Full Judgment Text
Neutral Citation Number : 2023:DHC:2982
$~17 & 18
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of decision: 26 April, 2023
(17)+ O.M.P. (COMM) 451/2017
GREAT EASTERN ENERGY CORPORATION LIMITED
..... Petitioner
Through: Mr.Darpan Wadhwa, Sr. Adv.
with Mr.Ajay Bhargava,
Mr.Aseem Chaturvedi &
Mr.Shivank Diddi, Advs.
versus
SOPAN PROJECTS
..... Respondent
Through: Mr.V. Seshagiri, Mr.Adhish
Rajvanshi, Mr.Bikram
Bhattacharya, Advs. with
Mr.Gaurav Sachar, AR.
(18)+ O.M.P. (COMM) 100/2018
SOPAN PROJECTS
..... Petitioner
Through: Mr.V. Seshagiri, Mr.Adhish
Rajvanshi, Mr.Bikram
Bhattacharya, Advs. with
Mr.Gaurav Sachar, AR.
versus
GREAT EASTERN ENERGY CORPORATION LTD.
..... Respondent
Through: Mr.Darpan Wadhwa, Sr. Adv.
with Mr.Ajay Bhargava,
Mr.Aseem Chaturvedi &
Mr.Shivank Diddi, Advs.
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 1 of 19
Neutral Citation Number : 2023:DHC:2982
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
NAVIN CHAWLA, J. (ORAL)
1. These cross petitions under Section 34 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) have been
filed by both the parties to the arbitration proceedings, challenging the
Arbitral Award dated 10.11.2017 (hereinafter referred to as the
‘Impugned Amended Arbitral Award’) passed by the learned Sole
Arbitrator.
2. The disputes between the parties arose out of the Work Order
for construction/expansion of existing Gas Gathering Station-North
placed by Great Eastern Energy Corporation Limited (hereinafter
referred to as the ‘petitioner’) on Sopan Projects (hereinafter referred
to as the ‘respondent’). The said disputes were settled by an Arbitral
Award dated 25.08.2017 (hereinafter referred to as the ‘Original
Award’) passed by the learned Sole Arbitrator. The respondent
thereafter filed an application under Section 33 of the Act. On the said
application, the learned Sole Arbitrator passed an order dated
25.10.2017, allowing the application of the respondent and making
certain corrections in the Award. The petitioner, aggrieved of the said
order, filed an application seeking recall of the said order, on which,
with the consent of the parties, the learned Sole Arbitrator recalled the
order dated 25.10.2017 and the amended Award dated the same. The
learned Sole Arbitrator, on hearing the parties on the application filed
by the respondent, by an order dated 10.11.2017, allowed the said
application and passed the Impugned Amended Arbitral Award. As
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 2 of 19
Neutral Citation Number : 2023:DHC:2982
noted herein above, both the parties to the arbitration proceedings
challenge the Impugned Amended Arbitral Award.
3. The learned senior counsel for the petitioner submits that in
terms of the Original Award dated 25.08.2017, the learned Sole
Arbitrator had awarded a sum of Rs.32,02,553/- in favour of the
petitioner herein, while further directing that the respondent would be
entitled to a sum of Rs.24,73,375/- towards Central Sales Tax and
Entry Tax. He submits that the petitioner duly implemented the Award
as far as the Central Sales Tax and Entry Tax is concerned, and issued
Form C to the respondent. It was, therefore, only the petitioner who
was to receive a sum of Rs.32,02,553/- from the respondent. He
submits that even this amount was adjusted against the amounts
awarded in favour of the respondent under the other Arbitral Awards
dated 25.08.2017 between the same parties.
4. He submits that by the Impugned Amended Arbitral Award
passed by the learned Sole Arbitrator, purportedly under Section 33 of
the Act, the learned Sole Arbitrator has in fact reviewed his Original
Award. He submits that by the Impugned Amended Arbitral Award,
the learned Sole Arbitrator has held the respondent to be entitled to
Service Tax, a claim that was expressly rejected by the learned Sole
Arbitrator in the Original Award.
5. He submits that the learned Arbitrator in the Impugned
Amended Arbitral Award has reduced the ad hoc amount admittedly
received by the respondent from the petitioner, from Rs.3,31,56,341/-
to Rs.2,25,91,275/-, and on basis thereof, instead of the respondent
owing an amount to the petitioner, the petitioner has been found liable
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 3 of 19
Neutral Citation Number : 2023:DHC:2982
to pay a sum of Rs.79,08,206/- to the respondent. He submits that this
also amounts to review of the Original Award.
6. He further submits that in the Original Award, there was no
direction for payment of interest, whereas in the Impugned Amended
Arbitral Award, the petitioner has been held liable to pay interest at
the rate of 8% per annum from the date of filing of the Statement of
Claim and future interest at the rate of 2% higher than the current rate
of interest prevalent on the date of the Award. He submits that for
award of interest, leave alone the same being in the form of a review
of the Award, no reasons have been given by the learned Sole
Arbitrator for either the rate or period of interest. He submits that even
otherwise, the learned Arbitrator could not have awarded a higher rate
of interest on default of the petitioner to pay the awarded amount. The
learned Arbitrator has no power to grant penalty.
7. The learned senior counsel for the petitioner places reliance on
the judgments of the Supreme Court in State of Arunachal Pradesh v.
Damani Construction Co. , (2007) 10 SCC 742 and Gyan Prakash
Arya v. Titan Industries Limited , (2023) 1 SCC 153, and submits that
in the garb of an application under Section 33 of the Act, the learned
Sole Arbitrator could not have reviewed his Award and passed a fresh
Award.
8. The learned senior counsel for the petitioner submits that for the
above reasons, the Impugned Amended Arbitral Award should be set
aside by this Court, while keeping the original Arbitral Award dated
25.08.2017 intact. He submits that in Gyan Prakash Arya (supra), the
Supreme Court had also restored the original Award while setting
aside the modified Award.
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 4 of 19
Neutral Citation Number : 2023:DHC:2982
9. On the other hand, the learned counsel for the respondent
submits that the Original Award suffered from clerical and
computational errors apparent on the face of the Award. He submits
that the application under Section 33 of the Act was, therefore, rightly
filed and has been allowed by the learned Arbitrator. In support, he
submits that it cannot be disputed that the respondent had filed 17
invoices on record before the learned Sole Arbitrator. The learned
Sole Arbitrator while passing the Original Award, had considered only
16 invoices, as is reflected in the Original Award itself. He submits
that this, therefore, was a clerical error, which has been rightly
corrected by the learned Arbitrator. He submits that, in fact, the
respondent is aggrieved of even the Impugned Amended Arbitral
Award, as the claim of the respondent could not have been curtailed to
only the invoices that were placed on record once the petitioner had
not disputed that in all 22 invoices had been raised by the respondent
on the petitioner.
10. On the grant of Service Tax, he submits that merely because the
relevant Clause was not reproduced in the written submissions of the
respondent, the learned Sole Arbitrator in the original Arbitral Award
held that the Service Tax was not payable to the respondent. In the
Impugned Amended Arbitral Award, the learned Arbitrator has,
therefore, rightly included the quantum of Service Tax while granting
the claim of the respondent on the invoices.
11. He submits that there was an apparent arithmetical error also in
considering the amount of bank guarantee, both as an admitted
amount paid to the respondent as also for the adjustment made in
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 5 of 19
Neutral Citation Number : 2023:DHC:2982
favour of the petitioner. For this reason, the reduction in the ad hoc
amount liable for adjustment cannot be faulted.
12. He further submits that the learned Arbitrator in the original
Award had also made an arithmetical error in taking the admitted
amount received by the respondent as Rs. 3,31,56,341/-. In this regard
he has drawn my attention to the paragraphs 5.3 and 5.4 of the
Statement of Claim, wherein it is mentioned that the total amount of
Rs.3,31,56,341/- received by the respondent from the petitioner
includes an amount of Rs. 1,05,65,066/- paid directly by the petitioner
to the suppliers. He submits that once the Arbitrator has held that the
respondent cannot lay any claim on the supply invoices post the
amendment of the Contract, wherein payment was to be made directly
to the suppliers by the petitioner, this amount also was not liable to be
adjusted as received by the respondent. In such a situation, both the
invoices for supply as also the payment made against them, are to be
excluded from consideration. He submits that, therefore, there was
clearly an arithmetical error in taking the amount of adjustment as
Rs.3,31,56,341/-, and the same has rightly been rectified in the
Impugned Amended Arbitral Award.
13. On the respondent’s own challenge, the learned counsel for the
respondent submits that the respondent has made a total claim of
Rs.7,06,37,274/- as invoices unpaid between the period 20.03.2012 to
08.01.2013. The learned Arbitrator, however, has arbitrarily reduced
the said claim to Rs.1,14,28,741/-. He submits that no reason has been
given by the learned Arbitrator to confine the claim to only 17
invoices, especially where the witnesses of the petitioner had admitted
that in all 22 invoices were raised by the respondent on the petitioner
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 6 of 19
Neutral Citation Number : 2023:DHC:2982
for a sum of Rs.7,06,37,274/-. Once the learned Arbitrator found that,
in principle, all these invoices were payable, he could not have
confined the Award only to 17 invoices.
14. I have considered the submissions made by the learned counsels
for the parties.
15. It cannot be disputed that the power of the Arbitrator under
Section 33 of the Act is rather limited and can be invoked only to
correct any computational errors, clerical or typographical errors, or
other errors of a similar nature occurring in the Award, or where the
parties were aggrieved, give an interpretation of a specific point or
part of the Award. The Arbitral Tribunal may also make an additional
Award on the claim presented in the arbitral proceedings but omitted
from the Arbitral Award. The said power, however, does extend to
review of the Award on merit.
16. In Damani Construction Co . (supra), the Supreme Court has
held as under:-
“8. Firstly, the letter had been designed not
strictly under Section 33 of the Act because
under Section 33 of the Act a party can seek
certain correction in computation of errors, or
clerical or typographical errors or any other
errors of a similar nature occurring in the
award with notice to the other party or if
agreed between the parties, a party may
request the Arbitral Tribunal to give an
interpretation of a specific point or part of the
award. This application which was moved by
the appellant does not come within any of the
criteria falling under Section 33(1) of the Act.
It was designed as if the appellant was seeking
review of the award. Since the Tribunal had no
power of review on merit, therefore, the
application moved by the appellant was wholly
misconceived. Secondly, it was prayed whether
the payment was to be made directly to the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 7 of 19
Neutral Citation Number : 2023:DHC:2982
respondent or through the court or that the
respondent might be asked to furnish bank
guarantee from a nationalised bank as it was
an interim award, till final verdict was
awaited. Both these prayers in this case were
not within the scope of Section 33. Neither
review was maintainable nor the prayer which
had been made in the application had anything
to do with Section 33 of the Act. The prayer
was with regard to the mode of payment. When
this application does not come within the
purview of Section 33 of the Act, the
application was totally misconceived and
accordingly the arbitrator by communication
dated 10-4-2004 replied to the following
effect:
“However, for your benefit I may
mention here that as per the scheme of
the Act of 1996, the issues/claims that
have been adjudicated by the interim
award dated 12-10-2003 are final and
the same issues cannot be gone into
once again at the time of passing the
final award.”
9. Therefore, the reply given by the
arbitrator does not give any fresh cause
of action to the appellant so as to move
an application under Section 34(3) of
the Act. In fact, when the award dated
12-10-2003 was passed the only option
with the appellant was either to have
moved an application under Section 34
within three months as required under
sub-section (3) of Section 34 or within
the extended period of another 30 days.
But instead of that a totally
misconceived application was filed and
there too the prayer was for review and
with regard to mode of payment. The
question of review was totally
misconceived as there is no such
provision in the Act for review of the
award by the arbitrator and the
clarification sought for as to the mode
of payment is not contemplated under
Section 33 of the Act. Therefore, in this
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 8 of 19
Neutral Citation Number : 2023:DHC:2982
background, the application was totally
misconceived and the reply sent by the
arbitrator does not entitle the appellant
a fresh cause of action so as to file an
application under Section 34(3) of the
Act, taking it as the starting point of
limitation from the date of reply given
by the arbitrator i.e. 10-4-2004.”
(Emphasis Supplied)
17. In the present case, it is evident that the learned Arbitrator has
reviewed the original Award on various aspects, including on the
aspect of Service Tax. In the original Award, the learned Arbitrator
has held as under:-
“The service tax claimed by the Claimant is
not being awarded as the contract was an all
inclusive contract except for Central Sales
Tax.”
18. However, in the Impugned Amended Arbitral Award, the
learned Arbitrator has held as under:-
“The service tax claimed by the Claimant is
being awarded as the contract was exclusive
of service tax.”
19. The learned Arbitrator in his order dated 10.11.2017, passed on
the application of the respondent filed under Section 33 of the Act, has
explained the reason for this change as under:-
“In respect of the service tax, the Claimant
argued that the contract was a lump sum
contract exclusive of service tax and central
sales tax and in support the clauses were
shown during the argument. However in the
written submissions the service tax clause was
not extracted and due to voluminous pleadings
in this matter, and the final hearings spread
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 9 of 19
Neutral Citation Number : 2023:DHC:2982
over months, the said clause missed the
attention of the Tribunal and hence the said
amount was not awarded to the Claimant. I
interpret such a mistake as omission falling
under Section 33(4) on the Tribunal's part and
hence deem it appropriate to award the same
to the Claimant.”
20. Clearly, the above reason given by the learned Arbitrator
amounts to a review of the Award and cannot be sustained as being in
exercise of power vested in the Arbitrator under Section 33 of the Act.
If the clause in the agreement was overlooked due to it not being
extracted in the written submissions, this may be a ground to review
an Award, however, as there is no power vested with an Arbitrator to
review his Arbitral Award, the order passed by the learned Arbitrator
shall be without jurisdiction.
21. Equally, the Original Award, on basis of calculations found that
the respondent was to pay a sum of Rs.32,02,553/- to the petitioner.
Interest was not awarded to the petitioner on the said amount.
However, in the Impugned Amended Arbitral Award, while correcting
the so-called arithmetical errors, the learned Arbitrator has proceeded
to Award interest in favour of the respondent on the amounts that are
now found payable by the petitioner to the respondent. No reasons for
the rate of interest or the period of interest have been given by the
learned Arbitrator in the modified Award.
22. The Supreme Court in Executive Engineer (R and B) and
Others v. Gokul Chandra Kanungo (Dead) Thr. his Lrs, 2022 SCC
OnLine SC 1336, on the issue of awarding of interest by an Arbitrator,
has held as under:-
“10. The provisions of Section 31(7)(a) of the
1996 Act fell for consideration before this
Court in many cases including in the cases of
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 10 of 19
Neutral Citation Number : 2023:DHC:2982
Hyder Consulting (UK) Limited (supra) and
Delhi Airport Metro Express Private Limited
v. Delhi Metro Rail Corporation5. A perusal
of clause (a) of subsection (7) of Section 31 of
the 1996 Act would reveal that, no doubt, a
discretion is vested in the arbitral tribunal to
include in the sum for which the award is
made interest, on the whole or any part of the
money, for the whole or any part of the period
between the date on which the cause of action
arose and the date on which the award is
made. However, it would reveal that the
section itself requires interest to be at such
rate as the arbitral tribunal deems reasonable.
When a discretion is vested to an arbitral
tribunal to award interest at a rate which it
deems reasonable, then a duty would be cast
upon the arbitral tribunal to give reasons as to
how it deems the rate of interest to be
reasonable.”
(Emphasis Supplied)
23. Therefore, it is evident that while awarding interest, the learned
Arbitrator has not only exceeded his jurisdiction in reviewing the
original Award, but has also failed to give any reasons for awarding
interest to the respondent, when the same was denied to the petitioner
in the Original Award, and for the rate and period of such interest.
24. The learned Arbitrator has further reduced the amount paid to
the respondent from Rs.3,31,56,341/- to Rs.2,25,91,275/-. While the
reasons for such adjustment may be correct, as is also evident from the
order dated 10.11.2017 passed by the learned Arbitrator on the
application filed under Section 33 of the Act by the respondent,
however, at the same time, such change would also amount to a
review of the Original Award, which cannot be done in exercise of
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 11 of 19
Neutral Citation Number : 2023:DHC:2982
power under Section 33 of the Act. The finding of the learned
Arbitrator on this issue is as under:-
“In so far as computation error of the
Tribunal is concerned pertaining to the
adjustment of the amount of Rs. 1,05,65,066/-
paid by Respondent to the Claimant is
concerned, I am of the view that the Bank
Guarantee adjustment and was a computation
error falling under Section 33(1)(a) and is
hence rectifiable under Section 33. Even the
wrongful deduction of the payment made by
the Respondent directly to the third party from
Claimants awarded amount is an error of
similar nature and hence shall fall within the
purview of Section 33 of the Act. Significantly
Claimant has demonstrated that the said sum
of Rs. 1,05,65,066/- was not a part of its claim.
Similarly the Respondent has been unable to
show any admission on record of this Tribunal
that the Claimant had admitted the receipt of
the said amount of Rs.1,05,65,066/- .”
(Emphasis supplied)
25. In the Statement of Claim, the respondent had pleaded as
under:-
“5. CLAIM A
TOWARDS UNPAID CERTIFIED
INVOICES
5.1 The Claimant upon executing the works
entrusted to it by the Respondent under
the Contract has raised 22 invoices that
have been duly certified by the
Respondent between March 20, 2012
and January 8, 2013 for a sum of
Rs.7,06,37,274/- (Rupees Seven Crores
Six Lakhs Thirty Seven Thousand Two
Hundred Seventy Four Only). The
Respondent however, failed to make the
payment under the aforementioned
invoices to the claimant even after
repeated requests made by the
Claimant. Therefore, considering the
obligations of the Respondent under the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 12 of 19
Neutral Citation Number : 2023:DHC:2982
Contract, the Respondent has unlawfully
withheld Rs.7,06,37,274/-, due and
payable to the Claimant by the
Respondent.
5.2. The Claimant states that the non-
payment by the Respondent is an act
which is manifestly perverse and
unlawful and against the terms of the
Contract and constitutes a material
breach on the part of the Respondent.
Therefore, the Claimant is entitled to
claim not only the amount due which
has not been paid by the Respondent
against the certified invoices as raised
by the Claimant for the work done under
the Contract but also for those invoices
which have not been certified.
th
5.3 The Respondent had on 27 Dec 2011,
advanced to the Claimant a sum of
Rs.1,60,00,000/- (Rupees One Lakh
Sixty Lakhs only) as mobilization
advance which was to be adjusted
proportionately against the Running
Bills. The Respondent had adjusted a
sum of Rs.34,08,725/- from the Running
Bills of the Claimant. The Respondent is
therefore, entitled to a further sum of
Rs.1,25,91,275/- to be deducted from the
invoices of the Claimant. Further the
Respondent had made an ad hoc
payment of Rs.1,00,00,000/- (One Crore
Only) towards the works executed
between August, 2012 and December,
2012 and a further sum of
Rs.1,05,65,066/- (One Crore Five Lakhs
Sixty Five Thousand Sixty Six Only)
paid by the Respondent to the suppliers
of the Claimant directly. The said
amounts have been included in the
certified invoices raised by the
Claimant. A copy of the Demand Drafts
issued by the Respondent directly to the
suppliers are attached herewith and
marked as Annexure P-18 .
5.4 After giving a due credit of
Rs.3,31,56,341/- (Rupees Three Crore
Thirty One Lakhs Fifty Six Thousand
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 13 of 19
Neutral Citation Number : 2023:DHC:2982
Three Hundred Forty
One Only) to the Respondent, the
Respondent is liable to pay the Claimant
an amount of Rs.3,74,80,933/- (Rupees
Three Crore Seventy Four Lakhs Eighty
Thousand Nine Hundred Thirty Three
Only) against certified invoices.”
26. The Arbitrator, in the original Award, held as under:
“The Claimant in its own pleading has
accepted that the Respondent has paid the
Claimant an adhoc amount of Rs.3,31,56,341/-
Thus the amount found due and payable to the
Claimant amounts to Rs.2,14,53,788/- along
with Rs. 5,00,000/- towards cost and expenses
of the present proceeding.
Thus the above mentioned amount i.e. Rs.
2,19,53,788/- needs to be adjusted against the
adhoc payment made by the Respondent.
After adjusting the amount awarded to the
Claimant, Rs.1,12,02,553 remains as extra
payment made by the Respondent.
Thus the Respondent is entitled to retain Rs.
80,00,000/- towards the encashment of
Advance Bank Guarantee.
The Claimant is thus directed to give the
Respondent Rs. 32,02,553/- out of the release
of Bank Guarantee from the Registrar General
Delhi High Court amounting to Rs.
80,00,000/- and retain the rest.”
27. The learned Sole Arbitrator has, therefore, considered the
amount in the hands of the respondent as Rs. 3,31,56,341/-. The same
included Rs. 1,05,65,066/-, which was paid by the petitioner to the
suppliers. In the Impugned Amended Arbitral Award, the learned
Arbitrator, as respondent hereinabove, excluded this amount, finding
that the same was not included in the claim of the respondent nor was
admitted to be received by it. This again amounts to a review of the
Award.
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 14 of 19
Neutral Citation Number : 2023:DHC:2982
28. In view of the above, the Impugned Amended Arbitral Award
cannot be sustained and is liable to be set aside.
29. This now brings me to the submission of the learned senior
counsel for the petitioner that once the Impugned Amended Arbitral
Award is set aside by this Court, the Original Award shall be operable.
In support, he places reliance on the judgment in Gyan Prakash Arya
(supra).
30. I am unable to agree with the submissions of the learned senior
counsel for the petitioner in the facts of the present case. In the present
case, the learned Arbitrator himself has recognized that there were
errors apparent on the face of the record in the Original Award. I also
find the errors to be apparent on the face of the record in the Original
Award. Merely because a relevant clause was not mentioned in the
Written Submissions filed by a party but otherwise pointed out to the
arbitrator, cannot be a sufficient reason for upholding an Award that is
passed in ignorance of such a clause of the agreement. It is not a
question of interpretation of the Award but a case of disregard of the
terms of the Award.
31. I also find, as is evident from the Statement of Claim
reproduced hereinabove, that the respondent had clearly stated that Rs.
1,05,65,066/- had been paid by the petitioner directly to the suppliers.
The learned Arbitrator even in the Original Award held that post the
amendment of the Agreement, the respondent is not entitled to any
payment towards the supply invoices, but is entitled to a margin of
10% of the supply bills raised by the respondent prior to the
amendment. The relevant finding in the Original Award is as under:-
“In so far as the supply invoices out of those
16 bills are concerned, in light of the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 15 of 19
Neutral Citation Number : 2023:DHC:2982
amendment dated 16.08.2012 signed by both
the parties, the supply invoices raised by the
Claimant cannot be paid to the Claimant as
the parties mutually agreed that the payments
for pending supply items will be made by the
Respondent directly.
However, it is a known fact that while entering
into the Contract the Claimant must have
calculated a margin in making the supply
payments itself. Thus the supply bills
preceding the 16.08.2012 amendment
containing the margin as contemplated by the
Claimant should be granted to the Claimant.
The Supply bills raised post amendment shall
not be considered by the Tribunal as post
amendment payments to third party were
agreed to be made by the Respondent and once
consent given by the Claimant, no margin or
payment qua the supply invoices can be raised
by the Claimant.
The Claimant has not pleaded in its case that
what percentage of the supply invoices was its
margin in the contract entered into between
the parties, however after making reasonable
estimate of the margin of the Claimant and in
the interest of justice the Tribunal grants
10% of the supply bills raised by the Claimant
before the amendment dated 16.08.2012 i.e.
Rs. 23,26,987/-. ”
32. If that be so, the amount of Rs. 1,05,65,066/- could not have
been adjusted as been received by the respondent. The respondent had
stated in the Statement of Claim that this amount was paid by the
petitioner directly to the suppliers. If the supply invoices are not to be
paid to the respondent, any amount paid to the suppliers against such
invoices also cannot be accounted for as an amount paid to the
respondent. This error was sought to be corrected by the learned
Arbitrator in the Impugned Amended Arbitral Award. The bank
guarantee amount had also been counted twice over while making the
adjustment of the amount in the Original Award. Though the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 16 of 19
Neutral Citation Number : 2023:DHC:2982
Impugned Amended Arbitral Award cannot be sustained as it is found
to be beyond the jurisdiction of the learned Arbitrator, at the same
time, the Original Award also cannot be sustained as it would cause
grave injustice to the respondent.
33. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
15 SCC 131, the Supreme clarified that though the jurisdiction of the
Court under Section 34 of the Act is highly limited, interference with
an Award will be justified if the Award gives a finding which is
perverse. A finding based on no evidence or in ignorance of vital
evidence would be perverse. It has been held as under:-
| “41. What is important to note is that a decision | |
|---|---|
| which is perverse, as understood in paras 31 and 32 | |
| of Associate Builders , while no longer being a ground | |
| for challenge under “public policy of India”, would | |
| certainly amount to a patent illegality appearing on the | |
| face of the award. Thus, a finding based on no | |
| evidence at all or an award which ignores vital | |
| evidence in arriving at its decision would be perverse | |
| and liable to be set aside on the ground of patent | |
| illegality. Additionally, a finding based on documents | |
| taken behind the back of the parties by the arbitrator | |
| would also qualify as a decision based on no evidence | |
| inasmuch as such decision is not based on evidence led | |
| by the parties, and therefore, would also have to be | |
| characterised as perverse. |
34. The Original Award passed by the learned Sole Arbitrator
suffers from such patent illegality. In the facts of this case, therefore,
it cannot be held that on setting aside of the Impugned Amended
Arbitral Award, the Original Award shall revive and bind the parties.
35. In Gyan Prakash Arya (supra), the original Award was based
on the Statement of Claim filed by the respondent therein itself. After
passing of the original Award, the respondent therein filed an
application under Section 33 of the Act, which, in fact, sought to
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 17 of 19
Neutral Citation Number : 2023:DHC:2982
amend its Statement of Claim. This was allowed by the learned
Arbitrator. It was in those circumstances that the Supreme Court held
as under:-
| “13. The original award was passed | |
|---|---|
| considering the claim made by the claimant as | |
| per its original claim and as per the statement | |
| of the claim made and therefore subsequently | |
| allowing the application under Section 33 of | |
| the 1996 Act to modify the original award in | |
| exercise of powers under Section 33 of the | |
| 1996 Act is not sustainable. Only in a case of | |
| arithmetical and/or clerical error, the award | |
| can be modified and such errors only can be | |
| corrected. In the present case, it cannot be | |
| said that there was any arithmetical and/or | |
| clerical error in the original award passed by | |
| the learned arbitrator. What was claimed by | |
| the original claimant in the statement of claim | |
| was awarded. Therefore, the order passed by | |
| the learned arbitrator on an application filed | |
| under Section 33 of the 1996 Act and | |
| thereafter modifying the original award | |
| cannot be sustained. The order passed by the | |
| learned arbitrator in the application under | |
| Section 33 of the 1996 Act is beyond the scope | |
| and ambit of Section 33 of the 1996 Act. | |
| Therefore, both, the City Civil Court as well as | |
| the High Court have committed a grave error | |
| in dismissing the arbitration suit/appeal under | |
| Sections 34 and 37 of the 1996 Act | |
| respectively. The modified award passed by | |
| the learned arbitrator allowing the application | |
| under Section 33 of the 1996 Act cannot be | |
| sustained and the same deserves to be quashed | |
| and set aside. | |
| 14. In view of the above and for the reasons | |
| stated above, the present appeal is allowed. | |
| The impugned judgment and orders passed by | |
| the High Court in an appeal under Section 37 | |
| of the 1996 Act and the City Civil Court in | |
| arbitration suit under Section 34 of the 1996 | |
| Act and the order passed by the learned | |
| arbitrator dated 14-1-2011 modifying the | |
| original award dated 4-12-2010 are hereby | |
| quashed and set aside. Consequently, the |
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 18 of 19
Neutral Citation Number : 2023:DHC:2982
| original award passed by the learned | |
|---|---|
| arbitrator dated 4-12-2010 stands restored. | |
| However, in the facts and circumstances of the | |
| case, there shall be no order as to costs.” |
the record. The same, therefore, cannot be sustained and has to be
equally set aside.
37. Accordingly, the Original Award dated 25.08.2017 as also the
Impugned Amended Arbitral Award dated 10.11.2017 are set aside.
The parties are left to take their own remedies in accordance with law.
38. The petitions are disposed of in the above terms. There shall be
no order as to costs.
NAVIN CHAWLA, J
APRIL 26, 2023 /rv
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:04.05.2023
11:25:00
O.M.P. (COMM) 451/2017 & 100/2018 Page 19 of 19