Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 10
CASE NO.:
Appeal (civil) 6656-6657 of 1994
Appeal (civil) 5115-5117 of 1996
Appeal (civil) 5118-5120 of 1996
PETITIONER:
VERIGAMTO NAVEEN
Vs.
RESPONDENT:
GOVERNMENT OF ANDHRA PRADESH & ORS.
DATE OF JUDGMENT: 18/09/2001
BENCH:
S. Rajendra Babu & D.P. Mohapatra.
JUDGMENT:
[With C.A.Nos. 6658-6659/94, 6642-6646/94, 6647-6650/94 & 6651-6655/94]
J U D G M E N T
RAJENDRA BABU, J. :
In these two sets of appeals, the appellants are calling in question
two orders made by two Full Benches of the High Court one on
September 2, 1994 and the other on March 4, 1996.
CIVIL APPEAL NOS. 6656-6657/94, 6658-6659/94, 6642-6646/94,
6647-6650/94 & 6651-6655/94
The Government of Andhra Pradesh declared, on 7.1.1974, that
the barytes ore bearing areas in Mangampett and Anandarajpet of
Cuddapah District are reserved exclusively for exploitation in the public
sector however excluding the lands that had already been leased to
private persons. By two notifications issued on 10.2.1975 and 19.2.1983,
the Government of Andhra Pradesh granted mining leases over an extent
of different areas in favour of the Andhra Pradesh Mineral Development
Corporation [hereinafter referred to as the Corporation]. On 6.1.1991,
the Government of Andhra Pradesh accorded permission for grant of
sub-lease by the Corporation subject to certain terms and conditions
mentioned in G.O.Ms.No. 215 dated 22.4.1980. The Government of
Andhra Pradesh by different orders accorded permission for grant of sub-
lease for further extent of lands in the month of May 1991. The
Government of Andhra Pradesh on 1.12.1993 took decision to put an end
to all the existing sub-leases in order to enable the Corporation to carry
on the mining operations directly and on 7.12.1993, the Government
withdrew permission granted earlier to the Corporation to grant sub-
leases in respect of certain areas.
The appellants in the first set of appeals challenged, by way of writ
petitions before the High Court on the various grounds, the validity and
legality of the said notifications withdrawing the permission granted
earlier to sub-lease the mining lands in question. The learned Single
Judge of the High Court allowed the writ petitions on the basis that the
Government had not followed due procedure as contemplated under
Section 4-A of the Mines & Minerals (Regulation & Development) Act,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 10
1957 [hereinafter referred to as the Act] and Rule 37 of the Mineral
Concession Rules, 1960 [hereinafter referred to as the Rules]. Writ
appeals were preferred against the same and the Division Bench referred
the matter to a Full Bench.
In writ appeals Nos. 131/94 to 134/94 and 169/94 to 175/94, the
Full Bench of the High Court examined the questions raised before it by
an order made on 2.9.1994. The Full Bench first considered the effect of
clauses 15 and 16 in the deed of sub-lease executed by the Corporation.
It was observed by the Full Bench that clause 15 reserved the right of the
lessee Corporation to terminate the sub-lease if there is any violation of
terms and conditions of the lease or default or any breach of contract
and, therefore, the High Court felt that it was nobodys case that the
Corporation has taken steps to pre-maturely terminate the sub-leases
because none of the conditions for exercise of that right having arisen. It
was also held that Clause 16 merely provided that in the event of
termination of sub-leases any damage was to arise by reason of the State
Government withdrawing the permission under Rule 37A of the Rules
during the tenure of the leases or on account of any other governmental
action, the sub-lessee is precluded from claiming damages from the
lessee Corporation. Therefore, the Full Bench felt that neither Clause 15
nor Clause 16 is attracted to the case.
Next the Full Bench examined as to whether the order directing the
premature determination of the sub-lease without complying with
Section 4A(3) of the Act or withdrawing consent for sub-lease without
notice is invalid in law. On examination of the scheme of the Act, the
Full Bench found that undisputedly barytes is a major mineral and
Section 4A(1) of the Act is attracted only in cases of major minerals and
in the present cases, the State Government could not have exercised that
power as available under Section 4A of the Act because that was
reserved only to the Central Government.
Thereafter, the Full Bench considered the withdrawal of consent
given for granting the sub-leases to the Corporation in favour of the writ
petitioners. This aspect was examined with respect to the scope of Rule
37 of the Rules. Rule 37, as such, does not provide for withdrawal of the
consent once given and, therefore, the Government and the Corporation
relied upon the executive power of the Government to withdraw the same
or whatever could be done under the Rules could be undone as provided
under the General Clauses Act. On this aspect also, the Full Bench felt
that inasmuch as barytes being a major mineral coming under the
exclusive jurisdiction of the Central Government under the Act, the
executive power of the State could extend only to the extent of the
legislative power to be exercised by the State and, therefore, no executive
power was available to the State Government. On the argument raised
on the basis of the General Clauses Act, it was held that this is not a
simple case of mere grant of permission and withdrawal without any
other consequences. Further the same procedure as provided in the
matter of grant of permission should have been followed in the matter of
withdrawal of permission, but such procedure had not been followed.
The High Court did not agree that the exercise of power was under that
provision and that was sufficient for the Full Bench to proceed to dispose
the matter.
However, the Full Bench noticed certain other arguments, namely,
[1] that no consent under Rule 37 of the Rules could have been granted
by the State Government and no sub-lease could have been entered into
between the lessee Corporation and the writ petitioners in respect of any
part of the area reserved under Rule 58 of the Rules having regard to the
provisions of Rule 59(1) of the Rules; [2] that prior approval of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 10
Central Government as contemplated under Rule 37 of the Rules had not
been obtained; [3] the infirmities and irregularities pointed out in the
House Committee Report will be perpetuated resulting in immense public
harm unless the leases are cancelled and consent is withdrawn. The Full
Bench did not express any opinion on these three aspects. The Full
Bench declined to examine these aspects because these were not
grounds indicated in the course of the order of the Government while
withdrawing consent or order of Corporation in cancelling the sub-
leases.
The Full Bench dismissed the writ appeals in the following terms:
We leave it open to the appellants if they propose to
terminate the sub-leases or withdraw the consent, to
issue notices to the sub-leases to show cause as to why
such an action should not be taken, grant them
reasonable time for submitting their explanation,
consider the same and pass appropriate orders in
accordance with law. For this purpose, we consider it
just to direct the parties to maintain status-quo
obtaining as on this day for a period of 3 months from
today. If no fresh orders are passed within the said
period of three months pursuant to the show cause
notice, it would be open to the sub-leases to proceed
with the mining operations in accordance with the sub-
leases granted to them. The orders under appeals are
accordingly modified and subject to the above
modification and observations, the appeals are
dismissed, but in the circumstances of the case, we
direct the parties to bear their own costs.
The decision of the Full Bench is reported in AIR 1995 AP 1
(Government of Andhra Pradesh vs. Y.S. Vivekananda Reddy).
Against this order the writ petitioners, the Government and the
Corporation have come up in appeal and this Court while granting leave
made an order on 6.10.1994 in the following terms:
As a result of the cancellation of the sub-leases and
withdrawal by the State Government of its consent for
grant of the sub-leases by the Corporation being held
by the High Court to be void in its judgment, the
operation of the further direction given by the Full
Bench of the High Court to maintain status quo for a
period of three months from the date of the judgment
meaning thereby that the sub-leases would not be
entitled to carry on the mining operations till then,
shall remain stayed. The sub-lessees shall, however,
maintain true and faithful account of the mining
operation which would be verified by the appropriate
Mining Officer every fortnight. It is clarified that the
exercise of the right of the Corporation as well as the
State Government to proceed in accordance with law
as a result of the High Courts judgment is not stayed.
Thereafter, during the pendency of these proceedings, the
Government of Andhra Pradesh issued notices and on receipt of replies
thereto, heard the appellants, who are the original writ petitioners, and
decided against them. Against that decision, revision petitions were filed
under Section 30 of the Act read with Rule 35 of the Rules before the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 10
Central Government [Tribunal] and the Central Government [Tribunal] by
its order made on 9.9.1998 dismissed the said revision petitions. It
appears that only one petitioner, C.M.Ramanath Reddy alone filed
W.P.Nos.36884/98 and 366885/98 against that order of the Central
Government [Tribunal] before the High Court and the same are pending.
The sub-leases granted in favour of the writ petitioners are detailed
as under:
Name of the
Sub Lessee
State Govt.
permission No. &
Date
Survey
Numbers
Extent
Date of
execut- of
Sub lease
Deed
Date of
Expiry
1. Sri K.
Sivananda
Reddy (Legal
heir of Late Sri
K.Obul Reddy
Memo No.
1515/M.III/80-1
Dt. 28-8-1980
70/5 B and C
0.8741
hectares
3-9-1980
21-9-1998
2. Sri Y.S. Raja
Reddy
G.O.MS.No. 455
Dt. 19-7-1982
133/1 to 9 parts
134/1 to 6 parts
3.102
hectares
20-7-1982
18-2-1995
3. Sri C.M.
Ramanatha
Reddy
Memo No.
1935/M.III/80-1
Dt. 19-9-1984
70/1, 71/2 part
0.2064
hectares
29-9-1984
19-9-1998
4. Sri C.M.
Ramanatha
Reddy
Memo
No.1973/M.III/8
0-1
dt. 19-9-1984
70/6 part, 74/4,
74/5, 70/7,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 10
69/3 part &
70/5 part
0.1660
hectares
29-9-1984
19-9-1998
5. Sri C.M.
Ramanatha
Reddy
Memo
No.1940/M.III/8
0-1
Dt. 19-9-1984
74/1 part, 74/2
part & 74/8
0.8503
hectares
29-9-1984
21-9-1998
6. Sri C.M.
Ramanatha
Reddy
Memo
No.1614/M.III/80
-1
Dt. 19-9-1984
75/1
0.3800
hectares
29-9-1984
1-9-1998
7. Sri C.M.
Ramanatha
Reddy
Memo
No.2085/M.III/80
-1
Dt. 19-9-1984
63/2
0.8800
hectares
29-9-1984
17-6-1998
8. Sri C.M.
Ramanatha
Reddy
G.O.MS.No. 441
Dt. 5-11-1990
75/2 to 5, 78/8
to 10, 111 part,
112
Acres
4.845
(1.9607
hectares)
8-11-1990
18-2-1995
9. Sri Y.S.
Vivekananda
Reddy
M/S
Vijayalakshmi
Minerals
Trading Co.
G.O.MS.No. 194
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 10
Dt. 1-6-1991
71/1, 72/3A
part, 72/6 part,
37/6 part, 37/4
part, 124 part,
114 part, 115
part
Acres
4.49
Cents
(1.8170
hectares)
4-6-1991
18-2-1995
10. Sri K. Raja
Mohan Reddy
G.O.MS.No. 148
Dt. 25-4-1991
79
Acres
1.90
(0.7525
hectares
8-5-1991
18-2-1995
The sub-leases granted in all these cases except one in favour of
the V.Ramalingaiah comprised in Survey Nos.83/1, 8 to 10, 84/2, 20
and 22, measuring about 1 acre 89 cents, have expired either in the year
1985 or 1988 and in case of C.M.Ramanatha Reddy it had expired in the
month of June, 1998 while in case of others it had expired in the month
of September 1998. The relief sought for in the writ petitions is in
relation to cancellation of the sub-leases. On that aspect the writ
petitioners succeeded while the Government and the Corporation could
not sustain the action taken by them. Now when the mining leases have
come to an end by efflux of time and the term of those sub-leases have
already expired, it will be an academic exercise to examine the various
contentions urged in these appeals. Therefore, we are of the view that
these appeals filed either by the private parties or by the Government
and the Corporation have become infructuous.
Thus the first set of appeals are disposed as having become
infructuous, except to the extent indicated in case of Sri V.
Ramalingaiah.
From the facts available on record Sri V. Ramalingaiah obtained
sub-lease pertaining to land comprised in Survey Nos. 83/1, 8 to 10,
84/2, 20 and 22, measuring about 1 acre 89 cents on 17.5.1991. It is
not clear as to whether this lease is granted pursuant to the earlier
general permission obtained from the Government in respect of all sub-
leases under Rule 37 or any separate permission was secured from the
Government and on what date. Therefore, it becomes necessary to
examine as to when the consent was given in his case. Let the
Government determine if the consent in this case has been given
subsequent to the amendment of Rule 37 of the Rules. The sub-lease
may get affected if it is later than 20.2.1991, when amended Rule 37 of
the Rules came into effect, and if it is earlier than 20.2.1991, it may not,
and it is open to the Government to take appropriate steps in his case.
CIVIL APPEAL NOS. 5115-5117/96 & 5118-5120/96
The period of sub-leases in each of these cases expired on
18.2.1995 or in September 1998 on different dates or in case of one lease
on 17.6.1998. Thereafter another set of writ petitions was filed before
the High Court. In that batch of cases, the contention put forth is that
on account of illegal cancellation of the sub-leases and withdrawal of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 10
consent by the State Government, the writ petitioners could not work the
mines for a substantial period and they could not do so on account of the
orders made by the High Court to maintain status quo and started
operating only after this Court gave direction on 6.10.1994, after which
alone they could resume mining operations and they claimed that they
are entitled for exclusion of the period and appropriate relief. The High
Court based its decision on the findings recorded by the Full Bench in
Y.S.Vivekananda Reddys case and held that the withdrawal of the
consent by the State Government for grant of sub-leases and their
cancellation is void.
Two issues were posed before the High Court by the writ petitions
in the following terms:
1. Whether the sub-leasees are entitled to be
compensated for the loss of the period of the mining
operation/work by them on account of illegal withdrawal of
the consent and the cancellation of the sub-leases by the
State Government? And
2. If it is held that they are entitled to be compensated,
whether the compensation will be by treating the period of
lease completed by adding to it the period lost by illegal
interruptions?
The writ petitioners contended that there were interruptions for the
period 17.12.1993 to 6.10.1994 and in writ petition No. 22730/94 there
was an additional loss of period of six months and sixteen days from
2.1.1991 to 18.6.1991 by an order of stay of the sub-leases granted in
their favour by the State Government and the Corporation.
In answering the contention urged on behalf of the State that the
State Government shall not grant to any person a mining lease except
with the previous approval of the Central Government, the High Court
proceeded to hold that the restriction is upon the grant of mining lease
on the State Government and the State Government had already granted
sub-leases in favour of the Corporation and the State Government is not
leasing the lands in question in favour of the writ petitioners. The sub-
lease is granted by the Corporation, to which the lease has already been
granted and, therefore, sub-lease made is in order. However, reliance
was placed on Rule 37 of the Rules, which was amended substantially on
20.2.1991 and imposed the condition that the lessee shall not without
the previous consent in writing of the State Government and in the case
of mining lease in respect of any mineral specified in the First Schedule
to the Act, without the previous approval of the Central Government,
assign, sublet, mortgage, or in any other manner, transfer the mining
lease, or any right, title or interest therein or enter into or make any
bona fide arrangement, contract or understanding. Sub-leases having
been granted prior to February 20, 1991, the High Court took the view
that Rule 37 was not attracted to the case of the writ petitioners.
Thereafter, the High Court proceeded to consider as to in what manner
the writ petitioners should be compensated and held that any speculative
compensation, in their opinion, in the form of damages, will not be
proper and appropriate and further held that the Government and the
Corporation were liable to put the writ petitioners in possession of the
leasehold property to continue their mining operations for the periods
which they have lost in all cases from 17.12.1993 to 6.10.1994 and in
the case of petitioner in writ petition no. 22730/94 from 2.1.1991 to
18.6.1991. It is this order, which is in challenge before us in this set of
appeals.
On behalf of the Government and the Corporation, the following
contentions have been raised :
1. No prior permission having been obtained from the Central
Government to grant the sub-lease, which is also a kind of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 10
lease, is void ab initio either under Section 4-A of the Act or
under Rule 37 of the Rules.
2. In the decision rendered in W.A. No. 131 of 1994 and connected
matters by the Full Bench no question was decided and the Full
Bench of the High Court could not presume that validity or
otherwise of the leases has been decided.
3. Even under the terms of the contract of sub-lease, the writ
petitioners are not entitled to damages.
4. The order for specific performance could not have been passed
at all, which is a matter arising purely in a contractual field.
5. After the expiry of the lease restoration of property is not
available at all.
Under Section 4A of the Act the restriction to grant lease without
permission of the Central Government is upon the State Government and
not upon the Corporation to which the State Government had already
granted lease. Hence, lease being void ab initio would not arise. The
consent to grant the sub-leases had been given a long before to coming
into force of the amendment to Rule 37 of the Rules and inasmuch as in
all sub-leases (except in the case of V.Ramalingaiah, which came into
existence only in the month of May, 1991, i.e., after 20.2.1991, the date
of amendment) this amended rule which required a prior approval of the
Central Government is not required and, therefore, the contention that
the sub-leases are void ab initio would not arise. Therefore, the view
taken by the Full Bench on this aspect is correct.
On the question that the relief as sought for and granted by the
High Court arises purely in the contractual field and, therefore, the High
Court ought not to have exercised its power under Article 226 of the
Constitution placed very heavy reliance on the decision of the Andhra
Pradesh High Court in Y.S.Raja Reddy vs. A.P.Mining Corporation
Ltd., 1988(2) ALT 722, and the decisions of this Court in Harshankar vs.
Deputy Excise & Taxation Commissioner, 1975 (1) SCC 737;
Radhakrishna Agarwal vs. State of Bihar, AIR 1977 SC 1496; Ram Lal
& Sons vs. State of Rajasthan, AIR 1976 SC 54; Shiv Shankar Dal
Mills vs. State of Haryana, AIR 1980 SC 1037; Ramana vs.
I.A.Authority of India, AIR 1979 SC 1628; Basheeshar Nath vs.
Income Tax Commissioner, AIR 1959 SC 149. Though there is one set
of cases rendered by this Court of the type arising in Radhakrishna
Agarwals case, much water has flown in the stream of judicial review in
contractual field. In cases where the decision making authority exceeded
its statutory power or committed breach of rules or principles of natural
justice in exercise of such power or its decision is perverse or passed an
irrational order, this Court has interceded even after the contract was
entered into between the parties and the Government and its agencies.
We may advert to three decisions of this Court in M/s Dwarkadas
Marfatia & Sons vs. Board of Trustees of the Port of Bombay, 1989(3)
SCC 293; Mahabir Auto Stores & Ors. vs. Indian Oil Corporation &
Ors., 1990(3) SCC 752; and Srilekha Vidyarthi vs. State of U.P., AIR
1991 SC 537. Where the breach of contract involves breach of statutory
obligation when the order complained of was made in exercise of
statutory power by a statutory authority, though cause of action arises
out of or pertains to contract, brings within the sphere of public law
because the power exercised is apart from contract. The freedom of the
Government to enter into business with anybody it likes is subject to the
condition of reasonableness and fair play as well as public interest. After
entering into a contract, in cancelling the contract which is subject to
terms of the statutory provisions, as in the present case, it cannot be
said that the matter falls purely in a contractual field. Therefore, we do
not think it would be appropriate to suggest that the case on hand is a
matter arising purely out of a contract and, therefore, interference under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 10
Article 226 of the Constitution is not called for. This contention also
stands rejected.
The fact that the cancellation of sub-leases or withdrawal of
consent being void flowing from the order of the Full Bench decision of
the High Court has also been noticed by this Court in its interim order
dated 6.10.1994 and hence the High Court proceeding on that basis in
its order is not incorrect.
There was, therefore, no impediment for the High Court to find out
whether there is breach of contract so as to enable the parties to claim
damages or the liability of the Corporation or the Government to make
good the same.
For the sake of convenience, we will proceed to examine first the
question as to the exercise of discretion by the High Court in extending
the period of lease or sub-lease after its original period had expired.
In Kalyanpur Lime Works Ltd. vs. State of Bihar & Anr., AIR
1954 SC 165, the Government had entered into a contract with Lime
Company and when it entered into the said contract it had an imperfect
title inasmuch as it could not grant a fresh lease to anyone during the
existence of the previous lease in favour of another party and when the
lease in favour of another party expired the impediment in the way of the
Government to grant stood removed and the Lime companys right to get
the lease revived in its favour was urged. It was held that though Section
18 of the Specific Relief Act, 1877 was attracted to the case but as
substantial period of lease had already expired, relief could be given only
under Section 15 of the Specific Relief Act. Therefore, in that case this
Court did not think that it was a fit case for grant of decree for specific
performance as there are only a few months left before unexpired portion
of the lease will run out. Indeed by the time the lease comes to be
extended in pursuance of the Courts order it would be scarcely
worthwhile to carry on quarrying operations.
There are at least three weighty reasons as to why the period of
sub-lease could not have been extended after the expiry of period of
original lease and they are :-
(i) In most of the present cases, the interruptions in
respect of which the claim is made is for a period of
about 10 months and in one other case an additional
period of 6½ months. In some cases the lease having
expired as early as in the year 1995 or in others in
1998, it would not be appropriate to direct the
extension of lease in the year 2001 particularly when
the sub-leases have expired as a result of which the
parties have to re-establish their infrastructure and
put in great deal of logistical support though for a
short period once over again, to work the mines which
will have a pernicious effect on the mines and the
parties concerned.
(ii) The claim for renewal of leases has been refused
already as the policy of the Government is not to grant
lease or sub-lease in favour of private parties. Now to
ask to the Government to enter into fresh contracts
will be contrary to its policy.
(iii) When several malpractices had been pointed out by
House Committee, it would not be in public interest to
extend the period of lease which will perpetuate the
same.
Therefore, the High Court ought not to have exercised its discretion
for extension of period of sub-lease.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 10
For the reasons aforesaid, we think, it would be appropriate to set
aside the order made by the High Court and allow these appeals to the
extent the High Court has granted the relief of extension of the sub-
leases.
Insofar as claim for damages is concerned, it is unnecessary for us
to decide the same inasmuch as it would be appropriate for the parties to
work out their respective rights by making an appropriate claim in a civil
suit to be filed by each one of them. We have refused the relief of
restitution by way of extension of lease period without examining the
question as to whether there is breach of contract as a consequence of
which the party aggrieved is entitled to damages. That aspect is left open
to be considered or be dealt with in the civil suit irrespective of and
uninfluenced by the observations or findings of the High Court on this
aspect. If such a civil suit is filed, the cause of action should be
reckoned only from the date of this order when we finally pronounced
upon the rights of the parties, which protection will adequately take care
of the interests of the writ petitioners.
Subject to the aforesaid observations, the second set of appeals
shall stand partly allowed. No costs.
...J.
[ S. RAJENDRA BABU ]
...J.
[D.P.MOHAPATRA]
SEPTEMBER 18, 2001.