Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
CASE NO.:
Appeal (civil) 5343 of 2002
PETITIONER:
M/s Southern Ispat Ltd.
RESPONDENT:
State of Kerala & Ors.
DATE OF JUDGMENT: 25/03/2004
BENCH:
K.G. Balakrishnan & B. N. Srikrishna.
JUDGMENT:
J U D G M E N T
SRIKRISHNA, J.
The judgment of the Division Bench of the Kerala High Court
dismissing writ appeal no.2614/2001 of the appellant is challenged before
us in this appeal. The writ appeal itself was to impugn the judgment of the
single Judge dismissing O.P. No.9007/1999 by the appellant.
With a view to encouraging the industrial process in the State of
Kerala, and as a measure of incentive, the State Government decided as a
matter of policy that new industrial units established in the State would be
exempted for a period of 5 years from payment of enhanced power tariff
which had come into effect on 1.1.1992. This policy was reflected in the
G.O. (MS) No.4/92/ID dated 6.2.1992 which indicated that the concession
would be available:
"i. to the units from the date of commercial
production which start such production between
1.1.1992 and 31.12.1996.
ii. To manufacturing units only and not to service
and entertainments units;
iii. To existing units for substantial expansion/
modernisation / diversification. The concession
in such cases will be available only for the
consumption of the new machinery and
equipment which add to the capital asset, by not
less than 25 % of the existing fixed capital
investment excluding land and building the
installation of which is to be certified by the
competent authority.
iv. For modernisation, to industrial units having a
contract demand not exceeding 500 KVA. In
such cases, new equipments alone will be
eligible for the concession."
The Government order also indicated that the eligibility for the
concessions would have to be certified by the Kerala State Industrial
Development Corporation (KSIDC) / Kerala Financial Corporation (KFC)
in respect of units funded by them, or by the Director of Industries and
Commerce in other cases, and by the concerned General Manager, District
Industries Centres in respect of Small Scale Industrial units. It was also
declared in Government order that the industrial units which set up their
captive power generating units for their own consumption would be
exempted from payment of electricity duty to the extent to which they
generate power for their own consumption. The said concession was made
available to the units which may have started commercial production or set
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
up captive power generating units between 23.9.1991 and 31.12.1991.
On 26/27.6.1995 the appellant company was registered with the
Registrar of Companies office at Palakkad in Kerala State. The company
intended to manufacture alloy steel M.S. Sections, C.T.D. Bars, Steel
Castings and allied products. The company had an authorised capital of
Rs.550 lakhs out of which shares worth Rs.205 lakhs were issued to and
subscribed by the Directors and their friends and rest were issued to and
subscribed by the public. The appellant company also raised loans from the
Kerala State Industrial Development Corporation and the Kerala Financial
Corporation for setting up the unit. According to the appellant, the total
project cost was Rs.820 lakhs. Land was purchased in Kottai village in
Palakkad District of Kerala and construction of buildings and installation of
machinery for steel melting and re-rolling was commenced.
On 17.7.1995 the appellant made an application to the Chief Engineer,
Kerala State Electricity Board (’KSEB’) for allocation of 2450 KVA of
power. The appellant requested for registration of its application and sought
a feasibility certificate for the allocation of power at the earliest to facilitate
sanction of loan from KFC /KSIDC and working capital from South Indian
Bank Ltd.
On or about 17.6.1996 the appellant made a representation to the
Ministry of Steel, Government of India to persuade the KSEB to expedite
the sanction of power. The Regional Development Commissioner for Iron
and Steel, Government of India, Ministry of Steel, addressed a D.O. letter
dated 3.7.1996 to the Chairman KSEB, strongly recommending the urgent
sanction of the power to the appellant. By a letter dated 16.7.1996 the
Chairman, KSEB, informed the Regional Development Commissioner for
Iron and Steel, Madras that the State of Kerala was facing acute shortage of
electrical energy and that the KSEB was resorting to all possible ways to tide
over the situation. As a part of their efforts to bring down the energy
consumption, they had even banned new domestic connections. Hence, the
Chairman said, "in the present scenario I am not in a position to think of
giving power allocation to a power intensive industry like steel producing
unit" and said "if the situation improves, the application of M/s Southern
Ispat Ltd., can be taken up". The said reply was forwarded to the appellant
by the office of the Regional Development Commissioner for Iron and
Steel.
By a letter dated 10.9.1996 addressed to the appellant the KSEB
sanctioned power allocation to the extent of 1950 KVA at 11 KV with
contract demand of 1950 KV to the appellant’s factory. The allocation was
made subject to the following conditions:
"1. Supply is liable to be restricted or cut of during
power shortage period after giving notice.
2. Power should not be used for industrial purpose
between 6 P.M. to 10 P.M. or any other
restrictions necessitated by local condition or
otherwise when imposed should be strictly
complied with.
3. Charges payable as minimum will have to be
paid even if power is not availed of within three
months from the date on which the readiness of
the Board to supply power to you is intimated.
4. Specific provision regarding the above
condition will be incorporated in the service
connection agreement.
5. You have to execute a power supply agreement
in the form to be specified by the Deputy Chief
Engineer, Ele. Circle, Palakkad and agree to pay
the tariff and other charges specified by the
Board from time to time as per rules in force in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
the Board within 6 months from the date of this
letter failing which the allocation sanctioned
will stand cancelled.
6. You have to request remit the required amount
under OYEC scheme which may be ascertained
from the Assistant Executive Engineer,
Electrical Major section, Parali.
7. The power allocated can be availed only after
drawing separate 11 KV feeder from Parali Sub
Station (Extentsion of 1.12 KM of S/C line and
duplicating 2.3 KM of the Kottayi feeder) for
which OYEC amount has to be remitted by the
applicant.
8. The power allocated can be given only after
providing separate outlet in the 110 KC Sub
Station, Parali and the cost of work has to be
met by the application under OYEC Scheme."
The Executive Engineer KSEB Palakkad informed the appellant
by a letter dated 3.10.1996 that an estimate amounting to Rs.8,73,200
had been sanctioned for the power allocation work to the appellant
under Own Your Electric Connection (OYEC) basis. The appellant was
called upon to remit a sum of Rs.8,73,200/- in cash, at the earliest, to the
electrical section. On 11.11.1996 the appellant wrote a letter to the
Executive Engineer, Electrical Division, KSEB Palakkad informing him
that it had completed all civil works at the site and erected over 50% of
plant and machinery and that other machines were in transit and were
expected to reach very shortly. He, therefore, requested that instructions
be issued to the Executive Engineer Electrical, Parali to accept the
amount of Rs.8,73,200 so that the KSEB electrical work may start to
meet the requirements. On 12.11.1996 the Executive Engineer Electric
Division Palakkad addressed a letter to the Deputy Chief Engineer,
Electrical Circle, Palakkad on the subject. He pointed out that an
estimate for Rs.8,73,200 towards construction of 1.12 Kms 11 KV
overhead line and duplicating 2.3 KM of Kottayi feeder from 110 KV
sub station Parali for giving high tension connection under OYEC basis
had been sanctioned in favour of the appellant. He also stated that the
appellant was ready to remit the amount on OYEC basis and requested
further instructions in the matter.
On or about 14.11.1996 the appellant sent a letter to the Deputy
Chief Engineer, Electrical Circle, Palakkad thanking him for the
inspection of the work site on 12.11.1996. It also enclosed a Charted
Accountant’s certificate detailing the investment of Rs.379.68 lakhs and
a photocopy of KSIDC’s letter dated 11.11.1996 giving full details.
Finally, the letter requested permission to deposit the amount of
Rs.8,73,200 at Electrical Major Section, Parali so that the construction
of line may begin. A copy of the letter from KSIDC requesting
expedition and commission of the project was also forwarded.
Apprehending that the KSEB was deliberately delaying the
matter, so that the appellant would not be able to carry out commercial
production before the cut off date of 31.12.1996, the appellant
submitted a scheme to the Government of Kerala for generation of 125
KVA electrical energy by installation of a diesel power generating set in
its factory. By the letter dated 6.12.1996 of the Chief Electrical Inspector
to the appellant sanction for the scheme was granted subject to the
following conditions:
"1. Copy of Power allocation sanction for additional
loads if required should be obtained from the
K.S.E.Board/ Licensee and a copy of the same
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
forwarded to Electrical Inspector.
2. Installation of all switch boards and distribution
boards should be in conformity with Rule 51 (1)
(c) of I.E. Rules, 1956.
3. Fuses should be graded properly and selected
based on the rating of cables. Low watt loss
fuses shall be selected.
4. Earthing of the installation should conform to
provisions in I.S.3043/87.
5. Isolation facility should be provided for all
equipments within a distance of 3 meters from
equipments conforming to Rule 50(1)(d) of I.E.
Rules, 1956.
6. M.V. installation should conform to I.S. 732.
7. Installation of all cables should be as per
standards.
8. An energy meter should be provided in the
generator circuit which should be got tested and
sealed by Kerala State Electricity Board/
Standards Laboratory attached to this
Department and a copy of the test report should
be forwarded to Electrical Inspector.
9. Sanction from K.S.E.B. under Section 44 of
Supply Act 1948 should be obtained and copy
forwarded to the Electrical Inspector.
10. Only materials with I.S. certification as required
under QCO should be used. The Electrical
Inspector should ensure this.
11. Only energy efficient equipments shall be used
in the installation.
12. Completion report should be submitted to this
office for arranging inspection.
13. The voltmeter and frequency meter may be
provided before the breaker in the generator
control panel."
On 6.12.1996 the appellant also applied to the Secretary of
Kottayi Gram Panchayat for permission to install and utilise a diesel
generator set of 125 KVA for its factory with the help of which it was
proposed to use a 10 HP motor.
On 11.12.1996 the appellant forwarded a cheque for Rs.8,73,200
to the Assistant Executive Engineer, Electrical Major Section, Parli and
requested him to accept it towards the estimate for the construction
work to be carried out. He was also requested to draw up an agreement
so that it can be executed and the security amount be deposited.
According to the appellant, it purchased stamp papers for
executing the agreement with KSEB for supply of electricity on
9.12.1996. On 11.12.1996 the Assistant Executive Engineer, Parali
accepted the cheque of Rs.8,73,200 towards the cost of construction of
electric line. By an order made by the Chief Engineer Transmission
(North) Kozhikode, on 12.12.1996 sanction was accorded for an
estimate amounting to Rs.13,10,000 for modification of sub-station for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
providing 11 KV Outlet at 110 KV sub-station, Parali and registered as
21/96-97. It was directed by the order that the cost on account of this
had to be met from the deposit to be made by the beneficiary under
OYEC Scheme.
On 13.12.1996 the appellant gave a declaration to the KSEB that
the private generator set installed at the premises of its factory would
not be synchronised with KSEB board mains and that a meter would be
installed. On the same day the agreement on stamp paper of Rs.60 was
forwarded to the Assistant Executive Engineer, Electrical Major
Section, Parli, Palakkad for being processed. He was also requested to
intimate the amount to be deposited towards security. On 16.12.1996
the appellant deposited a sum of Rs.13,10,000/- with the KSEB as
directed in the order of the Chief Engineer.
The appellant moved the High Court of Kerala by O.P.
No.6456/1997 seeking a writ of Mandamus directing the KSEB and its
officers to take urgent and immediate steps to give sanctioned power
connection to the appellant’s factory at Kottayi and also sought an
interim order for grant of power connection temporarily from the feeder
line to the neighbouring industrial unit, M/s Elgi Tyre & Treads Ltd.
Kottayi, so as to enable the petitioner to maintain nominal production
and marketing of its products and reduce the overheads and other losses.
This petition was disposed of by a learned single Judge of the Kerala
High Court by an order dated 11.4.1997 with the direction to the Deputy
Chief Engineer, Electrical Circle, Vydyuthi Bhavan, Palakkad, to
consider and take a decision on Exhibit P-15 (the appellant’s
representation dated 23.12.1996) addressed to him highlighting the
grievances of the appellant, with notice to the petitioner, within a period
of three weeks.
Pursuant to the directions made by the High Court, the KSEB
considered the grievances made by the appellant and the appellant was
informed as under by letter dated 23.5.1997 :
"I have been directed by the Secretary/ K.S.E.B.
Trivandrum-4 to intimate you the decision regarding
your representation vide Ex. P-15 in the above OP.
Accordingly I may inform that:
1) Power allocation to the extent of 1950 KVA was
granted to you by the Chief Engineer (Distt.
North), Kozhikode on 12.9.1996 on the specific
conditions that
a) The power can be availed only after
drawing separate 11 KV feeder from Parli
Sub-Station under OYEC; and
b) The power can be given only after
providing separate outlet in the 110 KV
Sub-Station / Parli under OYEC.
The above conditions were stipulated taking into
consideration all technical aspects such as loading on
11 KV feeder, Voltage regulation, flexibility of 11 KV
lines, existing Power system/ line capacity etc. As you
have already remitted the OYEC for all the above
works (a) & (b) above, action has been taken by the
Executive Engineer/ Elec. Division/ Palakkad to
finalise the tenders for the construction of 11 KV new
feeder.
Taking into account the existing consumers in
the 11 KV Elgi Feeder and all technical aspects, I
regret to inform that it is not technically feasible to
connect your factory load from the existing Elgi
feeder.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
Further, I may inform that due to acute Power
shortage, the Board has ordered a total ban on new
connections to the Power Intensive units \026 during the
period of Power cut, w.e.f. 30.7.1996.
Yours faithfully
Sd/-
EXECUTIVE ENGINEER IN/C."
For a period of almost two years the appellant made no grievance,
nor took any other steps. The appellant moved a writ petition No.OP
9007/1999 before the High Court of Kerala challenging the bill for
charges for electrical energy supplied to the appellant’s industrial unit at
rates in excess of the pre-1992 tariff rates. This writ petition was moved
on 31.3.1999 and challenged the invoice no.23602 dated 23.3.1999 by
which the appellant was called upon to pay a sum of Rs.2,28,578/-
towards consumption of electricity during the month of February, 1999.
By a judgment dated 3.7.2001 the learned single Judge who heard the
writ petition dismissed the writ petition holding generally that appellant
had not complied with the conditions subject to which power supply at
concessional tariff rates have to be made. Being aggrieved thereby, the
appellant filed writ appeal no.2614/2001 which was dismissed by the
Division Bench by the judgment impugned before this Court.
It is contended by the appellant that the delay in sanction and
supply of electric supply was only on account of the tardy manner in
which the KSEB functioned. It is also urged that, despite the lethargy
shown by the KSEB, to meet the deadline the appellant had installed its
own diesel generator set and commenced "commercial production" on
14.12.1996. The appellant relied on certain invoices for sales made to
customers in the month of December, 1996, a certificate dated 11.9.1998
issued by the KSFC, the copies of the nil return made to the commercial
taxes department, declaration made to the superintendent of Central
Excise and Register of daily stock in support of its contention that it had
commenced ’commercial production’ in the month of December, 1996.
Reference was also made to the assessment order issued by the Sales Tax
Department and the Balance Sheet of the company as on 31.3.1997 for
this purpose.
The respondents strongly refute the contentions urged and support
the judgment of the Division Bench of the High Court as being correctly
decided on the facts of the case.
As the Division Bench rightly pointed out, the question to be
decided in this case is essentially a question of fact, namely, whether the
appellant had started ’commercial production’ between 1.1.1992 and
31.12.1996 so as to be entitled to power supply at concessional tariff
rates. As a rule, it is not the practice of this Court to interfere with factual
findings which have been concurrently recorded by two courts below.
Both the learned single Judge and Division Bench have concurrently
answered all factual findings against the appellant. On that ground itself
the appellant must fail. Nonetheless, as the appeal was argued with some
seriousness, we propose to deal with the facts and examine the factual
findings only from the point of view of interference under our special
jurisdiction under Article 136.
The Division Bench of the High Court rightly pointed out that
though the policy of granting concessional tariff was announced by the
State Government on 6.2.1992, followed by the KSEB order dated
27.3.1992, the appellant did nothing till or about June 1995. It is only in
June 1995 that the appellant company was incorporated and an application
for power allocation was made on 17.7.1995. The appellant’s factory had
yet to be constructed and machinery to be transported and installed after
the construction of the factory building . Undoubtedly, the application
was moved on 17.7.1995 in anticipation. The material on record suggests
that there was acute shortage of electricity as a result of which even
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
domestic power connections were being refused. The high tension power
supply required by the appellant had to be specially arranged by drawing
the electrical lines on the OYEC basis by construction of PSC polls along
the line at the Appellant’s cost. This amount was deposited on 11.12.1996,
only a few days before the concession was about to lapse. Having
examined the correspondence on record, we are not in a position to accept
the contention of the appellant that the respondents had acted with undue
tardiness or lethargy. Further, the remittances of Rs.8,54,700/- and
Rs.3,45,200/- made by way of security deposit for executing the power
supply agreement were actually made on 1.2.1997 and 4.2.1997, after the
expiry of the period of concession.
The KSEB made the power allocation on the specific condition that
power would be supplied subject to drawing of 11 KVA exclusive feeder
line from 110 KV Parali station under the OYEC scheme. The electric
wiring was completed in the factory of the appellant and the wiring
contractor submitted completion certificate on 29.8.1998. There were
some deficiencies which were rectified by the appellant only on 1.12.1998.
The electrical inspector is required to sanction the electrical wiring, and
this was done on 14.12.1998. Power supply commenced only on
19.2.1999. Thus, upto and including 19.2.1999 the appellant had not
functioned with the power supplied by the KSEB either temporarily or on
permanent basis.
The contention of the appellant that commercial production had
commenced in December 1996 can hardly be accepted. The appellant was
setting up the factory for manufacturing of alloy steel M.S. Sections,
C.T.D. bars, Steel ingots and so on with a planed production of 24000 tons
of iron and steel ingots and 24000 tons of iron and steel bars, coils etc.. It
hardly stands to reason that "commercial production" of such a factory
could have commenced by using of a 125 KVA diesel generator set. There
is also no material on record to show that the appellant had run the factory
by using 125 KVA generator set during the period December 1996 to
February 1999. It is pointed out by the High Court, and rightly in our
view, that even the diesel unit could also not be used until permission was
obtained under Rule 65 of the Indian Electricity Rules, 1956, from the
Chief Electrical Inspector. Such permission was obtained from the Chief
Electrical Inspector only on 14.12.1998. Thus, it is clear that even the
order for energisation of the 125 KVA diesel generator set was accorded to
the appellant only in 1998.
In these circumstances, we find it difficult to accept the contention
of the appellant that ’commercial production" had started in December
1996 by using diesel generator set as alleged.
The appellant contends that the certificate issued by the Kerala
Financial Corporation dated 11.9.1998 is conclusive evidence of the fact
that the appellant had commenced "commercial production" in December
1996. Interestingly, the KFC’s certificate is very guarded and states:
"This is to certify that Southern Ispat Limited has
commenced its commercial production of C.i. Shot
and grits with the help of Generator set as Kottayi in
Palakkad district on the 14th day of Decembr, 1996
as per records submitted by the company."
(Emphasis is ours)
In the first place, we are unable to accept that the certificate issued
by the KFC is conclusive in the matter. At the highest, it may be one of
the facts to be considered by the KSEB in the light of all other relevant
material.
The High Court has pointed out a series of difficulties in accepting
this certificate as conclusive. Firstly, the certificate has been issued only
on 11.9.1998. The certificate is issued "To whom so ever it may
concern". There is no reference to the electrical inspector’s findings on
the matter of conditions of appellant’s high tension installations, which
was a pre-requisite for the KFC to issue a proper certificate for the
purpose of entitlement to the pre-1992 tariff concessions. There is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
nothing to show that the KFC had made any inquiry of their own. On the
contrary, as the certificate shows, the certificate appears to have been
issued merely on the basis of record produced by the company. The
record produced by the company could not have shown that the appellant
company had started commercial production. The High Court has also
disbelieved and rejected the other documents relied upon in support of the
appellant’s case of commencing of commercial production prior to
31.12.1996.
The High Court points out the fact that promoters of the appellant
company had a factory at Raipur in Madhya Pradesh and the possibility of
the Appellant having bought manufactured goods from there and sold
them within the State of Kerala to create documents to show that the
production started before 1996 could not be ruled out. Even the
documents produced by the appellant do not show any continuous
’commercial production’ during the period December 1996 to February
1999. We agree with the conclusion of the High court that it was not
sufficient for showing ’commercial production’ that some small items
were sold by the appellant in December 1996 and ’nil’ assessment of
sales tax was made and a small excise duty payment was also made. We
agree with the High Court’s view that these were all self-serving
documents created as evidence for commercial production prior to the cut
off date of 31.12.1996.
Upon an overall assessment of the facts on record, we are not
satisfied that the view taken by the Division Bench of the High Court on
facts is so perverse that it requires interference by this Court under
Article 136 of the Constitution.
In the result, the appeal is dismissed. However, there shall be no
order as to costs.