Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
ABDUL KUDDUS MONDAL AND OTHERS
Vs.
RESPONDENT:
STATE OF ASSAM AND ANOTHER
DATE OF JUDGMENT: 23/08/1999
BENCH:
R.C.Lahoti, N. Santosh Hegde
JUDGMENT:
The application, for bringing on record legal
representatives of petitioner NO.2, is allowed. Legal
representatives are brought on record. They are present and
represented.
Delay condoned.
Leave granted.
This appeal arises out of land acquisition
proceedings. The preliminary Notification under Section
6(1) of the Assam Land (Requisition etc.) Act, 1964 was
issued by the Collector, Dhubri and possession of subject
land was taken over by the Collector on 7th March, 1988.
The Land Acquisition Collector made an Award in the case of
the appellants whereby land was assessed @ Rs.3804/- per
Bigha of Basti/ Sali and Rs.15,953/- per Bigha of Road side
land/ trade site land. The appellants were also awarded a
sum of Rs.15,087.10 for demolition and removal of the malba
of the houses belonging to the appellants, which were
standing on that land. The total Award made in favour of
the appellants on 2nd April, 1991 was for a sum of
Rs.46,118.40 including compensation for Zirut. The amount
was accepted by the appellants under protest. The
appellants sought a Reference under Section 18 of the Land
Acquisition Act, 1894. Evidence was led before the
Reference Court of the learned District Judge, Dhubri by the
parties. After examination of the evidence, the learned
Reference Court determined the market value of the land at
Rs.36,600/-; value of the houses at Rs.1,88,000/-; damages
on account of removal of houses at Rs.15,087.00; interest
on the difference on the amount of Award made by the
Collector from the date of possession of the land i.e. with
effect from 7th March, 1988 @ 9 % per annum and Solatium @
30% on the market value of the land. The amount of
compensation, on account of Zirut, as made by the Collector,
which was included in the detailed Award, was upheld. The
order of the Reference Court dated 22nd August, 1994 was put
in issue by the State before the Gauhati High Court. The
appellants also filed cross-objections in the High Court and
sought enhancement of the compensation fixed by the
Reference Court. The Division Bench of the High Court, vide
order dated 7th February, 1996, while directing respondents
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
to deposit 50% of the amount awarded by the District Judge,
Dhubri alongwith interest calculated till 30th April, 1996,
permitted the appellants to withdraw the amount so
deposited. The appeal was finally disposed of by the High
Court vide order dated 13th August, 1998. The Division
Bench fixed the rate of the compensation for the acquired
land at Rs.20,000/- per bigha. Insofar as compensation for
the houses is concerned, the same was completely negatived
and instead a sum of Rs.37,000/- being 20% of the valuation
of the houses fixed by the District Court was awarded as
just and proper compensation towards the loss and removal
costs of the houses. The directions regarding rate of
interest and solatium were not interfered with nor was
compensation for Zirut upset. The appellants have put the
order of the High Court in issue.
We have heard learned counsel for the parties.
It appears to us that the High Court fell into a basic
error in not awarding compensation for the houses on the
ground that since land had been acquired, it is only
compensation for removal of houses standing thereon, which
could have been granted because houses had not been
acquired. That is not a correct approach. The compensation
was required to be paid for the houses which was standing on
that land. The land could not have been acquired without
the houses standing thereon. The Reference Court had
rightly awarded compensation for the houses. The order of
the High Court on this account suffers from apparent error.
Insofar as the reduction in the rate for land from
Rs.36,600/-, as awarded by the Reference Court to
Rs.20.000/- per Bigha by the High Court is concerned, we are
not persuaded to disagree because we have not found any
error to have been committed by the High Court in that
behalf. The High Court has not adverted to the compensation
on account of Zirut separately, though compensation on that
account had been awarded by the Land Acquisition Collector
and upheld by the Reference Court. In the facts and
circumstances of this case and keeping in view the material
on the record, more particularly the evidence of the expert
who had valued the houses belonging to the appellants, we
are of the opinion that while the appellants are entitled to
compensation for land @ 20,000/- per Bigha, the appellants
are also entitled to compensation towards cost of houses.
The cost of houses was calculated by the Reference Court, on
the basis of expert evidence, at Rs.1,88.000/-. Taking into
account proper calculations, in our opinion, the appellants
are entitled to receive Rs.1,70,000/- towards cost of houses
and not Rs.1,88,000/-. Since, we are allowing the cost of
houses, the question of grant of damages and compensation of
Rs.15,087/- for removal of houses does not arise. The order
to that extent is set aside. Besides, the appellants are
also entitled to a sum of Rs.10,000/- for Zirut. So far as
interest is concerned, the interest at the rate of 9% per
annum shall be so calculated as to take into account the
amount already deposited by the State in the Executing Court
under orders of the High Court, which amount was allowed to
be withdrawn and has actually been withdrawn by the
appellants. The interest shall, therefore, be calculated
only on the differential amount for the remaining period
from the date of possession of the land by the Collector
i.e. 7.3.1988. The appellants shall be entitled to
Solatium at the rate of 30%.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
With the aforesaid modification of the order of the
High Court, the appeal is disposed of. No costs.