Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 12
CASE NO.:
Appeal (civil) 5244-5246 of 2003
PETITIONER:
Food Corporation of India
RESPONDENT:
M/s A.M. Ahmed & Co. and Anr.
DATE OF JUDGMENT: 31/10/2006
BENCH:
Dr. AR. Lakshmanan & Altamas Kabir
JUDGMENT:
J U D G M E N T
Dr. AR. Lakshmanan, J.
The appellant - Food Corporation of India (hereinafter
called the ’FCI’) preferred the above appeals against the
judgment and final order dated 13.08.2002 passed by the
Division Bench of the High Court of Judicature at Madras in
OSA Nos. 157-159 of 1997 whereby the High Court dismissed
the appeals filed by the FCI and passed a decree in terms of
the Award together with interest @ 12% p.a. from the date of
the decree till the date of the payment.
The present dispute and differences arise out of the
contract relating to the work of clearing, stevedoring,
forwarding, exporting, handling and transport contract and
delivery of foodgrains, sugar, flour, for the users, gift,
hospital/suppliers and other commodities and gunny/twine
bales imported at the Port of Tuticorin at the FCI Storage
Godowns in and around Tuticorin for a period of two years
from the date of contract i.e. 08.04.1981 in pursuance of Work
Order No. SPC.1(1)/80 dated 20.04.1981 issued by the Senior
Regional Manager, FCI, Madras. The respondent-
contractor/claimant submitted his offer on 20.02.1981along
with covering letter. On 07.04.1981, a communication was
issued by the FCI to the claimant accepting their offer which
had been reduced through negotiation to 397% ASOR.
According to the FCI, a perusal of the said tender document
shows that in addition to cargo handling work at the Port, the
respondent-contractor had to perform various other duties
including unloading of food grains from railway wagons,
machine-stitching of food grain bags, loading into trucks and
other vehicles, etc. etc. According to the FCI, the tender
agreement did not provide for any escalation clause and also
stated that other than the rates agreed between the parties,
the contractor would not be entitled to any other payments.
On 01.09.1981, the Tamil Nadu Government issued a
notification in the Gazette notifying the settlement arrived at
between the Port Users and Cargo Handling labour of
Tuticorin Port regarding implementing of the settlement dated
04.01.1981. The respondent, by his letter dated 07.09.1981
to the FCI, pointed out the revision of wages and asked the
FCI to review its case for revision of rates and pass necessary
orders for revising the rates. The claim for escalation made by
the respondent was rejected by the FCI by its letter dated
14.03.1984. The respondent filed O.P. No. 49 of 1986 in the
Subordinate Court, Tuticorin for appointment of an Arbitrator
in the dispute regarding escalation. The said Court passed an
order appointing an Arbitrator in the matter. The High Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 12
of Madras modified the order passed by the Subordinate Court
and directed the Managing Director of the FCI to appoint an
Arbitrator in terms of contract between the parties. The
special leave petition filed against the aforesaid order was
dismissed by this Court on 05.05.1989. The special leave
petition was filed by the FCI being aggrieved by the finding
that the dispute between the parties was an arbitrable
dispute, since the only question to be determined was
payment of escalation which was not provided for in the
contract, therefore, could not have been referred to arbitration.
Following the dismissal of the special leave petition, the
FCI appointed respondent No.2 \026 Mr. B.S.Hegde Joint
Secretary and Legal Advisor Government of India as Sole
Arbitrator. Respondent No.1 filed Statement of Claim raising
several claims. The FCI filed a counter claim. The Arbitrator,
on 10.04.1992, passed the Award awarding a sum of
Rs.57,10,517/- and Rs. 22,84,207/- under claims (i) and (ii)
respectively with interest @ 9% p.a. from 08.08.1989 till date
of the award and future interest @ 12% p.a. till date of decree
or realization.
The FCI filed O.P.No. 350 of 1992 under Section 14(2) of
the Arbitration Act praying for a direction to the Arbitrator to
file the Award before the High Court so as to enable it to
challenge the same. Respondent No.2 filed the Award before
the Sub-Court Tuticorin on 30.06.1992. The claimant filed a
petition before the Subordinate Court for making the Award
rule of Court and a decree in terms of the Award. The Division
Bench of the Madras High Court in appeal preferred by the
FCI against the dismissal of O.P. No. 350 of 1992 directed
withdrawal of the O.P. filed before the Tuticorin Court to the
High Court. The FCI, upon being informed by the Registry of
the High Court regarding transfer of OPs and their re-
numbering as O.P.Nos. 441 and 441A of 1993, filed objections
to the Award under Sections 30 and 33 of the Arbitration Act
which was numbered as O.P. No. 697 of 1993. A learned
Single Judge of the High Court dismissed the objections filed
by the FCI by holding the same to be time-barred and made
the Award as rule of Court and passed decree in terms of the
Award. The FCI preferred an appeal to the Madras High Court
which was dismissed by the Division Bench of the said Court
on 14.07.1997. The High Court, vide judgment and order in
special leave petition Nos. 21377-21379 of 1997, set aside the
dismissal and remanded the matter back to the Division
Bench of the High Court for disposal on merits. The Division
Bench, after dismissing the objections filed by the FCI, passes
a decree in terms of the Award together with interest @ 12%
p.a. from the date of the decree till the date of the payment.
Aggrieved by the dismissal of the appeal by the High Court,
the FCI preferred the above appeals.
We heard Mr. K. Mohan, learned senior counsel and ASG
appearing for the appellant and Mr. R. Anand Padmanabha,
learned counsel for respondent No.1.
Mr. K. Mohan, learned senior counsel appearing for the
appellant, made the following submissions:
1. In the absence of an escalation clause in the contract,
the Arbitrator could not have awarded any amount
towards escalation and, therefore, the Arbitrator has
erred in awarding and the courts below in upholding
the escalation awarded by the Arbitrator;
2. The High Court completely erred in not noticing that
Clause 7 of the contract deals with payment of
minimum wages and this is different from the wage
increase in the present case which is not minimum
wages but are wages prescribed through settlement
and, therefore, erred in holding that there was an
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 12
implied provision in the contract to pay the wages;
3. The High Court ought not to have taken into account
the ex-gratia payment made by the Corporation to
bypass the absence of the escalation clause and in
holding that despite absence of escalation clause, the
contractor would be entitled to escalation.
4. Relying on the judgment of this Court reported in
(2000) 3 SCC 27 State of Orissa vs. Sudhakar Das
(dead) by LRs submitted that in the absence of any
escalation clause, an arbitrator cannot assume any
jurisdiction to award any amount towards escalation
and, therefore, that part of the award which grants
escalation charges is clearly not sustainable and
suffers from patent error;
5. Relying on the judgment of this Court reported in
(1990) 4 SCC 647 S.Harcharan Singh vs. Union of
India for the proposition that only when there is
provision for variation the arbitrator can award
escalation and since there was no such clause the
arbitrator has exceeded his jurisdiction;
6. Associated Engineering Company vs. Govt. of A.P.
reported in 1999 (4) SCC 93 was relied on for the
purpose that the award in question was rendered
beyond the limits of contract and that the arbitrator
cannot depart from the contract and award;
7. He placed strong reliance on Rajasthan State Mines
and Minerals Limited vs. World Engineering
Enterprises and Others, 1999 (9) SCC 283 for the
very same proposition that the award cannot be
against the stipulation in the contract;
8. 2001 (4) SCC 241 Ramachandra Reddy vs. State of
Andhra Pradesh was cited for the proposition that
the escalation in rates of labour and materials can
only be granted on the basis of agreement;
9. He also relied on 2002 (1) SCC 659 State of
Rajasthan vs. New Bharat Construction Company
for the proposition that award of 9% interest for the
period 08.08.1989 to 10.04.1992 and 12% interest for
the future is excessive. He placed strong reliance on
para 8 of the said judgment wherein this Court
reduced the rate of interest from 18% and 15% to 6%
through out;
10. He also drew our attention to the award passed by the
arbitrator, orders passed by the different courts and
also the relevant clauses in the agreement with
reference to the appointment of wages etc.;
11. Concluding his argument, Mr. Mohan submitted that
the High Court has completely erred in not noticing
that the award suffers from the gross errors apparent
on the face of the record and that the arbitrator has
not gone into the evidence as to the amount of
enhanced wages actually paid by the respondent to the
workers and has merely awarded an assumed amount
without giving any reason as to how the amount was
arrived at.
Mr. Anand Padmanabha, learned counsel, made the
following submissions by way of reply to the arguments
advanced by the appellant’s counsel:
1. there is no specific bar to the claim for escalation being
made and that the conduct of the FCI when it requested
the claimant to continue their work would amount to
promissory or equitable estoppel;
2. the claim for escalation is justifiable on the ground that
the claimant could never have anticipated the sudden
wage increase and other statutory obligations imposed by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 12
the Government under any stretch of imagination while
tendering for the work as early as February, 1981. It is
further submitted that the claimant had quoted for the
work based on the then prevailing wages at the time of
tender who by providing them with a marginal increase
for feasibility of execution.
3. The statutory obligation to pay higher wages arose under
the notification published in the Tamil Nadu Gazette
extraordinary published in Part-6 Section 3a dated
01.09.1981 marked as Exhibit-C5.
4. The above claim of unawareness of increase in wages
consequent to Tuticorin being declared as a major Port
entailing higher wages on par with wages being paid to
dock labour in other major ports.
5. Owing to the enormous losses that mounted up, the
claimants had represented the matter to the FCI
reiterating the grave and disastrous monetary losses,
sustained by them and requesting for relief by
neutralizing the increased operational cost and its
payment. Thereafter, the FCI had appointed a series of
committees who had gone into the requests made and
although the committees have recognized the need to
neutralize the increase of extra costs incurred by the
claimants on labour, as it has occasioned by an order of
Government, but to the dismay of the claimant, no
adequate relief was granted by the FCI. Various
representations were made by the claimants to the
official hierarchy of the FCI as early from 07.09.1981,
06.11.1981, 23.12.1981 during the currency of the
contract and thereafter effective persuasion continued
since then. Notwithstanding the fact that the FCI
hierarchy was fully convinced to be just and proper in
neutralizing these losses, it was only marginally met with
by the Zonal Manager (South) who had reimbursed a
paltry sum as an interim relief and recommended for
sanction of appropriate escalation to be granted.
Although the claimants were given the sanguine hope for
their entitlement as genuine and reasonable, no final
decision was taken during the tenure of contract
including extended period of three months which the
claimant was called upon to continue for the storage
operations.
6. Large amounts were expended by the claimants to meet
this extra cost incurred to pay the new wage structure
and additional benefits given to labour as per the
directives of the Government. The unexpected
expenditure incurred by the wage hike, necessitated
immediate requirement of enormous outlay which
crippled the claimants resources. Consequently, the
claimants had to raise additional funds from private
sources at exorbitant interest to meet these
contingencies. Instead of resorting to a cease work out of
frustration in contract by a supervening event which was
not within the contemplation of the parties at the time of
entering into the contract, the claimants had carried on
with the work effectively making enhanced wage
payments in sizable amounts on the strength and faith of
the assurance given by the FCI hierarchy. The huge
expenditure incurred in mobilizing resources at
exorbitant interest to meet the emergent situation had
created additional burden on the claimants by way of
accumulation of interest alone, owing to the indecisions
of the FCI in settling this matter. Therefore, the
claimants have claimed to 10% contractor’s profit or
interest as damages as the case may be on the amounts
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 12
claimed for reimbursement. Ever since 07.09.1991,
various representations submitted by the claimants
seeking redressal of their grievances, the matter
remained pending for want of final decision. Although
the claims of the claimants were justified and had every
reason for granting the same as recommended by the FCI
officials at, different levels, of late, it has been turned
down and denied to the claimants. Therefore, disputes
and differences had arisen between the parties to the
subject contract.
7. The claimants acted upon and carried on the work on the
strength and faith of the assurance given by the FCI to
meet the claimants demand and in the interest of smooth
working of the contract and in order to avoid the
stoppage of work a decision was taken to grant enhanced
rates w.e.f. 01.09.1981.
We have carefully considered the rival submissions with
reference to the records, pleadings, judgments and with
reference to the rulings cited by both the sides.
This Court, while issuing notice dated 13.12.2002 in the
special leave petition passed the following order
"ORDER
Learned Attorney General argues that there is no
clause providing for escalation to reimburse the expenses
incurred by the contractor in the contract agreement. In
spite of the same the Arbitrator has awarded escalation in
expenses.
Issue notice on SLPs as also on the prayer for interim
relief."
In our opinion, the argument of the learned senior
counsel for the FCI that there is no clause in the contract
providing for escalation to reimburse the expenses and,
therefore, the arbitrator had exceeded his jurisdiction has no
substance. The issue of jurisdiction of the arbitrator to go into
the claim of the claimant towards compensation and
neutralization of the extra expenditure incurred on account of
statutory wage revisions had already concluded in the earlier
proceedings arising out of the application filed by the claimant
firm under Section 20 of the Arbitration Act for appointment of
the arbitrator. The FCI in the said proceedings specifically
contended that there was no escalation clause in the contract,
the claim of the claimants for compensation on account of
wage revision should not be referred to arbitration and that
the said claim was non-arbitrable. However, the learned
Subordinate Judge, Tuticorin by order dated 16.02.1987 in
O.P. No. 49 of 1986 rejected the said contention holding that
the said claim was arbitrable. On appeal filed by the FCI
before the High Court the High Court also confirmed the same
by order dated 01.03.1989 in CMA No. 291 of 1987. This
Court also dismissed the special leave petition No. 5213 of
1989 filed by the FCI by order dated 05.05.1989. Thus, the
FCI is barred by res judicata from raising the same issue again
in the present proceedings.
Even on merits, the claimants firm is entitled to be paid
the said compensation, in view of clause 7 of the contract
dealing with payment of wages.
PAYMENT OF WAGES TO WORKERS:
The contractors shall pay not less than minimum wages
to the workers engaged by them on either time-rate basis or
piece rate basis on the work. Minimum wages both for the
time rate and for the piece rate work shall mean the rate(s)
notified by the appropriate authority at the time of inviting
tenders for the work. Where such wages have not been so
notified by the appropriate authority, the wages prescribed by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 12
the Senior Regional manager as minimum wage shall be made
applicable. The contractors shall maintain necessary records
and registers like wage book and wage slip etc., register of
unpaid wages and Register of fines and deductions giving the
particulars as indicated in appendix VI. The minimum wages
prescribed for the time being for piece-rate and time-rate
workers are as indicated below:-
(1) Time Rate
Worker (Male) : Rs.5.50 (Rupees Five and paise fifty
only per day)
Time Rate
Worker (Female) : Rs.5.50 (Rupees Five and paise
fifty only per day)
(2) Piece rate
Workers: Rs.5.50 (Rupees Five and paise fifty only
per day)"
It is also submitted that in the subsequent
correspondence with the claimant firm also the FCI agreed to
pay the expenditure incurred on account of wage revision. In
this regard, the learned Arbitrator after elaborately considering
the correspondence between the parties has found in the
impugned award as follows:-
"Whatever may be the arguments now put forth by the
respondents, from the admitted facts, it is borne out and
evident that the respondents had accepted their
responsibility to compensate the extra expenditure sustained
by the claimants. Having not made any reservations about
its responsibility to neutralize the extra expenditure of the
claimants by enhancing the contract rates, the respondents
had accepted its liability after an exhaustive study of the
matter, including the aspects of the arguments now put forth
by the respondents and finally accorded sanction for
enhancement in the contract rates. Since the relief was
meager and inadequate, the claimants again appealed for the
balance due to them which too was not protested or denied
but on the contrary was acted upon. The respondents
sincerely wanted to know the actual expenditure incurred by
the claimants and its bonafides, for which purpose the
District Officers at Tuticorin were deputed in Oct.81 for
verification of payments vouchers and other relevant records
connected with the discharge of one Vessel prior to
01.09.1981 and one after 01.09.1981. This aspect is very
relevant and has a direct bearing on the issues relating to
claims I & II.
It is borne out from the records and argued by the
claimants that soon after the completion of the claimant’s
contract, the next contract was awarded by the Food
Corporation to a Stevedoring Agency for 1297% ASOR for
port operations alone (vide Ex.C24) as against the claimants’
rate of 397% ASOR for port as well as godown and railhead
operations combined, which was offered prior to the
introduction of the new working pattern and increased wages
in labour rates. According to the claimants, the tenders for
godown operations were separately called for and was
awarded by the Food Corporation at a rate of 777% ASOR
which was the lowest tender received. The percentage and
the figures of this statement submitted by the claimants are
accepted to be correct by the respondents FCI. The
claimants reiterated that this will be ample justification and
testimony to prove and establish the rates that prevailed for
the port operations and godown operations in Tuticorin at
the time of execution of the work by the claimants and
thereafter. The rates are reflected in terms and ASOR by
virtue of the acceptance of these percentage by the Food
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 12
Corporation for the subsequent years’ work obtained as the
lowest offer on the competitive tenders invited by the Food
Corporation. It was also stated that the other users of
Tuticorin Port viz. M/s SPIC and Railways had also accepted
the revised notification as mandatory and binding on all Port
Users being statutory in character and accordingly had
reimbursed the difference by way of escalated rates fully
neutralizing the excess expenditure incurred by its
contractors. The claimants had also produced documents by
way of Exhibits to this effect as certificates issued by the
respective organizations for having reimbursed the difference
of escalated rates. Respondents do not dispute these
aspects, but state that the payment by other Port Users
cannot fasten them with any similar liabilities nor is it
binding on them."
We have carefully perused the award. The award, in our
view, is not vitiated by any error of fact or law on the face of
the record and that the arbitrator has not committed any
misconduct within the meaning of the Act. The High Court
has also in para 19 of the impugned judgment correctly
dismissed the objection raised by the FCI on the issue of
absence of any escalation clause in the contract while
rendering the following finding, Raviraja Pandian,J. speaking
for the Bench, held;
"From the payment of wages clause (Clause 1) of the letters
referred to above and also of the fact that, a committee of the
High Officials of the appellant has been constituted to go in
depth of the factual position as to the payment of wage hike
as per the notification dated 01.09.1981 and the further fact
that, the committee has gone into and submitted a report as
to the actual payment and also the interim payment made by
the appellant would clearly prove that, the appellant had by
the above said actions alive to the circumstance of payment
of enhanced wages considered the just demand of increase of
rates and not stick to his stand that there was no escalation
clause in the agreement and as such the claim of the
respondents not maintainable. Hence, we are of the view
that, the learned counsel for the appellant is not well placed
in the contention that, the arbitrator has mis-conducted
himself and passed an award for escalation of price without
their being any clause for escalation in the contract and the
same has to be rejected and is rejected."
The respondent claimant was awarded the contract for
carrying out the work of clearing, forwarding, stevedoring etc.
from the Ports at Tuticorin for the period and from 08.04.1981
to 07.04.1983. During the currency of the contract w.e.f.
30.08.1981, the wages of the workmen employed in the cargo
handling was sharply increased to almost three-fold
consequent upon the settlement arrived under Section 12(3) of
the Industrial Disputes Act. The State Government notified
the same in the Gazette on 01.09.1981. In view of the
statutory increase in the wages payable to the port labourers,
the claimant made a representation dated 07.09.1981 to the
FCI to revise the rates in respect of the contract besides
pointing out that the Claimant would be constrained to
discontinue the work as the work at the contracted rates
would result in large loss. The claimant again wrote a letter
on 23.12.1981 to the FCI detailing the handling cost in view of
the revised wage pattern and for early order on the
representation. In the said letter, the claimant has also
mentioned that it had offered its explanations on 22.12.1981
to the Committee appointed by the FCI and visited the FCI in
this behalf. The Committee constituted by the FCI made a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 12
report dated 15.01.1982 to the FCI after inspecting the place
of contract and after examining the issue. The said Committee
recommended for allowing the escalated rates specified
therein, supplementing with details. The first respondent
wrote another letter on 19.01.1982 expressing anguish over
the non-grant of relief claimed and inability to carry on the
works from 25.01.1982 as notified in the letter dated
25.12.1982. The FCI in its reply dated 21.01.1982 stated as
follows:
"The Committee’s report is under examination. You are
requested not to bring about any stoppage in the work as
contemplated by you as this will complicate matters."
The claimant was also served a phonogram dated
23.01.1982 which reads thus:
"Your request for escalation of rates is under consideration
of the Zonal Manager. Pending decision, request continue
work without stoppage."
The claimant was acting and carrying on the contract
work without bringing any stoppage of work from 25.01.1982
incurring heavy loss, as it was thus made to believe that it
would be adequately compensated.
While the matter stood so, the FCI appointed Mr.
P.N.Chinnaswamy, Joint Manager, New Delhi to look into the
matters relating to the demand of the contractor for increase
in rates consequent upon the implementation of the
settlement arrived at between the representatives of Port Users
and cargo handling labour in Tuticorin which is effective from
01.09.1981. Mr. Chinnaswamy in his report dated 17.02.1982
under the head "Final Recommendations" stated as follows:
"There is definitely a necessity for escalating the rates of the
present contractors. Contractors were not aware of the
definite shape of matters to take place when they submitted
their tender initially in February 1981. Enhanced rates of
payment have become statutory as the scheme has also been
published in the Gazette consequent upon settlement of
31.08.1981.." He recommended for 962% over SOR for the
operations at New Port and 1108% over SOR for the
Operations at Old Port at Tuticorin instead of 397% ASOR
originally agreed for both the ports."
The claimant did not get any response from the FCI even
after the report of Mr. P.N.Chinnaswamy, a letter dated
24.02.1982 was sent to the FCI that it would become
impossible for the contractor to continue the work if the issue
was not settled as the FCI did not keep the promise that the
issue would be settled by 04.03.1982.
The FCI by its letter dated 28.03.1982 communicated the
contractor as follows:
"With reference to your telephonic information given, that
you will be stopping the work from Monday the 29th March,
1982 at the port and at Godowns in the absence of a
decision on your demand for escalation of rates, please be
informed that, our Regional office at Madras have already
taken up the matter with Head Office, New Delhi and a
decision is awaited. In the meantime please arrange to
continue the work at the port as well as at the godowns
without any interruption."
However, the FCI by its letter dated 13.04.1982 accorded
sanction of 488% of ASOR instead of 397% ASOR in relation to
old port operations and which would workout to an increase of
91% only and 430% of ASOR instead of 397% of ASOR for the
operations at new port and which would come to an increase
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 12
of 31% only .
The claimant accepted the same under protest and
without prejudice by its letter dated 17.04.1982 and requested
the FCI, New Delhi for review of the decisions of the above
grant of marginal relief.
It is seen from the records that the contract period was
from 08.04.1981 to 07.04.1983 for a period of two years.
Wage revision came into effect from 01.09.1981. From
07.09.1981 to 28.02.1984, the contractor made various
representations during the currency of the contract. The FCI
did not allow the contractor to discontinue the contract work
during the currency of the contract promising that the revision
of wages is under their consideration. It is stated by the
contractor that they had handled about 1.68 lacs metric tones
of foodgrains at both the ports incurring huge loss and after
the contractor had completed the performance of the contract
the FCI by its letter dated 14.03.1984 informed the contractor
that the request for escalation of rates had not been agreed to
by their Head Quarters, New Delhi which compelled the
contractor to approach the court for redressal of its
grievances.
The Corporation had raised a specific question before the
arbitrator that escalation in rates claimed by the contractor
could not be granted for the simple reason that the agreement
did not provide for any grant of the escalated rates during the
tenure of contract and hence no enhanced rates other than
the rates agreed upon can be granted. The learned arbitrator
specifically rejected the above contention on the basis of the
subsequent acceptance of responsibility by the FCI.
In our view, the arbitrator has not mis-conducted himself
and that the award has been passed in consonance with the
principles of natural justice. The High Court of Madras has
also upheld the award of arbitrator rightly holding that there
is no error apparent on the face of the record.
As already noticed, the subject matter relates to the
performance of the contract between the periods from
08.04.1981 to 07.04.1983. Now that 23 years and odd had
already elapsed since the contract period and that the
contractor is being prevented by the FCI to receive the monies
spent by him as awarded by the arbitrator. It is also seen
from the records that the quantum claimed by the
respondents was never disputed by the FCI and it is an
admitted fact that the wage revision came into force w.e.f.
01.09.1981 and the contractor firm had paid the workers
revised wages from 01.09.1981.
It was argued by Mr. Mohan that the award of interest
@9% for the period 08.08.1989 to 10.04.1982 and 12% for the
future is excessive and in support of the said contention 2002
(1) SCC 659 was relied on. During the pendency of the appeal,
this Court while granting special leave directed the FCI to
deposit 50% of the awarded amount which cannot be
withdrawn by the respondent-contractor. It is stated in the
I.A. Nos. 4-6 of 2003 that the FCI had deposited only a sum of
Rs.39,97,362/- on 22.08.2003 which is 50% of the principal
amount in the award and that the FCI had not deposited 50%
of the total amount awarded which includes the principal
amount of Rs.79,94,724/- and interest @ 9% p.a. from
08.08.1989 till date of publication of the award i.e. 10.04.1992
and future award @ 12% p.a. till the date of realization.
Therefore, an application was moved to pass appropriate
orders directing the FCI to deposit the balance of the amount
as per the directions of this Court dated 25.07.2003. In
clarification of the order dated 25.07.2003, this Court directed
the FCI to deposit half of the amount awarded by the
arbitrator with interest and permitted the contractor to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 12
withdraw the said amount on furnishing bank guarantee of a
nationalized bank to the satisfaction of the Registrar of this
Court. 3 months time was granted for depositing the amount.
Pursuant to the Court’s order, an amount of
Rs.1,04,10,664/- has been deposited and kept in FD and the
same is renewed from time to time. Accordingly, the amount
has been released to the contractor on their submitting the
bank guarantee to cover the entire amount. However, it was
alleged that the bank guarantee submitted on 12.08.2005 has
since expired on 15.08.2006 and that the contractor has not
taken steps to submit fresh bank guarantee to cover the
amount. The contractors are liable for the consequences
thereof. In the circumstances, the FCI prayed for a direction
to produce fresh bank guarantee or to renew the existing bank
guarantee so that the amount is secured as per the directions
of this Court. On 31.08.2006, the Contractor filed extended
bank guarantee and the validity of the same is up to
15.02.2007.
Two judgments of this Court on escalation and legal
misconduct of the arbitrator can be beneficially referred to,
followed and applied to the case on hand.
The first judgment is in Hyderabad Municipal
Corporation vs. M. Krishnaswami Mudaliar & Mudaliar &
Anr., (1985) 2 SCC 9. The only question argued by the
counsel for the Hyderabad Muncipal Corporation was that the
respondent contractor was not entitled to claim 20% extra over
and above the rates originally agreed upon between the parties
under the contract. Under the contract, drainage work in
question was entrusted to the respondent and under the terms
of the contract the work was to be completed by the contractor
within a period of one year. Admittedly, at the instance of the
Executive Engineer, PWD due to financial difficulties \026 less
budget having been provided for in the year in question,
therefore the respondent-contractor was requested to spread
over the work for two years more that is to say to complete the
same in three years but the contractor was agreeable to
spread over the work for two years as suggested on condition
that extra payment will have to be made to him in view of
increased rates of either material or wages. The Government
did not intimate to the contractor that no extra payment on
account of increased rates would be paid to him or that he will
have to complete the work on the basis of original rates. In
fact, no reply was sent by the Government and a studied
silence was maintained by the Government in regard to the
contractor’s demand for extra payment, in spite of several
reminders in that behalf, till the contractor actually completed
the work during the spread over period. After completion of
work, the contractor submitted his final bill claiming 20%
extra over and above the rates originally agreed upon between
the parties. The Government stated that he was not entitled to
increased rates. The High Court, after considering the
correspondence exchanged between the parties has taken the
view that the government was liable to make extra payment for
the work done as there was no dispute that the rates of
material, etc. had increased during the extended period of two
years and the contractor was entitled to such extra payment.
This Court, after considering the relevant material on record,
was also of the view that both in equity and in law the
contractor is entitled to receive extra payment and the High
Court was right in deciding the question in contractor’s favour.
This Court held that the liability to make this extra payment
has been properly saddled on the Municipal Corporation.
The second judgment is in P.M. Paul vs. Union of India,
AIR 1989 SC 1034. In this case, the dispute that was referred
to the arbitrator was as to who is responsible for the delay,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 12
what are the repercussions of the delay in completion of the
building and how to apportion the consequences of the
responsibility. The arbitrator found that there was escalation
and, therefore, he came to the conclusion that it was
reasonable to allow 20% of the compensation under the claim.
He accordingly allowed the same. Counsel appearing for the
Union of India submitted before this Court that the arbitrator
had granted a sum of Rs. 2 lakhs as escalation charges and
cost in the absence of escalation clause was not a matter
referred to the arbitrator. In other words, it was urged that
the arbitrator had traveled beyond his jurisdiction in awarding
the escalation cost and charges. This Court in paragraphs 11
& 12 of the judgment held thus:
11. It is well-settled that an award can only be set
aside under Section 30 of the Act, which enjoins that an
award of an arbitrator/umpire can be set aside, inter alia, if
he has misconducted himself or the proceeding. Adjudicating
upon a matter which is not the subject-matter of
adjudication, is a legal misconduct for the arbitrator. The
dispute that was referred to the arbitrator was, as to who is
responsible for the delay, what are the repercussions of the
delay in completion of the building and now to apportion the
consequences of the responsibility. In the objections filled on
behalf of the respondent, it has been stated that if the work
was not completed within the stipulated time the party has
got a right for extention of time. On failure to grant extention
of time, it has been asserted, the contractor can claim
difference in prices.
12. In the instant case, it is asserted that the
extension of time was granted and the arbitrator has granted
20% of the escalation cost. Escalation is a normal incident
arising out of gap of time in this inflationary age in
performing any contract. The arbitrator has held that there
was delay, and he has further referred to this aspect in his
award. The arbitrator has noted that Claim I related to the
losses caused due to increase in prices of materials and cost
of labour and transport during the extended, period of
contract from 9.5.1980 for the work under phase I, and from
9.1 1.80 for the work under phase II. The total amount
shown was Rs. 5,47,618.50. After discussing the evidence
and the submissions the arbitrator found that it was evident
that there was escalation and, therefore, he came to the
conclusion that it was reasonable to allow 20% of the
compensation under Claim I, he was accordingly allowed the
same. This was a matter which was within the jurisdiction of
the arbitrator and hence, the arbitrator had not
misconducted himself in awarding the amount as he has
done.
The above two cases, in our opinion, squarely apply to
the facts and circumstances of the case on hand.
Escalation, in our view, is normal and routine incident
arising out of gap of time in this inflationary age in performing
any contract of any type. In this case, the arbitrator has
found that there was escalation by way of statutory wage
revision and, therefore, he came to the conclusion that it was
reasonable to allow escalation under the claim. Once it was
found that the arbitrator had jurisdiction to find that there
was delay in execution of the contract due to the conduct of
the FCI, the Corporation was liable for the consequences of the
delay, namely, increase in statutory wages. Therefore, the
arbitrator, in our opinion, had jurisdiction to go into this
question. He has gone into that question and has awarded as
he did. The Arbitrator by awarding wage revision has not mis-
conducted himself. The award was, therefore, made rule of
the High Court, rightly so in our opinion.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 12
In our opinion, having considered the totality of the
circumstances, we feel that it would be just and proper to
award interest @9% p.a. throughout instead of 12% as
awarded by the arbitrator for the period in question. The
amount already received by the claimant will be adjusted
towards the entire claim and the balance amount together
with interest at 9% p.a. shall be paid by the FCI within 2
months from the date of this order failing which the said
balance amount shall carry interest @12% from the date of its
due till realization. In view of this order in this judgment, the
bank guarantee furnished by the respondent-contractor shall
stand discharged. The Supreme Court Registry is directed to
do the needful immediately.
The impugned judgment of the High Court is modified
accordingly. The appeals are thus partly allowed as above
leaving the parties to bear their own costs.