Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
PATNA REGIONAL DEVELOPMENTAUTHORITY & ORS.
Vs.
RESPONDENT:
M/S.RASHTRIYA PARIYOJANA NIRMANNIGAM & ORS.
DATE OF JUDGMENT: 07/05/1996
BENCH:
VERMA, JAGDISH SARAN (J)
BENCH:
VERMA, JAGDISH SARAN (J)
MANOHAR SUJATA V. (J)
CITATION:
1996 AIR 2074 1996 SCC (4) 529
JT 1996 (6) 113 1996 SCALE (4)488
ACT:
HEADNOTE:
JUDGMENT:
WITH
CIVlL APPEAL NO 7830 OF 1996
(Arising out Or S.L.P. (C) No.4434 of 1996)
M/s.Walia Builders
V.
Rashtriya Pariyojana Nirman Nigam
& Ors.
O R D E R
Leave granted.
The Patna Regional Development Authority (hereinafter
referred to as the ’appellants’) invited tenders tor the
construction of a high rise building ’Maurya Towers’ in the
town of Patna. Of the three bids which were submitted, the
bid of the first respondent, namely, Rashtriya Pariyojana
Nirman Nigam was found to be the lowest. The second lowest
bid was of respondent No.4, M/s.Walia Builders. Although the
tender submitted by the first respondent was the lowest, the
Tender Committee took into account the fact that the first
respondent had been black-listed for a period of five years
by the Water Resources Department, Government of Bihar under
a black-listing order dated 26.9.1991, and decided not to
award the contract to the first respondent. Instead, it
awarded the contract to the fourth respondent. The fourth
respondent, after negotiation, agreed to do the work at the
rates offered by the first respondent.
This decision of the appellants was challenged by the
first respondent by filing a writ petition being C.W.J.C.
No.3964 of 1995 which was filed on 13.6.1995 in the Patna
High Court. The first respondent also filed another writ
petition bearing C.W.J.C. No.4064 of 1995 challenging the
black-listing order of 26.9.1991. Writ Petition C.W.J.C.
No.4064 of 1995 was rejected by a learned Single Judge of
the Patna High Court by his order dated 18.9.1995 on the
ground of delay, since the order of black-listing was
challenged more than four years after it was made. The first
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
respondent filed an appeal to a Division Bench of the Patna
High Court being L.P.A. No.1473 of 1995.
Writ Petition C.W.J.C. No.3964 of 1995 filed by the
first respondent against the decision not to award the
contract to it, was allowed by a learned Single Judge of the
Patna High Court. He held, inter alia, that before the
appellants decided not to award the contract to the first
respondent on the ground of its being black-listed, no show-
cause notice was issued by the appellants to the first
respondent. Hence their decision was against the principles
of natural justice and was bad in law. Two Letters Patent
Appeals were filed from this judgment and order, being
L.P.A. No.912 of 1995 filed by the appellants and L.P.A.
No.1078 of 1995 filed by the fourth respondent, M/s.Walia
Builders.
These two Letters Patent Appeals along with L.P.A.
No.1473 of l9g5 were heard together by the Division Bench of
the Patna High Court. It has held that the order of black-
listing must be set aside because the order was not
communicated to the first respondent. It has further held
that since the order of black-listing has been set aside,
the question of award of tender must be re-examined by the
first respondent.
In our view the impugned decision of the Division Bench
of the Patna High Court cannot be sustained. The decision of
26.6.1991 taken by the water Resources Department to black-
list the first respondent for five years was communicated by
a letter of the same date to the first respondent. The High
Court has, however, held that the letter of 26.9.1991
addresses by the Water Resources Department, Government of
Bihar to the first respondent was not served on the first
respondent. This conclusion is arrived at by the High Court
only on the ground that the allegation of non-service of the
letter, made by the first respondent in their pleading is
not denied by the appellants in their pleading. But as the
High Court’s judgment itself records, the appellants had, in
fact, stated in their pleading that the letter of 26.9.1991
was communicated to the first respondent. The High Court,
however, has proceeded on the basis that there was non-
traverse of the statement made by the first respondent that
the letter of 26.9.1996 was not received by the first
respondent. The appellants had clearly pleaded that the
order of 26.9.1991 was communicated to the first respondent.
This cannot be construed as non-traverse. In any case, the
proviso to Order VIII Rule 5(1) of the Civil Procedure Code
states that the court may, in its discretion, require any
fact so admitted to be proved otherwise than by such ad
issue. Looking to the nature of the pleadings the High Court
should have asked that the receipt or nonreceipt of the
order of 26.9.1991 be proved otherwise than by the alleged
admission. It should not have set aside the order of black-
listing after a lapse of four years only on the ground of
alleged non-traverse.
The decision of the Tender Committee taken on 30.5.1995
not to award the contract to the first respondent has been
set aside by the Division Bench of the High Court only on
the ground that the order of black-listing is not a valid
order. Hence the decision of the Tender Committee requires
to be re-considered. The very basis for this finding is
defective. In considering whether the decision of the Tender
Committee to award the tender to the fourth respondent is
arbitrary or unreasonable, one will have to examine the
existing circumstances at the time when the decision was
taken. The Tender Committee rightly took into account the
fact that the Water Resources Department of the State of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
Bihar had black-listed the first respondent for a period of
five years. This was a relevant consideration in deciding
whether a tender should be awarded to the first respondent.
There was no challenge to the black-listing order at the
relevant time. The performance record of the first
respondent while executing previous contracts was relevant
in deciding whether to award the contract to the first
respondent or note. The impugned decision thus took into
account relevent factors. It cannot be considered as
arbitrary or unreasonable.
The first respondent contended that the order of black
-listing was not in force because even after 1991, it had
been awarded two contracts. The first contract referred to
in this connection by the first respondent is a contract
for the construction of the Lok Nayak Bhawan given to it by
the Patna Zilla Parishad. This contract was awarded to the
first respondent before 27.2.1991 and prior to the order of
black-listing. The second contract relied upon is by the
Chief Engineer, Rural Engineering Organization of Chotta
Nagpur and Santhal Pargana Wing. This contract relates to
the Bihar Plato Development Project and was awarded to the
first respondent in 1994. On enquiry from the appellants,
the Chief Engineer of the Rural Engineering Organization
informed the appellants that when the contract was awarded
to the first respondent, the fact of its having been black-
listed in the State of Bihar was not brought to his notice.
It was because of the suppression of this information that
the work was allotted to the first respondent. This
contention of the first respondent, therefore, has no force.
The first respondent also contends that the
disqualification imposed by the State Government will not
automatically disqualify the first respondent qua the
appellants, an autonomous body. The appellants, however, can
legitimately take into account the fact that The first
respondent has been blacklisted by the Water Resources
Department, State of Bihar, in deciding whether to give work
to the first respondent or not.
There was also no question of issuing of any show-cause
notice to the first respondent before the Tender Committee
of the appellants took the decision on 30.5.1995. The
appellants were merely taking note of an existing order.
There was no question of their sitting in judgment over the
black-listing order. Nor was this a case of the appellants
themselves issuing an order black-listing the first
respondent.
The appeals are, therefore, allowed. The impugned
judgment and order of the Patna High Court is set aside and
Writ Petitions bearing C.W.J.C. Nos.3964 and 4064 of 1995
filed in the Patna High Court are dismissed with costs.