Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
M.P. ELECTRICITY BOARD, JABALPUR.
Vs.
RESPONDENT:
M/S. VIJAYA TIMBER CO.
DATE OF JUDGMENT: 05/12/1996
BENCH:
M.M. PUNCHHI, K. VENKATASWAMI.
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
K.VENKATASWAMI J.
The appelltant/defendant in Civil Suit. No.9-A/67 on
the file of the Court of Civil Judge. Class-I, Rajandgaon,
has suffered a decree at the hands of the trial Judge,
directing the removal Of the electric line with poles
situated in the land bearing Kh. No. 908/2 area 1.32 acres
at village Nandai. In addition to that, the appellant was
also directed to pay a sum of Rs.1770/- towards past damages
and to pay future damages @ 5/- per day to the plaintiff
(respondent-herein) from the date of institution of suit
till the removal of electric line.
Aggrieved by decree, an appeal was preferred to the
first Additional District judge, Durg, at Rajnadgaon, The
appellate court dismissed the appeal by judgment and decree
dated 5.2.1984. Still aggreived, he preferred a second
appeal in the High Court of Madhya Pradesh, Jabalpur. The
High Court modified the decree by removing the mandatory
injunction directing the defendant to remove the electric
line with poles but sustained the decree for damages, past
and future. The above appeal is directed against the
judgment and decree of the High Court.
Shri Pallav Sishoia, learned counsel appearing for the
appellant attempted to argue the appeal by raising a point
which was neither raised in the pleadings nor argued in the
courts below, namely, that the suit was barred by
limitation. As this question to limitation on the facts of
this, case was not one of pure question of law- but a mixed
question of fact and law, we did not permit the learned
counel to raise this point for the first time before us.
The learned counsel for the appellant. therefore, has
to confine his argument as to the bar of the suit as raised
before the High Court. BY referring to Sections 12. 1",, and
52 of Indian Electricty Act, learned counsel submitted that
the suit, as filed in the present case was barred. In other
words, according to the learned counsel, the civil Court
could not adjudicate the dispute raised in the suit for
which remedies and forum are provided under the Act itself
and the plaintiff/respondent ought to have pursued those
remedies before the forum mentioned in the Act. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
contention of the learned counsel for the appellant was that
in view of the forum provided in the Act for resolving the
dispute, the suit must be taken to have been barred
impliedly under Section 9 of the Code of Civil Procedure.
For appreciating the above contention, minimal facts
may now be noted.
The grievance of the plaintiff/respondent was that in
the land belonging to him which has been set apart for
industrial use, the appellant Board had taken 33 KV high
tension transmission lines over the construction already
started in the said land without its consent and as such the
erection was unauthorised and liable to be removed. The
defence was that there was no erection when the high tension
transmission lines were taken through the land and the
plaintiff/respondent never objected for taking those lines.
However, the findings of all the three courts are to the
effect that the transmission lines were laid without the
plaintiff’s consent after the plaintiff has already
constructed portion of its saw mill, that the overhead
transmission lines are likely to endanger the property of
the plaintiff, that there was no sanctioned scheme for the
transmission lines and that the plaintiff suffered damages @
5/- day.
In the light of above concurrent findings of all the
three courts. we do not think that there is any case for the
appellant to sustain the defence it has taken in the written
statement.
The High Court has given a finding after referring to
Section 12 of the Electricity Act, 1910 as well as the
provisions of the Electricity (Supply) Act, 1948, that the
provisions of latter Act have no application to the facts of
the case as admittedly, the tranmission lines were not laid
under any approved scheme. The High Court further held that
the appellant Board having laid the transmission lines
without taking the consent of the plaintiff, cannot be
treated as having acted in accordance with the provisions of
the lndian Electricity Act to take shelter under those
provisions. Therefore according to the High Court. the
remedy of the plaintiff was not to take recourse under the
provisions of the Act but to file a civil suit for
compensation/damages under the common law. In support of
this conclusion, the High Court has relied on a judgment of
the Madras High Court in S.M.E.S. Corpn. vs. Jagannatha (AIR
1960 Madras 374) and also Another judgment of this Court in
Amalgamated Electricity Co. vs. N.S. Bathena (AIR 1964 sc
1598).
It is well-settled that the exclusion of jurisdiction
of civil court cannot be readily inferred and the normal
rule is that civil courts have jurisdiction to try all suits
of a civil nature except those of which cognizance by them
is either expressly or impliedly excluded. A Constitution
Bench of this Court in Dhulabhai vs. State of M.P. ( 1968 3
SCR 663) had laid down several propositions in this regard.
The first proposition is apposite for the facts of this
case. lt reads as under:
"(1) Where the Statute gives
finality to the orders of the
special tribunals, the civil
court’s jurisdiction must be held
to be excluded, if there is
adequate remedy do in What the
civil court would normally do in a
suit. Such a Provision, however,
does not exclude those cases where,
the provision of the particular Act
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
have not been complied with or the
statutory tribunal has not acted in
conformity with the fundamental
principles of judical procedure."
In the light of the findings of the courts below which
we have extracted above. we do not think that the High Court
has committed any error in holding that the suit was
maintainable and also granting the modified relief.
Before parting with the case. we may observe that we
gave an opportunity to the appellant to settle the matter
outside the court but the learned counsel appearing for the
appellant after getting instructions reported that the
settlement was not possible. It is unfortunate. In the
result the appeal is dismissed. However, there will no order
as to costs.