Full Judgment Text
NON REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
| .A. NO.4<br>I | OF 201<br>N |
M/S. ADANI POWER LTD. … APPLICANT/APPELLANT
Versus
GUJARAT ELECTRICITY REGULATORY
COMMISSION & OTHERS … RESPONDENTS
O R D E R
Chelameswar, J.
1. This application is filed by the appellant in Civil Appeal
JUDGMENT
No.11133/2011. The prayer in the application is as follows:
“a) to stay the operation of the impugned Judgment dated
7.9.2011 and suspend further supply of electricity in terms of the
PPA during the pendency of this Appeal.
b) in the alternative to prayer (a) above, during the pendency
of the accompanying Civil Appeal the Hon’ble Court may direct
the Respondent(s) to pay the tariff as per CERC norms for tariff on
cost plus basis; and also make the payment from the date of the
supply of power under the PPA of the differential amount between
the PPA tariff and the tariff as per CERC norms for tariff on cost
1
Page 1
plus basis on the such terms and condition as this Hon’ble court
deems fit as just and proper;”
However, prayer (a) was not pressed when the matter was
| A brief | backgro |
|---|
2. The appellant company is a power generating company.
nd
The 2 respondent herein is a company owned by the State of
Gujarat carrying on business of purchasing power in bulk
from power generating companies such as the appellant herein
and supplying to various distributing companies in the State
of Gujarat.
nd
3. The appellant and the 2 respondent entered into a
JUDGMENT
Power Purchase Agreement (hereinafter PPA, for short). Under
the said agreement, the appellant is obliged to sell 1000
megawatt of power from the appellant’s power project. For
various reasons, the details of which are not necessary at this
stage, the appellant issued a notice of termination dated
28.12.2009 of the above mentioned PPA w.e.f. 4.1.2010.
2
Page 2
nd
4. After some correspondence, the 2 respondent filed a
petition before the Gujarat Electricity Regulatory Commission
| ein) seek<br>ion of the | ing adju<br>PPA by |
|---|
st
5. The 1 respondent, by its order dated 31.8.2010, set
aside the termination notice sent by the appellant and directed
nd
the appellant to supply power to the 2 respondent as per the
terms of the PPA.
6. Aggrieved by the said order, the appellant carried the
matter in appeal before the Appellate Tribunal for Electricity
unsuccessfully. Hence, the appeal No.11133/2011. The
appeal was admitted by an order dated 13.8.2012 and since
JUDGMENT
pending. Hence the instant application with averments as
follows:
“7. If the relief sought for by the Appellant is not granted, there
is a serious risk of Mundra Power Project becoming a Non
Performing Asset causing an irreparable harm to the consumers as
well as the lenders of the Mundra Power Project. Since the main
Civil Appeal is pending adjudication for final hearing and the
Appellant is supplying the power to the Respondent No.2 –
GUVNL, the present application is being filed to compensate the
3
Page 3
Appellant upto the actual cost of generation as per CERC norms
for determination of tariff. The same is in order to sustain the
generation and supply of power pending the hearing of the main
Civil Appeal.
xxxx xxxx xxxx
| itted that w<br>uge losses up | hereas the<br>on the App |
|---|
nd
7. On behalf of the 2 respondent, an affidavit dated
23.11.2015 is filed. The said affidavit, while contesting the
various assertions made by the appellant and its rights,
stated:
15. I submit that, without prejudice to the rights of the
Respondent No.2 to contest the present appeal, the answering
Respondent with the approval of Government of Gujarat has
already shown its willingness to pay compensatory tariff
prospectively (from next month of CERC order i.e. March 2014)
subject to paras 12 and 13 above to resolve the issue by making
suitable adjustments in tariff which till date is not implemented
because of non acceptance by Appellant and other stakeholders.
JUDGMENT
16. I say that without prejudice to its rights in the present
appeals the Respondent No.2 is willing to implement the decisions
of State Govt. for paying compensatory tariff prospectively (from
next month of CERC order i.e. March 2014) to resolve the issue by
making suitable adjustment in tariff on the directions of the
Hon’ble Court. xxxxxx”
4
Page 4
| hushan, | learned |
|---|
respondent No.4 opposed the prayers of the applicant alleging
nd
that the 2 respondent is colluding with the appellant as there
is no occasion for the respondent to make any concession
nd
such as the one made in the affidavit filed by the 2
respondent (the relevant portion of which are already extracted
nd
above). More particularly, when the 2 respondent succeeded
nd
before two fora below, the concession of the 2 respondent to
pay compensatory tariff to the appellant though said to be
subject to the contentions of the respondent in the appeal is
JUDGMENT
nothing but largesse of the State to the appellant and not
consistent with public interest. He further submitted that this
Court may not affix a stamp of approval for such a decision of
nd
the 2 respondent by passing any order accepting the
concession made by the respondent. He also submitted that
the payment of compensatory tariff to the appellant would
5
Page 5
ultimately result in compelling the consumers to pay higher
price.
| nd, Shri<br>ant deni | Harish<br>ed the a |
|---|
nd
between the appellant and the 2 respondent. He argued that
nd
the decision of the 2 respondent is supported by a decision of
the State of Gujarat on an assessment of the subsequent
developments. He submitted that compelling the appellant to
supply energy in terms of the PPA is bound to financially
destroy the appellant company and therefore prayed that the
nd
2 respondent be permitted to make the payment in terms of
his concession.
JUDGMENT
10. A PPA is a contract between the parties and the terms of
any contract are nothing but the agreed terms of the
contracting parties. It is also a settled principle of the law of
contracts that parties to a contract can alter the terms of the
contract subsequent to the formation of the contract by
mutual consent.
6
Page 6
| hts of th<br>e realm | e State<br>of contr |
|---|
by the considerations of public interest. Apart from such
general principle, the rights and obligations of the parties to
the PPA in question are also subject to certain statutory
prescriptions.
12. The questions (i) whether the appellant is entitled to
terminate the PPA and (ii) if so, on what terms and conditions
are to be examined in the appeal.
13. Independent of such right, if any, of the appellant, if the
JUDGMENT
parties to the PPA are agreeable to alter the terms of the PPA
(as indicated in the counter) for whatever reasons, whether
such a variation is consistent with the requirements of the
statutes applicable to the contract is a separate question.
Whether such a variation is consistent with the larger public
7
Page 7
interest is altogether a different question. An ancillary
question arises whether such an issue can be properly the
subject matter of the instant appeal. All these matters require
| as and | when the |
|---|
hearing.
nd
14. Coming to the question whether the 2 respondent be
directed to pay the appellant compensatory tariff as indicated
in its counter, we are of the opinion no direction can be given
at this stage during the pendency of the appeal as the right of
the appellant for such compensatory tariff appears to be one of
the issues in the appeal.
nd
15. In so far as the question of permitting the 2 respondent
JUDGMENT
to pay the compensatory tariff as indicated in its counter, we
are of the opinion that it requires no permission from this
nd
Court. It is upto the 2 respondent to take a decision in
accordance with law to the best of its understanding. We may
nd
make it clear that if the 2 respondent chooses to make such
payment, the same shall be subject to the result of the appeal.
8
Page 8
16. The I.A. is disposed of as indicated above.
….………………………….J.
(J. Chelameswar)
…….……………………….J.
(Abhay Manohar Sapre)
New Delhi;
December 3, 2015
JUDGMENT
9
Page 9