Full Judgment Text
1
Reportable
IN THE SUPREME COURT OF INDIA
EXTRAORDINARY CIVIL JURISDICTION
Special Leave Petition (C) No.27337 of 2017
E. Jeevanandam …Petitioner
Versus
N. Koteswara Rao & Ors. …Respondents
AND WITH
Special Leave Petition (C) No.35197 of 2017
O R D E R
Dr Dhananjaya Y Chandrachud, CJI
1 The petitioner was the Chairperson of the erstwhile Maduravoyal Town
Panchayat. On 28 November 2001, during his tenure as Chairperson, a resolution
was passed by the local body to provide sewerage facilities to the area enclosing
a list of streets in which ward No 147 of Rukmani Nagar Road, Chennai was
Signature Not Verified
Digitally signed by
CHETAN KUMAR
Date: 2023.01.30
17:07:27 IST
Reason:
2
included. A scheme was prepared in terms of the request made by the local body.
2 On 3 June 2009, the Government accorded administrative sanction for
spending an amount of Rs 57.45 crores. The scheme commenced on 18 August
2009. Sewerage facilities were laid since there was no objection except for an area
covering 110 meters at Rukmani Nagar Road. The sewerage main was laid down
both upstream and downstream of Rukmani Nagar except to the extent of the 110
meters. The petitioner purchased the property in 2011, inclusive of the road over
which the proposed sewerage line was sought to be laid.
3 Certain civil disputes are pending before the civil court as regards the claim
of the petitioner in regard to the ownership of the land. Notice was issued to the
petitioner under Section 67(3) of the Chennai Metropolitan Water Supply &
1
Sewerage Act, 1978 . The petitioner suggested that an alternative route should be
taken for laying the sewerage line. On 19 June 2015, an order was passed invoking
the provisions of Section 67(3) of the 1978 Act. This gave rise to a writ petition at the
behest of the petitioner.
4 During the course of the hearing of the writ petition, the Single Judge was
informed that almost the entire work was completed save and except to the extent
of 110 meters along the Rukmani Nagar Road. The Single Judge held that the
1
“1978 Act”
3
residents of three streets would be deprived of sewerage facilities if a realignment
as sought by the petitioner were to be granted. The Single Judge observed as
follows:
“Residents of the three streets would be deprived of the
facility if the realignment as sought for by the petitioner is
undertaken. The road has been shown as a public road as
stated in the counter affidavit filed, through various
documents. In fact it has been shown as such. Even during
the tenure of the chairmanship of the petitioner, the scheme
was contemplated and proposed by the local body. The
road has also been relaid by the local body on two
occasions. It is only a link road between Ganga Nagar and
Rukmani Nagar.”
5 After noting that the petitioner was himself a party to the resolution in 2001 in-
spite of which he had purchased the property in 2011, the Single Judge dismissed
the petition. The Single Judge observed that prima facie it appeared that there
was a public road which was being used for the last few decades and the
petitioner who had dealt with the issue in a different capacity in 2001 could not be
stated to be unaware of the laying of the sewer line, having purchased the
property subsequently in 2011.
6 The petitioner instituted an appeal against the order of the Single Judge. On
27 April 2017, a Division Bench of the High Court disposed of the appeal by
directing the State government to choose a better option so as to minimize the
4
damage that could be caused to the petitioner by laying the sewer main and
sewer pumping station in the land of the petitioner.
2
7 In the meantime, a Pubic Interest Litigation was instituted before the High
Court of Judicature at Madras. The petitioner was impleaded as sixth respondent to
the writ petition. The PIL was instituted on behalf of the residents of Ward No. 147
who sought a direction for the completion of the underground drainage work so as
to enable them to have the benefit of a sewerage facility. The residents submitted
that 15,000 families were affected because of the failure to lay pipelines along the
stretch of the 110 meters connecting the underground drainage to the pumping
station.
8 The Division Bench in its judgment dated 3 October 2017, adverted to the writ
petition instituted by the petitioner which was dismissed by the Single Judge of 4
April 2017. The Division Bench also noted that there was an appellate order of 27
April 2017. After having noticed the provisions of the statute, the Division Bench
disposed of the writ petition by directing the Board to lay the pipelines and
complete the underground drainage within three months. The last paragraph of
the order indicates that the petitioner was directed to be impleaded as the sixth
respondent, together with the final order disposing of the petition.
2
“PIL”
5
9 The challenge in the first Special Leave Petition is to the order of the Division
Bench dated 3 October 2017 by which the authorities have been directed to
complete the laying of the drainage line. The companion Special Leave Petition
has been instituted by the Chennai Metropolitan Water Supply & Sewerage Board
for challenging the order dated 27 April 2017 of the Division Bench.
10 As regards the first of the two Special Leave Petitions under Article 136 of the
Constitution, the petitioner does have a legitimate grievance that an order was
passed in the PIL directly affecting the rights of the petitioner without furnishing an
adequate opportunity of being heard. As noted earlier, the order for the
impleadment of the petitioner was passed when the PIL was disposed of finally on 3
October 2017.
11 Ordinarily, we would have been inclined to set aside the impugned order of
the High Court and to remit the proceedings back for fresh consideration. That
however would not resolve the substance of the controversy. When the Special
Leave Petition arising from the order of the Division Bench dated 3 October 2017
was entertained by this Court on 27 October 2017, while issuing notice, the Court
observed that if the petitioner succeeds, he shall be entitled to compensation in
accordance with law. In the absence of an order of stay, the work of laying the
sewerage line has been completed. The developmental work which has been
6
carried out by the Board is in the form of a public amenity to the residents of the
area. The title of the petitioner is by no means free from doubt since it is the subject
matter of a civil dispute.
12 In this backdrop, setting aside the impugned order of the Division Bench
would give rise to further complications since at this stage it would be difficult to
restore the status quo ante by directing the removal of the sewerage line.
Ultimately, the claim of the petitioner at the highest would be for the payment of
damages and for compensation for the laying of the sewerage line subject to the
rights of the petitioner to the property being established in accordance with law.
13 For the above reasons, having heard Ms Kiran Suri, senior counsel appearing
on behalf of the petitioner and Mr Jaideep Gupta, senior counsel appearing on
behalf of the Board, we are of the considered view that the relief which should be
granted to the petitioner would be to allow him the liberty to pursue his rights and
remedies in accordance with law for establishing a case of compensation and for
the award of damages subject to his rights to the land being established in a
competent court.
14 The challenge by the Board to the order of the Division Bench dated 27 April
2017 does not require to be enquired into at this stage in view of the subsequent
developments; the work of laying the sewer line having been duly completed.
7
15 Both the Special Leave Petitions shall accordingly stand disposed of subject
to the above observations by which the Court has granted liberty to the petitioner
in the first Special Leave Petition to pursue his claim for compensation in
accordance with law and for establishing his title to the land on which the
sewerage line has been laid.
16 Pending applications, if any, stand disposed of.
…….…..………………………………CJI
[Dr Dhananjaya Y Chandrachud]
……..……………………………………J
[V Ramasubramanian]
…….……………………………………J
[J B Pardiwala]
New Delhi;
January 23, 2023