M/S PENNA ELECTRICITY LTD.(NOW M/S PIONEER POWER LTD.) vs. TAMILNADU ELECTRICITY BOARD

Case Type: Civil Appeal

Date of Judgment: 15-03-2023

Preview image for M/S PENNA ELECTRICITY LTD.(NOW M/S PIONEER POWER LTD.) vs. TAMILNADU ELECTRICITY BOARD

Full Judgment Text

NON­REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO(S). 706 OF 2014 M/S PENNA ELECTRICITY LIMITED (NOW M/S PIONEER POWER LIMITED) ….APPELLANT(S)                VERSUS THE TAMIL NADU ELECTRICITY  BOARD & ORS. ….RESPONDENT(S) J U D G M E N T Rastogi, J. 1. The instant appeal has been filed under Section 125 of the Electricity Act, 2003(hereinafter being referred to as the “Act 2003”) assailing   the   judgment   and   order   of   the   Appellate   Tribunal   for Electricity dismissing the appeal filed at the instance of the present Signature Not Verified Digitally signed by Jayant Kumar Arora Date: 2023.03.15 16:02:39 IST Reason: appellant. 1 2. The appellant initially filed a petition under Section 86(1)(f) of the Act, 2003 and sought the following reliefs:­ (a) direct   the   Respondent   to   make   the   payment   of   Rs.25.63 Crores towards fixed charges and Rs.8.10 Crores towards payment   due   on   the   actual   variable   charges   payable   in respect   of   the   power   generated   and   availed   for   153.26 millions unit during the period 29.10.2005 to 30.06.2006 to the Petitioner. (b) direct   the   Respondents   to   make   the   payment   to   the Petitioner   of   the   sum   of   Rs.18.06   Crores   towards   under recovered   fixed   charges   in   respect   of   operations   of   the generating station of the Petitioner for the period 01.07.2006 to 15.06.2009. (c) direct   the   Respondents   to   make   the   payment   to   the Petitioner   of   the   sum   of   Rs.12.77   crores   towards   under recovered additional cost of generation (variable charges) in respect of operations of generating Station of the Petitioner for the period 01.07.2006 to 15.06.2009. (d) direct the respondent to take immediate decisions on the use of   Naphtha   or   any   other   compatible   fuel   as   alternate/ supplemental fuel to increase and maintain the PLF of the plant   as   contemplated   in   the   amending   PPA   dated 25.08.2004   in   future   thereby   enabling   the   plant   being operated at optional level so as to ensure the advantage to the   Respondent   and   also   the   assured   return   to   the Petitioner.     The permission to use of the Naphtha/other compatible   fuel   should   also   contemplate   dispatching   the plant under merit order under gas based tariff only.  If the Respondent   desires   otherwise,   the   Petitioner   should   be assured of the fixed charges. (e) For any reason if the Respondent were not to consider any or all of the relief claimed above by the Petitioner, to direct the Respondent to make the payments due to the Petitioner as in prayer (a), (b) and (c) above and relieve the Petitioner from the obligations of the amendment PPA dated 25.08.2004. 2 3. The   Tamil   Nadu   Electricity   Regulatory   Commission   thereby th disposed   of   the   petition   by   order   dated   30   December   2011, rejecting the claim of the appellant relating to unpaid fixed charges of Rs.18.06 under Combined Cycle Operation as well as the claim of underpaid variable charges of Rs. 12.77 crores under Combined st th Cycle Operation for the period between 1  July, 2006 to 15  June, 2009. 4.   This came to be challenged by the appellant in appeal before the Appellate Tribunal for Electricity(hereinafter being referred to as the “Tribunal”).   After the matter came to be heard, taking into consideration   the   material   on   record,   the   Tribunal   returned   a finding in paras 35, 36 and 38(1) and (2), and dismissed the appeal under the impugned judgment.  The relevant paras are as under:­ “35. We   find   that   there   is   no   provision   for   compensation   for capacity charges and variable charges due to the fact that the plant was not able to maintain the normative availability/Plant Load   Factor   on   account   of   shortage   of   fuel   in   the   Central Commission’s Tariff Regulations, 2004 which were in vogue when the amended PPA was entered into between the parties or in the Sate Commission’s Tariff Regulations, 2005.  Admittedly, the State Commission’s Tariff Regulations were made effective subsequent to the signing of the PPA. The State Commission could not intervene 3 in allowing amendment in the provisions of the PPA in this regard which were voluntarily agreed by both the parties and which are not in contravention to any provision of the Act or Rules or the Regulations. 36. Therefore, there is no infirmity in the findings of the State Commission in not agreeing to interfere with the provisions of the PPA declaring the PPA unworkable with regard to compensation for fixed charges for the above period due to shortage of supply of gas. 37. xxx xxx 38. Summary of Our Findings i) The Appellant is not entitled to payment of full fixed charges and actual variable charges in respect of supply of energy between   1.7.2006   to   15.6.2009   when   the   operational parameters were affected on account of shortage supply of gas by M/s GAIL in view of non availability of any provision in this regard in the PPA or Tariff Regulations. ii) There is no infirmity in the findings of the State Commission in not agreeing to interfere with the provisions of the PPA or declaring the PPA unworkable with regard to compensation for fixed and variable charges for the above period due to shortage of supply of gas.” 5. Mr. Parag P. Tripathi, learned senior counsel for the appellant submits   that   in   the   absence   of   any   clause/provision   under  the th amended   Power   Purchase   Agreement   dated   25   August, 2004(hereinafter   being   referred   to   as   the   “PPA”)   in   reference   to payment of fixed charges, it was incumbent upon the Tribunal to have   considered   that   the   short   supply   of   gas   was   due   to   the diversion of gas to other generating stations and on this account the 4 Tamil Nadu Electricity Board (hereinafter being referred to as the “Board”) could not have made the appellant to suffer by citing the terms   of   the   PPA.     However,   the   Tribunal   omitted   to   note   the unimpeachable evidence and it has not been disputed before the Tribunal that the short supply of gas was due to the diversion of gas   to   the   generating   stations   of   Board   and   the   appellant   has suffered financial losses due to the diversion of gas to the other generating stations. 6.   Learned   counsel   further   submits   that   there   was   sufficient evidence   on   record   regarding   the   communication   between   Gas Authority of India Limited(GAIL) and the Board in reference to the diversion of gas to other generating stations and this has seriously impaired the functionality and efficiency of the appellant company. 7. Learned counsel further submits that it cannot be disputed that the generating station of the appellant is capable of achieving the technical parameters and 85% of Plant Load Factor(hereinafter referred   to   as   the   “PLF”).     In   the   aforesaid   premise,   the   Board cannot be allowed to take benefit due to its own wrong at the cost of the appellant Company. 5 8. Learned counsel further submits that the amended PPA dated th 25  August, 2004 was not approved in terms of Section 86(1)(b) of the Act 2003 still it is a binding document between the parties inter se and since the electricity was sold to the Board otherwise than as a gratuitous act, Board needs to pay for the same on the principle of  Quantum Meriut .   In support of his submissions, learned counsel has placed reliance on the judgment of this Court in  State of West 1 Bengal  Vs.  B.K. Mondal and SonsUnion of India  Vs.  Sita Ram 2  and  Jaiswal Food Corporation of India and Others  Vs.  Vikas 3 Majdoor Kamdar Sahkari Mandli Limited . 9. Learned counsel further pressed that even in the absence of PPA   not   been   approved   and   enforceable,   still   the   compensation payable to the appellant ought to be computed as per the tariff fixed by the Commission for open market purchases by Board, or at least in   accordance   with   the   relevant   regulations   and   this   being   the manifest error which the Tribunal has committed in rejecting the claim of the appellant needs to be interfered by this Court. 1 1962(Suppl) 1 SCR 876 2 1976(4) SCC 505 3 2007(13) SCC 544 6 10. Per   contra,   learned   counsel   for   the   respondents,   while supporting the concurrent finding returned by the Commission and confirmed by the Tribunal under the impugned judgment submits that the appellant has failed to meet the PLF as agreed to under the PFA ­ apart from the fact that admittedly PPA was not approved under the Act 2003.   That apart, there is no clause in the PPA which provides for payment of full fixed cost, even when generator fails   to   meet   the   PLF.     Any   compensation   by   way   of   deemed generation or relaxed heat rate due to partial loading of machine due   to   shortage   of   fuel   supply   is   the   sole   responsibility   of   the appellant. 11.   Learned counsel further submits that the shortfall in PLF and increase in tariff heat rate was due to two factors, (i) poor efficiency of the power plant; and (ii) short supply of natural gas by fuel st supplier(GAIL).  Further, during the period between 1  July, 2006 rd and   23   October,   2007,   sufficient   quantity   of   natural   gas   was available to the appellant in order to operate the power at 52.8 MW (the contracted capacity) but tariff heat rate of the plant was always more than 1980 Kcal/Kwr due to its poor efficiency of the plant. 7 The PLF achieved  by the appellant’s power  plant  for  the period st st between 1  July, 2006 and 1  July, 2009 is as under:­
Period ConcernedPLF Achieved
1st July, 2006 to 30th June,<br>200780.82%
1st July, 2007 to 30th June,<br>200873.20%
1st July, 2008 to 1st July, 200967.09%
12.   In the given circumstances, the respondents cannot be held responsible to meet the short supply of gas to the appellant.  Thus, issue of short supply of gas as alleged is an issue between GAIL and the appellant.  It was submitted that the inability of the appellant to achieve 85% of the PLF is not due to any  Force Majeure  as claimed. More so, the appellant never initiated any proceedings under the clause of  Force Majeure  as per procedure provided under the PPA. 13. In addition,   learned  counsel further  submits  that PPA was entered   into   between   the   parties   based   on   notification   of th Government of India dated 6  November, 1995.  Therefore, claim of compensation by way of deemed generation due to shortage in fuel 8 supply is the responsibility of the generator and not applicable in th terms   of   PPA   dated   25   August,   2004.     Therefore,   the   State Commission’s   refusal   to   allow   claim   of   underpaid   charges   and variable   charges   is   well   founded   and   rightly   confirmed   by   the Tribunal under the impugned judgment. 14. We have heard learned counsel for the parties and with their assistance perused the material available on record. 15. From   the   facts,   it   manifest   that   the   appellant   is   an Independent   Power   Producer(IPP)   operating   and   maintaining   a Combined Cycle Gas Turbine Power Generating station in Tamil Nadu   with   a   generating   capacity   of   52.8   MW   and   the   said generating station is dedicated to the Board and the entire power generated by the appellant is to be supplied to the Board. th 16. It is not disputed that the PPA dated 25   August, 2004 was not approved under Section 86(1)(b) of the Act 2003.  That apart, there is no clause in the PPA which provides for full fixed cost, even when appellant fails to meet the PLF.  PPA between the parties was th entered   based   on   notification   of   Government   of   India   dated   6 November, 1995 and in terms of clause 4.3 of the said notification, 9 the   responsibility   of   the   fuel   linkage   would   be   that   of   the independent power producer and any fuel supply risk would have to be shared between the power and fuel producer/supplier and not by the Board to indemnify. 17. There is a bi­partite agreement executed between appellant and the GAIL, to which the respondent Board is not privy, and if any default has been committed by GAIL in supply of natural gas to the appellant, the respondent Board is not supposed to indemnify, that apart, there is nothing on record to show that any remedial action   was   taken   by   the   appellant   against   the   gas   supplier   on account of short supply of gas, if permissible under the law. 18. At   the   same   time,   the   appellant   has   not   been   able   to demonstrate any provision either under the Act, 2003 or under the PPA although has not been approved by the competent authority under the Act, 2003 which may protect the right and interest of the appellant.  That apart, no clause of the PPA has been pointed out indicating if there is a short supply of gas due to diversion of gas to the other generating station of the Board, the respondent Board has to indemnify the appellant.  10 19. The thrust of submission of learned counsel for the appellant that it is the respondent Board who have sent letters to the GAIL to divert the gas to other generating units of the Board, at least on this account, the Board could not have made the appellant to suffer by citing the terms of the PPA.   There is no dispute that the project th was taken over on the basis of the notification dated 6  November, 1995 issued by Government of India and in terms of para 4.3 of the notification, the fuel of the power project was either fuel oils or natural gas.  The said clause of the Notification is as under:­ “4.3   The   responsibility   of   either   indigenous   or   imported   fuel linkage would be that of the Independent Power Producer(IPP) and any   fuel   supply   risks   would   have   to   be   shared   between   the IPP/Fuel suppliers.  The State Electricity Board will not take any fuel supply risk.” 20. In terms of the notification referred to above, it is clear that the responsibility of fuel linkage ­ either heavy fuel or natural gas ­ would be that of the appellant to the generator.  If there is any risk in the supply, the same has to be shared between the generator and the fuel supplier.  The notification has classified that the Board will not take any fuel supply risk and is not supposed to indemnify in the given situation.   11 21. It is also not disputed that there is no clause in PPA which provides for payment of full fixed cost to the generator, even when generator fails to meet the PLF.   In the given circumstances, any compensation by way of deemed generation or released heat rate due to partial loading of machine, arising due to shortage to fuel supply   which   is   the   sole   responsibility   of   the   appellant,   is   not th applicable   as   per   the   amended   PPA   dated   25   August,   2004. Furthermore,   there   is   no   provision   for   compensation   by   way   of deemed generation or partial norms due to operation of the power plant at partial load due to shortage of fuel in Central Government’s Tariff Regulations, 2004 which admittedly were in force when the agreement was entered into between the parties.   22. The submission made by learned counsel for the appellant that because of the diversion of gas to the other generating stations of the Board, at least on this account, the Board could not have made the appellant to suffer by citing the terms of PPA, on the first blush appears to be attractive but has no legs to stand for the reason   that   in   the   absence   of   there   being   any   provision   for compensation for capacity charges and variable charges due to the 12 fact   that   the   plant   was   not   able   to   maintain   the   normative availability/PLF   on   account   of   shortage   of   fuel   in   terms   of   the Central   Government’s   Tariff   Regulations,   2004,   at   least   the respondent Board cannot be said to be at fault and that was the reason prevailed upon the Commission to arrive at the conclusion that the appellant was not entitled to payment of fuel fixed charges and actual variable charges in respect of supply of energy between st th 1  July, 2006 and 15  June, 2009 during the period when partial parameters were rejected because of shortage of supply in view of the provision in PPA or tariff regulations. 23. We find no infirmity in the finding returned by the Tribunal in the impugned judgment which may call for our interference.  24. Consequently, the appeal fails and is accordingly dismissed. No costs. 25. Pending application(s), if any, shall stand disposed of. …………………………….J. (AJAY RASTOGI) 13 …………………………….J. (C.T. RAVIKUMAR) NEW DELHI; MARCH 15, 2023   14