Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 16
CASE NO.:
Appeal (civil) 5789 of 2002
PETITIONER:
L.M.L. Ltd.
RESPONDENT:
State of U.P. & Ors.
DATE OF JUDGMENT: 13/12/2007
BENCH:
S.B. SINHA & HARJIT SINGH BEDI
JUDGMENT:
J U D G M E N T
WITH
CIVIL APPEAL NO. 1106 OF 2007
Executive Engineer, Uttaranchal Power Corporation \005Appellant
Versus
M/s Kashi Vishwanath Steel Ltd. & Ors. \005Respondents
WITH
CIVIL APPEAL NO. 1622 OF 2007
Diamond Cements \005Appellant
Versus
U.P. Power Corporation Ltd. & Ors. \005Respondents
WITH
CIVIL APPEAL NO. 1623 OF 2007
M/s Saini Alloys Pvt. Ltd. \005Appellant
Versus
U.P. Power Corporation & Ors. \005Respondents
WITH
CIVIL APPEAL NO. 1624 OF 2007
Modipon Fibre Company \005Appellant
Versus
U.P. Power Corporation & Ors. \005Respondents
WITH
CIVIL APPEAL NO. 1625 OF 2007
M/s. Samtel Colour Ltd. \005Appellant
Versus
U.P. Power Corporation & Anr. \005Respondents
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 16
WITH
CIVIL APPEAL NO. 1626 OF 2007
Rama Paper Mills Ltd. \005Appellant
Versus
U.P. Power Corporation & another \005Respondents
WITH
CIVIL APPEAL NO. 1627 OF 2007
M/s Ram Ganga Cement (Pvt.) Ltd. & another \005Appellants
Versus
U.P. Power Corporation Ltd. & Ors. \005Respondents
WITH
CIVIL APPEAL NO. 1628 OF 2007
M/s Kajaria Ceramics Ltd. \005Appellant
Versus
U.P. Power Corporation and another \005Respondents
WITH
CIVIL APPEAL NO. 1716 OF 2007
M/s Sandila Metal Wires (P) Ltd. \005Appellant
Versus
U.P. Power Corporation Ltd. & Ors. \005Respondents
AND
SPECIAL LEAVE PETITION (C) No. 6721 of 2007
M/s. Jagannath Steels Pvt. Ltd. ... Petitioner
Versus
U.P. Power Corporation Ltd. & Ors. \005 Respondents
S.B. SINHA, J :
1. Effect of two Circular letters issued by the U.P. Power
Corporation Limited is involved in these appeals, which arise out of a
judgment and order dated 25th April, 2001 of the High Court of
Judicature at Allahabad in CMWP No.40692 of 2000 ; judgment and
order dated 17th January, 2007 passed by the High Court of
Uttaranchal at Nainital in WP No. 936 of 2001 and judgment & order
dated 19th October, 2006 of the High Court of Judicature at Allahabad,
Lucknow Bench, Lucknow, in Appeal No.82 of 2002 etc. etc.
2. State of Uttar Pradesh constituted Uttar Pradesh Electricity
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 16
Board in terms of the provisions of the Electricity (Supply) Act, 1948.
In the year 1999 Uttar Pradesh Electricity Reforms Act, 1999 (for
short, \021the 1999 Act\022) was enacted, in terms whereof the U.P.
Electricity Regulatory Commission (for short, \021the Commission\022) was
constituted. Indisputably, three licensees, namely, (i) U.P. Power
Corporation Ltd. (for short, \021UPPCL), (ii) Kanpur Electricity Supply
Company (for short, \021KESCO\022); and (iii) NOIDA Power Company
Ltd. (for short \021NPCL\022) filed applications before the Commission for
determination of \021tariff\022.
3. By reason of a notification dated 07.08.2000, tariff was framed
which was to come into force from 09.08.2000, inter alia, providing
for :
\023RATE SCHEDULE HV-2
LARGE AND HEAVY POWER
1. Applicability :
This rate schedule shall apply to all consumers who have
contracted load of more than 75 KW (100 BHP) for
industrial and/or processing purposes as well as to
Acr/Induction, Furnaces Rolling/Re-Rolling Mills, Mini
Steel Plants and to any other power consumers not
covered under any other rate schedule.
This rate schedule shall also apply to commercial light,
fan & power consumers (LMV-2) and power consumers
of Rate Schedule LMV-6, subject to the condition that
they opt for this Rate Schedule.
The contracted demand shall be expressed in whole
number only.
2. .... ... ...
3. ... ... ...
4. Rate of charge
Description
Demand Charge
Energy
Charge
A. Basic Rate
(Applicable
to Urban
Consumers)
Rs. 130/- per
KVA/
Month
P
L
U
S
390
paise/KWH
Notes :
(a) In respect of consumers who opt for power
supply during restricted/peak hours an additional
surcharge of 15% on the amount billed at the \023Rate of
Charge\024 under item 4-A above, i.e. Demand Charge and
Energy Charge shall be levied.
However, in respect of consumers getting power supply
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 16
on independent feeders emanating from 400/220/132 KV
sub-stations an additional surcharge of 15% on demand
and energy charges shall be charged further subject to the
condition that these consumers will get an assured supply
of minimum 500 hours in a month. In case of short fall
in above guaranteed hours of supply a rebate @ 1% for
each 10 hours short fall will be admissible on the bill
amount computed under \023Rate of Charge\024.
(b) ... ... ...
(c) ... ... ...
(d) In respect of supply during peak hours/restricted
hours, the consumers shall have to take the permission
from UPPCL.\024
4. Appellant LML Ltd. prior to framing of the said tariff and
bifurcation of U.P. State Electricity Board had been taking supply of
electrical energy in the form of a three phase alternatives current at
declared pressure of 132 K.V. and a power not exceeding 8000 K.V.
in their respective factories. Whereas in the case of L.M.L. Limited,
their factory being situated at Kanpur, electrical energy was supplied
by KESCO, but so far as other consumers are concerned, electrical
energy was supplied to them by UPPCL
5. Appellants-consumers herein claimed that although they had
been running a non-continuous process industry but was not to
observe peak hours restriction and in terms thereof they did not
consume power from 6.00 p.m. to 11.00 p.m. (being the peak hours).
6. A confusion arose in regard to interpretation of the said
purported levy of 15% surcharge on demand and energy charge on
independent feeders from 400/220/132 KV sub-stations having
assured supply of minimum 500 hours in a month. In the event, the
consumers were to get power supply from independent feeders, were
to get supply of minimum 500 hours in a month, indisputably, they
were to pay 15% surcharge on demand.
7. UPPCL, however, on construction of the said provisions of the
statute issued a circular letter dated 08.09.2000 calling for options
from the consumers of electrical energy, who did not intend to have a
continuous power supply of 500 hours in a month. A copy of the said
circular letter admittedly was sent to the Secretary of the Commission,
the relevant paragraphs whereof read thus :
\023Some other important guidelines/directions are being
issued with the request that please make aware to all your
concerned subordinate officers and ensure its strict
compliance.
1. 15% surcharge will be payable for Electricity use
in prohibited period in new rate list of L.M.V. \026 6
and HV-2. Consumers who were notified by U.P.
Government under continuous category before
new tariff should be necessarily imposed 15%
surcharge in their bills. The facility of Electricity
supply in prohibited should be continued as before
to consumers falling under this category and
option letter should not be asked from them.
In addition, consumers of non-continuous category
will not be provided the facility to use Electricity
in prohibited period. But, if the consumer of this
category wants to use electricity in prohibited
period, he will intimate to concerned Executive
Engineer through registered letter.
Executive Engineer within three days of receiving
this letter will issue office circular which will
indicate the date from which this facility can be
provided . 15% surcharge will be payable by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 16
consumer from the said date mentioned in above
letter. This option once given will not be revoked.
2(a) Consumers connected to independent feeders will
be charged 15% surcharge against guarantee of
500 hours electricity supply from sub-stations of
400 KV, 220 KV and 132 KV in HV-2 rate list.
500 hours electricity supply will be ensured to the
consumers of this category. 1% rebate will be
given on Electricity Bill of 10 hours or its part, if
they receive electricity supply less than 500 hours.
If the consumers connected to these independent
feeders who do not want guaranteed supply of 500
hours electricity supply then 15% surcharge will
not be charged on their electricity bills. These type
of consumers will intimate to Executive Engineer
(Distribution) if they do not want 500 hours
guarantee of electricity supply. Executive
Engineer will issue office memo in this regard. If
any consumer of this category does not exercise
this option, then he will be guaranteed 500 hours
electricity supply and will be charged 15%
surcharge. It will be the responsibility of
SSO/Assistant Engineer to ensure that consumers
of this category should not use electricity in the
restricted period. In case consumers of this
category use electricity in the restricted period then
they will be charged (15+15) 30 % surcharge.
2(b) Normally the availability of electricity supply to
the consumers from these feeders will depend
upon data of electronic meters installed in their
establishments and no officer will be authorized
for issuing any certificate and nor such certificate
will be acceptable.
2(c) In case electric meter is not available at
consumers\022 establishment or is defective, then
during this period only no employee below the
level of Asstt. Engineer will issue any certificate
under his signatures under any circumstances
regarding period of electricity supply/hours etc.
and in case this is issued the same will no be
accepted, and the concerned officer/employee will
be deemed guilty of indiscipline and appropriate
action will be taken against them. As per
requirement, this type of certificate can be issued
by Asstt. Engineer or above level officer and they
may get the signature of subordinate
officer/employee if they wish. This certificate will
be made available to concerned Executive
Engineer (Distribution) for each month.
2(d) Every months intimation/certificates of electricity
supply hours alongwith the reason of less supply
hours will be provided by Sub-division Officer of
sub station of 400, 220 and 132 KV to Executive
Engineer (Distribution) for the purpose of issuing
bill to consumer.
The supply hours should tally with the hours
written in the log book of sub station. Along with
this, the sub-division officer will provide the
certificate confirming whether electricity was
supplied in peak hours or not? In case the power
supply to large and heavy power consumers is less
than prescribed hours for two consecutive months,
then, concerned Dy. General Manager of the sub-
station will review the situation at his level and
resolve the same.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 16
Review of power supply to small and medium
consumers shall be done by Executive Engineer of
concerned sub-station.\024
8. On or about the 14.09.2000, the Executive Engineer of UPPCL issued
notices to the parties, inter alia, stating :
\023 As per the Extra-ordinary Gazette dated 27.07.2000
of Government of U.P., the U.P.P.C. Ltd. has revised the
tariff of consumers of all the categories from 9.8.2000.
Accordingly, both the categories i.e. Continuous and non-
continuous have been amalgamated. The restriction is that
they will have to submit their separate option for use of
electricity consumption in peak hours and restricted use of
electricity that if they want to consume the electricity in
peak hours and restricted period, they will be required to
pay 15% extra surcharge on the amount worked out as per
category 4 of the tariff rate. Without permission of
U.P.P.C. Ltd., the consumption of electricity in this period
is prohibited otherwise action as per rules will be taken.
You are, therefore, hereby requested that you
intimate in writing to this office within 15 days of receipt
of this letter that whether you want to consume the
electricity during the peak hours and restricted use of
electricity period or not so that you tariff rate could be
fixed accordingly in H.V. 2 category. The consumption
of electricity during the said period will be prohibited
without permission of U.P.P.C. Ltd. In case of violation,
you will be liable to financial and other losses. Option
given by you shall be effective from 9.8.2000.\024
9. Pursuant thereto and in furtherance thereof, by reason of a letter
dated 16.09.2000, the consumer opted for not having a continuous
power supply of 500 hours, a sample copy whereof is as under :
\023As you already know that we are electricity
consumer in the category of Non-continuous process of
132 KVA. We have to inform you that we shall not be
consuming the same during the peak hour restrictions.
Further we are not opting for such guaranteed supply of
electricity for 500 hours per month and in default thereof
a rebate of 1% for every 10 hours of electricity non-
supply. This does not, however, mean that you shall
subject us to any unscheduled and arbitrary cuts in the
supply in future
We are sure that you shall continue to supply
electricity as in the past from the same feeder line. This
letter is in compliance of the requirement of the above
notification dated 8.9.2000, and hence the additional
surcharge of Rs.6,33,898.45 shall be withdrawn from our
bill dated 5.9.2000. The payment of Rs.53,01,727/-
having been made by cheque No.207076 dated 11.9.2000
(handed over in the Court of Chief Justice, Allahabad on
13.9.2000). Thus the aforesaid bill stands finally paid.
We are sure that in future our bills shall not be
loaded with additional surcharge of 15%.\024
10. It appears that meetings were also held by and between the
consumers and Secretary and Chairman of UPPCL at PHD Chambers
of Commerce at Delhi, wherein it was decided that only thermal
industries would not be charged 15% additional surcharge who did not
want to go for assured supply of 500 hours.
11. It further appears that UPPCL issued another circular letter
dated 15.12.2000, the relevant portion whereof reads thus :
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 16
\023U.P Electricity Regulatory Commission in its
revised tariff for the year 2000-01 applicable to HV-2
rate schedule consumers who are getting supply from
independent feeders for levy of 15% surcharge on the
guarantee of 500 hours of power supply per month.
In this regard, detailed guidelines have been issued
by this office vide letter No. 1423 dated 9.8.2000.
In this regard, it is directed that those consumers
who will exercise option, of not availing 500 hours
guaranteed supply, through a registered letter to
Executive Engineer (Distribution) by 31.12.2000, they
will not be charged 15% surcharge from the very date of
its applicability i.e. 7.8.2000. For consumers, who will
submit their option after 31.12.2000, this facility will be
applicable from the date of receipt of the application.\024
12. Although no such circular letter was issued by KESCO, relying
on or on the basis of circular letter issued by UPPCL, L.M.L. Limited
filed a writ petition in the Allahabad High Court.
13. Upon taking into consideration the jurisdiction of the UPPCL to
implement the tariff fixed by the Commission vis-‘-vis the procedure
required to be adopted therefor, the High Court by reason of the
impugned judgment and order dated 25.04.2001 opined that it had
absolutely no jurisdiction to make any modification in the tariff and in
that view of the matter the purported circular letter issued on
08.09.2000 was invalid in law, inter alia, stating :
\023The contention raised on the basis of circular dated
8.9.2000 issued from the office of Chief General
Manager (Commercial), UPPCL, is equally untenable.
The provision in later part of paragraph 2 Ka thereof
which lays down that 15 per cent surcharge would not be
levied in case a consumer getting supply from an
independent feeder emanating from 400/220/132 KV
sub-station gave an option that he did not want a
guarantee of 500 hours of supply in a month, is contrary
to the tariff approved by the Commission. The
Commission in its order approving the tariff had merely
provided that in case of shortfall in 500 hours of assured
supply in a month, a rebate of 1 per cent for each 10
hours shortfall will be admissible on the total amount
computed under \023Rate of Charge\024. The Circular while
retaining this provision has made an additional provision
to the effect that if such type of consumer gave an option
that he did not want an assured supply of minimum 500
hours in a month, the 15 per cent surcharge shall be not
levied. This is a clear alteration of the approved tariff
which is not permissible in law.
14. Relying on or on the basis of the said judgment of the Division
Bench of the Allahabad High Court delivered in the case of L.M.L.
Limited, UPPCL issued another circular dated 31.08.2001 cancelling
the earlier circulars, stating :
\023Since some confusion has arisen amongst the
Field/Regional Officers on this provision, Commercial
Division vide its letter Nos. 1423-HC/UPPCL/Five-1974-
1204 dated 8.09.2000 and No. 3046/HC
/Tariff/SAMA/Nirdesh dated 15.12.2000 had issued
clarifications after discussions with U.P. Electricity
Regulatory Commission.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 16
LML Kanpur had filed a Writ Petition
No.40692/2000 before the Hon\022ble Allahabad High
Court on this subject. Hon\022ble Allahabad High Court in
its order has directed that tariff as approved by Electricity
Regulatory Commission only will be applicable and the
licensee cannot amend the tariff. Therefore, in the light
of Hon\022ble Allahabad High Court\022s judgment Circular
No. 1423 dated 8.9.2001 (Point No. 2) and letter No.
3046 dated 15.12.2000 stand rescinded from the date of
their issue.\024
Bills were issued in October 2001 with retrospective effect from
November 2000.
15. Appellants other than L.M.L. Limited filed several writ
petitions questioning the legality and/or validity of the said circular
dated 31.08.2001.
Several contentions were raised in the writ petitions including
the jurisdiction of UPPCL to issue bills with retrospective effect.
It was furthermore contended that the appellants having altered
their position pursuant to or in furtherance of the promise made by
UPPCL in terms of its circular letter dated 08.09.2000, they were
estopped and precluded from raising any bill, with retrospective effect
or otherwise.
Attention of the High Court in the subsequent writ petitions
were also drawn to the fact that UPPCL had carried out extensive
consultation with the Commission on several dates.
16. It was pointed out that UPPCL itself in its counter affidavit
filed in the case of Modi Pon Fibre Company, Ghaziabad before the
High Court had stated as under :
\0234. That there was some confusion in the category of
consumers who were covered by both category (i)
and (ii) above, and who on plain reading of the
tariff were liable to pay surcharge of 15% plus
15%. To clarify the above UP Power Corporation
Limited, hereinafter referred to in brief as UPPCL,
held discussions both with the Commission and the
Government of Uttar Pradesh through Principal
Secretary, Power. The above discussions
culminated in the passing of Circular No.1423-
HC/UPPCL/5-1974-1204-C/2000 dated 8.9.2000
by UPPCL. The above circular as per its Para
2(Ka) gives an option to the consumers under
category (ii) that in case they do not want to
receive supply of assured 500 hours in a month no
surcharge of 15% shall be charged from them. It
was provided in the above circular that the
concerned consumer may give their option of
waiver of assured supply by registered post to the
concerned Executive Engineer (Distribution). It
was further provided in the above circular that in
case the consumer fails to exercise the above
option, he will be assured supply of 500 hours and
he shall be liable to pay surcharge of 15%. A copy
of the above circular is endorsed to the Secretary
of the Commission for information and necessary
action. A copy of the above circular dated
8.9.2000 is appended to this Short Counter
Affidavit as its Annexure CA-1.
5. By another Circular No.3046-HC/Tariff/general
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 16
instruments, dated 15.12.2000, it was provided that
the consumers of category (ii) above may exercise
their option of not availing 500 hours guaranteed
supply through a registered letter to Executive
Engineer (Distribution) by 31.12.2000. A copy of
the above circular was endorsed to the Secretary of
the Commission for information and necessary
action. A copy of the above circular dated
8.9.2000 is appended to this Short Counter
Affidavit as its Annexure CA-2.
It was further stated therein :
7. Since the circular dated 8.9.2000 now stands
rescinded pursuant to the orders of the Hon\022ble
Allahabad High Court and since UPPCL has failed
to elicit any response from the Commission to its
letters (Annexure Nos. CA-3, 3A and 3B), UPPCL
has initiated action for charging 15% surcharge
from consumers of category (ii) above which as
per the tariff order dated 27.7.2000 passed by the
Commission. A circular No. 925 HC/LML/LS-15
dated 31.8.2001 has been issued by the respondent
to the above effect. A copy of the above circular
dated 31.8.2001 is appended to this Short Counter
Affidavit as its Annexure No. cA-4\024
17. Before the High Court, several other documents were brought
on record, including a letter dated 11.06.2001 which had been filed
before the Commission, which was in the following terms :
\023 In accordance with the rates specified by
U.P.E.R.C. in its Tariff Orders dated 27.7.2000, it was
provided in the Notification for rate Schedule for HV-2
category issued by U.P.P.C.L. that 15% surcharge will be
levied on consumers who opt for power supply during
restricted/peak hours. It was also provided that
additional surcharge of 15% on demand and energy
charges will be payable by the consumers getting supply
on independent feeders subject to the condition that they
will get assured supply of 500 hours in a month.
Subsequently, as per discussions in the Hon\022ble
Commission it was clarified by UPPCL vide letter No.
1423-HC/UPPCL/V-1974-1204-C/2000 dated 8.9.2000
that the levy of 15% surcharge on consumers on
independent feeder will be optional subject to their
giving the option.
A writ was filed by M/s LML, Kanpur who is a
consumer of KESCO claiming that 15% additional
surcharge for independent feeder should not be levied on
them as provided in circular no. 1423-HC/UPPCL dated
8.9.2000 referred to above. The Hon. High Court,
Allahabad have held that the provision of para-2(Ka) of
above referred circular dated 8.9.2000 giving option to
the consumers on independent feeders is a clear alteration
of the approved tariff. They have further held that the
circular of UPPCL insofar as it is inconsistent with the
tariff approved by the Commission is void and wholly
inoperative in law. The petitioner, therefore, cannot get
any advantage by exercising an option in terms of
circular by way of informing through the registered post
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 16
that he did not want an assured supply of 500 hours in a
month.
It may kindly be recalled that the clarification
issued vide above referred letter no. 1423 dated 8.9.2000
was subsequent to the detailed discussions held in the
Commission as well the then Pramukh Sachiv Oorja.
It is, therefore, requested that the above facts may
kindly be brought to the notice of the Hon\022ble
Commission and further directions may kindly be issued
so that the same may be implemented as ordered by the
Hon. High Court, Allahabad.\024
18. The Chief General Manager, UPPCL by reason of a letter dated
23.06.2001 drawing the attention of the Commission to the said letter
dated 11.06.2001 had requested it to issue necessary guidelines in the
light of the order dated 25.04.2001 passed by the Allahabad High
Court in W.P. No.40692 of 2000.
19. Yet again, on or about 24.08.2001, the Executive Director,
UPPCL, referring to its earlier letter dated 11.06.2001 as also a
reminder letter dated 23.06.2001 requested the Secretary of the
Commission to issue necessary guidelines in regard to the levy of
15% surcharge , inter alia, stating :
\023...It may also be brought to the kind notice of the
Commission that at present field unit of UPPCL are not
charging 15% surcharge from such consumers on
independent feeders who have given option for not
availing 500 Hrs. of guaranteed supply during a month.\024
20. Other Division Benches of the Allahabad High Court, however,
chose to follow its earlier decision in L.M.L. Limited (supra).
21. We may notice that some of the appellants herein had filed
reference applications before the Commission, which were found to
be not maintainable. A Review Application was also filed whereafter,
the First Appeals were filed before the High Court. It may, however,
be placed on record that in regard to the meaning of \021independent
feeders\022 some matters are still pending before the Commission.
22. We may also note that on similar questions, the Uttaranchal
High Court has allowed the writ applications filed before it.
23. The learned counsel appearing on behalf of the appellants, inter
alia, would submit that the High Court committed a manifest error in
passing the impugned judgment insofar as it failed to take into
consideration that in terms of sub-section (6) of Section 24 of the
1999 Act, it was for the licensee to modify the tariff and in view of the
fact that before doing so, they had held extensive consultation with the
Commission; the impugned judgments are wholly unsustainable.
It was also submitted that in any event, the doctrine of
promissory extoppel could squarely be applicable in the instant case
as the appellants herein had altered their position relying on or on the
basis of the representation so made.
24. Mr. Rakesh Dwivedi, learned Senior Counsel appearing on
behalf of the respondents, on the other hand, submitted :
(i) No promise having been made by KESCO, the principle
of promissory estoppel will have no application.
(ii) In any event there cannot be any estoppel against the
statute.
(iii) So far as UPPCL is concerned, having regard to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 16
provisions of the 1999 Act in terms whereof the
Commission alone possessed the power to modify the
tariff, the impugned judgments are unassailable.
25. The 1999 Act was enacted to provide for the restructuring of
the electricity industry, the rationalization of generation, transmission,
distribution and supply of electricity, regulation by an independent
electricity regulatory Commission of the electricity industry including
the purchase, distribution, supply and utilization of electricity, the
quality of service, tariff and other charges keeping in view the interest
of the consumers and utilities, creation of an environment which will
attract participation of private sector entrepreneurs in the electricity
industry in the State and generally for taking measures conducive to
the development and management of the electricity industry in the
State in an efficient, economical and competitive manner and for
matters connected therewith or incidental thereto.
26. \021Commission\022 is defined in Section 2(f) of the 1999 Act to
mean the Uttar Pradesh State Electricity Regulatory Commission
referred to in Section 3 thereof. Section 10 of the 1999 Act provides
for the functions of the Commission including the one to determine
the tariff for electricity - wholesale, bulk, grid or retail, as the case
may be.
27. Section 13 provides for formation and functions of the Uttar
Pradesh Power Corporation.
28. Section 24 occurring in Chapter VII of the 1999 Act provides
for licensee\022s revenue and tariffs. Sub-section (1) of Section 24 states
that the licensee shall follow the procedure prescribed in the
regulations in calculating the expected revenue from charges which he
is permitted to recover and in determining tariffs. Sub-section (2) of
Section 24 provides for the factors which are relevant for the purpose
of determining the tariffs in the following terms :
\02324. Licensee\022s revenues and tariffs. \026
(1) \005 \005 \005.
(2) Save as provided in sub-section (3), the
Commission may specify in regulations the terms and
conditions for the determination of the revenue and
tariffs and, in doing so, the Commission shall be guided
by the following, namely :-
(a) the financial principles and their application
provided in Sections 46, 57 and 57-A of the Electricity
(Supply) Act, 1948 and in the Sixth Schedule thereto;
(b) the factors which would encourage
efficiency; economical use of the resources, good
performance, optimum investments, observance of the
conditions of the licence and other matters which the
Commission may consider appropriate for the purposes
of this Act; and
(c) the interest of the consumers.\024
29. Sub-section (3) of Section 24 of the Act provides that in the
event the Commission departs from the factors specified in clauses (a)
to (c) of sub-section (2), reasons therefor shall be assigned. Sub-
section (6) of Section 24 read as under :
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 16
\023(6) The Commission may, after notifying its
decision on the licensee \021s calculations as provided in
sub-section (5), determine whether the tariff charged by
the licensee is required to be modified, and if so,
require the licensee to modify the tariff or any part
thereof with immediate effect.
30. Section 27 provides for enforcement of the orders and
directions of the Commission. Section 28 provides for penal
provisions. Section 36 provides for appeals from the orders of the
Commission to the High Court.
31. The Commission in this case proceeded to determine the tariff
keeping in view the fact that the electricity rates for industries in the
State of Uttar Pradesh were quite high and any sharp increase in the
rates would be counter productive. It, however, though to impose
15% surcharge in relation to two types of supply, inter alia, keeping
in view : (i) supply during peak hours; and (ii) supply of independent
feeders in terms whereof continuous supply of minimum 500 hours in
a month shall be assured.
32. Surcharge, therefore, was levied when the supply was to be
made by the licensee on fulfillment of conditions laid down therein.
33. We may notice that the Commission itself directed
discontinuance of the said surcharge with effect from 01.09.2001 by
issuing a tariff order in the following terms :
\023The U.P.E.R.C. in terms has recorded that
discontinuation of 15% surcharge is due to (i)
inability/incapability on the part of UPPCL for technical
and operational reasons to ensure the guaranteed supply
of 500 hours, (ii) it was difficult for UPPCL even to
distinguish between the two consumers on independent
feeder who asked for assured supply and who do not, (iii)
most of the consumers having opted against this
agreement and (iv) the financial implication was also
negligible if the scheme was discontinued.\024
34. Appellants-Consumers at all material times had been
complaining in regard to irregular supply of electrical energy by the
licensee.
35. A supplier of electrical energy is presumed to know as to
whether it would be in a position to abide by the terms of supply
imposed by the Commission. It was required to gauze its capacity to
make uninterrupted supply of electrical energy to a class of
consumers. Manufacturers of electrical energy belong to different
classes. Manufacturers of certain categories of goods having regard to
the nature of their products would require continuous supply of
electrical energy; be it peak hours or otherwise. The licensees in such
cases are required to make special arrangements for continuous supply
of electrical energy to such class of consumers.
36. We have noticed hereinbefore that the consumers of electrical
energy, who are before us, did not intend to have supply of electrical
energy during peak hours. Their need in relation thereto, therefore,
was not such which would have required continuous supply of
electrical energy. If keeping in view such a contingency, the suppliers
intended to have an assessment of their own capacity to supply
uninterrupted electrical energy by asking for option of the consumers
concerned, we do not see as to how thereby they can be said to have
deviated from the tariff determined by the Commission. If one of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 16
objects of the Commission was to ensure uninterrupted supply of
electrical energy, it was for the supplier itself to assess its own
capacity therefor. Surcharge may or may not be a part of tariff. Even
if it is a part of tariff in respect thereof, the levy was conditional. If
the supplier was not itself in a position to fulfill the condition, the
question of insisting on implementation of the said provision would
not arise.
37. While we say so, we are not unmindful of the fact that
imposition of 15% surcharge was not dependent upon the exercise of
option in terms of the tariff provision, which was confined to the
supply of electrical energy during peak hours.
38. Those suppliers, who keeping in view of their capacity to
supply uninterrupted electrical energy had made a representation and
pursuant thereto the consumers had altered their position, cannot be
permitted to take a different stand as the doctrine of promissory
estoppel would apply against them. The said doctrine is premised on
the conduct of party making a representation to the other so as to
enable him to arrange its affairs in such a manner as if the said
representation would be acted upon. It provides for a cause of action.
It need not necessarily be a defence.
39. Application of said doctrine has been analysed by this Court in
several judgments. We would only refer to some of them. In
Southern Petrochemical Industries Co. Ltd. vs. Electricity Inspector
& Etio and others : (2007) 5 SCC 447 this Court upon noticing a
large number of precedents including State of Punjab vs. Nestle
India Ltd. and another : (2004) 6 SCC 465 opined as under :-
\023 The doctrine of promissory estoppel would
undoubtedly be applicable where an entrepreneur alters
his position pursuant to or in furtherance of the promise
made by a State to grant inter alia exemption from
payment of taxes or charges on the basis of the current
tariff. Such a policy decision on the part of the State
shall not only be expressed by reason of notifications
issued under the statutory provisions but also under the
executive instructions. Appellants had undoubtedly
been enjoying the benefit of payment of tax in respect
of sale/ consumption of electrical energy in relation to
the cogenerating power plants.\024
40. In Express Newspapers Pvt. Ltd. and others vs. Union of India
and others : (1986) 1 SCC 133 this Court held :-
\023179. It would appear that Denning, J. evoked two
doctrines : (1) that assurances intended to be acted upon
and in fact acted upon were binding; and (2) that where a
Government department wrongfully assumes authority to
perform some legal act, the citizen is entitled to assume
that it has that authority, and he dismissed the contention
that estoppels do not bind the Crown by saying that ’that
doctrine has long been exploded’ and that the Crown
cannot fetter its future executive action. Professor Wade
points out that the proposition about wrongful
assumption of authority evoked by Denning, J. was
immediately repudiated by the House of Lords in a later
case in which Denning, LJ. had again put it forward in
Howell v. Falmouth Boat Construction Company Ltd.,
L.R. [1951] A.C. 837, it is beyond the scope of this
judgment to enter into a discussion as to how far Denning
J’s dictum can still be regarded as part of the common
law in England. But there appears to be a school of
thought in India laying down that the doctrine of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 16
promissory estoppel applies to the Government except
under certain circumstances.
41. We may also notice that the Commission did not take any
decision despite repeated communications by the Power Corporation.
If in a situation of this nature where the licensee wanted some
alteration in the tariff, it was expected of it to take a decision
forthwith. It should not have whiled away the time and allowed the
Power Corporation to proceed with its proposal. Such a conduct on
the part of the Commission may invite the doctrine of acceptance sub
silentio. The statute provides for a consultation and not a
concurrence. It does not provide for the consequence of any alteration
of tariff applicable to a particular category of consumer. It merely, as
indicated hereinbefore, brings about the situation where a licensee
found itself unable to supply electrical energy uninterruptedly to the
consumer.
42. There can, however, be no doubt that ordinarily the doctrine of
promissory estoppel would not be applied against statute. Sub-section
6 of Section 24 of 1999 Act inter alia empower the holder of a licence,
to modify the tariff. If the implementation of tariff was dependent
upon fulfillment of certain conditions precedent which in turn would
be dependent upon the capacity of the producer of electrical energy to
fulfil the same, in our opinion, no impropriety was caused by the
Power Corporation to ask for the said option. The fact, that such an
option had indeed been called for and pursuant thereto the consumers
had altered their position is not in dispute. While dealing with a
question as to whether an action on the part of the State to make a
representation is contrary to a statute or not, in our opinion, a
distinction should be borne in mind between an act which goes
clearly contrary to the mandatory provisions thereof and a case where
irregularities have been committed.
43. We may notice that in The Paper Products Ltd.
vs. Commissioner of Central Excise : 1999 (7) SCC 84 this Court
held :-
\023 As stated above, it is an admitted fact that by virtue of
Circular No. 4/85 dated 23-7-1986 as clarified by
Circular dated 7-8-1987, all the three products of the
appellant are to be treated as the products of the printing
industry and not that of the packaging industry. A change
in the said view of the Board occurred for the first time
by virtue of the Circular No. 6/89 dated 16-1-1989.
Further, the Board itself by its subsequent Circular No.
29/89 dated 5-5-1989 has made it abundantly clear that
the change notified in Circular No. 6/89 will be
prospective from the date of issuance of Circular No.
6/89, that is, from 16-1-1989. Therefore, it is clear that
till the issuance of Circular No. 6/89 which is dated 16-1-
1989 the products of the appellant, by virtue of the two
Circulars dated 23-7-1986 and 7-8-1987, have to be
classified under Chapter 49 of the Act as being products
of the printing industry eligible for exemption of duty
under Notification Nos. 122/75 and 234/82 as applicable
at the relevant time. The impugned show cause notices
and consequent demand being ab initio bad inasmuch as
the same was contrary to the existing Circulars of the
Board, the same cannot be sustained.\024
44. In Collector of Central Excise Vadodra vs. Dhiren Chemical
Industries : (2002) 2 SCC 127 this Court held :-
\023 We need to make it clear that, regardless of the
interpretation that we have placed on the said phrase, if
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 16
there are circulars which have been issued by the Central
Board of Excise and Customs which place a different
interpretation upon the said phrase, that interpretation
will be binding upon the Revenue.\024
45. The latter decision is also an authority for the proposition that a
circular would be binding on the State in appropriate cases. We are
not oblivious of the decisions of this Court where the Commission has
been held to be the sole tariff making authority. [ See Association of
Industrial Electricity Users Vs. Respondent: State of Andhra
Pradesh and others : (2002) 3 SCC 711] and West Bengal Electricity
Regulatory Commission vs. C.E.S.C. Ltd. etc. etc : (2002) 8 SCC
715. In CESC (supra) this Court observed :-
\02358. Having carefully considered the provisions of the
Act as also the arguments advanced in this regard, we are
of the opinion that under the 1998 Act, it is the
Commission concerned and in the instant case the State
Commission of West Bengal, which is the sole authority
to determine the tariff, of course as per the procedure in
the said Act.\024
46. We may also notice that in BSES Ltd. Vs. Tata Power Co.,
Ltd. and others : (2004) 1 SCC 195 this Court held :-
\02316. The word "tariff" has not been defined in the Act.
"Tariff’ is a cartel of commerce and normal it is a book of
rates. It will mean a schedule of standard prices or
charges provided to the category or categories of
customers specified in the tariff. Sub-section (1) of
Section 22 clearly lays down that the State Commission
shall determine the tariff for electricity (wholesale, bulk,
grid or retail) and also for use of transmission facilities. It
has also the power to regulate power purchase of the
distribution utilities including the price at which the
power shall be procured from the generating companies
for transmission, sale, distribution and supply in the
State. ’Utility’ has been defined in Section 2(1) of the Act
and it means any person or entity engaged in the
generation, transmission, sale, distribution or supply, as
the case may be, of energy. Section 29 lays down that the
tariff for intra-State transmission of electricity and tariff
for supply of electricity, wholesale, bulk or retail in a
State shall be subject to the provisions of the Act and the
tariff shall be determined by the State Commission. Sub-
section (2) of Section 29 shows that terms and conditions
for fixation of tariff shall be determined by Regulations
and while doing so, the Commission shall be guided by
the factors enumerated in Clauses (a) to (g) thereof. The
Regulations referred to earlier show that generating
companies and utilities have to first approach the
Commission for approval of their tariff whether for
generation, transmission, distribution or supply and also
for terms and conditions of supply. They can charge from
their customers only such tariff which has been approved
by the Commission. Charging of a tariff which has not
been approved by the Commission is an offence which is
punishable under Section 45 of the Act. The provisions of
the Act and Regulations show that the Commission has
the exclusive power to determine the tariff. The tariff
approved by the Commission is final and binding and it
is not permissible for the licensee, utility or any one else
to charge a different tariff.\024
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 16
47. The abovesaid three decisions are distinguishable on facts.
They were not dealing with a situation of the present kind. It was not
a case where the supplier had difficulty of supplying uninterrupted
electrical energy.
48. The proximity of issuance of the circular vis-a-vis Notification
must also be noticed. The tariff was framed on 7th August, 2000
which came into force from 9th August, 2000 whereas the circular was
issued on 8th September, 2000. The consumers exercised their option
on 31st October, 2000. The judgment in the case of LML (supra) was
delivered on 25th April, 2001. The circular dated 31st August, 2001
undoubtedly was issued in view of the said judgment. The said
judgment did not deal with the questions raised before us. In any
event if the licensee violates the tariff approved by the Commission
appropriate legal action can be taken against it. But it would be too
much to contend that for a mistake on the part of the Corporation, the
consumers would suffer. In this view of the matter, we are of the
considered view that the doctrine of estoppel shall apply in the cases
where the promise was made. However, the principle of said doctrine
would, however, not be applicable where no such promise was made.
49. Respondent-Kanpur Electricity Supply Company would not be
bound thereby. Tariff is fixed for providing a service. Supply of
electrical energy is a public utility service. While carrying out a
function of this nature, the court of law must keep in mind the
equitable principles also. Equity does not postulates that although the
supplier did not fulfil its obligation, still it would be entitled to the
benefits envisaged under the law.
50. Similarly Uttarnachal Power Corporation also does not appear
to have made such a promise. The doctrine of promissory estoppel in
those cases also will have no application.
51. In view of the fact that several matters are pending before the
Commission on question of independent feeder we need not express
any opinion thereupon. If any appeal is pending before the
Commission on the said question it would decide the same
independent of the same irrespective of the result of this decision..
We, therefore, without expressing any opinion on the said question,
permit the appellants to agitate the same point before the Commission.
52. We, therefore, allow these appeals only to the extent mentioned
hereinbefore in terms of the promise made by the U.P. Power
Corporation and allow the appeals on question of independent feeder
to be withdrawn subject to the observations made by us hereinabove.
53. Civil Appeal No.5789 of 2002 which relates to Kanpur
Electricity Supply Company is dismissed.
54 Civil Appeal No.1106 of 2007 filed on behalf of the
Uttaranchal Power Corporation is allowed.
55 There shall, however, be no order as to costs.
SLP (C) NO. 6721/2007
The only issue involved in this petition is the question of
independent feeder and the appeal being pending before the
Commission, this special leave petition is permitted to be withdrawn.