Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
UNION OF INDIA
Vs.
RESPONDENT:
SALWEEN TIMBER CONSTRUCTION (INDIA) & ORS.
DATE OF JUDGMENT:
25/09/1968
BENCH:
RAMASWAMI, V.
BENCH:
RAMASWAMI, V.
SHAH, J.C.
GROVER, A.N.
CITATION:
1969 AIR 488 1969 SCR (2) 224
CITATOR INFO :
RF 1971 SC1495 (32)
RF 1984 SC1072 (41)
F 1985 SC1156 (45)
ACT:
Arbitration--Arbitration clause in contract--Dispute
whether arises out of contract--Test for determining.
HEADNOTE:
There was a dispute between the appellant and respondent
regarding the supply of timber. In pursuance of the clause
in the contract which provided that in the event of any
question or dispute arising under the. contract or in
connection with the contract it should be referred to
arbitration, the dispute was so referred. One of the items
in dispute was a ’claim by the respondent that there was an
excess supply of timber to cover up possible rejection,
which should be returned by the appellant with compensation
for deterioration, or that payment should be made for it at
the market value. The appellant contended that the terms of
the contract did not require the respondent to tender for
inspection an,of quantity in excess of the contracted
quantity, that the claim was in detinue relating to an
involuntary bailment and not in relation to anything done in
the performance, implementation or execution of the
contract; and therefore., it was not a dispute arising out
of the contract or in connection with the contract.
On the question whether the arbitrators had jurisdiction
to adjudicate upon the claim,
HELD: The test for determing the question is whether
recourse to the contract, by which both the parties are
hound, was necessary for the purpose of determining
whether the claim of the respondent was justified or
otherwise. Since it was necessary to have recourse to
the terms of the, contract for the purpose of deciding the
matter in dispute, the matter was within the scope of the
arbitration clause and the arbitrators had jurisdiction to
decide it.
Ruby General Insurance Co. Ltd. v. Peary Lal Kumar,
[1952] 5.C.R. 501, followed.
Piercy v. Young, 14 Ch.D. 200 and Turnock v. Sartoris 43
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
Ch.D.150, explained.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 549 of
1966.
Appeal by special leave from the order dated October 23,
1964 of the Punjab High Court, Circuit Bench at Delhi in
Civil Revision No. 438-D of 1964.
V.A. Seyid Muhammad and S.P. Nayar, for the appellant.
S.V. Gupte and A.K. Nag, for respondents Nos. 1 and 2.
A.G. Ratnaparkhi, for respondent No. 5.
225
The Judgment of the Court was delivered by
Ramaswami, J.This appeal is brought by Special leave
against the judgment of the Punjab High Court in Civil
Revision No. 438-D of 1964 by which the revision petition of
the appellant against the order of Shri D.R. Khanna,
Subordinate Judge, 1st Class, Delhi dated 20th April, 1964
in Suit No. 128 of 1’963 was dismissed in limine. Suit No.
128 of 1963 was an application by the Union of India under
sections 5, 12(2),31(3), 32 and 33 of the Arbitration Act,
1940 for obtaining a declaration that the reference of the
claim of the respondent firm in respect of excess quantity
of timber alleged to have been delivered and certain other
matters was not covered by the arbitration agreement and for
leave to revoke the authority of the Arbitrators and Umpire.
The petition was rejected by the Subordinate Judge by his
order dated 20th April, 1964.
By a savingram dated 21st December, 1953 the Union of
India (hereinafter called the appellant) entered into a
contract of purchase of ’1,01,750 cubic feet of teak logs at
Rs. 9/12/- Vet c.ft. to be delivered F.O.R. Halisahaar and
Lillooah, both in West Bengal near Calcutta. The consignee
was the District Controller of Stores, Eastern Railway. The
formal acceptance of tender confirming the savingram and
containing the other terms of the contract was issued on
13th January, 1954. Besides the quantity of teak logs
originally contracted to be supplied, the respondent firm
subsequently supplied a quantity of 1676.95 c.ft. Burma
teak squares at the same rate and the contract was
accordingly amended on 13th December, 1957. It was provided
in clause 17(c) of the acceptance of tender that the
respondent firm was to offer the timber for inspection at
its own premises at Halisahaar and Lillooah. Although the
delivery time was extended from time to time, upto 26th
January, 1958. the respondent firm supplied only 77,21/.89
cubic feet of timber and the contract in respect of the
unsupplied quantity was cancelled on 20th june, 1958 and
that the supplied quantity was repurchased by Government
from third party at a loss of Rs. 1,54,541.36 on 23rd July,
1958. Including this item the appellant made a claim of
Rs. 3,50.085.99 against the respondent firm out of which it
recouped Rs. 1,79.366 from the sums due to the respondent
firm leaving a balance of Rs.1.70,719.99. The contract in
question is governed by the arbitration agreement contained
in clause 21 of the form W.S.B. 133 which states as follows
:--
"Arbitration:
In the event of any question or dispute
arising under these conditions or any
special conditions of contract or in-
connection with this contract (except as to
any matters the decision of which is specially
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
provided for
226
by these conditions) the same shall be
referred to the award of an arbitrator to be
nominated by the Purchaser and an arbitrator
to be nominated by the Contractor, or in case
of the said arbitrators not agreeing then to
the award of an Umpire to be ,appointed by the
arbitrators in writing before proceeding on
the reference and’ the decision of the
arbitrators, or in the ’event of their not
agreeing, of the Umpire appointed by them,
shall be final and conclusive and the
provisions of the Indian Arbitration Act,
1940, and of the Rules thereunder and any
Statutory modification thereof shall’ be
deemed to apply to and be incorporated in this
contract.
Upon every and any such reference, the
assessment of the costs incidental to the
reference and award respectively shah be in
the discretion of the arbitrators or in the
event of their not agreeing of the Umpire
appointed by them."
In pursuance of the arbitration .clause the respondent
firm appointed one Mr. T.R. Sharma as its arbitrator and the
appellant appointed Mr. R.R. Desai, Deputy Legal Adviser,
Ministry of Law, Government of India as its nominee. Mr.
P.S. Bindra, a retired District Judge was appointed as the
Umpire by order of the Sub-Judge dated 2-8-1961. Both the
parties filed their respective claims before the
arbitrators. The respondent firm claimed a sum of Rs.
73,50,000 while the appellant contended that the respondent
committed breach of the contract by not supplying the
stipulated quantity of timber under the contract and as
such claimed damages to the extent of Rs. 3,00,000. The
case of the respondent firm was that in order to cover up
possible rejection, a quantity of timber much in excess of
the contracted quantity was despatched to the consignees and
the excess quantity measuring 3,400 tons i.e. 1,70,000 cubic
feet was still lying with the Lillooah consignnee and 1,500
tons i.e. 75,000 cubic feet with the Halisahaar consignee
and had not been returned despite repeated requests. The
respondent firm claimed return of this quantity of timber
and compensation for its deterioration. It was
alternatively contended that in case the Government failed
to return the whole or part of the excess timber, then
payment for that quantity at the market rate should be made.
The appellant in its reply denied the allegation relating to
the delivery and retention of excess quantity. It was
specifically denied that 4,900 tons or any quantity was due
to be returned to the respondent firm or that it was
entitled to recover Rs. 73,50,000 or any amount as claimed.
It was contended that in terms of the contract the
respondent firm was to offer inspection of the store at its
own premises ’at Lillooah and Halisahaar but instead doing
so, the respondent firm started to despatch the logs to the
DCO’s Lillooah and Halisahaar to be
227
inspected at the consignees’ premises. This was done for
its own convenience and at its own risk. The inspected
stores were retained by the consignee while the rejected
stores were to be removed by the respondent firm from the
consignee’s premises at their own expense. It was
submitted that the dispute raised by the respondent firm was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
outside the scope of the arbitration agreement and that the
arbitrators had no jurisdiction to entertain such a claim.
After hearing the parties, the Subordinate Judge rejected
the application of the appellant by his order dated 20th
July, 1964.
It is necessary at this stage to quote the relevant
clauses of the contract. Clause 13 ( 1 ) provides:
"Inspection and Rejection: Facilities
for Test and Examination:---The Contractor
shall afford at his own expense the Inspector
all reasonable accommodation and facilities
for satisfying himself that the stores are
being or have been manufactured in accordance
with the particulars and for this purpose the
Inspector shall have full and free access at
any time during the contract to the
Contractor’s work and may require the
Contractor to make arrangements for anything
to be inspected at his premises or at any
other place and the Contractor shall reserve a
similar right as regards any sub-contract he
may make.
The Contractor shall pay all costs connected
with such tests and provide, without extra
charge, all materials, tools, labour and
assistance of every kind which the Inspector
may consider necessary for any test and
examination other than special or independent
tests which he shall require to be made on the
contractor’s premises, and shall pay all the
costs attendant thereon,failing these
facilities (in regard to which the inspector
will be the sole judge) at his own premises
for making the tests, the Contractor shall
bear the cost of Carrying out such tests
elsewhere".
Clause 13(4) reads as follows :--
"Inspection and rejection: The whole of a
consignment may be rejected, if, on
inspection, a portion upto 4 per cent of the
consignment (at the sole discretion of the
Inspector) is found’ to be unsatisfactory."
Clause 13(5) states:
"Rejection: If any stores are rejected as
aforesaid then, without prejudice to the
foregoing provisions, the Secretary,
Department of Supply shall be at liberty to
:--
228
(a) allow the contractor to resubmit stores in
replacement of those rejected within a time
specified by the Secretary, Department of
Supply, the contractor bearing the cost of
freight in such replacement without being
entitled to any extra payment, or
(b) buy the quantity of the stores rejected or
others of a similar nature elsewhere at the
risk and cost of the contractor without
affecting the contractor’s liability as
regards supply of any further consignment due
under the contract, or
(c) terminate the contract and recover from
the con- tractor the loss the purchaser
thereby incurs".
On behalf of the appellant Dr. Seyid Mohammad presented
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
the argument that the dispute regarding the respondent’s
claim in respect of the excess quantity of timber measuring
4,900 tons said to have been tendered but not inspected was
not a dispute ’arising under the contract" 0r ’in
connection with the contract’ and hence the arbitrators had
no jurisdiction to adjudicate upon that claim. It was stated
that the terms of contract did not require the respondent
firm to tender for inspection any quantity in excess of the
contracted quantity of timber and the alleged placing of
unlimited stocks of timber at the disposal of the
Government officials far in excess of the quantity ordered
was beyond the scope of the contract. It was argued that
the claim should be treated as a claim relating to a
transaction of involuntary bailment and not to anything done
in the performance. implementation or execution of the
contract. It was said that the claim for return of these
goods and damages for deterioration or in the alternative
for their market value was a claim in detinue and the
dispute was not hence a dispute "arising out of the
contract" or ’in connection with the contract’ but was a
dispute relating, to a tort of wrongful detention. We do
not think that there is any justification for the argument
put forward on behalf of the appellant. In our opinion. the
claim made by the respondent firm was a claim arising out of
the contract. The test for determining the question is
whether recourse to the contract by which both the parties
are bound is necessary for the purpose of determining
whether the claim of the respondent firm iS justified or
otherwise. If it is necessary to take recourse to the terms
of the contract for the purpose of deciding the matter in
dispute. it must be held that the matter is within the scope
of the arbitration clause and the arbitrators have
jurisdiction to decide this case. In Herman & lint. v.
Darwins Ltd.(1) the law on the point is very clearly stated
in the following passage:
(1) [1942] A.C. 356 at 365.
229
"An arbitration clause is a written
submission agreed to by the parties to the
contract, and, like other written submissions
to arbitration, must be construed according to
its language and in the light of the
circumstances in which it is made. if the
dispute is whether the contract which contains
the clause has ever been entered into at all,
that issue cannot go to arbitration under the
clause, for the party who denies that he has
ever entered into the contract is thereby
denying that he has ever joined in the
submission. Similarly, if one party to the
alleged contract is contending that it is
void ab initio (because, for example, the
making of such a contract is illegal), the
arbitration clause cannot operate, for on this
view the clause itself also is void. But, in
a situation where the parties are at one in
asserting that they entered into a binding
contract, but a difference has arisen between
them whether there has been a breach by one
side or the other, or whether circumstances
have ,arisen which have discharged one or both
parties from further performance, such
differences should be regarded as differences
which have arisen ’in respect oF or "with
regard to", or "under" the contract, and an
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
arbitration clause which uses these, or
similar expressions should be construed
accordingly".
In Stebbing v. Liverpool & London and Globe Insurance
Company Ltd. (1) the policy of insurance contained a clause
referring to the decision of an arbitrator "all differences
arising out of this policy". It also contained a recital
that the assured had made a proposal and declaration as the
’basis of the contract, and a clause to the effect that
compliance with the conditions indorsed upon the policy
should be a condition precedent to any liability on the part
of the insurers. One of the conditions provided that if any
false declaration should be made. e or used in support of a
claim all benefit under the policy should be forfeited. In
answer to a claim by the assured, the insurers alleged that
statements in the proposal and declaration were false. When
the matter came before tire arbitrator, the assured
objected that this was not a difference in the arbitration
and that the arbitrator had no power to determine whether
the answers were true or not, or to determine any matters
which called in question the validity of the policy. In
holding that the arbitrator had jurisdiction to decide the
matter, Viscount Reading, C.J. observed:
"If the company were seeking to avoid the
contract in the true sense they would have to
rely upon some matter outside the, contract,
such as a misrepresentation
(1) [1917] 2 K.B. 433.
230
of some material fact, inducing the contract,
of which force and effect are not declared by
the contract itself. In that case the
materiality of the fact and its effect in
inducing the contract would have to be tried.
In the present case the company are claiming
the benefit of. a clause in the contract when
they say that the parties have agreed that the
statements in question are material and that
they induced the contract. If they succeed in
escaping liability that is by reason of one
of the clauses in the policy. In resisting
the claim they are not avoiding the policy but
relying on its terms. In my opinion,
therefore, the question whether or not the
statement is true is a question arising out of
the policy".
The principle has been reiterated by this Court in Ruby
General Insurance Co’. Ltd. v. Pearey Lal Kumar & Anr.(1).
In that case the appellant company insured a car belonging
to respondent No. 1 and issued the policy which contained,
inter alia, the following terms :-
"All differences arising out of this
policy shall be referred to the decision of an
arbitrator to be appointed by the
parties .... If the company shall disclaim
liability to the insured for any claim
hereunder and such claim shall not within
twelve calendar months from the date of such
disclaimer have been referred to arbitration
then the claim shall have been deemed to have
been abandoned and shall not be recoverable".
The car was lost and company through its Branch Manager dis-
claimed liability on three different dates. The insured did
not take any action in regard to the appointment of an
arbitrator until more than twelve months after the last
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
disclaimer by the company.The case of the company was that
the insured must be deemed to have abandoned his claim by
virtue of the contract of insurance policy while the
respondent averted that there was never any valid disclaimer
by the company of its liability as the Branch Manager had no
authority to disclaim the liability and it could have been
disclaimed only by the resolution of the company. The
company made an application under s. 33 of the Indian
Arbitration Act praying for a declaration that the reference
to arbitration was illegal and the award if made by the
arbitrator would not bind the company. It was contended on
its behalf that the arbitration clause had ceased to be
operative and the question as to the existence and validity
of the arbitration agreement was triable by the court under
s. 33 of the Arbitration Act and not by the arbitrator. The
argument was rejected by this Court. It was held that the
point on which the parties were in dispute was a difference
(1) [1952] 3.C.R. 501.
231
arising out of the policy, because recourse to the contract
by which both the parties were bound was necessary for the
purpose of determining the matter in dispute between them.
As there was no contention raised by either of the parties
that there was no contract entered into at all or that it
was void ab initio the arbitrator had jurisdiction to decide
the matter referred to him. In our opinion, the principle
applies to the present case and it follows that the dispute
between the parties falls within the scope of the
arbitration clause.
On behalf of the appellant reliance was ’placed upon the
decision of Court of Appeal in Percy v. Young(1) in which it
was held that the clause "that any differences or disputes
that may arise between the partners shah be settled by an
arbitrator" does not include a dispute whether the
partnership has been terminated, or whether certain shares
have been paid on account to the partnership or to one
partner alone. In our opinion, the principle does not apply
in the present case where the question presented for
determination is quite different. Counsel for the appellant
also referred to Turnock v. Sartoris(2). In that case the
lessor was under a covenant to supply his lessee with a
specific quantity of water. The lease contained a
comprehensive arbitration clause. Dispute having arisen as
to the supply of water, an agreement was subsequently
entered into, binding the lessor to take certain steps to
secure the supply and varying the rights of the parties in
respect of the supply. The lessee brought an action
alleging that the steps agreed upon had not been taken and
that he had not been fully supplied with water and asking
for an action of the .damages to be taken. The lessor moved
to have the action stayed. lit was held that the disputed
matters arose partly under the agreement and were outside
the arbitration clause in the lease and that even if all the
matters for which damages were claimed could be brought
within the arbitration clause it would not be proper to
refer them to an arbitration who would not have the
authority to construe the agreement to determine its effect
upon the lease. It is manifest that the decision has no
bearing upon the question p.resented for determination in
the present case.
For the reasons. already expressed, we hold that the
claim of the respondent firm was within the scope of the
arbitration clause and the application made by the appellant
in Suit No. 128 of 1963 was. rightly dismissed by the
Subordinate Judge. Accordingly, the appeal fails and is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
dismissed with costs.
V.P.S. Appeal dismissed.
(1) 14 oh. D. 200.
(2) 43 Cn. D. 150.
232