Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(S).18671868 OF 2022
(Arising out of Special Leave Petition
(C) No(s).1412414125/2021)
NARENDRA HIRAWAT AND CO. ......Appellant(s)
VERSUS
SHOLAY MEDIA ENTERTAINMENT PVT.
LTD. & ANR. ......Respondent(s)
WITH
CIVIL APPEAL NO(S).18691870 OF 2022
(Arising out of Special Leave Petition (C)
No(s).1431614317/2021)
O R D E R
Leave granted.
In connection with a suit for injunction and other reliefs filed by
the appellants, the learned Single Judge of the High Court of
Judicature at Bombay granted an order of interim injunction,
th
delivered on 9 March, 2020 which was challenged in appeals filed
before the Division Bench of the High Court. The appeals have been
allowed and the order of interim injunction granted by the Single
Signature Not Verified
Judge has been reversed by the Appellate Bench. Questioning the
Digitally signed by
Rajni Mukhi
Date: 2022.03.22
16:58:09 IST
Reason:
legality of the said order of the Division Bench, these appeals by way
1
of special leave petitions have been filed. As these appeals have been
filed against an interim order, we are giving only skeleton facts
relevant for the purpose of present appeals.
On 09.09.2015, two agreements were entered into between the
appellant namely, Narendra Hirawat and Company (for short ‘NHC’)
and respondent no.1, namely Sholay Media Entertainment Pvt. Ltd.
(for short ‘SME’) for the rights of films “Sholay and Sholay 3D” for the
period from 01.04.2016 to 31.03.2022 for an amount of Rs.20 crores.
The second agreement of the same date was executed for the rights of
the same films “Sholay and Sholay 3D” for the period from 01.04.2022
to 31.03.2027 for an amount of Rs.5 crores. This was in regard to the
first set of appeals (hereinafter referred to as “Sholay appeal”). In the
second set of appeals, similar agreements were executed on the same
date between the NHC and respondent no.1 therein i.e., Generation
Three Entertainment Pvt. Ltd. (hereinafter referred to ‘G3’). These were
with regard to the rights of the 32 films given in favour of NHC for a
similar length of period. The facts in both these sets of appeals,
though may not be identical but are very similar. For convenience we
shall deal with the facts of the first set of appeals, which we shall
henceforth refer to as “Sholay appeal”.
After the aforesaid agreements were executed, on 12.07.2016 two
2
addenda were executed in the license agreements dated 09.09.2015.
These addenda stipulated that on an additional amount of Rs.1.75
crores to be paid by NHC, the NHC would have the rights for unlimited
runs of the film and the period was also extended from 31.03.2027 to
30.09.2027. There were certain disputes with regard to the
mechanism arrived at in relation to payments of amounts and burden
of tax, which got amicably settled between the appellantNHC and
respondent no.1 SME. In between on 16.05.2018, a sublicense
agreement was executed between the appellant NHC and the
respondent no.2 namely, Goldmines Telefilms Pvt. Ltd. for rights of the
said film in favour of the respondent no.2, which was for the period of
15.11.2021 to 14.11.2026.
As already mentioned, since there were certain disputes between
NHC and respondent no.1 SME, there were dialogues between the
parties and ultimately a memorandum of settlement was arrived at
between the two parties on 05.11.2018. Finally, on 03.12.2018, a
Deed of Settlement was executed between the NHC and the SME
respondent no.1 in which the main stipulation was that NHC was to
pay a further sum of Rs.8.71 crores in four tranches of Rs.1.25 crores,
Rs.2.46 crores, Rs.2.50 crores and Rs.2.50 crores and instead of the
period which earlier was till 30.09.2027, the same was extended by
3
further one year, up to 30.09.2028.
Ultimately, the final dispute which has now culminated in these
proceedings is allegedly for noncompliance of the final Deed of
Settlement dated 03.12.2018, as according to the respondent no.1 the
payments have not been made in terms of Deed of Settlement. Stand
of NHC, however, is that substantial payments have already been
made, and what has not been paid was because of certain non
compliances on the part of the respondent no.1. It is stated that NHC
has always been ready and willing to make the payment. However, on
the ground of alleged noncompliance of the terms of the Deed of
Settlement dated 03.12.2018, a termination notice was issued by the
respondent no.1 on 18.06.2019.
The respondent no.2, by notice dated 26.08.2019, terminated the
sublicense agreement dated 16.05.2018 which was entered into with
NHC, and demanded refund of over Rs.11 crores from NHC.
With regard to the termination notice dated 18.06.2019 issued by
respondent no.1, NHC filed a commercial suit on 30.08.2019. Reliefs
claimed included prayer for declaration that the plaintiff is the sole
and exclusive licensee in respect of the suit films for all territories,
further declaration that the termination letter was illegal, bad in law,
null and void and unenforceable, permanent injunction restraining the
4
defendants from enjoying the licensed rights and damages. Temporary
injunction was also asked for. By order dated 09.03.2020, the learned
Single Judge of the High Court (before whom the commercial suit was
filed) granted interim injunction in favour of NHC, restraining the
respondents from disturbing the enjoyment of license rights of the
appellant in the suit films and also restrained the respondent no.1
SME from acting on the termination notice. Respondents no.1 & 2
were also restrained from acting on the agreement executed on
24.10.2019 which, after the filing of the suit, was entered into between
respondents no.1 and 2, awarding rights of the film Sholay and Sholay
3D in the first set of appeals and 32 films in the second set of appeals
in favour of respondent no.2. An intracourt appeal was filed assailing
the order of the learned Single Judge before the Division Bench of the
High Court, which has been allowed in favour of the respondents and,
hence, these appeals before this Court.
Mr. Mukul Rohatgi and Dr. A.M. Singhvi, learned senior counsel
along with Mr. Ankur Saigal, learned counsel have appeared for the
NHC in both sets of appeals. Mr. Neeraj Kishan Kaul, Mr. Siddharth
Bhatnagar and Mr. C.U. Singh, learned senior counsel along with Mr.
R.P. Gupta and Ms. Pooja Dhar, learned counsel have represented the
respondents in both sets of appeals. We have heard them at length
5
and perused the records.
The facts as narrated above are not disputed by the learned
counsel for the parties. From the above facts, what can be culled out
is that though there were certain disputes with regard to the payments
and other clauses of the initial agreements as well as the addenda, but
after the execution of the Deed of Settlement on 03.12.2018, all prior
disputes had been ironed out and what was now required was
compliance of the said deed. This deed provided that NHC was to pay
a sum of Rs.8.71 crores to the respondent no.1 in four tranches and
the period of license was to be extended for one year i.e. up to
30.09.2028 (instead of 30.09.2027 as earlier). Learned Single Judge
had considered all the aspects of the matter and held that the balance
of convenience was in favour of NHC and thereafter granted the
injunction in favour of the appellant. On the aspect of primafacie
case, the Single Judge found the payment obligation were by and large
met by the plaintiff (appellant before us). Argument was advanced
before the learned Single Judge on the basis of Section 14(d) of the
Specific Relief Act 1963 by the defendants. It was contended that the
subject contracts were determinable and hence no specific
performance thereof could be granted. The learned Single Judge,
however, found that this was not a clause which contemplated
6
unilateral determination but the right to determine was subject to the
other party committing breach of the agreement. As a condition for
granting interim relief, direction was given to the plaintiff to deposit
the entire balance amount of Rs.3.25 crore as per the settlement deed.
Such deposit was to be made in Court and we are apprised by learned
counsel for the plaintiff that this part of the direction has been
complied with.
The Division Bench has, in appeal, reconsidered the entire case
and decided in favour of the respondents. It has been, interalia, held
by the Division Bench in the judgment under appeal:
“62. The impugned order has brought about a highly
inequitable situation. A Plaintiff, who was not ready
and willing having consistently breached essential
terms of the Agreements, who was admittedly in
arrears on the date of the suit, who is yet to establish
its rights at the final trial; is permitted by through a
mandatory interim injunction to exploit all rights
under the terminated Agreement. The true owners of
the licensed material are prevented from monetizing
their property rights. The Goldmines Telefims, which
has paid money to both, Plaintiff and Licensor
Appellants, is deprived of exploiting the licenses. No
extraordinary situation existed for such a drastic
interim order.
63. Therefore, to recapitulate, as per the true
construction of the contract between parties, Plaintiff
has failed to establish that Plaintiff was and has
always been ready and willing to perform an essential
part of the terms of the contract. No prima facie case,
much less a high prima facie case, is established by
Plaintiff. No extraordinary circumstances exist to
grant a mandatory injunction again akin to the stay of
7
the termination six months after the termination was
effected and third party rights were created. Since the
basic essential terms of the contract and documents
on the record itself have been overlooked while
passing the impugned order, the grant of an
injunction will have to be set aside, even though these
appeals are appeals on principle.
64. As a result, these four Commercial Appeal, are
allowed. The common impugned order 9 March 2020
passed by the learned Single Judge in Notice of Motion
No.2591/2019 in Commercial IP Suit No.1387/2019
and Notice of Motion No.2607/2019 in Commercial IP
Suit No.1469/2019 is set aside. Considering the facts
and circumstances, no order as to costs.”
As we have noticed above, the entire case falls around the Deed
of Settlement executed on 03.12.2018. What is not disputed is that
out of the four payments which were to be made by NHC to the
respondent no.1, the first and the second payments were made by the
appellant NHC either simultaneously on the issuance of the invoice
by respondent no.1 or after the invoice had been issued. However,
after the first two payments were made, the respondent no.1 issued a
third invoice for an amount of Rs.1.75 crores (although the third
installment was to be of Rs.2.50 crores) only on 03.06.2019 and after
the invoice was issued, the payment of the entire amount of Rs.1.75
crores was made by NHC on 10.06.2019. It is the case of NHC that
thereafter NHC had been asking the respondent no.1 for issuance of
the invoices for the balance amount so as to enable NHC to make the
8
balance payment out of Rs.8.71 crores as agreed under the Deed of
Settlement but since the invoices were not issued (as the same were
required for payment of GST), no further payment was made by the
appellant NHC. According to NHC, on every occasion earlier the
payments were made by NHC only after the invoices were issued by
the respondent no.1 – SME, which included the GST amount and the
last payment could not be made because of non issuance of the
invoice by the respondent no.1 – SME.
The contention of the learned counsel for the respondent no.1 is
that the requirement of issuance of invoices was not a condition
precedent to the payments to be made in terms of the Deed of
Settlement dated 03.12.2018, whereas the NHC asserts that in terms
of clause 4 of the Deed of Settlement, respondent no.1 was to issue
the invoices against each tranche of payment stating the amount,
including the GST, after which the appellant NHC was to make the
payment. The entire controversy in the present case would hinge
around this provision as to whether NHC did not pay the amount in
terms of the Deed of Settlement because of nonissuance of invoices
by the respondent no.1 or otherwise.
In the facts of the present case, what we notice is that prior to
the execution of the Deed of Settlement, NHC had already paid an
9
amount over Rs.20 crores in terms of the initial agreement dated
09.09.2015. Then as per the Deed of Settlement also, Rs.5.46 crores
had already been paid. What we also notice is that from the record it is
clear, and not disputed by the respondents, that every payment that
was made by NHC, was against the invoices which were issued by the
respondent no.1.
The only reason given by the learned counsel for the respondent
no.1 for not issuing the invoices with regard to the balance amount
was that the liability of payment of GST would accrue immediately on
issuance of the invoices, even if NHC did not pay the money. We
cannot accept this form of justification as for all previous payments,
invoices had been issued by the respondent no.1 – SME.
At this stage, we would not like to give final verdict with regard
the interpretation of the various clauses of the Deed of Settlement,
including clause 4 relating to issuance of invoices, as the same would
be a matter to be considered first in the suit proceedings. However,
considering the conduct of the parties, specially the fact that the
invoices were issued by the respondent no. 1 before each of the
payments were made by the appellant – NHC, and only fraction of the
total payment remained to be paid, which also the learned Single
Judge, while issuing injunction in favour of NHC directed them to
10
deposit in court, in pursuance of which Rs.3.5 crores has already been
deposited by NHC in the High Court and also considering the other
attending factors and circumstances, we are of the opinion that the
injunction order granted by the Trial Court in favour of the appellant
cannot be faulted.
Even otherwise, we are of the opinion that interference by the
Division Bench of the High Court in appeal against the order of the
learned Single Judge granting the injunction was not justified
specially when the injunction order passed could not, in our opinion,
be said to be perverse or unjustified in law. Several authorities were
cited on behalf of the learned counsel for the parties outlining the
principles for granting interim injunction. In Wander Ltd. and Anr.
vs. Antox India P. Ltd. [1990 (supp) SCC 727] , it had been held:
“14.The appeals before the Division Bench were against the
exercise of discretion by the Single Judge. In such appeals,
the appellate court will not interfere with the exercise of
discretion of the court of first instance and substitute its
own discretion except where the discretion has been shown
to have been exercised arbitrarily, or capriciously or
perversely or where the court had ignored the settled
principles of law regulating grant or refusal of interlocutory
injunctions. An appeal against exercise of discretion is said
to be an appeal on principle. Appellate court will not
reassess the material and seek to reach a conclusion
different from the one reached by the court below if the one
reached by that court was reasonably possible on the
material. The appellate court would normally not be
justified in interfering with the exercise of discretion under
appeal solely on the ground that if it had considered the
11
| matter at the trial stage it would have come to a contrary<br>conclusion. If the discretion has been exercised by the trial<br>court reasonably and in a judicial manner the fact that the<br>appellate court would have taken a different view may not<br>justify interference with the trial court's exercise of<br>discretion. After referring to these principles<br>Gajendragadkar, J. In Printers (Mysore) Private Ltd.v.Pothan<br>Joseph[(1960) 3 SCR 713 : AIR 1960 SC 1156] : (SCR 721) | ||
|---|---|---|
| “... These principles are well established, but as<br>has been observed by Viscount Simon inCharles<br>Osenton & Co.v.Jhanaton[1942 AC 130] ‘...the<br>law as to the reversal by a court of appeal of an<br>order made by a judge below in the exercise of<br>his discretion is well established, and any<br>difficulty that arises is due only to the<br>application of well settled principles in an<br>individual case’.” | ||
| The appellate judgment does not seem to defer to this<br>principle.” |
In the case of
Shah Babulal Khimji Vs. Jayaben D. Kania and
Anr. [(1981) 4 SCC 8] , a three Judge Bench of this Court had opined
that Section 104 read with Order 43 Rule 1 of the Code of Civil
Procedure, 1908 applied to a Letters Patent appeal as well. In Dorab
Cawasji Warden Vs. Coomi Sorab Warden and Ors. [(1990) 2 SCC
117] grant of mandatory injunction at the interim stage has been left
to the sound judicial discretion of the Court. Metro Marins and Anr.
Vs. Bonus Watch Co. (P) Ltd. and Ors. [(2004) 7 SCC 478] also
follows the principles laid down in the case of
Dorab Cawasji Warden
(supra). But these two authorities dealt with the question of grant of
12
interim injunction in relation to disputes arising out of transfer of
immovable property. Applicability of Rules 1 and 2 of Order 39 of the
Code on the question of granting interim injunction has been
reconfirmed by a Coordinate Bench of this Court in Best Seller Retail
(India) Private Ltd. Vs. Aditya Birla Nuvo Ltd. and Ors. [(2012) 6
SCC 792]. In Colgate Palmolive (India) Ltd. Vs. Hindustan Lever
Ltd. [(1999) 7 SCC 1] , the principles guiding grant of interim
injunction have been summarized as:
| “24. We, however, think it fit to note herein below certain<br>specific considerations in the matter of grant of interlocutory<br>injunction, the basic being nonexpression of opinion as to<br>the merits of the matter by the court, since the issue of grant<br>of injunction, usually, is at the earliest possible stage so far<br>as the timeframe is concerned. The other considerations<br>which ought to weigh with the court hearing the application<br>or petition for the grant of injunctions are as below: | ||
|---|---|---|
| (i) extent of damages being an adequate remedy; | ||
| (ii) protect the plaintiff's interest for violation of his<br>rights though, however, having regard to the injury<br>that may be suffered by the defendants by reason<br>therefor; | ||
| (iii) the court while dealing with the matter ought not<br>to ignore the factum of strength of one party's case<br>being stronger than the other's; | ||
| (iv) no fixed rules or notions ought to be had in the<br>matter of grant of injunction but on the facts and<br>circumstances of each case — the relief being kept<br>flexible; | ||
| (v) the issue is to be looked at from the point of view<br>as to whether on refusal of the injunction the plaintiff<br>would suffer irreparable loss and injury keeping in<br>view the strength of the parties' case; |
13
( vi ) balance of convenience or inconvenience ought to
be considered as an important requirement even if
there is a serious question or prima facie case in
support of the grant;
( vii ) whether the grant or refusal of injunction will
adversely affect the interest of the general public
which can or cannot be compensated otherwise.”
In our opinion, however, each individual case is to be decided on
its own facts and in the present case, in view of the facts as narrated
above, equity is in favour of NHC. It has made substantial payments
and the balance, which is little more than 10% of the total amount,
has already been deposited in the High Court in terms of the
injunction order of the Single Judge. As regards the claim of the
respondent no.2, what is noteworthy is that initially the sublicense
agreement was executed between NHC and respondent no. 2 on
16.05.2018. After the dispute arose, the termination notice was issued
by the respondent no.1 on 18.06.2019. The suit had been filed by
NHC on 29.08.2019 and it was only then, on 24.10.2019 that the
respondent no.2 entered into a fresh agreement with respondent no.1
with regard to the same films being Sholay and Sholay 3D in the first
set of appeals and 32 other films in the second set of appeals.
Considering the aforesaid facts and keeping in view that the
agreements between respondents no.1 and 2 were entered into during
the pendency of the civil suit, of which the respondent no.2 would also
14
be well aware of, we are of the opinion that respondent no.2 would
also be governed by the injunction order granted by the Single Judge
of the High Court.
Since the facts of both sets of appeals are on the same lines, with
slight differences of certain dates and some amounts to be paid, and
there being no other material difference, both sets of appeals would be
governed by this order.
Accordingly, as we are of the firm view that the appellant has
made out a prima facie case for grant of injunction and also that the
balance of convenience is in favour of the appellant – NHC, hence we
allow these appeals. The Single Judge’s order was founded on sound
reasoning and we find no fault in exercise of discretion by the Single
Judge in granting the order of injunction. We, thus, set aside the order
passed by the Division Bench of the High Court and restore the order
of the learned Single Judge. The learned Single Judge, however, is
requested to expedite the hearing of the suit and decide the same as
expeditiously as possible, preferably within one year, in accordance
with law and without being influenced by any observations made by
the Single Judge while granting the injunction order or by the Division
Bench of the High Court passed in appeal, as well as by this Court.
The parties shall not seek any unnecessary adjournment in the High
15
Court.
There shall be no order as to costs.
………………………………,J.
(VINEET SARAN)
………………………………,J.
(ANIRUDDHA BOSE)
NEW DELHI;
MARCH 07, 2022.
16
ITEM NO.42 Court 9 (Video Conferencing) SECTION IX
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Petition(s) for Special Leave to Appeal (C) No(s).14124-14125/2021
(Arising out of impugned final judgment and order dated 26-08-2021
in CAL No.8026/2020 26-08-2021 in CAL No. 9909/2020 passed by the
High Court Of Judicature At Bombay)
NARENDRA HIRAWAT AND CO. Petitioner(s)
VERSUS
SHOLAY MEDIA ENTERTAINMENT PVT. LTD. & ANR. Respondent(s)
(List on 07.03.2022 as a first case after fresh matter
IA No. 124327/2021 - APPLICATION FOR PERMISSION
IA No. 114326/2021 - EXEMPTION FROM FILING C/C OF THE IMPUGNED
JUDGMENT, IA No.122789/2021 - PERMISSION TO FILE ADDITIONAL
DOCUMENTS/FACTS/ANNEXURES, IA No.121256/2021 - PERMISSION TO FILE
ADDITIONAL DOCUMENTS/FACTS/ANNEXURES, IA No.118654/2021 -
PERMISSION TO FILE ADDITIONAL DOCUMENTS/FACTS/ANNEXURES)
WITH
SLP(C) No. 14316-14317/2021 (IX)
(IA No.124314/2021 - APPLICATION FOR PERMISSION
IA No. 115227/2021 - EXEMPTION FROM FILING C/C OF THE IMPUGNED
JUDGMENT, IA No.122766/2021 - PERMISSION TO FILE ADDITIONAL
DOCUMENTS/FACTS/ANNEXURES)
Date : 07-03-2022 These matters were called on for hearing today.
CORAM :
HON'BLE MR. JUSTICE VINEET SARAN
HON'BLE MR. JUSTICE ANIRUDDHA BOSE
For Petitioner(s) Mr. Mukul Rohatgi, Sr. Adv.
SLP(C) 14124-25/21 Mr. Mahesh Agarwal, Adv.
Mr. Ankur Saigal, Adv.
Mr. Anirudh Bhatia, Adv.
Ms. Deepshikha Mishra, Adv.
Mr. E. C. Agrawala, AOR
SLP(C) 14316-17/21 Dr. A.M. Singhvi, Sr. Adv.
Mr. Mahesh Agarwal, Adv.
Mr. Ankur Saigal, Adv.
Mr. Anirudh Bhatia, Adv.
Ms. Deepshikha Mishra, Adv.
Mr. E. C. Agrawala, AOR
For Respondent(s) Mr. Neeraj Kishan Kaul, Sr. Adv.
17
Mr. Siddharth Bhatnagar, Sr. Adv.
Mr. Mehul M. Gupta, Adv.
Ms. Shreya Parikh, Adv.
Mr. Archit Jayakar, Adv.
Ms. Divya Tyagi, Adv.
Mr. R. P. Gupta, AOR
Mr. Chander Uday Singh, Sr. Adv.
Mr. Aurup Dasgupta, Adv.
Mr. Rohan Thawani, Adv.
Ms. Pooja Dhar, AOR
Ms. Gunjan Ahuja, Adv.
UPON hearing the counsel the Court made the following
O R D E R
Leave granted.
The appeals are allowed in terms of the signed reportable
order.
Pending application(s), if any, stands disposed of
accordingly.
(ARJUN BISHT) (RAM SUBHAG SINGH) (ASHWANI THAKUR)
(COURT MASTER (SH) (BRANCH OFFICER) AR-CUM-PS
(Signed reportable order is placed on the file)
18