Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
STATE OF ASSAM
Vs.
RESPONDENT:
JITENDRA KUMAR SENAPATI & OTHERS
DATE OF JUDGMENT17/02/1981
BENCH:
KOSHAL, A.D.
BENCH:
KOSHAL, A.D.
FAZALALI, SYED MURTAZA
CITATION:
1981 AIR 969 1981 SCR (2) 850
1981 SCC (2) 221 1981 SCALE (1)328
ACT:
Land Acquisition Act, 1894, sections 23 and 34-
Agreement between the parties reduced in writing to accept a
specified sum by a specified date two years after the land
acquisition-Whehter the words "would not make any further
claim in regard to compensation" would exclude further
claims of interests under the Act.
HEADNOTE:
Accepting the State appeal, negativing the claim for
interest and dismissing the original writ petition, the
Court,
^
HELD: The expression "would not make any further claim
in regard to compensation" in the agreement dated the 24th
February, 1969 was clearly used by the petitioners-
respondents not in the sense in which it is used in sections
23 and 34 of the Land Acquisition Act but more
comprehensively Meaning reimbursement in full satisfaction
of their claim in respect of the acquisition. The condition
attached by them to the relinquishment of their claim was
that the agreed amount must be paid to them before 31st
March 1969, which agreement would show that by the
acceptance of the quantified sum of Rs. 4,41,202.45 they
condoned the delay in payment and also relinquished all
future claims to interest. If it were otherwise, the
respondents would have expressly reserved their right to
claim interest under section 34 of the Act. [853 A-B, D-F]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1947 of
1970.
From the Judgment and Order dated 17.3.1970 of the
Gauhati High Court in Civil Rule No. 1151/69.
S. N. Chowdhary for the Appellant.
D. N. Mukherjee for Respondent No. 2.
V. S. Desai, B. P.Maheshwari and Suresh Sethi and Miss
Asha Jain for the Respondent.
The Judgment of the Court was delivered by
KOSHAL, J. This is an appeal by certificate granted
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
under sub-clause (a) of clause (1) of article 133 of the
Constitution of India by the High Court of Assam and
Nagaland against its judgment dated 17th March, 1970
accepting a petition under article 226 of the Constitution
of India which arose in the circumstances that follow.
Land measuring 7.60 acres and situated at Lawshtun,
Bishnupur, Shillong, belonged to the 5 respondents when a
notification under section 4 of the Land Acquisition Act
(hereinafter referred to as the
851
Act) was published in respect thereof on 27th March 1967.
Three days later the possession of the land was taken over
by the Collector, United Khasi and Jaintia Hills, Shillong.
Proceedings for the award of compensation to the respondents
were pending when negotiations took place between the Chief
Secretary to the Government of Assam and two of the
respondents who agreed to the reduction of the cost of
acquisition of the land from Rs. 6,17,683.50 to Rs.
4,63,262.57 (inclusive of cost of establishment and
contingency amounting to Rs. 22,060.12). Thereafter the
Under Secretary to the Government of Assam in the Home and
Political/Department wrote to respondent No. 2 a letter
dated 21st February, 1969 detailing the agreement arrived at
between the Chief Secretary and the respondents and
requesting them-
"to please submit immediately a written document
signed by all the co-sharers of the land to the effect
that yourself and all other co-sharers are agreeable to
accept the L. A. cost of Rs. 4,41,202.45 for land at
Bishnupur and that you and your co-shares will make no
further claim for the land thus acquired by
Government."
The respondents lost no time in sending their reply
which was dated 24th February 1969 and in which they stated
that the delay in payment had caused to them great hardship
and that they had agreed to reduce the cost of the
acquisition in the course of their discussion with the Chief
Secretary whom they had urged "at the same time that the
payment should be made immediately." The reply was signed by
all the five respondents and was accompanied by an agreement
(also signed by all of them), the text of which may be set
out in extense:
"We, all the co-shares interested in the land
acquisition case for construction of quarters for
Special Branch Staff of Police Department at Lawsohtun,
Bishnupur, Shillong, hereby agree in response to the
Government Letter No. 356/ 66/55 dated the 21st
February, 1969 to accept the land acquisition cost of
Rs. 4,41,202.45P (Rupees four lakhs forty one thousand
two hundred and two and forty five paise only) subject
to Government making payment within the 31st March,
1969 for our land measuring more or less 7.60 acres at
Lawsohtun, Bishnupur, Shillong.
"We further agree that we will make no further
claim in regard to compensation for the same land
provided actual
852
payment is received within the above period of 31st
March, 1969."
The agreement between the parties was reduced by the
Collector to an award dated the 25th March 1969 and on the
very next day the sum of Rs. 4,41,202.45 was paid to the
respondents.
On 31st March 1969 the respondents made an application
to the Chief Secretary claiming interest at the rate of 12
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
1/2 percent per annum on the amount last mentioned. As there
was no response from the Chief Secretary, the respondents
applied to the Collector on 7th July, 1969 requesting him to
pay interest On the amount awarded at the rate of 6% per
annum for the period from 30th March 1967 to 26th March 1969
under section 34 of the Act which runs thus:
"When the amount of such compensation is not paid
or deposited on or before taking possession of the
land, the collector shall pay the amount awarded with
interest thereon at the rate of six per cent per annum
from the time of so taking possession until it shall
have been so paid or deposited."
The Collector informed the respondents by a letter
dated 31st July 1969 that no action was necessary "at this
stage". It was then that the respondents knocked at the door
of the High Court.
2. The High Court was of the opinion that the agreement
between the parties covered only the amount of
"compensation" as described in the various sections of the
Act including sections 23 and 34 and that interest had to be
paid on such compensation by reason of the statutory
requirement enacted in that behalf by section 34. The High
Court, therefore, accepted the petition filed before it and
held that the Collector was bound to pay to the respondents
interest on the amount covered by the award at the rate of 6
per cent per annum from 30th March 1967 (being the date on
which the possession of the land was taken over by the
Collector) to the date of payment, i.e., 26th March 1969. It
directed the Collector to dispose of the petition dated the
7th July 1969 made to him by the respondents in accordance
with law.
3. The short point requiring determination by us is
whether the agreement arrived at between the parties in
February 1969 embraced only the "Compensation" within the
meaning of that term as used in the Act or covered also the
payment of interest under section 34 there of. Having heard
learned counsel for the parties we are of the opinion that
the interpretation placed on the agreement by the High Court
can not be sustained and that the respondent are not
entitled to any interest on the sum already paid to them.
853
4. Although it is true that in the agreement dated the
24th A February 1969 which the respondents signed and sent
to the Government along with their letter of that date they
stated that they would not make any further claim in regard
to "compensation", but that expression, in our opinion, was
clearly used by them not in the sense in which it is used in
sections 23 and 34 of the Act but more comprehensively,
meaning reimbursement in full satisfaction of their claim in
respect of the acquisition. That this was 60 was made clear
in the letter addressed to them by the Under Secretary in
which he expressly stated that-
"you and your co-sharers will make no further
claim for the land thus acquired by the Government."
The Under Secretary did not use the word "compensation"
in his letter nor did the respondents use it in their reply
in which, on the other hand, they made a grouse of the
hardship which the delay in payment bad caused to them and
brought it to the pointed attention of the under Secretary
that immediate payment was an essential part of the bargain.
In the agreement signed by them (as pointed out above) they
no doubt used the word "compensation" but they added that
they would make no further claim in regard to it if actual
payment was received by them before the 31st March, 1969.
The condition thus attached by them to the agreement would
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
show that by the acceptance of the quantified sum of Rs.
4,41,202.45 they condoned the delay in payment and also
relinquished all future claims to interest. If it were
otherwise, there is no reason why the respondents would not
have expressly reserved their right to claim interest under
section 34 of the Act. The tenor of the two letters coupled
with the agreement leads to no other conclusion.
4. In the result the appeal succeeds and is accepted.
The judgment of the High Court is set aside and the
respondents’ petition decided by it is dismissed but with no
order as to costs.
S.R. Appeal allowed.
854