Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
THE STATE OF BIHAR
Vs.
RESPONDENT:
M/s. KARAM CHAND THAPAR & BROTHERS LTD.
DATE OF JUDGMENT:
07/04/1961
BENCH:
AIYYAR, T.L. VENKATARAMA
BENCH:
AIYYAR, T.L. VENKATARAMA
DAS, S.K.
KAPUR, J.L.
HIDAYATULLAH, M.
SHAH, J.C.
CITATION:
1962 AIR 110 1962 SCR (1) 827
CITATOR INFO :
F 1962 SC 113 (11)
R 1967 SC 203 (6)
RF 1971 SC1070 (17)
F 1977 SC2149 (8)
R 1988 SC2149 (13)
ACT:
Stamp--Award--Arbitrator sending copies of the award to
parties and to the court, duly signed--Validation of
unstamped award--Decree passed thereon--Validity--Indian
Stamp Act, 1899 (2 of 1899), s. 35.
Arbitration--Agreement to refer to arbitration--Execution on
behalf of Governor by Person specifically authorized--
Requirements of authorization--Government of India Act, 1935
(25 & 20 Geo. 5 Ch, 42), s. 175(3).
HEADNOTE:
A dispute between the respondent company and the Government
of Bihar over the bills for the amount payable to tile
company in respect of the construction works carried out by
it for the Government was referred to arbitration. The
agreement to refer to arbitration was executed on behalf of
the Governor by L, an executive engineer, who had been
specifically authorised to do so by a Secretary to the
Government. The arbitrator made his award and sent copies
thereof to the parties. The respondent applied to the Court
under the provisions of the Arbitration Act, 1940, for a
decree in terms of the award. The State filed objections
thereto and the matter was registered as a suit. While the
suit was pending the arbitrator sent to the court a copy of
the award duly signed by him for being filed as provided in
the Act, and on the receipt thereof the respondent bad it
validated on payment of the requisite stamp duty under s. 35
of the Indian Stamp Act, 1899. The appellant, the State of
Bihar, contended that no decree could be passed on the basis
of the award on the grounds (1) that the agreement for
reference to arbitration did not comply with the
requirements of s. 175(3) of the Government of India Act,
1935, inasmuch as it was not signed by the person authorised
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
to do so under the notification issued by the Government of
Bihar on April 1, 1937, in exercise of the powers conferred
by s. 175(3), and (2) that the instrument before the court
was a certified copy and that under S. 35 of the Indian
Stamp Act, 1899, a copy Could not be validated or acted
upon.
Held, that S. 175(3) of the Government of India Act, 1935,
does not prescribe any particular mode in which authority
must be conferred and that where authorisation is conferred
ad hoc on any person, the requirements of the section must
be held to be satisfied.
828
Held, further, that the award sent by the arbitrator to the
court was the original and not a copy of the award and by
applying the provisions of s. 35 of the Indian Stamp Act,
1899, it was effectively validated.
The Rajah of Bobbili v. Inuganti China Sitaramasami Garu
(1899) L.R. 26 I.A. 262, referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 209 of 1959.
Appeal from the judgment and order dated October 5, 1956, of
the Patna High Court in Miscellaneous Appeal No. 367 of
1953.
L. K. Jha and R. C. Prasad, for the Appellant.
M. C. Setalvad, Attorney-General for India, N. De and P.
K. Mukherjee, for the respondents.
1961. April 7. The Judgment of the Court was delivered by
VENKATARAMA AIYAR, J.-This is an appeal against the Judgment
of the High Court of Patna in an appeal under the
Arbitration Act, 1940. The appellant is the State of Bihar,
and the respondents are a company registered under the
Indian Companies Act, doing business as building
contractors. They entered into three contracts for the
construction of aerodrome, hangarettes, buildings, stores
and other works at Ranchi, the first of them being contract
No. 21 of 1942 dated November 5, 1942, and the other two
being contracts Nos. 6 and 8 dated April 5, 1943. After the
above works were completed, disputes arose between the
parties over the bills and eventually by an agreement dated
February 6, 1948, they were referred to the arbitration of
one Col. A. W. S. Smith. The arbitrator made his award on
June 4, 1948, and sent a copy thereof to the parties. The
respondents thereupon filed a petition under ss. 17 and 20
of the Indian Arbitration Act, 1940, for a decree in terms
of the award. The appellant filed objections thereto, and
the petition was then registered as Title Suit No. 53 of
1951. While this suit was pending, the arbitrator who had
meantime left for Hong Kong sent to the court of the
Additional Subordinate Judge of
829
Ranchi before whom the suit was pending a copy of the award
duly signed by him, for being filed as provided in the Act.
Notices were issued by the court under s. 14(2) of the Act,
and, in answer thereto, the appellant filed an application
to set aside the award on various grounds. To this, the
respondents filed their reply statement. In view of this
application, the respondents did not press their petition
tinder ss. 17 and 20 of the Arbitration Act, which was in
consequence dismissed, and the proceedings which commenced
with the receipt of the award from the arbitrator were
continued as Title Suit No. 53 of 1951. After an elaborate
trial the Additional Subordinate Judge, Ranchi, passed a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
decree in terms of the award except as to a part which he
held to be in excess of the claim. The appellant took the
matter in appeal to the High Court of Patna which confirmed
the decree of the Subordinate Judge but granted a certifi-
cate under Arts. 132 and 133(1) of the Constitution,
and hence this appeal.
Though the controversy between the parties-ranged in the
courts below over a wide area,, before us, it was restricted
to two questions-whether there was a valid agreement of
reference to arbitration binding on the Government and
whether a decree could be passed on the unstamped copy of
the award filed in the court. On the first question, the
appellant contends that the agreement for reference to
arbitration does not comply with the requirements of s.
175(3) of the Government of India Act, 1935, which was the
Constitutional provision in force at the relevant date, and
it is therefore void, that the award passed in proceedings
founded thereon is a nullity and that no decree should be
passed in terms thereof. Section 175(3) is as follows:-
"Subject to the provisions of this Act. with,
respect to the Federal Railway authority, all
contracts made in the exercise of the
executive authority of the Federation or of a
province shall be expressed to be made by the
Governor-General, or by the Governor of the
Province, as the case may be, and all such
contracts and all assurances of property
830
made in the exercise of that authority shall be executed on
behalf of the Governor-General or Governor by such persons
and in such manner as he may direct or authorise."
Under this section, a contract entered into by the Governor
of a Province must satisfy three conditions. It must be
expressed to be made by the Governor; it must be executed;
and the execution should be by such persons and in such
manner as the Governor might direct or authorise. We have
now to examine whether the agreement to refer to arbitration
dated February 6, 1948, satisfies the above conditions. It
expressed to be made between the Governor of Bihar and the
respondents. It is also a formal document executed by one
Y. K. Lall, Executive, Engineer, Ranchi Division, and by the
respondents. So the only point that remains for
consideration is whether the Executive Engineer was a person
who was directed or authorised by the Governor to execute
the agreement in question. The appellant contends that he
as not, and relies in support of his contention on a
notification dated April 1, 1937, issued by the Government
of Bihar. That notification, in so far as it is material,
is as follows:
"In exercise of the powers conferred by sub-section (3) of
section 175 of the Government of India
Act, 1935, the Governor of Bihar is pleased, in supersession
of all existing orders, to direct that the undermentioned
classes of deeds, contracts and other instrument may be
executed on his behalf as follows:-
A.In the case of the Public Works Department (subject to
any limit fixed by. Departmental orders)
2. All instruments relating to the execution of works of
all kinds connected with buildings, bridges, roads, canals,
tanks, reservoirs, docks and harbours and embankments, and
also instrumets relating
By Secretaries to Government, Chief Engineers, Superin-
tending Engineers, Divisional Officers, Sub-divisional Offi-
cers, Assistant or Assistant Executive
831
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
to the construction of water Engineers, and the
works, sewage works, the n Electric Inspector.
erection of machinery, and
the working of coal mines.
........................... ...................
12. All deeds and in- By Secretaries and
struments relating to any’ Joint Secretaries to
matters other than those Government".
specified in heads 1 to 11.
There was a discussion in the courts below as to whether the
present agreement fell within item 2 or item 12. If the
agreement could be held to be an instrument relating to the
execution of works, it would fall within item 2, and the
Executive Engineer would be a person authorised under this
notification to enter into this contract, but if it does not
fall within that item, it must fall within entry 12, in
which case he would not be competent to execute the
agreement. Both the courts below have held that the
agreement to refer to arbitration was not one relating to
execution of works as that had been completed and the
dispute related only to payment of the bills, and that
further the essential feature of an arbitration agreement
was the constitution of a private Tribunal and it could not
therefore be brought within item 2 and that accordingly it
fell within item 12. But the learned Judges of the High
Court were also of the opinion that Y. K Lall, the Executive
Engineer had in fact been specifically authorised to execute
the arbitration agreement, and that that was sufficient for
the purpose of s. 175(3). The appellant impugns the
correctness of this conclusion and contends that it is not
warranted by the record. It becomes, therefore, necessary
to refer in some detail to the correspondence bearing on
this point. On July 26, 1947, Mr. Murrel, Secretary to the
Government, wrote to Col. Smith as follows:
"I am directed to say that the Government of Bihar propose
to appoint you as Arbitrator for the settlement of a claim
put forth by Messrs. Karam Chand Thapar and Brothers
Limited in connection with the construction of the Hinoo
Aerodrome at Ranchi-Job 108 If You agree to undertake the
832
work....... the necessary forms of acceptance
of appointment of Arbitrator etc. may please
be for warded to this Department for
completion by the Government of Bihar and, by
the Contractor."
To this, Col. Smith sent a reply agreeing to act as
arbitrator. In that letter he also suggested that the
contract between the parties might be suitably amended so as
to permit arbitration. This is significant, because under
cl. 23 of the contract, all disputes between the parties had
to be referred to the Superintending Engineer whose decision
was to be final, and if that had been amended as suggested,
the arbitration clause would have become part of the
original contract and there would have been no occasion for
the present contention. Referring to the above suggestion
for amending the agreement, the Secretary, Mr. Murrel, wrote
on September 5, 1947, to Col. Smith that the opinion of the
Legal Remembrancer would have to be got. On January 19,
1948, Col. Smith wrote to the Secretary that he was ready
to take up his duties as arbitrator and again desired that
the contract should be amended so as to provide for
arbitration. On January 27, 1948, the Secretary to the
Government informed Col. Smith that opinion had been
received from the Legal Remembrancer that an agreement for
arbitration should be executed in accordance with the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
provisions of the Arbitration Act and that a "draft
agreement (copy enclosed) has been drawn up accordingly and
steps are being taken to execute it, as quickly as possible"
On the same date, the Executive Engineer wrote to the
respondents as follows:-
"It has since been decided by Government to
determine your claims in connection with the
above through arbitration conducted in
accordance with the provisions of the
Arbitration Act 1 of 1940. You are therefore
requested to please attend the Divisional
Office immediately to execute necessary
agreement for the purpose."
Pursuant to this letter, the respondents joined in the
execution of the agreement dated February 6, 1948, along
with the Executive Engineer for referring the
833
dispute to arbitration. On February 25, 1948 the Secretary
informed the arbitrator that the draft agreement had been
slightly modified in consultation with the Government
Pleader, and he also wrote to the Executive Engineer that
certain formal corrections should be made in the agreement
and signed by both the parties. And that was done.
Having carefully gone through the correspondence, we agree
with the learned Judges of the High Court that the Executive
Engineer had been authorised by the Governor acting through
his Secretary to execute the agreement for reference to
arbitration. It will be seen that it was the Secretary who
from the very inception took the leading part in arranging
for arbitration. He was throughout speaking in the name of
and on behalf of the Government and he did so "as directed".
The subject-matter of the arbitration was a claim which
concerned the Government. The proposal at the earlier
stages to amend cl. 23 of the original contract so as to
include an arbitration shows that the intention of the
parties was to treat the agreement for arbitration as part
and parcel of that contract. Even after the agreement was
executed, the Secretary made corrections and modifications
in the agreement on the basis that it was the Government
that was a party thereto. The conclusion from all this is,
in our judgment, irresistible that Y. K. Lall, the Executive
Engineer had been authorised to execute the agreement dated
February 6, 1948.
It was suggested that the Secretary was possibly labouring
under a mistaken notion that the agreement to refer to
arbitration was covered by item 2 and acting under that
misconception he directed Y. K. Lall to execute the
agreement. Even if that were so, that would not make any
difference in the position, because the Secretary
undoubtedly did intend that Y. K. Lall should execute the
agreement and that is all that is required under s. 175(3).
It was further argued for the appellant that there being a
Government notification of a formal character,
834
we should not travel outside it and find authority in a
person who is not authorised thereunder. But s. 175(3) does
not prescribe any particular mode in which authority must
be conferred. Normally, no doubt, such conferment will be
by notification in the Official Gazette, but there is
nothing in the section itself to preclude authorisation
being conferred ad hoc on any person, and when that is
established the requirements of the section must be held to
be satisfied. In the result, we hold that the agreement
dated February 6, 1948, was executed by a person who was
authorised to do so by the Governor, and in consequence
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
there was a valid reference to arbitration.
It is next contended that as the copy of the award in court
was unstamped, no decree could have been passed thereon.
The facts are that the arbitrator ,sent to each of the
parties a copy of the award signed by him and a third copy
also signed by him was sent to the court. The copy of the
award which was sent to the Government would appear to have
been insufficiently stamped. If that had been produced in
court, it could have been validated on payment of the
deficiency and penalty under s. 35 of the Indian Stamp Act,
1899. But the Government has failed to produce the same.
The copy of the award which was sent to the respondents is
said to have been seized by the police along with other
papers and is not now available. When the third copy was
received in court, tile respondents paid the requisite stamp
duty under s. 35 of the Stamp Act and had it validated. Now
the contention of the appellant is that the instrument
actually before the court, is, what it purports to be, "a
certified copy", and that under s. 35 of the Stamp Act there
can be validation only of the original, when it is unstamped
or insufficiently stamped, that the document in court which
is a copy cannot be validated and "acted upon" and that in
consequence no decree could be passed thereon. The law is
no doubt well-settled that the copy of an instrument cannot
be validated: That was held in The Rajah of, Bobbili v.
Inuganti China Sitaramasani Garu (1), where it was observed:
835
"The provisions of this section (section 35)
which allow a document to be admitted in
evidence on payment of penalty, have no
application when the original document, which
was unstamped or was insufficiently stamped,
has not been produced- and, accordingly,
secondary evidence of its contents cannot be
given. To hold otherwise would be to add to
the Act a provision which it does not contain.
Payment of penalty will not render secondary
evidence admissible, for under the stamp law
penalty is leviable only on an unstamped or
insufficiently stamped document actually
produced in Court and that law does not
provide for the levy of any penalty on lost
documents",
Therefore the question is whether the award which was sent
by the arbitrator to the court is the original instrument or
a copy thereof. There cannot, in our opinion, be any doubt
that it is the original and not a copy of the award. What
the arbitrator did was to prepare the award in triplicate,
sign all of them and send one each to the party and the
third to the court. This would be an original instrument,
and the words, "certified copy" appearing thereon are a mis-
description and cannot have the effect of altering the true
character of the instrument. There is no substance in this
contention of the appellant either. In the result, the
appeal fails and is dismissed with costs.
Appeal dismissed.
836