhan Singh vs Kanwarjit Singh Kochar & Anr.
- Court
- Delhi High Court
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Reserved on: 18 March, 2026
th
Pronounced on: 16 June, 2026
+ RFA 286/2020
SULAKHAN SINGH
S/o Shri Mota Singh
Proprietor of S.S. Interiors & Constructions,
At TA-28/1, Tuglakabad Extn.,
Kalkaji, New Delhi
.....Appellant
Through: Mr. Vijay Datt Gahtori, Mr. Shankar
Datt Gahtori, Advocates
versus
1. KANWARJIT SINGH KOCHAR
2. KANWALJIT SINGH KOCHAR
Both R/o H-25, Jangpura Extn., New Delhi
Also at:
Palam Show Room, RZ-123, Vaishali;
Palam, Dabri Road, Dwarka, New Delhi -110045
.....Respondents
Through: Mr. Arush Kapoor, Advocate
CORAM:
HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA
J U D G M E N T
NEENA BANSAL KRISHNA, J.
1. Regular First Appeal under Section 96 read with Order XLI of the
Code of Civil Procedure, 1908 ( hereinafter referred to as „CPC‟ ) has been
Signature Not Verified
RFA 286/2020 Page 1 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
filed by the Appellant against the Judgment dated 19.06.2020 , whereby the
learned ADJ, has dismissed the Suit filed by the Plaintiff/Appellant .
2. The Plaintiff had filed a Civil Suit bearing CS No. 9831/2016 (old
No. 1317/2005) for recovery of Rs.18,57,335/- along with Pendente Lite and
Future Interest.
3. The brief facts as narrated in the Plaint are that the Plaintiff is a Civil
Contractor working under the name and style of M/s S.S. Interiors &
Constructions, who was approached by Defendant No. 1 & 2 who are the
authorized dealers of Maruti Udyog Ltd., under the name and style of M/s
Magic Auto Workshop, for some addition and alteration to be carried out at
their workshop at Salvania and Laxman, Najafgarh Road, Moti Nagar, New
Delhi (hereinafter referred to as “Site-1”) and at 7/56, D.B.G Road,
Opposite Gautam Hotel, Karol Bagh, New Delhi (hereinafter referred to as
“Site-2”) .
4. The Agreement for necessary repairs, was done in the presence of
Defendant No. 3 Rajesh Pancholi, Architect and Sh. Jagir Singh on the rates
mutually agreed between the parties. As per the Agreement, the labour and
materials were to be arranged, provided and supplied by the Plaintiff.
5. The Defendants started the work on Site-1 on 28.05.2008 and at Site-
2 in the first week of June, 2008. For the work to be done the Plaintiff
arranged large number of labour and brought the grinding machines and
other equipment, to carry out the work, at both the sites. The work was being
supervised by Defendant No. 1 and 2 as well as the Architect/Supervisor
Defendant No. 3. The work was carried out as per the specifications of the
Defendants, and was nearing completion by 10.09.2008.
Signature Not Verified
RFA 286/2020 Page 2 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
6. According to the Plaintiff, the work was performed to the satisfaction
of Defendant No. 1 & 2 and their Supervisor Defendant No. 3, and no
deficiency was ever pointed out by the Defendants. About 70% of the work
was completed by the Plaintiff till 10.09.2008 at Site-1 and 7 bills
amounting to Rs.22,73,094/- were submitted to Defendant no. 1 and 2,
which were handed over to Defendant No. 3 for checking and reporting, in
regard to the Site-1. The Defendant No. 1 & 2 made a payment of
Rs.13,00,000/- to the Plaintiff from time to time and the balance amount of
Rs.9,73,094/- remained to be paid in respect of Site-1.
7. The Plaintiff further stated that 99% of the work at Site-2, was
completed till 10.09.2008. He submitted 5 bills amounting to Rs.16,41,980/-
to Defendant No. 1 and 2. The Defendant No. 3 checked and reported in
respect of the bills. The Defendant No. 1 & 2 made payment of
Rs.10,00,000/- to the Plaintiff from time to time, leaving a balance of
Rs.6,41,980/- to be paid in respect of Site-2.
8. The Plaintiff made a demand of further payment of the work done
from the Defendant No. 1 & 2 on 10.09.2008, on which they started abusing,
insulting and humiliating the Plaintiff and abruptly stopped the work, at both
the sites. They threatened the Plaintiff and labour of dire consequences and
asked them to leave the sites. The Plaintiff was even manhandled by the
Defendant No. 1 and 2. Moreover, there was a lot of material and
machinery, and other equipment lying at the two sites, which the Plaintiff
was not allowed to lift.
9. They failed to settle the account of the Plaintiff even though the work
had been conducted under the supervision of Defendant No. 3 to his
Signature Not Verified
RFA 286/2020 Page 3 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
satisfaction. The Plaintiff claimed that Defendants were liable to pay the
damages.
10. The Plaintiff had reported the matter to the SHO, PS- Kirti Nagar on
15.09.2008 vide DD No. 46-D, but even thereafter, no action was taken by
the police.
11. The Plaintiff thus, filed the Suit for Recovery of Rs.18,57,335/-
along with Pendente Lite and Future Interest @ 12% p.a.
12. The Defendant No. 1 & 2 filed the Written Statement and
Counter-claim under Order VIII Rules 6(a) and 6(b) CPC of about
Rs.77,00,000/- under Order XXXV Rule 4 CPC. The Counterclaim was
returned by the learned Civil Judge, it being beyond the pecuniary
jurisdiction of the Court.
13. The Defendants took the preliminarily objection that the Plaint has not
been drafted as per Order VI CPC. There were no specific dates, particulars
mentioned and the Suit was liable to be dismissed.
14. The averments made in the Plaint were vague and ambiguous, and did
not disclose any cause of action. Mandate of Section 34 Specific Relief Act
is that the Plaintiff has to show his legal character or valid right in the
subject property to lay a claim in respect thereof. Herein, the Plaintiff had
concealed material facts and the Plaint was based on false averments. The
Plaintiff had not approached the Court with clean hands and had tried to
misrepresent the correct facts. The Suit was therefore, liable to be rejected
for which reliance was placed on S. P. Chengalvaraya Naidu (Dead) by LRs.
v. Jagannath (Dead) by LRs., AIR 1994 SC 853.
Signature Not Verified
RFA 286/2020 Page 4 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
15. On merits , the Defendants had admitted giving the contract for site-1
and site-2 to the Plaintiff, for carrying out the repairs and renovation, on the
term that the work was to be completed at both the Sites and handed over,
before 31.07.2008. It was however, claimed that while agreeing for the
work to be done by the Plaintiff, the Defendants had insisted on a written
agreement, to which the Plaintiff did not agree on the pretext that it was a
small work. It was admitted that the payment shall be made on the basis of
actual work done and there would be no advance payment made till the bill
is submitted. The Defendants on these assurances from the Plaintiff,
permitted him to carry out the work at Site-1 and Site-2. The work was
agreed to be completed on or before 31.07.2008.
16. The Defendants explained that the Site-1 had been taken on a monthly
rent of Rs.9,00,000/- excluding service tax and cess by the Defendants, under a
registered Lease Deed dated 26.05.2008, under which the Defendants were
provided with maximum 3 months period for completing the necessary repairs
and renovations at their own costs.
17. The Defendants thereafter, planned to carry out wooden work,
electricity work, glass work, etc., for a period of 25 days for which the work
at the Site was to be completed on 25.08.2008 so that the workshop could
commence functioning from 26.08.2008. The Defendants claimed that the
work was not completed within the timeframe; instead, Plaintiff started
harassing the Defendants by going slow and demanding advance money
without submitting the bills.
18. Further, the payment of Rs.23 lakhs was made to the Plaintiff without
the submission of any bill, and the major part of that money was taken by
Signature Not Verified
RFA 286/2020 Page 5 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
him in advance. It came to the knowledge of the Defendants that the
advance money was being diverted by the Plaintiff to some other contract
taken by him in Connaught Place. Thus, the Defendants reserved their right
to file a Counterclaim to claim damages from the Plaintiff.
19. The Defendants further asserted that the work at both the Sites till
10.09.2008 was not even 50% completed; rather, the Plaintiff abruptly left
the work and started harassing the Defendants through his labour by sitting
on Dharna and damaging the property at the Sites. The act of the Plaintiff
was devoid of any ethics in relation to business community and he cheated
the Defendants. Because of the conduct of the Plaintiff, the workshops could
not be put in operation on 26.08.2008.
20. Another mason was appointed in the month of October 2008, to
complete the remaining work, so that the Site No. 1 & 2 could be put in
operation in first week of January, 2009 and December 2008, respectively.
21. The Defendant No. 1 & 2 further stated that the work done by the
Plaintiff, was not being carried out by employing complete labour work
force; machines required for additions and alterations, were not in proper
number and those machines that were brought on rent, were from his own
persons and were old. The machines that were used broke after every few
hours and the machines kept on getting repaired by the labour, resulting in
wastage of time.
22. The Defendants requested the Plaintiff to rectify these defects and to
bring perfect machines and to call full labour, but despite giving false
assurances, the Plaintiff failed to complete the work and hand over the Sites
before 31.07.2008.
Signature Not Verified
RFA 286/2020 Page 6 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
23. During the month of June & July, 2008, the Plaintiff had demanded an
amount for which the Defendants had asked for the bills for the work done, in
order to release the amount. The Plaintiff insisted on releasing of money
without submitting the bills. On the assurance of the Plaintiff, the Defendants
released payment of Rs.23,00,000/- to the Plaintiff, which is admitted in the
plaint, but corresponding bills were claimed to have never been submitted.
24. The Defendants requested the Plaintiff in July, 2008 to complete
entire work in time, as they would be suffering a loss of more than
Rs.90,000/- per day w.e.f. 01.08.2008.
25. The Plaintiff requested some more time to complete the work. Again,
the Defendants kept on requesting him to complete the work in time bound
manner. Further, in the month of August, 2008 it was noted by the
Defendants that the labour were taking out the material brought on the Sites.
When the Defendants tried to enquire, they were informed that they were
doing so on the instructions of the Plaintiff.
26. On 10.09.2008, when the Plaintiff demanded the payment, the
Defendants had requested the Plaintiff to complete the work as soon as
possible. However, the Plaintiff started abusing the Defendants and
instigated his labour, who threatened the Defendants in order to extort the
unlawful payments. The Plaintiff thereafter, along with the labour, left the
Sites.
27. The Defendants claimed that they suffered a total loss during this
period of Rs.11,97,694/- for Site No. 1 and Rs.10,01,970/- for Site No. 2
besides other losses.
Signature Not Verified
RFA 286/2020 Page 7 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
28. The averments made by the Plaintiff in the Plaint, were denied. It was
submitted that there is no merit in the Suit of the Plaintiff, which is liable to
be dismissed.
29. The Plaintiff in the Replication , re-affirmed the assertions as made
in the plaint.
30. The issues on the pleadings, were framed on 24.05.2014, as under:
“1. Whether the plaintiff had failed to complete the job
work within the time frame as alleged in the written
statement? OPD
2. Whether the plaintiff is entitled to recover a sum of
Rs.18,57,335/- from the defendants as sought in the
plaint? OPP
3. Whether the plaintiff is entitled to the interest? If so,
at what rate and for which period? OPP
4. Relief.”
31. The Plaintiff, Sulakhan Singh examined himself as PW1 and
produced the documents Ex.PW1/1 to Ex. PW1/20, which were the
Statement of Account/Ledger Account Summary, Copy of Muster Role and
Wages Payment Register, Machine Hiring Charges, Photographs, Legal
Notice, Reply and the Complaints that had been made by him.
32. The Defendant No. 1-Sh. Kanwarjit Singh Kochar examined
himself as DW1 and proved the Lease Deed dated 26.05.2008 as DW1/1 and
the computer generated statement of account of the payments of rents as
Ex.DW1/2.
Signature Not Verified
RFA 286/2020 Page 8 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
33. The DW2, Sanjay Kumar, Manager, Recovery of the Defendants
deposed about the two Sites having been taken on rent by the Defendants to
expand their business.
34. The learned ADJ on appreciation of the evidence of the parties,
concluded that the Plaintiff had failed to complete his work job till
31.07.2008, as had been agreed between the parties. It was further held that
the Plaintiff had failed to state in the Plaint or produced any evidence about
the nature and the extent of work that was to be carried out at the two Sites.
35. PW1 even in his testimony had given vague statement about the work
to be done. The Plaintiff had relied upon certain drawings/working drawings
Ex.P-1. (colly), but he failed to disclose as to who had given him those
drawings. It was observed that the drawings had no clarity as regard to the
Site on which the work was done.
36. The Plaintiff had relied upon 59 photographs Ex.PW1/8 (colly) and
the CDs Ex. PW1/9 (colly) to demonstrate the work done on the two Sites,
but these photographs were also not held sufficient to corroborate the claim
of the Plaintiff to prove the work completed at the Sites. The Plaintiff had
deputed two Supervisors Jagir Singh (since deceased) and Sh. Ram Parkash,
but none was examined to support the extent of the work that was done. The
bills Ex.PWl/4 (colly) in respect of Site No. 1 were handwritten bills,
prepared on pages without any dates and were held to be not reliable to
prove the case of the Plaintiff.
37. The Plaintiff was also not able to prove that it was the Defendants
who had stopped the work at Sites.
Signature Not Verified
RFA 286/2020 Page 9 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
38. It was, therefore, held that the Plaintiff was unable to prove his claim
for recovery of money and the Suit was dismissed.
39. Aggrieved by the dismissal of the Suit, present Regular First Appeal
has been preferred.
40. The grounds of challenge are that there were specific averments
made in the Plaint, but the Defendants in their Written Statement, failed to
specifically deny each and every averments and their response was not only
evasive, but also general and not sustainable under the law.
41. The learned ADJ has not considered that all the bills were duly
acknowledged by the Defendants and the same had been proved by the
Plaintiff along with the entries in books of account, and the Defendants’
evidence denying the signatures on the bills, could not have been accepted.
42. It has not been considered that the Defendants did not put any
questions to the Plaintiff's witness during cross-examination, regarding the
defence taken in their Written Statement. The material facts from the books
of account maintained by the Plaintiff in regular course of business, has been
rejected.
43. The Defendants have failed to prove the allegations raised by them,
through cogent and certain evidence. There is no description of the work
assigned and work done by the Appellant on the part of the Respondents.
The photographs and the CDs proved on record, were sufficient to pass a
decree in favour of the Appellant. The circumstances proving the
truthfulness of the case, were rejected by the learned ADJ.
44. The material evidence and the testimony of the witnesses have not
been considered by the learned ADJ. The Defendants had failed to produce
Signature Not Verified
RFA 286/2020 Page 10 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
any statement of account or records, to justify their assertions. The onus was
on the Defendants to prove that the work was not completed within the
timeframe as was alleged in the Written Statement. However, no document
or evidence has been led in this regard.
45. The Defendants had only been intending to delay the process before
the learned Trial Court since 2010, without any reason. On one hand, they
intended to file a Counterclaim, which was returned by learned ADJ on
17.01.2011, but the same has not been filed, as is apparent from the Order
dated 21.09.2016 of the learned ADJ.
46. The learned Trial Court has erroneously disregarded the ratio of the
judgment in Gyan Chand & Bros & Anr. v. Ratan Lal @ Ratan Singh in
Civil Appeal No. 130/2013 decided on 08.01.2013 by the Apex Court.
47. The learned ADJ has not considered the basic principles of law that
when the Appellant had stated some facts, onus of proof shifted on
Respondents, as was held in the case of AIR 94 SC 303.
48. It is therefore, submitted that the Impugned Judgment be set aside
and the Suit of the Plaintiff be decreed.
49. The Respondent No. 1 in the reply to the Appeal as well as
Written Synopsis has referred to the evidences of the parties, to contend
that the evidence has been rightly appreciated to dismiss the Suit of the
Plaintiff/Appellant.
50. The Appellant in the Written Synopsis, has reiterated the grounds as
stated in the Appeal.
Submissions heard and record perused.
Signature Not Verified
RFA 286/2020 Page 11 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
51. It is an admitted case of the parties that Defendant No. 1 & 2 had
engaged the Plaintiff/Appellant for the renovation and repair work at Sites
No. 1 & 2, respectively, and the Site-1 was handed over on 28.05.2008 and
Site-2 was handed over in the first week of June, 2008 to the Plaintiff, for
carrying out the necessary work. Admittedly, there was no written contract
between the parties.
52. The first aspect for consideration is the schedule within which work
was to be completed. The Plaintiff had asserted that the work was to be
completed in the “shortest possible time” , subject to the demand of the
Defendants, but this shortest time was not defined by the Plaintiff, either in
his pleadings or in evidence.
53. The learned ADJ has referred to the testimony of Plaintiff as PW1
where he deposed that “shortest time as mentioned in the last line of page 5
of replication filed by him means that the work was to be completed within
the period of 6 months”. The learned ADJ has rightly observed that the
alleged period of 6 months, was nowhere defined either in the pleadings or
in the affidavit of evidence of the Plaintiff, and this period was for the first
time claimed in the cross-examination. The term used in the pleadings was
‘ shortest time‟ without defining the months within which the work was to be
completed.
54. On the other hand, the Defendants had taken a specific plea that the
work was to be completed, on or before 31.07.2008. To corroborate their
assertions, they have proved registered Lease Deed dated 26.05.2008
Ex.DW1/1 vide which they had taken the Site on a monthly rent of
Rs.9,00,000/- excluding service tax and cess. As per Clause 4 of this Lease
Signature Not Verified
RFA 286/2020 Page 12 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
Agreement, the Lessee was given 3 month’s time for the execution of the
Lease Deed, to carry out the necessary repairs and renovation at their own
costs and no rent was to be charged for this period.
55. The Defendants had asked the Plaintiff to complete the work by
31.07.2008, as they needed 25 days for completion of wooden work,
electricity work, glass work, etc., to ensure that their workshop started
functioning w.e.f. 26.08.2008.
56. The Defendants had stated specifically in their Written Statement that
the work was to be completed by 31.07.2008, which stands completely
substantiated by the testimony of Defendants along with the documents
produced by them. On the other hand, the averments of the Plaintiff about
the tenure of completing the renovation work, were absolutely vague.
57. It has been rightly observed by the learned ADJ that “ it is impossible
to believe that any prudent man entering into a contract for repair and
renovation for such a Site would not make time the essence of the contract,
as clearly he would start suffering losses if the renovation work was not
completed and the workshop not started during the period of 3 months.”
58. Weighing the evidence of both the parties, it has been established that
the work had to be completed by 31.07.2008 as has been rightly held by the
learned ADJ. It is the case of the Plaintiff himself that he had completed
70% of work at Site-1 and 99% work at Site-2. It is the admission of
Plaintiff himself that work had not been completed at the two Sites.
59. Having concluded that the work was not completed, the next pertinent
question which arises is “whether the Plaintiff is entitled to Rs.18,57,335/-,
as claimed by him” . In this context, the first thing which needs to be
Signature Not Verified
RFA 286/2020 Page 13 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
established is that, what exactly was the scope of work to be carried out by
the Plaintiff. It was stated in the Plaint that the work included addition and
alterations, flooring, plaster work, bricks work and other related works.
60. In order to understand the scope of renovation and repair work
undertaken by the Plaintiff, Para No. 4 of the Plaint may be reproduced ,
which reads as under:
“that the Plaintiff and Defendant no.1 and 2 entered
into an oral agreement/contract in the month of May-
2008 for doing additions & alterations, flooring,
plaster work ,bricks work and connected other works
including raising of fresh construction on the above
stated Sites no.1 and 2 in the presence of Defendant
no.3 and Shri Jagir Singh s/o Shri Eachan Singh r/o B-
1851, Shastri Nagar, New Delhi on the rates mutually
agreed between the parties and labour and materials
were to be arranged, provided and supplied by the
Plaintiff.”
61. The bare perusal of the averments so made in Para No. 4 of the Plaint
clearly shows that the exact scope of work has not been defined and there is
only a vague mention, broadly specifying the nature of work which was to
be done at the two Sites. There was as assertion in this paragraph that the
work included fresh construction and the rates were mutually agreed
between the parties.
62. Pertinently, even this term has not been explained by the Plaintiff.
Though, the Defendants also had not stated anything, but the initial onus
was on the Plaintiff to have proved the details of the work and the date at
which the work was to be delivered.
Signature Not Verified
RFA 286/2020 Page 14 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
63. In Para No. 4 of the Plaint, as reproduced above, in the scope of work,
it is also mentioned that the work included raising of fresh construction .
However, there is again, no detail of the kind of fresh construction which
was to be undertaken. Moreover, PW1 /the Plaintiff in his evidence has not
explained what fresh construction was to be carried out. This aspect is also
as vague, as the other averments made by the Plaintiff.
64. The Plaintiff in order to corroborate his assertions, that he had carried
out the renovation and the repair has relied upon the drawings of the Site
which are Ex.PW1/1 (Colly). However, in his entire evidence, he failed to
disclose as to who has given him these drawings.
65. Learned ADJ noted that these drawings were not signed by anyone
and they also did not indicate which Site Plan pertained to which of the two
Sites. These drawings did not even reflect the extent of
construction/renovation that was required to be done.
66. Pertinently, these drawings had not been put to DW1 in the cross-
examination to seek any confirmation about their authenticity and also to
confront him in regard to the extent of repairs/renovations carried out by
him.
67. PW1 in his cross-examination had claimed that there was a delay in
completion of work only because the drawings were not provided by the
Architect. This admission is significant as there is no evidence as to how did
they come in possession of the Plaintiff. Moreover, there is no evidence
about the person who had prepared those Site Plans, and merely by
exhibiting the same as PW1/1 by the Plaintiff, cannot be considered as proof
of contents of the two Site Plans. The learned ADJ thus, rightly observed
Signature Not Verified
RFA 286/2020 Page 15 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
that these two Site Plans did not support the evidence of the Plaintiff to
prove the extent of construction.
68. Furthermore, in order to support his assertions that he had completed
70% work at Site-1 and 99% on Site-2, the Plaintiff had relied upon 59
photographs which are Ex.PW1/8 (colly). These photographs also like Site
Plans did not indicate which photograph pertained to which Site and also
were not depicting the kind and the extent of construction which had been
carried out at the two Sites. These photographs again had not been put to
DW1 either to establish their authenticity or to confront him with the extent
of work done as depicted in the photographs. These photographs again did
not corroborate the assertions made by the Plaintiff.
69. Similar was the fate of videos in Ex.PW1/9, which claimed to have
been prepared of the work done. As noted by learned ADJ, these videos were
not even played during evidence when they were exhibited. These again
were not put to DW1 to establish the authenticity of the two Sites.
70. The next significant aspect was that as per the Plaintiff, the work was
supervised by the two Supervisors, namely, Jagir Singh (since deceased) and
Sh. Ram Parkash. Neither of the Supervisors had been examined, to
corroborate the testimony of the Plaintiff.
71. The Plaintiff had claimed that he had done the work as admittedly
Rs.23,00,000/- were paid by the Defendants. The case of the Defendants is
that 50% work was done, which explains the part payment.
72. To claim the balance amount, the Plaintiff had proved the bills
Ex.PW1/4 (Colly). However, bare perusal of these bills reflect that they are
hand written and prepared on register pages, without any date. There is no
Signature Not Verified
RFA 286/2020 Page 16 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
signature of any person, who had prepared the bills. Not only this, there
were no supporting vouchers about the payments made.
73. These bills no doubt, had endorsement received with some initials
underneath. However, these endorsements of receiving did not have the
stamp or the date of the receiving company. Moreover, the Plaintiff in his
cross-examination had stated that these bills were received by different
persons at different times. The Plaintiff had claimed that signatures on
PW1/4, may be of 3-4 employees, which was against the endorsements on
the bills. Moreover, the Plaintiff failed to give the name of the employees of
the Defendants who had received the bills, which again created a doubt
about the authenticity of the bills on which reliance had been placed by the
Plaintiff. Moreover, learned ADJ observed that it was evident from their bare
perusal, that all the bills had same initials.
74. Mere production of bills without they being supported with any bills
of purchase of material or giving details of labourers cannot be considered
as authentic documents supporting the case of the Plaintiff.
75. It is established from the evidence that the repair and renovation work
was given to the Plaintiff, to be completed by 31.07.2008. However,
admittedly the work continued on the Sites till September, 2008. It is evident
that the Plaintiff failed to complete the work and it was stopped in regard to
which the Plaintiff had allegedly made various complaints. It all reflects that
the Plaintiff had failed to complete the renovation work as was agreed
between the parties and that he was paid Rs.23,00,000/- for the work
executed by him at the two Sites.
Signature Not Verified
RFA 286/2020 Page 17 of 18
Signed By:VIKAS
ARORA
Signing Date:16.06.2026
18:02:01
76. The onus was on the Plaintiff to have proved the extent of work
carried out and also to corroborate that the work under the disputed bills,
pertained to the work that had already been executed by him.
77. The learned ADJ rightly observed that once the work had been
stopped midway, it is as ordinary prudence dictates that the Plaintiff had not
completed the entire work. From the evidence as led by the parties, it is
established that he has received the money for the work executed by him.
The Plaintiff was unable to prove his claim for Rs.18,57,335/- towards the
work executed by him at the Sites, for which the payment has not been made
to him.
78. The learned ADJ in a well detailed and well appreciated evidence,
has rightly dismissed the Suit of the Plaintiff.
Conclusion:
79. There is not merit in the present Appeal, which is hereby, dismissed.
The pending Application(s), if any, are disposed of accordingly.
(NEENA BANSAL KRISHNA)
JUDGE
JUNE 16, 2026/ N
Signature Not Verified
RFA 286/2020 Page 18 of 18