Full Judgment Text
REPORTABLE
2024 INSC 532
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 7821 OF 2024
(ARISING OUT OF SLP (C) NO. 3792 OF 2024)
SBI GENERAL INSURANCE CO. LTD. …APPELLANT
VERSUS
KRISH SPINNING …RESPONDENT
WITH
CIVIL APPEAL NO. 7822 OF 2024
(ARISING OUT OF SLP(C) No. 7220 OF 2024)
J U D G M E N T
Signature Not Verified
Digitally signed by
Sanjay Kumar
Date: 2024.07.18
14:54:23 IST
Reason:
J. B. PARDIWALA, J.:
For the convenience of exposition, this judgment is divided into the following
parts: -
INDEX
A. FACTUAL MATRIX ............................................................................................. 3
B. SUBMISSIONS ON BEHALF OF THE APPELLANT ................................... 14
C. SUBMISSIONS ON BEHALF OF THE RESPONDENT ............................... 16
D. ISSUES FOR DETERMINATION .................................................................... 18
E. ANALYSIS ............................................................................................................ 19
i. Whether the execution of a discharge voucher towards the full and final settlement
between the parties would operate as a bar to invoke arbitration? ...................... 21
a. Whether the arbitration agreement contained in a substantive contract survives even
after the underlying contract is discharged by “accord and satisfaction”? .............. 25
ii. What is the scope and standard of judicial scrutiny that an application under
Section 11(6) of the Act, 1996 can be subjected to when a plea of “accord and
satisfaction” is taken by the defendant? .................................................................. 31
iii. What is the effect of the decision of this Court in In Re: Interplay Between
Arbitration Agreements under the Arbitration and Conciliation Act 1966 and the
Indian Stamp Act 1899 on the scope of powers of the referral court under Section
11 of the Act, 1996? .................................................................................................... 65
a. Arbitral Autonomy ........................................................................................ 66
b. Negative Competence-Competence .............................................................. 69
c. Judicial Interference under the Act, 1996 ..................................................... 71
F. CONCLUSION .................................................................................................... 84
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 1 of 85
1. Leave granted.
2. Since the issues raised in both the captioned appeals are the same, the
subject-matter also being the same and the parties are also the same, they
were taken up analogously for hearing and are being disposed of by this
common judgment and order.
3. The SLP(C) No. 7220 of 2024 arises from the impugned judgment and
order dated 22.09.2023 passed by the High Court of Gujarat at Ahmedabad
in Arbitration Petition No. 209 of 2021 wherein the High Court after
assigning detailed reasons for allowing the application filed by the
respondent for the appointment of an arbitrator, directed that the said
application be listed before the appropriate bench in accordance with the
roster for the purpose of passing appropriate order for appointment of
arbitrator.
4. The SLP(C) No. 3792 of 2024 arises from the impugned judgment and
order dated 01.12.2023 passed by the High Court of Gujarat at Ahmedabad
in Arbitration Petition No. 209 of 2021 wherein relying upon the judgment
and order dated 22.09.2023 referred to above passed by a co-ordinate
bench in the self-same arbitration application, the High Court allowed the
application of the respondent for the appointment of an arbitrator and
thereby appointed Justice K.A. Puj, former Judge of the High Court of
Gujarat as an arbitrator to resolve the disputes between the parties.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 2 of 85
A. FACTUAL MATRIX
5. The appellant, SBI General Insurance Co. Ltd., is a Private Sector General
Insurance Company engaged in the business of providing general
st
insurance to its customers, having one of its offices at 1 floor, Shukan
Business Centre, Swastik Cross Road, C.G. Road, Navrangpura,
Ahmedabad.
6. The respondent, M/s Krish Spinning, is a partnership firm registered under
the provisions of the Indian Partnership Act, 1932, and is engaged in the
business of manufacturing and spinning of cotton filaments at its factory
premises situated at Survey No. 845, Ghodasar, Nenpur, Taluka
Memdabad.
7. The respondent obtained a standard fire and special perils (material
damage) insurance policy from the appellant on 31.03.2018 for a total sum
insured of Rs 7,20,00,000/- with the period of insurance being 31.03.2018
to 30.03.2019.
8. During the period of insurance cover, two incidents of fire took place at the
factory premises of the respondent, as a result of which the respondent
suffered loss of assets such as cotton stocks in the form of raw materials,
semi-finished goods, electrical installations, plant and machinery.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 3 of 85
9. The first incident of fire took place on 28.05.2018 in which the respondent
claims to have suffered a total loss amounting to Rs 1,76,19,967/-. The
second incident of fire took place on 17.11.2018 wherein the respondent
claims to have suffered a total loss amounting to Rs 6,32,25,967/-. It is
pertinent to observe that the present appeals pertain only to the dispute
arising from the settlement of claim relating to the first incident of fire
which took place on 28.05.2018.
10. After the first incident of fire that took place, M/s Paresh Shah & Associates
was appointed as the surveyor by the appellant company on 29.05.2018 under
Section 64UM of the Insurance Act, 1938. The surveyor visited the factory
premises of the respondent on a number of occasions between 29.05.2018 and
29.08.2018 for the purpose of assessing the extent of loss suffered by the
respondent in the fire accident, and accordingly prepared the final survey
report dated 30.12.2018. In the said report, it was inter alia observed that the
fire could not have been caused by any external factor, and that it could have
been caused by spontaneous combustion due to humid temperatures. The
quantum of loss suffered by the respondent, after accounting for deductions
under multiple heads was assessed by the surveyor at Rs 84,19,579/-.
11. Although the respondent had initially submitted its claim bill dated
27.07.2018 claiming Rs 1,76,19,967/- from the appellant, yet on
24.12.2018, a consent letter was issued by the respondent to the surveyor
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 4 of 85
accepting the assessment of loss made by the surveyor, i.e., at Rs
84,19,579/-. In the consent letter, the respondent stated that in view of the
detailed discussion it had with the surveyor as regards the volumetric
calculation of the quantity of cotton bales said to have been damaged, it
was ready to accept the quantity to be 3,17,085.30 kg as against its initial
claim of 4,41,111.58 kg.
12. After addressing the consent letter as aforesaid to the surveyor, the
respondent signed an advance discharge voucher dated 04.01.2019,
confirming the receipt of Rs 84,19,579/- from the appellant as the full and
final settlement towards their claim. The discharge voucher also stated,
inter alia, that the respondent was discharging the appellant of the liability
arising under its claim.
13. Subsequent to the signing of the advance discharge voucher, the appellant
released the claim settlement amount of Rs 84,08,957/- on 31.01.2019.
14. Thereafter, in relation to the claim arising out of the second fire incident,
the appellant released a total amount of Rs 4,86,67,050/- in three
instalments. The third and final instalment of Rs 2,23,67,050/- was
released on 14.10.2019.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 5 of 85
15. On 25.10.2019, that is eleven days after the receipt of the third and final
instalment in relation to the claim arising out of the second fire incident,
the respondent dropped one letter by hand delivery at the office of the
appellant. The respondent, inter alia, stated in the said letter that a copy of
the surveyor’s final assessment report was not provided to it despite earlier
requests. The respondent alleged that it had to sign the final discharge
voucher as it was badly in need of money. The respondent further stated in
its letter that it had been unable to take any action due to non-receipt of the
surveyor’s report. The appellant refused to accept the letter and returned it
back to the respondent. The contents of the letter are reproduced
hereinbelow:
“Date:- 25/10/2019
To,
The Manager,
SBI General Insurance Company,
Ahmedabad.
Subject: - Fire claim no.513768 for loss dated 28/05/2018.
Respected Sir,
In connection to the above, we have requested you to
provide the copy of the complete survey report along with
all enclosures thereof to enable us to understand the
calculations made by the surveyor to arrive at the gross
and net loss / damage. Please note that despite our request,
we have not received the copy of survey report, which
shows your arrogant approach.
At this stage, we wish to inform you that you have taken
our consent on the amount assessed by the surveyor. We
have signed the working sent by you. During the said
period, there was another fire in our factory, in which the
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 6 of 85
entire stock, building, plant and machinery have been
damaged and we were badly in need of money, hence
considering you being a reputed insurance company, you
must have examined the assessment made by the surveyor
and on that trust bearing in mind, we have signed the
working sheet of assessments and voucher is also signed
by us in your office as you have informed that we would
get the payment immediately. But the same was also
delayed beyond reasonable time.
Now, since our auditors and bankers would like to know
the grounds considering which, the balance amount of our
claim is not considered by you / surveyor, you are once
again requested to provide the copy of survey report along
with all the documents submitted to you by the surveyor,
based on which, the claim has been settled and paid by you.
Since we have not received the copy of surveyor report, we
are unable to take further action. Once again, you are
requested to provide the copy of survey report along with
all enclosures thereof.
Please consider this letter as a notice.
Yours Faithfully
For KRISH SPINNING”
16. The respondent, on the same day, sent an email to the appellant with a copy
of the aforesaid letter calling upon the respondent to take appropriate and
necessary action. The contents of the said email are reproduced
hereinbelow:
“Sir,
This is in reference to the above subject, today at around
04:00 pm, or personnel visited your office to hand over a
letter requesting you to provide the complete survey report
of our fire claim no.-513768 for loss dated 28/05/2018.
You, in turn returned the letter without accepting it, asking
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 7 of 85
to get the letter signed by our Mr. Ashwinkumar N. Kacha
and resubmit the same.
We wish to inform that Mr. Ashwinkumar Kacha is busy
with medical emergency, and we will submit the letter
signed by him, when he is relieved from the medical
emergency. Attached herewith, is the copy of the said letter
for your kind reference and necessary action.
Thanks & Regards”
17. The appellant replied to the aforesaid letter as well as the email vide the
letter dated 07.11.2019 refuting the allegations of the respondent by stating
that the assessment of loss was personally explained by the surveyor to the
representative of the respondent who in turn had taken an informed
decision of accepting the settlement amount and signing the consent letter
and the advance discharge voucher. A copy of the survey report was also
provided to the respondent along with the reply letter. The contents of the
said reply letter are reproduced hereinbelow:
“SBI GENERAL INSURANCE
Dt: 07/11/2019
To
M/s Krish Spinning
Survey No. 845, Nenpur Haidarvas Road,
Ghodsar Gam,
Tal: Mehmdabad,
Gujarat-387110
(M): 9377071329
Dear Sir,
Re: Claim No. 513768 under Policy No. 9006820 Date of
Loss: 28/05/2018 Sub: Reply of Your letter dated
25/10/2019
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 8 of 85
We refer to your letter dated 25/10/2019, wherein you have
made reference of previous communications asking for
copy of survey report. We have reviewed our records and
we regret to inform that we are not able to locate any
communication in our record through which a request was
made seeking copy of Survey Report of Surveyor M/s
Paresh Shah & Associates. Unless proved otherwise, we
are accordingly considering your letter dated 25/10/2019
as first communication requesting for copy of survey
report.
We reiterate that loss assessment was personally explained
to Mr. Ashwin kacha from your office on 24th December
2018 at our Ahmedabad office and only after
understanding the assessment, Mr. Kacha had taken an
informed decision of signing the consent letter. This
consent letter was also followed with an advance
discharge voucher which was submitted by your office in
response to our settlement offer.
Furthermore, the payment remittance for claim settlement
amount was carried out on 8th January 2019 which is
within 15 days from the date of submission of consent letter
and thus there was no delay beyond reasonable time as
alleged in your letter.
As requested in your referred letter, we are pleased to
attach copy of survey report that forms basis of claim
remittance. You may also note that loss assessment arrived
by surveyor in attached survey report is in line with loss
workings reviewed with Mr. Kacha.
Yours Sincerely
For SBI General Insurance Company Ltd.,
(Sd)
Authorized Signatory”
18. On 02.03.2020, the respondent issued a legal notice calling upon the
appellant to release the balance payment of the claim amount arising out
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 9 of 85
of the first fire incident. The respondent, in the said notice, alleged, inter
alia, that he had signed the consent letter and the advance discharge
voucher under the apprehension that if he would not have signed the said
documents, then the claim in relation to the second fire incident, which was
pending on the date of the signing of the discharge voucher, would have
been detrimentally affected. Thus, the discharge voucher could be said to
have been signed under coercion, undue influence, and without free will
and volition of the respondent. The respondent further stated that it had
sent the protest letter dated 25.10.2019 immediately after receiving the
final instalment in relation to the claim arising out of the second fire
incident. The respondent further stated that in the event of the appellant’s
denial or failure to pay the balance amount within a period of 15 days, the
legal notice should be treated as notice invoking arbitration.
19. The appellant replied to the aforesaid legal notice on 16.03.2020 refuting
the allegations made by the respondent, alleging them to be mala fide and
an after-thought. The appellant stated that the discharge voucher signed by
the respondent was unqualified and on his own free will and volition. It
was further stated by the appellant that the amount being claimed by the
respondent was not due in the first place, thereby making the dispute not
one of quantum but one of liability, and therefore the arbitration agreement
would not be attracted to the dispute raised.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 10 of 85
20. As the parties were unable to arrive at any amicable resolution of the
dispute, and as no arbitrator was nominated by the appellant in response to
the notice invoking arbitration, the respondent, on 25.10.2021 filed a
petition for the appointment of arbitrator under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (hereinafter “ the Act, 1996 ”)
before the High Court.
21. The case of the respondent before the High Court was that as against the
loss of Rs 1,76,19,967/- suffered by it, the appellant company paid only Rs
84,19,579/- and thus it was not completely indemnified. It was also argued
that the appellant had not explained why at the time of obtaining the
consent letter an amount of Rs 92,00,388/- was deducted from the total
amount claimed.
22. The appellant, on the other hand, contested the arbitration petition filed by
the respondent on the ground that the claim raised by the respondent herein
was stale and having once signed the consent letter dated 24.12.2018, it
was not open for it to turn around and raise a dispute. The appellant also
contended that it was open for the court to look into the question of
arbitrability at the stage of deciding the Section 11 petition.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 11 of 85
23. The High Court, having regard to the aforesaid submissions of the parties,
held that the dispute in question was falling in the realm of adjudication
and the same is the function to be discharged by an arbitrator. Placing
reliance on the decision of this Court in Oriental Insurance Company Ltd.
v. Dicitex Furnishing Ltd. reported in (2020) 4 SCC 621 , the High Court
held that if the dispute existing between the parties could be referred to
arbitration under the arbitration agreement, then appointment of arbitrator
has to follow. Some pertinent observations made by the High Court are
extracted hereinbelow:
| “6. Therefore, on one hand, the company has taken a stand | ||
|---|---|---|
| that the petitioner is paid the amounts due and payable under | ||
| the policy and that there is no need to refer the disputes to the | ||
| arbitration under clause 13 of the policy, on the other hand, | ||
| the petitioner disputes such case on various grounds. It was | ||
| stated that amount of Rs. 92,00,388/-is wrongfully deducted | ||
| while making payment of Rs. 84,19,579/ inasmuch as total | ||
| claim lodged was Rs. 1,76,19,967/-. | ||
| 6.1 Therefore, the above aspects indeed travels to the | ||
| adjudicatory realm, which is the function to be discharged by | ||
| the arbitrator. When the claim is disputed, it is the arbitrator | ||
| who may competently decide the claim. Arbitrability of the | ||
| dispute is also to be decided by the arbitrator. While | ||
| exercising the powers under section 8 of the Arbitration and | ||
| Conciliation Act, 1996, such questions cannot be gone into | ||
| by this Court and when there is an arbitration clause, the | ||
| aspects are to be decided by the arbitrator for such purpose. | ||
| 6.2 Following observations of the Supreme Court in Oriental | ||
| Insurance Company Ltd. vs. Dicitex Furnishing Ltd. | ||
| [(2020) 4 SCC 621], may be pertinently noticed, | ||
| "...an application under Section 11(6) is in the | ||
| form of a pleading which merely seeks an order |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 12 of 85
| of the court, for appointment of an arbitrator. It | ||
|---|---|---|
| cannot be conclusive of the pleas or contentions | ||
| that the claimant or the concerned party can | ||
| take, in the arbitral proceedings. At this stage, | ||
| therefore, the court which is required to ensure | ||
| that an arbitrable dispute exists, has to be prima | ||
| facie convinced about the genuineness or | ||
| credibility of the plea of coercion; it cannot be | ||
| too particular about the nature of the plea, | ||
| which necessarily has to be made and | ||
| established in the substantive (read: | ||
| arbitration) proceeding. If the court were to take | ||
| a contrary approach and minutely examine the | ||
| and plea judge its credibility or reasonableness, | ||
| there would be a danger of its denying a forum | ||
| to the applicant altogether, because rejection of | ||
| the application would render the finding (about | ||
| the finality of the discharge and its effect as | ||
| satisfaction) final, thus, precluding the | ||
| applicant of itsright event to approach a civil | ||
| court." | ||
| 6.3 In the proceedings under section 8 of the Arbitration Act, | ||
| it is not the function of the Court to examine in detail, the | ||
| extant and nature of dispute, if dispute exist is referable to | ||
| the arbitration clause occurring in the agreement between | ||
| the parties, the appointment of arbitrator has to follow. | ||
| 6.4 It is observed that this Court has not expressed any | ||
| opinion on merits of the dispute and arbitrability thereof. | ||
| 6.5 In view of the above discussion, the prayer made in the | ||
| present application for appointment of arbitrator shall have | ||
| to be adverted to. | ||
| 7. In the result, the Registry is directed to list the same before | ||
| the appropriate Bench in accordance with roster for the | ||
| purpose of passing the order regarding appointment of | ||
| arbitrator.” |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 13 of 85
24. The aforesaid observations were made by the High Court in its order dated
22.09.2023 which has been impugned by the appellant in SLP(C) No. 7220
of 2024. After making the above quoted observations in favour of the
respondent, the High Court directed that the arbitration application be
listed before an appropriate bench in accordance with the roster. In
pursuance of the said order, the matter came to be listed before the Chief
Justice of the High Court, wherein an order for appointment of arbitrator
was passed. The said order dated 01.12.2023 has been impugned by the
appellant in SLP(C)No. 3792 of 2024.
B. SUBMISSIONS ON BEHALF OF THE APPELLANT
25. Mr Ketan Paul, the learned counsel appearing on behalf of the appellant,
submitted that a full and final settlement was arrived at between the parties
thereby indicating that a distinct understanding was arrived at between
them. No plea or assertion has been made by the respondent, nor any prima
facie evidence has been adduced to establish that the appellant had made
the execution of the discharge voucher a pre-condition to the payment of
the claim, or offered the amount on a “take it or leave it basis”. Seen thus,
the test laid down by this Court in paragraph 52(iv) of the National
Insurance Co. Ltd. v. Boghara Polyfab reported in (2009)1 SCC 267 can
neither be said to have been alleged nor satisfied.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 14 of 85
26. It was further submitted that there has been an inordinate delay on the part
of the respondent in levelling allegations of coercion. Such allegations
came to be so levelled for the first time in the arbitration notice dated
02.03.2020, that is, almost 14 months after the payment of the subject
claim and five months after the payment of the second claim. The counsel
submitted that the claim amount as per the assessment of the loss by the
surveyor was known to the respondent since 24.12.2018, thereby
indicating that the allegations of coercion were an afterthought.
27. In support of his aforesaid submission, the counsel placed reliance on the
decision of this Court in NTPC Ltd. v. SPML Infra Ltd. reported in (2023)
SCC OnLine SC 389 . He submitted that even when examined through the
“eye of the needle” test, the claim could be said to be deadwood and the
arbitration application ought to have been rejected by the High Court on
this count alone. The counsel also placed reliance on the decision of this
Court in New India Assurance Co. Ltd. v. Genus Power Infrastructure
Ltd. reported in (2015) 2 SCC 424 to submit that arbitration ought to be
refused in case of inordinate delay in raising the dispute or levelling
allegations of coercion by the party seeking the referral of disputes to
arbitration.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 15 of 85
28. One another submission made by the counsel was that the pleadings of the
respondent lack the basic material particulars about any alleged coercion
and the poor financial condition of the respondents. It was further
submitted that even in the arbitration notice all that the respondents have
stated is that had they not signed the discharge voucher in respect of the
first claim, their second claim also would have been affected.
29. The counsel submitted that the letter dated 25.10.2019 addressed by the
respondent cannot be said to be a protest letter as the letter only asked for
a copy of the surveyor’s report to be provided and no allegation of any
coercion or any demand for any amount was even raised in the said letter.
The counsel finally submitted that a discharge voucher for effecting the full
and final settlement in relation to the second claim was also signed by the
respondent on 30.09.2019, which was accepted and no dispute has been
raised in the last five years, which indicates that the appellant acted in a
bona fide manner as per the prescribed norms.
C. SUBMISSIONS ON BEHALF OF THE RESPONDENT
30. Ms Savita Singh, the learned counsel appearing on behalf of the
respondent, at the outset submitted that her client had to succumb before
the surveyor on account of acute economic distress and also on account of
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 16 of 85
pendency of huge amount of claim with the appellant, i.e., around Rs 8
crore cumulatively arising out of the two claims. The respondent was also
under pressure from other financial institutions from whom loan had been
availed.
31. The counsel further submitted that the circumstances were such that her
client had to issue the discharge voucher, otherwise payment towards the
admitted amount would not have been released and her client would have
been put in immense difficulties. She submitted that mere signing of the
discharge voucher by her client would not imply that there was consensus
in arriving at the full and final settlement. The counsel submitted that the
coercion, though subtle, was very much real and thus in such a situation
where the settlement is not voluntary, but under duress, the arbitration
clause can be invoked to refer the disputes to arbitration.
32. The counsel also submitted that it cannot be said that there was an
inordinate delay in raising the plea of coercion as the letter dated
25.09.2019 was sent by her client to the appellant within 11 days of the
receipt of final payment in relation to the second insurance claim.
However, the appellant provided a copy of the surveyor’s report only on
07.11.2019 based on which the notice of arbitration was issued on
02.03.2020.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 17 of 85
33. The counsel, in the last, submitted that the issues raised by the appellant
are subject matter of arbitration by the tribunal and not of the referral court,
which has to limit its scrutiny to the issue of arbitrability in view of the
settled position of law.
D. ISSUES FOR DETERMINATION
34. Having heard the learned counsel appearing for the parties and having gone
through the materials on record, the following three questions fall for our
consideration: -
i. Whether the execution of a discharge voucher towards the full and
final settlement between the parties would operate as a bar to invoke
arbitration?
ii. What is the scope and standard of judicial scrutiny that an
application under Section 11(6) of the Act, 1996 can be subjected to
when a plea of “accord and satisfaction” is taken by the defendant?
iii. What is the effect of the decision of this Court in In Re: Interplay
Between Arbitration Agreements under the Arbitration and
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 18 of 85
Conciliation Act 1966 and the Indian Stamp Act 1899 on the scope
of powers of the referral court under Section 11 of the Act, 1996?
E. ANALYSIS
35. Clause 13 of the insurance policy issued in favour of the respondent
contains the following arbitration clause:
“13) If any dispute or difference shall arise as to the quantum
to be paid under this Policy (liability being otherwise
admitted) such difference shall independently of all other
questions be referred to the decision of a sole arbitrator to be
appointed in writing by the parties to or if they cannot agree
upon a single arbitrator within 30 days of any party invoking
arbitration the same shall be referred to a panel of three
arbitrators, comprising of arbitrators, one to be appointed by
each of the parties to the dispute/difference and the third
arbitrator to be appointed by such two arbitrators and
arbitration shall be conducted under and in accordance with
the provision of the Arbitration and Conciliation Act, 1996.
It is clearly agreed and understood that no dispute or
difference shall be referrable to arbitration as hereinbefore
proved, if the Company has disputed or not accepted liability
under or in respect of this policy. It is hereby expressed
stipulated and declared that it shall be a condition precedent
to any right of action or suit upon this Policy that the award
by such arbitrator/arbitrators of the amount of the loss or
damaged shall be first obtained”
36. A preliminary objection was raised on behalf of the appellant that the
arbitration clause as contained in the insurance policy referred to above is
not attracted in the present case as there is no admission of liability on the
part of the appellant, whereas the said arbitration clause envisages
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 19 of 85
reference to arbitration only in cases where liability is admitted and there
is a dispute as regards the quantum of liability.
37. However, we find no merit in the aforesaid submission of the appellant. It
is evident from the record that the appellant had admitted its liability with
respect to the first claim and had even disbursed an amount of Rs
84,19,579/- in pursuance of the signing of the advance discharge voucher
by the respondent. Thus, it is clearly a case of admission of liability by the
appellant. However, the quantum of liability is in dispute as the amount
claimed by the respondent is at variance with the amount admitted by the
appellant. Thus, the dispute being one of quantum and not of liability, it
falls within the ambit of the conditional arbitration clause as contained in
the insurance policy.
38. One another preliminary objection raised by the appellant was that the
claim sought to be referred to arbitration is a deadwood claim and thus the
application for appointment of arbitrator ought to have been rejected at the
outset by the High Court. It is clear from the facts as discussed in the
preceding paragraphs that the notice invoking arbitration was sent by the
respondent to the appellant on 02.03.2020 and the petition seeking
appointment of arbitrator under Section 11(6) of the Act, 1996 was filed
before the High Court on 25.10.2021. Thus, the arbitration petition was
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 20 of 85
filed before the High Court much prior to the expiry of the limitation period
of three years. Further, the notice invoking arbitration was also sent by the
respondent well within time from the date of the accrual of the cause of
action. Considered thus, it cannot, by any stretch of imagination, be said
that the claim is a deadwood claim or the arbitration application before the
High Court was time-barred.
39. Having rejected the aforesaid two preliminary objections raised by the
appellant, the question that now remains to be examined is whether, in the
facts of the present case, the respondent could have invoked arbitration
after having signed the consent letter dated 24.12.2018 and the advance
discharge voucher dated 04.01.2019.
i. Whether the execution of a discharge voucher towards the full and final
settlement between the parties would operate as a bar to invoke
arbitration?
40. A contract between parties can come to an end by the performance thereof
by both the parties, that is, by the fulfilment of all the obligations in terms
of the original contract. This is referred to as discharge by performance.
Alternatively, the contract may also be discharged by substitution of certain
new obligations in place of the obligations contained in the original
contract, and subsequent performance of the substituted obligations. The
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 21 of 85
substituted obligations are referred to as ‘accord’ and the discharge of the
substituted obligations is referred to as ‘satisfaction’. It is referred to as
discharge by “accord and satisfaction” or by “full and final settlement” in
common parlance.
41. A written confirmation of discharge by “accord and satisfaction” can also
be in the form of a full and final discharge voucher or a No-Dues or a No-
Claims Certificate issued by one of the parties acknowledging that there
are no outstanding claims and that such a party has received the full and
final payment to its satisfaction. In the insurance sector, the general
practice is that the insurer obtains undated discharge vouchers from the
insured in advance by making the insured to sign on dotted lines before
processing the payment in respect of the claims of the insured.
42. The concept of discharge of a contract by “accord and satisfaction” is
embodied in Section 63 of the Indian Contract Act, 1872, which provides
that the promisee may, inter alia , accept any substituted obligation in place
of the original promise made to him, and such acceptance on the part of the
promisee would amount to the discharge of the contract. Section 63 along
with the illustrations is reproduced hereinbelow:
“63. Promisee may dispense with or remit performance of
promisee.—Every promisee may dispense with or remit,
wholly or in part, the performance of the promisee made to
him, or may extend the time for such performance, or may
accept instead of it any satisfaction which he thinks fit.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 22 of 85
Illustrations
(a) A promises to paint a picture for B. B afterwards forbids
him to do so. A is no longer bound to perform the promise.
(b) A owes B 5,000 rupees. A pays to B, and B accepts, in
satisfaction of the whole debt, 2,000 rupees paid at the time
and place at which the 5,000 rupees were payable. The whole
debt is discharged.
(c) A owes B 5,000 rupees. C pays to B 1,000 rupees, and B
accepts them, in satisfaction of his claim on A. This payment
is a discharge of the whole claim.
(d) A owes B, under. a contract, a sum of money, the amount
of which has not been ascertained. A, without ascertaining
the amount, gives to B, and B, in satisfaction thereof, accepts,
the sum of 2,000 rupees. This is a discharge of the whole debt,
whatever may be its amount.
(e) A owes B 2,000 rupees, and is also indebted to other
creditors. A makes an arrangement with his creditors,
including B, to pay them a [composition] of eight annas in
the rupee upon their respective demands. Payment to B of
1,000 rupees is a discharge of B’s demand.”
(Emphasis supplied)
43. The Privy Council in Payana Reena Saminathan v. Pana Lana
Palaniappa reported in (1913-14) 41 IA 142 defined the term “accord and
satisfaction” as follows:
“… The ‘receipt’ given by the appellants and accepted by
the respondent, and acted on by both parties proves
conclusively that all the parties agreed to a settlement of all
their existing disputes by the arrangement formulated in the
‘receipt’. It is a clear example of what used to be well known
as common law pleading as ‘accord and satisfaction by a
substituted agreement’. No matter what were the respective
rights of the parties inter se they are abandoned in
consideration of the acceptance by all for a new agreement.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 23 of 85
The consequence is that when such an accord and
satisfaction takes place the prior rights of the parties are
extinguished. They have in fact been exchanged for the new
rights; and the new agreement becomes a new departure, and
the rights of all the parties are fully represented by it.”
(Emphasis supplied)
44. As discussed in the preceding paragraphs, the appellant has contested that
once a full and final settlement was arrived at between the parties, the
insurance contract between the parties could be said to have been
discharged. Once the contract stood discharged, it was not open to the
respondent to resile from the settlement and invoke the arbitration clause,
as no obligations remained to be fulfilled under the contract pursuant to the
discharge of the contract. In other words, it is the contention of the
appellant that as no arbitrable disputes remained after a full and final
settlement was arrived at, there was nothing left to be referred to the
arbitrator and hence the appointment of arbitrator being an exercise in
futility, should not have been undertaken by the High Court.
45. To answer the aforesaid contention of the appellant, the question that needs
to be considered is whether the “full and final settlement” of claims arising
under a contract, is by itself sufficient to preclude any future arbitration in
respect of such settled claims?
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 24 of 85
46. It is indeed so that once a contract has been fully performed, it can be said
to have been discharged by performance. Once the contract has been
discharged by performance, neither any right to seek performance, nor any
obligation to perform remains under it.
47. However, whether there has been a discharge of contract or not is a mixed
question of law and fact, and if any dispute arises as to whether a contract
has been discharged or not, such a dispute is arbitrable as per the
mechanism prescribed under the arbitration agreement contained in the
underlying contract.
a. Whether the arbitration agreement contained in a substantive
contract survives even after the underlying contract is discharged by
“accord and satisfaction”?
48. Arbitration for the purpose of resolving any dispute pertaining to any claim
which has been “fully and finally settled” between the parties can only be
invoked if the arbitration agreement survives even after the discharge of
the substantive contract.
49. The arbitration agreement, by virtue of the presumption of separability,
survives the principal contract in which it was contained. Section 16(1) of
the Act, 1996 which is based on Article 16 of the UNCITRAL Model Law
on International Commercial Arbitration, 1985 (hereinafter, “ Model
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 25 of 85
Law ”) embodies the presumption of separability. There are two aspects to
the doctrine of separability as contained in the Act, 1996: -
i. An arbitration clause forming part of a contract is treated as an
agreement independent of the other terms of the contract.
ii. A decision by the arbitral tribunal declaring the contract as null and
void does not, ipso facto , make the arbitration clause invalid.
50. The doctrine of separability was not part of the legislative scheme under
the Arbitration Act, 1940. However, with the enactment of the Act, 1996,
the doctrine was expressly incorporated. This Court in National
Agricultural Coop. Marketing Federation India Ltd. v. Gains Trading
Ltd. reported in (2007) 5 SCC 692 , while interpreting Section 16 of the
Act, 1996, held that even if the underlying contract comes to an end, the
arbitration agreement contained in such a contract survives for the purpose
of resolution of disputes between the parties.
51. The fundamental premise governing the doctrine of separability is that the
arbitration agreement is incorporated by the parties to a contract with the
mutual intention to settle any disputes that may arise under or in respect of
or with regard to the underlying substantive contract, and thus by its
inherent nature is independent of the substantive contract.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 26 of 85
52. In Heyman v. Darwins Ltd. reported in [1942] AC 356 , it was held by the
House of Lords that the repudiation or breach of a contract does not
extinguish the arbitration agreement as it survives for the purpose of
resolution of any outstanding claims arising out of the breach. It was
observed thus:
"I am, accordingly, of the opinion that what is commonly
called repudiation or total breach of a contract, whether
acquiesced in by the other party or not, does not abrogate the
contract, though it may relieve the injured party of the duty
of further fulfilling the obligations which he has by the
contract undertaken to the repudiating party. The contract is
not put out of existence, though all further performance of the
obligations undertaken by each party in favour of the other
may cease. It survives for the purpose of measuring the
claims arising out of the breach, and the arbitration clause
survives for determining the mode of their settlement. The
purposes of the contract have failed, but the arbitration
clause is not one of the purposes of the contract."
(Emphasis supplied)
53. Thus, even if the contracting parties, in pursuance of a settlement, agree to
discharge each other of any obligations arising under the contract, this does
not ipso facto mean that the arbitration agreement too would come to an
end, unless the parties expressly agree to do the same. The intention of the
parties in discharging a contract by “accord and satisfaction” is to relieve
each other of the existing or any new obligations under the contract. Such
a discharge of obligations under the substantive contract cannot be
construed to mean that the parties also intended to relieve each other of
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 27 of 85
their obligation to settle any dispute pertaining to the original contract
through arbitration.
54. Although ordinarily no arbitrable disputes may subsist after execution of a
full and final settlement, yet any dispute pertaining to the full and final
settlement itself, by necessary implication being a dispute arising out of or
in relation to or under the substantive contract, would not be precluded
from reference to arbitration as the arbitration agreement contained in the
original contract continues to be in existence even after the parties have
discharged the original contract by “accord and satisfaction”.
55. The aforesaid position of law has also been consistently followed by this
Court as evident from many decisions. In Boghara Polyfab (supra), while
rejecting the contention that the mere act of signing a “full and final
discharge voucher” would act as a bar to arbitration, this Court held as
follows:
“44 . … None of the three cases relied on by the appellant lay
down a proposition that mere execution of a full and final
settlement receipt or a discharge voucher is a bar to
arbitration, even when the validity thereof is challenged by
the claimant on the ground of fraud, coercion or undue
influence. Nor do they lay down a proposition that even if the
discharge of contract is not genuine or legal, the claims
cannot be referred to arbitration. […]”
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 28 of 85
56. Again, in R.L. Kalathia and Company v. State of Gujarat reported in
(2011) 2 SCC 400 , it was re-iterated that the mere issuance of the no-dues
certificate would not operate as a bar against the raising of genuine claims
even after the date of issuance of such certificate. The relevant observations
are extracted hereinbelow:
“13. From the above conclusions of this Court, the following
principles emerge:
(1) Merely because the contractor has issued "no-dues
certificate", if there is an acceptable claim, the court cannot
reject the same on the ground of issuance of "no-dues
certificate".
(ii) Inasmuch as it is common that unless a discharge
certificate is given in advance by the contractor, payment of
bills are generally delayed, hence such a clause in the
contract would not be an absolute bar to a contractor raising
claims which are genuine at a later date even after
submission of such "no-claim certificate".
(iii) Even after execution of full and final discharge
voucher/receipt by one of the parties, if the said party is able
to establish that he is entitled to further amount for which he
is having adequate materials, he is not barred from claiming
such amount merely because of acceptance of the final bill by
mentioning "without prejudice" or by issuing "no-dues
certificate".
(Emphasis supplied)
57. The position that emerges from the aforesaid discussion is that there is no
rule of an absolute kind which precludes arbitration in cases where a full
and final settlement has been arrived at. In Boghara Polyfab (supra),
discussing in the context of a case similar to the one at hand, wherein the
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 29 of 85
discharge voucher was alleged to have been obtained on ground of
coercion, it was observed that the discharge of a contract by full and final
settlement by issuance of a discharge voucher or a no-dues certificate
extends only to those vouchers or certificates which are validly and
voluntarily executed. Thus, if the party said to have executed the discharge
voucher or the no dues certificate alleges that the execution was on account
of fraud, coercion or undue influence exercised by the other party and is
able to establish such an allegation, then the discharge of the contract by
virtue of issuance of such a discharge voucher or no dues certificate is
rendered void and cannot be acted upon.
58. It was further held in Boghara Polyfab (supra) that the mere execution of
a full and final settlement receipt or a discharge voucher would not by itself
operate as a bar to arbitration when the validity of such a receipt or voucher
is challenged by the claimant on the ground of fraud, coercion or undue
influence. In other words, where the parties are not ad idem over accepting
the execution of the no-claim certificate or the discharge voucher, such
disputed discharge voucher may itself give rise to an arbitrable dispute.
59. Once the full and final settlement of the original contract itself becomes a
matter of dispute and disagreement between the parties, then such a dispute
can be categorised as one arising “in relation to” or “in connection with”
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 30 of 85
or “upon” the original contract which can be referred to arbitration in
accordance with the arbitration clause contained in the original contract,
notwithstanding the plea that there was a full and final settlement between
the parties.
ii. What is the scope and standard of judicial scrutiny that an application
under Section 11(6) of the Act, 1996 can be subjected to when a plea of
“accord and satisfaction” is taken by the defendant?
60. Whether the issue as regards the validity of the full and final settlement is
to be determined by the referral court acting under Section 11 of the Act,
1996 or by the arbitral tribunal has been considered in a number of
decisions of this Court. Some of these decisions have also delineated the
extent and standard of enquiry which can be undertaken at the stage of
Section 11 petition. We shall discuss these decisions in detail for the benefit
of the exposition of the law on the subject.
61. One of the earliest decisions dealing with the issue of “full and final
settlement” in the specific context of an application for appointment of
arbitrator under the Arbitration Act, 1940 was rendered by a two-Judge
Bench of this Court in Damodar Valley Corporation v. K.K. Kar reported
in (1974) 1 SCC 141 . It was observed, inter alia, that any dispute arising in
relation to the validity of the discharge by “accord and satisfaction” would
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 31 of 85
be covered by the arbitration agreement contained in the original contract,
and thus should be referred to the arbitral tribunal for determination. The
relevant observations are extracted hereinbelow:
“4. On these facts the short question for determination is:
where one of the parties refers a dispute or disputes to
arbitration and the other party takes a plea that there was a
final settlement of all claims, is the Court, on an application
under Sections 9(b) and 33 of the Act, entitled to enquire into
the truth and validity of the averment as to whether there was
or was not a final settlement on the ground that if that was
proved, it would bar a reference to the arbitration inasmuch
as the arbitration clause itself would perish.
xxx xxx xxx
6. It appears to us that the question whether there has been
a full and final settlement of a claim under the contract is
itself a dispute arising “upon” or “in relation to” or “in
connection with” the contract. These words are wide enough
to cover the dispute sought to be referred. The respondent's
contention is that the contract has been repudiated by the
appellant unilaterally as a result of which he had no option
but to accept that repudiation because if the appellant was
not ready to receive the goods he could not supply them to
him or force him to receive them. In the circumstances, while
accepting the repudiation, without conceding that the
appellant had a right to repudiate the contract, he could
claim damages for breach of contract. Such a claim for
damages is a dispute or difference which arises between
himself and the appellant and is ‘upon’ or ‘in relation to’ or
‘in connection with’ the contract.
7. The contention that has been canvassed before us is that
as there has been a full and final settlement under the
contract, the rights and obligations under the contract do not
subsist and consequently the arbitration clause also perishes
along with the settlement. If so, the dispute whether there has
or has not been a settlement cannot be the subject of an
arbitration. There is, in our view, a basic fallacy underlying
this submission. A contract is the creature of an agreement
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 32 of 85
between the parties and where the parties under the terms of
the contract agree to incorporate an arbitration clause, that
clause stands apart from the rights and obligations under that
contract, as it has been incorporated with the object of
providing a machinery for the settlement of disputes arising
in relation to or in connection with that contract. The
questions of unilateral repudiation of the rights and
obligations under the contract or of a full and final settlement
of the contract relate to the performance or discharge of the
contract. Far from putting an end to the arbitration clause,
they fall within the purview of it. A repudiation by one party
alone does not terminate the contract. It takes two to end it,
and hence it follows that as the contract subsists for the
determination of the rights and obligations of the parties, the
arbitration clause also survives. This is not a case where the
plea is that the contract is void, illegal or fraudulent etc. in
which case, the entire contract along with the arbitration
clause is non est, or voidable. […]”
(Emphasis supplied)
62. In Bharat Heavy Electricals Ltd. vs. Amar Nath Bhan Prakash reported
in (1982) 1 SCC 625 it was observed by this Court that the question
whether there was discharge of the contract by “accord and satisfaction” or
not is a dispute liable to be resolved by the arbitral tribunal and the court
ought to appoint an arbitrator in such matters when a party approaches it
seeking relief for the same. It was observed thus:
“1. It appears from the order of the High Court impugned in
the appeal that the High Court has not correctly appreciated
the position that the question whether there was discharge of
the contract by accord and satisfaction or not, is a dispute
arising out of the contract and is liable to be referred to
arbitration and hence the application of the Respondent
under Section 20 of the Indian Arbitration Act should have
been allowed and the matters in dispute between the parties,
including the question whether or not there was discharge of
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 33 of 85
the contract by accord and satisfaction should have been
referred to arbitration.”
(Emphasis supplied)
63. However, the position on the issue witnessed a change with subsequent
decisions of this Court in P.K. Ramaiah and Company v. Chairman and
Managing Director, National Thermal Power Corporation reported in
1994 Supp (3) SCC 126 and Nathani Steels Ltd. v. Associated
Constructions reported in 1995 Supp (3) SCC 324 .
64. In P.K. Ramaiah (supra) , the decision in Damodar Valley (supra) was
distinguished on facts, and it was held that once “full and final settlement”
is arrived at, no arbitral dispute subsists, and hence there can be no referral
to arbitration. The relevant observations made therein are as follows:
“6. [….] If there is an arbitrable dispute, it shall be referred
to the named arbitrator. But there must exist a subsisting
dispute. Admittedly the appellant acknowledged in writing
accepting the correctness of the measurements as well as the
final settlement and received the amount. Thereafter no
arbitrable dispute arise for reference.
xxx xxx xxx
8. […] Accordingly, we hold that the appellant having
acknowledged the settlement and also accepted
measurements and having received the amount in full and
final settlement of the claim, there is accord and satisfaction.
There is no existing arbitrable dispute for reference to the
arbitration. The High Court is, therefore, right in its finding
in this behalf. The appeals are dismissed but in the
circumstances without costs.”
65. In Nathani Steels (supra) , relying upon the decision in P.K. Ramaiah
(supra) it was observed thus:
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 34 of 85
“3. […] It would thus be seen that once there is a full and
final settlement in respect of any particular dispute or
difference in relation to a matter covered under the
Arbitration clause in the contract and that dispute or
difference is finally settled by and between the parties, such
a dispute or difference does not remain to be an arbitrable
dispute and the Arbitration clause cannot be invoked even
though for certain other matters, the contract may be in
subsistence. […]”
66. It is important to note that the aforesaid four decisions were rendered in the
context of appointment of arbitrator under the Arbitration Act, 1940. With
the introduction of the Act, 1996, a different regime came into being insofar
as the question of appointment of arbitrator is concerned. In Jayesh
Engineering Works v New India Assurance Co. Ltd. reported in (2000)
10 SCC 178 , dealing with an application for appointment of arbitrator
under the Act, 1996, a position similar to the one taken in Amar Nath
(supra) was taken by this Court. It was held thus:
“1. […] Whether any amount is due to be paid and how far
the claim made by the Appellant is tenable are matters to be
considered by the Arbitrator. In fact, whether the contract
has been fully worked out and whether the payments have
been made in full and final settlement are questions to be
considered by the Arbitrator when there is a dispute
regarding the same. […]”
67. While the aspect of “accord and satisfaction” in the specific context of the
appointment of arbitrator has been discussed by this Court on numerous
occasions, we also deem it necessary to refer to and discuss some important
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 35 of 85
decisions touching upon the contours of the power of the referral court
under Section 11 of the Act, 1996 as they directly affect the issue at hand.
68. The role to be played by the Chief Justice or his designate in the
appointment of an arbitrator has been at the heart of number of decisions
of this Court. In Konkan Railway Corpn. Ltd. v. Rani Construction (P)
Ltd. reported in (2002) 2 SCC 388 , a five-Judge Bench of this Court
observed that the power exercised by the referral court under Section 11 of
the Act, 1996 is an administrative power and thus the Chief Justice or his
designate do not have to decide any preliminary issue at that stage.
Accordingly, it held that any issues pertaining to non-arbitrability, validity
and existence of the arbitration agreement are to be decided by the
arbitrator.
69. The aforesaid view occupied the field till a seven-Judge Bench of this
Court in SBP & Co. v. Patel Engg. Ltd. reported in (2005) 8 SCC 618 ,
characterised the power conferred upon the Chief Justice or his designate
under Section 11 of the Act, 1996 as a judicial power and not merely
administrative power. This Court held that the Chief Justice or his
designate had the right to decide all preliminary issues at the referral stage
under Section 11(6) of the Act, 1996. The Court took such view on the
premise that Section 16 of the Act, 1996, which empowers the Arbitral
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 36 of 85
Tribunal to rule on its own jurisdiction, applies only when the parties go
before the Tribunal without having taken recourse to Sections 8 or 11
respectively of the Act, 1996 first.
70. In Boghara Polyfab (supra), this Court examined the extent of judicial
interference at the stage of referral under Section 11(6) of the Act, 1996 as
laid down in SBP & Co. (supra) and elucidated three categories of issues
which could arise before the referral court as follows:
“22.1. The issues (first category) which the Chief Justice/his
designate will have to decide are:
(a) Whether the party making the application has approached
the appropriate High Court.
(b) Whether there is an arbitration agreement and whether
the party who has applied under Section 11 of the Act, is a
party to such an agreement.
22.2. The issues (second category) which the Chief
Justice/his designate may choose to decide (or leave them to
the decision of the Arbitral Tribunal) are:
(a) Whether the claim is a dead (long-barred) claim or a live
claim.
(b) Whether the parties have concluded the
contract/transaction by recording satisfaction of their mutual
rights and obligation or by receiving the final payment
without objection.
22.3. The issues (third category) which the Chief Justice/his
designate should leave exclusively to the Arbitral Tribunal
are:
(i) Whether a claim made falls within the arbitration clause
(as for example, a matter which is reserved for final decision
of a departmental authority and excepted or excluded from
arbitration).
(ii) Merits or any claim involved in the arbitration.”
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 37 of 85
71. The decision in Boghara Polyfab (supra) was followed in a number of
subsequent decisions of this Court. In Union of India v. Master
Construction Co. reported in (2011) 12 SCC 349 , this Court held that while
deciding an application under Section 11(6) of the Act, 1996, the referral
court must satisfy itself that the allegations raised against the full and final
discharge voucher were at least prima facie bona fide and genuine.
Applying the said reasoning to the facts before it, this Court held that the
dispute was not a bona fide one and declined to refer the matter to
arbitration. The relevant extracts are reproduced hereinbelow:
| “18. In our opinion, there is no rule of the absolute kind. In<br>a case where the claimant contends that a discharge voucher<br>or a no-claim certificate as been obtained by fraud and the<br>other side contests the correctness, the Chief Justice must<br>look into this aspect to find out at least, prima facie whether<br>or not the dispute is bona fide and genuine. Where the dispute<br>raised by the claimant with regard to validity of the discharge<br>voucher or no-claim certificate or settlement agreement,<br>prima facie, appears to be lacking in credibility, there may<br>not be a necessity to refer the dispute for arbitration at all.<br>xxx xxx xxx | “18. In our opinion, there is no rule of the absolute kind. In | |
|---|---|---|
| a case where the claimant contends that a discharge voucher | ||
| or a no-claim certificate as been obtained by fraud and the | ||
| other side contests the correctness, the Chief Justice must | ||
| look into this aspect to find out at least, prima facie whether | ||
| or not the dispute is bona fide and genuine. Where the dispute | ||
| raised by the claimant with regard to validity of the discharge | ||
| voucher or no-claim certificate or settlement agreement, | ||
| prima facie, appears to be lacking in credibility, there may | ||
| not be a necessity to refer the dispute for arbitration at all. | ||
| xxx xxx xxx | ||
| 23. The present case in our opinion appears to be a case | ||
| falling in the category of exception noted in Boghara | ||
| Polyfab[(2009) 1 SCC 267](p.284, para 25). As to the | ||
| financial duress or coercion, nothing of this kind is | ||
| established prima facie. Mere allegation that no-claim | ||
| certificates have been obtained under financial duress and | ||
| coercion, without there being anything more to suggest that, | ||
| does not lead to an arbitrable dispute. The conduct of the | ||
| contractor clearly shows that “no-claim certificates” were | ||
| given by it voluntarily, the contractor accepted the amount | ||
| voluntarily and the contract was discharged voluntarily.” | ||
| (Emphasis supplied) |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 38 of 85
72. In New India Assurance (supra) , this Court, relying upon Boghara
Polyfab (supra) and Master Construction Co. (supra), upon examining the
Section 11 petition held that a mere bald assertion of fraud, undue influence
or coercion would not warrant referral of disputes to arbitration, if the
matter had already been fully and finally settled between the parties. The
relevant observations are reproduced hereinbelow:
“10. In our considered view, the plea raised by the
Respondent is bereft of any details and particulars, and
cannot be anything but a bald assertion. Given the fact that
there was no protest or demur raised around the time or soon
after the letter of subrogation was signed, that the notice
dated 31.03.2011 itself was nearly after three weeks and that
the financial condition of the Respondent was not so
precarious that it was left with no alternative but to accept
the terms as suggested, we are of the firm view that the
discharge in the present case and signing of letter of
subrogation were not because of exercise of any undue
influence. Such discharge and signing of letter of subrogation
was voluntary and free from any coercion or undue influence.
In the circumstances, we hold that upon execution of the letter
of subrogation, there was full and final settlement of the
claim. Since our answer to the question, whether there was
really accord and satisfaction, is in the affirmative, in our
view no arbitrable dispute existed so as to exercise power
Under Section 11 of the Act. The High Court was not
therefore justified in exercising power Under Section 11 of
the Act.”
(Emphasis supplied)
73. The net effect of the decisions in SBP & Co. (supra) and Boghara Polyfab
(supra) was that the scope for interference available to the referral courts
when acting under Section 11 of the Act, 1996 was substantially expanded.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 39 of 85
The referral courts were conferred with the discretion to conduct mini trials
and indulge in the appreciation of evidence on the issues concerned with
th
the subject matter of arbitration. The Law Commission of India in its 246
report took note of the issue of significant delays being caused to the
arbitral process due to enlarged scope of judicial interference at the stage
of appointment of arbitrator and suggested as follows:
i. First , that the power of appointment conferred upon the Chief
Justice be devolved on to the Supreme Court and the High Court, as
the case may be; and
ii. Secondly , the power of appointment under Section 11 be clarified to
be an administrative power and not a judicial one.
iii. Thirdly , the scope of interference under Sections 8 and 11
respectively of the Act, 1996 be restricted only to those cases where
the court finds that no arbitration agreement exists or is null and
void.
74. The Law Commission suggested the insertion of Section 11(6-A) in the
Act, 1996. The aforesaid recommendations of the Commission were taken
note of by the Parliament and accordingly the Act, 1996 was amended in
2015 to incorporate Section 11(6-A), which reads thus:
“(6A) The Supreme Court or, as the case may be, the High
Court, while considering any application under sub-
section (4) or sub-section (5) or sub-section (6), shall,
notwithstanding any judgment, decree or order of any Court,
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 40 of 85
| confine to the examination of the existence of an arbitration | |
|---|---|
| agreement.” | |
75. Interestingly, Section 11(6-A) was omitted by the 2019 amendment to the
Act, 1996 on the basis of a report of the High-Level Committee to Review
the Institutionalisation of Arbitration Mechanism in India. However, in the
absence of the omission being notified, Section 11(6-A) of the Act, 1996
continues to remain on the statute book and thus has to be given effect as
such.
76. The impact of the addition of Section 11(6-A) was elaborately discussed
by this Court in Duro Felguera, S.A. v. Gangavaram Port Ltd reported in
(2017) 9 SCC 729 as follows:
“48. […] From a reading of Section 11(6-A), the intention of
the legislature is crystal clear i.e. the court should and need
only look into one aspect—the existence of an arbitration
agreement. What are the factors for deciding as to whether
there is an arbitration agreement is the next question. The
resolution to that is simple—it needs to be seen if the
agreement contains a clause which provides for arbitration
pertaining to the disputes which have arisen between the
parties to the agreement.
| xxx xxx xxx | |
| 59. The scope of the power under Section 11(6) of the 1996 | |
| Act was considerably wide in view of the decisions in SBP | |
| and Co. [(2005) 8 SCC 618] and Boghara Polyfab [(2009) 1 | |
| SCC 267]. This position continued till the amendment | |
| brought about in 2015. After the amendment, all that the | |
| courts need to see is whether an arbitration agreement | |
| exists—nothing more, nothing less. The legislative policy and | |
| purpose is essentially to minimise the Court's intervention at |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 41 of 85
the stage of appointing the arbitrator and this intention as
incorporated in Section 11(6-A) ought to be respected.”
(Emphasis supplied)
77. Despite the decision in Duro Felguera (supra), this Court in United India
Insurance Co. Ltd. v. Antique Art Exports Pvt. Ltd. reported in (2019) 5
SCC 362 , while dealing with the issue of “full and final settlement” in the
context of appointment of an arbitrator, held that mere bald allegation by a
party that the discharge voucher was obtained under coercion or undue
influence would not entitle it to seek referral of the dispute to arbitration
unless it is able to produce prima facie evidence of the same during the
course of proceedings under Section 11(6) of the Act, 1996. Important
paragraphs from the said decision are extracted hereinbelow:
| “15. From the proposition which has been laid down by this | |
|---|---|
| Court, what reveals is that a mere plea of fraud, coercion or | |
| undue influence in itself is not enough and the party who | |
| alleged is under obligation to prima facie establish the same | |
| by placing satisfactory material on record before the Chief | |
| Justice or his Designate to exercise power under Section | |
| 11(6) of the Act, which has been considered by this Court | |
| in New India Assurance Co. Ltd. case [...] | |
| xxx xxx xxx | |
| 17. It is true that there cannot be a rule of its kind that mere | |
| allegation of discharge voucher or no claim certificate being | |
| obtained by fraud/coercion/undue influence practised by | |
| other party in itself is sufficient for appointment of the | |
| arbitrator unless the claimant who alleges that execution of | |
| the discharge agreement or no claim certificate was obtained | |
| on account of fraud/coercion/undue influence practised by | |
| the other party is able to produce prima facie evidence to |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 42 of 85
substantiate the same, the correctness thereof may be open
for the Chief Justice/his Designate to look into this aspect to
find out at least prima facie whether the dispute is bona fide
and genuine in taking a decision to invoke Section 11(6) of
the Act.
18. In the instant case, the facts are not in dispute that for the
two incidents of fire on 25-9-2013 and 25-10-2013, the
appellant Company based on the Surveyor's report sent
emails on 5-5-2016 and 24-6-2016 for settlement of the
claims for both the fires dated 25-9-2013 and 25-10-2013
which was responded by the respondent through email on the
same date itself providing all the necessary information to the
regional office of the Company and also issued the discharge
voucher in full and final settlement with accord and
satisfaction. Thereafter, on 12-7-2016, the respondent
desired certain information with details, that too was
furnished and for the first time on 27-7-2016, it took a U-turn
and raised a voice of undue influence/coercion being used by
the appellant stating that it being in financial distress was left
with no option than to proceed to sign on the dotted lines. As
observed, the phrase in itself is not sufficient unless there is
a prima facie evidence to establish the allegation of
coercion/undue influence, which is completely missing in the
instant case.
19. In the given facts and circumstances, we are satisfied that
the discharge and signing the letter of subrogation was not
because of any undue influence or coercion as being claimed
by the respondent and we find no difficulty to hold that upon
execution of the letter of subrogation, the claim was settled
with due accord and satisfaction leaving no arbitral dispute
to be examined by an arbitrator to be appointed under
Section 11(6) of the Act.
20. The submission of the learned counsel for the respondent
that after insertion of sub-section (6-A) to Section 11 of the
Amendment Act, 2015 the jurisdiction of this Court is
denuded and the limited mandate of the Court is to examine
the factum of existence of an arbitration and relied on the
judgment in Duro Felguera, S.A. v. Gangavaram Port
Ltd. [Duro Felguera, S.A. v. Gangavaram Port Ltd., (2017)
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 43 of 85
9 SCC 729 : (2017) 4 SCC (Civ) 764] The exposition in this
decision is a general observation about the effect of the
amended provisions which came to be examined under
reference to six arbitrable agreements (five agreements for
works and one corporate guarantee) and each agreement
contains a provision for arbitration and there was serious
dispute between the parties in reference to constitution of
Arbitral Tribunal whether there has to be Arbitral Tribunal
pertaining to each agreement. In the facts and circumstances,
this Court took note of sub-section (6-A) introduced by the
Amendment Act, 2015 to Section 11 of the Act and in that
context observed that the preliminary disputes are to be
examined by the arbitrator and are not for the Court to be
examined within the limited scope available for appointment
of arbitrator under Section 11(6) of the Act. Suffice it to say
that appointment of an arbitrator is a judicial power and is
not a mere administrative function leaving some degree of
judicial intervention; when it comes to the question to
examine the existence of a prima facie arbitration agreement,
it is always necessary to ensure that the dispute resolution
process does not become unnecessarily protracted.
21. In the instant case, prima facie no dispute subsisted after
the discharge voucher being signed by the respondent
without any demur or protest and claim being finally settled
with accord and satisfaction and after 11 weeks of the
settlement of claim a letter was sent on 27-7-2016 for the first
time raising a voice in the form of protest that the discharge
voucher was signed under undue influence and coercion with
no supportive prima facie evidence being placed on record in
absence thereof, it must follow that the claim had been settled
with accord and satisfaction leaving no arbitral dispute
subsisting under the agreement to be referred to the
arbitrator for adjudication.
22. In our considered view, the High Court has committed a
manifest error in passing the impugned order and adopting a
mechanical process in appointing the arbitrator without any
supportive evidence on record to prima facie substantiate
that an arbitral dispute subsisted under the agreement which
needed to be referred to the arbitrator for adjudication.”
(Emphasis supplied)
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 44 of 85
78. It is pertinent to observe that in Antique Art (supra) the Court placed
reliance on the decisions in Master Construction (supra) and New India
Assurance (supra) . Both these decisions were delivered before the
insertion of Section 11(6-A) by the 2015 amendment to the Act, 1996.
Thus, this Court in Antique Art (supra) failed to take into account the
legislative intent behind the introduction of Section 11(6-A), which was
also succinctly explained in Duro Felguera (supra).
79. A three-Judge Bench of this Court in Mayavati Trading Private Limited v.
Pradyut Deb Burman reported in ( 2019) 8 SCC 714 overruled the decision
in Antique Art (supra) and clarified that the position of law existing prior
to the 2015 amendment to the Act, 1996 under which referral courts had
the power to examine the aspect of “accord and satisfaction” had come to
be legislatively overruled by Section 11(6-A) of the Act, 1996. The Court,
while affirming the reasoning given in Duro Felguera (supra), observed
thus:
“10. This being the position, it is clear that the law prior to
the 2015 Amendment that has been laid down by this Court,
which would have included going into whether accord and
satisfaction has taken place, has now been legislatively
overruled. This being the position, it is difficult to agree with
the reasoning contained in the aforesaid judgment [United
India Insurance Co. Ltd. v. Antique Art Exports (P) Ltd.,
(2019) 5 SCC 362 : (2019) 2 SCC (Civ) 785] , as Section
11(6-A) is confined to the examination of the existence of an
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 45 of 85
arbitration agreement and is to be understood in the narrow
sense as has been laid down in the judgment in Duro
Felguera, SA [Duro Felguera, SA v. Gangavaram Port Ltd.,
(2017) 9 SCC 729 : (2017) 4 SCC (Civ) 764] — see paras 48
& 59
11. We, therefore, overrule the judgment in Antique Art
Exports (P) Ltd. [United India Insurance Co. Ltd. v. Antique
Art Exports (P) Ltd., (2019) 5 SCC 362 : (2019) 2 SCC (Civ)
785] as not having laid down the correct law but dismiss this
appeal for the reason given in para 3 above.”
(Emphasis supplied)
80. A two-Judge Bench of this Court in Uttarakhand Purv Sainik Kalyan
Nigam Ltd. v. Northern Coal Field Ltd. reported in (2020) 2 SCC 455 was
called upon to determine the scope of judicial interference at the stage of
Section 11(6) petition wherein the plea of claims being time barred was
taken by the defendant. Referring to the principal of competence-
competence enshrined in Section 16 of the Act, 1996 and the legislative
intent behind the introduction of Section 11(6-A) to Act, 1996 by the 2015
amendment, this Court held that the issue of limitation being a mixed
question of law and fact should be best left to the tribunal to decide. The
referral court should restrict its examination to whether an arbitration
agreement between the parties exists. The relevant observations are
reproduced hereinbelow:
“7.10. In view of the legislative mandate contained in Section
11(6-A), the Court is now required only to examine the
existence of the arbitration agreement. All other preliminary
or threshold issues are left to be decided by the arbitrator
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 46 of 85
under Section 16, which enshrines the kompetenz-kompetenz
principle.
7.11. The doctrine of “kompetenz-kompetenz”, also referred
to as “compétence-compétence”, or “compétence de la
recognized”, implies that the Arbitral Tribunal is empowered
and has the competence to rule on its own jurisdiction,
including determining all jurisdictional issues, and the
existence or validity of the arbitration agreement. This
doctrine is intended to minimise judicial intervention, so that
the arbitral process is not thwarted at the threshold, when a
preliminary objection is raised by one of the parties. The
doctrine of kompetenz-kompetenz is, however, subject to the
exception i.e. when the arbitration agreement itself is
impeached as being procured by fraud or deception . This
exception would also apply to cases where the parties in the
process of negotiation, may have entered into a draft
agreement as an antecedent step prior to executing the final
contract. […]7.12. The legislative intent underlying the 1996
Act is party autonomy and minimal judicial intervention in
the arbitral process. Under this regime, once the arbitrator
is appointed, or the tribunal is constituted, all issues and
objections are to be decided by the Arbitral Tribunal.
7.13. In view of the provisions of Section 16, and the
legislative policy to restrict judicial intervention at the pre-
reference stage, the issue of limitation would require to be
decided by the arbitrator. Sub-section (1) of Section 16
provides that the Arbitral Tribunal may rule on its own
jurisdiction, “including any objections” with respect to the
existence or validity of the arbitration agreement. Section 16
is as an inclusive provision, which would comprehend all
preliminary issues touching upon the jurisdiction of the
Arbitral Tribunal. The issue of limitation is a jurisdictional
issue, which would be required to be decided by the
arbitrator under Section 16, and not the High Court at the
pre-reference stage under Section 11 of the Act. Once the
existence of the arbitration agreement is not disputed, all
issues, including jurisdictional objections are to be decided
by the arbitrator.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 47 of 85
| 7.14. In the present case, the issue of limitation was raised | |
|---|---|
| by the respondent Company to oppose the appointment of | |
| the arbitrator under Section 11 before the High Court. | |
| Limitation is a mixed question of fact and law. In ITW | |
| Signode (India) Ltd. v. CCE [ITW Signode (India) | |
| Ltd. v. CCE, (2004) 3 SCC 48] a three-Judge Bench of this | |
| Court held that the question of limitation involves a question | |
| of jurisdiction. The findings on the issue of limitation would | |
| be a jurisdictional issue. Such a jurisdictional issue is to be | |
| determined having regard to the facts and the law. Reliance | |
| is also placed on the judgment of this Court in NTPC | |
| Ltd. v. Siemens Atkeingesellschaft [NTPC Ltd. v. Siemens | |
| Atkeingesellschaft, (2007) 4 SCC 451], wherein it was held | |
| that the Arbitral Tribunal would deal with limitation under | |
| Section 16 of the 1996 Act. If the tribunal finds that the claim | |
| is a dead one, or that the claim was barred by limitation, the | |
| adjudication of these issues would be on the merits of the | |
| claim. Under sub-section (5) of Section 16, the tribunal has | |
| the obligation to decide the plea; and if it rejects the plea, | |
| the arbitral proceedings would continue, and the tribunal | |
| would make the award. Under sub-section (6) a party | |
| aggrieved by such an arbitral award may challenge the | |
| award under Section 34. […]” | |
| (Emphasis supplied) | |
2019 INSC 1241 this Court left the issue of “accord and satisfaction” to be
decided by the arbitrator and held thus:
“16. […] On behalf of the Respondent, it has been seriously
disputed that issuance of "No Claim" certificate as to the
supplementary agreement recording accord and satisfaction
as on 06.05.2014 (CA No. 6400/2016) and issuance of "No
Claim" certificate on 28.08.2014 (CA No. 6420/2016) that
they were issued under compulsion and due to undue
influence by the railway authorities. We are not inclined to
go into the merits of the contention of the parties. It is for the
arbitrator to consider the claim of the Respondent(s) and the
stand of the Appellant-railways. This contention raised by the
parties are left open to be raised before the arbitrator.”
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 48 of 85
82. Thereafter, a three-Judge Bench of this Court in Vidya Drolia & Ors v.
Durga Trading Corporation reported in ( 2021) 2 SCC 1 extensively dealt
with the scope of powers of the referral court under Section 8 and 11
respectively of the Act, 1996. It held, inter alia, that Sections 8 and 11 of
the Act, 1996 are complementary to each other and thus the aspect of
‘existence’ of the arbitration agreement, as specified under Section 11
should be seen along with its ‘validity’ as specified under Section 8. This
Court also held that the exercise of power of prima facie judicial review to
examine the existence of arbitration agreement also includes going into the
validity of the arbitration agreement and this does not go against the
principles of competence-competence and the presumption of separability.
It further held that the prima facie review of the aspects related to non-
arbitrability may also be undertaken. The relevant observations are
extracted hereinbelow:
“147.4. Most jurisdictions accept and require prima facie
review by the court on non-arbitrability aspects at the
referral stage.
147.5. Sections 8 and 11 of the Arbitration Act are
complementary provisions as was held in Patel Engg.
Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] The
object and purpose behind the two provisions is identical to
compel and force parties to abide by their contractual
understanding. This being so, the two provisions should be
read as laying down similar standard and not as laying down
different and separate parameters. Section 11 does not
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 49 of 85
| prescribe any standard of judicial review by the court for | |
|---|---|
| determining whether an arbitration agreement is in | |
| existence. Section 8 states that the judicial review at the stage | |
| of reference is prima facie and not final. Prima facie standard | |
| equally applies when the power of judicial review is exercised | |
| by the court under Section 11 of the Arbitration Act. | |
| Therefore, we can read the mandate of valid arbitration | |
| agreement in Section 8 into mandate of Section 11, that is, | |
| “existence of an arbitration agreement”. | |
| 147.6. Exercise of power of prima facie judicial review of | |
| existence as including validity is justified as a court is the | |
| first forum that examines and decides the request for the | |
| referral. Absolute “hands off” approach would be | |
| counterproductive and harm arbitration, as an alternative | |
| dispute resolution mechanism. Limited, yet effective | |
| intervention is acceptable as it does not obstruct but | |
| effectuates arbitration. | |
| 147.7. Exercise of the limited prima facie review does not in | |
| any way interfere with the principle of competence- | |
| competence and separation as to obstruct arbitration | |
| proceedings but ensures that vexatious and frivolous matters | |
| get over at the initial stage. | |
| 147.8. Exercise of prima facie power of judicial review as to | |
| the validity of the arbitration agreement would save costs and | |
| check harassment of objecting parties when there is clearly | |
| no justification and a good reason not to accept plea of non- | |
| arbitrability. […] | |
| xxx xxx xxx | |
| 147.11. The interpretation appropriately balances the | |
| allocation of the decision-making authority between the court | |
| at the referral stage and the arbitrators' primary jurisdiction | |
| to decide disputes on merits. The court as the judicial forum | |
| of the first instance can exercise prima facie test jurisdiction | |
| to screen and knock down ex facie meritless, frivolous and | |
| dishonest litigation. Limited jurisdiction of the courts ensures | |
| expeditious, alacritous and efficient disposal when required | |
| at the referral stage.” | |
| (Emphasis supplied) |
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 50 of 85
83. This Court further held that the referral court, while exercising its powers
under Sections 8 and 11 respectively of the Act, 1996 could exercise its
powers to screen and knock down ex facie meritless, frivolous and
dishonest litigation so as to ensure expeditious and efficient disposal at the
referral stage.
“148. Section 43(1) of the Arbitration Act states that the
Limitation Act, 1963 shall apply to arbitrations as it applies
to court proceedings. Sub-section (2) states that for the
purposes of the Arbitration Act and Limitation Act,
arbitration shall be deemed to have commenced on the date
referred to in Section 21. Limitation law is procedural and
normally disputes, being factual, would be for the arbitrator
to decide guided by the facts found and the law applicable.
The court at the referral stage can interfere only when it is
manifest that the claims are ex facie time-barred and dead,
or there is no subsisting dispute. All other cases should be
referred to the Arbitral Tribunal for decision on merits.
Similar would be the position in case of disputed “no-claim
certificate” or defence on the plea of novation and “accord
and satisfaction”. As observed in Premium Nafta Products
Ltd. [Fili Shipping Co. Ltd. v. Premium Nafta Products Ltd.,
2007 UKHL 40 : 2007 Bus LR 1719 (HL)] , it is not to be
expected that commercial men while entering transactions
inter se would knowingly create a system which would
require that the court should first decide whether the contract
should be rectified or avoided or rescinded, as the case may
be, and then if the contract is held to be valid, it would require
the arbitrator to resolve the issues that have arisen.”
(Emphasis supplied)
84. Speaking in the specific context of “limitation” and “accord and
satisfaction”, this Court in Vidya Drolia (supra) held that the procedural
and factual disputes, like the one in the present litigation, should be left for
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 51 of 85
the arbitrator to decide, who in turn, would be guided by the facts as
determined by him and the law applicable. However, while re-iterating the
position established in Mayavati Trading (supra), i.e., the principal of
minimal interference at the stage of Section 11(6) petitions by referral
courts in light of the introduction of Section 11(6-A) to the Act, 1996, this
Court in Vidya Drolia (supra) carved out an exceptional category of cases
in which interference by the referral court was permissible thus:
“154.1. Ratio of the decision in Patel Engg. Ltd. [SBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] on the scope of
judicial review by the court while deciding an application
under Sections 8 or 11 of the Arbitration Act, post the
amendments by Act 3 of 2016 (with retrospective effect from
23-10-2015) and even post the amendments vide Act 33 of
2019 (with effect from 9-8-2019), is no longer applicable.
154.2. Scope of judicial review and jurisdiction of the court
under Sections 8 and 11 of the Arbitration Act is identical but
extremely limited and restricted.
154.3. The general rule and principle, in view of the
legislative mandate clear from Act 3 of 2016 and Act 33 of
2019, and the principle of severability and competence-
competence, is that the Arbitral Tribunal is the preferred first
authority to determine and decide all questions of non-
arbitrability. The court has been conferred power of “second
look” on aspects of non-arbitrability post the award in terms
of sub-clauses (i), (ii) or (iv) of Section 34(2)(a) or sub-clause
(i) of Section 34(2)(b) of the Arbitration Act.
154.4. Rarely as a demurrer the court may interfere at
Section 8 or 11 stage when it is manifestly and ex facie
certain that the arbitration agreement is non-existent, invalid
or the disputes are non-arbitrable, though the nature and
facet of non-arbitrability would, to some extent, determine
the level and nature of judicial scrutiny. The restricted and
limited review is to check and protect parties from being
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 52 of 85
forced to arbitrate when the matter is demonstrably “non-
arbitrable” and to cut off the deadwood. The court by default
would refer the matter when contentions relating to non-
arbitrability are plainly arguable; when consideration in
summary proceedings would be insufficient and
inconclusive; when facts are contested; when the party
opposing arbitration adopts delaying tactics or impairs
conduct of arbitration proceedings. This is not the stage for
the court to enter into a mini trial or elaborate review so as
to usurp the jurisdiction of the Arbitral Tribunal but to affirm
and uphold integrity and efficacy of arbitration as an
alternative dispute resolution mechanism.”
(Emphasis supplied)
85. As is clear from the aforesaid extract, Vidya Drolia (supra) held that
although the arbitral tribunal is the preferred first authority to determine
the questions pertaining to non-arbitrability, yet the referral court may
exercise its limited jurisdiction to refuse reference to arbitration in cases
which are ex-facie frivolous and where it is certain that the disputes are
non-arbitrable.
86. The decision of this Court in Vidya Drolia (supra) was subsequently relied
upon by a two-Judge Bench of this Court in DLF Home Developers Ltd.
v. Rajapura Homes (P) Ltd. reported in (2021) 16 SCC 743 wherein it was
held that the prima facie review as laid down in Vidya Drolia (supra) , in
exceptional cases, warrants interference by the court to protect the wastage
of public money.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 53 of 85
“21. The jurisdiction of this Court under Section 11 is
primarily to find out whether there exists a written agreement
between the parties for resolution of disputes through
arbitration and whether the aggrieved party has made out a
prima facie arbitrable case. The limited jurisdiction,
however, does not denude this Court of its judicial function
to look beyond the bare existence of an arbitration clause to
cut the deadwood. A three-Judge Bench in Vidya
Drolia [Vidya Drolia v. Durga Trading Corpn., (2021) 2
SCC 1, paras 236, 237, 244.3, 244.4, 244.5, 244.5.1-244.5.3
: (2021) 1 SCC (Civ) 549] , has eloquently clarified that this
Court, with a view to prevent wastage of public and private
resources, may conduct “prima facie review” at the stage of
reference to weed out any frivolous or vexatious claims.”
87. In BSNL v. Nortel Networks (India) (P) Ltd., reported in (2021) 5 SCC
738 , this Court explained the scope of primary examination regarding the
aspect of non-arbitrability in the context of time-barred claims as laid down
in Vidya Drolia (supra) thus:
“45. In a recent judgment delivered by a three-Judge Bench
in Vidya Drolia v. Durga Trading Corpn. [Vidya
Drolia v. Durga Trading Corpn., (2021) 2 SCC 1 : (2021) 1
SCC (Civ) 549] , on the scope of power under Sections 8 and
11, it has been held that the Court must undertake a primary
first review to weed out “manifestly ex facie non-existent and
invalid arbitration agreements, or non-arbitrable disputes”.
The prima facie review at the reference stage is to cut the
deadwood, where dismissal is barefaced and pellucid, and
when on the facts and law, the litigation must stop at the first
stage. Only when the Court is certain that no valid arbitration
agreement exists, or that the subject-matter is not arbitrable,
that reference may be refused.
45.1. […] While exercising jurisdiction under Section 11 as
the judicial forum, the court may exercise the prima facie test
to screen and knockdown ex facie meritless, frivolous, and
dishonest litigation. Limited jurisdiction of the courts would
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 54 of 85
ensure expeditious and efficient disposal at the referral stage.
At the referral stage, the Court can interfere “only” when it
is “manifest” that the claims are ex facie time-barred and
dead, or there is no subsisting dispute. […]”
(Emphasis supplied)
88. The decision in Vidya Drolia (supra) was applied in the context of “accord
and satisfaction” by a two-Judge Bench of this Court in Indian Oil
Corporation Limited v. NCC Limited reported in (2023) 2 SCC 539 . It was
held that although the referral court under Section 11 of the 1996 Act may
look into the aspect of “accord and satisfaction”, yet it is advisable that in
debatable cases and disputable facts, more particularly in reasonably
arguable cases, the determination of whether accord and satisfaction was
actually present or not should be left to the arbitral tribunal. This Court also
expressed disagreement with the High Court which had held that post the
insertion of Section 11(6-A) to the Act, 1996, the scope of interference of
the referral court in a Section 11 petition was limited to the aspect of
examining the existence of a binding arbitration agreement qua the parties
before it. Relevant extracts are reproduced hereinbelow:
“90. […] Therefore, even when it is observed and held that
such an aspect with regard to “accord and satisfaction” of
the claims may/can be considered by the Court at the stage
of deciding Section 11 application, it is always advisable
and appropriate that in cases of debatable and disputable
facts, good reasonably arguable case, the same should be
left to the Arbitral Tribunal. Similar view is expressed by
this Court in Vidya Drolia [Vidya Drolia v. Durga Trading
Corpn., (2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549] .
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 55 of 85
91. Therefore, in the facts and circumstances of the case,
though it is specifically observed and held that aspects with
regard to “accord and satisfaction” of the claims can be
considered by the Court at the stage of deciding Section
11(6) application, in the facts and circumstances of the
case, the High Court has not committed any error in
observing that aspects with regard to “accord and
satisfaction” of the claims or where there is a serious
dispute will have to be left to the Arbitral Tribunal.
92. However, at the same time, we do not agree with the
conclusion arrived at by the High Court that after the
insertion of sub-section (6-A) in Section 11 of the
Arbitration Act, scope of inquiry by the Court in Section 11
petition is confined only to ascertain as to whether or not a
binding arbitration agreement exists qua the parties before
it, which is relatable to the disputes at hand.
93. We are of the opinion that though the Arbitral Tribunal
may have jurisdiction and authority to decide the disputes
including the question of jurisdiction and non-arbitrability,
the same can also be considered by the Court at the stage of
deciding Section 11 application if the facts are very clear
and glaring and in view of the specific clauses in the
agreement binding between the parties, whether the dispute
is non-arbitrable and/or it falls within the excepted clause.
Even at the stage of deciding Section 11 application, the
Court may prima facie consider even the aspect with regard
to “accord and satisfaction” of the claims.
94. Now, so far as the submission on behalf of the respective
parties on the decision of the General Manager on notified
claims in Civil Appeal No. 341 of 2022 arising out of SLP
(C) No. 13161 of 2019 is concerned, the General Manager
has decided/declared that the claims are not arbitrable
since they had been settled and the arbitration agreement
has been discharged under Clause 6.7.2.0 of GCC and no
longer existed/subsisted. As observed hereinabove, the
claims had been settled or not is a debatable and disputable
question, which is to be left to be decided by the Arbitral
Tribunal. Therefore, matters related to the notified claims
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 56 of 85
| in the facts and circumstances of the case also shall have to | |
|---|---|
| be left to be decided by the Arbitral Tribunal as in the fact | |
| situation the aspect of “accord and satisfaction” and | |
| “notified claims” both are interconnected and interlinked.” | |
| (Emphasis supplied) | |
(supra) . While the dictum in Vidya Drolia (supra) allows for interference
by the referral court, it only allows so as an exception in cases where ex-
facie meritless claims are sought to be referred to arbitration. However, the
view taken in Indian Oil (supra) takes a position which was taken by this
Court in Boghara Polyfab (supra), wherein it was held that the issue of
accord and satisfaction could either be decided by the referring authority
or be left for the arbitrator to decide. This pre-2015 position, as was also
pointed in Mayavati Trading (supra), was legislatively overruled by the
2015 amendment to the Act, 1996 and the introduction of Section 11(6-A).
Thus, in our view, the intention of this Court in Vidya Drolia (supra) was
not to hold that despite the 2015 amendment, the position regarding
“accord and satisfaction” would continue to be one which was taken in
Boghara Polyfab (supra) . Vidya Drolia (supra) only went a step ahead
from the position in Mayavati Trading (supra) to create an exception that
although the rule is to refer all questions of “accord and satisfaction” to the
arbitral tribunal, yet in exceptional cases and in the interest of expediency,
ex facie meritless claims could be struck down.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 57 of 85
90. In NTPC Ltd. v. SPML Infra Ltd. reported in (2023) 9 SCC 385 , a two-
Judge Bench of this Court was again faced with the issue of “accord and
satisfaction” in the context of a Section 11 petition for appointment of
arbitrator. Placing reliance on Vidya Drolia (supra) , this Court gave the
“Eye of the Needle” test to delineate the contours of the power of
interference which the referral court may exercise under Section 11 of the
Act, 1996. The first prong of the said test requires the court to examine the
validity and existence of the arbitration agreement which includes an
examination of the parties to the agreement and the privity of the applicant
to the contract. The second prong of the test requires the court to, as a
general rule, leave all questions of non-arbitrability to the arbitral tribunal
and only as a demurrer reject the claims which are ex-facie and manifestly
non-arbitrable. However, it was clarified that the standard of the aforesaid
scrutiny is only prima facie , that is, unlike the pre-2015 position, the
scrutiny does not entail elaborate appreciation of evidence and conduct of
mini trials by the referral courts. The relevant observations made therein
are reproduced hereinbelow:
“24. Following the general rule and the principle laid down
in Vidya Drolia [Vidya Drolia v. Durga Trading Corpn.,
(2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549] , this Court has
consistently been holding that the Arbitral Tribunal is the
preferred first authority to determine and decide all questions
of non-arbitrability. In Pravin Electricals (P) Ltd. v. Galaxy
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 58 of 85
Infra & Engg. (P) Ltd. [Pravin Electricals (P) Ltd. v. Galaxy
Infra & Engg. (P) Ltd., (2021) 5 SCC 671, paras 29, 30 :
(2021) 3 SCC (Civ) 307] , Sanjiv Prakash v. Seema
Kukreja [Sanjiv Prakash v. Seema Kukreja, (2021) 9 SCC
732 : (2021) 4 SCC (Civ) 597] , and Indian Oil Corpn.
Ltd. v. NCC Ltd. [Indian Oil Corpn. Ltd. v. NCC Ltd., (2023)
2 SCC 539 : (2023) 1 SCC (Civ) 88] , the parties were
referred to arbitration, as the prima facie review in each of
these cases on the objection of non-arbitrability was found to
be inconclusive. Following the exception to the general
principle that the Court may not refer parties to arbitration
when it is clear that the case is manifestly and ex facie non-
arbitrable, in BSNL v. Nortel Networks (India) (P)
Ltd. [BSNL v. Nortel Networks (India) (P) Ltd., (2021) 5 SCC
738 : (2021) 3 SCC (Civ) 352] (hereinafter “Nortel
Networks”) and Secunderabad Cantonment Board v. B.
Ramachandraiah & Sons [Secunderabad Cantonment
Board v. B. Ramachandraiah & Sons, (2021) 5 SCC 705 :
(2021) 3 SCC (Civ) 335] , arbitration was refused as the
claims of the parties were demonstrably time-barred.
Eye of the needle
25. The abovereferred precedents crystallise the position of
law that the pre-referral jurisdiction of the Courts under
Section 11(6) of the Act is very narrow and inheres two
inquiries. The primary inquiry is about the existence and the
validity of an arbitration agreement, which also includes an
inquiry as to the parties to the agreement and the applicant's
privity to the said agreement. These are matters which
require a thorough examination by the Referral Court. The
secondary inquiry that may arise at the reference stage itself
is with respect to the non-arbitrability of the dispute.
26. As a general rule and a principle, the Arbitral Tribunal
is the preferred first authority to determine and decide all
questions of non-arbitrability. As an exception to the rule,
and rarely as a demurrer, the Referral Court may reject
claims which are manifestly and ex facie non-
arbitrable [Vidya Drolia v. Durga Trading Corpn., (2021) 2
SCC 1, para 154.4 : (2021) 1 SCC (Civ) 549] […]
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 59 of 85
27. The standard of scrutiny to examine the non-arbitrability
of a claim is only prima facie. Referral Courts must not
undertake a full review of the contested facts; they must only
be confined to a primary first review [Vidya Drolia v. Durga
Trading Corpn., (2021) 2 SCC 1, para 134 : (2021) 1 SCC
(Civ) 549] and let facts speak for themselves. This also
requires the Courts to examine whether the assertion on
arbitrability is bona fide or not. [Vidya Drolia v. Durga
Trading Corpn., (2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549]
The prima facie scrutiny of the facts must lead to a clear
conclusion that there is not even a vestige of doubt that the
claim is non-arbitrable. [BSNL v. Nortel Networks (India)
(P) Ltd., (2021) 5 SCC 738, para 47 : (2021) 3 SCC (Civ)
352] On the other hand, even if there is the slightest doubt,
the rule is to refer the dispute to arbitration [Vidya
Drolia v. Durga Trading Corpn., (2021) 2 SCC 1, para 154.4
: (2021) 1 SCC (Civ) 549].”
(Emphasis supplied)
91. The justification given in NTPC v. SPML (supra) for allowing the scrutiny
of arbitrability at the stage of Section 11 petition was that the referral court
is under a duty to protect the parties from being forced to arbitrate when
the matter is demonstrably non-arbitrable, and any interference by the
referral court preventing such ex-facie meritless arbitration could be
termed as legitimate. It was observed thus:
“28. The limited scrutiny, through the eye of the needle, is
necessary and compelling. It is intertwined with the duty of
the Referral Court to protect the parties from being forced to
arbitrate when the matter is demonstrably non-arbitrable . It
has been termed as a legitimate interference by Courts to
refuse reference in order to prevent wastage of public and
private resources [Vidya Drolia v. Durga Trading Corpn.,
(2021) 2 SCC 1, para 139 : (2021) 1 SCC (Civ) 549] .
Further, as noted in Vidya Drolia [Vidya Drolia v. Durga
Trading Corpn., (2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549] ,
if this duty within the limited compass is not exercised, and
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 60 of 85
the Court becomes too reluctant to intervene, it may
undermine the effectiveness of both, arbitration and the
Court [Vidya Drolia v. Durga Trading Corpn., (2021) 2 SCC
1, para 139 : (2021) 1 SCC (Civ) 549] . Therefore, this Court
or a High Court, as the case may be, while exercising
jurisdiction under Section 11(6) of the Act, is not expected
to act mechanically merely to deliver a purported dispute
raised by an applicant at the doors of the chosen arbitrator,
as explained in DLF Home Developers Ltd. v. Rajapura
Homes (P) Ltd. [DLF Home Developers Ltd. v. Rajapura
Homes (P) Ltd., (2021) 16 SCC 743, paras 22, 26 : 2021 SCC
OnLine SC 781, paras 18, 20]”
92. The position that emerges from the aforesaid discussion of law on the
subject as undertaken by us can be summarised as follows: -
i. There were two conflicting views which occupied the field under the
Arbitration Act, 1940. While the decisions in Damodar Valley
(supra) and Amar Nath (supra) took the view that the disputes
pertaining to “accord and satisfaction” should be left to the arbitrator
to decide, the view taken in P.K. Ramaiah (supra) and Nathani
Steels (supra) was that once a “full and final settlement” is entered
into between the parties, no arbitrable disputes subsist and therefore
reference to arbitration must not be allowed.
ii. Under the Act, 1996, the power under Section 11 was characterised
as an administrative one as acknowledged in the decision in Konkan
Railway (supra) and this continued till the decision of a seven-Judge
Bench in SBP & Co. (supra) overruled it and significantly expanded
the scope of judicial interference under Sections 8 and 11
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 61 of 85
respectively of the Act, 1996. The decision in Jayesh Engineering
(supra) adopted this approach in the context of “accord and
satisfaction” cases and held that the issue whether the contract had
been fully worked out and whether payments had been made in full
and final settlement of the claims are issues which should be left for
the arbitrator to adjudicate upon.
iii. The decision in SBP & Co. (supra) was applied in Boghara Polyfab
(supra) and it was held by this Court that the Chief Justice or his
designate, in exercise of the powers available to them under Section
11 of the Act, 1996, can either look into the question of “accord and
satisfaction” or leave it for the decision of the arbitrator. However,
it also specified that in cases where the Chief Justice was satisfied
that there was indeed “accord and satisfaction”, he could reject the
application for appointment of arbitrator. The prima facie standard
of scrutiny was also expounded, stating that the party seeking
arbitration would have to prima facie establish that there was fraud
or coercion involved in the signing of the discharge certificate. The
position elaborated in Boghara Polyfab (supra) was adopted in a
number of subsequent decisions, wherein it was held that a mere bald
plea of fraud or coercion was not sufficient for a party to seek
reference to arbitration and prima facie evidence for the same was
required to be provided, even at the stage of the Section 11 petition.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 62 of 85
iv. The view taken by SBP & Co. (supra) and Boghara Polyfab (supra)
was seen by the legislature as causing delays in the disposal of
Section 11 petitions, and with a view to overcome the same, Section
11(6-A) was introduced in the Act, 1996 to limit the scope of enquiry
under Section 11 only to the extent of determining the “existence”
of an arbitration agreement. This intention was acknowledged and
given effect to by this Court in the decision in Duro Felguera
(supra) wherein it was held that the enquiry under Section 11 only
entailed an examination whether an arbitration agreement existed
between the parties or not and “ nothing more or nothing less ”.
v. Despite the introduction of Section 11(6-A) and the decision in Duro
Felguera (supra) , there have been diverging views of this Court on
whether the scope of referral court under Section 11 of the Act, 1996
includes the power to go into the question of “accord and
satisfaction”. In Antique Art (supra) it was held that unless some
prima facie proof of duress or coercion is adduced by the claimant,
there could not be a referral of the disputes to arbitration. This view,
however, was overruled in Mayavati Trading (supra) which
reiterated the view taken in Duro Felguera (supra) and held that
post the 2015 amendment to the Act, 1996, it was no more open to
the Court while exercising its power under Section 11 of the Act,
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 63 of 85
1996 to go into the question of whether “accord and satisfaction”
had taken place.
vi. The decision in Vidya Drolia (supra) although adopted the view
taken in Mayawati Trading (supra) yet it provided that in
exceptional cases, where it was manifest that the claims were ex-
facie time barred and deadwood, the Court could interfere and refuse
reference to arbitration. Recently, this view in the context of “accord
and satisfaction” was adopted in NTPC v. SPML (supra) wherein
the “eye of the needle” test was elaborated. It permits the referral
court to reject arbitration in such exceptional cases where the plea of
fraud or coercion appears to be ex-facie frivolous and devoid of
merit.
93. Thus, the position after the decisions in Mayavati Trading (supra) and
Vidya Drolia (supra) is that ordinarily, the Court while acting in exercise
of its powers under Section 11 of the Act, 1996, will only look into the
existence of the arbitration agreement and would refuse arbitration only as
a demurrer when the claims are ex-facie frivolous and non-arbitrable.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 64 of 85
iii. What is the effect of the decision of this Court in In Re: Interplay Between
Arbitration Agreements under the Arbitration and Conciliation Act 1966
and the Indian Stamp Act 1899 on the scope of powers of the referral court
under Section 11 of the Act, 1996?
94. A seven-Judge Bench of this Court, in In Re: Interplay Between
Arbitration Agreements under the Arbitration and Conciliation Act 1966
and the Indian Stamp Act 1899 reported in 2023 INSC 1066 , speaking
eruditely through one of us, Dr Dhananjaya Y. Chandrachud, Chief Justice
of India, undertook a comprehensive analysis of Sections 8 and 11
respectively of the Act, 1996 and, inter alia, made poignant observations
about the nature of the power vested in the Courts insofar as the aspect of
appointment of arbitrator is concerned. Some of the relevant observations
made by this Court in In Re: Interplay (supra) are extracted hereinbelow:
“179. […] However, the effect of the principle of
competence-competence is that the arbitral tribunal is vested
with the power and authority to determine its enforceability.
The question of enforceability survives, pending the curing of
the defect which renders the instrument inadmissible. By
appointing a tribunal or its members, this Court (or the High
Courts, as the case may be) is merely giving effect to the
principle enshrined in Section 16. The appointment of an
arbitral tribunal does not necessarily mean that the
agreement in which the arbitration clause is contained as
well as the arbitration agreement itself are enforceable. The
arbitral tribunal will answer precisely these questions.
xxx xxx xxx
185. The corollary of the doctrine of competence-competence
is that courts may only examine whether an arbitration
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 65 of 85
agreement exists on the basis of the prima facie standard of
review. The nature of objections to the jurisdiction of an
arbitral tribunal on the basis that stamp-duty has not been
paid or is inadequate is such as cannot be decided on a prima
facie basis. Objections of this kind will require a detailed
consideration of evidence and submissions and a finding as
to the law as well as the facts. Obligating the court to decide
issues of stamping at the Section 8 or Section 11 stage will
defeat the legislative intent underlying the Arbitration Act.
186. The purpose of vesting courts with certain powers under
Sections 8 and 11 of the Arbitration Act is to facilitate and
enable arbitration as well as to ensure that parties comply
with arbitration agreements. The disputes which have arisen
between them remain the domain of the arbitral tribunal
(subject to the scope of its jurisdiction as defined by the
arbitration clause). The exercise of the jurisdiction of the
courts of the country over the substantive dispute between the
parties is only possible at two stages:
a. If an application for interim measures is filed under
Section 9 of the Arbitration Act; or
b. If the award is challenged under Section 34.
Issues which concern the payment of stamp-duty fall within
the remit of the arbitral tribunal. The discussion in the
preceding segments also make it evident that courts are not
required to deal with the issue of stamping at the stage of
granting interim measures under Section 9.”
(Emphasis supplied)
95. We would like to analyse and elaborate some of the observations from the
aforesaid decision which are highly pertinent to the dispute at hand.
a. Arbitral Autonomy
96. The principle of judicial non-interference permeates the scheme of the Act,
1996. The principle of competence-competence as contained in Section 16
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 66 of 85
of the Act, 1996 indicates that the arbitral tribunal enjoys sufficient
autonomy from the national courts. The underlying principle behind
arbitral autonomy and judicial non-interference is that when parties
mutually decide to settle their disputes through arbitration, they surrender
their right to agitate the same before the national courts.
97. Section 5 of the Act, 1996 also minimises the supervisory role that the
courts may play in the arbitral process. There are two facets to Section 5 –
positive and negative. The positive facet allows the judicial authorities to
exercise jurisdiction over matters expressly permitted under the Act, 1996.
The negative aspect, on the other hand, prohibits the judicial authorities
from intervening in the arbitral proceedings in situations where the arbitral
tribunal has been conferred with exclusive jurisdiction.
98. What follows from the negative facet of arbitral autonomy when applied
in the context of Section 16 is that the national courts are prohibited from
interfering in matters pertaining to the jurisdiction of the arbitral tribunal,
as exclusive jurisdiction on those aspects vests with the arbitral tribunal.
The legislative mandate of prima facie determination at the stage of
Sections 8 and 11 respectively ensures that the referral courts do not end
up venturing into what is intended by the legislature to be the exclusive
domain of the arbitral tribunal.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 67 of 85
1
99. Gary B. Born describes arbitral autonomy as intrinsically related to the
‘right to arbitrate’, which in turn is a concomitant of freedom of contract,
liberty of association and personal autonomy. He describes “ the right of
parties to resolve their disputes, with one another, in a manner of their
own choosing ” as “ a basic aspect of individual autonomy and liberty,
which is properly accorded protection in almost all developed legal
systems .” He also stresses on the importance of autonomy of parties to
arbitrate as giving effect to fundamental right to autonomy of parties and
increasing their access to justice. Characterising the right to arbitrate as an
important political right, he observes that “ voluntary agreements, by free
men and women, to resolve their disputes between themselves, in a manner
which they structure, are the exercise of basic rights of liberty, association
2
and property and a bulwark against governmental oppression. ”
100. In Hayter v. Nelson reported in [1990] 2 Lloyd's Rep. 265, 272 , it was
observed that the “ modern view in line with the basic principles of the
English law of freedom of contract and indeed International Conventions
is that there is no good reason why the Courts should strive to take matters
rd
1
Gary B. Born, Internation Commercial Arbitration, 3 Ed. (2021), pp. 685
rd
2
Gary B. Born, Internation Commercial Arbitration, 3 Ed. (2021), pp. 696
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 68 of 85
out of the hands of the tribunal into which the parties have by agreement
undertaken to place them ”.
b. Negative Competence-Competence
101. Section 16 of the Act, 1996 recognises the doctrine of competence-
competence and empowers the arbitral tribunal to rule on its own
jurisdiction. The policy consideration for the same is, firstly , to recognise
the intention of the parties in choosing arbitration as the method for
resolving the disputes arising out of the contract and secondly , to prevent
the parties from initiating parallel proceedings before courts and delaying
the arbitral process.
102. The negative aspect of competence-competence is aimed at restricting the
interference of the courts at the referral stage by preventing the courts from
examining the issues pertaining to the jurisdiction of the arbitral tribunal
before the arbitral tribunal itself has had the opportunity to entertain them.
The courts are allowed to review the decision of the arbitral tribunal at a
later stage.
103. The principle of negative competence-competence has also been codified
by the national statutory frameworks for international arbitration. For
example, in French New Code of Civil Procedure, 1981 and the French
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 69 of 85
Decree No. 2011- 48 of 13 January 2011 Reforming the Law Governing
Arbitration, the concept of negative competence-competence was codified
based on the decision of Court of Appeal in Colmar Impex v. PAZ ,
reported in 1968 Rev. Arb. 149, 155 (Colmar Cour d’Appeal) . In the said
decision, it was observed that, “ the principle is that the judge hearing a
dispute has jurisdiction to determine his own jurisdiction. This necessarily
implies that when that judge is an arbitrator, whose powers derive from
the agreement of the parties, he has jurisdiction to examine the existence
and validity of such agreement ”.
104. Supreme Court of the United States too has, on a number of occasions,
consistently affirmed that by virtue of the separability presumption, where
there is only a challenge to the validity or legality of the underlying
contract, and no challenge to the existence, validity, or legality of the
associated arbitration clause itself, the claims should be referred to
arbitration. [See: Prima Paint Corp. v. Flood & Conklin Manufacturing
Co . reported in 388 U.S. 395 (U.S. S.Ct. 1967) ; Buckeye Check Cashing,
Inc. v. Cardegna reported in 546 U.S. 440 (U.S. S.Ct. 2006) ]
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 70 of 85
3
105. In the specific context of settlement of original contract, Gary Born writes
that “ US lower courts have repeatedly applied the separability
presumption in holding that claims regarding the validity or enforceability
of the underlying contract do not impeach the separable arbitration clause
and for decisions by the arbitrators .” Referring to the cases in which the
aforesaid principles have been applied, he writes “that approach has been
opted in diverse settings including in the case of Ambulance Biling Sys.,
Inc. v. Gemini Ambulance Servs., Inc., 103 S.W.3d 507, 514-515 (Tex. App.
2003) wherein arbitrators were given the power to decide regarding
whether a settlement agreement was reached replacing or cancelling
original agreement.”
106. In Howsam v. Dean Witter Reynolds, Inc. reported in 537 U.S. 79, 84
(U.S. S.Ct. 2002) , it was observed by the US Supreme Court that "the
presumption is that the arbitrator should decide allegation[s] of waiver,
delay, or alike defense to arbitrability.”
c. Judicial Interference under the Act, 1996
107. The parties have been conferred with the power to decide and agree on the
procedure to be adopted for appointing arbitrators. In cases where the
rd
3
Gary B. Born, Internation Commercial Arbitration, 3 Ed. (2021), pp. 1251
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 71 of 85
agreed upon procedure fails, the courts have been vested with the power to
appoint arbitrators upon the request of a party, to resolve the deadlock
between the parties in appointing the arbitrators.
108. Section 11 of the Act, 1996 is provided to give effect to the mutual
intention of the parties to settle their disputes by arbitration in situations
where the parties fail to appoint an arbitrator(s). The parameters of judicial
review laid down for Section 8 differ from those prescribed for Section 11.
The view taken in SBP & Co. (supra) and affirmed in Vidya Drolia (supra)
that Sections 8 and 11 respectively of the Act, 1996 are complementary in
nature was legislatively overruled by the introduction of Section 11(6-A)
in 2015. Thus, although both these provisions intend to compel parties to
abide by their mutual intention to arbitrate, yet the scope of powers
conferred upon the courts under both the sections are different.
109. The difference between Sections 8 and 11 respectively of the Act, 1996 is
also evident from the scope of these provisions. Some of these differences
are:
i. While Section 8 empowers any ‘judicial authority’ to refer the
parties to arbitration, under Section 11, the power to refer has been
exclusively conferred upon the High Court and the Supreme Court.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 72 of 85
ii. Under Section 37, an appeal lies against the refusal of the judicial
authority to refer the parties to arbitration, whereas no such
provision for appeal exists for a refusal under Section 11.
iii. The standard of scrutiny provided under Section 8 is that of prima
facie examination of the validity and existence of an arbitration
agreement. Whereas, the standard of scrutiny under Section 11 is
confined to the examination of the existence of the arbitration
agreement.
iv. During the pendency of an application under Section 8, arbitration
may commence or continue and an award can be passed. On the
other hand, under Section 11, once there is failure on the part of the
parties in appointing the arbitrator as per the agreed procedure and
an application is preferred, no arbitration proceedings can
commence or continue.
110. The scope of examination under Section 11(6-A) is confined to the
existence of an arbitration agreement on the basis of Section 7. The
examination of validity of the arbitration agreement is also limited to the
requirement of formal validity such as the requirement that the agreement
should be in writing.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 73 of 85
111. The use of the term ‘examination’ under Section 11(6-A) as distinguished
from the use of the term ‘rule’ under Section 16 implies that the scope of
enquiry under section 11(6-A) is limited to a prima facie scrutiny of the
existence of the arbitration agreement, and does not include a contested or
laborious enquiry, which is left for the arbitral tribunal to ‘rule’ under
Section 16. The prima facie view on existence of the arbitration agreement
taken by the referral court does not bind either the arbitral tribunal or the
court enforcing the arbitral award.
112. The aforesaid approach serves a two-fold purpose – firstly, it allows the
referral court to weed out non-existent arbitration agreements, and
secondly, it protects the jurisdictional competence of the arbitral tribunal
to rule on the issue of existence of the arbitration agreement in depth.
113. Referring to the Statement of Objects and Reasons of the Arbitration and
Conciliation (Amendment) Act, 2015, it was observed in In Re: Interplay
(supra) that the High Court and the Supreme Court at the stage of
appointment of arbitrator shall examine the existence of a prima facie
arbitration agreement and not any other issues. The relevant observations
are extracted hereinbelow:
“209. The above extract indicates that the Supreme Court or
High Court at the stage of the appointment of an arbitrator
shall “examine the existence of a prima facie arbitration
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 74 of 85
agreement and not other issues”. These other issues not
only pertain to the validity of the arbitration agreement, but
also include any other issues which are a consequence of
unnecessary judicial interference in the arbitration
proceedings. Accordingly, the “other issues” also include
examination and impounding of an unstamped instrument by
the referral court at the Section 8 or Section 11 stage. The
process of examination, impounding, and dealing with an
unstamped instrument under the Stamp Act is not a
timebound process, and therefore does not align with the
stated goal of the Arbitration Act to ensure expeditious and
time-bound appointment of arbitrators. […]”
(Emphasis supplied)
114. In view of the observations made by this Court in In Re: Interplay (supra) ,
it is clear that the scope of enquiry at the stage of appointment of arbitrator
is limited to the scrutiny of prima facie existence of the arbitration
agreement, and nothing else. For this reason, we find it difficult to hold
that the observations made in Vidya Drolia (supra) and adopted in NTPC
v. SPML (supra) that the jurisdiction of the referral court when dealing
with the issue of “accord and satisfaction” under Section 11 extends to
weeding out ex-facie non-arbitrable and frivolous disputes would continue
to apply despite the subsequent decision in In Re: Interplay (supra) .
115. The dispute pertaining to the “accord and satisfaction” of claims is not one
which attacks or questions the existence of the arbitration agreement in any
way. As held by us in the preceding parts of this judgment, the arbitration
agreement, being separate and independent from the underlying
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 75 of 85
substantive contract in which it is contained, continues to remain in
existence even after the original contract stands discharged by “accord and
satisfaction”.
116. The question of “accord and satisfaction”, being a mixed question of law
and fact, comes within the exclusive jurisdiction of the arbitral tribunal, if
not otherwise agreed upon between the parties. Thus, the negative effect
of competence-competence would require that the matter falling within the
exclusive domain of the arbitral tribunal, should not be looked into by the
referral court, even for a prima facie determination, before the arbitral
tribunal first has had the opportunity of looking into it.
117. By referring disputes to arbitration and appointing an arbitrator by exercise
of the powers under Section 11, the referral court upholds and gives effect
to the original understanding of the contracting parties that the specified
disputes shall be resolved by arbitration. Mere appointment of the arbitral
tribunal doesn’t in any way mean that the referral court is diluting the
sanctity of “accord and satisfaction” or is allowing the claimant to walk
back on its contractual undertaking. On the contrary, it ensures that the
principal of arbitral autonomy is upheld and the legislative intent of
minimum judicial interference in arbitral proceedings is given full effect.
Once the arbitral tribunal is constituted, it is always open for the defendant
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 76 of 85
to raise the issue of “accord and satisfaction” before it, and only after such
an objection is rejected by the arbitral tribunal, that the claims raised by
the claimant can be adjudicated.
118. Tests like the “eye of the needle” and “ex-facie meritless”, although try to
minimise the extent of judicial interference, yet they require the referral
court to examine contested facts and appreciate prima facie evidence
(however limited the scope of enquiry may be) and thus are not in
conformity with the principles of modern arbitration which place arbitral
autonomy and judicial non-interference on the highest pedestal.
119. Appointment of an arbitral tribunal at the stage of Section 11 petition also
does not mean that the referral courts forego any scope of judicial review
of the adjudication done by the arbitral tribunal. The Act, 1996 clearly
vests the national courts with the power of subsequent review by which the
award passed by an arbitrator may be subjected to challenge by any of the
parties to the arbitration.
120. The principle of subsequent judicial review has been enshrined in the US
doctrine of “Second Look”. In a leading U.S. Supreme Court judgement of
PacifiCare Health Systems, Inc. v. Book reported in 538, U.S. 401 (U.S.
S. Ct. 2003) , it was held that the question of non-arbitrability should be
considered in the first instance by the arbitral tribunal. The Court observed
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 77 of 85
that, “ since we do not know how the arbitrator will construe the remedial
limitations, the question ... whether they render the parties' agreements
unenforceable is better left for initial arbitral consideration” . This
doctrine has also been affirmed by judgements of the U.S. lower courts in
cases of Dillon v. BMO Harris Bank, NA reported in 856 F.3d 330, 333
(4th Cir. 2017) and Escobar v. Celebration Cruise Operator, Inc. reported
in 805 F.3d 1279, 1288-89 (11th Cir. 2015) wherein it was reasoned that
the issues of U.S. statutory law and arbitrability should be submitted first
to arbitration, with the possibility of subsequent judicial review in
recognition and enforcement proceedings.
121. In a case with similar facts but where an arbitration agreement is not in
existence, the claimant would have the recourse to approach a civil court
with its claims. Even in such proceedings before the civil court, it would
be open to the defendant to put forward the defence of “accord and
satisfaction” on the basis of the discharge voucher. Similarly, it would be
open to the claimant to allege that the voucher had been obtained under
fraud, coercion or undue influence. In such a scenario, the civil court would
consider the evidence as to whether there was any fraud, undue influence
or coercion. If the civil court finds that there was none, then it would reject
the claims at the outset. However, if it finds that the allegations of fraud
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 78 of 85
are true, then it would reject the discharge voucher and proceed to
adjudicate the claims on merit.
122. Once an arbitration agreement exists between parties, then the option of
approaching the civil court becomes unavailable to them. In such a
scenario, if the parties seek to raise a dispute, they necessarily have to do
so before the arbitral tribunal. The arbitral tribunal, in turn, can only be
constituted as per the procedure agreed upon between the parties.
However, if there is a failure of the agreed upon procedure, then the duty
of appointing the arbitral tribunal falls upon the referral court under Section
11 of the Act, 1996. If the referral court, at this stage, goes beyond the
scope of enquiry as provided under the section and examines the issue of
“accord and satisfaction”, then it would amount to usurpation of the power
which the parties had intended to be exercisable by the arbitral tribunal
alone and not by the national courts. Such a scenario would impeach
arbitral autonomy and would not fit well with the scheme of the Act, 1996.
123. The power available to the referral courts has to be construed in the light
of the fact that no right to appeal is available against any order passed by
the referral court under Section 11 for either appointing or refusing to
appoint an arbitrator. Thus, by delving into the domain of the arbitral
tribunal at the nascent stage of Section 11, the referral courts also run the
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 79 of 85
risk of leaving the claimant in a situation wherein it does not have any
forum to approach for the adjudication of its claims, if it Section 11
application is rejected.
124. Section 11 also envisages a time-bound and expeditious disposal of the
application for appointment of arbitrator. One of the reasons for this is also
the fact that unlike Section 8, once an application under Section 11 is filed,
arbitration cannot commence until the arbitral tribunal is constituted by the
referral court. This Court, on various occasions, has given directions to the
High Courts for expeditious disposal of pending Section 11 applications.
It has also directed the litigating parties to refrain from filing bulky
pleadings in matters pertaining to Section 11. Seen thus, if the referral
courts go into the details of issues pertaining to “accord and satisfaction”
and the like, then it would become rather difficult to achieve the objective
of expediency and simplification of pleadings.
125. We are also of the view that ex-facie frivolity and dishonesty in litigation
is an aspect which the arbitral tribunal is equally, if not more, capable to
decide upon the appreciation of the evidence adduced by the parties. We
say so because the arbitral tribunal has the benefit of going through all the
relevant evidence and pleadings in much more detail than the referral court.
If the referral court is able to see the frivolity in the litigation on the basis
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 80 of 85
of bare minimum pleadings, then it would be incorrect to doubt that the
arbitral tribunal would not be able to arrive at the same inference, most
likely in the first few hearings itself, with the benefit of extensive pleadings
and evidentiary material.
126. Before, we close the matter, it is necessary for us to clarify the dictum as
laid in M/s Arif Azim Co. Ltd. v. M/s Aptech Ltd. reported in 2024 INSC
155, so as to streamline the position of law and prevent the possibility of
any conflict between the two decisions that may arise in future.
127. In Arif Azim (supra), while deciding an application for appointment of
arbitrator under Section 11(6) of the Act, 1996, two issues had arisen for
our consideration:
i. Whether the Limitation Act, 1963 is applicable to an application for
appointment of arbitrator under Section 11(6) of the Arbitration and
Conciliation Act, 1996? If yes, whether the petition filed by M/s Arif
Azim was barred by limitation?
ii. Whether the court may decline to make a reference under Section 11
of Act, 1996 where the claims are ex-facie and hopelessly time-
barred?
128. On the first issue, it was observed by us that the Limitation Act, 1963 is
applicable to the applications filed under Section 11(6) of the Act, 1996.
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 81 of 85
Further, we also held that it is the duty of the referral court to examine that
the application under Section 11(6) of the Act, 1996 is not barred by period
of limitation as prescribed under Article 137 of the Limitation Act, 1963,
i.e., 3 years from the date when the right to apply accrues in favour of the
applicant. To determine as to when the right to apply would accrue, we had
observed in paragraph 56 of the said decision that “ the limitation period
for filing a petition under Section 11(6) of the Act, 1996 can only commence
once a valid notice invoking arbitration has been sent by the applicant to
the other party, and there has been a failure or refusal on part of that other
party in complying with the requirements mentioned in such notice .”
129. Insofar as the first issue is concerned, we are of the opinion that the
observations made by us in Arif Azim (supra) do not require any
clarification and should be construed as explained therein.
130. On the second issue it was observed by us in paragraph 67 that the referral
courts, while exercising their powers under Section 11 of the Act, 1996,
are under a duty to “ prima-facie examine and reject non-arbitrable or dead
claims, so as to protect the other party from being drawn into a time-
consuming and costly arbitration process.”
131. Our findings on both the aforesaid issues have been summarised in
paragraph 89 of the said decision thus: -
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 82 of 85
“89. Thus, from an exhaustive analysis of the position of law
on the issues, we are of the view that while considering the
issue of limitation in relation to a petition under Section 11(6)
of the Act, 1996, the courts should satisfy themselves on two
aspects by employing a two-pronged test – first, whether the
petition under Section 11(6) of the Act, 1996 is barred by
limitation; and secondly, whether the claims sought to be
arbitrated are ex-facie dead claims and are thus barred by
limitation on the date of commencement of arbitration
proceedings. If either of these issues are answered against the
party seeking referral of disputes to arbitration, the court may
refuse to appoint an arbitral tribunal.”
132. Insofar as our observations on the second issue are concerned, we clarify
that the same were made in light of the observations made by this Court in
many of its previous decisions, more particularly in Vidya Drolia (supra)
and NTPC v. SPML (supra) . However, in the case at hand, as is evident
from the discussion in the preceding parts of this judgment, we have had
the benefit of reconsidering certain aspects of the two decisions referred to
above in the light of the pertinent observations made by a seven-Judge
Bench of this Court in In Re: Interplay (supra) .
133. Thus, we clarify that while determining the issue of limitation in exercise
of the powers under Section 11(6) of the Act, 1996, the referral court should
limit its enquiry to examining whether Section 11(6) application has been
filed within the period of limitation of three years or not. The date of
commencement of limitation period for this purpose shall have to be
construed as per the decision in Arif Azim (supra). As a natural corollary,
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 83 of 85
it is further clarified that the referral courts, at the stage of deciding an
application for appointment of arbitrator, must not conduct an intricate
evidentiary enquiry into the question whether the claims raised by the
applicant are time barred and should leave that question for determination
by the arbitrator. Such an approach gives true meaning to the legislative
intention underlying Section 11(6-A) of the Act, and also to the view taken
in In Re: Interplay (supra) .
134. The observations made by us in Arif Azim (supra) are accordingly
clarified. We need not mention that the effect of the aforesaid clarification
is only to streamline the position of law, so as to bring it in conformity with
the evolving principles of modern-day arbitration, and further to avoid the
possibility of any conflict between the two decisions that may arise in
future. These clarifications shall not be construed as affecting the verdict
given by us in the facts of Arif Azim (supra) , which shall be given full
effect to notwithstanding the observations made herein.
F. CONCLUSION
135. The existence of the arbitration agreement as contained in Clause 13 of the
insurance policy is not disputed by the appellant. The dispute raised by the
claimant being one of quantum and not of liability, prima facie, falls within
the scope of the arbitration agreement. The dispute regarding “accord and
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 84 of 85
satisfaction” as raised by the appellant does not pertain to the existence of
the arbitration agreement, and can be adjudicated upon by the arbitral
tribunal as a preliminary issue.
136. For all the aforesaid reasons, we uphold and affirm the appointment of
Justice K.A. Puj, former Judge of the High Court of Gujarat as an arbitrator
to resolve the disputes between the parties.
137. The order staying the arbitration proceedings stands vacated.
138. All legal contentions including objections available to the appellant are
kept open to be taken up before the learned Arbitrator.
139. Pending application(s), if any, shall stand disposed of.
…………………………………….CJI
(Dr. Dhananjaya Y. Chandrachud)
………………………………………J.
(J.B. Pardiwala)
………………………………………J.
(Manoj Misra)
New Delhi;
th
18 July, 2024
Special Leave Petition (C) Nos. 3792/2024 & 7220/2024 Page 85 of 85