Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 5210 of 2007
PETITIONER:
ONGC Ltd.
RESPONDENT:
Garware Shipping Corpn. Ltd.
DATE OF JUDGMENT: 14/11/2007
BENCH:
Dr. ARIJIT PASAYAT & S.H. KAPADIA
JUDGMENT:
J U D G M E N T
(Arising out of SLP (C) No.15036 of 2005)
Dr. ARIJIT PASAYAT, J.
1. Leave granted.
2. Challenge in this appeal is to the judgment rendered by a
Division Bench of the Bombay High Court dealing with an
appeal questioning the correctness of the order passed by a
learned Single Judge who dismissed the appellant\022s appeal
under Section 34 of the Arbitration and Conciliation Act, 1996
(in short the \021Act\022) questioning the Arbitrator\022s award.
3. The controversy lies within a very narrow compass.
4. The factual background is almost undisputed and is
essentially as follows:
The appellant required off shore vessels (in short \021OSVs\022)
inter-alia, for supplying material from its onshore bases to its
offshore installations. After initially meeting its requirements
by chartering foreign OSVs, the appellant decided to develop a
fleet of Indian Flag vessels. Various Indian companies
including the respondent and the Shipping Corporation of
India (in short \021SCI\022) acquired OSVs, with a view to chartering
them to the appellant. The respondent acquired five vessels-
(named Garware I to Garware V) which were handed over to
the appellant in the months of November and December, 1983
and January and March, 1984.
The dispute pertains to the cost of repairs and
maintenance of the respondent\022s OSVs for the eleventh to the
sixteenth year of their operation. Even though there is no
dispute regarding the first two terms of five years each,
reference to the manner in which the rates for the same were
arrived at is necessary. A working group under the Director
General of Shipping was constituted by the Ministry of
Petroleum to determine the floor day rate in respect of the
vessels keeping two objects in mind, i.e. (a) long term
availability of the OSV\022s for the appellant and (b) economic
viability to ensure the respondent\022s survival in the business.
The report was submitted by the working group on 8.3.1984
suggesting the day rate which comprised of two components,
i.e. (a) capital recovery factor and (b) operating expenses.
Contracts were accordingly entered into for the first five year
period beginning from 1983-84. The Government of India by
an order dated 18.8.1984 approved the report in certain
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
respects only. There is no dispute between the parties
regarding the payments of operating costs for the first five
years. The charter was extended by another five years. A
committee presided over by Dr. A.N.Saxena was formed to
review the operating costs payable for the extended term. The
Government approved the report of the Committee on
5.8.1993. There is no dispute between the parties in respect of
the payments regarding the second five year period also.
5. The present dispute relates to the period beyond ten
years so far as relates to the basis for computing the rates for
repairs and maintenance. By an order dated 29.4.1993 the
charter was extended by a further six years. By an order dated
16.3.1995 and as modified by an order dated 14.9.1995, a
committee also presided over by Dr. A.N. Saxena was formed
to recommend a suitable formula for the charter rate for the
further extended period.
6. The committee submitted its report on 14.9.1997. This
committee made recommendations inter-alia in respect of
repair and maintenance expenses. The reference to arbitration
was confined only to the payment of these repairs and
maintenance expenses.
7. The Government of India by a letter dated 15.6.1998
accepted the recommendations of the second Dr. A.N. Saxena
Committee only partially. Representations were thereafter
made by the Indian Shipping Companies including the
respondent for reconsideration of the recommendations.
Pursuant thereto, the Government of India appointed a High
Level Working Group presided over by Mr. Naresh Narad for
considering the outstanding pending issues. The following
recommendations of the High Power Committee are relevant:
\023Pending Issues.
1. Determination of year a) 1 to 5 years as per
from which R & M payments already
expenses are to be made. Settled cases
actualized. Not to be reopened.
b) 6 to 10 years as per
norms fixed by Dr.
Saxena Committee
of 1995-77.
c) 11 and 12 years to
actualized on the basis
of S.C.Is\022 OSVs as
recommended by
Dr. Saxena Committee
of 1995-77.\024
8. Disputes and differences arose between the appellant
and inter-alia the respondent and others regarding the method
to the adopted for calculating rates payable with reference to
the eleventh to the sixteenth years. The respondent, therefore,
filed Writ Petition No.2788 of 2001 for various reliefs.
9. By an order dated 7.12.2001 a Division Bench of the
High Court recorded that the Writ Petition involved certain
contractual disputes and that both the parties had agreed to
refer the disputes raised in the Writ Petition to the sole
arbitration of Mr. Justice M.L.Pendse (a former Judge of the
Bombay High Court and the former Chief Justice of the
Karnataka High Court). The order which is a short one, reads
as follows:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
\023This writ petition involves certain contractual
disputes relating to repairs and maintenance
expenses etc. contract between the parties
contain an arbitration clause. Both the
parties agree to refer the disputes raised in
the writ petition to sole arbitration of Justice
M.L. Pendse (Retd.). Parties further agree
that in case Justice Pendse is not in a
position to take up the arbitration, Justice
D.R. Rege (Retd.) shall be the arbitrator for
the disputes between the parties. Arbitrator
is requested to dispose of the arbitration as
expeditiously as possible.
Petition is disposed of.\024
10. The learned arbitrator noted the respondent\022s
submission that while calculating the payments due for the
11th to 16th years of the operation of the OSVs of the
respondent, the appellant has overlooked the important fact
that the OSVs of the respondent were taken on charter one
year prior to the appellant obtaining the OSVs of the SCI. The
respondent, therefore, contended that it was not correct that
the corresponding years of SCI should be taken into account
while determining amounts payable to the respondent. The
learned arbitrator rejected the appellant\022s contention. He held
that the committee nowhere recommended that irrespective of
the period of induction, the years should be calculated of that
of the SCI. He held that the respondent had not questioned
the recommendations made by the High Level Working Group
Report and the second Saxena Committee Report but merely
contended that the mode of implementation thereof was
incorrect. The arbitrator further observed and accepted that it
was not open for him to go behind the report and the only
area of enquiry is whether or not the report was correctly
implemented. He came to the conclusion that on a close
scrutiny of the reports, it was clear that neither of the
committees examined whether the entitlement of each OSV is
to be determined with reference to the years of actual user or
only with reference to the calendar years. He also came to the
conclusion that for the computation of repairs and
maintenance expenses, it was necessary to take into
consideration the years of operation and not the calendar
years. It was held that the 12th year of operation of SCI\022s
OSVs should be equated with the 13th year of operation of the
OSVs of the respondent and so on. He also held that the
interpretation suggested by the appellant would lead to great
injustice. For instance, the OSV of the respondent would
complete 11 years of operation while the OSVs of the SCI
would have operated only for 10 years.
11. Appellant questioned correctness of learned Arbitrator\022s
conclusion by filing an appeal under Section 34 of the Act.
Learned Single Judge dismissed the appeal holding that the
conclusion was rational. An appeal filed was also dismissed.
12. According to the Division Bench, the learned arbitrator
has considered and construed the reports while arriving at his
conclusions. The entire dispute in the Writ Petition and before
the learned arbitrator centered around this issue. The basis of
the calculation adopted by the learned arbitrator was, not only
logical but just and fair. The provisions of the said reports are
not such that they required no interpretation and were merely
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
to be applied without anything more. They called for a proper
interpretation and construction before being applied to the
facts of the case. The learned arbitrator did so.
13. The learned Single Judge held that undoubtedly there
was no reference so far as the period of 13 to 16 years are
concerned to the learned Arbitrator. But the prayers and the
writ petitions clearly indicated that even for that period an
issue was raised.
14. The Division Bench was of the view that even if the mode
of calculation as applied by the arbitrator is not very
appropriate in its effect, that could not be a ground for
exercise of power under Section 34.
15. It noted that the reference in fact did not include the 13th
to the 16th year to inspect that the arbitrator thought it
improper to open the same. The High Court was of the view
that a narrow technical reading of the Award cannot be made.
16. In support of the appeal, learned counsel for the
appellant submitted that both learned Single Judge and the
Division Bench failed to notice that the Award made by the
Arbitrator was beyond the reference made. The arbitrator\022s
view that the corresponding year could be a more appropriate
factor is without foundation. The Bench mark of SCI in a
particular year could not be departed from. There was no
scope for shifting of figures. There is no rule of universal
application that the cost of maintenance would be more when
the vehicle becomes older. The normative figure for third
period remained constant. The order of operation is the
operating order and the financial order is defining. Though in
the Writ Petition there was challenge to 13 to 16 years, a bare
reading of the writ petition shows that it did not relate to the
said period.
17. In response, learned counsel for the respondent
submitted that two views are possible and, therefore, High
Court\022s view should not have interfered. Arbitrator had
accepted one view which is possible. No one says that it is de
hors the Committee\022s report. It is a case where no interference
is called for under Article 136 of the Constitution of India,
1950 (in short the \021Constitution\022) as substantive justice had
been done, even though the order may be wrong on some
parts.
18. Some of relevant parts of the Report of HLWG need to be
noted:
\023This High Level Working Group
therefore, concludes that R&M expenses are
to be actualized with effect from the 11th year
of operation.\024
It was further noted as follows:
\023This Committee was seized of the anomaly of
lower rates being paid to those Owners who
exercised greater management effectiveness
by ensuring lower capital costs, lower interest
rates and lower debt equity ratios.
19. The High Level Working Group, therefore, felt that
though it is now not possible to correct any anomalies that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
may have crept in during the first twelve years, at least for the
last term of four years the formula should reflect, as far as
practicable, the principle of equal pay for equal work.
20. It is to be noted that the anomalies referred to in the
subsequent paragraphs relate to the anomaly of lower rates
being paid to owners to exercise greater management
effectiveness by ensuring lower capital because of lower
interest rate and lower rate equality ratio.
21. The recommendations of the HLWG are as follows:
1.
Determination of year
from which R&M
expenses are to
be actualized
a. 1st to 5th year as per
payments already made.
Settled cases not to be
reopened.
b. 6th to 10th year as
per norms fixed by the Dr.
Saxena Committee of
1995-97.
c. 11th and 12th years
to be actualised on the
basis of SCI\022s OSVs as
recommended by the Dr.
Saxena Committee of
1995-97.
5.
Ceiling rates for\023A\024 type
Vessels only pertaining
to the period beyond 12
years of operation
a. From 1st to 5th year
ceiling rates as already
paid by ONGC.
b. From 6th to 1Oth year
floor rates to be paid by
ONGC.
c. For the 11th and 12th
years ceiling rates to be
paid by ONGC
6. Compensation in lieu
of CRF
a. The Operating
Expenses (including Crew
Salary & Wages covering
agreements between INSA
and MUI/ NUSI) as
determined on the last day
of the 12th year of
operation for each vessel,
(as per recommendations
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
of the Dr. Saxena
Committee and further
modified by this Working
Group) to be fixed and
made applicable for the
next four year i.e. from the
13th to the 16th year.
22. Operating costs are to be calculated on the basis of
actual expenditure incurred by SCI in operating SCI\022s OSVs
for full (first) one year period.
23. The committee observed that the actual expenses of SCI
have not followed any uniform pattern. The scale to be
suggested by the committee needed to be based on some
normative amount for a base year over which an escalation of
9.5% per annum may be considered for a block of five years
and for subsequent block of five year the base may be changed
in the same pattern as that of victualling cost. The committee
observed that the total cost of repair and maintenance for the
block of five years, that is, 1988-89 to 1992-93 of SCI\022s OSVs
is Rs.106.482 lacs per OSV as against the recommended
amount of Rs.97.618 lacs given in the JS & FA committee
report. The committee considered that the SCI\022s audited
statement of R&M expenses may be considered as appropriate
amount for reimbursement to Shipowners. The difference
between SCI\022s audited R&M expenses and the normative
amount was to be reimbursed to the Shipowners on receipt of
SCI\022s audit statement from time to time in proportion to the
BHP of the respective OSVs.
24. As the concept of reimbursement is the measure fixed,
the year of operation can vary is an irrelevant factor. The
repair and maintenance expenses have also been dealt by the
Committee.
25. In accordance with the deliberation of the Committee on
this at para 3.5.5, the committee recommended the normative
R&M expenses of OSV of 5400 BHP for the year 1988-89 to
1993-94 to be same as given in the JS&FA Committee report.
The R&M expenses for the subsequent years were
recommended at the rate of 9.5% escalation per annum on the
expense of the year 1993-94 upto 1998-99 and the amount for
of subsequent years @ 9.5% escalation per annum. The
difference between the recommended normative amount given
and the actual R&M expense of SCI\022s OSVs of 5400 BHP
(Audited statements) were to be reimbursed on year to year
basis after receipt of the audited statement from SCI
additional reimbursement of corresponding overhead expenses
in the ratio of 15:85 of the differential amount will also be
made. The differential amounts for other OSVs were
recommended to be calculated pro rata basis of the BHP of the
respective OSVs w.r.t. above differential amount for OSVs of
5400 BHP.
26. Though there was some controversy as to whether the
year referred to is the financial year as reimbursement was on
year to year basis after receipt of the auditor\022s statement from
SCI the norms obviously relate to financial year.
27. A few factual aspects need to be noted. So far as Essar is
concerned, the year is same as SCI. In case of Bann, there was
one time settlement and it is only JESCO which challenged
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
the report. SCI\022s first year of operation was 1984-85. The
figures for that year provide some material for rationalization.
It is to be noted that stress is on re-imbursement. Thus the
measure is fixed and, therefore, year of operation is
immaterial. It needs no reiteration that claim was for 11th and
12th years and the award also covered from 13th to 16th year. It
is also to be noted that the HLWG referred to certain
anomalies. But they related to the previous years. The \023Bench
Mark\024 is the figure of SCI of particular year. So when entry to
business was made is irrelevant.
28. There is no proposition that the courts could be slow to
interfere with the arbitrator\022s Award, even if the conclusions
are perverse, and even when the very basis of the Arbitrator\022s
award is wrong. In any case this is a case where interference is
warranted and we set aside the norms prescribed by the
Arbitrator as upheld by the learned Single Judge and the
Division Bench.
29. The appeal is allowed to the aforesaid extent with no
order as to costs.