PARSA KENTA COLLIERIES LTD. vs. RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LTD.

Case Type: Civil Appeal

Date of Judgment: 27-05-2019

Preview image for PARSA KENTA COLLIERIES LTD. vs. RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LTD.

Full Judgment Text

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 9023 OF 2018 Parsa Kente Collieries Limited ..Appellant Versus Rajasthan Rajya Vidyut Utpadan Nigam Limited ..Respondent J U D G M E N T M.R. SHAH, J. Feeling   aggrieved   and   dissatisfied   with   the   impugned judgment and order dated 28.02.2018 passed by the Commercial Appellate Court/Division Bench of the High Court of Judicature for   Rajasthan,   Bench   at   Jaipur   in   D.B.   Civil   Miscellaneous Signature Not Verified Digitally signed by MANISH SETHI Date: 2019.05.27 16:34:10 IST Reason: Appeal No. 3785 of 2017, by which the High Court has allowed 1 the said appeal preferred by the respondent herein – Rajasthan Rajya Vidyut Utpadan Nigam Limited and has quashed and set aside the award passed by the learned Arbitrator, confirmed by the Commercial Appellate Court at Jaipur, the appellant – the original claimant – Parsa Kente Collieries Limited has preferred the present appeal. 2. That in the month of March, 2006, the respondent floated a tender for joint venture to undertake coal block development, mining and transportation of coal and delivery.  That one Adani Enterprises Limited (AEL) submitted a bid which was accepted on 12.05.2006.     A   Letter   of   Intent   was   issued   to   AEL   by   the respondent on 23.10.2006.  Respondent and AEL entered into a joint   venture,   namely,   Parsa   Kente   Collieries   Limited,   the appellant herein.  A Coal Mining Service Agreement was entered into between the said Parsa Kente Collieries Limited and AEL. That a Coal Mining and Delivery Agreement (hereinafter referred to   as   ‘CMDA’)   was   executed   between   the   appellant   and   the respondent on 16.07.2008 for supply of coal.   2.1 As per CMDA, the date of commencement of the contract was 25.06.2011.   As per CMDA between the appellant and the 2 respondent,  the  coal  supply  was  to commence  at the  earliest within   42   months,   or   within   48   months   from   the   date   of allotment of coal blocks, i.e., by 25.06.2011. CMDA also provided a clause for extending the date of commencement.  Clause 3.2.1 of the CMDA provided for scope of work; Clause 4.1.3 and 4.1.4 provided   for   responsibility   of   the   respondent   to   inform   the appellant as regards the requirement of coal in advance.  Clause 4.5 provided for commencement of the date; clause 5.1 provided for  contract of   price;  clause  5.2.2.   provided  for  calculation  of basic price; clause 5.4.3 provided for escalation in price; clause 7.1 provided for force majeure and clause 7.3 provided for effect of force majeure.  There was a delay of 21 months in obtaining the forest clearance and environmental clearance.  The appellant started   supply   of   coal   to   the   respondent   with   effect   from 25.3.2013, i.e., after a delay of 21 months.  It appears that the date of commencement was extended by mutual agreement from 25.6.2011   to   25.3.2013.     However,   certain   disputes   arose between the parties, more particularly the escalation price, fixed costs, amount lying in Escrow account and cost of construction of railway siding.  Therefore, the appellant invoked clause 10.2 of the CMDA and sought arbitration.  A retired Hon’ble Judge of the 3 Rajasthan High Court was appointed as the sole arbitrator.  The appellant submitted the statement of claim and thereafter filed another statement of claim.   2.2 Before the learned Arbitrator, the claim was bifurcated into four heads, namely, (1) Price Adjustment; (2) Fixed Costs; (3) Escrow Account; and (4) Construction of Railway Siding.   The learned Arbitrator passed an award dated 27.05.2015 allowing the claims under the heads of ‘Price Adjustment’, ‘Fixed Costs’ and   ‘Escrow   Account’   and   rejected   the   claim   under   the   head ‘Construction of Railway Siding’.  While allowing the claim under the head ‘Price Adjustment’, the learned Arbitrator held that the date   of   commencement   of   the   first   operating   year   for   the purposes of clauses 5.2.2 read with 5.4.3 would be 25.06.2011. The learned Arbitrator further held that thus the Zero year for the purpose of price escalation has to be 2011­2012.  The learned Arbitrator   accordingly   held   that   because   the   date   of commencement   of   the   agreement   for   the   purpose   of   price escalation is 25.06.2011, the appellant shall be entitled to the enhanced amount as applicable in 2013­2014.  Accordingly, the learned Arbitrator held that the appellant is entitled to the coal 4 price   at   Rs.837/­   PMT   in   F.Y.   2013­14   and   thereafter   the escalated   price   in   the   subsequent   years   as   per   the   relevant clauses of the contract – CMDA.   2.3 That while allowing the claim with respect to ‘Fixed Costs’, the learned Arbitrator held that the respondent could not take the required delivery of the coal from the appellant, thus causing loss to the appellant. The learned Arbitrator held that therefore the appellant is entitled to compensation as claimed for Rs.78 crores. 2.4 That   while   allowing   the   claim   with   respect   to   ‘Escrow Account’, the learned Arbitrator held that the undertaking given by the appellant was limited to a contingency where on account of failure of completion of mine closure activity by the appellant led   to   the   forfeiture   of   any   amount   deposited   in   the   escrow account, the respondent would be entitled to recover the same from the monthly running bills of the appellant.   The learned Arbitrator observed, however, as no such occasion has arisen, the question of any deduction on the said count does not arise. Consequently, the learned Arbitrator directed the respondent to 5 return that amount which was lying in the escrow account which was deducted from the monthly running bills of the appellant. 2.5 As   observed   hereinabove,   the   learned   Arbitrator   rejected claim   no.4,   namely,   under   the   head   ‘Construction   of   Railway Siding’.   The award declared by the learned Arbitrator came to be confirmed   by   the   learned   Commercial   Court,   Jaipur   in   an application under section 34 of the Arbitration and Conciliation Act. 3. Feeling aggrieved, the respondent preferred an appeal under Section 37 of the Arbitration Act before the Commercial Appellate Court/Division Bench of the High Court of Rajasthan at Jaipur. By the impugned judgment and order dated 28.02.2018, the High Court has allowed the said appeal and has set aside the award passed   by   the   learned   Arbitrator   and   confirmed   by   the Commercial Court, Jaipur. 4. Feeling   aggrieved   by   the   impugned   judgment   and   order passed by the Division Bench of the High Court, the original claimant – the appellant has preferred the present appeal. 5. Shri Ranjit Kumar, learned Senior Advocate has appeared on   behalf   of   the   appellant   and   Shri   Tushar   Mehta,   learned 6 Solicitor   General   of   India   has   appeared   on   behalf   of   the respondent. 5.1 Shri Ranjit Kumar, learned Senior Advocate appearing on behalf of the appellant has vehemently submitted that in the facts and circumstances of the case, the High Court ought not to have interfered with the concurrent findings of the learned sole Arbitrator and the learned Commercial Court under Section 34 of the Arbitration Act by giving an alternate construction to the CMDA.  It is vehemently submitted that by passing the impugned judgment   and   order,   the   High   Court   has   exceeded   in   its jurisdiction in interfering with the award passed by the learned Arbitrator,  confirmed   by   the  learned  Commercial  Court,  while exercising the powers under Section 37 of the Arbitration Act. 5.2 It   is   further   submitted   by   the   learned   Senior   Advocate appearing on behalf of the appellant that under Section 37 of the Arbitration Act, the scope of judicial inquiry is narrow and does not   entail   giving   own   construction   to   the   contract.     It   is submitted by disturbing the findings, the High Court has gone beyond the limited scope of inquiry contemplated under Section 37 of the Arbitration Act.  7 5.3 It   is   further   submitted   by   the   learned   Senior   Advocate appearing on behalf of the appellant that the Division Bench of the High Court has failed to appreciate that the interpretation made by the learned sole Arbitrator on the clauses of CMDA was plausible   construction/interpretation   and   therefore   the   same could not have been substituted by the High Court in exercise of powers under Section 37 of the Arbitration Act. In support of his above submissions, Shri Ranjit Kumar, learned Senior Advocate has heavily relied upon the decisions of this Court in the cases of  Associate Builders v. Delhi Development Authority, reported in (2015) 3 SCC 49; Steel Authority of India Limited v. Gupta Brother Steel Tubes Limited, reported in (2009) 10 SCC 63   and the recent decision of this Court in the case of Ssangyong   Engineering   &   Construction   Co.   Limited   v.   National Highways Authority of India (NHAI), rendered on 08.05.2019 in Civil Appeal No. 4779 of 2019, reported in 2019 SCC Online SC 677. 5.3.1 It is further submitted by the learned Senior Advocate appearing on behalf of the appellant that admittedly there was a delay of 21 months in supply of coal, which was due to the  force 8 majeure   as there was a delay in obtaining the forest clearance and   environmental   clearance.     It   is   submitted   that   the   price which was agreed by the appellant in the year 2008 to be paid in the year 2011 would never remain the same in the year 2013­14. It is submitted that therefore though the commencement date as per CMDA was extended due to an admitted fact of  force majeure to 25.3.2013, the commencement date would remain as the date defined under the CMDA, i.e., 25.06.2011 and therefore the price escalation ought to be considered from that date. 5.3.2 It is further submitted by the learned Senior Advocate appearing   on   behalf   of   the   appellant   that   though   by   mutual agreement   the   commencement   date   was   extended   due   to   an admitted   fact   of   force   majeure   to   25.03.2013,   there   was   no agreement to supply the coal at the same price which was to be supplied in the year 2011.  It is submitted that there is a specific clause – clause 4.5.2 which allows extension of commencement date in cases of   force majeure , however, no such corresponding clause has been provided in clause 5.4.3, which is a clause for price escalation.  It is submitted that the intention of parties was never to unilaterally extend the first operating year referred to in 9 clause 5.2.2.  It is submitted that therefore the price escalation has to be necessarily applied from the contractually stipulated date, i., 25.06.2011. 5.3.3 It is submitted that in any case the interpretation by the learned Arbitrator was plausible and as such was equitable also.   Merely because some other view was possible, the High Court   is   not   justified   in   interfering   with   the interpretations/findings recorded by the learned sole Arbitrator and   that   too   in   exercise   of   powers   under   Section   37   of   the Arbitration Act.   It is submitted that the interpretation of the relevant clauses of the CMDA with respect to claim no.1 was actually in consonance with the relevant clauses of the CMDA.  It is submitted therefore the High Court has erred in interfering with the award passed by the learned Arbitrator, confirmed by the learned Commercial Court.    5.4 Now so far as claim no.2 under the head ‘Fixed Costs’ is concerned,   Shri   Ranjit   Kumar,   learned   Senior   Advocate   has heavily relied upon clause 8.2(iii) of the CMDA.  It is submitted that   due   to   the   lapse   on   the   part   of   the   respondent,   the respondent   was   unable   to   take   delivery   of   the   coal   for   the 10 financial year 2013­14.  It is submitted that there was an event of default by the respondent as contemplated in clause 8.2(iii) of the CMDA. 5.4.1 It is submitted that due to inability of the respondent to take coal as per the stipulated delivery schedule, the appellant had to operate its plant at a sub­optimal level which resulted in incurring fixed costs.  It is submitted that it was mandatory for the coal to be lifted within 3 months of production to prevent spontaneous combustion and to ensure that there is no hazard to the plant.  It is submitted that despite this, the respondent failed to take delivery. 5.4.2 It is further submitted by the learned Senior Advocate appearing on behalf of the appellant that the High Court has committed an error by not granting the said claim on the ground that the loss was incurred by AMPL (sub­contractor) under Coal Mining Services Agreement to which the respondent was not a party and secondly that loss of Rs.78 crores is not substantiated beyond   the   Chartered   Accountant’s   certificate.   It   is   further submitted by the learned Senior Advocate appearing on behalf of the appellant that CMDA does not prohibit appointment of AMPL 11 as   a   sub­contractor   and   in   fact   any   such   appointment   was approved by the appellant and therefore AMPL cannot be said to be a complete third party to the CMDA.   It is submitted that therefore when the respondent failed to lift the fixed quantity of the coal and there was a delay in taking the delivery of the coal for the F.Y. 2013­14, the appellant shall be entitled to the loss suffered to the extent of Rs.78 crores.  It is submitted therefore the High Court has committed a grave error in disallowing the said claim. 5.5 Now so far as claim no.3 under the head ‘Escrow Account’ is concerned,   it   is   submitted   by   the   learned   Senior   Advocate appearing on behalf of the appellant that the High Court has erroneously   held   that   the   respondent   was   entitled   to   make deductions from the appellant’s bills for payments made in the escrow account.   It is submitted that as such the learned sole Arbitrator rightly came to a conclusion that the stage of closing of mines had not been arrived at and therefore the deductions to make the payments into escrow account were premature.   It is submitted that the issue of deduction would arise only after a passage of 30 years at the time of closure of the mining plant.  It 12 is further submitted that the deposit of amount in the escrow account had arisen due to the guidelines issued by the Ministry of Coal, which was subsequent to the execution of the CMDA.  It is   submitted   that   therefore   the   said   circular   issued   by   the Ministry of Coal would not bind the parties to the CMDA.  It is submitted therefore the High Court has committed a grave error in rejecting claim no.3. 5.6 Making the above submissions and relying upon the above decisions, it is prayed to allow the present appeal. 6. Shri Tushar Mehta, learned Solicitor General of India, while opposing the present appeal, has vehemently submitted that in the facts and circumstances of the case and having found that the claims allowed by the learned sole Arbitrator, confirmed by the learned Commercial Court, were just contrary to the relevant clauses of the CMDA, the High Court is justified in reversing the award passed by the learned Arbitrator, confirmed by the learned Commercial Court. 6.1 It is vehemently submitted by the learned Solicitor General that as per the settled proposition of law, the learned Arbitrator cannot substitute the terms of the contract and/or interpret the 13 relevant clauses of the contract, which would make the relevant clauses of the contract nugatory.  It is submitted that the award, by   standing   in   complete   contravention   of   clear   and   express provisions of the CMDA, is in conflict with the public policy of India.  It is submitted that in the present case, according to the respondent, regarding the “commencement date”, there was only one possible interpretation that could have been accepted by the learned   arbitrator.     It   is   submitted   that   however   the interpretation that has been upheld by the learned arbitrator, apart from being devoid of any reasoning in its support, is wholly incompatible with the terms of the CMDA and the conduct of the parties.  It is submitted that any award, by standing in complete contravention of clear and express provisions of the CMDA, is in conflict with the public policy of India and therefore is liable to be set aside.  It is submitted therefore the High Court has rightly set aside the award in exercise of powers under Section 37 of the Arbitration   Act.     In   support   of   his   above   submissions,   Shri Tushar   Mehta,   learned   Solicitor   General   of   India   has   heavily relied upon the decision of this Court in the case of  ONGC v. Saw Pipes   Limited,   reported   in   (2003)   5   SCC   705;   Hindustan   Zinc 14 Limited v. Friends Coal Carbonisation, reported in (2006) 4 SCC 445 and Associate Builders v. DDA, reported in  (2015) 3 SCC 49. 6.2 Now   so   far   as   claim   no.1,   namely,   price   escalation   is concerned, it is vehemently submitted by Shri Tushar Mehta, learned Solicitor General that the term “commencement date” has been defined in the agreement to have the same meaning as given to it in clause 4.5.1. It is submitted that as per clause 4.5.3 the date   of   commencement   is   the   essence   to   the   contract.     It   is submitted that as per the relevant clauses of the CMDA, the commencement date was extendable and in fact with the mutual agreement the same was extended to 25.03.2013.  It is submitted that the term “commencement date” is defined to be the date on which the actual supply of coal begins.   It is submitted that in the present case, admittedly, the date of supply of the coal is 25.03.2013,   and   therefore,   the   appellant   shall   be   entitled   to escalation in price only after the completion of 12 months from the commencement date, i.e., 25.03.2013.  It is submitted under the CMDA, the appellant is entitled to the escalation in price in each operating year provided that the first escalation shall occur only   after   completion   of   12   months   from   the   commencement 15 date, i.e., 25.03.2013.  It is submitted that thus any escalation in price is linked to the date of commencement of coal supply.  It is submitted that thus if the coal supply is commenced as planned on   25.06.2011,   the   first   operating   year   would   have   been 25.06.2011   to   31.03.2012.     However,   since   coal   supply   only commenced on 25.03.2013, the first operating year ought to have been 25.03.2013 to 31.03.2013.   It is submitted therefore that when   the   commencement   date   is   25.06.2011,   the   first   price escalation   would   be   applicable   for   the   F.Y.   2013­14.     It   is submitted that however if the commencement date is held to be 25.03.2013 (which in fact was extended by mutual agreement), the  first  price   escalation  would   occur   in   F.Y.   2014­15.     It  is submitted that it is evident from clause 5.4.3 of the CMDA that an escalation in price was to be made only after the delivery of coal had commenced and it is an admitted fact that actual supply of coal started on 25.03.2013.   It is submitted therefore that there is no question of price escalation for F.Y. 2013­14.   It is submitted   that   therefore   the   award   passed   by   the   learned Arbitrator was just contrary to the relevant clauses of the CMDA and therefore the same is rightly set aside by the High Court.   16 6.3 It is further submitted by the learned Solicitor General of India that in fact the respondent lifted the full quantity of the fixed quantity and therefore there was no loss and in fact the appellant failed to adduce any evidence with respect to the actual loss either due to delay in lifting the coal and/or lifting the loss quantity of the coal than they agreed.   The same is rightly set aside by the High Court. 6.4 It   is   further   submitted   by   the   learned   Solicitor   General appearing on behalf of the respondent that similarly the High Court has rightly set aside the claim with respect to “escrow account”.  It is submitted that as such the “escrow account” was required to be opened as per the circular issued by the Ministry of Coal.  It is submitted that, in fact, the appellant consented to open   the   escrow   account   which   as   such   was   required   to   be opened as per the guidelines issued by the Ministry of Coal.  It is submitted that therefore in fact the appellant consented that the money is being recovered from its running bills to be deposited in the escrow account.   It is submitted that even the same is in consonance   with   clause   3.2.1   of   the   CMDA.     It   is   submitted 17 therefore the High Court has rightly disallowed the said claim made in escrow account. 6.5 Making the above submissions and relying upon the above decisions, it is prayed to dismiss the present appeal.  7. We have heard the learned counsel for the respective parties at length. 8. At   the   outset,   it   is   required   to   be   noted   that   by   the impugned judgment and order, the Division Bench of the High Court   in   exercise   of   its   powers   under   Section   37   of   the Arbitration Act has set aside the award passed by the learned Arbitrator, confirmed by the learned Commercial Court.   Therefore,   the   short   question   which   is   posed   for consideration   before   this   Court   is,   whether   in   the   facts   and circumstances   of   the   case,   the   Division   of   the   High   Court   is justified   in   interfering   with   the   award   passed   by   the   learned Arbitrator, confirmed by the learned Commercial Court, in an appeal under Section 37 of the Arbitration Act? 9. While answering the aforesaid question, certain decisions of this   Court   and   the   law   declared   on   the   jurisdiction   of   the 18 appellate   Court   while   considering   the   award   passed   by   the learned Arbitrator are required to be considered. 9.1 In the case of  Associate Builders (supra) , this Court had an occasion to consider in detail the jurisdiction of the Court to interfere with the award passed by the Arbitrator in exercise of powers under Section 34 of the Arbitration Act.  In the aforesaid decision, this Court has considered the limits of power of the Court to interfere with the arbitral award.  It is observed and held that only when the award is in conflict with the public policy in India, the Court would be justified in interfering with the arbitral award.  In the aforesaid decision, this Court considered different heads of “public policy in India” which, inter alia, includes patent illegality.  After referring Section 28(3) of the Arbitration Act and after   considering   the   decisions   of   this   Court   in   the   cases   of McDermott International Inc. v. Burn Standard Co. Ltd., reported in (2006) 11 SCC 181 (paras 112­113) and Rashtriya Ispat Nigam Limited v. Dewan Chand Ram Saran, reported in (2012) 5 SCC 306   (paras   43­45) ,   it   is   observed   and   held   that   an   arbitral tribunal   must   decide   in   accordance   with   the   terms   of   the contract, but if an arbitrator construes a term of the contract in a 19 reasonable manner, it will not mean that the award can be set aside   on   this   ground.     It   is   further   observed   and   held   that construction   of   the   terms   of   a   contract   is   primarily   for   an arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something that no fair minded or reasonable person could do.  It is further observed by this Court in the aforesaid decision in paragraph 33 that when a court is applying the “public policy” test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected.   A possible view by the arbitrator on facts  has   necessarily   to   pass   muster   as   the   arbitrator   is   the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award.   It is further observed   that   thus   an   award   based   on   little   evidence   or   on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. 9.2 Similar   is   the   view   taken   by   this   Court   in   the   cases   of National Highways Authority of India v. ITD Cementation India Limited, reported in (2015) 14 SCC 21(para 25) and Steel Authority 20 of India Limited v. Gupta Brother Steel Tubes Limited, reported in (2009) 10 SCC 63 (para 29) . 10. Applying   the   law   laid   down   by   this   Court,   we   have   to examine   whether   the   Division   Bench   of   the   High   Court   has exceeded in its jurisdiction in setting aside the arbitral award impugned before it. 11. For convenience, we shall deal with the impugned judgment and order passed by the High Court claim­wise.  The first claim is with respect to “price adjustment/escalation”; the second claim is with respect to “fixed costs” and the third claim is with respect to “escrow account”. 11.1 Now   so   far   as   the   claim   with   respect   to   “price adjustment/escalation” is concerned, the learned arbitrator held that the date of commencement of the first operating year for the purposes of clauses 5.2.2 read with 5.4.3 would be 25.06.2011 and therefore zero year for the purpose of price escalation has to be 2011­12.   Accordingly, the learned arbitrator considered the escalated price in F.Y. 2013­14 at Rs.895/­ per MT.   However, according to the respondent, as the date of commencement was changed from 25.06.2011 to 25.03.2013, the zero year for the 21 purpose of price escalation would be 2013­14.  It is required to be   noted   that   it   is   not   in   dispute   that   price   escalation   is permissible under the contract/agreement itself and there shall be price escalation every year as per the formulae mentioned in the agreement,  commencing  from  the  date  of  commencement. However, it is true that the initial date of commencement, i.e., 25.06.2011   came   to   be   extended   to   25.03.2013   by   mutual agreement. However, the same was due to  force majeure  as there was a delay of 21 months in obtaining the forest clearance and environmental clearance.  The price was quoted in the year 2007­ 08,   applicable   from   2011.   However,   there   was   a   delay   in obtaining the forest clearance and environmental clearance and therefore   the   date   of   commencement   of   supply   came   to   be changed.     In between there would be hike in labour charges, transportation charges, etc.  Though the date of commencement of supply was extended, there was no corresponding amendment in the relevant clauses of the agreement with respect to price escalation.   There was no specific agreement that in the year 2013, the appellant would supply the coal at the same price, without any price escalation.  Therefore, considering the overall facts   and   circumstances   of   the   case   and   by   giving   cogent 22 reasons, the learned arbitrator interpreted the relevant clauses of the contract and specifically held that the date of commencement of the first operating year for the purposes of clauses 5.2.2 read with 5.4.3 would be 25.06.2011 and accordingly the zero year for the purpose of price escalation would be 2011­12 and therefore the appellant shall be entitled to the enhanced amount as is applicable in the year 2013­14 (the price escalation).   Having considered the reasoning given by the learned arbitrator, we are of the opinion that the interpretation by the learned arbitrator was   both   possible   as   well   as   plausible.     Therefore,   merely because some other view could have been taken, the High Court is not justified in interfering with the interpretation made by the arbitrator   which   as   observed   was   possible   and   plausible. Therefore, in the facts and circumstances of the case, we are of the   opinion   that   the   High   Court   has   clearly   exceeded   in   its jurisdiction in interfering with the award passed by the learned arbitrator   with   respect   to   claim   no.1   –   price adjustment/escalation.  At this stage, it is required to be noted that though the High Court has observed that the award passed by the learned arbitrator with respect to claim no.1 was against the public policy, with respect, we do not see any element of 23 public policy.  It was pure and simple case of interpretation of the relevant clauses of the agreement which does not involve any public policy.  Therefore, we are of the opinion that the impugned judgment and order passed by the High Court for quashing and setting aside the award passed by the learned arbitrator with respect to claim no.1 – price adjustment/escalation cannot be sustained and the same deserves to be quashed and set aside. 11.2 Now so far as claim no.2 – “fixed costs” and an amount of Rs.78 crores awarded by the learned arbitrator with respect to compensation   of   loss   is   concerned,   having   gone   through   the relevant material on record, we are of the opinion that the High Court  has   rightly   set  aside   the   award   passed   by   the   learned arbitrator with respect to claim no.2.  Except the CA’s certificate, no further evidence had been led with respect to actual loss. Considering the material on record, it is on the contrary found that in the relevant year the quantity of the coal lifted by the respondent was much above the fixed quantity.  Thus, the award passed by the learned arbitrator with respect to claim no.2 was contrary to the evidence on record and therefore is rightly set aside by the High Court. 24 11.3 Similarly, even with respect to claim no.3 – “Escrow Account” is concerned, the High Court has rightly interfered with the award passed by the learned arbitrator with respect to claim no.3.   It is required to be noted that the escrow account was required   to   be   opened   as   per   the   guidelines   issued   by   the Ministry of Coal, Government of India for the preparation of mine closure plant.   The guidelines required, inter alia, the mining company to open an escrow account with any schedule bank. Accordingly,   the   respondent   opened   an   escrow   account   and executed   an   escrow   agreement.     From   the   correspondence between the parties, it appears that even the appellant consented for opening the escrow account.  The appellant also agreed that the   amount   to   be   deposited   in   the   escrow   account   will   be recovered by the respondent from immediate next payment of the coal bills of the joint venture company – PKCL raised towards dispatches of coal from appellant’s coal blocks. Thus, thereafter it was not open for the appellant to claim the amount lying in the escrow account.   If the amount lying in the escrow account is returned to the appellant, the purpose and object of opening the escrow account which was as per the guidelines of the Ministry of Coal would be frustrated.  The object and purpose of opening the 25 escrow account was to see that the appellant company fulfils the contract as per the agreement and till the closure of the coal blocks.  Therefore, the High Court has rightly interfered with the award passed by the learned arbitrator with respect to claim no.3 – escrow account by observing that the reasoning is perverse or so irrational that no reasonable person could have arrived at on the material/evidence on record.  We are in complete agreement with the view taken by the learned Division Bench of the High Court. 12. In view of the above and for the reasons stated above, the present appeal succeeds in part. The impugned judgment and order passed by the High Court insofar as quashing and setting aside the award passed by the learned sole arbitrator, confirmed by the learned Commercial Court, insofar as claim no. 1 – price adjustment/escalation is hereby quashed and set aside and the award passed by the learned arbitrator with respect to claim no.1 is hereby restored. The impugned judgment and order passed by the High Court insofar as quashing and setting aside the award passed by the learned arbitrator with respect to rest of the claims, namely, 26 claim  no.2   –  fixed   costs  and   claim   no.3   –  escrow   account   is hereby confirmed.   The present appeal is partly allowed to the aforesaid extent only.  However, in the facts and circumstances of the case, there shall be no order as to costs. ………………………….J. [ARUN MISHRA] NEW DELHI; ………………………….J. MAY 27, 2019. [M.R. SHAH] 27