Full Judgment Text
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.9845-9846 OF 2016
M/S. INDSIL HYDRO POWER AND
MANGANESE LIMITED …APPELLANT
VERSUS
STATE OF KERALA AND OTHERS …RESPONDENTS
WITH
CIVIL APPEAL NOS.9847-9850 OF 2016
J U D G M E N T
Uday Umesh Lalit, J.
1. Civil Appeal Nos.9845-9846 of 2016 preferred by M/s Indsil Hydro
Power and Manganese Limited (hereinafter referred to as “INDSIL”) and Civil
Appeal Nos.9847-9850 of 2016 preferred by Carborundum Universal Limited
(hereinafter referred to as “CUMI”) are directed against the common judgement
Signature Not Verified
1
and order dated 03.04.2014 passed by the Division Bench of the High Court
Digitally signed by
Indu Marwah
Date: 2021.09.06
18:14:00 IST
Reason:
1
The High Court of Kerala at Ernakulam.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
2
allowing Writ Appeal Nos.1345 and 1355 of 2013 preferred by State of Kerala
against INDSIL and CUMI respectively.
2
2. On 07.12.1990, the Government framed a policy vide
G.O.(MS)No.23/90/PD (the Policy, for short) allowing private agencies and
public undertakings to set up hydel schemes for generation of electricity at their
own cost. As per the Policy, the matters concerning the construction, operation
and maintenance of the hydel scheme were to be managed as per the
3
stipulations made by the Government/Board . Clauses 2, 14 and 15 of the
Policy were as under: -
“ 2 . Private agencies/ public undertakings shall be allowed
the setting up of sanctioned hydel schemes of the category
small/ mini/ micro at their own cost, the construction,
operation and maintenance being managed by them as per
the stipulations insisted upon by Government/ Board. (The
stipulated conditions as per Indian Electricity Act, 1910.
Electricity (Supply) Act, 1948, other related rules and orders
from Central and State Governments).
14 . Royalty for the use of water together with the tax and
duties on generation of power as fixed by
Government/Board from time to time have to be paid by the
agency.
Normally generation of power from schemes of the category
small/mini/micro utilizing the storage benefits of existing
reservoirs and tailrace benefit of existing power stations will
2
The Government of Kerala
3
Kerala State Electricity Board
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
3
not be entrusted with private agencies. But, Government
may under special circumstances allow such schemes to be
set up by private parties. In such cases, in order to account
for the additional advantage gained by the agency by way of
getting the Controlled releases, the agency will have to pay
to Government or the Board, as the case may be, in tariff
equivalent to the cost component for the controlled release
utilized by the agency for the energy generated from the
scheme. This will be in addition to the royalty of water if
any, to be paid. The tariff storage/controlled release as
above are to be worked out in respect of each scheme
separately taking into account the above factors.
15 . For assessment of water quantity used, the application
of the formula BH-Power in KW where Q is in NI/Sec and
H is the net head in meter for which the machines are
designed by the manufacturers, will be made use of.”
3. CUMI has three factories in State of Kerala and is in the business of
manufacturing electro minerals using electric arc furnaces, which process
requires continuous supply of electricity. CUMI filed an application with the
State for allotment of “Maniyar Hydel Scheme” in the River Kakkad Basin.
After the Scheme was allotted vide order dated 18.01.1991, CUMI undertook
to establish the Maniyar Hydro Electric Project with 12 MW capacity on River
Kakkad, as a Captive Generating Station for its industrial units. An Agreement
was entered into between CUMI and the Board on 18.05.1991 (CUMI
Agreement for short), which specifically referred to the Policy and stated that
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
4
the terms and conditions of the Policy “shall form part of this agreement as if
incorporated herein”. Clauses 8 and 14 of CUMI Agreement were as under:-
“ 8 . The energy from Maniyar Hydro Electric Project fed into
the K.S.E.B. Grid will be metered at a location as detailed
above (using meter duly calibrated by K.S.E.B.) and this
quantum of energy less twelve percent towards wheeling
charges and T & D Lesses will be delivered free of cost to
CUMI at their E.B.T. Terminate at the point of supply in their
installations. In the case of supply or receipt made in LT Lines
the allowance for lessee and wheeling charges will be more and
will be as stipulated by the KSEB.
In case energy in excess of the requirement of CUMI is
generated from the projects during one accounting year such
excess energy shall be fed into the KSEB grid itself at rates to
mutually agreed upon. Under no circumstances shall CUMI be
entitled for the sale or transfer of any excess energy or any
energy produced from the project to any party other than the
KSEB. The accounting of the energy fed into the grid and
supplied by KESB to CUMI or operating their factories in
Kerala at Palakkad, Koratty and Kalamaooery will be settled
on an annual basis, the year being reckoned from lot of July to
th
30 June.
… … …
14 . Royalty for the use of water together with the tax and
duties on generation of power as fixed by govt/KESB from time
to time have to be paid by CUMI, to K.S.E.B.
Maniyar Hydro Electric Projects will utilize the existing head
works benefit of the Maniyar Irrigation Dam of P.W.D. which
is fed mainly by the controlled release of water from existing
Moozhiar Power House of KSEB. In order to account for the
additional advantage gained by way of getting such controlled
released, CUMI will have to pay to KSEB the cost components
for the energy generated from the scheme. This will be in
addition to the royalty on water to be paid. The charges for
controlled release as above as well as royalty on water, will be
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
5
reckoned on the quantum of energy generated and shall be ten
percent of energy tariff rate for E.H.T. consumer current from
time to time for every unit of energy generated and shall be paid
to the K.S.E.B.”
4. By 1994 the Project was commissioned by CUMI at a cost of Rs.22
crores and since then CUMI has been generating electricity which is used for
self consumption in terms of CUMI Agreement.
5. INDSIL has a factory in the State for the manufacture of Ferro Alloys
and was availing supply of electric energy from the Board.
6. INDSIL having expressed interest in setting up a small hydel scheme,
due negotiations and meetings were held. In a meeting held with the Board on
08.04.1994, one of the decisions was :-
“ i) Royalty to be charged on water – It was decided that
Irrigation Dept. will be requested not to charge the cess or
royalty especially where water is being retained in the same
basin and there is no consumptive use.”
7. An Agreement (INDSIL Agreement, for short) was thereafter entered
into between INDSIL and the Board on 30.12.1994 for setting up “Kuthungal
Phase I and II Project” in Idukki district of the State with 21 MW installed
capacity for generation of electricity. INDSIL Agreement referred inter alia to
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
6
the terms and conditions set out in the Policy and stated that said terms and
conditions “shall form part of this Agreement as if incorporated herein.”
Clauses 10 and 19 of INDSIL Agreement were to the following effect: -
“ 10 . The energy from KUTHUNGAL PHASE I AND
PHASE II project fed into the KSEB grid will be metered,
at a location as detailed above (using meter duly calibrated
by KSEB) and this quantum of energy less 12% (Twelve
percent) towards wheeling charges and T & D losses will be
delivered free of cost to the company and their associate
M/s. Sun Metals & Alloys Pvt. Ltd., Kanjikode, Palaghat at
the EHT Terminals at the point of supply in their
installations if any, or it will be banked by the KSEB if the
company so desires. The KSEB will collect 1% (One
percent) of the energy so banked as its commission. This will
be in addition to wheeling and loss towards transmission and
distribution charges.
… … …
19 . Cess/ Royalties for use of water, if decided by the
Government together with tax/ duties as fixed by the
Government from time to time shall be paid by the company
to Government.”
8. Since the setting up of the project by June, 2001 at a cost of Rs.50
crores, INDSIL has been generating electricity which is essentially used by it
and its associates as stated in Clause 10 of INDSIL Agreement.
9. The respective projects were thus set up by CUMI and INDSIL for
Captive Power Consumption and such producers of electricity for own
consumption are called Captive Power Producers (CPP) as against Independent
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
7
Power Producers (IPP) who generate electricity not for self consumption but
for supply in its entirety to the Board.
10. On 11.10.2002, Guidelines were issued by the Government after noting
the Policy and the recommendations of the Empowered Committee set up vide
G.O. dated 5.9.2002. These Guidelines dealt with transmission and distribution
losses in wheeling the energy to CPPs but did not deal with royalty for the use
of water. The relevant portion of these Guidelines was: -
“The Empowered Committee constituted as per the GO read as
rd
3 paper above, to oversee the implementation of the reforms
of the KSEB and to examine the details for the erection of Small
and Mini Hydel Projects, in its meeting held on 5.9.02 and
12.09.02 considered the scope for taking small hydel projects
and recommended to Government that the small hydel projects
excluding dam toe and tail race projects should be opened up
for captive consumers and Independent Power Producers
including public sector undertakings and also made the
following recommendations:-
1. The Public Sector undertakings and the power intensive
industries within the State may be given preference in allotment
of the small hydro projects.
2. The allowance to KSEB to compensate the T & D loss in
wheeling the energy from generating station to the
consumption point of Captive Power Producers (CPPs) which
has been fixed at 10% as per clause (9) of the G.O. (MS)
No.23/90/PD dt.7.12.90 may continue to be allowed to KSEB.
3. Wheeling charges to KSEB which has been fixed at 2% as
per clause (9) of G.O. (MS No.23/90/PD. dt. 7.12.90 may be
increased to 5%.”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
8
11. The Guidelines were revised vide G.O. dated 16.1.2003 which dealt
with CPPs and IPPs. As regards CPPs the revised Guidelines stated: -
“…… As per G.O. (MS) 23/90/PD dt.7.12.1990,
Government laid down terms and conditions for allotment
of small hydel projects. Since the Government proposes to
invite more private participation in this sector, it has become
necessary to prescribe revised guidelines for allotment.
Power schemes utilizing controlled releases form the
existing reservoirs and tailrace are reserved for KSE Board.”
Nothing was specified with regard to the royalty for the use of water by
CPPs but while dealing with IPPs, it was stipulated: -
“… 15 . Water Cess: Water Cess not required since, it will
reflect on tariff and hence not investor friendly.”
12. Both CUMI and INDSIL have been paying wheeling charges for
consumption of electricity. Right from 1994 till April 2003, CUMI had also
paid charges for the use of controlled supply of water at the rate specified in
Clause 14 of the CUMI Agreement. In May 2003, CUMI however made a
representation that it be exempted, like other projects from payment of such
charges. Attempts on part of the Board to charge royalty/cost component for
controlled release of water from CUMI and INDSIL in terms of clause 14 of
the Policy has led to the disputes in the instant matters which are subject matter
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
9
of these appeals. Before we set out the pleadings pertaining to such disputes,
the locations of the respective Projects and what kind of flow of water is used,
must be noted:-
CUMI: The water flowing down from Moozhiyar Power House of the
Board is diverted to the Kakkad Power House (50 MW) of the Board for
generation of electricity using “tail race” benefit of Moozhiyar Power House.
After power generation at the Kakkad Power House, the water is allowed to
flow back into the river and is then utilized for irrigation and for the Maniyar
Hydro Electric Project of CUMI.
INDSIL: Anayirankal Dam, one of the largest earthen dams in State of
Kerala was built in the 1960s and soon thereafter, the Paniyar Power House
having capacity of generating 32 MW electricity was built by the Board.
Kuthungal is situated in between Anayirankal Dam (at the higher altitude) and
Paniyar Power Station of the Board (at the lower level). Thus the water released
from Anayirankal Dam for generation of electricity at Paniyar Power Station
passes through the area where the project of INDSIL is situated.
13. CUMI filed O.P. No.6880 of 2003 praying, inter alia, that the Board
had no authority to levy, demand or collect any charges for controlled release
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
10
of water or royalty from CUMI in respect of electricity generated by it at its
Maniyar Hydel Project. The necessary pleadings from the writ petition were:
nd nd
“ 2 . … … The 2 respondent Board had set up its 2 largest
Hydro-Electric project of Sabirigiri on River Pamba. The
nd
waters of the said river were utilized by the 2 respondent
Board for generating electricity at Moozhiyar Generating
Station and part of the water flowing down from Moozhiyar
Generating Station after generation of electricity was being
utilized for irrigation purpose and rest of it is flown down to
Arabian Sea. Part of the water flowing from the Generating
Station at Moozhiyar is utilized also for generating
electricity at Maniyar Hydro Electric Project which was
taken up by the petitioner as a captive generating station for
the petitioner’s industrial units at Kalamassery and Koratti
to meet part of its requirements. …… Petitioner had no
option but to sign the agreement stipulated by the
respondents and was compelled to sign the same.
3. … … Apart from unconstitutional impost the method of
imposition and rate of royalty and alleged controlled release
of water is totally irrational, arbitrary and unfair. The
royalty can only be based on the quantity of material or
benefit consumed by a person from the facility.
4. … … It is submitted that water required for generating
electricity at the Mooziyar Power House is a fixed quantity
based on the capacity of the turbine and whatever water is
required for such generation has to flow down from the
turbine. There is absolutely no controlled release of such
water to the petitioner’s Hydro-Electric Project at Maniyar
in Kakkad river. The water flowing down from Moozhiyar
Power House supplemented by water from the catchman
area of river banks below the Moozhiyar Power Station was
partly utilized for irrigation purpose and the remaining water
flows down earlier, it was only part of such water from
Moozhiyar Power Station and from catchman areas that is
utilized for generation of electricity by the petitioner at its
Maniyar Hydel Project. However, from the year 1998 the
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
11
water flowing down from Moozhiyar Power House was
nd
diverted to the Kakkad Power House of the 2 respondent
and after generation of electricity at Kakkad Power House
the water flowing down flows back to the same river at a
lower stage and utilized for irrigation and partly for the
petitioner’s Maniyar Project. It is submitted that the water
released from Moozhiyar Power House is thus diverted to
Kakkad Power House and utilized for power generation
there. The alleged controlled release of water from
Moozhiyar Power House to the petitioner’s hydel project at
Maniyar is no longer there and has ceased to be available to
the petitioner after commissioning of the Kakkad Power
nd
Station by the 2 respondent. It is therefore submitted that
nd
the 2 respondent cannot in any manner charge or collect
the so-called cost component for controlled release of water
from Moozhiyar Power House since there is no such release,
much less controlled release of water from Moozhiyar
Power House to the petitioner after 1998. Petitioner submits
that in any event the charge and collection of cost component
from the petitioner after 1998 is totally without authority of
law, arbitrary, illegal and unfair.
5 . … … There is no provision in the Electricity Supply Act
nd
conferring any power on the 2 respondent to impose
royalty or any charges on generating company which have
the same powers, duties and functions for the flow of water
in river Pamba or its tributaries.
6 . Petitioner submits that the respondents have granted
permission and rights to several other generating companies
like the petitioner to set up small hydel projects. Thus
private industrial generating companies like INDSIL
Limited, Silcal Metallurgic Limited TECIL Hydro Power
Limited had all set up private hydro-electric stations in
which the respondents have not subjected them to any
royalty or alleged cost component of released water form the
Hydro-electric projects upstream on the respective rivers.
Petitioner submits that the respondents have singled out the
petitioner and subjected the petitioner to discriminatory
charges.”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
12
14. In the counter affidavit filed on behalf of the Board, the assertions made
by CUMI in the writ petition were denied. It was submitted:
“ 2 …… In the Ext.P1 Government Order dated 07.12.1990,
it is clearly stated in Clause 21 that before implementation
of the scheme, an agreement setting forth all the aspects in
the Government Order and such conditions as found
necessary will be entered into between the agency on the one
part and the KSE Board/Government on the other. Hence
nd
the allegation of the petitioner that the 2 respondent has no
authority of law or competency to stipulate or impose any
conditions or agreement is not true. Moreover, the
respondents have not compelled the petitioner to sign the
agreement and hence the allegation in this regard are not true
and hence denied. The petitioner has applied for the captive
generation station in pursuance of the Ext.P1 Government
Order dated 07.12.1990 and the Government have granted
permission strictly in accordance with stipulation in the
above said Government Order. Having executed the
agreement and setting up the plant the petitioner cannot now
turn around and say that the conditions were thrust upon him.
3 ……. The KSE Board had to construct and maintain dams
and reservoir for collection of water by investing crores of
rupees. The water stored in the dam is released periodically
and controlled release of water is effected by the Board to
the petitioner licensee. So the petitioner is getting sufficient
water for generating power regularly as per their
requirement without any capital investment for storage of
water. …….. It is further stated that normally generation of
power from schemes of the category small/mini/micro
utilizing the storage benefit of the existing reservoir and
tailrace benefit of existing power stations will not be
entrusted with private agencies. But Government under
special circumstances allowed such schemes to be set up by
private parties. In such case, in order to account for the
additional advantage gained by the agency by way of getting
the controlled release, the agency will have to pay to
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
13
government or the Board, as the case may be, in tariff
equivalent to the cost component for energy generated from
the scheme. This will be in addition to the royalty of water
if any, to be paid. The tariff storage/controlled release as
above are to be worked out in respect of each scheme
separately taking into account the above factors.
5. It is submitted that from the year 1998, the water flowing
down from Moozhiyar Power House is collected in the
nd
reservoir of Kakkad Power House of the 2 respondent and
after generation of electricity at Kakkad Power House the
water flowing down to the same river and to the reservoir of
the petitioner’s Maniyar Project. Thus, the water released
from the Moozhiyar Power is further controlled at Kakkad
Power House. Maniyar Project thus runs with the controlled
release of water from the Kakkad Power House which was
commissioned after setting up of the Maniyar Hydro Electric
Project. Water utilized for generation in their project is from
absolute controlled release if it was either from Moozhiyar
Power House or later on form Kakkad Power House and
hence the allegation that charge and collection of cost
compound from the petitioner after 1998 is totally without
authority of law, arbitrary, illegal and unfair is baseless and
untenable.”
15. In its rejoinder to the aforestated counter affidavit, CUMI submitted:
6. … … Whatever quality of water used at the Kakkad
Power House can only flow down and cannot be prevented
nd
by the 2 respondent from flowing down. There is no
question of controlling the water that has to flow down from
the power house to the river. In addition to the water flowing
down that Kakkad Power Station large quantity of water
flows into the river from the river banks flooding the river
during heavy rains and there is no control on the flow of
water to the petitioner’s Maniyar generating station, which
is about 6 kms. downstream from Kakkad generating
station.”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
14
16. On 03.07.2004 an order was issued by the Government that in terms of
Clause 19 of INDSIL Agreement, INDSIL would be liable to pay royalty and
cost of controlled release of water. The order stated:
“The Kuthungal HEP (21 MW) is a CPP implemented by
M/s INDSIL. The project utilizes the water available from
the free catchment between Anayirankal Dam and
Kuthungal weir as well as the controlled releases from
Anayirankal Dam.
The Maniyar HEP (12 MW) the first CPP owned by M/s.
Carbourandum Universal utilizes the controlled releases
from Sabarigiri and Kakkad Hydro Electric Project of
KSEB. The royalty for this project is being charged at the
rate of 10% of the energy tariff rate for EHT Consumers and
is paid to KSEB.
Government after detailed examination hereby order that the
royalty and cost of controlled release of water to the
Kuthungal HEP shall be reckoned on the quantum of energy
generated and shall be 10% of the energy tariff rate for EHT
Consumers current from time to time for every unit of
energy generated and in addition, the Company is liable to
pay 1.2 paise per unit as electricity duty for each unit of
electricity generated in accordance with the provision of the
Kerala Electricity Duty Act.
The Chief Electrical Inspector shall collect the royalty from
the company and remit it to the State revenue.”
17. INDSIL challenged the order dated 03.07.2004 by filing Writ Petition
(C) No.22187 of 2004 in the High Court. The Writ Petition was however
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
15
withdrawn with liberty to make an appropriate representation to the
Government. This led to some correspondence and representations from
INDSIL. The Government, however, refused to recall its decision to recover
royalty and cost of controlled release of water, which was communicated vide
order dated 23.01.2008. The action on part of the Government was challenged
by INDSIL by filing Writ Petition (C) No.4596 of 2008 in the High Court.
18. With regard to the use of controlled water INDSIL submitted:-
“ 11 . Kuthungal is situated between Anayriankal at the higher
end and Ponmudi at the lower end. Paniyar power station at
Vellathooval has a capacity to generate 30 MW of power.
The said power station funcitons on water flowing across
Paniyar river. There are two storages maintained by the
KSEB for its Paniyar Power Station. One is at Ponmudi and
other is at Anayirankal which is situated at a height of 1850
Meters above the sea level. As submitted above, there is a
reservoir at Anayirankal where the water is stored. Water
stored in the Anayirankal reservoir is released by the KSEB
during the peak summer months between January and April
for the generation of power at Paniyar Power Station. This is
done normally for a period of about 45 days out of the afore
mentioned three/four months from January to April such
release of water by the KSEB from Anayirankal is dictated
by the requirement in Paniyar Power Station at Vellathooval;
commencement of the releases is decided by the KSEB;
quantum of water is controlled by the KSEB and determined
by the rquirements in Paniyar Power Station. Cessation of
release is also decided by the KSEB to sit the requirement of
Paniyar Power Station. As submitted above, Kuthungal
Hydro Electric Project is situated at Kuthungal which is at a
lower level than Anayirankal but higher than Paniyar Power
Station.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
16
… … …
When there is a release of water from the Anayirankal
Reservoir to enable generation of power at Paniyal Hydro
Electric Station at Vellathooval, petitioner company is also
enabled to utilize the said water for diversion into Kuthungal
Hydro Electric facility for generation of power there from.
This is done only for a period of about 45 days during the
peak summer months and controlled release of water from
Anayirankal is effected by the KSEB only in accordance
with its own schedule to suit its own requirement of
generation of power at Paniyar Hydro Electric Station and
such release of water is not simply done to suit the
requirement of petitioner or to bring about any advantage to
the petitioner as such.”
Seeking to draw distinction between the project of CUMI and that of
INDSIL, it was stated:-
“ ….the agency under Exhibit-P2 agreement is dependent on
the controlled release of water from Sabarigiri and Kakkad
Hydro Electric Project. Such controlled release, quantum of
release and cessation of same are all made suited to the
requirement of the project in question. Release of water was
utilized by Messrs Carboradum Universal Limited for the
purpose of generating power in the Maniyar Hydro Electric
Project. Water released from Sabarigiri and Kakkad Power
Project are controlled releases. This is totally unlike in the
case of the petitioner where the actual release of water from
Anayrankil is in the manner mentioned above.”
19. The reply given on behalf of the Government to the petition by INDSIL
was:-
“ 9 . … … In fact, the scheme envisages utilization of
controlled release from Anayirankal reservoir in addition to
water from 114 sq.km., free catchment downstream of the
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
17
dam as per the detailed project report prepared by KSEB in
August, 1991. The petitioner had also made their own
assessment as per the techno economic feasibility report
submitted by them. As already mentioned, the scheme
envisages utilization of water from 114 sq.km. of free
catchment downstream of existing Anayirankal reservoir
drained from a catchment of 65 sq. Km for power generation
as per the detailed report mentioned above. The averment
and allegations in paragraphs 10 and 11 of the writ petition
are not fully correct and hence denied. The description of the
project of the petitioner given in the said paragraph
explaining that is designed as a “run of the river” scheme
does not deny the fact that it is using the water released from
Anayirankal reservoir for the months from January to April.
It is true that the release of water from Anayirankal reservoir
is mainly decided based on the generation requirements at
the Panniyar Power Station. However, this water when
released is being utilized at Kuthunnal for power generation.
The entire water after power generation flows down to
Ponmudi reservoir without any depletion of quantity of
water which is the case in every hydro electric project. The
petitioner’s contention that the release of water from
Anayirankal reservoir is not done in order to suit the
requirement of the petitioner but in accordance with the
requirement of Panniyar Power Station is in correct. In fact,
the petitioner Company is getting the full advantage of
power generation from the release of water from
Anayirankal reservoir in the peak summer months.
… … …
12 . … … Even though the controlled release of water from
Anayirankal reservoir is made to suit the requirement of
power generation at Panniyar, it is also utilized for power
generation at Kuthungal Hydro Electric Project. It is to be
noted that the power generation from the Kuthungal Project
was comparatively high when there is water releases from
the Anayirankal reservoir, which would otherwise have been
negligible if water from Anayirankal reservoir is not
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
18
released. During this period a total generation was 266.69
MU and generation from controlled released is 60.12 MU,
which is about 22.54% of the total generation. During the
drought year of 2002-03, 50% of the total generation from
the project was during summer months utilizing water
release from Anayirankal. The above facts clearly
establishes that the petitioner is a beneficiary of the
controlled release of water from Anayirankal.”
20. Writ Petition (C) No. 4596 of 2008 preferred by INDSIL was allowed
by the Single Judge of the High Court by his judgment and order dated
15.02.2013. It was observed that the action on the part of the Government was
discriminatory, as all CPPs with the exception of CUMI were not subjected to
such royalty. The explanation offered that CPPs and IPPs stood on different
footings was not accepted. It was concluded that there was no jurisdiction to
recover any royalty or cess and accordingly the order dated 03.07.2004 was
quashed.
21. O.P. No.6880 of 2003 preferred by CUMI was allowed by the Single
Judge of the High Court by his judgment and order dated 03.04.2013 with
following observations :
“Even though in W.P.(C) No.4596/2008, I have given some
findings against the petitioner, in view of my findings in
Paragraphs 36 to 41 and 51 to 53 of the said judgment, I
allow this writ petition and set aside the impugned order,
Annexure P-3 holding that the Government is devoid of
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
19
jurisdiction to realize any amount from the petitioner by way
of Royalty or other charges on the water used for the
Maniyar Hydel Project. In the circumstances, there will be
no order as to costs.”
22. The decisions of the Single Judge in the matters of INDSIL and CUMI
were called in question by the Board by filing Writ Appeal Nos.1345 of 2013
and 1355 of 2013 respectively before the Division Bench, which appeals were
allowed by the Division Bench vide its common judgment and order dated
03.04.2014.
The judgment of the Division Bench comprises of two parts: the first
part dealt with the case of INDSIL; while the second part considered the case
of CUMI.
22.1 After considering some of the decisions of this Court, it was held that
after entering into an agreement, a party would be estopped from disputing its
liability in terms of the agreement. With regard to the submission based on
discrimination, the Division Bench observed:-
“ 24 . The first ground on which the learned single Judge has
interfered with Ext.P11 is that it violated Article 14 of the
Constitution of India which prohibits discrimination. The
judgment shows that according to the learned single judge,
st
the distinction between 1 respondent’s Hydro Electric plant
and others on the basis that the former is a CPP and the latter
is an IPP, is an artificial one and has no object that is sought
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
20
to be achieved by it. In our view, this conclusion of the
learned single Judge has no basis. As we have already seen
st
the Hydro Electric Project of the 1 respondent is a Captive
Power Plant, which is meant only to cater to their own
requirement of electrical energy at their factory in Palalkkad.
Therefore, generation at CPP does not involve any sale
either to the Electricity Board or to anybody else. On the
other hand, the remaining power plants, except the one
established by M/s Carborandum Universal Limited, are
Independent Power Plants which have entered into power
purchase agreements with the KSB on the basis of which the
entire power generated is purchased by the Electricity Board
on terms and conditions which are mutually agreed between
the parties. In respect of the power thus generated by the
IPP’s, if the Board or the State levys royalty, cess or other
charges, that will necessarily be added to the price at which
the energy generated is sold to the Board. Such increased
price paid by the Board to the generating company,
necessarily will have to be passed on to the Board’s
consumers, who are the end users of the energy generated.
This necessarily will lead to a situation where the energy
generated and sold to consumers would become costlier.
According to the Board and the Government, this was the
reason why the IPP’s were relieved of the obligation to pay
royalties or cess or other charges on the energy generated by
them.
25 . Learned single Judge has held that both IPP and CPP are
established for the same purpose of augmenting energy
generation. But the learned single Judge has lost sight of the
distinguishing factor that the energy generated by the CPP
st
of the 1 respondent is not available for distribution to
consumers and that it is only for self consumption unlike the
other IPP’s. Therefore, in our view, the justification that if
royalty or cess or other charges are levied, the energy
generated at IPP’s would be more expensive to the consumer
and that it was therefore that the IPP’s were relieved of that
obligation, is a valid reason for classification of IPP’s and
CPP’s under Article 14 of the Constitution of India.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
21
st
26 . Secondly, IPP’s that are complained of by the 1
respondent were established to Exts.P8 and P9 orders issued
by the Government of Kerala in 2002 and 2003. These
orders show that the terms and conditions that are
incorporated in these orders are totally different from what
are contained in Ext.P1, pursuant to which sanction was
accorded, agreement was executed and the project was
st
established by the 1 respondent. Therefore, the obligations
st
undertaken by the 1 respondent in Ext.P3 agreement and
the obligations that are fastened on the beneficiaries of
Ext.p8 and Ext.P9 are incomparable and different. That itself
st
shows that the 1 respondent and the owners of the
independent power plants fall in separate classes and
therefore also there cannot be any discrimination to be
complained of.
27 . Yet another reason, in our view, a valid one, urged by
st
the Electricity Board was that unlike the case of the 1
respondent, the 59 IPP’s are not beneficiaries of controlled
release of water. The pleading show that according to the
st
State, 22.54% of the power generated by the 1 respondent
at its CPP is attributable to controlled release of water. On
the other hand, IPP’s are not beneficiaries of such controlled
release. That also is a sound reason to hold that the CPP’s
and IPP’s are not similarly situate.
28 . In sum and substance, we are unable to endorse the
conclusion of the learned single Judge that by issuing
st
Ext.P11, the 1 respondent was treated in a discriminatory
manner or the Ext.P11 is arbitrary or unreasonable offending
Article 14 of the Constitution of India.”
22.2 Considering the nature of obligation undertaken in terms of INDSIL
Agreement, the Division Bench observed:-
“ 38 . Since royalty in these cases is only a contractual
payment reserved by the granter and is not a levy in the
nature of tax, the question of the State being legislatively
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
22
competent or incompetent to levy royalty on the water
consumed at the hydel plant of the first respondent does not
arise. Even if the words royalty and cess are interchangeably
used, that is inconsequential, in so far as the nature of the
levy of royalty is concerned. Therefore, this conclusion of
the learned single Judge also cannot be sustained.
39 . The learned single Judge also held that even if the levy
is payable, such levy cannot have retrospective effect. This
st
view also cannot be endorsed because once the 1
respondent has undertaken the liability to pay royalty as and
when levied by the Government, Government is always at
liberty to levy royalty from the time the benefit of the
st
agreement was derived by the 1 respondent. Therefore, this
contention also cannot be accepted.
st
40 . Learned senior counsel for the 1 respondent argued that
the controlled release of water from Anayirankal Dam was
made by the Board through Panniyar river depending upon
the requirements of the Panniyar Power Project of the Board.
According to him, this water is diverted by the weir across
Panniyar river at Mukkudi to the Kuthungal Project and
made use of these only because of the situs of the Kuthungal
Project. This, according to the counsel, is only an incidental
benefit and that to make them liable for controlled release,
water should be released solely at their instance and for
generation at their project and not otherwise. In our view,
this argument has no substance. Parties are governed by a
mutually agreed contract evidence by Ext.P3. Agreement
provides that for the additional advantage of controlled
release derived by them, the agency is liable to pay charges
as provided in the agreement. Agreement does not state that
st
such controlled release should be at the instance of the 1
respondent and that it should be for their sole benefit.
Instead, if the agency is a beneficiary of the controlled
release of water, they are liable to pay for it. Admittedly, the
st
1 respondent is generating energy utilizing the controlled
release of water from Anayirankal and so long as it is so, in
st
view of Clause 14 of the Ext.P1, the 1 respondent cannot
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
23
get itself absolved of that liability. Therefore, this contention
is only to be rejected and we do so.”
22.3 The Division Bench thus found that the Single Judge of the High Court
had erred in allowing the Writ Petition preferred by INDSIL. It, however,
concluded that the demand raised by the Government vide order dated
03.07.2004 was on the quantum of energy generated rather than being linked
to the quantity of water used or the utilization of controlled release of water. It,
therefore, directed the Government to pass fresh orders after due notice to the
appellant as under:-
“ 42. Therefore, royalty under clause 14 of Ext.P1
Government Order should be levied assessing the quantity
of water used applying Clause 15 of Ext.P1. However, in
Ext. P11 royalty is levied on the quantum of energy
generated. This, in our view, is inconsistent with Ext.P1
Government Order and Ext. P3 agreement which permits
levy of royalty only for the use of water, which also should
be based on the quantity of water as assessed by applying
the formula specified in Clause 15 thereof and not on the
quantity of energy generated.
43. Similarly, for the benefit of getting the controlled
release of water, Government is free to levy on the agency,
in tariff equivalent to the cost component for energy
generated from the scheme. For this purpose, as is evident
from clause 14 of Ext.P1 Government Order, what is
st
payable by the 1 respondent is tariff equivalent to the cost
component for the controlled release utilized by the grantee
for the energy generated. Though at one stage, it was
contended that 35% of the energy generated was utilizing
controlled release, in the counter affidavit filed, it is stated
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
24
that it was 22.54%. While we agree that this figure cannot
be a constant one, it is a fact that entire energy is not
generated utilizing controlled release of water. But, since
the charges for controlled release as ordered in Ext.P11, and
which was confirmed by the Government in Exts.P15 and
P28, is on the entire energy generated, the demand is
inconsistent with Exts. P1 and P3, we are unable to sustain
the orders.”
22.4 With regard to the matter concerning CUMI, it was observed:
“ 57 . In our view, the provisions of the Electricity (Supply)
Act, 1948 dealt with generation of electricity and the
provisions of the Act did not prevent a Government or Board
from entering into an agreement, agreeing to provide natural
resources of water to a generating company for the
generation of energy by setting up a hydel generation station
against royalty or other charges payable by the grantee.
Therefore, if under the contract, the Government agree to a
st
private party like the 1 respondent that it shall make
available water to a Hydro Electric Project for generation of
energy and in consideration, royalty is required to be paid to
the Government and that contractual right of the
Government or the obligation of the generating company to
pay are not affected by any of the provisions of the
st
Electricity (Supply) Act, 1948. Therefore, the 1 respondent
who has willingly entered into an agreement undertaking to
pay royalty and other charges to the Government and after
having enjoyed the benefit thereof, cannot now rely on the
provisions of the Electricity (Supply) Act and contend that
the Government or the Board have no power under the
Electricity (Supply) Act to realise the charges that are
contractually payable by them. Therefore, this contention of
the learned senior counsel is unacceptable and is rejected.
58 . The second contention raised by the learned senior
st
counsel for the 1 respondent was that there was no
controlled release to the Maniyar Hydro Electric Project and
that therefore the charges levied on them for controlled
release of water is unsustainable. We have already rejected
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
25
st
such a contention raised by the 1 respondent in WA
Nos.1345/13 and 18/14 and the reasons assigned by us
should apply to this case also. Morever, we are unable
accept this contention of the learned senior counsel for the
reason that Clause 14 of Ext.P2 agreement provides for
st
controlled release of water and the 1 respondent shall pay
charges to the Board. If there was no controlled release of
st
water, there was no reason why the 1 respondent should
have entered into such an agreement taking over the liability
to pay charges for the controlled release of water also. That
apart, both in Exts. P5 and P6, the representations made by
them objecting to the levy, they had no case that there was
no controlled release of water. Therefore, by the above
agreement and correspondence, the first respondent
themselves have admitted that there is controlled release of
water and therefore it is too late in the day for them to turn
around and contend that there is no controlled release of
water absolving them from the contractual obligations in
Clause 14 of the agreement.”
22.5 The Writ Appeal preferred against CUMI was thus allowed and the
decision of the Single Judge was set aside.
23. INDSIL being aggrieved, filed Civil Appeals Nos.9845-9846 of 2016
reiterating its submissions advanced in the High Court.
In the response filed on behalf of the Government, it was submitted inter
alia :-
“D. … …the Petitioner is a Captive Power Plant which
generates power from the water course along with the
controlled release of water from the Anayirankal reservoir to
Ponmudi for self-consumptioin and thereby collection of
royalty by Government cannot reflect in the tariff, because
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
26
the energy so generated is not sold to KSEB for distribution.
Further, 22.54% of the power generated by the Petitioner at
its Captive Power Plant is attributable to controlled release
of water. Unlike the case of the Petitioner, the 59 IPP’s are
not beneficiaries of such controlled release. Royalty was
demanded by Government as consideration for granting the
right to usage of water from the natural resource vested in
the Government, for generation of electricity, which does
not fall within the purview of the powers of the Regulatory
Commission constituted between the Petitioner and KSEB is
conclusive and is absolutely binding on the Petitioner.
… … …
I. … … The project utilizes the water from the free
catchment between Anayirankal dam and Kuthunkal weir
alongwith the controlled release of water. The controlled
release of water from Anayirankal dam was done by the
Board through the Panniyar River depending upon the
requirements of the Panniyar Power Project of the Board.
This water, when released, is being utilized at Kuthungal for
power generation. This controlled release of water is
diverted by a weir across Panniyar River at Mukkudi to the
Kuthungal project and used for generation of power. In the
absence of Anayirankal reservoir, the water would have
flown to Ponmudi during monsoon months and the weir
would be overflowing most of the time. And during summer
months there would be substantial shortfall in the generation
of power at the Kuthungal project in the absence of water
release from Anayirankal dam. The release of water at
Anayirankal is made in the months of January, February,
March and April every year and the scheme generates mostly
during these months in a year and primarily generates power
out of the water released from Anayirankal. The total
generation of power during this period was 266.69 MU and
generation from controlled release was 60.12 MU, which is
about 22.54% of the total generation. The Petitioner is
getting the full advantage of power generation from the
release of water from Anayirankal reservoir in the peak
summer months. In the drought year of 2002-03, 50% of the
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
27
total generation from the project was during summer months
by utilizing the water from Anayirankal dam.”
23.1 In the affidavit in rejoinder, it was submitted by the INDSIL:-
“That Respondent no.1 & 2 have further drawn distinction
on the fact that the petitioner’s project is based on controlled
release of water from the Anayirankal dam while the other
59 projects are not based on any controlled release. It is
submitted that the petitioner’s project is not based on
controlled release of water and therefore there is no question
of the petitioner utilizing the State’s natural resources with
controlled release of water from Anayirankal dam for our
exclusive benefits. It is submitted that wherever the State
Government has entered into a contract with a party like M/s
Carborandum’s project, involving controlled release of
water, it has provided a specific clause to this effect since it
would involve incurring of cost for providing the services. It
is submitted that in the case of the petitioner’s, no such
clause is provided and it is for this reason that the State
th
Government specifically agreed in the meeting dated 8
April, 1994 that water cess for the use of water would not be
charged. It is thus submitted that the petitioner is being
discriminated against by respondent no.1 & 2 in the facts of
the instant case in grave violation of its fundamental rights
guaranteed under Article 14 of the Constitution of India.
7. it is pertinent to mention here that respondent no.1 & 2
have imposed the same rate of royalty on Carborundum’s
project and that of the petitioner’s. It is submitted that it is
an admitted fact that Carborundum’s Project is based on
controlled release. In the Petitioner’s case, there is no such
controlled release. Further, on an average, only 22.54% of
the petitioner’s generation comes from the alleged controlled
release. It is submitted that on this ground alone, the levy put
on the petitioner is unreasonable and arbitrary.”
24. In Civil Appeal Nos.9847-9850 of 2016, the grounds of appeal raised
by CUMI have reiterated its submissions before the High Court. The assertions
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
28
with respect to the location of the project and use of controlled release of water
were:-
“The alleged controlled release of water must be directly to
the petitioners’ Maniyar Hydroelectric project from the
water releasing point at Moozhiyar Power House of KSEB
and not to Irrigation Dam of PWD or to its own
Hydroelectric project at Moozhiar. After the year 1998,
KSEB has set up its own Hydro Electric Project at Kakkad
upstream of the river and two more Private Hydel Power
Project had been approved and set up on the same river
upstream, i.e. in between the Moozhiyar Power House of
KSEB and the Petitioner’s Maniyar Power Plant. It is
pertinent to note that the alleged controlled release of water
being used by the Board’s Hydro Electric Project at Kakkad
at the first instance and then flows further down to two other
private Hydro Electric Projects at Ullunkal & Karikkayam
before it reaches the irrigation dam owned by PWD from
where the Petitioner draws water for its Maniyar Hydro
Electric Project. It is further to be noticed that when the flow
of the controlled release of water further strengthened by two
more minor rivers and forms confluence on its way of
flowing further down along with the other source of water
from the catchment area of 237 square kilometers as
evidence by the map on record.”
24.1 In the affidavit in reply filed by the Board, it was stated:-
“8. … …the Hydro Electric Project are generally classified
into two categories based on the storage capacity namely (a)
Hydro projects with reservoir of large capacity and (b)
Hydro projects having small capacity reservoir /run of river
projects.
… … …
11 . The Sabarigiri Power Project comprises of two dams,
one across the river Pamba (Pamba reservoir) and the other
across its tributary Kakki (Kakki reservoir) with a flanking
dam also at Anathode. These two reservoirs are connected
through a interconnecting tunnel of 105241 feet long
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
29
(3209.82m). The water from the Kakki reservoir is drawn
through 18209 ft (5553.73m) long power tunnel and a set of
three penstocks leading the waters to the power house with
an original installed capacity of 300 MW consisting of 6
units of 50 MW. After Renovation and Modernisation of the
station, the installed capacity is increased to 340 MW. The
total storage capacity of Kakki and Pamba reservoirs is
477.67 MCM (Million Cubic Metre). In addition to the
above, augmentation schemes like Upper Moozhiyar (0.035
MCM, Meenar 1 (0.028 MCM), Meenar – II (0.057 MCM)
and Kullar – Gaviar (2.78 MCM) agument the Pamba and
Kakki reservoirs. Thus, the total storage capacity of Kakki
and Pamba reservoirs is 480.54 MCM.
12 . The Maniyar Power House operated by M/s
Carborandum Universal Ltd. the petitioner herein belongs to
the second category where the gross storage is only 8 MCM
(Million Cubic Metre), which is not even sufficient for two
days full load operation of the Power House. However, the
Maniyar Power Station is operated throughout the year only
due to the large storage of the Pamba-Kakki storage
reservoir (about 60 times larger than Maniyar storage) and
controlled release of water from Sabarigiri Power House.
When M/s Carborandum Universal Ltd., executed the
agreement with KSEB on 18.05.1991, the construction of
Kakkad Power Station on the down stream of Sabarigiri
Power Station was going on. It is to be noted that the Kakkad
Power Station also has a very small storage capacity. The
Moozhiyar reservoir with storage capacity of 1.16 MCM and
Veluthodu reservoir with storage capacity of 0.607 MCM
are the reservoirs of Kakkad Power Station. Thus, the
storage capacities of the three power stations are as shown
below:
Sabarigiri Power House – 480.54 MCM (Effective)
Kakkad Power House – 1.767 MCM (Effective)
Maniyar Power House – 8.0 MCM (Gross)
…. …. ….
14 . … … The Pamba Dam across Pamba river, Kakki Dam
across Kakki river and a flanking dam at Anathode are the
main three dams of Sabarigiri Project. These Dams are at an
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
30
elevation of about 900 M from the sea level. Water from the
Kakki reservoir is brought to Sabarigiri Power House, the
water is again stored at Moozhiyar by a concrete Gravity
Dam. Water from other small streams like Saippinkuzhy
stream also reaches this reservoir. This water is brought to
Kakkad Power Station through under ground tunnel and
utilized it for power generation. Water from another stream
called Veluthode is also brought to Kakkad Power Station
by constructing a small Dam across the stream. Before the
commissioning of the Kakkad Power Station, the controlled
release of water from Sabarigiri Power House directly
reached the maniyar barrage (owned by Kerala Irrigation
Department) and this was utilized by M/s. Caborandum
Universal Ltd., for power generation at maniyar Power
House. The only difference after the commissioning of
Kakkad Power Station is that the same water is once again
utilized for power generation at Kakkad Power Station.
There is an added advantage that some more
control/regulation can be done at Kakkad Power House also.
It is to be noted that there are no major sources of water
(rivers) between Kakkad and Maniyar which can
substantially contribute for the supply of water to Maniyar
Power House. Now, two more small power stations at
Ullumkal (7MW) and karikayam (10.5 MW) are established
between Kakkad and Maniyar Power Stations. All these
power stations at Kakkad, Ullumkal, Karikayam and
Maniyar have small reservoirs and utilize the huge storage
and controlled release of water from the Sabarigiri Power
Station for power generation throughout the year. Had there
been no Sabarigiri Power Project, the water from Pamba and
Kakki rivers would have flown though the natural flow path
of these rivers and would reached much below the Maniyar
Power House as it can be seen from the sketch attached.”
24.2 In its rejoinder to the aforestated reply, it was submitted by CUMI:-
“ 19 . That the contents of para (8) of the counter affidavit
need no reply as the said contents are not relevant for the
adjudication of the instant SLP.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
31
20 . That the contents of para (9) to (18) of the counter
affidavit are denied as wrong and baseless. It is submitted
that the averments contained in the aforesaid paragraphs
are new pleas taken by respondent no.2 for the first time
before this Hon’ble Court and as such the same cannot be
allowed to be raised for the first time at special leave
petition state….”
25. Mr. V. Giri, learned Senior Advocate for INDSIL submitted:-
a) Clause 14 of CUMI Agreement was distinct and different from Clause
19 of INDSIL Agreement. Further, the matter was required to be seen in the
light of the decision dated 08.04.1994 and imposition of royalty on the use of
water would be in contravention of the decision dated 08.04.1994.
b) No explanation was forthcoming as to why, as against specific inclusion
of Clause 14 in CUMI Agreement, no such provision was made in INDSIL
Agreement.
c) Being at a lower level than the Anayirankal Reservoir but higher than
the Paniyar Power Station, the project of INDSIL was conceived as a “run of
the river scheme”. The release of water from Annayirankal Reservoir would be
only for 45 days in a year, and the regulation of release of water would be
completely at the discretion of the Board and meant to facilitate the generation
of power at the Paniyar Power Station. The release of water would be
determined by the requirements of the Board at the Paniyar Power Station and
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
32
that utilization of such controlled release constituted only 22.54% of the
generation by the INDSIL.
d) The controlled release of water in the case of CUMI would be meant to
suit the requirements of its project. On the other hand, such controlled release
of water would not be exclusively for the benefit of INDSIL but for the benefit
of the Plant at Paniyar. It would therefore be illegal to draw similarity between
the case of CUMI and that of INDSIL.
e) The imposition of royalty on the use of water would be unconstitutional
as INDSIL was discriminated against other similarly situated hydroelectric
plants.
f) Imposition of royalty in terms of Clause 19 of INDSIL Agreement
would partake the nature and character of a “Tax”. Assuming that the royalty
imposed on INDSIL had genesis in a contract, no decision was taken by the
Government as contemplated under said Clause 19.
g) Assuming that the terms of the Policy were incorporated into INDSIL
Agreement, the tariff for storage/controlled release was required to be worked
out in respect of each scheme separately.
26. Appearing for CUMI, Mr. C.A. Sundaram, learned Senior Advocate
submitted:-
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
33
a) When its Agreement was entered into, CUMI was the only Power
Project in private sector and as such, there was no question of any
discrimination. However, the discrimination arose when other Power Projects
were given the benefit of controlled release of water without any charge.
b) There could be no distinction between CPPs and IPPs. Guidelines of
2002 as revised did not make any such distinction. The basis for levy was the
advantage gained from controlled release of water. Therefore, the differentia
could be between those having the benefit of controlled release of water on one
hand and those not having such advantage on the other. Any other distinction
such as CPPs as against IPPs would be unnatural and irrational.
c) Even if, the relevant Clause in the Agreement was a negotiated Clause,
said Clause being arbitrary or discriminatory was liable to be struck down.
Reliance was placed on the decision of this Court in Central Inland Water
4
Transport Corporation vs. Brojo Nath Ganguly , ICOMM Tele Limited v.
5
Punjab State Water Supply and Sewerage Board and Anr. and Pioneer Urban
6
Land and Infrastructure Ltd. v. Govindan Raghavan .
d) The Power Plant of CUMI had been receiving water not just from
Sabarigiri and Moozhiyar reservoirs but also from the streams in the catchment
4
(1986) 3 SCC 156.
5
(2019) 4 SCC 401.
6
(2019) 5 SCC 725.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
34
area. Thus, the entirety of the supply of water to CUMI could not be treated as
controlled water from Moozhiyar Power House of the Board.
e) The relevant Clause in CUMI Agreement would, at best, attract levy of
charges for controlled release of water on the cost component thereof.
Therefore, the stipulation in Clause 14 of CUMI Agreement providing 10% of
tariff for the electricity generated was ultra vires the Policy.
f) Further, the levy in question had to be commensurate with the service
rendered, otherwise, it would cease to be a fee and would be wholly beyond the
competence of the Board. Reliance was placed upon the decision of this Court
in the State of Maharashtra & Ors. vs. Salvation Army, Western India
7
Territory .
g) Considering the facts of the case, the calculations were required to be
revisited where all relevant aspects had to be properly accounted for and the
levy had to be linked to the cost of advantage gained from controlled release of
water and not from other sources from catchment area.
7
(1975) 1 SCC 509.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
35
27. Mr. Jaideep Gupta and Mr. P.V. Surendranath, learned Senior
Advocates appearing for the Board and the State respectively, in both the
appeals, submitted: -
(a) Terms and conditions of the Policy including Clause 14 of the Policy
stood specifically incorporated in INDSIL and CUMI Agreements. Said Clause
14 of the Policy dealt with the additional advantage gained by an agency/
project by way of controlled release of water and stipulated that the cost
component for such controlled release would be required to be paid. Clause 15
of the Policy then set out the formula to be used for ascertainment of the
relevant indicia. The Agreements having accepted the liability to pay such
controlled release of water, the matter was purely in the realm of contract.
(b) There was no unequal or unnatural bargaining so as to invoke the
principles laid down in some of the decisions of this Court. Both CUMI and
INDSIL had willingly accepted the liability to pay for the use of controlled
release of water. It was a commercial contract which was entered into after due
negotiations.
(c) The location of the projects of CUMI and INDSIL as well as the facts
on record would show that both the projects were enjoying the benefit of
controlled supply of water. CUMI had been enjoying the benefit of “tail race”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
36
water discharge flowing down from Moozhiyar Power House of the Board
while INDSIL Project had been enjoying the advantage of controlled supply of
water discharge from Anayirankal Dam.
(d) Clause 14 of the Policy had stipulated that normally such benefits of
existing reservoirs and “tail race” benefit of existing power stations would not
be entrusted with private agencies but in case under special circumstances such
schemes were allowed to the private parties, they would have to pay charges
for controlled release of water.
(e) Unlike the projects which would depend upon irregular and intermittent
supply of water, the assured and controlled supply of water enabled smooth
running of the turbines for generation of electricity. Such assured supply was
the element based on which the terms of the Policy were incorporated in the
Agreements and liability was accepted.
(f) Having agreed to abide by the terms of the Policy including Clause 14
of the Policy, it would not be open to CUMI and INDSIL to submit that
imposition of charges for controlled supply of water would be discriminatory
and irrational.
(g) Even if there was no specific clause in INDSIL Agreement similar to
Clause 14 in CUMI Agreement, Clause 19 of INDSIL Agreement read with the
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
37
terms of the Policy made the situation quite clear and there would be no escape
from the liability to pay the charges for controlled release of water.
(h) There was no inter se distinction between INDSIL on one hand and
CUMI on the other. Both had been enjoying benefits of controlled release of
water and their cases came within the ambit of Clause 14 of the Policy.
(i) The charges payable for controlled release of water had their genesis in
the Policy and the terms of the Agreements. The submissions on the part of
CUMI and INDSIL that it would amount to compulsory exaction was therefore
without any merit.
28. Before we deal with the principal submissions, an aspect of the matter
highlighted on behalf of the Appellants needs to be dealt with.
It was submitted that a decision was taken on 08.04.1994 that no
charges for benefit of controlled water would be imposed if the water was being
retained in the same basin. The decision in said meeting was only to make a
recommendation but the final call had to be taken by the Irrigation Department
of the State. It cannot therefore be said that no liability could be imposed after
08.04.1994. Pertinently, INDSIL Agreement was entered into on 30.12.1994.
Though no specific Clause comparable to Clause 14 of CUMI Agreement was
included in INDSIL Agreement a specific reference to the terms and conditions
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
38
of the policy was made and such terms and conditions were incorporated in
INDSIL Agreement. Thus the decision dated 08.04.1994 had no bearing on the
matter in question.
29. The first question that arises for consideration is whether the projects
of CUMI and INDSIL are located at places where the advantage of controlled
supply of water is assured and can be derived.
30. Hydro-Electric Projects rely on the force of fall of water from a height
to enable the turbines to generate electricity. Normally, the water is supplied
through penstocks from a reservoir. The stored water from a reservoir assures
consistent and regular supply of water for the smooth functioning of the
generating units.
The supply of water from a large reservoir is one way of ensuring
consistent and controlled supply of water. However, because of topography,
large reservoirs are not always close to a generating unit. In such cases, the
water from a large reservoir located at a greater height is steadily released and
collected in a smaller reservoir or a weir from which the water is thereafter
supplied to the generating units; and depletion in the stock of water is regularly
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
39
replenished from the large reservoir. This is another way of ensuring consistent
and controlled supply of water for generation of electricity.
After the force of the water is used for propelling the turbines, the water
is discharged from the generating unit or powerhouse. Such discharge of water
or “tail race” benefit will also be consistent, depending upon the supply of water
that such generating unit or powerhouse receives. If another generating unit is
at a lower level than such powerhouse, the discharge from the powerhouse at a
higher attitude may itself assume and ensure consistent supply of water to the
generating unit at a lower level or altitude.
31. The location of the project of CUMI is at a place where the discharge
of water from Moozhiyar Power House of the Board is diverted to Kakkad
Power House of the Board, which gets steady supply of water in the form of
“tail race” benefit of the Moozhiyar Power House. After generation of
electricity at the Kakkad Power House, the water is allowed to flow back into
the river. The capacity of Kakkad Power House is 50 MW while that of CUMI
is 12 MW.
The supply of water even if meant for a powerhouse situated at a height
and with larger capacity thus definitely ensures consistent and controlled
supply of water to the project of CUMI located at a lower altitude.
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
40
32. Similarly, the water from a larger reservoir namely, Anayirankal Dam
is allowed to flow so as to reach Paniyar Power House having a capacity of 32
MW electricity. Before reaching Paniyar Power House, the water passes
through the area where the project of INDSIL is situated, which has a capacity
of 21 MW. The location of the project of INDSIL would thus have natural
advantage of consistent and controlled supply of water.
33. The facts on record thus show that both the projects have certainly
derived advantage of controlled supply of water as contemplated in Clause 14
of the Policy. How much benefit of controlled supply of water each of the
projects has received or will receive in future would be a matter of computation
and calculation.
34. The Agreements entered into by CUMI and INDSIL show that the
terms and conditions of the Policy including Clause 14 thereof were
consciously incorporated in the Agreements. Both CUMI and INDSIL were
alive to the fact that because of peculiar location, their units would certainly
have the advantage of controlled supply of water.
Thus, the absence of a specific clause, akin to Clause 14 of CUMI
Agreement, in INDSIL Agreement, would be of no consequence. The
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
41
relationship between the parties would be governed by Clause 14 of the Policy,
as incorporated in the respective Agreements.
35. The next questions to be considered are whether Clause 14 of CUMI
Agreement and Clause 14 of the Policy which stood incorporated into the
respective Agreements could be termed to be unconscionable and/or manifestly
arbitrary.
36. The decision of this Court in Central Inland Water Transport
4
Corporation which was pressed in service, was in relation to terms in a
Contract of Employment. This Court found that such term would get included
in the contract only at the instance of the employer where because of lack of
bargaining power the employee would have no other option but to accept such
term. It was in this context that the relevant term contained in the Contract of
Employement was found to be unconscionable. At the same time, the
principles which weighed with the Court for holding such terms
unconscionable were specifically stated to be inapplicable in cases of
commercial contracts. The relevant discussion in paragraph 89 of the decision
was:-
“ 89 . … …The Constitution was enacted to secure to all the
citizens of this country social and economic justice. Article
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
42
14 of the Constitution guarantees to all persons equality
before the law and the equal protection of the laws. The
principle deducible from the above discussions on this part
of the case is in consonance with right and reason, intended
to secure social and economic justice and conforms to the
mandate of the great equality clause in Article 14. This
principle is that the courts will not enforce and will, when
called upon to do so, strike down an unfair and unreasonable
contract, or an unfair and unreasonable clause in a contract,
entered into between parties who are not equal in bargaining
power. It is difficult to give an exhaustive list of all bargains
of this type. No court can visualize the different situations
which can arise in the affairs of men. One can only attempt
to give some illustrations. For instance, the above principle
will apply where the inequality of bargaining power is the
result of the great disparity in the economic strength of the
contracting parties. It will apply where the inequality is the
result of circumstances, whether of the creation of the parties
or not. It will apply to situations in which the weaker party
is in a position in which he can obtain goods or services or
means of livelihood only upon the terms imposed by the
stronger party or go without them. It will also apply where a
man has no choice, or rather no meaningful choice, but to
give his assent to a contract or to sign on the dotted line in a
prescribed or standard form or to accept a set of rules as part
of the contract, however unfair, unreasonable and
unconscionable a clause in that contract or form or rules may
be. This principle, however, will not apply where the
bargaining power of the contracting parties is equal or
almost equal. This principle may not apply where both
parties are businessmen and the contract is a commercial
transaction. In today’s complex world of giant corporations
with their vast infrastructural organizations and with the
State through its instrumentalities and agencies entering into
almost every branch of industry and commerce, there can be
myriad situations which result in unfair and unreasonable
bargains between parties possessing wholly disproportionate
and unequal bargaining power. These cases can neither be
enumerated nor fully illustrated. The court must judge each
case on its own facts and circumstances.”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
43
(Emphasis added)
8
37. In S.K. Jain v. State of Haryana and another a Bench of three Judges
of this Court summed up as under:-
“It is to be noted that the plea relating to unequal bargaining
power was made with great emphasis based on certain
observations made by this Court in Central Inland Water
4
Transport Corpn. Ltd. v. Brojo Nath Ganguly . The said decision
does not in any way assist the appellant, because at para 89 it has
been clearly stated that the concept of unequal bargaining power
has no application in case of commercial contracts.
38. To similar effect, were the observations by this Court in ICOMM Tele
5
Limited , where this Court held:-
“11. As has correctly been argued by learned counsel
appearing on behalf of the respondents, this Court’s
4
judgment in Central Inland Water Transport Corpn. , which
lays down that contracts of adhesion i.e. contracts in which
there is unequal bargaining power, between private persons
and the State, are liable to be set aside on the ground that
they are unconscionable, does not apply where both parties
are businessmen and the contract is a commercial transaction
(see para 89 of the said judgment). In this view of the matter,
the argument of the appellant based on this judgment must
fail.”
6
39. In Pioneer Urban Land and Infrastructure Ltd , certain terms in the
agreements entered into between the flat purchasers and the builder were ex
8
(2009) 4 SCC 357
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
44
facie found to be one sided, unfair and unreasonable. Relying on the decision
4
of this Court in Central Inland Water Transport Corporation , it was held that
the terms of the agreements would not bind the flat purchasers.
40. The law is thus clear that in cases where a term of contract or agreement
entered into between the parties is completely one sided, unfair and
unreasonable, where the other party having less bargaining power had to accept
such term by force of circumstances, the relief in terms of the decision of this
4
Court in Central Inland Water Transport Corporation can be extended. It may
be stated that the Agreements were entered into after long deliberations where
both CUMI and INDSIL had the advantage of legal counsel.
It cannot be said that CUMI and INDSIL were in a position with lesser
bargaining power or were so vulnerable that by force of circumstances they
were forced to accept such term. Therefore, the concerned Clause in CUMI
Agreement as well as the terms of the Policy that stood incorporated in the
respective Agreements, cannot be termed unconscionable.
5
41. In ICOMM Tele Limited , this Court found Clause 25 (viii) of the
Notice Inviting Tender to be arbitrary as said clause deterred a party to an
arbitration agreement from invoking the alternative dispute resolution process
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
45
unless it complied with requirements of pre-deposit. Though this Court did not
4
accept the submission, based on Central Inland Water Transport Corporation ,
that the clause in question was unconscionable, the matter was considered from
the stand point whether said clause could be said to be manifestly arbitrary. The
clause was found to be contrary to the object of de-clogging the Court process
and rendering the arbitral process ineffective. Relying upon the decision of
9
this Court A.L. Kalra v. Project and Equipment Corporation of India it was
found in paragraph 23 that the clause had no nexus to the filing of frivolous
claims. The discussion in paragraph 23 was:
“ 23. The important principle established by this case is that
unless it is first found that the litigation that has been embarked
upon is frivolous, exemplary costs or punitive damages do not
follow. Clearly, therefore, a “deposit-at-call” of 10 per cent of
the amount claimed, which can amount to large sums of money,
is obviously without any direct nexus to the filing of frivolous
claims, as it applies to all claims (frivolous or otherwise) made
at the very threshold. A 10 per cent deposit has to be made
before any determination that a claim made by the party
invoking arbitration is frivolous. This is also one important
aspect of the matter to be kept in mind in deciding that such a
clause would be arbitrary in the sense of being something
which would be unfair and unjust and which no reasonable man
would agree to. Indeed, a claim may be dismissed but need not
be frivolous, as is obvious from the fact that where three
arbitrators are appointed, there have been known to be majority
and minority awards, making it clear that there may be two
possible or even plausible views which would indicate that the
claim is dismissed or allowed on merits and not because it is
9
(1984) 3 SCC 316
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
46
frivolous. Further, even where a claim is found to be justified
and correct, the amount that is deposited need not be refunded
to the successful claimant. Take for example a claim based on
a termination of a contract being illegal and consequent
damages thereto. If the claim succeeds and the termination is
set aside as being illegal and a damages claim of Rupees One
crore is finally granted by the learned arbitrator at only ten
lakhs, only one-tenth of the deposit made will be liable to be
returned to the successful party. The party who has lost in the
arbitration proceedings will be entitled to forfeit nine-tenths of
the deposit made despite the fact that the aforesaid party has an
award against it. This would render the entire clause wholly
arbitrary, being not only excessive or disproportionate but
leading to the wholly unjust result of a party who has lost an
arbitration being entitled to forfeit such part of the deposit as
falls proportionately short of the amount awarded as compared
to what is claimed.”
42. On the touchstone of these principles, it needs to be seen whether
Clause 14 of the Policy can be termed to be manifestly arbitrary. The Policy
had made it quite clear that the benefit of controlled supply of water would
normally be confined to the electricity generating units or power houses in
public sector.
The reason for such Policy statement would clearly be that considerable
amount of insfrastructure and development had been and would be made by the
State in erecting and maintaining dams and reservoirs and as such the
incremental advantage or benefit of such investment must go back to the public
through units in public sector. If the advantage was, however, allowed to be
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
47
given to a private entity or agency, the Policy contemplated impostion of
charges for the use of such controlled supply of water.
There is nothing arbitrary or unreasonable in having such term in the
Policy. Since the private entity or agency would stand to gain from and out of
the capital outlay and infrastructure put in place by the State, some reasonable
charges for such benefit would naturally be imposed. It was only under such
Policy that both CUMI and INDSIL were given permissions to set up their
electricity generating units and such term was consciously accepted by them.
The submission that the relevant Clause would be manifestly arbitrary,
therefore, does not merit acceptance.
43. Though we have considered the submissions that Clause 14 of the
Policy would be unconscionable or arbitrary on merits, reference may also be
made to the following statement of law culled out in Rajasthan State Industrial
Development and Investment Corporation and Another vs. Diamond and Gem
10
Development Corporation Limited and Another :-
“ 15. A party cannot be permitted to “blow hot-blow cold”,
“fast and loose” or “approbate and reprobate”. Where one
knowingly accepts the benefits of a contract, or conveyance,
or of an order, he is estopped from denying the validity of,
10
(2013) 5 SCC 470
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
48
or the binding effect of such contract, or conveyance, or
order upon himself……”
44. Moving further, even if the relevant term in the Policy is not found to
be unconscionable or arbitrary and is found to be perfectly justified, the
question still remains whether in the application of said term to CPPs alone and
not to IPPs, was any discriminatory treatment meted out to CPPs.
Qualitatively, the CPPs and IPPs have a basic distinction. CPPs
produce electricity for self consumption. In the present case both CUMI and
INDSIL generate electricity to be consumed in their factories or industrial
units. Under the terms of their Agreements, if anything is produced in excess
of their requirements, the surplus or excess electricity would be accepted by
the Board. However, the principal purpose and end use would be self
consumption. As against that, IPPs produce electricity not for self
consumption but for the use of the Board. The electricity generated by IPPs
becomes part of the grid of the Board to be supplied by the Board to its
consumers like electricity produced by the generating units or power houses
of the Board. If the charges towards controlled supply of water were to be
imposed uniformly for CPPs and IPPs, the effect would be that the electricity
supplied through IPPs to common consumers and general public would
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
49
necessarily have an additional burden or load towards proportionate element
of water charges. In these circumstances, if the Board decided not to apply
Clause 14 of the Policy in case of all IPPs, such decision would not be termed
as discriminatory.
The distinction or classification brought out was based on a clear rationale
with the object of reducing the additional burden on the consumers. Since the
electricity generated by CPPs would be self consumed, there would be no such
question of putting any ultimate or resultant burden on the common consumers.
The basis for such distinction or classification was quite correct and as such
this question was rightly answered by the Division Bench of the High Court
against CUMI and INDSIL. Rather than being unnatural or irrational, the
classification had a clear nexus or relationship with the object of reducing
resultant burden on the common consumers.
This submission therefore, is, meritless and rejected.
45. This takes us to the last set of submissions challenging the imposition
of royalty or charges on controlled supply of water on the ground of absence or
lack of jurisdiction and some ancilliary issues.
The matter in that behalf was considered by the Division Bench of the
High Court in paragraphs 38, 39 and 57 as quoted hereinabove. As rightly
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
50
observed, the basis or genesis of such imposition was Clause 14 of the Policy
which, as agreed between the parties, stood incorporated in the respective
Agreements.
46. The submission on behalf of the appellants was that the royality or
charges for controlled supply of water in the instant case would be nothing but
compulsory exaction and in the absence of any statutory sanction behind such
imposition, the actions on part of the Board would be without jurisdiction. The
counter submission on behalf of the State and the Board was that such royalty
or charges had the genesis in respective contracts and as such the action on part
of the Board was fully justified.
47. The distinction between tax and fee was brought out by the Constitution
Bench of this Court in Hingir-Rampur Coal Co. Ltd. and Others vs. State of
11
Orissa and Others as under:-
“The first question which falls for consideration is whether
the levy imposed by the impugned Act amounts to a fee
relatable to Entry 23 read with Entry 66 in List II. Before
we deal with this question it is necessary to consider the
difference between the concept of tax and that of a fee. The
neat and terse definition of tax which has been given by
12
Latham, C.J., in Matthews v. Chicory Marketing Board is
often cited as a classic on this subject. “A tax”, said
Latham, C.J., “is a compulsory exaction of money by
11
(1961) 2 SCR 537
12
(1938) 60 C.L.R. 263, 276
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
51
public authority for public purposes enforceable by law,
and is not payment for services rendered”. In bringing out
the essential features of a tax this definition also assists in
distinguishing a tax from a fee. It is true that between a tax
and a fee there is no generic difference. Both are
compulsory exactions of money by public authorities; but
whereas a tax is imposed for public purposes and is not,
and need not, be supported by any consideration of service
rendered in return, a fee is levied essentially for services
rendered and as such there is an element of quid pro quo
between the person who pays the fee and the public
authority which imposes it. If specific services are rendered
to a specific area or to a specific class of persons or trade
or business in any local area, and as a condition precedent
for the said services or in return for them cess is levied
against the said area or the said class of persons or trade or
business the cess is distinguishable from a tax and is
described as a fee. Tax recovered by public authority
invariably goes into the consolidated fund which ultimately
is utilised for all public purposes, whereas a cess levied by
way of fee is not intended to be, and does not become, a
part of the consolidated fund. It is earmarked and set apart
for the purpose of services for which it is levied. There is,
however, an element of compulsion in the imposition of
both tax and fee. When the Legislature decides to render a
specific service to any area or to any class of persons, it is
not open to the said area or to the said class of persons to
plead that they do not want the service and therefore they
should be exempted from the payment of the cess. Though
there is an element of quid pro quo between the tax payer
and the public authority there is no option to the tax-payer
in the matter of receiving the service determined by public
authority. In regard to fees there is, and must always be, co-
relation between the fee collected and the service intended
to be rendered. Cases may arise where under the guise of
levying a fee Legislature may attempt to impose a tax; and
in the case of such a colourable exercise of legislative
power courts would have to scrutinise the scheme of the
levy very carefully and determine whether in fact there is a
co-relation between the service and the levy, or whether the
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
52
levy is either not corelated with service or is levied to such
an excessive extent as to be a pretence of a fee and not a
fee in reality. In other words, whether or not a particular
cess levied by a statute amounts to a fee or tax would
always be a question of fact to be determined in the
circumstances of each case. The distinction between a tax
and a fee is, however, important, and it is recognised by the
Constitution. Several Entries in the Three Lists empower
the appropriate Legislatures to levy taxes; but apart from
the power to levy taxes thus conferred each List
specifically refers to the power to levy fees in respect of
any of the matters covered in the said List excluding of
course the fees taken in any Court.
The question about the distinction between a tax and a fee
has been considered by this Court in three decisions in
1954. In Commissioner, Hindu Religious Endowments,
Madras v. Sri Lakshmindra Thirtha Swamiar of Sri Shirur
13
Mutt the vires of the Madras Hindu Religious and
Charitable Endowments Act, 1951 (Madras Act 19 of
1951), came to be examined. Amongst the sections
challenged was Section 76(1). Under this section every
religious institution had to pay to the Government annual
contribution not exceeding 5% of its income for the
services rendered to it by the said Government; and the
argument was that the contribution thus exacted was not a
fee but a tax and as such outside the competence of the
State Legislature. In dealing with this argument Mukherjee,
J., as he then was, cited the definition of tax given by
14
Latham, C.J., in the case of Matthews and has elaborately
considered the distinction between a tax and a fee. The
learned Judge examined the scheme of the Act and
observed that “the material fact which negatives the theory
of fees in the present case is that the money raised by the
levy of the contribution is not earmarked or specified for
defraying the expense that the Government has to incur in
performing the services. All the collections go to the
consolidated fund of the State and all the expenses have to
13
(1954) S.C.R. 1005
14
(1938) 60 C.L.R. 263
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
53
be met not out of those collections but out of the general
revenues by a proper method of appropriation as is done in
the case of other Government expenses”. The learned
Judge no doubt added that the said circumstance was not
conclusive and pointed out that in fact there was a total
absence of any co-relation between the expenses incurred
by the Government and the amount raised by contribution.
That is why Section 76(1) was struck down as ultra vires.
The same point arose before this Court in respect of the
Orissa Hindu Religious Endowments Act, 1939, as
amended by amending Act 2 of 1952 in Mahant Sri
15
Jagannath Ramanuj Das v. State of Orissa . Mukherjea,
J., who again spoke for the Court, upheld the validity of
Section 49 which imposed the liability to pay the specified
contribution on every Mutt or temple having an annual
income exceeding Rs 250 for services rendered by the State
Government. The scheme of the impugned Act was
examined and it was noticed that the collections made
under it are not merged in the general public revenue and
are not appropriated in the manner laid down for
appropriation of expenses for other public purposes. They
go to constitute a fund which is contemplated by Section
50 of the Act, and this fund to which the Provincial
Government contributes both by way of loan and grant is
specifically set apart for the rendering of services involved
in carrying out the provisions of the Act. 12. The same view
was taken by this Court in regard to Section 58 of the
Bombay Public Trust Act, 1950 (Act 29 of 1950) which
imposed a similar contribution for a similar purpose in
16
Ratilal Panachand Gandhi v. State of Bombay . It would
thus be seen that the tests which have to be applied in
determining the character of any impugned levy have been
laid down by this Court in these three decisions; and it is in
the light of these tests that we have to consider the merits
of the rival contentions raised before us in the present
petition.”
15
(1954) S.C.R. 1046
16
(1954) S.C.R. 1055
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
54
17
48. In State of West Bengal vs. Kesoram Industries Limited and Ors. ,
another Constitution Bench of this Court explained certain observations in
18
India Cement Limited vs. State of Tamil Nadu , and stated as under:-
“ 59. First we will refer to certain dictionaries oft-cited in
courts of law:
Words and Phrases , Permanent Edn. (Vol. 37-A, p. 597):
“ ‘Royalty’ is the share of the produce reserved to owner
for permitting another to exploit and use property. The
word ‘royalty’ means compensation paid to landlord by
occupier of land for species of occupation allowed by
contract between them. ‘Royalty’ is a share of the
product or profit (as of a mine, forest etc.) reserved by
the owner for permitting another to use his property.”
Stroud’s Judicial Dictionary of Words and Phrases (6th
Edn., 2000, Vol. 3, p. 2341):
“The word ‘royalties’ signifies, in mining leases, that
part of the reddendum which is variable, and depends
upon the quantity of minerals gotten or the agreed
payment to a patentee on every article made according to
the patent. Rights or privileges for which remuneration is
payable in the form of a royalty.”
Words and Phrases, Legally Defined (3rd Edn., 1990, Vol.
4, p. 112):
“A royalty, in the sense in which the word is used in
connection with mining leases, is a payment to the lessor
17
(2004) 10 SCC 201
18
(1990) 1 SCC 12
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
55
proportionate to the amount of the demised mineral
worked within a specified period.”
Wharton’s Law Lexicon (14th Edn., p. 893):
“ Royalty .—Payment to a patentee by agreement on every
article made according to his patent; or to an author by a
publisher on every copy of his book sold; or to the owner
of minerals for the right of working the same on every
ton or other weight raised.”
Mozley & Whiteley’s Law Dictionary (11th Edn., 1993, p.
243):
“A pro rata payment to a grantor or lessor, on the working
of the property leased, or otherwise on the profits of the
grant or lease. The word is especially used in reference
to mines, patents and copyrights.”
Prem’s Judicial Dictionary (1992, Vol. 2, p. 1458):
“Royalties are payments which the Government may
demand for the appropriation of minerals, timber or other
property belonging to the Government. Two important
features of royalty have to be noticed, they are, that the
payment made for the privilege of removing the articles
is in proportion to the quantity removed, and the basis of
the payment is an agreement.”
Black’s Law Dictionary (7th Edn., p. 1330):
“ Royalty .—A share of the product or profit from real
property, reserved by the grantor of a mineral lease, in
exchange for the lessee’s right to mine or drill on the
land.
Mineral royalty .—A right to a share of income from mineral
production.”
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
56
19
60. In D.K. Trivedi & Sons v. State of Gujarat a Bench of
two learned Judges of this Court dealt with “rent”, “royalty”
and “dead rent” and held as follows: (SCC pp. 53-54, paras
38-39)
“ 38 . Rent is an integral part of the concept of a lease. It
is the consideration moving from the lessee to the lessor
for demise of the property to him.
… … …
39 . In a mining lease the consideration usually moving
from the lessee to the lessor is the rent for the area leased
(often called surface rent), dead rent and royalty. Since
the mining lease confers upon the lessee the right not
merely to enjoy the property as under an ordinary lease
but also to extract minerals from the land and to
appropriate them for his own use or benefit, in addition
to the usual rent for the area demised, the lessee is
required to pay a certain amount in respect of the
minerals extracted proportionate to the quantity so
extracted. Such payment is called ‘royalty’. It may,
however, be that the mine is not worked properly so as
not to yield enough return to the lessor in the shape of
royalty. In order to ensure for the lessor a regular income,
regardless of whether the mine is worked or not, a fixed
amount is provided to be paid to him by the lessee. This
is called ‘dead rent’. ‘Dead rent’ is calculated on the basis
of the area leased while royalty is calculated on the
quantity of minerals extracted or removed. Thus, while
dead rent is a fixed return to the lessor, royalty is a return
which varies with the quantity of minerals extracted or
removed. Since dead rent and royalty are both a return to
the lessor in respect of the area leased, looked at from
one point of view dead rent can be described as the
minimum guaranteed amount of royalty payable to the
lessor but calculated on the basis of the area leased and
not on the quantity of minerals extracted or removed.”
19
(1986) Supp SCC 20
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
57
20
In H.R.S. Murthy v. Collector of Chittoor too the
Constitution Bench of this Court had defined royalty to mean
“the payment made for the materials or minerals won from
the land”.
61. The judicial opinion as prevailing amongst the High
Courts may be noticed. A Full Bench of the High Court of
Orissa held in Laxmi Narayan Agarwalla v. State of
21
Orissa : (AIR p. 224, para 12) “[R]oyalty is the payment
made for the minerals extracted. It is not tax.” In Surajdin
22
Laxmanlal v. State of M.P., Nagpur a Division Bench of
the High Court of Madhya Pradesh referred to Wharton’s
Law Lexicon and Mozley & Whiteley’s Law Dictionary and
said (at AIR p. 130, para 7) “royalties are payments which
the Government may demand for the appropriation of
minerals, timber or other property belonging to the
Government”. The High Court opined that there are two
important features of royalty: ( i ) the payment is in proportion
to the quantity removed; and ( ii ) the basis of the payment is
an agreement.
… … …
71. We have clearly pointed out the said error, as we are fully
convinced in that regard and feel ourselves obliged
constitutionally, legally and morally to do so, lest the said
error should cause any further harm to the trend of
jurisprudential thought centring around the meaning of
“royalty”. We hold that royalty is not tax. Royalty is paid to
the owner of land who may be a private person and may not
necessarily be a State. A private person owning the land is
entitled to charge royalty but not tax. The lessor receives
royalty as his income and for the lessee the royalty paid is an
expenditure incurred. Royalty cannot be tax. We declare that
23
even in India Cement it was not the finding of the Court
that royalty is a tax. A statement caused by an apparent
20
AIR 1965 SC 177 : (1964) 6 SCR 666
21
AIR 1983 Ori 210 : (1983) 55 Cut LT 364 (FB)
22
AIR 1960 MP 129 : 1960 MPLJ 39
23
(1990) 1 SCC 12
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
58
typographical or inadvertent error in a judgment of the Court
should not be misunderstood as declaration of such law by
the Court. We also record our express dissent with that part
24
of the judgment in Mahalaxmi Fabric Mills Ltd. which
says (vide para 12 of SCC report) that there was no
23
“typographical error” in India Cement and that the said
conclusion that royalty is a tax logically flew from the earlier
paragraphs of the judgment.”
49. In State of Himachal Pradesh and Others vs. Gujarat Ambuja Cement
25
Ltd. and Another , a Bench of three Judges of this Court observed:-
“44. “Royalty” is not a term used in legal parlance for the
price of the goods sold. It is a payment reserved by the
grantor of a patent, lease of a mine or similar right, and
payable proportionately to the use made of the right by the
26
grantee as held in Titaghur Paper Mills Co. Ltd. case .
45. In its primary and natural sense “royalty” in the legal
world, is known as the equivalent or translation of “jura
regalia” or “jura regia”. Royal rights and prerogatives of a
sovereign are covered thereunder. In its secondary sense, the
word “royalty” would signify, as in mining leases, that part
of the reddendum, variable though, payable in cash or kind,
for rights and privileges obtained. (See Inderjeet Singh Sial
27
v. Karam Chand Thapar .)
46. “Royalty” is not a tax. Simply because the royalty is
levied by reference to the quantity of the minerals produced
and the impugned cess too is quantified by taking into
consideration the same quantity of the mineral produced, the
latter does not become royalty. The former is the rent of the
24
1995 Supp (1) SCC 642
25
(2005) 6 SCC 499
26
1985 Spp SCC 280 : 1985 SCC (Tax) 538
27
(1995) 6 SCC 166
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
59
land on which the mine is situated or the price of the
privilege of winning the minerals from the land parted with
by the Government in favour of the mining lessee. The cess
is a levy on mineral rights with impact on the land and
quantified by reference to the quantum of mineral produced.
The distinction, though fine, yet exists and is perceptible.
16
(See State of W.B. v. Kesoram Industries Ltd. ).
50. On the essential charcteristics of a tax, following observations of
Banumathi, J. in the concurring opinion in Jindal Stainless Limited and another
28
vs. State of Haryana and others cull out the essence:-
| “334. The essential characteristics of a tax are that: (i) it is | ||
|---|---|---|
| imposed under a statutory power without the taxpayer's | ||
| consent and the payment is enforced by law; (ii) it is an | ||
| imposition made for public purpose without reference to any | ||
| special benefit to be conferred on the payer of the tax; and | ||
| (iii) it is part of the common burden. In Commr., Hindu | ||
| Religious Endowments v. Sri Lakshmindra Thirtha Swamiar | ||
| of Sri Shirur Mutt13, the Constitution Bench has laid down | ||
| the characteristics of a tax which has since been consistently | ||
| followed and it is as under: (AIR p. 284, para 43) | ||
| “43. … “A tax” … ‘is a compulsory exaction of money | ||
| by a public authority for public purposes enforceable by | ||
| law and is not payment “for services rendered”.’ | ||
| This definition brings out, in all opinion, the essential | ||
| characteristics of a tax as distinguished from other forms | ||
| of imposition which, in a general sense, are included | ||
| within it. It is said that the essence of taxation is | ||
| compulsion, that is to say, it is imposed under statutory | ||
| power without the taxpayer's consent and the payment is | ||
| enforced by law. The second characteristic of tax is that it | ||
| is an imposition made for public purpose without |
28
(2017) 12 SCC 1
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
60
| reference to any special benefit to be conferred on the | ||
|---|---|---|
| payer of the tax. This is expressed by saying that the levy | ||
| of tax is for the purposes of general revenue, which when | ||
| collected forms part of the public revenues of the State. | ||
| As the object of a tax is, not to confer any special benefit | ||
| upon any particular individual there is as it is said, no | ||
| element of “quid pro quo” between the taxpayer and the | ||
| public authority.… Another feature of taxation is that as | ||
| it is a part of the common burden, the quantum of | ||
| imposition upon the taxpayer depends generally upon his | ||
| capacity to pay.” | ||
51. It is true that as a result of order passed by this Court in Mineral Area
29
Development Authority and Others vs. Steel Authority of India and Others ,
certain questions concerning “royalty” as determined under the provisions of
Mines and Minerals (Development and Regulation) Act, 1957 now stand
referred to a Bench of nine Judges, which reference is still pending
consideration. However, none of those issues arise in the present matter.
52. On the use of the expression “royalty” in a contract, we may note
following observations in Inderjeet Singh Sial and another vs. Karam Chand
27
Thapar and others :-
“ 12. … … The word ‘royalty’ thus, in the deed was used in
a loose sense so as to convey liability to make periodic
payments to the assignor for the period during which the
lease would subsist; payments dependent on the coal gotten
and extracted in quantities or on despatch. We have
therefore to construe document Ex. D-5 on its own terms and
29
(2011) 4 SCC 450
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
61
| not barely on the label or description given to the stipulated | |||
|---|---|---|---|
| payments. Conceivably this arrangement could well have | |||
| been given a shape by using another word. The word | |||
| ‘royalty’ was perhaps more handy for the authors to be | |||
| employed for an arrangement like this, so as to ensure | |||
| periodic payments. In no event could the parties be put to | |||
| blame for using the word ‘royalty’ as if arrogating to | |||
| themselves the royal or sovereign right of the State and then | |||
| make redundant the rights and obligations created by the | |||
| deed. | |||
| 13. The commodity goes by its value; not by the wrapper in | |||
| which it is packed. A man is known for his worth; not for | |||
| the clothes he wears. Royal robes worn by a beggar would | |||
| not make him a king. The document is weighed by its | |||
| content, not the title. One needs to go to the value, not the | |||
| glitter. All the same, we do not wish to minimise the | |||
| importance of the right words to be used in documents. What | |||
| we mean to express is that if the thought is clear, its | |||
| translation in words, spoken or written, may, more often | |||
| than not, tend to be faulty. More so in a language which is | |||
| not the mother tongue. Those faulted words cannot bounce | |||
| back to alter the thought. Thus in sum and substance when | |||
| the contracting parties and the draftsman are assumed to | |||
| have known that the word ‘royalty’ is meant to be employed | |||
| to secure for the State something out of what the State | |||
| conveys, their employment of that word for private ensuring | |||
| was not intended to confer on the assignor the status of the | |||
| sovereign or the State, and on that basis have the document | |||
| voided. … … ”. | |||
| 53. We may also note the following observations from the decision of a | |||
| Bench of three Judges of this Court in Union of India and others vs. Motion |
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
62
| Picture Association and others30, where the payment of fee was under the | ||
| terms of a contract between the parties. | ||
| “31. The exhibitors also contend that the charge of one per | ||
| cent on the net recoveries is a compulsory exaction in the | ||
| form of a tax. Neither the Act nor the provisions of the | ||
| licence stipulate payment of any such tax. Hence imposition | ||
| of this amount is in violation of Article 265 of the | ||
| Constitution. It is true that neither the relevant Act nor the | ||
| notification nor the rules nor the terms and conditions of the | ||
| licence stipulate the payment of any rental. This amount is | ||
| required to be paid under an agreement which the exhibitors | ||
| individually enter into with the Films Division for the supply | ||
| of these films. It is a payment under the terms of a contract | ||
| between the two parties. It cannot, therefore, be viewed as a | ||
| tax at all. The exhibitors contend that because they are | ||
| required to enter into these agreements, any payment under | ||
| the agreement is a compulsory exaction and is, therefore, | ||
| tax. We do not agree. Under the terms of the agreement, the | ||
| Films Division has to supply certain prints to the theatre | ||
| owners at stated intervals. The Films Division is required to | ||
| maintain a distribution network for this purpose. It is | ||
| required to pack these films and is required to allow the | ||
| exhibitors to retain these films in their possession for a | ||
| certain period. The films are to be returned to the Films | ||
| Division thereafter. The charge is termed in the agreement | ||
| as rental for the films. It covers charges for preparing the | ||
| prints of the films for distribution, and for packing them for | ||
| delivery. These are clearly services rendered by the Films | ||
| Division for which it is paid one per cent of the net collection | ||
| as a rental. As stated earlier, the total cost of preparing | ||
| prints, packing them and distributing them is much higher | ||
| than the total recovery made by the Films Division by way | ||
| of rental from all the exhibitors. There is a clear nexus | ||
| between the services rendered and the payment to be made. | ||
| The payment, therefore, is in the nature of a fee rather than | ||
| a tax though there may not be an exact quid pro quo. |
30
(1999) 6 SCC 150
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
63
Nevertheless the element of quid pro quo is very much
present.
32. The exhibitors relied upon a number of cases which
distinguish a tax from a fee. We will only refer to some of
them. In the case of District Council of the Jowai
31
Autonomous Distt. v. Dwet Singh Rymbai this Court held
that a compulsory exaction for public purposes would
amount to a tax while a payment for services rendered would
amount to a fee. On the facts in that case, the Court said that
there was no element of quid pro quo which will justify the
imposition of royalty as a fee. In Commr., H.R.E. v. Sri
13
Lakshmindra Thirtha Swamiar of Sri Shirur Mutt this
Court as far back as in 1954, laid down the distinction
between a tax and a fee. This Court has described a tax as a
compulsory exaction for public purposes which does not
require the taxpayer's consent; while fee is a charge for
specific service to some, and it must have some relation to
the expenses incurred for the service. In Ahmedabad Urban
Development Authority v. Sharadkumar Jayantikumar
32
Pasawalla this Court has said that an express authorisation
for the levy of a fee is necessary. In the present case,
however, the rental is charged by the Films Division by
virtue of an agreement between the Films Division and the
individual exhibitor. This is in consideration of the Films
Division supplying films to the exhibitor, packing the film
and arranging for its delivery. This is clearly an agreed fee
charged for rendering services. It cannot be viewed as a
compulsory exaction or as a tax. There is a statutory
obligation which is cast on the exhibitors to exhibit certain
films. To carry out this statutory obligation, if the exhibitors
enter into an agreement with the Films Division and agree
to pay a certain amount of rental for procuring the films from
the Films Division to comply with the statutory obligation,
the levy must, since it is correlated with the Films Division
discharging certain obligations under the contract, be
viewed, at the highest, as a fee and not as a tax. It is an
31
(1984) 4 SCC 38
32
(1992) 3 SCC 285 : AIR 1992 SC 2038
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
64
| agreed payment, and is not unreasonable. The High Court | |||
| has rightly negatived the contention of the respondent | |||
| exhibitors.” | |||
| 54. Thus, the expression ‘Royalty’ has consistently been construed to be | |||
| compensation paid for rights and privileges enjoyed by the grantee and | |||
| normally has its genesis in the agreement entered into between the | |||
| grantor and the grantee. As against tax which is imposed under a statutory | |||
| power without reference to any special benefit to be conferred on the payer | |||
| of the tax, the royalty would be in terms of the agreement between the parties | |||
| and normally has direct relationship with the benefit or privilege conferred | |||
| upon the grantee. | |||
| Whatever be the nomenclature, the charges for use of controlled | |||
| release of water in the present cases were for the privilege enjoyed by | |||
| INDSIL and CUMI. Like the case in Motion Picture Association31, the basis | |||
| for such charges was directly in terms of, and under the arrangement entered | |||
| into between the parties, though, not referable to any statutory instrument. | |||
| The controlled release of water made available to INDSIL and CUMI, has | |||
| always gone a long way in helping them in generation of electricity. For such | |||
| benefit or privilege conferred upon them, the Agreements arrived at between |
Civil Appeal Nos. 9845-9846 of 2016 etc.
M/s. Indsil Hydro Power and Manganese Limited vs. State of Kerala and Ors.
65
the parties contemplated payment of charges for such conferral of advantage.
Such charges, in our view, were perfectly justified.
55. The submission that it was compulsory exaction and thus assumed the
characteristics of a tax was completely incorrect and untenable. It was a pure
and simple contractual relationship between the parties and the Division
Bench was right in rejecting the submissions advanced by CUMI and
INDSIL.
56. Thus, all the submissions advanced on behalf of CUMI and INDSIL
are rejected. The instant appeals are, therefore, dismissed without any order
as to costs.
……..…………………….J.
[UDAY UMESH LALIT]
…..……………………….J.
[VINEET SARAN]
NEW DELHI;
September 06, 2021.