Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
CASE NO.:
Appeal (civil) 6114 of 1999
PETITIONER:
STATE OF A.P. & ORS.
RESPONDENT:
M/S. PIONEER BUILDERS, A.P.
DATE OF JUDGMENT: 25/09/2006
BENCH:
H.K. SEMA & D.K. JAIN
JUDGMENT:
J U D G M E N T
WITH
Civil Appeal No.6115/1999, Civil Appeal No.1005/2000
and
Civil Appeal No.1006/2000
D.K. JAIN, J.:
These four cross appeals, by special leave, are
directed against two judgments and orders, both dated
3.3.1999, rendered by the High Court of Judicature
Andhra Pradesh at Hyderabad in Appeals No.2206-2207
of 1996 and 236-237 of 1998. The State of Andhra
Pradesh, the first defendant in the suit and plaintiff,
namely, M/s. Pioneer Builders, Engineers and
Contractors, Hyderabad, hereinafter referred to as "the
contractor" are the appellants before us. Since the
factual matrix and the questions of law involved in all the
appeals are common, these are being disposed of by this
judgment. However, we shall refer to the facts of Civil
Appeal No.6115/1999 as illustrative.
2. Sometime in the year 1988, the Superintending
Engineer, Srisailam Right Branch Canal (for short
"SRBC"), defendant No.2 in the Suit, issued notice
inviting tenders from pre-qualified bidders of eligible
source countries, which included India, for the work of
excavation, lining and construction of structures of
SRBC. It was a time bound project supported by credit
loans from the International Development Association
and International Bank for Reconstruction and
Development.
3. The tender of the contractor being the lowest, he
was awarded the work valued at Rs.8,42,93,617/-. A
formal agreement was executed. Time for completion of
the work was thirty six months from the date of handing
over of the site. Clause 57 of General Conditions of
Contract laid down the procedure for resolution of
disputes. It reads thus:
"57. RESOLUTION OF DISPUTES:
1) Settlement of claims for Rs.50,000/- and
below by Arbitration.
All disputes or differences in respect of which
the decision, if any, of the Engineer or Employer has
not become final and binding as aforesaid, shall on
the initiative of either party in dispute be referred to
the adjudication as follows:
a) Claims upto a value Superintending Engineer
of Rs. 10,000/- S.R.B.C. Circle No.III
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
Banganapalli at Nandyal
b) Claims above Rs. Chief Engineer,
10,000/- & upto Major Irrigation,
Rs.50,000/- Hyderabad
The arbitration shall be conducted in
accordance with the provisions of Indian Arbitration
Act of 1940 or any statutory modifications thereof.
2. Settlement of claims above Rs.50,000/-
All claims of above Rs.50,000/- are to be
settled by a court of competent jurisdiction by way
of Civil Suit."
4. It seems that only 50% of the allotted work could be
completed by the due date. Apprehending expulsion, on
24.3.1992, the contractor filed a petition under Sections
8 and 20 of the Indian Arbitration Act, 1940 read with
Section 26 and Order VII Rule 1 of the Code of Civil
Procedure (for short "C.P.C"), registered as an original
suit, with the following prayers:
"(a) Arbitrate the disputes mentioned in para
17 arising between the plaintiff and
defendant under clauses 56 and 57 of
section 2, vol.I of the contract and also
direct the defendants to pay to the
plaintiff the amount so determined as
payable.
(b) Or in alternative to direct the defendants
to file the agreement before the Hon’ble
Court and appoint a sole arbitrator for
adjudicating the said disputes referred to
in paragraph 17 arising between the
plaintiff and defendants under the
Arbitration Act, 1940.
(c) Payment of interest on the amount
payable to the plaintiff at the rate of 21%
per annum from the date of execution of
work till payment.
(d) Costs."
5. On 26.3.1992 defendant No.2 issued notice to the
contractor expelling them from the contract on the
ground that they had failed to maintain the rate of
progress as per the approved programme. On 13.4.1992,
the contractor filed an application seeking interim
injunction, restraining the defendants from encashing the
bank guarantees for an amount of Rs.1,26,00,000/-,
furnished by them towards mobilization advance and as
performance guarantee. The suit was resisted by the
defendants mainly on merits though it was averred that
"the plaintiff suit is not maintainable either in law or on
facts". No separate reply to the application appears to
have been filed. However, the application was dismissed
by the subordinate Judge. Aggrieved, the contractor
preferred appeal to the High Court, which was dismissed
vide order dated 13.11.1992. While dismissing the
appeal, the High Court observed that having regard to the
language of the arbitration agreement between the parties
and the fact that there was no claim for any specified
amount in the petition, the suit as filed by the contractor
was not maintainable. The Court, however, clarified that
it would be open to the contractor to amend the plaint in
accordance with law, if so advised.
6. In the light of the said order, on 17.1.1993, the
contractor filed three applications in the pending suit: (i)
I.A. No.1/1993 \026 under Order VI Rule 17 C.P.C. for
amendment of the plaint; (ii) I.A. No. 2/1993 - for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
production of documents by the defendants; (iii) I.A.
No.3/1993 - for dispensing with notice under Section 80
of C.P.C. All the applications were opposed by the
defendants on merits of the claims made in the
application seeking amendment of the plaint. No
objection with regard to the maintainability of the
applications was raised. However, in the penultimate
paragraph of reply to I.A. No. 3/1993, it was stated that
since time was required to examine the claims, "issue of
notice under Section 80 C.P.C. was necessary and was
not superfluous". All the three applications were allowed
by the subordinate Judge vide docket order dated
2.2.1993. Order passed in I.A. No.3/1993 reads as
follows:
"Heard both counsels. I don’t find any tenable
ground to refuse the relief asked for, allowed."
7. The orders passed in the said applications were not
challenged. Instead two additional written statements
were filed on behalf of the defendants. On the basis of
the pleadings, as many as eighteen issues were framed.
None of the issues pertained to maintainability of the
suit. After trial, the suit was decreed in respect of some
of the claims made by the contractor with interest from
the date of the filing of the suit. However, some of the
claims made by the contractor were rejected.
8. Being aggrieved, both the parties preferred First
Appeals to the High Court (No.2206-2207 of 1996 and
236-237 of 1998). By the impugned order, the High
Court has dismissed all the appeals. Hence, the present
appeals.
9. We have heard Mr. Anoop G. Choudhary, learned
senior counsel appearing on behalf of the State and Mr.
V.R. Reddy, learned senior counsel appearing for the
contractor only on the two legal issues emanating from
the orders passed by the subordinate Judge in I.A. Nos. 1
and 3/1993, namely, (i) maintainability of the
amendment application filed under Order VI Rule 17
C.P.C. and (ii) maintainability of the suit for want of
notice under Section 80 C.P.C.
10. Mr. Choudhary has vehemently submitted that
Section 80 C.P.C. being mandatory and in the absence of
any prayer for an urgent and immediate order, the Trial
Court was not justified in dispensing with the
requirement of issue of notice under that Section. It is
asserted that the provisions of sub-Section (2) of Section
80 C.P.C. were not attracted on the pleaded facts and,
therefore, in the absence of requisite notice under sub-
section (1) of Section 80, the Trial Court could not
entertain the suit. Learned counsel has also urged that
the petitions filed by the contractor initially under
Sections 8 and 20 of the Arbitration Act could not be
converted into civil suits by way of amendment
applications under Order VI Rule 17 C.P.C. In support
reliance is placed on the decisions of this Court in P.A.
Ahammed Ibrahim Vs. Food Corporation of India
and Bharat Coking Coal Ltd. Vs. Raj Kishore Singh
and Another , wherein it has been held that converting
an application under Section 20 of the Arbitration Act
into a suit for recovery by permitting it to be amended
under Order VI Rule 17 C.P.C. would amount to
introducing a totally new cause of action and change the
nature of the action. It is, thus, pleaded that the High
Court has failed to take into consideration the settled
principles of law on both the issues.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
11. Per contra, Mr. Reddy has contended that though
the suit filed initially was styled as a petition under
Sections 8 and 20 of the Arbitration Act on account of
vague language of the arbitration agreement but in fact it
was a civil suit. Learned counsel has also submitted that
having failed to take any objection with regard to the
maintainability of the suit for want of notice under
Section 80 C.P.C. and further having failed to challenge
the orders passed by the Trial Court, allowing the
applications filed under Section 80(2) and Order VI Rule
17 C.P.C., and having participated in proceedings before
the Trial Court, the defect, if any, stood waived and the
State is now estopped from raising such objections.
Relying on Ghanshyam Dass and Others Vs. Dominion
of India and Others , learned counsel has submitted
that Section 80 C.P.C. being merely a part of the adjective
law, dealing with procedure alone, it should be
interpreted in a manner so as to subserve and advance
the cause of justice rather than to defeat it on a mere
technicality. Learned counsel has also urged that
relegating the contractor to the stage of notice under
Section 80 C.P.C. would be travesty of justice.
12. The first question that arises for determination is as
to whether or not the suit filed by the contractor was
maintainable because of the alleged non-compliance with
the provisions of Section 80 C.P.C.?
Section 80 C.P.C. reads as follows:-
"80. Notice \026 (1) Save as otherwise provided in
sub-section (2), no suit shall be instituted
against the Government (including the
Government of the State of Jammu and
Kashmir) or against a public officer in respect
of any purporting to be done by such public
officer in his official capacity, until the
expiration of two months next after notice in
writing has been delivered to, or left at the
office of \026
(a) in the case of a suit against the
Central Government, [except where it
relates to a railway], a Secretary to
that Government;
(b) in the case of a suit against the
Central Government where it relates
to a railway, the General manager of
that railway;
*
(bb) in the case of a suit against the
Government of the State of Jammu
& Kashmir, the Chief Secretary to
that Government or any other officer
authorised by that Government in
this behalf;
(c) in the case of a suit against [any
other State Government], a Secretary
to that Government or the Collector of
the district;
*
*
and in the case of a public officer,
delivered to him or left at his office,
stating the cause of action, the name,
description and place of residence of the
plaintiff and the relief which he claims;
and the plaint shall contain a statement
that such notice has been so delivered or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
left.
(2) A suit to obtain an urgent or
immediate relief against the Government
(including the Government of the State of
Jammu and Kashmir) or any public
officer in respect of any purporting to be
done by such public officer in his official
capacity, may be instituted, with the
leave of the Court, without serving any
notice as required by sub-section (1); but
the Court shall not grant relief in the
suit, whether interim or otherwise, except
after giving to the Government or public
officer, as the case may be, a reasonable
opportunity of showing cause in respect
of the relief prayed for in the suit:
Provided that the Court shall, if it is
satisfied, after hearing the parties, that
no urgent or immediate relief need be
granted in the suit, return the plaint for
presentation to it after complying with
the requirements of sub-section (1).
(3) No suit instituted against the
Government or against a public officer in
respect of any act purporting to be done
by such public officer in his official
capacity shall be dismissed merely by
reason of any error or defect in the notice
referred to in sub-section (1), if in such
notice \026
(a) the name, description and the
residence of the plaintiff had been
so given as to enable the
appropriate authority or the public
officer to identify the person serving
the notice and such notice had been
delivered or left at the office of the
appropriate authority specified in
sub-section (1) and
(b) the cause of action and the relief
claimed by the plaintiff had been
substantially indicated."
13. From a bare reading of sub-section (1) of Section 80,
it is plain that subject to what is provided in sub-section
(2) thereof, no suit can be filed against the Government or
a public officer unless requisite notice under the said
provision has been served on such Government or public
officer, as the case may be. It is well-settled that before
the amendment of Section 80 the provisions of
unamended Section 80 admitted of no implications and
exceptions whatsoever and are express, explicit and
mandatory. The Section imposes a statutory and
unqualified obligation upon the Court and in the absence
of compliance with Section 80, the suit is not
maintainable. (See: Bhagchand Dagdusa Gujrathi &
Ors. Vs. Secretary of State for India ; Sawai Singhai
Nirmal Chand Vs. The Union of India and Bihari
Chowdhary & Anr. Vs. State of Bihar & Ors. ). The
service of notice under Section 80 is, thus, a condition
precedent for the institution of a suit against the
Government or a public officer. The legislative intent of
the Section is to give the Government sufficient notice of
the suit, which is proposed to be filed against it so that it
may reconsider the decision and decide for itself whether
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
the claim made could be accepted or not. As observed in
Bihari Chowdhary (supra), the object of the Section is
the advancement of justice and the securing of public
good by avoidance of unnecessary litigation.
14. It seems that the provision did not achieve the
desired results inasmuch as it is a matter of common
experience that hardly any matter is settled by the
Government or the public officer concerned by making
use of the opportunity afforded by said provisions. In
most of the cases, notice given under Section 80 remains
unanswered. In its 14th report (reiterated in 27th and 54th
Report), the Law Commission, while noting that the
provisions of this section had worked a great hardship in
a large number of cases where immediate relief by way of
injunction against the Government or a public officer was
necessary in the interests of justice, had recommended
omission of the Section. However, the Joint Committee of
Parliament, to which the Amendment Bill 1974 was
referred, did not agree with the Law Commission and
recommended retention of Section 80 with necessary
modifications/relaxations.
15. Thus, in conformity therewith, by the Code of Civil
Procedure (Amendment Act, 1976) the existing Section 80
was renumbered as Section 80(1) and sub-sections (2)
and (3) were inserted with effect from 1.2.1977. Sub-
section (2) carved out an exception to the mandatory rule
that no suit can be filed against the Government or a
public officer unless two months’ notice has been served
on such Government or public officer. The provision
mitigates the rigours of sub-section (1) and empowers the
Court to allow a person to institute a suit without serving
any notice under sub-section (1) in case it finds that the
suit is for the purpose of obtaining an urgent and
immediate relief against the Government or a public
officer. But, the Court cannot grant relief under the sub-
section unless a reasonable opportunity is given to the
Government or public officer to show cause in respect of
the relief prayed for. Proviso to the said sub-section
enjoins that in case the Court is of the opinion that no
urgent and immediate relief should be granted, it shall
return the plaint for presentation to it after complying
with the requirements of sub-section (1). Sub-section (3),
though not relevant for the present case, seeks to bring in
the rule of substantial compliance and tends to relax the
rigour of sub-section (1).
16. Thus, from a conjoint reading of sub-sections (1)
and (2) of Section 80, the legislative intent is clear,
namely, service of notice under sub-section (1) is
imperative except where urgent and immediate relief is to
be granted by the Court, in which case a suit against the
Government or a public officer may be instituted, but
with the leave of the Court. Leave of the Court is a
condition precedent. Such leave must precede the
institution of a suit without serving notice. Even though
Section 80(2) does not specify how the leave is to be
sought for or given yet the order granting leave must
indicate the ground(s) pleaded and application of mind
thereon. A restriction on the exercise of power by the
Court has been imposed, namely, the Court cannot grant
relief, whether interim or otherwise, except after giving
the Government or a public officer a reasonable
opportunity of showing cause in respect of relief prayed
for in the suit.
17. Having regard to the legislative intent noticed above,
it needs little emphasis that the power conferred in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
Court under sub-section (2) is to avoid genuine hardship
and is, therefore, coupled with a duty to grant leave to
institute a suit without complying with the requirements
of sub-section (1) thereof, bearing in mind only the
urgency of the relief prayed for and not the merits of the
case. More so when want of notice under sub-section (1)
is also made good by providing that even in urgent
matters relief under this provision shall not be granted
without giving a reasonable opportunity to the
Government or a public officer to show cause in respect
of the relief prayed for. The provision also mandates that
if the Court is of the opinion that no urgent or immediate
relief deserves to be granted it should return the plaint
for presentation after complying with the requirements
contemplated in sub-section (1).
18. Bearing in mind the afore-noted legal position, we
advert to the facts in hand. As noted above, the
subordinate Judge, vide Order dated 2nd February, 1993
came to the conclusion that "there was no tenable ground
to refuse the relief asked for". Though there may be some
substance in the submission of Mr. Choudhary, learned
senior counsel appearing for the State, that the order
allowing the application, seeking dispensation of the
requirement of notice, is cryptic but the fact remains that
by allowing the application, after hearing the defendant
State, the Judge has opined that the suit is for the
purpose of obtaining an urgent and immediate order.
Had the satisfaction been against the contractor, the
Court was bound to return the plaint to the contractor for
re-presentation after curing the defect in terms of sub-
section (1) of Section 80. Although we do not approve of
the manner in which the afore-extracted order has been
made and the leave has been granted by the subordinate
Judge but bearing in mind the fact that in its reply to the
application, the State had not raised any specific
objection about the maintainability of the application on
the ground that no urgent and immediate relief had
either been prayed for or could be granted, as has now
been canvassed before us, we are of the opinion that
having regard to the peculiar facts and the conduct of
both the parties it is not a fit case where the matter
should be remanded back to the subordinate Judge for
re-consideration. We find it difficult to hold that the
order passed by subordinate Judge on contractor’s
application under Section 80(2) C.P.C. was beyond his
jurisdiction. Accordingly, we decline to interfere with the
finding recorded by the High Court on this aspect of the
matter. The High Court has held that having participated
in the original proceedings, it was not now open to the
State to raise a fresh issue as to the maintainability of the
suit, in view of waiving the defect at the earliest point of
time. The High Court has also observed that knowing
fully well about non-issue of notice under Section 80
C.P.C. the State had not raised such a plea in the written
statement or additional written statement filed in the suit
and therefore, deemed to have waived the objection. It
goes without saying that the question whether in fact,
there is waiver or not necessarily depends on facts of
each case and is liable to be tried by the Court, if raised,
which, as noted above, is not the case here.
19. We may now advert to the other aspect of the
matter, viz. whether or not leave to amend the
petition/plaint was granted by the subordinate Judge in
accordance with the principles regulating amendments of
pleadings?
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
20. Principles governing amendment of pleadings are
well-settled. Order VI Rule 17 C.P.C. deals with the
amendment of pleadings and provides that the Court may
at any stage of the proceedings allow either party to alter
or amend pleadings in such a manner and on such terms
as may be just and all such amendments shall be made
as may be necessary for the purpose of determining the
real questions in controversy between the parties. It is
trite that though an amendment cannot be claimed as a
matter of right under all circumstances, yet the power to
allow the amendment is wide and can be exercised at any
stage of the proceedings in the interest of justice. It is
equally well-settled that unless serious injustice or
irreparable loss is likely to be caused to the other side,
the Court should adopt liberal approach and not a hyper-
technical approach particularly in a case where the other
side can be compensated with costs. Dominant object to
allow the amendment in the pleadings liberally is to avoid
multiplicity of proceedings (See: L.J. Leach & Co. Ltd. &
Anr. Vs. M/s. Jardine Skinner & Co. , Smt. Ganga Bai
Vs. Vijay Kumar & Ors. and B.K. Narayana Pillai Vs.
Parmeswaran Pillai & Anr. Nevertheless, one distinct
cause of action cannot be substituted for another nor the
subject-matter of the suit can be changed by means of an
amendment. The following passage from the decision of
the Privy Council in Ma Shwe Mya Vs. Maung Mo
Hnaung , succinctly summarises the principle which
may be kept in mind while dealing with the prayer for
amendment of the pleadings:
"All rules of court are nothing but provisions
intended to secure the proper administration
of justice, and it is therefore essential that they
should be made to serve and be subordinate to
that purpose, so that full powers of
amendment must be enjoyed and should
always be liberally exercised, but nonetheless
no power has yet been given to enable one
distinct cause of action to be substituted for
another, nor to change, by means of
amendment, the subject-matter of the suit."
21. Having briefly noted the principles governing
amendment of pleadings, we may advert to the facts of
the present case.
22. Incidentally, the order passed by the subordinate
Judge allowing the amendment application has not been
filed but learned counsel appearing for both the parties
have stated before us that it was identical to the one
passed in the Application under Section 80(2) C.P.C. (I.A.
No. 3 of 1993), extracted above. Before the High Court it
was argued on behalf of the State and so before us that
since the amendment prayed for had the effect of
changing the nature and character of the suit, it could
not be allowed. However, we find that though the
submission has been noted but somehow in the
impugned judgment the High Court has altogether
omitted to deal with the aspect of amendment of the
plaint and straight away proceeded to decide the claims
on merits. Initially filed as a petition under Sections 8
and 20 of the Arbitration Act, by means of an application
under Order VI Rule 17 C.P.C. it was sought to be
converted into a civil suit. It is pleaded before us that the
original petition was also, in fact, in the nature of a civil
suit as the court fee paid was much more than what was
required to be paid on a petition under the Arbitration
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
Act. We are of the considered view that in the absence of
any finding by the High Court on this aspect of the
matter, it will not be proper for us to comment on the
validity of the order passed by the subordinate Judge on
contractor’s application seeking amendment of the
plaint/petition, particularly when, as noted above, the
High Court, in its order dated 13.11.1992 had observed
that in the absence of any claim for a specified amount,
the suit, originally filed by the contractor, was not
maintainable. We feel that certain factual aspects may
also have to be gone into by the High Court in the First
Appeals filed by the State, wherein orders passed by the
subordinate Judge on 2.2.1993 (in I.A. Nos. 1 and
3/1993) had been challenged. Under these
circumstances, we deem it just and proper to remand the
matter back to the High Court for consideration of the
issue with regard to the maintainability and the merits of
the application filed by the contractor under Order VI
Rule 17 C.P.C.
23. In the result, the appeals filed by the State are
allowed to the extent indicated above. We may, however,
clarify that we have not expressed any opinion on the
merits of the decree passed by the subordinate Judge
and upheld by the High Court. We keep the issue open.
It will be open to the parties to take recourse to
appropriate proceedings, including revival of the present
appeals, after the High Court has rendered its decision
on the afore-noted issue. The parties are, however, left to
bear their respective costs.