Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3455 OF 2010
GUJARAT URJA VIKAS NIGAM LTD. … APPELLANT
VERSUS
ESSAR POWER LIMITED ...RESPONDENT
J U D G M E N T
ADARSH KUMAR GOEL, J.
Part I : Introductory
1. This appeal has been preferred under Section 125 of the
Electricity Act, 2003 (‘the Act’) against the judgment and order
nd
dated 22 February, 2010 passed by the Appellate Tribunal for
JUDGMENT
Electricity (the Tribunal) in Appeal No.86 of 2009 whereby the
Tribunal has set aside the order of the Gujarat Electricity
Regulatory Commission (‘the Commission’) which was in favour of
the appellant.
2. The substantial question of law sought to be raised by the
appellant is :
“Whether the Tribunal has correctly interpreted the terms of
th
Power Purchase Agreement dated 30 May, 1996 (PPA) and is
Page 1
2
justified in reversing the finding of the Commission based on
interpretation of the said PPA and other documents on
record.?”
Part II : Facts
the successor of the Gujarat Electricity Board and is a deemed
licencee under Section 2 (39) read with Sections 12 and 14 of the
Act. The respondent, ESSAR Power Limited (‘the EPL’), is a
generation company within the meaning of Section 2 (28) of the
Act. The appellant filed a petition before the Commission under
Section 86 (i)(f) of the Act for adjudication of the dispute arising
out of the Power Purchase Agreement (‘the PPA’). The appellant
inter alia sought compensation for wrongful allocation of electricity
by the EPL to its sister concern, Essar Steel Ltd. (ESL) in preference
JUDGMENT
to the appellant.
4. According to the appellant, the EPL was required to allocate
300 MW out of the total 515 MW of electricity and the remaining
215 MW was to be allocated to ESL. In case the quantum of
generation was less than 515 MW, the allocation was to be in the
proportion of 300 : 215. Contrary to this requirement, the EPL
allocated more electricity to ESL. The EPL agreed, vide letter
Page 2
3
dated 17.02.2000, that the appellant will be entitled to electricity
in the proportion of 300 : 215 but the same was not adhered to.
This resulted in loss to the appellant and gain to the EPL which,
| llant, ten | tatively |
|---|
crores (towards principal amount). It was further pleaded by the
appellant that under the agreement, the appellant was liable to
pay the annual fixed charges, the variable charges, incentive etc.
in relation to the allocated capacity of 300 MW out of total 515
MW. Similarly, the ESL to whom balance capacity of 215 MW was
allocated was to bear proportionate annual fixed cost, thus, the
EPL was required to make electricity available to the appellant in
the proportion of 300 : 215 as per clause 3 of the Agreement. The
EPL was required to declare the availability in the same proportion
so that the dispatch instruction could be issued as per the
JUDGMENT
Agreement. The appellant pleaded that it was entitled to
compensation for wrong allocation of electricity based on the
applicable HT rate from time to time. The appellant claimed
damages equal to the difference of rate at which electricity was to
be supplied to it and the rate at which the appellant was to supply
the same to its consumers. For this purpose, the respondent was
liable to give true details and complete account of the allocation
Page 3
4
made to the appellant and to ESL. The appellant had also raised a
claim for recovery of Deemed Generation Incentive paid to the
respondent to which the respondent was not entitled but the said
| ect matte | r of this |
|---|
Tribunal in that respect having become final.
5. It will be appropriate to refer to the prayer clause in the
petition filed by the appellant :-
“(a) hold that the petitioner is entitled to adjust in the
tariff payable by the petitioner to the respondent for
purchase of electricity all amounts received by the
respondent as a result of wrong allocation of
electricity; and deemed generation incentive when
Naphtha is proposed to be used as fuel;
(b) award cost of the proceedings in favour of the
petitioner and against the respondent; and
JUDGMENT
(c) pass such other or further orders as may be
deemed proper to give relief to the petitioner;
(d) continue to raise bills on Essar Group Companies
based on proportionate methodology.”
6. The above claims were contested by the respondent based
on preliminary objections including the plea of limitation as well as
on merits.
Page 4
5
Part III : Pleadings
7. As noticed in Para 4 above, the case of the appellant in the
| Commis | sion was |
|---|
its sister concern, against the rights and interest of the appellant
in violation of the PPA, the respondent allocated part of generating
capacity required to be allocated to the appellant to its sister
concern. The appellant had the obligation to pay annual fixed
charges, variable charges, incentive etc. in relation to the specified
allocated capacity and the sister concern of the respondent was to
pay proportionate annual fixed cost. The Agreement required the
EPL to declare availability in the specified proportion even when
generation was less than the total 515 MW capacity. Contrary to
JUDGMENT
the said requirement, the respondent allocated more electricity to
ESL and offered proportionately less electricity to the appellant.
Thereby, not only the agreement was violated, the understanding
reflected in letters issued by the respondent was also not honored.
In para 23.0 it was specifically mentioned that the appellant was
entitled to claim compensation for the wrong allocation and in
para 24.0, it was mentioned that the respondent was required to
give detailed and complete account of the allocation made.
Page 5
6
8. As against the above stand of the appellant, the stand of the
respondent in its written submission filed before the Commission
th
on 15 January, 2009 is that its only obligation was to supply 300
| d when c | alled upo |
|---|
bar to supply more than 215 MW to ESL. There is no evidence of
any loss suffered by the appellant. Article 3.1 of the Agreement
could not be read as suggested by the appellant. Further, if supply
was below the quantum specified in the dispatch instructions,
penalty could be claimed as per clause 7.4.3 of Schedule VII of the
Agreement. Further, the appellant was defaulter in complying with
its obligations in making timely payment.
Part IV : Finding of the Commission
9. The Commission upheld the plea of limitation raised by the
JUDGMENT
respondent to the extent that the appellant was held entitled to its
claims only for three years preceding the filing of the petition, i.e.,
th th
from 14 September, 2002, the petition having been filed on 14
September, 2005. The Tribunal upheld the said finding. Though
the appellant had filed Civil Appeal No.3454 of 2010 on this
aspect, the said appeal was dismissed by this Court vide order
nd
dated 2 September, 2011 as follows :
Page 6
7
| xcept to t<br>to the ap<br>of claims | he exten<br>pellant<br>for the |
|---|
10. The Tribunal also upheld the order of the Commission
accepting the claim of the appellant under the head of a Deemed
Generation Incentive and the respondent has not challenged this
aspect.
11. Thus, the only question for consideration is the claim of the
appellant for failure to declare availability of power in the
th
proportion of 300 : 215 MW for the period from 14 September,
JUDGMENT
2002 onwards.
12. The Commission on this aspect held as follows :
“ 9.1 The PPA was executed on 30.5.1996 and effective for a
period of 20 years. The relevant clauses of the PPA have been
examined. It is quite clear that under the PPA, GUVNL has an
obligation to pay an annual fixed cost for the allocated capacity,
which is 300 MW. Having paid the annual fixed cost for the said
capacity, GUVNL has a right for an equivalent amount of electrical
output. The purpose of paying annual fixed cost is to ensure that
GUVNL alone has the right to the said capacity and that no part of
the same can be sold to any other party. It is true that 41 the
normal industry practice is that unless the allocated capacity, for
Page 7
8
which fixed charges are being paid by the beneficiary is
surrendered, the beneficiary has the ability to sell/ negotiate any
transaction for utilisation of such allocated capacity. In this
context, reference is also made to the CERC (Terms and Conditions
of Determination of Tariff) Regulations, 2004.
| hat arises<br>on a prop | for consi<br>ortionate |
|---|
9.3 Although in the definition of allocated capacity, it is only
mentioned that 192MW capacity during Open Cycle mode
operation and 300MW capacity during Combined Cycle mode
operation is allocated to GUVNL, the same is further elaborated in
Article 3.1. In Article 3.1, the parties have agreed as follows:
“3.1 The allocation of the Capacity shall be as under:
a) During Open Cycle mode operation prior to
commissioning of the Combined Cycle mode operation:
138MW to the Essar Group of Companies; and 192 MW
to the Board
b) During Combined Cycle mode:
215 MW to the Essar Group of Companies; and
300 MW to the Board
JUDGMENT
The Company undertakes that, subject to the provisions and
during the term of this Agreement, it will fuel and operate the
Generating Station to meet the requirements of electrical output
that can be generated corresponding to the allocated capacity, in
accordance with its Dynamic Parameters so as to comply with the
Operating Characteristics except to the extent:
(i) as anticipated under the Maintenance Programme during
the period of Scheduled Outage.
(ii) That to do so would not be in accordance with Good
Industry Practice;
(iii) That may be necessary due to circumstances relating to
Safety (of personnel or plant apparatus);
(iv) that to do so would be unlawful;
(v) That may be necessary for reasons of Force Majeure
Natural or NonNatural.”
Page 8
9
9.4 For the interpretation of the contract the following principle as
laid down by the Supreme Court in Mrs. M.N. Clubwala v. Fida
Hussain Saheb (1964) 6 SCR 642 has to be kept in mind:
| f landlord<br>the decis | and tena<br>ive consi |
|---|
Also, the Hon’ble Supreme Court has held in State of Andhra
Pradesh. Vs. Kone Elevators India Ltd. (2005) 3 SCC 386:
“It is a settled law that the substance and not the form of
the contract is material in determining the nature of the
transaction”.
Therefore, it is necessary to read the PPA as a whole in order to
give a correct interpretation to the terms therein contained. The
definition of ‘Allocated Capacity’ in the PPA has to be read in
conjunction with Article 3.1. Article 3.1 clearly records the
allocation of capacity between two entities i.e. GUVNL as well as
Essar Steel.
JUDGMENT
9.5 From the reading of the Article 3.1 of the PPA as also the
corresponding Articles in the PPA with Essar Steel, it is clear
that the intention of the parties was that the capacity of the
generating plant will be shared between the two
beneficiaries only. The fact that Article 3.1 of the present PPA
records the capacity allocated to the Essar Group companies
along with the capacity allocated to GUVNL shows that
intention of the parties was to provide for allocation in the
proportion of 138:192 (while working in open cycle mode)
and 215:300 (while working in combined cycle mode).
Otherwise there is no reason for mentioning in Article 3.1. of
PPA about the quantum that is contracted with Essar Steel.
Similarly, the fact that the PPA with Essar Steel states the
Page 9
10
| ace. The<br>nly from t<br>apacity. T | intention<br>he two b<br>his is cle |
|---|
9.6 The submission of EPL that there is no clause in the PPA
that it cannot supply more than 215 MW to Essar Steel is also
not correct. Once the entire capacity has been allocated
between the two parties in a particular proportion, EPL
cannot violate the proportionate allocation for the benefit of
any one party. Having sold the capacity of 300 MW to GUVNL
and 215 MW to Essar Steel, for which fixed charges are paid
in the said proportion, EPL cannot argue that it can sell
power to Essar Steel beyond the capacity allocated to it.
There is no spare capacity that allows EPL to do that. Under
the procedure for dispatch in Schedule VI of the PPA, EPL had
to declare weekly schedules of the “Capacity” that is
available for the entire station (and not the “Allocated
capacity”). On the basis of such declaration,
requirement-schedule and dispatch instructions are issued.
The obligation of EPL is clearly to declare the “Capacity” of
the generating plant as a whole. Once the declared
availability for the entire plant is known, the beneficiaries will
proceed to issue dispatch instructions in accordance with the
terms of the PPA. Hence, the argument of EPL that it does not
have the obligation to declare capacity for the entire plant is
incorrect and contrary to the terms of Schedule VI of the PPA.
This submission is contrary to the procedure prescribed in
the PPA as well as the normal industry practice. Once the
capacity of the generating station as a whole is available, the
allocation of capacity has to take place in the proportion that
is contracted. Also, the submission of EPL that the
Petitioner's only concern, under terms of the PPA, is that it
must get electricity in accordance with its Dispatch
JUDGMENT
Page 10
11
| e gener<br>ciple of<br>s a nat | ating p<br>allocation<br>ural con |
|---|
9.7 In view of the aforesaid, the Commission accepts the
submission made by GUVNL to the effect that, if in a time
block the declared availability for the station with 515 MW of
the installed capacity in only 400 MW, the same should be
declared available to GUVNL to the extent of 233 MW and to
Essar Group to the extent of 167 MW, maintaining the
proportion of 58% : 42% (300:215). It is not valid for
EPL to declare available in any time block to Essar Group to
the extent of 215 MW towards their share and declare
available to GUVNL 185 MW. Such an act would mean that
Essar Group is being preferred at the cost of GUVNL. As
against the GUVNL’s entitlement of 233 MW they will get
only 185 MW and therefore a deficit of 48 MW equivalent of
electricity. That certainly cannot be the intention of the
parties.
JUDGMENT
9.8 Under the PPA, the obligation to supply power by EPL to
GUVNL is limited to the electrical output equivalent to the
allocated capacity of 300 MW. The fact that the EPL has an
obligation to make payment of deemed non generation
incentive and reduce annual fixed charges on a pro rata
basis, cannot in any manner negate the proportionate
principle of allocation when EPL declares availability less
than the allocated capacity.
Page 11
12
| In fact A<br>schedules<br>tement o | rticle 12.<br>attache<br>f the ter |
|---|
9.10 Furthermore, in the letter dated 17.02.2000, EPL
categorically agreed to the concept that power should be
supplied in the ratio of 58:42 provided certain conditions are
fulfilled. The conditions mentioned in the said letter will
demonstrate that the each condition is either in the nature of
additional concessions / modification that were sought by EPL
or alleged defaults on the part of GUVNL, which was not
agreed to by GUVNL.
9.11 However, if GUVNL does not take the power declared
available by EPL in terms of the aforesaid ratio, EPL will have
the right to sell the power to its sister concern subject to
reimbursement of the proportionate of the annual fixed
charges. GUVNL cannot make a submission that although it
will not purchase such power as declared available by EPL,
EPL cannot sell the same to its sister concern. Such a
submission would defeat the purpose of the Electricity Act,
2003 and the National Electricity Policy which promotes
generation and encourages sale of surplus capacity. If GUVNL
does not schedule the power to the extent of availability
declared by EPL of the entire plant in terms of the PPA, it
cannot complain if the power is sold to EPL’s sister concern
and the proportionate of the annual fixed cost is reimbursed.
JUDGMENT
9.12 The Commission is of the view that GUVNL is entitled to
claim compensation for the energy diverted to Essar Steel
from the capacity allocated to GUVNL under the PPA. EPL at
all times has an obligation under the present PPA to declare
availability for the entire plant and allocate the supply on the
Page 12
13
basis of 300:215 or 58:42.
| en 1998 a<br>ology for<br>greed th | nd Septe<br>determi<br>at GUVNL |
|---|
9.14 The Commission also directs that for the remaining
period of the PPA, EPL has a legal obligation to declare
availability for the entire capacity and that it shall not divert
any power to its sister concern in a manner contrary to the
proportionate principle. If GUVNL declines to purchase power
allocated on the proportionate basis, EPL will have the right
to sell the power to its sister concern subject to
reimbursement of proportionate of the fixed cost. ”
JUDGMENT
Part V : Appeal to the Tribunal and the Finding of the Tribunal
13. The respondent preferred an appeal before the Tribunal being
Appeal No.86 of 2009. Contention of the appellant was that the
EPL was not obliged to declare electricity availability in ratio of 300
: 215 MW to the appellant. The PPA signed with the appellant and
the sister concern of the EPL were independent. The obligation to
supply was to arise after receiving dispatch instructions only.
Page 13
14
14. The Tribunal framed following questions for consideration :
| city of th<br>vely? | e Electric |
|---|
(ii) Whether the Appellant, which failed to declare the entire
capacity of its generating station to the Electricity Board made
the supply of electricity to its sister concern Essar Steels Ltd. in
excess of the said ratio is liable to be held responsible for the
breach of the terms of PPA and consequently the Appellant is
liable to compensate the Electricity Board (R-1)”…..
15. The Tribunal upheld the stand of the EPL. It was held that
Articles I and III of Schedule VI to the PPA did not require the EPL
to declare the capacity in the ratio of 300 : 215 MW. As regards
th
letters dated 17th February, 2000 and 4 October, 2001 by which
the respondent accepted its liability, it was held that the GUVNL
JUDGMENT
never accepted or complied with its obligations and therefore, the
respondent was not bound by the stand in the said letters. It was
st
further observed that the claim for the period from 1 July, 1996
stood settled in view letter dated 13th October, 2006 of the
GUVNL to accept Rs.64 crores for diverting electricity to ESL.
Non-declaration of available capacity on proportionate basis was
not shown to have resulted in any loss or damage to GUVNL.
GUVNL had not proved any actual loss. It was observed that on
Page 14
15
the principle of Section 35 of the Sale of Goods Act, 1920, there
was no obligation to deliver in absence of dispatch instructions.
Further, the ESL supplied fuel to EPL for conversion into electricity
| GUVNL, t | he EPL h |
|---|
outside. GUVNL also made default in making payment to the EPL
which amounted to breach of reciprocal obligation. GUVNL also
failed to establish letter of credit to secure the payment of the
amount payable to the EPL which also was breach on the part of
the appellant.
16. The finding of the Tribunal is :-
“45. From these provisions of Schedule-VI, it is clear that there
is no provision, express or implied, to suggest that the EPL is
liable to declare the available capacity in the said ratio to the
Board and the Essar Steels Ltd. All these provisions would only
say that the EPL has to first give Weekly Schedules to the
Electricity Board indicating the time and capacity which would
be available and the Electricity Board shall thereafter issue its
requirement schedule through Despatch Instructions and
thereupon EPL is liable to operate generating station in
accordance with the Despatch Instructions given by the
Electricity Board and supply.
JUDGMENT
46. On a combined reading of Articles 1 and 3 and Schedule VI
of the PPA-1, it is clear that EPL has to declare available
capacity up to the allocated capacity to both the Electricity
Board as well as to Essar Steels Ltd. and not on proportionate
theory basis.
47. As a matter of fact, Article 5.2 of the PPA-1 obligates the
Electricity Board to pay to the Appellant its Annual Fixed
Page 15
16
Charges including the cost of the project on the level of
generation achieved up to the allocated capacity and not on the
allocated capacity itself. The Electricity Board has accordingly
paid the Annual Fixed Charges on monthly basis on the level of
generation achieved up to the allocated capacity.
| by the Ld | . Senior |
|---|
49. In such circumstances, the Electricity Board (R-1) cannot
claim that by reasons of it’s making payment for the Annual
Fixed Charges up to the allocated capacity, it was always
obligatory on the part of the EPL to supply power to the extent
of 58% to the Electricity Board and that since EPL has sold a
part of Electricity Board’s share in the power generated by the
EPL to its sister concern, EPL is liable to compensate the
Electricity Board for the same by treating such power which sold
by EPL to Essar Steel Ltd. as if it was sold by the Electricity
Board itself to Essar Steel Ltd. after purchasing the same from
the EPL.
50. On the basis of letters dated 17.02.2000 and 04.10.2001, it
is contended on behalf of the Electricity Board (R-1) that EPL
has conceded to its proportionate theory basis and as such it
cannot go back. This contention is not tenable. EPL in those
letters merely expressed its willingness to agree to the
proportionate theory basis subject to the condition that
Electricity Board should commit default in making the payment
of dues payable under the PPA-1 to EPL and also subject to the
condition that the Electricity Board shall comply with other
conditions of the PPA-1.
JUDGMENT
51. Admittedly, the stipulated conditions in those letters were
neither accepted nor complied with by the Electricity Board.
Hence the offer made by the EPL to the Electricity Board for
agreeing to the proportionate theory basis would not be
construed to be conceding and as such it is binding on it.
Page 16
17
| ricity Boa<br>ions is no | rd regard<br>t binding |
|---|
53. Furthermore, when there is an amendment to the PPA-1 on
18.12.2003, there is no reference about these amendments for
declaration of supply of power in the ratio of 58:42 to the
Electricity Board as well as to the Essar Steels Ltd. respectively.
The preamble of the said Supplemental Agreement dated
18.12.2003 clearly establishes that EPL is only obliged to
generate the electricity up to 300 MW allocated to the
Electricity Board and nothing more. In other words, there is no
amendment with regard to the declaration of electricity
generated on proportionate basis in the said Supplemental
Agreement dated 18.12.2003.
54. Under such circumstances, it is not open to the Electricity
Board to rely upon the aforesaid letters dated 17.02.2000 and
04.10.2001 to advance the plea of its proportionate theory.
55. It is an admitted fact that the Electricity Board through its
letter dated 29.10.2003 demanded from EPL the payment of an
aggregate amount of Rs. 537 crores on account of alleged
diversion of power by EPL to Essar Steels Ltd for the period
commencing from 01.07.1996 to 31st March 1999. It is also an
admitted fact that the parties thereafter held several rounds of
discussions and as a result of those discussions, a settlement
was actually arrived at by the parties in October 2004. Pursuant
to the said settlement, the Electricity Board recalculated the
amount, due on the basis of power supplied by the EPL to Essar
Steels Ltd in excess of the allocated capacity of 215 MW shall
alone be treated as sold and supplied by the Electricity Board.
On this basis, the Electricity Board itself furnished a statement
to the Appellant, EPL showing that a sum of Rs. 64 crores is
payable for the aforesaid period and on the aforesaid basis, the
EPL accepted the same as a part of overall package and
authorized the Electricity Board to recover the same on a
condition that the same methodology would be adopted in
JUDGMENT
Page 17
18
future also. Thereafter, through their letter dated 13.10.2006,
the Electricity Board accepted to receive Rs. 64 crores for
diverting the electricity to the Essar Steels Ltd.
| ainst the<br>y the EPL | EPL wit<br>to Essar |
|---|
57. Admittedly, it is not established that there is any breach of
the contract as the part of the Appellant under PPA-1 on
account of non-declaration of available capacity to the
Electricity Board on proportionate basis. The compensation can
be claimed only when there is a breach and due to the same
there was a loss or damage caused by the said breach of
contract. This has to be pleaded and proved. Unless this is
done, no compensation can be claimed. This is a settled law as
held by the Supreme Court in (1974) Vol-2 SCC 231 – Raman
Foundry V/s Union of India.
58. In the present case, the Electricity Board has not pleaded
and proved the actual loss or damage caused to it due to the
alleged breach of contract. The principle enshrined in section 73
of the Contract Act has been incorporated in Article 10.1 of the
PPA-1 which reads as follows:
JUDGMENT
“……neither Party shall be liable to the other Party in
contract, trot, warranty, strict liability or any other any
other legal theory for any indirect, consequential,
incidental, punitive or exemplary damages. Neither
Party shall have any liability to the other Party except
pursuant to, or for breach of this Agreement, provided,
however, that this provision is not intended to constitute
a waiver of any rights of one Party against the other
with regard to matters related to this Agreement or any
activity contemplated by this Agreement”.
59. Similarly, the explanation to Section 73 of the Indian
Contract Act provides that in estimating the loss or damage
Page 18
19
| or dam<br>esent ca<br>failed to | age aris<br>se, the<br>declare |
|---|
60. As indicated above, as per Article 3.2 of PPA-1, the EPL
becomes liable to deliver the capacity to the Electricity Board at
the delivery point in accordance with the Despatch Instructions.
The Despatch Instructions are instructions for delivery of
electricity. The principle contained in Article 3.2 of PPA-1 is in
terms of the provisions of Section 35 of the Sale of Goods Act,
1920. Section 35 of the Sale of Goods Act declares that the
seller of goods is not bound to deliver until the buyer applies for
the delivery.
xxx
74. One more aspect needs to be mentioned. The arrangement
in relation to supply of electricity up to the allocated capacity
of 300 MW between the Appellant EPL and the Electricity Board
under the PPA-1 and between the EPL and its sister concern
Essar Steels Ltd. under PPA-2 read with Fuel Management
Agreement dated 18.10.1996 are materially different. The Essar
Steels Ltd supplies fuel to EPL for conversion into electricity,
whereas the Electricity Board is under no obligation to supply
fuel to EPL. Admittedly, the EPL has to procure fuel from outside
and use it for generating electricity for sale to the Electricity
Board.
JUDGMENT
75. The PPA-1 is a contract between the EPL and the Electricity
Board containing reciprocal promises. In consideration of EPL
supplying electricity to the Electricity Board up to the allocated
capacity in accordance with the Despatch Instructions, the
Electricity Board had agreed and undertaken to pay the EPL the
tariff as mentioned in the PPA- 1. It is an admitted fact that the
Page 19
20
| lectricity<br>under the | Board i<br>PPA-1 ri |
|---|
76. It is also an admitted fact that EPL had written several
letters to the Electricity Board to establish Letter of Credit to
secure the payment of the amount payable under PPA-1 and
also pay the amounts when due. But the Electricity Board did
not heed to the request made by the EPL in this behalf and as a
result of it the ability of EPL to purchase the fuel for generating
electricity meant for sale to the Electricity Board got impaired.
77. As mentioned above, the claim for compensation made by
the Electricity Board against EPL in the present case is due to
the alleged breach of contract by EPL in declaring and supplying
the power to the Electricity Board in the proportion of 300MW
out of the total capacity 515 MW. The grievance is that EPL has
supplied less power than what is due to the Electricity Board
under the PPA-1. As aforesaid, Article 3.2 of the PPA-1 obliges
the Appellant to supply electricity to the Electricity Board only
in accordance with the Despatch Instructions given by the
Electricity Board from time to time. As a matter of fact, there is
no provision in the PPA-1 which restricts the right of the
Electricity Board to demand for supply of electricity only up to
the declared available capacity of the EPL. Admittedly, many a
times the Electricity Board asked for supply of more quantum of
electricity than what was declared as available to it by the EPL
by revising its Despatch Instructions and immediately thereafter
the EPL met this demand.
JUDGMENT
xxx
81. In the light of the above position, the direction given by the
State Commission with reference to reimbursement of Annual
Fixed Charges to the Electricity Board when the Electricity Board
has not secured energy to the extent allocated under the
Page 20
21
| ensation | we hold t |
|---|---|
| he comp<br>succeeds | ensation<br>in this |
| as claimed<br>ssue. Conse<br>on on this i | |
| not entitled to get the compensation a<br>the Appellant EPL succeeds in this is<br>findings given by the State Commissio<br>aside. “<br>Part VI : Rival Submissions<br>17. We have heard Shri C.A. Sundaram,<br>for the appellant and Shri K.K. Venugopal,<br>for the respondent.<br>18. Learned counsel for the appellant sub | a<br>s<br>o |
had ignored the implications of Article 3 of the PPA. The true
JUDGMENT
import of the PPA clearly casts an obligation on the EPL to allocate
electricity in ratio of 300 : 215 MW. This interpretation was
th th
accepted by the EPL in its letters dated 17 February, 2000, 4
th
March, 2000 and 4 October, 2001. Issues of non payment of
money due or not opening the letter of credit and not making
advance payment of fuel stood settled by Supplementary
th th
Agreement dated 18 December, 2003 and letter dated 19
December, 2003. Thus, the Tribunal erroneously assumed that
Page 21
22
amount of Rs.519 crores was outstanding. Moreover, there is an
error in the order of the Tribunal in observing that GUVNL had not
proved suffering of any damage. Para 23 of the petition expressly
| There is | further |
|---|
Schedule VI in regard to the obligation to declare the availability
of generating power upon which the dispatch instructions could be
issued. In absence of such declaration, the dispatch instructions
could not be issued. Finding that the appellant accepted Rs.64
crores by way of settlement was against record.
19. The EPL supports the view taken by the Tribunal. It is
submitted that there was no obligation for proportionate
declaration of available generation capacity. The respondent was
to meet the requirement of electric output corresponding to
JUDGMENT
allocated capacity of 300 MW. This obligation was subject to
reciprocal performance of obligation by the appellant. The PPA
executed by the respondent with the ESL was on different terms.
The appellant was required to make payment on due dates under
Article 5.3 of the Agreement and was also required to establish a
letter of credit under Article 5.5. As against this, under Article 4.1
of the PPA with the ESL, fuel is to be supplied by the ESL which
created an obligation to generate electrical output upto the
Page 22
23
capacity allocated to the ESL. For supply to the appellant, fuel is
required to be arranged by the respondent. The appellant had not
paid cost for its allocated capacity. The cost was pegged at Rs.945
| tment of | Rs.2061 |
|---|
th
The stand taken in the letter of the Respondent dated 17
February, 2000 could not be read as obligation of the respondent
for proportionate generation of the output or declaration of
available capacity in absence of compliance of obligations under
th
the PPA by the appellant. In letter dated 4 March, 2000, it was
made clear that if letter of credit was not opened by the appellant,
respondent will not be obliged to supply power.
Part VII : Points for consideration
20. The points which arise for consideration are :
JUDGMENT
(i) True interpretation of PPA to determine whether
there is any obligation to declare availability of power in
the ratio of 300 : 215;
th th
(ii) Effect of letters dated 17 February, 2000, 4
th
March, 2000 and 4 October, 2001on the rights of the
parties;
(iii) Interpretation of Schedule VI to determine whether
the obligation to issue dispatch instructions arose
before declaration of availability.
Page 23
24
(iv) Relief to which the appellant may be entitled to.
Part VIII : Decision on above points and reasons therefor
Re : (i) :
21. It is necessary to refer to the relevant provisions of the
Agreement:
“Article 3
3.1 Allocation of the Capacity
The allocation of the Capacity shall be as under:
a) During Open Cycle mode operation prior to commissioning of
the Combined Cycle mode operation: 138MW to the Essar Group
of Companies; and 192 MW to the Board
b) During Combined Cycle mode:
215 MW to the Essar Group of Companies; and
300 MW to the Board
JUDGMENT
The Company undertakes that, subject to the provisions and
during the term of this Agreement, it will fuel and operate the
Generating Station to meet the requirements of electrical output
that can be generated corresponding to the allocated capacity, in
accordance with its Dynamic Parameters so as to comply with the
Operating Characteristics except to the extent:
(i) as anticipated under the Maintenance Programme during the
period of Scheduled Outage.
(ii) That to do so would not be in accordance with Good Industry
Practice;
(iii) That may be necessary due to circumstances relating to
Safety (of personnel or plant apparatus);
(iv) that to do so would be unlawful;
(v) That may be necessary for reasons of Force Majeure Natural or
Non-Natural.”
Page 24
25
3.2 Delivery of Active Energy
| ecified in<br>ompany s<br>and the o | Schedul<br>hall have<br>ther elect |
|---|
3.3 Availability Declarations
From the date of Entry into Commercial Service of the first
Unit the Company shall, submit to the Board from time to time,
Declared Available Generation Capacity as per the procedures set
forth in Schedule VI.
xxx
Schedule VI
6.1 Submission of Weekly Schedules
The Company will submit to the Board’s Load Dispatch
Centre at Jambua, Baroda weekly schedules indicating the times
and Capacity which will be available from Generating Station and
if not available and reasons therefor. These weekly schedules will
be submitted on or before each Friday for the next week starting
from Monday. If at any time after the issue of such schedule,
there is any change in circumstances, the Company will notify the
Board about the revisions necessary in the weekly schedule and
the reasons therefor.
JUDGMENT
6.2 Issuance of Requirement Schedule
The Board shall issue to the Company’s Generating Station
at Hazira a Schedule of its requirement with respect to the
generation of the Allocated Capacity by the Generating Station
during each day by 5.00 PM on the preceding day. This schedule
will indicate the level of Active Power required to be produced by
Generating Station.
Page 25
26
6.3 Issuance of Dispatch Schedule
| ured at th<br>ion. | e Deliver |
|---|
6.4 Operation of Generating Station
The Company, subject to the provisions contained in Article
3.3 of this Agreement, shall operate Generating Station in
accordance with the relevant Dispatch Instructions given by the
Board from time to time provided that the Company shall not be
obliged to comply with such instructions to the extent that it
would require the Company to operate the Generating Station
otherwise than the Dynamic Parameters applicable from time to
time.
Schedule VII
7.1 TARIFF
The Tariff shall be determined as follows
a) Annual Fixed Charges to be determined in terms of Section
7.1.1
JUDGMENT
b) Variable Charges to be determined in terms of Section 7.2
c) Incentive Payment to be determined in terms of Section 7.3.
7.1.1 Annual Fixed Charges: Computation and payment
The Annual Fixed Charge shall be computed on the following
basis:
a) Interest on Debt:
It shall be computed on the Debt as per the Financial Plan
Page 26
27
approved by the Board. Interest on Debt shall also include lease
rentals payable in respect of lease assistance obtained by the
Company towards financing the Capital Cost.
| , the Inter<br>ling rates | est on De<br>of interes |
|---|
In respect of interest on Foreign Debt, the interest liability on the
applicable Foreign Debt shall first be computed in the applicable
foreign currencies and thereafter be converted to Rupees by
adopting the Base Exchange Rate and such amount shall be
adopted for the purposes of computing Interest on Debt.
A Supplementary Invoice shall be raised for an amount equal to
the difference between the amount of interest liability on Foreign
Debt as determined on the basis of Base Exchange Rate and the
amount of interest liability as on the due dates of the payment of
interest as per the Financing Plan computed on the basis of the
then prevailing exchange rate. If the amount payable to the
Company is determined to be less, on account of foreign exchange
variation, than the amount paid by the Board at the Base
Exchange Rate, such difference shall be repaid to the Board within
14 days from the date of the determination.
b) Operation and Maintenance Expenses (O&M) Expenses:
JUDGMENT
O&M Expenses including Insurance Charges for the first full
Accounting Year, after commissioning of Combined Cycle
Operation of the Generating Station, shall be calculated at the
rate of 2.5% of the Capital Cost of Rs.945 crores in respect of the
Allocated Capacity.
The expenditure on the O&M expense in each subsequent year
shall be revised on the basis of the weighted Price Index based on
the Wholesale Price Index and Consumer Price Index in the ratio of
70:30 respectively or at the rate of 10% progressively every year,
whichever is lower. O&M expenses shall not qualify for foreign
exchange variations.
c) Depreciation
Depreciation will mean the depreciation as notified by the
Page 27
28
Government of India from time to time and provided under the
Electricity (Supply) Act, 1948 and shall be first computed on the
assets of the Generating Station and thereafter apportioned for
the purposes of the determining the Annual Fixed Charges as a
proportion of the Allocated Capacity over the Nominal Installed
Capacity.
| in accorda<br>every year as | |
|---|---|
| d) Tax on Income:<br>Tax on Income shall be determined<br>provisions of the Income Tax Act, 1961 e<br>Tax payable by the Company x Retur<br>Total taxable Income Incen<br>For the purposes of determination of t<br>the Tax on Income shall be computed on<br>under or over recovery of Tax on Incom<br>year on the basis of certificate of docu<br>assessment by the Income Tax Officer co<br>e) Return on Equity (ROE):<br>Return on Equity shall be computed on | e |
JUDGMENT
Return on Foreign Equity (ROFE) shall be computed at the rate of
16% on the amount of Foreign Equity in the applicable foreign
currency and thereafter be converted to Rupees at the Base
Exchange Rate and such amount shall be adopted for the purpose
of computing ROFE.
A Supplementary Invoice shall be raised at the end of each
Quarter in an Accounting Year, for an amount equal to the
difference between the amount of ROFE determined on the basis
of Base Exchange Rate and the amount of ROFE as at the end of
each Quarter computed on the basis of the then prevailing
exchange rate. If the amount payable to the Company is
determined to be less, on account of foreign exchange variation
than the amount paid by the Board at the Base Exchange Rate,
such difference shall be re-paid to the Board within 14 days from
the date of the determination.
Page 28
29
f) Interest on Working Capital :
The amount of working capital on the Allocated Capacity shall be
computed on the basis of annual estimated level of generation
adopting the following norms:
| iquid fuels | only for o |
|---|
ii) Operation & Maintenance expenses (Cash) for one month;
iii) Maintenance Spares at actual but not exceeding one year’s
requirement, less value of One Fifth of initial spares already
capitalized; and
iv) Receivable equivalent to two months’ average billing for sale
of electricity.
The Interest on Working Capital shall be computed by applying the
rate of interest as applied by the Company’s bankers or the
Board’s Bankers whichever is lower on the amount of working
capital computed above.
g) Base Foreign Debt Repayment Adjustment Amount:
In respect of the Foreign Debt, the amounts falling due for
repayment during the Accounting Year shall be first computed in
the applicable foreign currencies and thereafter be converted to
Rupees by adopting the Base Exchange Rate. The difference
between the amounts of repayment determined as above and the
amount of repayment of Foreign Debt falling due during the
relevant Accounting Year and expressed in rupees adopting the
exchange rate as per the Financing Plan shall be included in the
Annual Fixed Charges.
JUDGMENT
A Supplementary Invoice shall be raised for an amount equal to
the difference between the amount of repayment on Foreign Debt
determined on the basis of Base Exchange Rate and the amount
of repayment on Foreign Debt as on the due dates of repayment
of Foreign Debt as per Financing Plan on the then prevailing
exchange rates. If the amount payable to the Company is
determined to be less on account of foreign exchange variation
than the amount paid by the Board at the Base Exchange Rate,
such difference shall be re-paid to the Board within 14 days from
Page 29
30
the date of the determination.
| f monthly<br>med. | Invoice 1 |
|---|
The Invoice in each month shall further specify the number of
units of Active Energy and Deemed Generation expressed in Kwh
achieved during such month and the cumulative Level of
Generation including Deemed Generation less Deemed
Non-Generation achieved upto end of such month.
22. The agreement clearly contemplates the proportion of
allocation of a capacity. The EPL has to fuel and operate the
generating station to meet the requirement of electric output that
can be generated corresponding to the allocated capacity. The
appellant has to pay annual fixed cost as determined in terms of
clause 7.1.1 of Schedule VII of the Agreement. The Commission is
JUDGMENT
thus, right in observing that once the entire capacity has been
allocated in two parts in a particular proportion, the contention of
the EPL that it could sell power to ESL beyond the allocated
capacity could not be accepted. The EPL was under obligation as
per Schedule VI to declare weekly schedule of the capacity
available and the dispatch instructions were to be issued on the
basis of the said declaration. It could not thus be said that the EPL
had no obligation to declare the capacity and the obligation of
Page 30
31
GUVNL to issue dispatch instructions was not dependent on
declaration of the available capacity by the EPL. Contrary view of
the Tribunal is clearly erroneous. In paras 45 and 46 and
| ent, the T | ribunal e |
|---|
was no obligation to declare available capacity on proportionate
basis. The finding of the Commission in paras 9.5 to 9.12 of its
order quoted above is the correct interpretation of the Agreement.
We hold accordingly.
Re : (ii) :
23. The Commission in this aspect observed :
“8.4 In the present case, the PPA was executed on 30.5.1996 and
remains operational for a period of twenty years. Under the terms
of the PPA, the generating company i.e. EPL is required to declare
availability and supply of electricity for the entire duration of the
PPA, while the Petitioner GUVNL has an obligation to purchase
electricity and pay the tariff in terms thereof. The dispute appears
to have arisen sometime in 1998-99, when the CAG Report for
the year 1998-99 rejected the contention of the Government that
there was no adverse financial impact as a result of diversion of
power. Thereafter, on or around 10.2.2000, a meeting was
conducted with the GEB to discuss the issue of diversion. On
17.2.2000, EPL subject to certain conditions accepted that power
is required to be supplied on a 58:42 basis. Attempts were made
to renegotiate the PPA. By a letter dated 23.4.2002, GEB wrote to
EPL identifying certain key areas for negotiation of PPA. The issue
of allocation of power was also part of the agenda. Since the
issue of allocation of power could not be settled, GEB by its letter
dated 29.10.2003 raised a claim of Rs. 537 crores for the period
1.7.1996 to 31.3.1999. EPL by its letters dated 1.11.2003 and
1.12.2003 denied the claim of GUVNL.
JUDGMENT
Page 31
32
xxxx
| ditions m<br>the each<br>ions / mod | entioned<br>condition<br>ification |
|---|
24. It is clear from the above that the letters of the respondent
acknowledged its liability to allocate the generated power to the
appellant and to the ESL in the ratio of 58 : 42. The Tribunal in
para 54 quoted above, held that the said letters could not be relied
upon in support of the claim that the appellant was entitled to be
allocated generated power in proportion of 58 : 42. This
finding is clearly erroneous and is without any basis and is liable to
JUDGMENT
be set aside. The finding of the Commission is based on record.
Re : (iii) :
25. In interpreting Schedule VI, the Commission held that the
EPL was liable to declare weekly capacity available and on that
basis dispatch instructions were required to be issued (para 9.6).
The contrary view taken by the Tribunal in para 45 and elsewhere
Page 32
33
is clearly contrary to the agreement between the parties as
reflected in Schedule VI quoted above.
Re : (iv) :
26. The main basis of the order of the Tribunal in rejecting the
claim of the appellant is the finding that the respondent had no
obligation to allocate available power in the ratio of 58 : 42 under
the terms of the Agreement and in terms of correspondence
between the parties. Apart from this, the Tribunal held that the
appellant had claimed Rs.64 crores by way of full and final
settlement (para 55) and that the appellant was in default in not
opening letter of credit and not paying Rs.519 crores. In doing so,
the Tribunal has ignored clear stipulation in the letter of the
th
appellant dated 13 December, 2004 referred to in para 8.14 of
JUDGMENT
the Commission that the amount of Rs.64 crores was not accepted
by way of final settlement. Similarly, the Tribunal has ignored the
th
supplementary agreement between the parties dated 18
th
December, 2003 followed by letter dated 19 December, 2003
(page 337 and 341,Vol.V) under which amount of Rs.289.40 crores
was paid to the respondent by way of settlement for the delayed
payment charges and other heads. Thus, the Tribunal was not
Page 33
34
justified in observing in para 75 that the appellant had defaulted in
making payment of Rs.519 crores which was a breach of promise
on the part of the appellant, thereby absolving the respondent of
| power as | per the |
|---|
position with regard to letter of credit referred in para 17.6 of the
order of the Tribunal. We have been informed that these aspects
have been gone into by the State Commission in a subsequent
nd
dispute vide order dated 22 October, 2014 and Appeal No.2 of
2015 against the said order before the Tribunal. We thus, make it
clear that our observations may not be treated as affecting the
decision of the said appeal.
27. We thus, hold that the order of the Tribunal is erroneous. The
said order has given rise to the substantial question of law which
JUDGMENT
has been discussed above, i.e., the interpretation of the
Agreement between the parties and the obligation of the
respondent to declare availability of generated power in the ratio
of 58 : 42 and consequence of default therein. The Tribunal
erroneously held that there was no pleading for making the claim.
Thus, the Tribunal has committed error of law as well as of record
in recording its finding as demonstrated above. It may also be
noted that the Commission has left actual working out of the loss
Page 34
35
to be worked out separately and on that basis the appellant has
already filed its claim which was pending consideration before the
Commission. The said proceeding can now be revived in the light
of our finding.
28. Accordingly, we allow this appeal, set aside the order of the
Tribunal and restore that of the Commission.
An Epilogue
29. Before we part with this judgment, it appears to be necessary
to draw attention of all concerned to a vital issue of composition
and functioning of Tribunals and statutory framework thereof
especially its impact on working of this Court and in turn on the
JUDGMENT
rule of law.
nd
30. It is well known that in the wake of 42 Amendment to the
Constitution of India, incorporating Article 323A and 323B of the
Constitution under Part XIVA, various Tribunals have been set up.
The Tribunals constitute alternative institutional mechanism for
dispute resolution. The declared objective of such Tribunals is
inability of the existing system of courts to cope up with the
Page 35
36
volume of work. This Court has gone into the question of validity
of scheme under which the High Court is bypassed without the
alternative institutional mechanism being equally effective for the
| was ne | cessary c |
|---|
and this Court being over burdened with routine matters in several
judgments to which reference may be made.
1
31. In L Chandra Kumar Vs. Union of India , in the course of
considering the constitutional validity of exclusion of jurisdiction of
the High Courts in service matters against the orders of the
Central Administrative Tribunal, this Court observed that the
manner in which justice is dispensed with by the Tribunals left
much to be desired. The remedy of appeal to this Court from the
order of the Tribunals was too costly and inaccessible for it to be
JUDGMENT
real and effective. Furthermore, the result of providing such
remedy was that the docket of this Court was crowded with
decisions of the Tribunals and this Court was forced to perform the
role of a first appellate court. It was necessary that High Courts
are able to exercise judicial superintendence over decisions of the
Tribunals. With these observations this Court directed that “all”
decisions of the Tribunals will be subject to High Court’s writ
1 (1997) 3 SCC 261
Page 36
37
2
jurisdiction under Article 226/227 . It was further observed that
the then existing position of direct appeal to this Court from orders
3
of Tribunal will stand modified .
considered by this Court was validity of setting up of National Tax
Tribunals under the National Tax Tribunal Act, 2005. While striking
down the Act, this Court commented upon validity of various
provisions of the said Act. Section 5 of the Act which provided for
sittings to be at Delhi, it was observed that a litigant who may
belong to a distant/remote State, may have to travel a long
distance and may find it difficult to identify an advocate who will
represent him. It was further observed that while vesting
jurisdiction in an alternative court/Tribunal, it was imperative for
JUDGMENT
the legislature to ensure that redress should be available with the
same convenience and expediency as it was prior to the
5
introduction of the newly created court/tribunal . As regards
Section 6 dealing with the qualification for appointment of a
member, it was observed that it was difficult to appreciate how
non judicial members could handle complicated questions of law
2 Para 91
3 Para 92
4 (2014) 10 SCC 1
5 Para 123
Page 37
38
6
which the Tribunal was required to deal with . Further,
composition of tribunals which were like courts of first instance
whose decisions are amenable to challenge under Article 226/227
| ient to ju | risdiction |
|---|
on a different footing from the Tribunals whose appeals were
directly provided to Supreme Court. Such Tribunals were
practically substitute for the High Courts. Process of selection and
appointment of Chairperson and members of such Tribunals could
not be different from the manner of selection of the High Court
7
Judges .
33. The above resume of law laid down by this Court may call for
review of composition of Tribunals under the Electricity Act or
other corresponding statutes. Appeals to this Court on question of
JUDGMENT
law or substantial question of law show that Tribunals deal with
such questions or substantial questions. Direct appeals to this
Court has the result of denial of access to the High Court. Such
Tribunals thus become substitute for High Courts without manner
of appointment to such Tribunals being the same as the manner of
appointment of High Court Judges. A perusal of Sections 113(b)(i)
to (iii) and 113(3) read with Section 78, Sections 84, 85 and 125 of
6 Para 126
7 Para 130
Page 38
39
the Electricity Act and corresponding provisions of similar Acts
may, thus, need a fresh look.
| ed that in | some Tr |
|---|
India Act, 1997), the Tribunal exercises original jurisdiction to the
8
exclusion of all courts and is located only at Delhi . It may further
be noted that normally tenure of office of the Chairman and
members is of short duration of three to five years. Access to
justice may not be, thus, available with the convenience with
which it is available when jurisdiction is with the local civil courts
sought to be substituted. Such provisions may need review in
larger public interest and for providing access to justice.
35. Apart from the above aspect, further question is whether
JUDGMENT
providing appeals to this Court in routine, without there being
issues of general public importance, is not a serious obstruction to
the effective working of this Court.
36. This issue has already been subject matter of debate. In an
Article by Shri T.R. Andhyarujina former Solicitor General of India,
titled “Restoring the Character and Stature of the Supreme Court
8 Sections 14 and 15
Page 39
40
9
of India ” learned author states that it was necessary to restore
the character and stature of the Supreme Court. The jurisdiction
of the Supreme Court should by and large be limited to matters of
| nce and | matter |
|---|
questions of law of general importance. The Supreme Court of
India, like apex Courts in other jurisdictions, was not to be a final
court to decide ordinary disputes between parties. The highest
court has its unique assigned role. But after the year 1990, the
Supreme Court is losing its original character and becoming a
general court of appeal by entertaining and deciding cases which
do not involve important constitutional issues or issues of law of
national importance. The adverse effect of this trend is that
matters of constitutional importance are not getting the due
priority and are pending for several years. Reference has been
JUDGMENT
made to the Statement of Objects for amending the Supreme
Court (Number of Judges) Act, 1956 in the year 2008, to the effect
that “it has not been possible for the Chief Justice of India to
constitute a five-judge Bench on a regular basis to hear the cases
involving interpretation of constitutional law as doing that would
result in constitution of less number of Division Benches which in
turn would result in delay in hearing of other civil and criminal
9 (2013) 9 SCC (J) 43
Page 40
41
cases”. In spite of the said amendment to increase strength of
judges to 31, larger Benches to decide constitutional and
important cases have not been regularly functioning. On account
| of issues | other t |
|---|
substantial questions of general importance, all the Benches are
engaged in handling the heavy routine work. The court rooms are
so crowded that it is hardly possible to enter a court room or to
pass through the corridors. “No other Supreme Court presents
such an undignified sight.” Further reference has been made to
functioning of other Supreme/highest courts in the world to
emphasize that the highest courts are engaged in deciding cases
of national importance by larger benches of 9/11 judges while the
Supreme Court of India is deciding most of the cases by Benches
of two-judges, which has its own adverse implications. Reference
JUDGMENT
has also been made to the discussion between Sir B.N. Rau, the
Constitutional Advisor and Justice Frankfurter of the U.S. Supreme
Court that the jurisdiction exercisable by the Supreme Court
should be exercised by Full Court. It is further stated that the
highest court should have limited number of cases and should not
be overloaded. On an average, in a year 80 cases are decided by
Supreme Court of U.K., the Canadian Supreme Court and the
Page 41
42
Australian High Court. 38 cases are decided by Constitutional
Court of South Africa in a year. Supreme Court of India is deciding
large number of cases and the reports in the cases sometimes run
| a year | with onl |
|---|
constitutional or of national importance. In Australia there is no
appeal to the highest court as of right and the cases are
entertained only if they are of public importance. They are to
resolve difference of opinion in different courts. This was
necessary to preserve efficiency and standing. Reference is also
made to the expert opinion that no litigant should get more than
two chances in litigation. It is further stated that “The Supreme
Court of India must cease to be a mere court of appeal to litigants
and a daily mentor of the Government, if it is to preserve its
pristine character, dignity and stature comparable to the Supreme
JUDGMENT
Court in other jurisdictions.” The Article ends with observation
“This requires a national debate by Judges, Lawyers, jurists and
informed public.”
10
37. In Mathai alias Joby Vs. George , this Court referred to the
th
R.K. Jain Memorial Lecture delivered on 30 January, 2010 by Shri
K.K. Venugopal, senior advocate to the effect that “an alarming
10 .(2010) 4 SCC 358
Page 42
43
state of affairs has developed in this Court because this Court has
gradually converted itself into a mere court of appeal which has
sought to correct every error which it finds in the judgments of the
| ountry a | s well |
|---|
11
tribunals . The court has strayed from its original character as a
constitutional court and the apex court of the country. Failure to
hear and dispose of cases within reasonable time erode confidence
of the litigants in the apex court. Reference was made to an
Article by Justice K.K. Mathew to the effect that time, attention and
energy should be devoted to matters of larger public concern.
Functioning of Supreme Court was not to remedy a particular
litigant’s wrong, but consideration of cases involving principles of
wide public or governmental interest which ought to be
authoritatively declared by the final court. The docket of the court
JUDGMENT
should be kept down so that its volume did not preclude wise
adjudication. The matter was referred for consideration of the
larger Bench for interpretation of Article 136. By the time, the
th
matter came up for consideration of the larger Bench on 11
January, 2016, the SLP became infructuous as the suit in which the
impugned interim order was passed itself had been decided. This
Court while dismissing the SLP as infructuous observed that while
11 Para 15
Page 43
44
Article 136 could be used with circumspection but its scope could
not be limited.
| Support | Societ |
|---|
12
India , it was observed that Supreme Court was not a regular
court of appeal. If an additional forum above the Tribunal was
required to be set up, a separate national court of appeal could be
th
created. In this respect, the matter was also considered in 229
Report of the Law Commission submitted in August, 2009.
However, that is a different issue particularly when this aspect is
being separately considered by a different Bench in Writ Petition
(C) No.36 of 2016 titled V. Vasanthakumar Vs. Sri H.C. Bhatia.
JUDGMENT
th
39. In Justice H.R. Khanna Memorial Lecture delivered on 8
September, 2014 by Hon’ble Mr. Justice J. Chelameswar of this
Court, the topic was “the Supreme Court of India, its jurisdiction
13
and problem of arrears” . It was stated that :
“The law declared by the Supreme Court in Hindustan Commercial
Bank Ltd. v. Bhagwan Dass [AIR 1965 SC 1142] was that normally
a party should approach the Supreme Court with a certificate of
the High Court. Only in exceptional circumstances would the
Supreme Court relax that requirement, is simply ignored. The
12 (1986) 4 SCC 767
13 (2015) 9 SCC (J-I)
Page 44
45
exception has become the rule now. The result is more and more
unsuccessful people getting encouraged to have another go at it
by approaching the Supreme Court. In most of the cases, what is
sought is a simple second or third “guess on facts” or taking
another plausible view of the matter.
xxxx
| where the | rights an |
|---|
40. While there may be no lack of legislative competence with
the Parliament to make provision for direct appeal to the Supreme
Court from orders of Tribunals but the legislative competence is
not the only parameter of constitutionality. It can hardly be
gainsaid that routine appeals to the highest court may result in
obstruction of the Constitutional role assigned to the highest court
JUDGMENT
as observed above. This may affect the balance required to be
maintained by the highest court of giving priority to cases of
national importance, for which larger Benches may be required to
be constituted. Routine direct appeals to the highest court in
commercial litigation affecting individual parties without there
being any issue of national importance may call for
reconsideration at appropriate levels. Further question is
Page 45
46
composition of Tribunals as substitutes for High Courts and
exclusion of High Court jurisdiction on account of direct appeals to
this Court. Apart from desirability, constitutionality of such
| to be go | ne into. |
|---|
expressing any opinion on this aspect at this stage.
41. We are thus of the view that in the first instance the Law
Commission may look into the matter with the involvement of all
the stakeholders.
42. We make it clear that as far as heavy pendency in this Court
on account of liberal exercise of jurisdiction under Article 136 of
the Constitution of India is concerned, we do not wish to make any
comment as this is a matter in the discretion of the Court and it is
for the Court to address this issue. Our discussion is limited to the
JUDGMENT
consideration of desirability of providing statutory appeals directly
to this Court from orders of Tribunals on issues not affecting
national or public interest and other aspects of statutory
framework in respect of Tribunals as discussed above.
43. The questions which may be required to be examined by the
Law Commission are :
Page 46
47
I Whether any changes in the statutory framework
constituting various Tribunals with regard to persons
appointed, manner of appointment, duration of
| t, etc. is | necessar |
|---|
of this Court in Madras Bar Association (supra) or
on any other consideration from the point of view of
strengthening the rule of law?
II Whether it is permissible and advisable to provide
appeals routinely to this Court only on a question of
law or substantial question of law which is not of
national or public importance without affecting the
constitutional role assigned to the Supreme Court
having regard to the desirability of decision being
JUDGMENT
rendered within reasonable time?
III Whether direct statutory appeals to the Supreme Court
bypassing the High Courts from the orders of Tribunal
affects access to justice to litigants in remote areas of
the country?
IV Whether it is desirable to exclude jurisdiction of all
courts in absence of equally effective alternative
Page 47
48
mechanism for access to justice at grass root level as
has been done in provisions of TDSAT Act (Sections 14
and 15).
considered appropriate.
44. We request the Law Commission to give its report as far as
possible within one year. Thereafter the matter may be examined
by concerned authorities.
45. Action taken by the Central Government, after its
consideration, may be placed on record. List the matter in
November, 2017 before an appropriate Bench, preferably of three
Judges to consider the above issue.
JUDGMENT
………………………………………………..J.
[ ANIL R. DAVE ]
………………………………………………..J.
[ ADARSH KUMAR GOEL ]
NEW DELHI;
AUGUST 09, 2016.
Page 48
49
1A-FOR JUDGMENT COURT NO.13 SECTION XVII
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Civil Appeal No(s). 3455/2010
GUJARAT URJA VIKAS NIGAM LTD. Appellant(s)
VERSUS
ESSAR POWER LIMITED Respondent(s)
Date : 09/08/2016 This appeal was called on for pronouncement of
JUDGMENT today.
For Appellant(s)
Ms. Hemantika Wahi,Adv.
Ms. Puja Singh, Adv.
Mr. Shubham Arya, Adv.
For Respondent(s) Ms. N. Nagpal, Adv.
Mr. E. C. Agrawala,Adv.
Hon'ble Mr. Justice Adarsh Kumar Goel
pronounced the judgment of the Bench comprising
JUDGMENT
Hon'ble Mr. Justice Anil R. Dave and His Lordship.
The appeal is allowed in terms of the signed
Reportable Judgment inter alia with following
observations.
“We are thus of the view that in the first
instance the Law Commission may look into
the matter with the involvement of all the
stakeholders.
We make it clear that as far as heavy
pendency in this Court on account of
liberal exercise of jurisdiction under
Page 49
50
| bility<br>rectly t | of prov<br>o this C |
|---|
The questions which may be required to
be examined by the Law Commission are :
I Whether any changes in the statutory
framework constituting various Tribunals
with regard to persons appointed, manner
of appointment, duration of appointment,
etc. is necessary in the light of judgment
of this Court in Madras Bar Association
(supra) or on any other consideration from
the point of view of strengthening the
rule of law?
II Whether it is permissible and
advisable to provide appeals routinely to
this Court only on a question of law or
substantial question of law which is not
of national or public importance without
affecting the constitutional role assigned
to the Supreme Court having regard to the
desirability of decision being rendered
within reasonable time?
JUDGMENT
IIIWhether direct statutory appeals to
the Supreme Court bypassing the High
Courts from the orders of Tribunal affects
access to justice to litigants in remote
areas of the country?
IV Whether it is desirable to exclude
jurisdiction of all courts in absence of
equally effective alternative mechanism
for access to justice at grass root level
as has been done in provisions of TDSAT
Page 50
51
Act (Sections 14 and 15).
V Any other incidental or connected
issue which may be considered appropriate.
| t as far<br>Thereafte | as poss<br>r the |
|---|
Action taken by the Central
Government, after its consideration, may
be placed on record. List the matter in
November, 2017 before an appropriate
Bench, preferably of three Judges to
consider the above issue.”
(VINOD KUMAR JHA)
(SUMAN JAIN)
COURT MASTER
AR-CUM-PS
(Signed Reportable judgment is placed on the file)
JUDGMENT
Page 51