Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 42
CASE NO.:
Appeal (civil) 4492 of 1998
PETITIONER:
Mcdermott International Inc.
RESPONDENT:
Burn Standard Co. Ltd. & Ors.
DATE OF JUDGMENT: 12/05/2006
BENCH:
B.P. Singh & S.B. Sinha
JUDGMENT:
J U D G M E N T
I.A. NOS.2-3
IN
CIVIL APPEAL NO. 4492 OF 1998
S.B. SINHA, J :
INTRODUCTION
Oil was discovered in the Bombay High Region in 1974 whereupon a
plan of rapid development of off-shore oil and gas production was embarked
by the Government of India through Oil and Natural Gas Commission
(ONGC). With a view to achieve exploration of production programme,
ONGC appointed contractors to fulfill substantial portions of its off-shore
construction requirements. Burn Standard Company Limited (for short
"BSCL") was interested in the second stage of platform construction of
ONGC, i.e., structural and progress fabrication and material procurement.
Four contracts were thereafter awarded in favour of BSCL for fabrication,
transportation and installation of six platforms bearing No. ED, EE, WI-8,
WI-9, WI-10 and N3 and associated pipelines. They were to be installed in
ONGC’s Bombay High Sea.
CONTRACT
The said contracts covered:
(i) Material procurement and fabrication of the ED and EE jackets, piles
and decks.
(ii) Transportation and installation of the ED and EE jackets, piles and
decks.
(iii) Material Procurement and fabrication of the WI-8, WI-9, WI-10 and
N-3 Jackets, piles, temporary decks and decks (the "Four Platform
Fabrication Main Contract") and
(iv) Transportation and installation of the WI-8, WI-9, WI-10 and N-3
jackets, piles, temporary decks and decks, and installation of four
pipelines and eight risers (the "Four Platform Installation Main
Contract").
The said contracts contained arbitration agreements.
BSCL and Mcdermott International Inc. (for short "MII") entered into
Technical Collaboration Agreement on 25th September, 1984 in terms
whereof the latter agreed to transfer technology to the former with regard to
design, construction and operation of a fabrication yard. The said agreement
contains a separate arbitration clause between the parties.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 42
However, with regard to the fabrication and installation of off-shore
platforms, BSCL decided to give a sub-contract of the work to MII on a
project by project basis. BSCL while retained the job of fabrication of the
ED and EE decks, six helidecks and procurement of materials for the overall
project other than pipeline materials and some process equipment which was
issued by ONGC sub-contracted the remaining work.
In terms of a letter of intent dated 14th September, 1984 a contract was
entered into by and between BSCL and ONGC for fabrication and
installation of offshore platforms ED, EE, WI-8, WI-9, WI-10 and N-3 and
laying of WI-8 to WI-9, WI-9 to WI-10, WI-9 to WIS and N-3 to NO
pipelines and 8 associated risers as well as WI-7 to WI-8, WI-9 to SD, WI-
10 to SV, EB to SC1, EC to SHP, ED to SHP, EE to SHP pipelines and 11
associated risers. A part of the said contract work was assigned to MII in
respect of fabrication, transporation and installation of structures, modules,
platforms and pipeline components on or about 1st January, 1986. The work
under the said agreement was to be completed within 24 months but in all
respects it was completed in early 1989.
TERMS OF THE CONTRACT
The relevant covenants between the parties contained in the said
agreement are as under:
"Article 2. MII shall unless inconsistent with the
provisions of this Sub-contract perform fulfill and
observe all the obligations, covenants and
agreements required on the part of BSCL to be
performed, fulfilled and observed in terms of the
Main Contracts to the extent these obligations,
covenants and agreements relate to the Sub-
contract Work including such obligations,
agreements and covenants as may in future be
added, modified or provided in the Main Contracts
between the Buyer and BSCL with concurrence of
MII to the extent thereof. These obligations,
covenants and agreements, as have been agreed to
be performed, fulfilled and observed by MII shall
include the performance of the Sub-contract work
in the manner and to the specifications as provided
in the respective Main Contracts.
Article 3
3.1 MII shall be bound to BSCL by the terms of
this Sub-contract Agreement and to the extent that
the provisions of the respective Main Contract
between Buyer and BSCL apply to the relevant
Sub-Contract work of MII as defined in this Sub-
contract Agreement, MII shall assume towards
BSCL all the obligations and responsibilities
which BSCL, by such Main Contract, assumes to
Buyer and shall have the benefit of all rights,
remedies and redresses against BSCL which
BSCL, by such Main Contract, has against Buyer,
insofar as applicable to this sub-contract
Agreement, provided that when any provision of
the respective Main Contract between Buyer and
BSCL is inconsistent with this Sub-contract
Agreement, this Sub-contract Agreement shall
govern and prevail over the Main Contract.
3.2 BSCL shall be bound to MII by the terms of
this Sub-Contract Agreement and to the extent that
the provisions of the respective Main Contracts
between Buyer and BSCL apply to the relevant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 42
Sub-contract work of MII as defined in this Sub-
contract Agreement, BSCL shall assume towards
MII all the obligations and responsibilities that
Buyer, by such Main Contracts, assumes towards
BSCL, and shall have the benefit of all rights,
remedies and redress against MII which Buyer, by
such Main Contracts, has against BSCL insofar as
applicable to this sub-contract Agreement provided
that when any provisions of the Main Contract
between Buyer and BSCL is inconsistent with any
provisions of this Sub-contract Agreement, this
Sub-contract Agreement shall govern and prevail
over the Main Contract.
Article \026 5
5.1 Except as otherwise provided herein, all claims
made by Buyer against BSCL shall be the
responsibility of MII when such claims arise or are
derived from MII’s Sub-contract Scope of Work;
similarly, all claims made by Buyer that arise or
derive from BSCL’s Scope of Work shall be the
responsibility of BSCL. To the extent that BSCL,
as Main Contractor vis-‘-vis Buyer, would be
liable for any claims that arise or are derived from
MII’s Sub-contract Scope of Work, MII shall hold
harmless and keep indemnified BSCL from any
such claims to the extent analogous with MII’s
Sub-contract.
Article \026 6 - Arbitration
6.1 Should there by any dispute or difference
between BSCL and Buyer in regard to any matter
connected with BSCL relating to or arising out of
the Main Contract (s), which may involve MII’s
performance or affect MII’s interest under the
subcontract, BSCL shall keep MII informed and
shall act in consultation and coordination with MII
to ascertain the facts and agree on the appropriate
action to be taken. MII shall render all assistance
and cooperation that BSCL may require in this
regard. If it is determined that the dispute or
difference does not involve MII’s performance or
affect MII’s interests, MII shall render such
reasonable assistance and cooperation as BSCL
may require; provided, however, that MII shall be
entitled to reimbursement of costs, if any, incurred
therefor with the prior approval of BSCL.
6.2 If any dispute or difference arising between
BSCL and Buyer under or in respect of or relating
to the Main Contract insofar as it relates to the
work to be carried out by MII is referred to
arbitration and any award/ judgment/ decree/ order
is passed, or a settlement is otherwise reached with
MII’s consent, MII shall be bound to accept the
same and bear all MII’s liability resulting
therefrom. MII shall, however, be assisted at all
stages by BSCL with such arbitration proceedings
and MII shall bear all expenses of such arbitration/
litigation and/ or negotiated settlement, if any.
However, expenses incurred by BSCL in deputing
their officials to attend such arbitration/
proceeding/ litigation would be to BSCL/s
accounts.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 42
6.3 All disputes and differences in respect of any
matter relating to or arising out of or in connection
with the execution or construction of this
subcontract document, if the same cannot be and/
or is not the subject matter of dispute between
BSCL and the Buyer under the Main Contracts and
is not settled mutually by negotiation, shall be
referred to arbitration under the Indian Arbitration
Act, 1940, as amended from time to time, by
appointing some agency acceptable to both the
parties as Arbitrators and if no agency is found
acceptable to both the parties, then by constituting
a Board of Arbitration consisting of three
Arbitrators, one to be nominated/ appointed by
each party and the third to be appointed by the two
Arbitrators as Umpire. The arbitration proceeding
shall be held at New Delhi and the decision of the
Arbitrators or the Umpire as the case may be shall
be final and binding on both parties hereto. The
arbitrators or the umpire, as the case may be, shall
record their reasons for passing awards, copies of
which shall be sent to the parties.
Article -10
10.1 Any amendment and/ or modification of this
Sub-contract shall be valid only if it is in writing
and signed by both the parties.
All other terms and conditions not specified in this
sub-contract shall be as stipulated in the Main
Contracts.
10.2 This Sub-Contract Agreement shall be
governed by the Laws of the Republic of India."
DISPUTES
Disputes and differences having arisen between the parties, MII
invoked the arbitration clause by a legal notice dated 10th April, 1989.
Several proceedings as regards invocation of arbitration clause were
initiated by the parties before the Calcutta High Court. The said proceedings
ultimately ended in favour of MII leading to appointment of two arbitrators
for determination of the disputes and differences between the parties. The
arbitrators who were earlier appointed were removed and Mr. Justice A.N.
Sen, a retired Judge of this Court was appointed as a sole arbitrator. It is
stated that Mr. Justice A.N. Sen declined to act as an Arbitrator and by an
order dated 28th August, 1998, Mr. Justice R.S. Pathak was appointed by this
Court as a sole arbitrator. The Arbitrator was to continue with the
proceedings from the stage it had reached. The said order is in the following
terms:
"1. Mr. Justice R.S. Pathak, retired Chief Justice of
India is appointed as the sole Arbitrator. In the
case to resolve the disputes and differences which
had been raised by the parties and were the subject
matter of the arbitration proceedings before the
arbitrators earlier appointed;
2) That the Learned Arbitrator shall enter upon the
reference within three weeks from the date of
service of this order upon him.
3) That the arbitration proceedings shall be held at
New Delhi. However, in the event the learned
Arbitrator considers it necessary to hold any sitting
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 42
at any other place, he may do so with the consent
of the parties;
4) The learned Arbitrator shall continue with the
proceedings from the stage where the proceedings
of the arbitration were on 8.5.1998, when the
impugned order came to be made by the Calcutta
High Court;
5) All the proceedings held till 8.5.1998 shall be
treated as the arbitration proceedings held before
the learned sole Arbitrator now appointed;
6) It shall be in the discretion of the learned
Arbitrator to take or not to take oral evidence or to
take oral evidence by way of affidavits. The
learned arbitrator would be at liberty to adopt
summary proceedings for concluding arbitration
proceedings.
7) That the learned Arbitrator shall publish his
Award, as far as possible, within a period of one
year from the date of entering upon the reference;
8) That the fees of the Arbitrator (which may be
fixed by him) and all expenses of arbitration
proceedings shall be shared equally by the parties;
9) The learned Arbitrator shall file the Award in
this Court.
10) Any application which may become necessary
to be filed during or after the conclusion of
arbitration proceedings, shall be filed only in this
Court."
CLAIM OF MII
Before the learned Arbitrator, MII raised the following claims:
1.
For Fabrication of jackets,
Temporary Decks and Main Decks
US$ 1,182,817.94
2.
For Transportation and Installation
of jackets and Decks
US$ 4,351,062.68
3.
For Installation of Pipelines and
Risers
US$ 840,064.23
4.
For Structural Material
Procurement
US$ 5,301,534.13
For Bulk Material Procurement
US$ 84,919.14
UKL 262,296.43
S$ 680,764.29
5.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 42
For Transportation of Pipe
US$ 1,231,415.00
6.
For Reimbursables
US$ 377,309.30
7.
For Change Orders and Extra Work
US$ 7,423,741.95
8.
For Delays & Disruptions
US$ 13,233,343.00
8A.
For exchange Entitlements
US$ 2,881,195.03
9.
For Interest upto 21 August, 1989
US$ 10,909,772.19
UKL 148,254.14
S$ 521,102.56
Total
US$47,817,174.59
UKL 410,550.57
S$ 1,201,866.85"
Before the Arbitrator, apart from the aforementioned amount, interest
on the outstanding amount was also claimed at the rate of 15% per annum on
all claims for which invoices were not paid until the award, as well as
interest from 21st August, 1989 and future interest at the rate of fifteen per
cent.
BSCL filed counter statements as also counter-claims before the
learned Arbitrator.
The learned arbitrator took up for his consideration the following
claims for his consideration:
1. Fabrication of Jackets, Temporary Decks and Main Decks
2. Transportation and Installation of Jackets, Decks (Permanent &
Temporary) and Helidecks
3. Pipelines and Risers Installation
4. Structural Material and Rolling
5. Bulk Material
6. Transportation of Pipes
7. Reimbursables
8. Change Orders and Extra Works
9. Delays and Disruptions
9A. Whether MII is entitled to an exchange loss as claimed in
paragraphs 4.74 to 4.78 of the Statement of Claims? If so, in what
amount?
10. Interest
11. Jurisdiction
12. Did MII commit breach of the contract?
13. Is the Claim of MII barred by limitation?
14. Counter Claim
15. General
It was agreed to by and between the learned counsel for the parties
that the 1996 Act in stead and in place of 1940 Act shall apply.
PARTIAL AWARD
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 42
The learned arbitrator having heard the parties inter alia on
jurisdictional question initially passed a partial award on 9th June, 2003
determining the same in favour of MII. The decision on points Nos. 6, 8 and
9 were deferred for a period of four months by the learned Arbitrator so as to
enable BSCL to dispose of all claims raised by MII in the meanwhile which
had arisen before reference to the arbitration. The said claims were rejected.
A detailed reasoned statement by ONGC/BSCL referring to each individual
document relied upon were filed in the arbitral proceedings. However, by
reason of the said partial award, as regards points Nos. 1 to 5, 7 and 9A, MII
became entitled to payment from BSCL the following amounts:
"On Point No. 1
US$
1,182,817.69
On Point No. 2
US$
US$
3,133,612.40 &
28,400.00
On Point No. 3
US$
US$
665,039.41 &
54,000.00
On Point No. 4
US$
US$
2,809,100.54 &
2,300,200.00
On Point No. 5
US$
UK Pound
Singapore$
65,207.39
232,604.40 &
548,271.81
On Point No. 7
US$
322,351.87
US$
52,422.51
US$
1,573,466.00
US$
512,187.16
On Point No. 9A
US$
3,330,790.94"
PROCEEDINGS RE: ADDITIONAL AWARD
On point No. 10, MII was held to be entitled to interest on the amount
awarded at the rate of 10% per annum from the date on which the amount
fell due for payment till the date of the partial award and the awarded
amount together with interest was directed to bear interest at the same rate
from the date of the award to the date of payment.
The parties thereafter filed applications under Section 33 of the
Arbitration and Conciliation Act, 1996 alleging that certain claims made by
them had not been dealt with and/ or were omitted from consideration by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 42
learned arbitrator in his partial award.
MII in its application contended:
"(i) While deciding Point No. 4 regarding
Structural Material and Rolling, MII’s claim for
US$ 128,000.00 as contended in paragraph 4.29 of
the Statement of Claim has not been dealt with and
has been omitted from the Award.
(ii) While deciding Point No. 7 regarding
Corporate Income Tax, MII’s claim that BSCL
should be liable to the tax authorities for all further
liabilities for Indian Corporate Income Tax as may
be assessed in respect of the income received by
MII under the Sub-contract as also for all tax
liabilities that may be assessed in respect of any
Award in favour of MII in the present arbitration
proceedings as contained in paragraph 4.84 of the
Statement of Claim has not been dealt with and has
been omitted from the Award.
(iii) In deciding Point No. 7 regarding Corporate
Income Tax, MII has claimed two amounts one of
US$ 804,789.36 being interest @15% per annum
up to 29 February, 1992 paid by MII in respect of
Corporate Income Tax liability to the Tax
authority, and the other on account of principal
amount of tax payment of US$ 1,623,048.00. In
paragraphs 18.17 and 18.18 of the Award, the
learned Arbitrator has in respect of the principal
claim allowed an amount of US$ 1,573,466.00 on
account of Corporate Income Tax and an amount
of US$ 512,187.16 by way of interest. MII has
also claimed interest on these two amounts from
29 February 1992 till payment. This claim for
interest has not been dealt with in the Award and
has been omitted from the Award.
(iv) While deciding Point No. 10 relating to
interest, MII’s claim for interest on amounts paid
but paid late as contained in paragraphs 5.1 and 5.2
has not been dealt with and has been omitted from
the Award."
BSCL raised a preliminary objection in regard to the MII’s claim
under Section 33 of the Act contending that there exists no provision for
making a partial award.
ADDITIONAL AWARD
By reason of the additional award dated 29th September, 2003, the
learned Arbitrator, however, held:
"1. MII’s claim in respect of US$ 128,000.00 is
not accepted.
2. MII’s claim for a declaration that BSCL is liable
to the tax authorities for all further liabilities for
Indian Corporate Income-tax as may be assessed in
future in respect of income received by MII under
the Sub-Contract is allowed only insofar as it
related to MII’s liability, if any, to Corporate
Income-tax, on the amounts awarded to it by a
Partial Award, an Additional Award and a Final
Award.
3. MII is entitled to interest at 10% per annum for
the period from 1 March 1992 to the date of
payment in respect of the principal amount of US$
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 42
1,573,466.00 on account of Corporate Income-tax
and the interest amount of US$ 512,187.16
calculated up to 29 February, 1992.
4. MII is entitled to interest at 10% per annum for
the period of delay in BSCL making payment of
MII’s invoices, that if, for the period from due date
of payment to the date of actual payment. Such
amount will carry interest at 10% per annum from
the date of the Partial Award to the date of its
payment."
The learned Arbitrator rejected the BSCL’s objection in regard to the
maintainability of the said proceeding stating that the same can be a subject
matter for determination of jurisdictional question in a proceeding under
Section 33 of the 1996 Act.
BSCL filed an application under Section 34 of the Act questioning the
said partial award dated 9th June, 2003 as also the additional award dated
29th September, 2003.
FINAL AWARD
The learned Arbitrator thereafter took up the left over matters for his
consideration, viz., points Nos. 6, 8 and 9 observing that ONGC in the
meantime had expressed no interest in participating in the decision making
process at the inter-party level and, thus, arrived at an inference that the
machinery set up under the sub-contract has broken down and it would be
for him to determine the same.
The final award was thereupon passed.
On point No. 6 which related to transportation of pipes, the learned
arbitrator held MII to be entitled to US$ 919,194.32 against BSCL in respect
of the nine barge pipes for transporting them from Mangalore to Bombay.
Point No. 8 related to Change Orders and Extra Work. The learned
Arbitrator awarded MII US$ 305,840.00 as regards Change Order No. 1. As
regards Change Order No. 6, MII was awarded US$72,000.00 against
BSCL. Furthermore, in respect of Change Order No. 9, MII was awarded
US$ 300,000.00 against BSCL. As regards Extra Work, MII was awarded
US$ 4,870,290.96 against BSCL pursuant to the invoices covered under the
said point whereas MII’s claim for US $637,473.00 was rejected.
Point No. 9 related to delays and disruptions. MII was awarded US$
574,000.00 against BSCL in respect of Change Order No. 2. MII was
further awarded US$1,271,820.00 and US$355,000.00 against BSCL under
Change Order Nos. 3 and 7 respectively. As regards increased cost and
expenditure incurred by MII, it was awarded US$8,973,031.00.
So far as the claim of interest is concerned, the learned arbitrator
made the following order:
"MII is entitled to interest on the amounts awarded
under various heads by Final Award. In my
opinion, having regard to the circumstances of the
case, a rate of interest at 10 percent per annum will
be appropriate from the date on which the amount
fell due for payment to the date of this Final
Award. The awarded amount including interest
shall bear the interest at the same rate from the
date of this Final Award to the date of the payment
by BSCL."
The learned arbitrator also awarded US$750,000.00 as costs of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 42
arbitration.
An application was filed by BSCL under Section 34 of the Act
praying for setting aside the final award.
SUBMISSIONS:
Mr. Jayanto Mitra, learned senior counsel and Mr. Pallav Sisodia,
learned counsel appearing on behalf of BSCL made the following
submissions:
(i) The arbitrator had no jurisdiction to make a partial award which is
not postulated under the 1996 Act as an award in piecemeal is
impermissible in law.
(ii) While making the partial award, the learned Arbitrator opined that
involvement of ONGC was imperative for determination of point
Nos. 6,8 and 9, i.e., claims relating to transportation of pipes,
Change Orders and Extra Work and delays and disruptions and,
thus, the final award must be held to be bad in law.
(iii) As the subcontract provided for a back to back contract,
determination of various claims depended upon determination of
interpretative application of the main contract by ONGC wherefor
directions of ONGC were binding on the parties.
(iv) Although US $ 8.8 million has been awarded as regard alleged
delay and disruption of work, no reason, far less any cogent or
sufficient reason, as was mandatorily required in terms of Section
31 of the Act having been assigned, the impugned award is vitiated
in law.
(v) In its award, the learned Arbitrator was bound to determine the
actual loss suffered by the parties and as the same was not
determined, the award cannot be enforced.
(vi) The award as regards loss of profit under various heads is based on
no evidence and, thus, wholly unreasonable.
(vii) The claims made by MII were not only contrary to the terms of
contract but also substantive law of India and were otherwise
opposed to public policy.
(viii) As the contract did not contain any agreed schedule or any
stipulation as to whether the work was required to be finished
within a stipulated period, in view of the fact that the contention of
the MII was that the time was of the essence of contract, the only
remedy available to it in terms of Section 55 of the Indian Contract
Act was to revoke the contract upon giving a notice therefor. In
absence of such a notice, damages could not be claimed. Reliance
in this behalf has been placed on Arosan Enterprises Ltd. Vs.
Union of India and Another [(1999) 9 SCC 449].
(ix) No amount towards extra work was payable to MII having regard
to the payment clauses contained in the contract and in particular
the minutes of the meeting held by the parties on 9th August, 1984.
(x) In view of the clear terms of the contract, ONGC was a necessary
party and the learned Arbitrator committed an error in refusing to
implead it in the proceeding.
(xi) The learned Arbitrator having rejected the claim of the MII in his
partial award dated 9th June, 2003 on the ground that increased
overhead decrease of profit and additional management cost had
not been raised before reference to arbitration and, thus, was
beyond the scope of arbitral reference, could not have determined
the self same question in his final award. The objection and the
award for US$ 8.8 million had not been taken into consideration
and, thus, the same is liable to be set aside.
(xii) The learned Arbitrator could not have awarded the said sum solely
on the basis of the opinion of one Mr. D.J. Parson who did not
have any personal knowledge of the facts of the case, particularly
in view of the fact that no evidence was adduced as regards
sufferance of actual loss by MII. Mechanical application of
Emden Formula was also wholly uncalled for and no award could
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 42
be made relying on or on the basis thereof.
(xiii) So far as the claim of extra work is concerned, the learned
Arbitrator has wrongly allowed the claim of MII in respect of
invoice Nos. 2806470 to 2806475 although due date for payment
of the said amount fell after the commencement of reference to
arbitration and, thus, as no dues existed on that date, the Arbitrator
had no jurisdiction to make an award in relation thereto.
(xiv) As regards "exchange loss", MII’s claim was allowed without any
amendment to the statement of claim. Claim of MII was wrongly
allowed by the learned Arbitrator for entire value of the invoices
without any deduction as delay in making payment by BSCL to
MII on account of delay in receiving payment from ONGC has no
relevance and in any event was contrary to the terms of the
contract.
The learned Arbitrator had also not taken into consideration that in
terms of the contract, foreign exchange rate was frozen at the rate
of Rs. 100 X 8.575 Dollars as was applicable on 9th August, 1984.
(xv) The claim for US$ 2.3 million was outside the scope of reference
to arbitration as no demand therefor was made. Such a claim was
made for the first time only in the statement of claim.
(xvi) In terms of Clause 37 of the contract entered into by and between
ONGC and BSCL, no award by way of damage was payable.
Similar provision was also contained in the subcontract entered
into by and between the parties.
(xvii) As MII was to compensate for the supply of materials by BSCL
subsequently, no award for a sum of US$ 2.3 million could be
made.
(xviii) As no invoice in respect of the claim of US$ 28,400 on account of
an additional barge trip to transport the ED Temporary Deck had
been raised, the learned Arbitrator had no jurisdiction to decide the
same.
(xix) The award under the said head for a sum of US$ 54,000 on account
of additional survey of WIS and WI9 pipeline was not an arbitrable
dispute being clearly outside the purview of the arbitration
proceedings.
(xx) Relying on or on the basis of American Institute of Steel
Construction (AISC) Code as a base for measurement being
contrary to the contract, the award is liable to be set aside..
(xxi) (a) Re: Buoyancy Tanks in respect of ED and EE Jackets
As BSCL had paid MII for fabrication of the same buoyancy tanks
and the buoyancy tanks were the same which were used for W18,
W19 and W110 and N3 Platform, claim on the said account once
over again was not maintainable ignoring the the evidence of Mr.
S.K. Mukherjee (RW-1).
(b) Tie Down and Sea Fastening
As Tie Down materials are required for safe transportation of
structures allotted on transportation barge, the learned Arbitrator
erred in allowing the claim of MII as they are not permanent part
of jacket decks of any platform.
(c ) Substitution of Materials
The learned Arbitrator committed a serious error in not taking into
account the material evidence adduced by BSCL to the effect that
MII was instructed to substitute the specified materials with
available material at no additional cost of fabrication.
In terms of the contract, it was for the MII to procure the materials
which were to be reimbursed by BSCL. The claim for US$
20832.108 was based on fabrication charges on account of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 42
increased tonnage for material substitution for W18, W19, W110
and N3 jackets and piles as well as ED and EE jackets and, thus, as
the learned Arbitrator had allowed claim only to the extent of
fabrication, the amount claimed by MII could not have been
allowed in toto.
Mr. Dipankar Gupta, learned senior counsel appearing on behalf of
MII, on the other hand, submitted that no case has been made out for setting
aside the award of the learned Arbitrator.
In reply to the submissions made on behalf of BSCL, it was urged:
Re. Increased Overhead Decrease of Profit and Additional Management
Cost
The amount has been awarded on the basis of statement of Mr. D.J.
Parsons. The contract clearly provided that W18, W19, W110 and N3
platforms were to be completed by 30th December, 1985 whereas ED and EE
platforms were to be commissioned in February, 1986. It is not the case of
MII that the time was of the essence of contract and, thus, in terms of
Section 55 of the Indian Contract Act, damages were payable. Even in terms
of the main contract between BSCL and ONGC, time was not of the essence
of the contract. The contract contained clauses for extension of time and
liquidated damages which is also indicative of the fact that time was not of
the essence of the contract and, thus, damages for delay is permissible in law
in view of the decision of this Court in Hind Construction v. State of
Maharashtra [(1979) 2 SCC 70]
Change Order Nos. 2, 3 and 7 covered compensation under various
heads as specified therein. The award of the learned Arbitrator clearly
shows that additional costs had been incurred by MII and, thus, the award
cannot be faulted. The partial award did not deal with the said claims. The
dispute was specifically referred to arbitration in terms of notice dated 10th
April, 1998. The quantification of damages being a matter of evidence and
proof, no case has been made out for interference with the award particularly
in view of the fact that BSCL had never raised any objection as regards the
jurisdiction of the Arbitrator.
Reliance on the Emden Formula cannot be said to be against the law
prevailing in India as Sections 55 and 73 of the Indian Contract Act provided
only for entitlement to compensation and not the mode and manner in which
such compensation is to be quantified.
Clause 37 of the Main Contract between ONGC and BSCL has no
application as MII’s claim is not for any consequential damage but for the
direct losses occasioned by BSCL’s breach of contractual duty to honour its
time bound commitments. The said clause cannot be extended to the
obligations towards MII under the sub-contract as ONGC has no role to play
in respect of the breach of its obligations towards it by BSCL under the sub-
contract.
Re: Partial Award
A partial award is in effect and substance an interim award within the
meaning of Section 31(6) and 2(c) of the Act and, thus, the validity of the
partial award is not open to question.
Re: Exchange Loss
Clause 4.0 of contract only relates to payment for transportation and
installation and BSCL did not make any payment to MII despite receipt of
the whole amount from ONGC except an amount of Rs. 12,70,290/-. In any
event, Clause 4.0 has no relevance to the exchange loss dispute. BSCL
acted contrary to the agreed terms as it made payment upon applying the
fixed exchange rate of Rs. 100 = US$8.575. BSCL was to pay to MII the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 42
amount as per the current rate, only on reconciliation MII was to refund the
excess amount to BSCL which ensured that exchange loss would be shared
by both the parties.
Re: Uninvoiced Claims
BSCL never raised any objection before the Arbitrator that the claim
for US$ 2,300,200 for procurement of structural material could not be raised
in view of the provisions contained in Section 16 of the 1996 Act. Invoice
in any event, is merely a basis for claim and such a claim may be raised in
correspondences as also in the meetings. The claim for US$ 2,300,200 was
not strictly claim for damages, as in terms of the contract BSCL was
required to procure the steel and as it being not in a position to do so, MII
agreed to procure the same on its behalf if BSCL would agree to pay US$
2,300,200 to cover MII’s cost for accelerated procurement and other costs.
This offer was the subject matter of correspondence between the parties. As
no dispute was raised to recover the same amount from BSCL, procurement
job was undertaken. The finding arrived at by the learned Arbitrator in this
behalf is entirely a finding of fact. Reference to Clause 5 of the Contract was
wholly irrelevant. This clause provides that BSCL shall procure suitable
steel for "jackets’ on replacement basis for MII purchased steel. BSCL did
not procure the required amount of steel to replace the structural materials
that MII provided from its inventory as an accommodation to BSCL. MII did
so on the understanding that the structural material removed from MII’s
inventory would be promptly replaced by BSCL. BSCL did not replace the
material.
Re: Method of Measurement
Clause 23.1.1 (a) & (c) of the Main Contract between BSCL and
ONGC has no application as the same covers payment for ’structural
material’ which is an altogether different claim being Claim No. 4. The
claim was towards labour charges for fabrication of structures, labour
charges and not claim for cost of material. AISC Code applied in relation to
the fabrication job is as under:
"The scheme of the Contract provides in relation to
Fabrication and the application of AISC Code is
explained below:
(i) the sub-contract provides total estimated tonnage of
18, 178 ST with following break-up:
ED?EE Platforms 6078 ST (page 166 I.A. no.2 Vol.2)
WI8, WI9, WI10 and N3 platforms
12,100 ST/ 18, 178 ST (page 371 I.A. no.2 vol.2)"
Re: Buoyancy Tanks for ED and EE Jackets
MII’s claim is for labour cost at the rate of US$ 1067 per ST involved
for fabrication work in the refurbishment of the Buoyancy Tanks. The
finding of the Arbitrator is a finding of fact inter alia based on the admission
of the witness, namely, Shri S.K. Mukherjee, who was examined on behalf
of BSCL
Re: Tie Down and Sea Fastening
In offshore construction, jackets and decks are fabricated onshore and
then they are transported on barges to the offshore location for installation.
Jobs pertaining to Tie Down and Sea Fastening required substantial
fabrication work and no claim has been made towards costs of welding the
Tie Downs and Sea Fasteners to the deck.
Clause 2 of the Contract would have no application to the instant case
as it provides only for a stage payment on milestone basis. But, clause
2.1(a)(i) which substantially covers sea fastening job as part of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 42
fabrication contract would be applicable. BSCL had not been able to show
that the fabrication of Tie Down and Sea Fastening materials were included
within the scope of transportation and not as a separate item under the head
’fabrication’.
Re: Substitution
It was for BSCL in terms of the sub-contract to procure and supply all
materials but as it was not in a position to do so, MII on instructions of
BSCL used available materials which was having larger thickness and
weight vis-a-vis those specified in the ONGC’s specifications. The same
having been approved both by the Engineer and ONGC, MII was entitled to
compensation towards the labour charges at the rate of US$ 1067 per ST.
Re: Extra Work Invoice Nos. 2806470 to 2806475
The invoices which were contained in Annexure 9 to MII’s statement
of claims were substituted by new documents in terms whereof the due date
of invoice was corrected to 9th March, 1989 and, thus, fall due for payment
prior to the notice dated 10th April, 1989 invoking arbitration. The payment
of extra work became due when the work was performed and moreover, the
invoices in question did not specify any date for payment.
Re: Interest
The ground has been taken only in the supplementary affidavit filed
on behalf of BSCL on 21st September, 2004 beyond a period of three months
as specified in Section 34 of the Act. The Arbitrator has awarded the
principal amount and interest thereon upto the date of award and future
interest thereupon which do not amount to award on interest on interest as
interest awarded on the principal amount upto the date of award became the
principal amount which is permissible in law.
CHALLENGE TO AWARD: LEGAL SCOPE OF
Section 2(1)(b) of the 1996 Act reads as under:
"2(1)(b) "arbitration agreement" means an agreement
referred to in section 7"
In terms of the 1996 Act, a departure was made so far as the
jurisdiction of the court to set aside an arbitral award is concerned vis-‘-vis
the earlier Act. Whereas under Sections 30 and 33 of the 1940 Act, the
power of the court was wide, Section 34 of the 1996 Act brings about certain
changes envisaged thereunder.
Section 30 of the 1940 Act reads, thus:
"Grounds for setting aside award \026 An award shall not be
set aside except on one or more of the following grounds,
namely:
(a) That an arbitrator or umpire has misconducted
himself or the proceedings;
(b) That an award has been made after the issue of an
order by the Court superseding the arbitration or after
arbitration proceedings have become invalid under Sec
35;
(c) That an award has been improperly procured or is
otherwise invalid."
The Section did not contain expression "error of law\005.". The same
was added by judicial interpretation. While interpreting Section 30 of the
1940 Act, a question has been raised before the courts as to whether the
principle of law applied by the arbitrator was (a) erroneous or otherwise or
(b) wrong principle was applied. If, however, no dispute existed as on the
date of invocation, the question could not have been gone into by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 42
Arbitrator.
CHANGES UNDER THE NEW ACT
The 1996 Act makes a radical departure from the 1940 Act. It has
embodied the relevant rules of the modern law but does not contain all the
provisions thereof. The 1996 Act, however, is not as extensive as the
English Arbitration Act.
Different statutes operated in the field in respect of a domestic award
and a foreign award prior to coming into force of the 1996 Act, namely, the
1940 Act, the Arbitration (Protocol and Convention) Act, 1937 and the
Foreign Awards (Recognition and Enforcement) Act, 1961. All the
aforementioned statutes have been repealed by the 1996 Act and make
provisions in two different parts, namely, matters relating to domestic award
and foreign award respectively.
Vis-‘-vis Grounds for setting aside the award:
After the 1996 Act came into force, under Section 16 of the Act the
party questioning the jurisdiction of the arbitrator has an obligation to raise
the said question before the arbitrator. Such a question of jurisdiction could
be raised if it is beyond the scope of his authority. It was required to be
raised during arbitration proceedings or soon after initiation thereof. The
jurisdictional question is required to be determined as a preliminary ground.
A decision taken thereupon by the Arbitrator would be subject matter of
challenge under Section 34 of the Act. In the event, the arbitrator opined
that he had no jurisdiction in relation thereto an appeal thereagainst was
provided for under Section 37 of the Act.
The 1996 Act makes provision for the supervisory role of courts, for
the review of the arbitral award only to ensure fairness. Intervention of the
court is envisaged in few circumstances only, like, in case of fraud or bias by
the arbitrators, violation of natural justice, etc. The court cannot correct
errors of the arbitrators. It can only quash the award leaving the parties free
to begin the arbitration again if it is desired. So, scheme of the provision
aims at keeping the supervisory role of the court at minimum level and this
can be justified as parties to the agreement make a conscious decision to
exclude the court’s jurisdiction by opting for arbitration as they prefer the
expediency and finality offered by it.
However, this Court, as would be noticed hereinafter, has the occasion
to consider the matter in great detail in some of its decisions.
In Primetrade AG v. Ythan Ltd. [(2006) 1 All ER 367], jurisdictional
issue based on interpretation of documents executed by the parties fell for
consideration having regard to the provisions of the Carriage of Goods by
Sea Act, 1992. It was held that as the appellant therein did not become
holder of the bills of lading and alternatively as the conditions laid down in
Section 2(2) were not fulfilled, the arbitrator had no jurisdiction to arbitrate
in the disputes and differences between the parties.
Vis-‘-vis the duty to assign reasons
Another important change which has been made by reason of the
provisions of the 1996 Act is that unlike the 1940 Act, the Arbitrator is
required to assign reasons in support of the award. A question may
invariably arise as to what would be meant by a reasoned award.
In Bachawat’s Law of Arbitration and Conciliation, Fourth Edition,
pages 855-856, it is stated:
"\005’Reason’ is a ground or motive for a belief or a course
of action, a statement in justification or explanation of
belief or action. It is in this sense that the award must
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 42
state reasons for the amount awarded.
The rationale of the requirement of reasons is that
reasons assure that the arbitrator has not acted
capriciously. Reasons reveal the grounds on which the
arbitrator reached the conclusion which adversely affects
the interests of a party. The contractual stipulation of
reasons means, as held in Poyser and Mills’ Arbitration
In Re, "proper, adequate reasons". Such reasons shall not
only be intelligible but shall be a reason connected with
the case which the court can see is proper. Contradictory
reasons are equal to lack of reasons.
The meaning of the word " reason" was
exaplained by the Kerala High Court in the contest of a
reasoned award\005
"Reasons are the links between the materials on
which certain conclusions are based and the actual
conclusions."\005
A mere statement of reasons does not satisfy the
requirements of s.31(3) . Reasons must be based upon
the materials submitted before the arbitral tribunal. The
tribunal has to give its reasons on consideration of the
relevant materials while the irrelevant material may be
ignored\005
Statement of reasons is mandatory requirement
unless dispensed with by the parties or by a statutory
provision."
In Konkan Railway Corporation Ltd. v. Mehul Construction Company
[(2000) 7 SCC 201], this Court emphasized the mandatoriness of giving
reasons unless the arbitration agreement provides otherwise.
Public Policy
In Renusagar Power Co. Ltd. v. General Electric Co. [(1994) Supp 1
SCC 644], this Court laid down that the arbitral award can be set aside if it is
contrary to (a) fundamental policy of Indian Law, (b) the interests of India;
or (c) justice or morality. A narrower meaning to the expression ’public
policy’ was given therein by confining judicial review of the arbitral award
only on the aforementioned three grounds. An apparent shift can, however,
be noticed from the decision of this Court in Oil and Natural Gas
Corporation Ltd. v. Saw Pipes Ltd. (for short ’ONGC’)[(2003) 5 SCC 705].
This Court therein referred to an earlier decision of this Court in Central
Inland Water Transport Corporation Ltd. v. Brojo Nath Ganguly [(1986) 3
SCC 156] wherein the applicability of the expression ’public policy’ on the
touchstone of Section 23 of the Indian Contract Act and Article 14 of the
Constitution of India came to be considered. This Court therein was dealing
with unequal bargaining power of the workmen and the employer and came
to the conclusion that any term of the agreement which is patently arbitrary
and/ or otherwise arrived at because of the unequal bargaining power would
not only be ultra vires Article 14 of the Constitution of India but also hit by
Section 23 of the Indian Contract Act. In ONGC (supra), this Court, apart
from the three grounds stated in Renusagar (supra), added another ground
thereto for exercise of the court’s jurisdiction in setting aside the award if it
is patently arbitrary.
Such patent illegality, however, must go to the root of the matter. The
public policy violation, indisputably, should be so unfair and unreasonable
as to shock the conscience of the court. Where the Arbitrator, however, has
gone contrary to or beyond the expressed law of the contract or granted
relief in the matter not in dispute would come within the purview of Section
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 42
34 of the Act. However, we would consider the applicability of the
aforementioned principles while noticing the merit of the matter.
What would constitute public policy is a matter dependant upon the
nature of transaction and nature of statute. For the said purpose, the
pleadings of the parties and the materials brought on record would be
relevant to enable the court to judge what is in public good or public interest,
and what would otherwise be injurious to the public good at the relevant
point, as contradistinguished from the policy of a particular government.
[See State of Rajasthan v. Basant Nahata, (2005) 12 SCC 77].
In ONGC (supra), this Court observed:
"31. Therefore, in our view, the phrase "public
policy of India" used in Section 34 in context is
required to be given a wider meaning. It can be
stated that the concept of public policy connotes
some matter which concerns public good and the
public interest. What is for public good or in public
interest or what would be injurious or harmful to
the public good or public interest has varied from
time to time. However, the award which is, on the
face of it, patently in violation of statutory
provisions cannot be said to be in public interest.
Such award/judgment/decision is likely to
adversely affect the administration of justice.
Hence, in our view in addition to narrower
meaning given to the term "public policy" in
Renusagar case10 it is required to be held that the
award could be set aside if it is patently illegal.
The result would be \027 award could be set aside if
it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if
the illegality is of trivial nature it cannot be held
that award is against the public policy. Award
could also be set aside if it is so unfair and
unreasonable that it shocks the conscience of the
court. Such award is opposed to public policy and
is required to be adjudged void."
We are not unmindful that the decision of this Court in ONGC (supra)
had invited considerable adverse comments but the correctness or otherwise
of the said decision is not in question before us. It is only for a larger Bench
to consider the correctness or otherwise of the said decision. The said
decision is binding on us. The said decision has been followed in a large
number of cases. [See The Law and Practice of Arbitration and Conciliation
by O.P. Malhotra, Second edition, page 1174.]
Before us, the correctness or otherwise of the aforesaid decision of
this Court is not in question. The learned counsel for both the parties
referred to the said decision in ex tenso.
We, therefore, would proceed on the basis that ONGC (supra) lays
down the correct principles of law.
SUPERVISORY JURISDICTION
We may consider the submissions of the learned counsel for the
parties on the basis of the broad principles which may be attracted in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 42
instant case, i.e., (i) whether the award is contrary to the terms of contract
and, therefore, no arbitrable dispute arose between the parties; (ii) whether
the award is in any way violative of the public policy; (iii) whether the
award is contrary to the substantive law in India, viz., Sections 55 and 73 of
the Indian Contract Act; (iv) whether the reasons are vitiated by perversity in
evidence in contract ; (v) whether adjudication of a claim has been made in
respect whereof there was no dispute or difference; or (vi) whether the
award is vitiated by internal contradictions.
For the aforementioned purpose, it would be necessary to see as to
what law the arbitrator was required to apply.
We may, therefore, consider the legal submissions before adverting to
the merit of the matter.
VALIDITY OF THE ’PARTIAL AWARD’
The 1996 Act does not use the expression "partial award". It uses
interim award or final award. An award has been defined under Section 2(c)
to include an interim award. Sub-section (6) of Section 31 contemplates an
interim award. An interim award in terms of the said provision is not one in
respect of which a final award can be made, but it may be a final award on
the matters covered thereby, but made at an interim stage.
The learned arbitrator evolved the aforementioned procedure so as to
enable the parties to address themselves as regard certain disputes at the first
instance. As would appear from the partial award of the learned arbitrator,
he deferred some claims. He further expressed his hope and trust that in
relation to some claims, the parties would arrive at some sort of settlement
having regard to the fact that ONGC directly or indirectly was involved
therein. While in relation to some of the claims, a finality was attached to
the award, certain claims were deferred so as to enable the learned arbitrator
to advert thereto at a later stage. If the partial award answers the definition
of the award, as envisaged under Section 2(c) of the 1996 Act, for all intent
and purport, it would be a final award. In fact, the validity of the said award
had also been questioned by BSCL by filing an objection in relation thereto.
We cannot also lose sight of the fact that BSCL did not raise any
objection before the arbitrator in relation to the jurisdiction of the Arbitrator.
A ground to that effect has also not been taken in its application under
Section 34 of the Act. We, however, even otherwise do not agree with the
contention of Mr. Mitra that a partial award is akin to a preliminary decree.
On the other hand, we are of the opinion that it is final in all respects with
regard to disputes referred to the arbitrator which are subject matter of such
award. We may add that some arbitrators in stead and in place of using the
expression "interim award" use the expression "partial award". By reason
thereof the nature and character of an award is not changed. As, for
example, we may notice that in arbitral proceedings conducted under the
Rules of Arbitration of the International Chamber of Commerce, the
expression "partial award" is generally used by the arbitrators in place of
interim award. In any view of the matter, BSCL is not in any way
prejudiced. We may state that both the partial award and the final award are
subject matter of challenge under Section 34 of the Act.
Section 33 of the Act empowers the arbitral tribunal to make
correction of errors in arbitral award, to give interpretation of a specific
point or a part of the arbitral award, and to make an additional award as to
claims, though presented in the arbitral proceedings, but omitted from the
arbitral award. Subsection (4) empowers the arbitral tribunal to make
additional arbitral award in respect of claims already presented to the
tribunal in the arbitral proceedings but omitted by the arbitral tribunal
provided
1. There is no contrary agreement between the parties to
the reference;
2. A party to the reference ,with notice to the other party
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 42
to the reference ,requests the arbitral tribunal to make
the additional award;
3. Such request is made within thirty days from the receipt
of the arbitral award;
4. The arbitral tribunal considers the request so made
justified; and
5. Additional arbitral award is made within sixty days
from the receipt of such request by the arbitral tribunal
The additional award, in our opinion, is not vitiated in law.
DELAY AND DISRUPTION
Operative facts
According to the applicants, the contract entered into by and between
MII and BSCL did not provide for any period of completion. MII, on the
other hand, states that at that time when the contract was entered into it was
supposed to be performed by 30th December, 1985 as would appear
hereinafter:
"For Jackets and Temporary Decks (for platforms WI-8,
WI-9, WI-10 and N-3), the completion period is 30 April
1985 and for Decks and Helidecks ( for platforms WI -8,
WI-9, WI-10 and N-3) the completion date is 30
December 1985. Clause (ii) in the ’Schedule of
Completion of Well Platforms’ states: "\005the completion
dates\005.will be reckoned for purpose of L/d."
In terms of the provisions of the contract the jobs in respect of WI-8,
WI-9, WI-10 and N-3 were to be performed within the said period.
A stipulation for commissioning of ED and EE platforms within a
time frame has also been mentioned, i.e., February, 1986 as would appear
from the following:
"1. The agreed for commissioning of platforms ED & EE
is by end of February 1986, subject to the provisions of
this Contract."
MII served a notice on 10th April, 1998 invoking the arbitration
agreement. The same would not mean that it should have repudiated the
contract as soon as 20 months schedule fixed by the contract expired. Delay
and disruptions might have occurred for various reasons. In the instant case,
therefore, the matter would be covered by the second part of Section 55 of
the Indian Contract Act providing that where the parties did not intend time
to be of the essence of the contract, the contract was not voidable, but the
promisee was entitled to compensation for loss occasioned. For the
aforementioned purpose, no notice was required to be served. In any event,
the contract provided for extension of time, as would appear from clause
27(ii) and the relevant portions of clause 28 which read as under:
"27 (ii) Should be amount of extra work, if any, which
Contractor is required to perform under clause 24 to 26
ants, fairly entitled Contractor to extension of time
beyond the scheduled date for completion of either the
whole or part of the works or for such extra work as the
case may be, Company and Contractor shall mutually
discuss and decide extensions of time, to be granted to
Contractor and the revised schedule for completion of the
Works.
28 (i) Subject any requirements in the Contract
Specifications as to the completion of any portion of the
work before completion of the whole and subject to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 42
other provisions contained in the Contract, the Works
shall be completed in accordance with the agreed
schedule as indicated in Appendix-II. Company may, if
the exigencies of the works or other projects so required
amend the completion schedule and/or phase out
completion.
28(iii)\005No extension in completion shall be permitted
unless authorized in writing by Company as a "Variation
in completion schedule" or as otherwise specified in the
Contract. In any case, no portion of the works shall
extend beyond the commencement of the 1986
monsoon."
The parties, furthermore, agreed for payment of liquidated damages,
as would appear from clause 28(v)(a) which reads as under:
"a) recovery is its sole and only remedy for
delayed completion of work by Contractor, as
ascertained and agreed liquidated damages, and not by
way of penalty, as sue equivalent to 2.5% of the
Contract Price for the item which is delayed, for each
month of delay (or prorate thereof for part of a month),
beyond the scheduled completion date, subject to a
maximum of 7.5 % of the said Contract price. Such
liquidated damages shall be loveable after allowing a
grace period of 15 days. The monsoon peril requiring
which no work can be carried out orders, shall be
excluded for the purpose of determining the quantum of
delay in completion of work.."
Moreover, the contract itself contains provisions for extension of its
terms and payment of damages in case of delay in execution of the contract.
The claim for increased overhead and decreased profit and additional
project management cost flows out of the same operative facts as the delay
and disruption change in respect of Change Order Nos. 2, 3, and 7.
We may at the outset point out that the question as regards the effect
of the said claims which were not considered in the first round of the arbitral
proceedings shall be dealt with a little later.
So far as the Change Order No. 2 is concerned, the learned arbitrator
has accepted the contention of the MII that it had to incur additional cost due
to delay in receipt of equipment and materials supplied. In his Final Award,
the learned arbitrator noticed:
"\005It appears that BSCL accepted and
acknowledged that MII had incurred additional
cost on account of this delay occasioned by
BSCL\005"
So far as, Change Order No. 3 is concerned, the learned arbitrator in
paragraph 67.2 of the Final award noticed as under:
"\005This was followed by a meeting on 7-8 October
1986 attended by the representatives of ONGC,
EIL, BSCL and MII, during which ONGC advised
BSCL that BSCL should absorb one half the
mobilization and demobilization costs of MII’s
marine equipment, since the delay was occasioned
by BSCL in completing the helidecks\005"
So far as Change Order No. 7 is concerned, the learned Arbitrator has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 42
recorded in paragraph 68.1 of the Final Award as under:
"\005This Change Order was accepted by BSCL and
ONGC but MII has received no payment\005"
It was further recorded in paragraph 68.4 of the Final Award:
"\005Even after the work was completed, there was
a meeting on 16-17 June, 1987 at which ONGC
informed that the Change Order was agreed to in
principle\005"
So far as the claim of compensation in addition to the said Change
Order Nos. 2,3 and 7 is concerned, the statement of claim of MII is as under:
"4.65: The BSCL delays and disruptions required
McDermott to alter the fabrication and installation
sequence to match deliveries of equipment. This
precluded McDermott performing certain activities as
planned in the Subcontract. Change order No.2 relates to
additional cost incurred by McDermott due to delay in
receipt of equipment and material supplied by BSCL.
BSCL’s delivery of the equipment was upto seventeen
months late. During this period, McDermott continued to
fabricate the decks installing material as it became
available. The delay resulted in additional costs to
McDermott due to change order with cost effect of
US$574,000.00. BSCL has failed and neglected to make
payment of the invoice for this change order.
4.66: Change order no.3 relates to mobilization and
demobilization of Derrick Barge 26 to complete BSCL
work in the 1986/1987 construction season. The
Subcontract price was based on mobilization and
demobilization of a single barge in the 1984/1985 and
1985/1986 construction seasons only and performance of
the offshore scope of work in a continuous sequence.
Due to BSCL delays, the WI-8, WI-9, WI-10 and N3
decks and helidecks were not completed for installation
during the 1985/1986 work season. Further, the WI-7 to
WI-8 pipeline and five risers could not be installed due to
unavailability of material and lack of access to the EB
and EC jackets, which were still under construction. In
the 1986/1987 construction season, Mcdermott used
Derrick Barge 27, which was already in the field, to
install the WI-8, WI-9, WI-10 and N3 decks.
Mcdermott also had to mobilize Derrick Barge 26 in the
same construction season for installation of the WI-7 to
WI-8 pipeline and associated risers. On the
instructions of BSCL, Mcdermott mobilized Derrick
Barge 26 in February 1987. Derrick Barge 26 installed
the pipelines and risers and was demobilized from the
field on 10 March 1987. For the
mobilization/demobilization of Derrick Barge 26 for the
1986/1987 construction season work, McDermott
submitted a change order to BSCL with cost effect of US
$ 1,271,820.00. BSCL has failed and neglected to make
payment of the invoices for this change order.
4.67 Change Order no.7 relates to offshore installation
or late-supplied equipment on the WI-8 , WI-9, WI-10
and N3 decks. As early as February,1986, the parties
contemplated that certain BSCL-supplied equipment
planned for installation by McDermott onshore would
have to be installed offshore due to the projected late
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 42
delivery. The cost of installing equipment off shore is
much US $ 1,140,705.00. On 6 November 1986,
McDermott reviewed the list of outstanding equipment
and revised its change order to US $ 355,000.00. On the
instructions of BSCL, McDermott performed the change
order work and installed outstanding equipment offshore.
BSCL has failed and neglected to make payment of the
invoice for this change order."
In the Final Award also the learned arbitrator noticed:
"The discussion covering earlier issues establishes that
BSCL was guilty of delays and disruptions. Proceeding
from there, the question is whether MII is entitled to an
amount on account of increased overhead and loss of
profit and additional project management costs? MII
states that construction law recognizes that construction
contractor incurs two general jobs of costs in the course
of its operation; the operating costs that are attributable to
a particular project, and costs such as overhead that are
expended for the performance of the business as a
whole, including t‘he particular project. Consequently,
construction law recognizes that owner caused delay
entitles the contractor to recover from the owner the
increased overhead and loss of profit as part of damages.
Reference has been made to Hudson’s building and
Engineering Contracts. Article 8.176-91 pp. 1074-81
(11th edn.), Molly J.B., "A formula for Success". Three
formulae have been evolved for computation of a claim
for increased overhead and loss of profit due to
prolongation of the works : the Hudson Formula; The
Emden Formula and Eicheay Formula. Of these three, the
Emden Formula is the one widely applied and which has
received judicial support in a number of cases."
Section 55 of the Indian Contract Act
Section 55 of the Indian Contract Act reads as under:
"55. When a party to a contract promises to do a
certain thing at or before a specified time, or
certain things at or before specified time, and fails
to do any such thing at or before the specified
time, the contract, or so much of it as has not been
performed, becomes voidable at the option of the
promisee, if the intention of the parties was that
time should be of the essence of the contract.
If it was not the intention of the parties that time
should be of the essence of the contract, the
contract does not become voidable by the failure to
do such thing at or before the specified time; but
the promisee is entitled to compensation from the
promisor for any loss occasioned to him by such
failure.
If, in case of a contract voidable on account of the
promisor’s failure to perform his promise at the
time agreed, the promisee accepts performance of
such promise at any time other than that agreed,
the promisee cannot claim compensation for any
loss occasioned by the non-performance of the
promise at the time agreed, unless, at the time of
such acceptance, he gives notice to the promisor of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 42
his intention to do so."
In Arosan Enterprises Ltd. (supra), the law was stated in the following
terms:
"13. These presumptions of the High Court in our
view are wholly unwarranted in the contextual
facts for the reasons detailed below but before so
doing it is to be noted that in the event the time is
the essence of the contract, question of there being
any presumption or presumed extension or
presumed acceptance of a renewed date would not
arise. The extension if there be any, should and
ought to be categorical in nature rather than being
vague or on the anvil of presumptions. In the event
the parties knowingly give a go-by to the
stipulation as regards the time- the same may have
two several effects: (a) parties name a future
specific date for delivery, any (b) parties may also
agree to the abandonment of the contract- as
regards (a) above, there must be a specific date
within which delivery has o be effected and in the
event there is no such specific date available in the
course of conduct of the parties, then and in that
event, the courts are not left with any other
conclusion but a finding that the parties themselves
by their conduct have given a go-by to the original
term of the contract as regards the time being the
essence of the contract. Be it recorded that in the
event the contract comes within the ambit of
Section 55, Contract Act, the remedy is also
provided therein\005"
It was further observed:
"19. Turning now on to the issue of duty to speak,
can it be said that silence on the part of the buyer
in not replying to the letters dated 15-11-1989, 20-
11-1989, 24-11-1989, 4-12-1989 and 20-12-1989
only shows that the buyer was not willing to
extend the delivery period after 15-11-1989 \027 the
answer cannot but be in the negative, more so by
reason of the fact that fixation of a second delivery
date by the Appellate Bench of the High Court as
noticed above, cannot be termed to be in
accordance with the law. There was, in fact, a duty
to speak and failure to speak would forfeit all the
rights of the buyer in terms of the agreement.
Failure to speak would not, as a matter of fact,
jeopardise the seller’s interest neither would the
same authorise the buyer to cancel the contract
when there have been repeated requests for acting
in terms of the agreement between the parties by
the seller to that effect more so by reason of a
definite anxiety expressed by the buyer as
evidenced in the intimation dated 8-11-1989 and as
found by the arbitrator as also by the learned
Single Judge."
We, therefore, are of the opinion that in the instant case the second
part of Section 55 of the Indian Contract Act would be attracted and not the
first part.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 42
Whether time was the essence of contract
The question which, further, arises for consideration is as to whether
the Respondents having proceeded on the basis that time was of the essence
of the contract, it was bound to issue a notice of repudiating the contract
subject to reservation as regards its claim of damages. MII, however, states
that it had never raised a contention that the time was of the essence of the
contract, but the claim arises in view of the delay caused in completion of
the contract for a period of 34 months and consequent escalation of costs.
The price payable in terms of the sub-contract did not adequately cover
increased costs expended by MII. On a plain reading of the provisions of
Section 55 of the Indian Contract Act, it is evident that as the parties did not
intend that time was to be of the essence of the contract on the expiry
whereof the contract became voidable at the instance of one of the parties,
but by reason thereof the parties shall never be deprived of damages.
We may notice that the BSCL had never pleaded before the Arbitrator
that the time was of the essence of the contract. In Construction contracts
generally time is not of the essence of the contract unless special features
exist therefor. No such special features, in the instant case, has been brought
to our notice.
The learned arbitrator proceeded on the basis that the BSCL had
accepted and acknowledged that no additional cost on account of delay was
occasioned in completing the helidecks. MII is found to have incurred
additional cost for offshore installation. The learned arbitrator has also
found that MII had not received any payment on account of such increased
cost. The compensation under the said head of claim was only in addition to
Change Order Nos. 2,3 and 7 to which we shall advert to a little later.
This Court in Hind Construction v. State of Maharashtra [(1979) 2
SCC 70] stated:
"7. The question whether or not time was of the
essence of the contract would essentially be a question of
the intention of the parties to be gathered from the terms
of the contract. [See Halsbury’s Laws of England, 4th ed.,
Vol.4, para 1179]."
"8. Even where the parties have expressly proided that
time is of the essence of the contract such a stipulation
will have to be read along with other provisions of the
contract and such other provisions may, on construction
of the contract, exclude the inference that the completion
of the work by a particular date was intended to be
fundamental. [See Lamprell v. Billericay Union (19849)
3 Exch 283, 308; Webbv. Hughes (1870) LR 10 Eq 281;
Charles Rickards Ltd. v. Oppenheim (1950) 1 KB 616]."
UNINVOICED CLAIMS:
The principal question which arises for consideration is whether
uninvoiced claims could be a subject matter of dispute. While dealing with
the claims falling within the purview of the partial award, the arbitrator
noticed:
"23. Interruption of WI-9 to WI-S Pipeline laying (US$
115,087.50)
The Statement of claim by MII mentions that an amount
of US $ 10,671,340.00 on account of delay and
disruption expenses and costs are claimed. Admittedly,
they had not yet been invoiced when the reference to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 42
arbitration was made. It is not clear what are the specific
claims included within that sum. If they had not been
invoiced, it cannot be said that they remained unpaid, and
that therefore, a difference or dispute had arisen between
the parties when the reference to arbitration was made."
It was further noticed:
"Reference has been made to the claim in respect of the
standby of the MII transportation spread, additional
compensation on account of the construction of
temporary emergency helidecks, the extended stay of MII
personnel and a claim in respect of Lay Barge 26. All
these claims will be considered after it has been
satisfactorily proved that invoices in respect of each of
these claims were issued and had become due for
payment before the reference to arbitration was made and
also meanwhile the arbitration record will have received
the statement of ONGC/BSCL in respect of Change
Order Proposals Nos. 2,3,7 and 8. Therefore, the
consideration of these claims is deferred."
No invoice was raised by MII for the following claims:
(i) Claim of US$ 2,300,200 for procurement of structural material on
BSCL’s behalf.
(ii) US $28,400 for additional Barge trip.
(iii) US $54,000 for additional pipeline survey.
The said claims are the subject matter of the partial award. It was
dealt with by the learned arbitrator in the following terms:
"It was pointed out by BSCL that ONGC did not accept
the reconciliation attempted by MII in regard to the
pipelines. I have examined the documents pertinent to
this question, and I find that the variation is so marginal
that it can reasonably be ignored. It seems to me that to
take account of those variations is to attempt to make too
fine a point. I would accept the reconciliation statement
and proceed on that basis. BSCL contends that the claim
made by MII on account of the additional survey of the
WI-8, WI-9 pipelines is not acceptable because it is
covered within the lump sum price mentioned in the
Subcontract. I am not impressed by that submission
because had it been so covered ONGC would not have
undertaken to conduct the additional survey itself. It was
treated as some thing outside the subject matter covered
by the lump sum price and when ONGC requested BSCL
to conduct the additional survey, and at the behest of
BSCL the additional survey was conducted by MII, there
is good reason for MII to claim the payment of
US$54,000 for that survey."
While dealing with the claims for the standby of DB 26 and
interruption to WI-9 to WI S pipelines laying, the arbitrator in its partial
award held:
"22. Standby Derrick Barge 26 (US$1,396,800.00)
The claim for payment of standby charges in respect of
Derrick Barge 26 relates to a standby for 24 days of that
vessel. The MII Statement of Claim mentions that MII
has not sent any invoice to BSCL. Therefore it cannot be
said that any claim has been made by MII yet in the
matter. Consequently, the position is that no difference or
dispute concerning this had arisen between the parties
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 42
when the reference to arbitration was made. Therefore, so
far as this arbitration is concerned, the claim cannot be
entertained. It falls outside this arbitration and cannot be
considered."
"23. Interruption of WI-9 to WI-S Pipeline Laying
(US$115,087.50)
The Statement of Claim by MII mentions that an amount
of US$10,671,340.00 on account of delay and disruption
expenses and costs are claimed. Admittedly, they had not
yet been invoiced when the reference to arbitration was
made. It is not clear what are the Specific claims included
within that sum. If they had not been invoiced, it cannot
be said that they remained unpaid, and that therefore a
difference or dispute had arisen between the parties when
the reference to arbitration was made."
The said claims were, thus, rejected only on the ground that no
invoice had been raised and consequently no difference or dispute had arisen
by and between the parties at the time when the reference to arbitration was
made.
Mr. Mitra contended that applying the same line of reasoning, the
learned arbitrator should have rejected the aforementioned claims.
However, we may notice that the said claim as regard procurement of
structural material related to damages. According to MII, the said claim
strictly did not relate to damages under the contract. The BSCL was
required to procure the steel and as it was not in a position to do so, the MII
had agreed to procure steel on its behalf provided it agreed to cover the
MII’s cost for accelerated procurement, material priced premiums, order
fixing costs and other incidental charges. It is not in dispute that such a
claim was the subject matter of correspondence which passed between the
parties. Receipt of such letters from MII is not denied or disputed by BSCL.
It has also not been disputed that right reserved by MII to claim such
additional costs towards procurement of the materials on behalf of BSCL
was not denied or disputed. Only pursuant to or in furtherance of the said
correspondence, procurement on the said basis had been undertaken by MII
and acceptance of BSCL in this behalf was presumed. The learned
Arbitrator proceeded on such presumption. According to learned arbitrator,
despite such knowledge, BSCL failed to make payment. The learned
arbitrator in his award has gone into the said question in detail. Reference
had been made to the evidence of Shri A.R. Taylor, who was examined on
behalf of MII. The said witness was cross-examined by BSCL. Both the
parties had filed detailed written submissions before the learned arbitrator.
It is on the basis of such evidence brought on record and submissions made
before him, the learned arbitrator held:
"\005In my opinion, BSCL must be taken to have
accepted the proposal of MII and to have gone
along with MII’s action flowing from that proposal
and to have benefited thereby."
With a view to consider the submission of Mr. Mitra that in terms of
the contract entered into by and between the parties, MII was not entitled to
the said claim, it would be proper to notice the relevant clause of the contract
which is in the following terms:
"5. Replacement Steel :
BSCL shall procure suitable steel for jackets (based on
MTO supplied by MII) on a replacement basis for MII
purchased steel. BSCL shall purchase steel as plate
suitable for rolling 24 in O.D. and above tubulars.
Replacement material shall be delivered by BSCL to
MII’s yard at Dubai Emirate, United Arab Emirates or to
Singapore Port Authority for transshipment by MII (at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 42
BSCL’s cost) to Batam Island, Indonesia. MII shall
indicate the destination when furnishing the replacement
steel request."
In terms of the aforementioned provision of the contract, BSCL was
required to procure suitable steel for jackets on replacement basis in regard
to quantum of steel purchased by MII. If BSCL had failed to procure the
said required amount of steel to replace the structural materials which MII
had provided from its inventory as an accommodation to BSCL, indisputably
the understanding between the parties was that either such materials should
be replaced or the cost therefor had to be paid. It has not been disputed
before the arbitrator that BSCL promptly replaced the material. It is in that
view of the matter, the learned arbitrator in his partial award held:
" 15.19 The procurement was effected by MII from
its inventory on the basis that it would be replaced by
BSCL promptly. It was not so replaced. To effect the
replacement MII would be compelled to pass through the
entire burdensome process of procuring the structural
material directly from outside sources. MII suffered loss
and damage which it has quantified at US$ 2.3 million in
the light of the considerations mentioned by it earlier."
The arbitrator has noticed that the claim of MII arose only after it has
been satisfactorily proved that the invoices in respect of each of these claims
were issued and had become due for payment before reference to arbitrator.
It furthermore appears that paragraph 23 of the partial award and the claim
for compensation on the aforementioned head are not identical. Para 23 of
the partial award dealt with the claim in respect of WI-9 to WI-S pipeline
laying. So far as paragraph 24 of the said award is concerned, the learned
arbitrator noticed the specific invoices issued against Change Order Nos. 2,
3 and 7 relating to delay and disruptions. It is, therefore, in our considered
opinion, not correct to contend that the invoice is the only base whereby and
where under a claim can be made. There is no legal warrant for the said
proposition. A claim can also be made through correspondence or in
meetings.
A claim for overhead costs resulting in decrease in profit or additional
management costs is a claim for damages.
An invoice is drawn only in respect of a claim made in terms of the
contract. For raising a claim based on breach of contract, no invoice is
required to be drawn.
It is furthermore not in dispute that the claim for damages had been
made prior to invocation of arbitration. Once such a claim was made prior
to invocation, it became a dispute within the meaning of the provisions of
the 1996 Act. It is not disputed that the same claim was specifically referred
to arbitration by MII in terms of its notice dated 10th April, 1989.
While claiming damages, the amount therefor was not required to be
quantified. Quantification of a claim is merely a matter of proof.
In fact BSCL never raised any plea before the arbitrator that the said
claim was arbitrary or beyond its authority. Such an objection was required
to be raised by BSCL before the arbitrator in terms of Section 16 of the 1996
Act. It may also be of some interest to note that this Court even prior to the
enactment of a provision like Section 16 of the 1996 Act in Waverly Jute
Mills Co. Ltd. v. Raymon & Co. [(1963) 3 SCR 209; Dharma
Prathishthanam v. Madhok Construction (2005) 9 SCC 686] clearly held that
it is open to the parties to enlarge the scope of reference by inclusion of fresh
dispute and they must be held to have done so when they filed their
statements putting forward claims not covered by the original reference.
METHOD FOR COMPUTATION OF DAMAGES
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 42
What should, however, be the method of computation of damages is a
question which now arises for consideration. Before we advert to the rival
contentions of the parties in this behalf, we may notice that in M.N.
Gangappa v. Atmakur Nagabhushanam Setty & Co. and Another [(1973) 3
SCC 406], this Court held:
"In the assessment of damages, the court must
consider only strict legal obligations, and not ’the
expectations, however reasonable, of one
contractor that the other will do something that he
has assumed no legal obligation to do.
[See also Lavarack v. Woods of Colchester Ltd (1967) 1 QB 278]
The arbitrator quantified the claim by taking recourse to the Emden
formula. The learned arbitrator also referred to other formulae, but, as
noticed hereinbefore, opined that the Emden Formula is a widely accepted
one.
It is not in dispute that MII had examined one Mr. D.J. Parson to
prove the said claim. The said witness calculated the increased overhead
and loss of profit on the basis of the formula laid down in a manual
published by the Mechanical Contractors Association of America entitled
’Change Orders, Overtime, Productivity’ commonly known as the Emden
Formula. The said formula is said to be widely accepted in construction
contracts for computing increased overhead and loss of profit. Mr. D.J.
Parson is said to have brought out the additional project management cost at
US$1,109,500. We may at this juncture notice the different formulas
applicable in this behalf.
(a) Hudson Formula: In Hudson’s Building and Engineering Contracts,
Hudson formula is stated in the following terms:
"Contract head office overhead & x contract sum x period of delay"
Profit percentage contract period
In the Hudson formula, the head office overhead percentage is taken
from the contract. Although the Hudson formula has received judicial
support in many cases, it has been criticized principally because it adopts the
head office overhead percentage from the contract as the factor for
calculating the costs, and this may bear little or no relation to the actual head
office costs of the contractor.
(b) Emden Formula: In Emden’s Building Contracts and Practice, the
Emden formula is stated in the following terms:
"Head office overhead & profit x Contract sum x period of delay"
100 contract period
Using the Emden formula, the head office overhead percentage is
arrived at by dividing the total overhead cost and profit of the contractor’s
organization as a whole by the total turnover. This formula has the
advantage of using the contractors actual head office and profit percentage
rather than those contained in the contract. This formula has been widely
applied and has received judicial support in a number of cases including
Norwest Holst Construction Ltd. v. Cooperative Wholesale Society Ltd.,
decided on 17 February, 1998, Beechwood Development Company
(Scotland) Ltd. v. Mitchell, decided on 21 February, 2001 and Harvey
Shoplifters Ltd. v. Adi Ltd., decided on 6 March, 2003.
(c) Eichley Formula: The Eichleay formula was evolved in America
and derives its name from a case heard by Armed Services Board of
Contract Appeals, Eichleay Corp. It is applied in the following manner:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 29 of 42
Step 1
Contract Billings Total overhead for Overhead allocable
Total Billings for contract x contract period = to the contract
period
Step 2
Allocable overhead
Total days of contract = Daily Overhead rate
Step 3
Daily Contract Overhead Number of Days Amount of Unabsorbed
Rate x of delay = overhead"
This formula is used where it is not possible to prove loss of
opportunity and the claim is based on actual cost. It can be seen from the
formula that the total head office overheads during the contract period is first
determined by comparing the value of work carried out in the contract
period for the project with the value of work carried out by the contractor as
a whole for the contract period. A share of head office overheads for the
contractor is allocated in the same ratio and expressed as a lump sum to the
particular contract. The amount of head office overhead allocated to the
particular contract is then expressed as a weekly amount by dividing it by
the contract period. The period of delay is then multiplied by the weekly
amount to give the total sum claimed. The Eichleay formula is regarded by
the Federal Circuit Courts of America as the exclusive means for
compensating a contractor for overhead expenses.
Before us several American decisions have been referred to by Mr.
Dipankar Gupta in aid of his submission that the Emden formula has since
been widely accepted by the American courts being Nicon Inc.v. United
States, decided on 10 June, 2003 (USCA Fed. Cir.), Gladwynne
Construction Company v. Balmimore, decided on 25 September, 2002 and
Charles G. William Construction Inc. v. White, 271 F.3d 1055.
We do not intend to delve deep into the matter as it is an accepted
position that different formulas can be applied in different circumstances and
the question as to whether damages should be computed by taking recourse
to one or the other formula, having regard to the facts and circumstances of a
particular case, would eminently fall within the domain of the Arbitrator.
If the learned Arbitrator, therefore, applied the Emden Formula in
assessing the amount of damages, he cannot be said to have committed an
error warranting interference by this Court.
ACTUAL LOSS : DETERMINATION OF
A contention has been raised both before the learned Arbitrator as also
before us that MII could not prove the actual loss suffered by it as is required
under the Indian law, viz., Sections 55 and 73 of the Indian Contract Act as
Mr. D.J. Parson had no personal knowledge in regard to the quantum of
actual loss suffered by the MII. D.J. Parson indisputably at one point of time
or the other was associated with MII. He applied the Emden Formula while
calculating the amount of damages having regard to the books of account
and other documents maintained by MII. The learned Arbitrator did insist
that sufferance of actual damages must be proved by bringing on record
books of account and other relevant documents.
Sections 55 and 73 of the Indian Contract Act do not lay down the
mode and manner as to how and in what manner the computation of
damages or compensation has to be made. There is nothing in Indian law to
show that any of the formulae adopted in other countries is prohibited in law
or the same would be inconsistent with the law prevailing in India.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 30 of 42
As computation depends on circumstances and methods to compute
damage, how the quantum thereof should be determined is a matter which
would fall for the decision of the arbitrator. We, however, see no reason to
interfere with that part of the award in view of the fact that the
aforementioned formula evolved over the years, is accepted internationally
and, therefore, cannot be said to be wholly contrary to the provisions of the
Indian law.
In State of U.P. v. Allied Constructions [(2003) 7 SCC 396], this
Court held:
"4. Any award made by an arbitrator can be set
aside only if one or the other term specified in
Sections 30 and 33 of the Arbitration Act, 1940 is
attracted. It is not a case where it can be said that
the arbitrator has misconducted the proceedings. It
was within his jurisdiction to interpret clause 47 of
the agreement having regard to the fact-situation
obtaining therein. It is submitted that an award
made by an arbitrator may be wrong either on law
or on fact and error of law on the face of it could
not nullify an award. The award is a speaking one.
The arbitrator has assigned sufficient and cogent
reasons in support thereof. Interpretation of a
contract, it is trite, is a matter for the arbitrator to
determine (see Sudarsan Trading Co. v. Govt. of
Kerala). Section 30 of the Arbitration Act, 1940
providing for setting aside an award is restrictive
in its operation. Unless one or the other condition
contained in Section 30 is satisfied, an award
cannot be set aside. The arbitrator is a Judge
chosen by the parties and his decision is final. The
court is precluded from reappraising the evidence.
Even in a case where the award contains reasons,
the interference therewith would still be not
available within the jurisdiction of the court unless,
of course, the reasons are totally perverse or the
judgment is based on a wrong proposition of law.
An error apparent on the face of the records would
not imply closer scrutiny of the merits of
documents and materials on record. Once it is
found that the view of the arbitrator is a plausible
one, the court will refrain itself from interfering
(see U.P. SEB v. Searsole Chemicals Ltd. and
Ispat Engg. & Foundry Works v. Steel Authority
of India Ltd.)."
It is trite that the terms of the contract can be express or implied. The
conduct of the parties would also be a relevant factor in the matter of
construction of a contract. The construction of the contract agreement, is
within the jurisdiction of the arbitrators having regard to the wide nature,
scope and ambit of the arbitration agreement and they cannot, be said to
have misdirected themselves in passing the award by taking into
consideration the conduct of the parties. It is also trite that correspondences
exchanged by the parties are required to be taken into consideration for the
purpose of construction of a contract. Interpretation of a contract is a matter
for the arbitrator to determine, even if it gives rise to determination of a
question of law. [See Pure Helium India (P) Ltd. v. Oil & Natural Gas
Commission, (2003) 8 SCC 593 and D.D. Sharma v. Union of India (2004)
5 SCC 325].
Once, thus, it is held that the arbitrator had the jurisdiction, no further
question shall be raised and the court will not exercise its jurisdiction unless
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 31 of 42
it is found that there exists any bar on the face of the award.
The above principles have been reiterated in Chairman and MD,
NTPC Ltd. v. Reshmi Constructions, Buildres & Contractors (2004) 2 SCC
663; Union of India v. Banwari Lal& Sons (P) Ltd. (2004) 5 SCC 304;
Continental Construction Ltd. v. State of U.P. (2003) 8 SCC 4; State of U.P.
v. Allied Constructions (2003) 7 SCC 396.
A court of law or an arbitrator may insist on some proof of actual
damages, and may not allow the parties to take recourse to one formula or
the other. In a given case, the court of law or an arbitrator may even prefer
one formula as against another. But, only because the learned arbitrator in
the facts and circumstances of the case has allowed MII to prove its claim
relying on or on the basis of Emden Formula, the same by itself, in our
opinion, would not lead to the conclusion that it was in breach of Sections 55
or Section 73 of the Indian Contract Act.
CLAUSE 37 \026 EFFECT OF
We may now look at clause 37 of the main contract entered into by
and between ONGC and BSCL which reads as under:
"37. INDIRECT AND CONSEQUENTIAL
DAMAGES:
Neither company nor contractor shall be liable to
the other for any consequential damages, which
shall include but not be limited to loss of revenue/
profits, loss or escape of product, etc."
In Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority
[(1988) 2 SCC 338], whereupon Mr. Mitra placed strong reliance, an award
made under the old Act was in issue. A dispute had arisen whether there
was a claim and denial or repudiation thereof. In that context, it was held:
"There should be dispute and there can only be a dispute
when a claim is asserted by one party and denied by the
other on whatever grounds. Mere failure or inaction to
pay does not lead to the inference of the existence of
dispute. Dispute entails a positive element and assertion
of denying, not merely inaction to accede to a claim or a
request. Whether in a particular case a dispute has arisen
or not has to be found out from the facts and
circumstances of the case."
There is no dispute about the aforementioned principle but the same
would not mean that in every case the claim must be followed by a denial. If
a matter is referred to any arbitrator within a reasonable time, the party
invoking the arbitration clause may proceed on the basis that the other party
to the contract has denied or disputed his claim or is not otherwise interested
in referring the dispute to the arbitrator.
In Bharat Coking Coal Ltd. v. L.K. Ahuja [(2004) 5 SCC 109], this
Court opined:
"24. Here when claim for escalation of wage bills
and price for materials compensation has been paid
and compensation for delay in the payment of the
amount payable under the contract or for other
extra works is to be paid with interest thereon, it is
rather difficult for us to accept the proposition that
in addition 15% of the total profit should be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 32 of 42
computed under the heading "Loss or Profit". It is
not unusual for the contractors to claim loss of
profit arising out of diminution in turnover on
account of delay in the matter of completion of the
work. What he should establish in such a situation
is that had he received the amount due under the
contract, he could have utilised the same for some
other business in which he could have earned
profit. Unless such a plea is raised and established,
claim for loss of profits could not have been
granted. In this case, no such material is available
on record. In the absence of any evidence, the
arbitrator could not have awarded the same. This
aspect was very well settled in Sunley (B) & Co.
Ltd. v. Cunard White Star Ltd by the Court of
Appeal in England. Therefore, we have no
hesitation in deleting a sum of Rs. 6,00,000
awarded to the claimant."
We are herein not concerned with such a case.
In terms of Clause 37 of the main contract, reference whereto has
been made hereinbefore, neither of the parties are liable to the other for any
consequential damages. The claim for damages raised by MII cannot be said
to be consequential damages. The claim relates to direct losses purported to
have been occasioned by the failure to perform the contractual duty on the
part of the BSCL and to honour the time bound commitments. Such a loss,
according to MII, occurred on account of increased overhead cost and
decreased profit and additional management costs by reason of BSCL’s
delays and disruptions. It is only in that view of the matter, the Emden
formula was taken recourse to. Furthermore, clause 37 of the main contract
was a matter of an agreement by and between ONGC and BSCL. In law, it
could not have been extended to the obligations assumed by BSCL towards
MII in terms of the contract entered into by and between the said parties. So
far as ONGC is concerned, it cannot be said to have any role to play in the
event of breach of obligation on the part of the BSCL towards its sub-
contractor.
Article 3.1 of the sub-contract reads as under:
"MII shall be bound to BSCL by the terms of this Sub-
contract Agreement and to the extent that the provisions
of the respective Main Contract between Buyer and
BSCL apply to the relevant sub-contract work of MII as
defined in this sub-contract agreement, MII shall assume
towards BSCL all the obligations and responsibilities
which BSCL, by such Main Contract, assumes to Buyer
and shall have the benefit of all rights, remedies and
redresses against BSCL which BSCL, by such Main
Contract, has against Buyer, insofar as applicable to this
sub-contract Agreement, provided that when any
provisions of the respective Main Contract between
Buyer and BSCL is inconsistent with this sub-contract
agreement, this sub-contract agreement shall govern and
prevail over the Main Contract."
By reason of the said provision, therefore, the Main Contract between
ONGC and BSCL would apply to the relevant sub-contract work and MII
was enjoined with a duty towards BSCL to fulfill its obligations and
responsibilities. But, thereby, BSCL cannot absolve itself from its liability
so far as breach of the terms and conditions of the sub-contract is concerned.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 33 of 42
In other words, by reason of Article 3.1, the contract by and between ONGC
and BSCL has not been subsumed in the sub-contract so as to absolve the
BSCL from its own contractual liability for breach of contract or otherwise.
METHOD OF MEASUREMENT
The main contention of BSCL in this behalf is that the learned
arbitrator acted illegally and without jurisdiction in adopting the AISC Code.
The question arose in the context of the provisions in the contract that MII
was required to undertake to fabricate the materials which were required to
be supplied and, therefore, was entitled to fabrication charges from BSCL.
It has not been denied or disputed before us that the parties did not agree to a
fixed method of measurement. They did not refer to the AISC Code in the
contract but only because AISC code was not referred to in the contract, the
same by itself may not be a ground for us to hold that the arbitrator had gone
beyond the terms of the contract. Clause 23.1.1(a) and (c) of the main
contract reads as under:
"a) Payment for structural material viz. steel and steel
tubulars, anodes, flooding and grouting stems,
rubberized rings and rubberized items for barge
hampare, rub-strips and boat landing shall be made on
the basis of actual landed cost at Contractor’s yard.
Landed cost would include c.i.f. price, testing charges, if
any plus port charges clearing and handling charges at
Port, transportation to Contractor’s fabrication yard plus
local taxes (like octroi ) if any, company shall pay to
Contractor an additional 7 = per cent of the landed cost
referred to above to cover the cost of procurement."
(c ) In computing the quantity of steel materials used on
each platform for the purpose of sub-clause (a) above, an
allowance of 4% shall be made for wastage. The payment
to Contractor shall be for weights including the wastage
element credit for steel scrap shall be given by Contractor
to Company at the rate of Rs. 500.00 per short ton for the
said wastage of 4%."
Clause 11 and Clause 5 read as under:
"11. Fabricated Tonnages:
"The quantities of materials used in the Works shall be
jointly ( i.e. by ONGC/Engineer, BSCL and MII )
determined on the basis of as-fabricated tonnage as per
the Main Contract between Buyer and BSCL and shall
be used for adjusting the Subcontract Price."
"5. The preceding fabrication rates are worked out taking
into consideration installation of all equipment,
fabrication and installation of process piping, electricals
and instrumentation work including pre-commissioning
and all yard test in addition to structural fabrication work
in accordance with the specifications. For computing the
tonnage for reimbursement of fabrication, installation,
pre-commissioning and testing work at the yard by MII
the tonnage of equipment and items for top side facilities
shall not be included and fabrication tonnage shall be
solely on the basis of as built tonnage as approval by
buyer."
Submission of Mr. Mitra is that a combined reading of the
aforementioned provisions would go to show that the method of
measurement was the subject matter of the contract. We do not agree.
Clause 23.1.1 has no application in the present case as it covers payment for
structural material which has no nexus with the Claim No. 4. The claim of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 34 of 42
MII was for labour charges due under the sub-contract for fabricating the
structures.
The learned arbitrator, in his partial award, while dealing with the said
claim held:
"15.7: As regards replacement steel, BSCL would
procure suitable steel for jackets (based on MTO
supplied by MII) on a replacement basis for MII
purchased steel. BSCL would purchase steel as plate
suitable for rolling 24 in OD and tubulars. Replacement
material would be delivered by BSCL to MII’s yard at
Dubai, UAE or to Singapore Port Authority for
transshipment by MII , at BSCL’s cost, to Batam
Island, Indonesia. In the matter of computing the
prices payable for structural fabrication of piles, Jackets
and decks Clause 23.1.1 of the main fabrication
contracts provided that the prices would be computed as
follows: The payment for structural material, namely,
steel and steel tubulars and anodes, flooding and
grouting system, rubberized rings and rubberized items
for barge bumpers, rub strips and boat landing would be
made on the basis of actual landed cost at the yard of
BSCL or MII. The landed cost would include CIF
price, testing charges, if any plus port charges, clearing
and handling charges at port , transportation to BSCL’s
or MII’s fabrication yard plus local taxes, and ONGC
would pay to BSCL in additional 7 = per cent of the
landed cost to cover the cost of procurement."
Wastage allowance was relevant only for the purpose of allowance
due to BSCL from MII in respect of scrap materials. The learned arbitrator
in his award had referred to evidence adduced in this behalf by Shri A.R.
Taylor. The provisions of the contract have no bearing on calculation of
gross fabricated weight of the structures for determining the fabrication
charges due.
The use of AISC Code relates to the claim for fabrication charges
being Claim No. 1. The said claim was for labour charges which was not a
claim for cost of material and, thus, nothing to do therewith. The scheme of
the contract provides that total estimated tonnage of 18,178 ST will have the
following break \026 ups:
ED/EE Platforms \026 6078 ST
WI-8, WI-9, WI-10 and N3 platforms \026 12100 ST
18178 ST
Since the total tonnage of 18,178 ST was only an estimated tonnage,
the sub-contract made provision for variation of the contract price on the
basis of ’as fabricated’ tonnage. Further the quantities of the materials used
were to be jointly determined by ONGC /EIL, BSCL and MII on the basis of
fabricated tonnage which was to be used for adjusting the sub-contract price.
If the "as fabricated tonnage" was found to be less than the estimated
tonnage, the excess payment received by MII through monthly bills was to
be refunded. If the "as fabricated tonnage" was found to be more than the
estimated tonnage, MII was to be paid for the additional tonnage by applying
the rate of US $ 1067 per ST. The contract was silent with respect to the
method or code to be applied for determining the "as fabricated tonnage".
Clause 1.1.13 defined specifications to mean Industry Standard Codes
(ISC). In the absence of a contractually specified method of calculation, the
MII applied the AISC Manual of Steel Construction for calculating the as
fabricated tonnage. AISC is an industry standard. It has been applied by
ONGC in other contracts. Even the Arbitrator has noted that the BSCL has
also accepted the validity of the AISC Code. Now the BSCL cannot turn
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 35 of 42
around and take a contrary position before this court in the proceedings
under Section 34 of the Act. Hence by adopting the AISC Code, the
Arbitrator has not acted contrary to the terms of contract.
The arbitrator in his award noticed that the parties impliedly accepted
the validity of the AISC method of calculation for calculating the final
fabricated weight in the following terms:
"\005Instances of those contracts have been provided by
MII during the arbitration proceeding showing that the
AISC Code has been employed for determining the final
"as fabricated tonnage" of structures\005It seems to me
that inasmuch as BSCL has applied the AISC Code in the
case of long to long point distance measurement it cannot
be denied that the AISC Code is regarded as a valid basis
for measurement it cannot be denied that the AISC Code
is regarded as a valid basis for measurement. There is no
reason why it should be applied in the case of one
category of fabrication and not in the case of another."
If before the arbitrator, the said mode of calculation was accepted, we
do not see any reason why the BSCL should be permitted to raise the said
question before us.
BUOYANCY TANKS FOR ED AND EE JACKETS
It involves a question of fact. It was a part of Claim No. 1 for
fabrication. The contention of the BSCL is that whereas Buoyancy tanks
which were used in WI-8 and N3 jackets were removed by MII after
installation thereof, the same had been used after refurbishment on the
ED/EE jackets and in that view of the matter, no fabrication was required to
be done. The claim of MII was that it had nothing to do with the cost of
material or the nature of the fabrication work involved. Its claim was purely
based on the labour cost at the rate of US $1067 per ST which was incurred
by it towards fabrication work in the refurbishment of the Buoyancy Tanks.
According to it, the tonnage of the Buoyancy Tanks had not been taken into
account by ONGC on the ground that no fabrication work was done after
removal of the Buoyancy Tanks from N3 and WI-8 Jackets. The learned
arbitrator, however, in his partial award found as of fact that substantial
fabrication work had been done by MII in the refurbishment of the said
Buoyancy Tanks in the following terms:
"12.22\005Accepting those instructions, MII made
substantial fabrication in refurbishing, handling, rigging
and welding the buoyancy tanks on the ED and EE
jackets. The oral evidences of RW S.K. Mukherjee shows
that the attachment of buoyancy tanks involves
substantial fabrication activity. There can be no doubt
that fabrication work had to be done and that involved a
measure of labour activity. MII has demonstrated that
there was difference in weight between the original
buoyancy tanks used on the N-3 and W-8 jackets and the
weight of those tanks when used on the ED and EE
jackets. It says that this clearly points to substantial
fabrication activity for refurbishment of those two tanks."
It has further been held by the learned Arbitrator that MII had also
been able to establish that there had been a difference in weight between the
original Buoyancy Tanks used on N-3 and WI-8 Jackets and the weight of
those tanks when used in ED and EE Jackets. In fact, the learned arbitrator
in arriving at the said conclusion had taken into consideration the admission
of Shri S.K. Mukherjee who was examined on behalf of BSCL itself that
attachment of Buoyancy Tanks involved substantial fabrication activity.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 36 of 42
The dispute raised is a matter of appreciation of evidence. The findings
arrived at by the learned arbitrator cannot, thus, be said to be perverse.
TIE-DOWNS AND SEA-FASTENING
This claim relates to the question whether MII was entitled to
payment for fabrication as the tie-downs and sea-fastening require
substantial fabrication job in regard whereof there did not exist any
provision in the contract. The learned arbitrator has accepted the claim of
MII holding that offshore construction contracts, jackets and decks are
fabricated onshore and then they are transported on barges to the offshore
location for installation wherefor the lugs, braces and other sea-fastening and
tie-down items are required to be created which the installation contractor is
to use to weld the jackets and decks to the transportation barges, thereby
securing the jackets for their journey to the offshore location. MII had
merely claimed payment for fabrication of tie-downs and sea-fastening as
part of the fabrication scope of work. Reference has been made to clause 2
of the contract which is as under:
"2.1 (i) (a) Load-out, seafastening, \005. 60% of the
transportation and installation lumpsum
price of jacket, piles & appurtenances
(b) Load-out, seafastening, \005.40% of the
transportation and installation lumpsum
price of Decks, Hook-up and resting
The said provision has no application in the instant case as it merely
provides for stage payment on milestone basis. In fact, the clause which
would be attracted in the present case is contained in clause 2.1(a)(i) is as
under:
"The scope of work to be executed by Contractor under
this Contract shall comprises\005
(i) Jackets
Including bergs bumbers, best landing, grouting an
flooding systems, launch trustees, riser clamps. Catholic
protection anodes, and mats and other accessories and
components indicated in the drawings and specifications
including lifting lugs, pulling lugs, retaining lugs etc.
for lead out and refastening and upending of the jacket."
It specifically covers sea-fastening as part of the scope of fabrication
contract work. WI-8, WI-9, WI-10 and N-3 fabrication contract also
contains a similar clause in Clause 2.1.
The learned arbitrator in para 12.24 of his award noticed that BSCL
itself has acknowledged to ONGC that the tie-down materials had been
fabricated as part of the fabrication scope and the weight could not be
disallowed in calculating the ’as fabricated tonnage’. It, therefore, evidently
cannot take a stand which is contrary thereto and inconsistent therewith.
Thus, by reason of the award, the learned arbitrator was of the opinion that
the sea-fastening and tie-down were part of the transportation and
installation scope and BSCL did not succeed in proving that the said item
should be included in the scope of transportation and is not a separate item
under the head of fabrication. Again, the findings of the learned arbitrator
were within his domain, being findings of fact.
FOREIGN EXCHANGE
Dispute in relation to the said claim would depend upon the
interpretation of clause 3 of Section 2 of the Consolidated Sub-Contract
Price Schedule which provides:
"While the sub-contract price for the work described in
the letter of intent is payable by BSCL to MII in U.S.
Dollars the Main Contract Price is payable by ONGC to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 37 of 42
BSCL in Indian Rupees. It has been agreed that Rupee-
U.S. Dollar Excahnge rate shall remain fixed at Rs.
100.00=U.S$8.575 and loss or gain due to any variation
in the Rupee-U.S. Dollar exchange rate at the time of
actual remittance of bills would be to MII’s account.
The aforesaid rate was the prevailing rate as on 9
August 1984 as mentioned in the Letter of Intent dated
11 September 1984. Within 30 days of completion of
MII’s scope of work under the Sub-contract, a
reconciliation will be made of all the payments made
from time to time.
If the cumulative value of all Rupess expended to
buy U.S. Dollar remittance for the Sub-contract work
described in the Letter of Intent is less than the Rupee
equivalent of the Sub-contract price as determined on the
basis of the aforesaid rate prevailing on 9 August 1984,
BSCL shall remit the balance amount of Indian Rupees,
if any, to MII in U.S. Dollars at the prevailing rate of
exchange on the date of such U.S. Dollar remittance; and
if after such reconciliation it is found that BSCL have
expended Rupees in excess of the Rupees equivalent of
the Sub-contract Price for the work described in the
Letter of Intent, MII shall arrange to refund any such
excess in Rupees to BSCL."
Clause 4.0 of the contract provides that the payment will be made by
BSCL to MII on receipt of payment by BSCL from ONGC.
It is not in dispute that by reason of the contract entered into by and
between the parties the rate was frozen at Rs. 100 = US$ 8.575. One of the
questions which arise for consideration is as to whether the said provision
applied to all the claims or not. According to MII, having regard to the
provisions for milestone payments for transportation and installation, Clause
4.0 would apply only in relation thereto.
It is contended that BSCL had not correctly understood the merit and
purport of the said provision which has been sought to be explained. The
said provision according to MII would be as under:
If the contract is followed, MII gets US$100 and
pays back US$7.43, therefore the net receipt of
MII is US$ 92.57. However, BSCL had adjusted
the exchange rate at the time of payment only. The
rate as per contract 1 US$= 11.662. Thus, the rate
on the date of payment is Rs. 13. Therefore, the net
receipt of MII is only US$ 89.70. In reality, the
loss suffered by MII was much greater since in the
fifty-four month life of the project, the value of the
Indian rupee deteriorated drastically against the
U.S. dollar.
It is not in dispute that in terms of the contract, the payments made by
BSCL, which was to be in US dollars, was required to be reconciled at the
end of the contract. According to MII, if BSCL expended less than the
rupee amount stipulated in the sub-contract in dollar payments, BSCL would
convert the unused rupees to dollars to remit the dollars to MII. Whereas if
BSCL expended more than the agreed amount of rupees, MII would refund
the excess amount to BSCL so as to ensure sharing of exchange loss by both
the parties. According to MII, however, BSCL acted contrary to the said
provision insofar as instead of paying the full amount of invoice in US
dollars it paid at the fixed exchange rate relying on, or on the basis of, the
aforementioned provisions, resulting in loss suffered by MII.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 38 of 42
The learned arbitrator proceeded on the basis that loss of exchange
provisions had no application in respect of structural material (claim 4), bulk
material (claim 5), transportation of pipe (claim 6), reimbursables (claim 7),
change orders and extra work (claim 8) and delay and disruption (claim 9).
BSCL although has acted in breach of the contract in which variation
provision as regard the claims of the sub-contract, viz., scope of fabrication
work (Claim 1), transportation and installation of platforms (Claim 2) and
transportation and installation of pipelines and risers (Claim 3) while making
payments. It is, however, one thing to say that having regard to the nature of
breach on the part of BSCL, MII would be entitled to claim damages, but it
is another thing to say that by reason thereof it would be entitled to full
payment without deduction relating to the BSCL conversion of Indian
rupees to US dollars. It is not in dispute that the initial claim of MII was US
$ 2881195.03 which was later on revised to US $ 3330790.94.
In terms of the agreement, payments were to be made to MII if the
payments were certified by EIL and upon receipt of payments from ONGC
and upon receipt of foreign exchange clearance. For appreciating the
aforementioned disputes, it may be necessary to refer to the general terms of
payment clause:
"1. Fabrication
Claims for structural fabrication work is to be billed by
MII duly certified by EIL on monthly basis and the
payment of the same bills shall be released after 60 days
of receipt of the bill by BSCL.
4. Payments as stipulated above will be subject to the
following conditions:
(a) Receipt of foreign exchange clearance by BSCL.
(b) Payments on milestone basis will be made by
BSCL to MII only after payments have been received by
BSCL from ONGC."
The learned arbitrator held that MII would be entitled to receive the
entire amount as BSCL, despite receipt of payment from ONGC, did not pay
the amount to MII. For the purpose of applicability of the exchange rates,
the same, in our opinion, is irrelevant. The award was required to be made
in terms of the contract whereby and whereunder the foreign exchange rate
was frozen as was applicable on 9th August, 1994. The parties were bound
by the said terms of contract. It may be noticed that the sub-contract was
entered into on 1st January, 1986. The execution of the contract had started
much earlier, i.e., much before the date of entering into the contract. The
purpose for which the Rupee \026 US Dollar conversion rate has been frozen as
on 9th August, 1984 must be viewed from the angle that thereby the parties
thought that loss or gain towards the exchange rates would be on account of
MII. It is in the aforementioned situation that a letter of intent in the
following terms was served:
"M/s. McDermott International Inc.,
P.O. Box 3098
Dubai
United Arab Emerates.
Dear Sirs,
Sub: ED, EE, WI-8, 9, 10 & N3 Platforms
Ref: Minutes of Meeting dt. 9.8.84
Your offer P/M 547 dt. 9.8.84
8/3132 dt. 4.9.84
With reference to the above, we are pleased to issue this
Letter of Intent conveying acceptance of your offer for the
following:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 39 of 42
1.0 FABRICATION
1.1 Fabrication, load-out & sea-fastening of 6 Jackets with Piles
including all appurtenances such as boat landing, conductor,
riser clamps etc.
1.2 Fabrication, load-out & sea-fastening of 4 main decks, WI-
8, 9, 10 & N3 complete with installation of all equipment,
process piping, electricals and instrumentation work including
all yard test.
1.3 Refurbishing of 4 temporary decks to be supplied by
ONGC.
2.0 TRANSPORTATION
2.1 Transportation, installation, hook-up & commissioning of
all above i.e. 1.1, 1.2 & 1.3 and ED, EE Decks and 6 helidecks
fabricated by BSCL at Jellingham. Temporary deck will be
collected from ONGC and taken to MII yard. Additionally the
temporary decks will be removed prior to installation of this
deck and handed back to ONGC.
3.0 Transportation, installation, hook-up & commissioning of
Submarine Pipeines & Risers.
4.0 PRICES
The lump sum price is as follows:-
4.1 For 1.1, 1.2 & 1.3 of above US$ 19,400,000
4.2 For 2.0 of above US$ 23,025,000
TOTAL US$ 42,425,000
4.3 PIPELINES
For 3.0 above pipelines totaling 28 US$ 3,800,000 L.S. KM in
length and installation of 8 risers @ US$ 91 per metre of
pipeline and US$ 156,485 per Riser.
4.4 The above lump sum prices are based on estimated tonnages
and flowline length and number of risers. Any variation in the
above will alter the prices pro rata.
4.5 The above amounts are based on the exchange rate between
U.S. Dollars and Indian rupees (as ruling on 9.8.84). Any
variation in the above rate will be to MII’s account.
5.0 TERMS & CONDITIONS
5.1 All terms and conditions other than the payment terms as
stipulated by ONGC in their contract with BSCL for the above
platforms will be applicable to MII.
5.2 The lumpsum price is inclusive of all engineering required
for total scope of BSCL’s & MII’s work for six platforms as
well as all technical service support by provision of expert
personnel to BSCL.
6.0 TERMS OF PAYMENT
Terms of payment are to be mutually discussed and agreed to.
It is however understood that payment on milestone basis will
be made by BSCL to MII only after payments have been
received by BSCL from ONGC.
7.0 DELIVERY
MII will ensure delivery in such a manner that the delivery
dates as stipulated by ONGC for the above platforms will be
met.
8.0 It may be noted that this Letter of Intent is subject to
clearance of Import List form DGTD and receipt of sanction
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 40 of 42
from Government of India for release of requisite amount of
foreign exchange and import licenses etc. In case Govt’s
clearance/ approval is not received, this Letter of Intent will be
withdrawn without any financial repercussions on either side.
We shall however inform you as soon as Govt’s approval/
clearance is received by us.
Subject to this, we would request you to proceed with the work
to ensure completion within the agreed schedule."
There might be some delay on the part of BSCL to make payments.
We may not go into the aforementioned question, but to hold that the
exchange rate clause shall cease to have any application only because of the
breaches on the part of BSCL, cannot be accepted.
We are not in a position to accept that the exchange variation
provision does not relate to the payments in respect of Claim Nos. 1, 2 and
3. The objection raised by the claimant to the said extent is accepted.
SUBSTITUTION
It is not in dispute that MII had substituted heavier material, as
material conforming to ONGC specification was not available readily in the
market. The matter was referred to EIL. Use of material was found to be
technically acceptable to EIL to which ONGC agreed by a letter dated 3rd
May, 1985. ONGC, however, made it clear that it would not make payment
for the substituted material. BSCL immediately by a telex dated 13th May,
1985 informed the same to MII. ONGC also in its letter dated 6th December,
1984 categorically stated:
"The subject matter highlighted in your letter
mentioned above has been reviewed by us and we have
found that payment against increased tonnage on
account of material substitutions proposed by M/s.
BSCL/MII cannot be agreed to. Based on above we
reiterate our view that we will pay the material/
fabrication costs based on the materials shown in the
AFC drawings."
The claim of MII is based on the failure on the part of the BSCL to
fulfil its part of the obligation in procurement of the required material. It is
true that BSCL agreed to reimburse MII for the same. MII’s claim is
partially based on the facts that EIL had recommended payments therefor as
stated in a letter to ONGC dated 10 February 1987 and 6 April 1987.
However, it is also not in dispute that ONGC did not accept the said
recommendations and refused to take into consideration the substituted
tonnage for payment of ’as fabricated tonnage’.
There may be a dispute in this behalf between BSCL and ONGC.
However, admittedly, ONGC refused payment to BSCL.
In his partial award, the learned arbitrator noticed that ONGC’s
involvement was imperative. ONGC had all along maintained its stand that
it was not ready and willing to bear the extra costs. The correspondence
between the parties was brought on record.
Clause 5 of the contract categorically states that MII was to procure
the material which was to be reimbursed by BSCL. The extra amount
incurred by MII for procuring materials having extra thickness, therefore,
was not payable. To the aforementioned extent, there has been a novation of
contract. MII had never asserted, despite forwarding of the contention of
ONGC, that it would not comply therewith. It, thus, accepted in sub silentio.
It, thus, must be held to have accepted that no extra amount shall be payable.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 41 of 42
It is one thing to say that some more amount might have been spent towards
fabrication but the learned arbitrator has awarded the exact amount claimed
by MII in the following terms:
"I am satisfied that MII is entitled to a payment of US$
20, 832.108 for the disallowed tonnage of 19.584 ST at
the contractual rate of US$ 1067 per ST."
It is in the aforementioned context that the involvement of ONGC was
necessary and if it is the accepted case of the parties that ONGC would not
entertain any claim of BSCL in this behalf, a fortiori having regard to the
tripartite agreement, the learned arbitrator could have no jurisdiction to
determine the claim in favour of MII only because at one point of time
BSCL had raised its own claim with ONGC. In other words, any reduction
of the claim of the BSCL by ONGC had a direct nexus with the claim of
MII. It was, therefore, not a case where ONGC was not involved in the
matter. The exchange of letters categorically proves that MII had accepted
that it would not be entitled to any extra amount in that behalf. MII by
necessary implication accepted the said contention. The principle of
acceptance sub-silentio shall also be attracted in the instant case. MII was,
therefore, not entitled to raise a claim to the extent of fabrication on account
of the increased charges for substitution of material used for WI-8, WI-9,
WI-10 and N-3 Jackets and piles.
To the aforementioned extent, the claim of MII was beyond the terms
of the contract.
INTEREST
The power of the arbitrator to award interest for pre-award period,
interest pendent lite and interest post-award period is not in dispute. Section
31(7)(a) provides that the arbitral tribunal may award interest, at such rate as
it deems reasonable, on the whole or any part of the money, for the whole or
any part of the period between the date on which the cause of action arose
and the date on which award is made, i.e., pre-award period. This, however,
is subject to the agreement as regard the rate of interest on unpaid sum
between the parties. The question as to whether interest would be paid on
the whole or part of the amount or whether it should be awarded in the pre-
award period would depend upon the facts and circumstances of each case.
The arbitral tribunal in this behalf will have to exercise its discretion as
regards (i) at what rate interest should be awarded; (ii) whether interest
should be awarded on whole or part of the award money; and (iii) whether
interest should be awarded for whole or any part of the pre-award period.
The 1996 Act provides for award of 18% interest. The arbitrator in
his wisdom has granted 10% interest both for the principal amount as also
for the interim. By reason of the award, interest was awarded on the
principal amount. An interest thereon was upto the date of award as also the
future interest at the rate of 18% per annum.
However, in some cases, this Court was resorted to exercise its
jurisdiction under Article 142 in order to do complete justice between the
parties.
In Pure Helium India (P) Ltd. (supra) this Court upheld the Arbitration
award for payment of money with interest at the rate of 18% p.a. by the
respondent to appellant. However, having regard to long lapse of time, if
award is satisfied in entirety, respondent would have to any a huge amount
by way of interest. With a view to do complete justice to the parties, in
exercise of jurisdiction under Article 142 of the Constitution of India, it was
directed that award shall carry interest at the rate of 6% p.a. instead and in
place of 18% p.a.
Similarly in Mukand Ltd. v. Hindustan Petroleum Corpn., [2006 (4)
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 42 of 42
SCALE 453], while this court confirmed the decision of the division bench
upholding the modified award made by the learned single judge, the court
reduced the interest awarded by the learned single judge subsequent to the
decree from 11% per annum to 7 = % per annum observing that 7 = % per
annum would be the reasonable rate of interest that could be directed to e
paid by the appellant to the respondent for the period subsequent to the
decree.
In this case, given the long lapse of time, it will be in furtherance of
justice to reduce the rate of interest to 7 = %.
As regards certain other contentions, in view of the fact that the same
relate to pure questions of fact and appreciation of evidence, we do not think
it necessary to advert to the said contentions in the present case.
CONCLUSION
I.A. Nos. 2 and 3 are allowed in part and to the extent mentioned
hereinbefore. The award of the learned Arbitrator is modified to the
aforementioned extent. In the facts and circumstances of this case, there
shall be no order as to costs.