Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 15
PETITIONER:
SODAN SINGH
Vs.
RESPONDENT:
N.D.M.C. & ORS.
DATE OF JUDGMENT: 04/02/1998
BENCH:
S.B. MAJMUDAR, M. JAGANNADHA RAO.
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
M. JAGANNADHA RAO, J .
Leave granted.
This judgment is in continuation of two earlier
judgments of this Court rendered in this very case, which is
a public interest case concerning the hawkers, squatters,
etc, in the public streets in the New Delhi Municipal
Committee area. The first of the judgments WAS rendered by a
Connotation Bench on 30.8.1989 in Sodan Singh Vs. N.D.M.C. :
1989 (4) SCC 155 and the second was rendered on 13.3.1992 by
a three Judge Bench in Sodan Singh Vs. N.D.M.C 1992 (2) SCC
458. In sub - para 6 of para 10 of the latter judgment, all
cases then pending except one (the case now before us) were
treated as disposed of an claimants were permitted to seek
further directions in future as and when the Thareja
Committee Report (to which we shall presently refer) was
given. The said report WAS given in May 1996 and thereafter
about 130 I. As were filed in this S.L.P. pursuant to the
permission granted as stated above. We heard there IAs. We
have also heard the objections of the N.D.M.C. to the
Thareja Committee Report. Counsel made various submissions
on 6th, 7th & 8th January. Several IAs were rejected at the
time of the said hearing. In some IAs were the claimants
were found ‘eligible’ bu the Thareja Committee, orders were
passed adopting the recommendations of the Committee as
orders of the Court subject to "general directions" to be
given in the case now before us. Some IAs of ‘eiligible’
claimants were adjourned and are being disposed of
separately.
We shall make a berried reference to the events which
have taken place hitherto and then deal with the issues
argued before us.
The first Sodan Singh case- 1989 (4) SCC 155:
This decisions was by a Constitution Bench of this
Court and was rendered on 30.8.1989. It was held that the
right to carry on trade or business was not covered by
Article 21 of the Connotation of India but was covered by
Article 19 (1)(g) and could be reasonably restricted by law
made under Article 19(6). It was held that hawking on road -
sides fell within the expression ‘occupation, trade or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 15
business’ in Article 19(1)(g). It was also held that all
puce streets and roads vest in the State but the State holds
them as trustee on behalf of the public and the members of
the public are beneficiaries entitled to use them as a
matter of right. The Municipality has full authority to
permit ‘hawkers and squatters’ on the side walks wherever
the Municipality considers it practicable and convenient,
under the provisions of the Punjab Municipal Act, 1911 (or
Delhi Municipal Corporation Act, 1957). But there cannot be
a fundamental right vested in a citizen to occupy any
particular place on the pavement where he can squat and
engage in trading business. Nor can the hawkers assert a
fundamental right to occupy any place permanently on a
pavement. If the circumstances are appropriate and small
trader can do some business for personal guanine the
pavement to the advantage of the general public and without
discomfort or annoyance to others, there can be no
objection. Hawkers cannot be permitted to squat on every
road. Whether it is located close to a hospital or whether
there is need for security measures in a particular area,
etc. and similar eleventh factors has to be taken into
account for permitting business on a particular road.
Licence has to be given for trading but this does not mean
that licence is to be given on a daily basis. Regard must be
had also to the provisions of the Delhi Police Act, 1978 and
Delhi Control of Vehicular and other Traffic on Roads &
Streets Regulation, 1980. This Court, on a consideration of
all the above factors, directed the New Delhi Municipal
Committee to frame a scheme in regard to the areas or places
where hawking / squatting is to be permitted and as to the
number of squatters that could be allowed. The authorities
would be fully justified in refusing any facility to hawkers
who sell costly luxury articles. The right is basically for
poor hawkers and not to sellers of luxury items or smuggled
goods. Broadly, these are the directions given in the first
Sodan Sing’s case.
The NDMC Scheme: (10.11.1989)
Pursuant to the directions above stated, the N.D.M.C.
came forward with a detailed scheme on 10.11.1989. Under the
said scheme, the N.D.M.C. area was divided into 5 Zones and
the places where these squatters or hawkers could be
permitted to trade in each zone were identified. It was also
stated that squatting will not be permitted in certain areas
because of certain unique characteristics of the area or
because of the place being security-sensitive. However,
existing permission of Tehbazari or Kiosks in some of these
areas were not to be disturbed. Squatting would not be
permitted on the footpaths or on road so far as major roads
are concerned. No permissions, in verandah of markets which
have been declared as public streets, were to be granted.
Annexure A of the scheme gives details of places in
each zone where squatting/hawking could be permitted and the
total number, of the stalls, kiosks, pan tharas, Mocho
tharas, cycle repair tharas, telephone booths, tax booths,
vegetable tharas, tehbazari or tolerations which could be
given in each zone and also those which could be given on
compassionate grounds. Annexure B of the scheme gives the
total of stalls, kiosk, etc. already built as 108 degree and
states that the number of existing permissions for Tehbazari
is 228 and tolerations 106. Still, there are 1500 squatters
in N.D.M.C. area to be provide for a eligibility of
claimants was to be considered as per criteria stated in
para 6 of the Scheme.
Under para 6 of the scheme squatters were divide into 3
categories, (i) those before 1977. (ii) those between 1978
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 15
to 1980 and (iii) those between 1981 and 1987. The first
category who are the senior most, would get kiosks/stalls
subject to availability. Further, "till they are allotted
kiosks/stalls, they will be given permission for tehbazari
on usual charges". The second category of eligible squatters
of 1978-1980 will be given tehbazari permission in their
respective area subject to availability f stalls, unless
there are kiosks/stalls available as per their seniority.
The third category of eligible squatters of 1981 to 1987
would also be considered for allotment of tehbazari, in case
suitable vacant spaces in respective zones are available for
such allotment. A further procedure for reservation was
spelled out as follows:
(a) general category (60%) ; (b) SC/ST category (12 1/2%);
(c) physically handicapped (10%); (d) Ex-serviceman (2
1/2%); (e) war-widows (2%); (f) freedom fighters (3%); (g)
extreme hardship and humanitarian grounds (10%).
Paras 7 and 8 of the Scheme mention the conditions for
allotment of tehbazari. Only non-licensable trades excluding
sophisticated luxury items, imported or smuggled goods) are
to be permitted i.e. Pan, Biri, Cigarette, etc. No cooking
or sale of food items exposed to dust which could cause
health hazard, - was to be allotted. Para 9 of the Scheme
dealt with the issue of hawking licences. This question of
eligibility was to be examined by a Committee to be
appointed.
The Lok Adalat (Dated 19.11.1989) and recommendation as to
‘finality’.
After the Scheme was framed as above, a Lok Adalat,
presided by a learned Judge of this Court and a retired
Judge of the Allahabad High Court was held and the learned
Judges observed that the job allotment to individual
claimants should be given to a Committee consisting of 2
members from the N.D.M.C. and a Judicial Officer of the rank
of a District Judge. It was further directed that
"the decision by the Committee
shall be binding and final".
In other words, the decisions of the said allotment
Committee was to be final.
Supreme Court Orders dated 21.12.1989. 1.2.1990.
9.2.1990
We shall next briefly to refer to certain orders of
this Court. It was directed on 21.12.1989 that the District
Judge, Delhi should nominate a judicial officer with the
previous concurrence of the High Court to carry out the
suggestion made by the Lok Adalat. It was again directed on
1.2.1990 that initially 100 cases should be examine. By
another order dated 9.2.1990 it was directed that the
Judicial Officer nominated. could even make surprise
inspections etc. and work on a whole time basis.
The Judicial Officer nominated was Mr. Thareja. He gave
an interim repot. On 29.1.1991 this Court noticed that 5000
applications were pending before the Officer. This Court
directed that the Committee will consist only of Mr.
Thareja. In a latter order dated 28.10.1991. this Court
stated that the timings 4.00 Pm to 9.00 PM suggested by the
N.D.M.C. for the hawkers were not acceptable and that 12.00
Noon to 7.00 PM could be more appropriate.
The second Sodan Singh Case: [1992 (2) SCC 458]
(13.3.196)
The second judgment is dated 13.3.1992. This court,
initially rejected the complaint that the Thareja Committee
was applying very strict standards of proof for eligibility
and that this was affecting interests of bonafide claimants.
But in order to protect genuine claimants, this Court gave a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 15
set of nine directions. We do not propose to refer to all of
them except two. Under direction 8, the Thareja Committee
was to draw up a list of squatters/hawkers identified by it.
Under direction 9. the Committee was to draw up a seniority
list of squatters/hawkers and the Committee was to already
identified". All pending cases were to be treated a disposed
of, except one case. No Court was to entertain any fresh
case.
Public notice & cut off dated (22.5.1992):
As directed in para 12 of the second Sodan Singh’s
case, public notice was give inviting claims before the
Thareja Committee and cut off date namely 22.5.1992 was
fixed. Pursuant thereto, several claims were received. In
all, there were 5627 claims before the Committee, including
126 review petitions.
The Thareja Committee Report (May, 1996):
The Committee examined 5627 claims in a very detailed
fashion during a period of 5 1/2 years and passed detailed
orders in every case, examining the evidence produced by
both sides. We have gone through the Report and have also
read a large number of individual orders passed by the
Committee. It was against those orders that the 130 I. As
were filed in this Court questioning the adverse orders
passed against some of the claimants.
We must place on record our deep sense of appreciation
for the tremendous work dome by Mr. Thareja and the trouble
he had taken in completing these cases. He had also visited
the places where the hawking was being done or was claimed
as being done, - on various occasions with or without notice
to verify facts. He has also applied a judicial and
humanitarian approach to the problems of the hawkers. At the
sametime, he has also took care to apply principles which
eliminated any possible manipulations by the employees of
the N.D.M.C. or exploitation by them of these
squatters/hawkers regarding which there were complaints
before him.
The Thareja Committee took up the question of
identification of sites. Fourteen sub areas in the 5 zones
were identified., Others areas which were not accepted by
N.D.M.C., were subjected to detailed serenity to find out if
the objections raised by the NDMC were tenable. The Thareja
Committee, in Chapter II, has dealt with the individual
sites in each zone (page 56 to 310) and took up the
objections to the NDMC in respect of each site, and rejected
almost all the objections of the N.D.M.C., particularly in
regard to lucrative areas. The Committee has given elaborate
and very tenable and rational reasons. This part of the
Report is from page 56 to page 310, nearly 250 pages. we
shall deal with these areas lower down. The Committee has
also gone into claims of individual claimants and found only
760 as eligible persons to be accommodated. This figure is
in addition to the cases of ‘hardship’. The Committee also
compiled a separate volume (volume 2) of the Report in
respect of the names of eligible applicants, their trade,
and their seniority and details of the area occupied (6’x 4’
or 4 x 3’ or stall - kiosk) along with the photograph of the
particular claimant. The Committee here referred to the 760
claimants and also the other cases coming under the category
of hardship. This volume 2 runs to more than 200 pages. As
to eligibility of squatting at various places, the Committee
considered several claimants eligible and made tentative
allotments, subject to final allotment later on. The
Committee said (page 38 of its Report):
"Since the N.D.M.C. is contesting
the sites identified, it is yet not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 15
finally settled which sites are
available for purposes of
allocation to the squatters. The
sites identified have been dealt
with in Chapter II....Thus even the
list of squatters is not final as
yet. In this views of the matter,
no site has ben allocated to an
individual squatter. The scheme of
allocation of sites, however, bas
been described in brief in Chapter
III. The sites can be actually
allocated only after the identified
sites are approved by the Hon’ble
Supreme Court, the Scheme for
allocation is approved and also the
list of identified squatters is
finalised".
Thus the occupation of these places by eligible
squatters as decided by the Thareja Committee is only
tentative and subject to regular allotment after a decisions
arrived at as to whether the places in regard to which the
NDMC claimed exclusion (see below) would be accepted by the
Thareja Committee and by this Court. The tentative
allocation by the Thareja Committee is also subject to
further final allotment on the basis of priorities between
the three groups of squatters i.e. those before 1977 to
1987. Final allotment depended also on Seniority and
reservation ratio of the squatters in each of the three
groups.
An important aspect of timings as to "squatting.
hawkers " was considered by the Committee (pages 44-45) to
say that neither the hawkers nor the N.D.M.C. officials were
acting in accordance with the timings referred to by this
Court in one of its orders dated 28.10.1991. It was pointed
out by the Committee that those who were settling with
N.D.M.C. officials were being allowed all 24 hours while
others not so inclined were being harassed and discriminated
against. This resulted din a flood of IAs being filed before
the Committee in regale to timings alone. The Thareja
Committee therefore recommended time schedule as "sun-rise
to sun-set" - as has been granted to tehbazari". We accept
this recommendation to the above said extent. One of the
eligibility criteria followed by Thready Committee;
In respect of the period
(1) prior to 1977
(2) 1978-80
(3) 1981-87
The Thareja Committee was prepared to condone absence of
proof of squatting/hawking only for one year. Further the
squatting/hawking after 187 putto date of inspection by the
Committee has been also gone into. In other Words those who
were squatting in the periods (withal one year gap) were to
be squatting even after 1988. For the period after 1988 also
only one year gap has ben condoned. This principle was
followed uniformly. Some claimants whose claims were
rejected on this basis have filed IAs. We have rejected them
as we have agreed with the principles adopted by the Thareja
Committee.
Submissions of N.D.M.C. in this Court in regard to rejection
of NDMC’s objections to some sites:
In regard to the some important and if fact lucrative
areas to which the N.D.M.C. had objection before the
Committee and which objections were rejected by the Thareja
Committee, the N.D.M.C. has filed before us its written
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 15
submissions on 19.7.1997. The said objections (at pp 77 to
84 in the paper book of IA 3/91) also list out 76 sites for
which the N.D.M.C. has no objection. While making these
written submissions, the NDMC has also given number of
kiosks and/or tehbazari which could be accommodated in
various places for which there was no objection. Total
number of the available places is also given.
In addition 7 sites are proposed by the N.D.M.C. mostly
for kiosks or for covered Thara and, one place for 6
tehbazari.
The Thareja Committee while rejecting the objection of
the NDMC in respect of these areas and including them in the
list of acceptable places, has also given the figures of how
many kiosks, squatter or tehbazari can be accommodate in
these areas.
Objections were raised before us by the NDMC in regard
to (i) 26 important places in the various zones, (ii) place
in Sarojini Nagar and (ii) six other places in some zones -
in all 33. Learned senior counsel for the N.D.M.C. Sri R.K.
Maheshwari made his submissions in regard to each of these
items and referred to the reasons give by Mr. Thareja and
contended that these sites were wrongly included by the
Committee and have to be excluded and further that the
reasons given by the Thareja Committee are not sound.
The objections of the N.D.M.C. in respect of these
sites fall into the various categories : (i) Pedestrians
hindrances and major road, (ii) falls under development
scheme (iii) adds to congestion (iv) disturbs unique
character of Connaught Place (v) traffic congestion (vi)
security problem and major road (vii) over crowded (vii)
over congested (ix) no further scope. Part 9 of the report
of the Thareja Committee from pp 56 to 310 dealing with
these aspects has been read before us by the learned counsel
for NDMC for 2 days on 6th and 7th January. taking up item
by item. The reasons given by the Thareja Committee were
challenged.
We have heard these submissions and have also gone
through the elaborate reasons given by the Thareja Committee
in regard to each of these 33 places. We do not propose to
record our reasons nor to deal with each item independently.
We are indeed not sitting in appeal. Further, we are keeping
in mind the recommendation as to ‘finality’ made in the Lok
Adalat on 19.11.1989. Further the plea of the NDMC that
certain areas fall under ‘development scheme’ was a plea not
raised before the Thareja Committee and has been raised for
the first time before us. We find that the Redevelopment
Scheme prepared by the DDA is of March 1993 and the NDMC had
full knowledge thereof long before May 1996 when the Thareja
Committee Report was submitted to this court. Hence this
ground is liable to be rejected. We are satisfied that Mr.
Thareja has based his conclusions on valid material and on
the existing factual position at the grass-root levee. He
has also relied upon factual information gathered from
personal visits made by him to these places and kept in mind
the manner in which, the N.D.M.C. had itself already granted
certain kiosks, squatting or tehbazari rights in these very
areas earlier. In our view no exception can be taken to the
reasoning and conclusions of the Thready Committee in regard
to these items and to its ultimate recommendations to the
suitability (or otherwise) of these areas. We do not find
any grounds to modify or set aside the recommendations in
regard to these sites. In the result, we accept the
recommendation, reject the objection of the NDMC and
therefore these 33 sites would get added to the 76 and 7
sites already mentioned - resulting in 116 sites. (In this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 15
connection, our order in IA No. 114/97 may also be seen).
As already stated, the Thareja Committee also decided
the relative seniority of each claimant and wherever
individual claimants have questioned the adverse orders
passed by the Committee, we have passed separate orders in
the IAs. Subject to the orders passed in the IAs, the
recommendations of the Committee as to seniority are
accepted by us.
The Committee has recommended the procedure that could
be followed while making final allotments. It reads as
follows (p.309):
"....the squatters who have been
identified have been shows as per
the seniority in the list of
squatters squatting in respective
areas. The allocation of sites,
accordingly is to be made as per
the seniority of the squatters
identified in the area. To do this,
it is proposed that the squatters
of the particular area be invited
to give their preference for sites
available in that area, with
respect to the trade as approved in
consultation with the NDMC. Where a
site is preferred by an individual
squatter only, the same be
allocated to him. Where a
particular site has been preferred
by more than one squatter, then the
same be allocated by seniority or
by the system of draw of lots for
the first five senior squatters for
one site. A squatter shall be
eligible to give his preference for
only three sites so that a large
number of applications for one
single site is avoided. Such an
approach, it is felt shall not
result in objection from any of the
squatters and will be in fair
play."
In other words, apart from seniority, each eligible
squatter should be allowed three sites as options in the
zone.
We accept the above procedure recommended by the
Thareja Committee and the recommendation for giving three
options in the zone subject only to one modification that
the allocation will be accordingly to seniority as decided
by the Committee and not by draw of lots as alternatively
suggested by the Committee.
The concluding para of the Committee report reiterates
that the allotments made by the Committee are only tentative
and that final allotment has to be made after this Court
passes orders on the Committees Report. This part of the
recommendation (which is similar to recommendations at page
38 of its report) reads as follows (p.310):
"At present. it is not possible to
allocate a site to an individual
squatting in the area of NDMC as
the NDMC is contesting the
identified sites and it is not yet
finally decided by the Honorable
Supreme Court as to which sites are
available for purposes of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 15
allocation to the
squatters/hawkers. Various
petitions for directions against
the claims rejected by the
squatters are still pending
consideration before the Supreme
Court. The lists of the squatters
also cannot be said to be final as
yet. it is only after the petitions
for directions are decided that the
list of squatters can be said to be
final and the identified sites are
approved by the Supreme Court. that
the task of allocation of sites can
be done. Accordingly, the report is
submitted with respect to the
allocation of sites as was desired
by the Honorable Supreme Court in
its Order dated 23.9.1994."
Therefore, the allocation of palaces, if any, done by
the Thareja Committee in individual cases, is only tentative
inasmuch as new places have been added, seniority is now
fixed and three options are to be now given by each person
and question of reservation is also to be considered. Now
that the IAs regarding claims of squatters whose claims have
been rejected by the Committee have also been disposed of by
us and the seniority list stands accepted, and the
objections of the NDMC for excluding certain areas stand
rejected, while some areas ares suggested by the NDMC have
got added, the stage is therefore set for final allocation
of the sites to the various claimants. While making
allotments for squatters\tehbazari the proportion as to
reservation motioned in the scheme will also have to be
followed. We are, therefore, proposing that after a public
notice to be issued by the authority whom we propose to
nominate, claims will be filed in Part I by the eligible
claimants (Part II will deal with arrears of Tehbazari
charges).
Arrears if tehbazari charges:
The Thareja Committee has recommended that all
squatters who have been given seniority and eligibility for
allotment should pay arrears of dues towards tehbazari
within 2 weeks and that in case of failure to pay, the
claimant would not be entitled to benefit under the Scheme.
The said Committee also suggested that all approved
claimants - though they were squatting prior to 1.1.1990 and
were allowed to continue under orders passed by the
Committee, - should pay the arrears of tehbazari charges
only from 1.1.1990 and that the arrears proof to 1.1.1990 be
waived by the NDMC.
So far as waiver of the arrears of tehbazari charges
prior to 1.1.1990 by the NDMC is concerned, we heard
arguments and considered the facts and circumstances of the
case and we accept this recommendation.
So far as arrears after 1.1.1990 are concerned, it has
been stated before us that the tehbazari charges for a space
of 6’ x 4’ are Rs. 240/- p.m. and that for a space of 4’ x
3’ are Rs. 120/- p.m. There was considerable argument before
us as to whether in order to avoid dispute as to what is the
actual amount in arrears after 1.1.1990. we should fix a
lump sum amount applicable to all claimants or whether we
should order an enquiry into individual cases where there is
dispute as to the period of occupation. Having considered
this aspect carefully we are not inclined to fix a lump sum.
We are of the view that the authority whom we propose to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 15
nominate should examine, in case of dispute, the facts in
each case relating to arrears of tehbazari charges for the
period after 1.1.1990 and decide the extent of arrears in
each case after giving a reasonable opportunity of being
heard, to the claimants found eligible by the Thareja
Committee wherever there is a dispute as to the amount of
arrear. We also direct that deduction will be given for any
amounts already paid for the period after 1.1.1990 provided
adequate proof is produced therefor.
It has been argued for the NDMC that unless the arrears
are paid, the eligible claimants should not be allowed to
conduct their trade at the places tentatively allocated to
them or where they have been lawfully conducting their
trade. We are unable to agree with this contention
particularly because we have directed an iniquity into the
arrears after 1.1.1990, wherever the quantum is in dispute.
We are of the view pending a decision on arrears that the
current tentative occupation by these persons of any places,
as decided by the Thareja Committee, need not be disturbed.
The claimants will be permitted to carry on their avocations
at the places tentatively designated by the Thareja
Committee, subject of course to final allotment of places by
the authority to whom we propose to entrust the job for such
final allotment.
The authority whom we propose to designate shall, as
per the procedure for public notice indicated below, require
eligible claimants to file in Part II of their application,
details as to the Tehbazari charges paid after 1.1.1990, so
that the issue of arrears, if any, is not raked up after the
issue of allotment of site is finalised. Booth issued could
be decided more or less simultaneously, so that in case the
arrears finally determined are not paid, the final allotment
of site could be made to another eligible person by the new
Committee.
Construction of Kiosks: time to be fixed etc.:
As pointed by the Thareja Committee, those claimants
who are senior most would be allotted kiosks/stalls as
mentioned in the Report. It is however stated by the learned
counsel for the NDMC that the kiosks to be constructed are
92 in number and that construction of these kiosks at the
places identified by the Thareja Committee would take some
time and there is also need for obtaining adequate budgetary
provision for these purposes. Question has also arisen as to
whether at these places where the kiosks are to be
constructed by the NDMC, the places should be kept idle till
such time as the kiosks are constructed.
It has been rightly suggested by Shri Maheshwari for
the NDMC that it is not necessary to keep these places
identified for construction of kiosks idle till the kiosks
are actually constructed. In the meantime, those to whom
these kiosks have been allocated by the Thareja Committee
tentatively or who have already been authorisedly
continuing, will continue to squat at the places where the
kiosks are to come up and conduct their avocation subject to
any final allotment that may be made by the authority whom
we propose to dominate.
It has been argued for the NDMC that so far as the
construction of these kiosks is concerned, permission may be
obtained from Delhi Urban Arts Commission and also from the
Archaeological Survey of India and the Department Capital
Territory, New Delhi. If such a procedure is warranted by
law, surely the NDMC may follow the same. But, in the
meanwhile, if tentative allotment is already made by the
Thareja Committee or there are authorised occupants, they
will not be disturbed, pending construction of kiosks.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 15
Further if there are any ‘unauthorised’ persons at these
places where kiosks are to be constructed - conducting
tehbazari or squatting, - such persons shall forthwith be
removed from those places by the NDMC.
In the event of the Urban Arts Commission or the
Archaeology Departments mentioned above not approving any of
these sites for kiosks identified by the Thareja Committee,
the said places shall be available for tehbazari and the
authority whom we propose to nominate, shall consider the
said places for tehbazari and make such allotment as he may
deem fit, in accordance with the procedure already
indicated.
For the purpose of obtaining clearance from the
aforesaid authorities, we grant time to the NDMC putto
30.6.1998. Copy of our order will be communicated to the
above departments i.e. Delhi Urban Arts Commission;
Archaeology Survey of India, New Delhi and Department of
ARCHAEOLOGY, N.C.T., New Delhi.
Immediate eviction of unauthorised squatters/hawkers:
A reading of the Thareja Report and connected documents
does show that is several areas unauthorised squatters or
hawkers have been allowed to conduct their operations. It is
alleged by the learned counsel appearing for the
squatters/hawkers that this is done is collusion with the
NDMC or officers of other departments and this should be
stopped forthwith. In fact, it is vehemently argued that
such unauthorised squatters/hawkers are there in places in
respect of which the NDMC claimed exclusion on pleas of
heavy traffic sensitivity etc. It was therefore agreed
before us by the learned counsel for the NDMC, Sri
Maheshwari that these unauthorised squatters/hawkers will be
removed by the NDMC forthwith.
We are of the view that these persons should be removed
forthwith and that it is not necessary to wait till the
final allotment of these sites to the eligible claimants. We
accordingly direct that the unauthorised squatters/hawkers
trading at the places recommended by the Thareja Committee
or suggested by the NDMC - which have now been accepted by
us - should be removed by the NDMC within one week from
today and the NDMC shall also ensure that, in future, no
unauthorised squatter/hawker conduct his triad at the places
accepted by the Thareja Committee and by this Court. We make
it clear that if the above directions are violated by the
NDMC, it may call for serious action from this Court. It
will also be open to the authority whom we propose to
appoint to bring to the notice of this Court any breach by
the NDMC of this direction.
Mode of issuing public notice. fixing cut-off and
procedure for hearing before the authority:
We have already stated that for the purpose of final
allotment of the places to the authorised squatters/hawkers
as per their seniority, and to consider the three options of
each person, and for the purpose of deciding the quantum of
arrears of tehbazari charges for the period after 1.1.1990,
we will be nominating a particular authority. Question has
arisen s to what procedure he should adopt.
Public notice: inviting applications - Part I
(allotment of sites)
Initially he will issue a public notice that the
eligible claimants may submit their applications in respect
of the 116 sites and in Part I of their application they
shall state their claim in regard to the size (whether 6’ x
4’ or 4’ x 8’) within the respective Zones - restricting
choice to three places in each Zone - and quoting their
seniority ad decided by the Thareja Committee. (The option
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 15
in all will be only for 3 places in the zone). The public
notice shall also require the eligible claimants to state in
Part II details of the arrears of tehbazari charges from
1.1.90 and if there are arrears as on date or not. Public
Notice will be issued in one English and one Hindi Newspaper
having circulation in Delhi in this behalf. Such notices
will also be put up at the various offices of the NDMC. It
will also be stated that claimants can purr forward their
claims within three weeks (a specific cut off date is to be
given) before which the applications is to reach the
authority whom we propose to nominate. It shall also be
stated in the public notice in the newspaper that for the
purpose of giving the three options, the claimants can
ascertain. if necessary, the details of the location and
size of these 116 places for which they would give their
options - from the Notice Board of the NDMC at specified
places. We are emphasising this aspect to obviate any
grievance that the eligible claimants did not know details
of the available places in each Zone or the size and to
eliminate any grievance that they did not have a reasonable
opportunity of submitting the three options.
Public notice - Part II of application: (arrears of
Tehbazari)
As already stated, we have also required a statement
from the claimants regarding arrears of tehbazari charges in
Part II so that the question of arrears can also be
simultaneously decided and so that in case the amount is
decided and not paid and the claimant loses his eligibility
but to non-payment, the new Committee can proceed to
consider if the vacancy so available could be allocated to
some other eligible candidate, if any, who did not got any
allotment.
Cut off date for filing application and further notice
of hearing to petitioners or counsel
After receipt of the claims which are received on or
before the cut-off date indicated in the public notice the
nominated authority shall issue notices to the claimants by
registered post-A.D. fixing particular dates for hearing. It
could also - if it considers it necessary - issue a general
public notice through the NDMC that eligible claimant who
have lodged their claims, could appear before the nominated
authority on or before a particular date, for orally
submitting their case.
The nominated authority will decide rival options for
each place and for the that purpose it may evolve its own
procedure consistent with natural justice. On the question
of arrears from 1.1.1990 also separate orders will be
passed. Hearing will be given to the claimants who could
either represent their cases personally or through counsel,
Reasoned orders will be passed by the nominated authority
and the decisions shall be final and shall not be questioned
before any authority, tribunal or court or law or the High
Court of Delhi nor in this Court. In other words, as
recommended in the Lok Adalat on 19.11.1989. the decision of
the authority both on questions of allotment of place and
arrears due shall be binding on the claimants and the NDMC
as well.
Ban on further IAs:
We also direct that as from today, no IAs will be
allowed to be filed against the Thareja Committee Report or
against individual orders passed by the said Committee
before it submitted its Report in his Court. The IAs, if any
pending, as of date will be listed for final disposal so
that by the time the authority we propose to nominate, gives
its public notice, all the pending IAs are disposed of by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 15
this Court.
We are giving this direction to put a seal of finality
to the decisions of the authority so that the problems
arising out of this PIL case in respect of the squatters /
hawkers which have been pending in this Court since 1989
could come to an end atleast in 1998.
Change of trade:
(i) general right to change in trade:
This aspect is somewhat important. The first Sodan
Singh Case upheld the right to trade under Article 19(1)(g)
of the Constitution of India on the payment and sidewalks
without however, interfering with the freedom of others
using these places. This right could also be subject to
reasonable restrictions, if any, made by law under Article
19(6). As yet no such special law has been brought to our
notice except the Delhi Police Act, 1978 and Delhi (Control
of Vehicular and other traffic on Roads and Streets
Regulation) Act, 1980, referred to in the first Sodan Sing’s
Case. Of course, certain provisions of the Punjab
Municipality Act, Rules or bye laws thereunder could also be
relevant. In addition, the Scheme issued by the NDMC
pursuant to orders of this Court permits non-licensable
trades (excluding luxury and smuggled outlets) Further this
Court had also stated in the first Sodan Singh’s Case that
the grant of hawking/squatting right is not meant for
luxurious items or smuggled goods.
In IA No.83 of 1995. in which we have today passed a
separate order, the claimant, Bishwanath Roy, who was
trading in ‘tea’ wanted to change over to garments. The NDMC
took the stand that it had a discretion either to grant or
not to grant the change in trade to garments and it would
take up the issue after the Thareja Committee gave no
objection. The Thareja Committee did not pass final orders
but dealt with this question in its report. It pointed out
that absolute discretion for change of trade even in respect
of non-licensable trades cannot be granted to the NDMC and
that, for exampled there are some locations where the
business of hawkers could yield substantial gross income per
day and therefore abuse of discretion by the NDMC officials
could not be ruled out. Bearing all these factors in mind,
we have allowed IA No.83 of 1995 for change of trade to
garments in that case as such trade was not unlawful and was
not one in ‘luxurious goods’ or ‘smuggled goods’ and we
added the NDMC could, at the most, imposer reasonable with
Article 19(1)(g) (and Article 19(2). We have also stated
that in the matter of change of trade, if the NDMC’s orders
or the conditions imposed are unreasonable or arbitrary or
contrary to any provisions of law, if would be open to the
aggrieved parties to avail all remedies at law. We reiterate
the same position in this order also.
(ii) Lotteries:
In certain cases the eligible squatters were presently
selling lotteries which have since been barred. As agreed to
before us by some counsel appearing for those selling
lotteries, such claimants will, apply to the concerned
authority in the NDMC for change of trade. The NDMC shall,
if such new trade is not a prohibited one nor one relating
to imported or luxury items, grant the request for change in
trade. Such claimants will indicate in Part 1 of their
application as to whether they have (or are proposing to),
applied for change of trade from lottery to any other non-
prohibited trade.
Appointment of Shri V.C. Chaturvedi and infrastructure:
We hereby nominate Sri V.C. Chaturvedi, presently
working as Joint Registrar in the High Court of Delhi to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 15
undertake the various duties and functions enumerated as
above (which are again summarised below) and complete the
job, as far as possible, within a period of a 6 months from
the date of receipt of this order. We request the High Court
of Delhi to spare his services, during the remaining period
of his service as Joint Registrar in the Delhi High Court,
for the aforesaid purpose. ( We are passing separate orders
in connection with his remuneration, in this very SLP.) We
direct the NDMC to issue orders directing the Directorate
of Estates and the Director of Enforcement to help and
implement the decisions or directions or orders of Sri V.C.
Chaturvedi. The NDMC is directed to provide a place for the
office of Sri V.C. Chaturvedi, clerical staff, stenographer
and class IV employees and all other infrastructure required
by Sri V.C. Chaturvedi for the purpose of facilitating early
disposal of the matters. If any assistance or clarification
is required by Sri V.C. Chaturvedi, it shall be open to him
to seek appropriate directions from this Court by filling
IAs in this SLP, even though this SLP is disposed of. Nobody
else will be entitled to file any application or proceedings
before any other tribunal, Court of law, High Court or this
Court to challenge any orders passed by Sri V.C. Chaturvedi
on any ground whatsoever.
Summary of procedure to be followed by the Chaturvedi
Committee and N.D.M.C.
1. Sri Chaturvedi Committee (sole member) shall issue
public notice in an English and a Hindi Newspaper (expenses
to be borne by the NDMC) within 15 days from today
permitting the eligible claimants so found eligible by the
Thareja Committee to submit their application in Part I.
containing options in regard to the identified places and
sizes (whether 6’ x 4’ or 4’ x 3’) in the particular zone to
which these claims belong. The public notice in he newspaper
will state that the details regarding the available sites
and their locations and size is put up on the Notice Boards
of the NDMC at various place, whose addresses are given.
The notice will also require the claimants to state in Part
II of their applications the details as to payment of
Tehbazari charges due after 1.1.1990 and if there are or nor
any arrears as on date. The notice will also be put up in
the varies offices of the NDMC within the above said period.
The notice in NDMC office will also give a detailed list of
the places available for squatting/hawking and stating
whether it is a kiosk/stall or a place for mere vending on
Tehbazari basis as decided by the Thareja Committee and
indicating their sizes (6’ x 4’ or 4’ x 3’).
2. The eligible claimants will be given 3 weeks time to
file in Part I of their application their three options,
indicating the zone concerned, their seniority as decided by
Thareja Committee, stating whether they come under any
reservations category, the type of trade they have been
trading in or the new trade for which they have applied to
the NDMC and such other particulars as may be called for or
relevant. In Part II the eligible claimants shall specify if
they have made payments of Tehbazari arrears due for the
period after 1.1.1990 and it there are any arrears as on
date.
3. After receipt of the claims, Committee shall issue
notice to the concerned parties and the NDMC in regard to
each of the places at which squatting/hawking is permitted
as per the Thareja Committee Report and decide on the basis
of seniority and reservation, size of place and such other
relevant material as may be placed before the Committee, as
to who should be allotted at what place. The Committee shall
fix up dates of hearing by issuing Registered A.D. notices
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 15
to the parties concerned. (The expenditure in this behalf
shall be borne by the NDMC.) The Committee shall give an
opportunity of being heard and pass reasoned orders and its
decisions shall be final and shall not be questioned before
any other authority, tribunal, Court, nor the High Court nor
in this Court.
4. It shall however be open to Sri Chaturvedi to obtain,
if necessary, such direction or clarifications from this
Court by way of filing IAs in this SLP, even though it is
now disposed of.
5. The claimants will be permitted to appear before the
Chaturvedi Committee either in person or through their
counsel.
6. In case it is decided by the Chaturvedi Committee after
the hearing of the case in Part II that any eligible
claimant is in arrears of tehbazari dues for any period
after 1.1.1990 then the said Committee shall fix a date
before which the arrears have to be paid and informing that
if the amount is not paid by that date, the claimant will
lose his claim for the kiosk/stall or for the place. In case
the claimants rights cease as stated above, the Chaturvedi
Committee will consider if the vacancy can be allotted to
any other claimant already declared eligible by the Thareja
Committee.
7. In case any of the placed found eligible for
kiosks/stalls by the Thareja Committee are not accepted by
the Urban Arts Commission or the Archaeological Survey of
India and the Department of Archaeology of the Govt. of NCT,
the said places meant for kiosks/stall shall be available
for tehbazari and the Chaturvedi Committee shall pass
appropriate orders of allotment on that basis. As and when
the above said authorities inform the NDMC that the places
earmarked for kiosks/stalls are not acceptable for that
purpose, the NDMC shall inform the Chaturvedi Committee
about the said decision. (We have already observed that
pending construction of kiosk/stall the claimant tentatively
allotted the place or other person authorisedly using the
place for vending on Tehbazari; shall continue. We also said
unauthorised persons vending at these places be evicted by
the NDMC forthwith.)
For the purpose of obtaining clearance for the said
authority, the NDMC is granted time putto 30.6.1998 and for
construction of the Kiosks/stalls putto 31.10.1998.
8. In regard to eviction of unauthorised squatters of
other persons using the placed identified by the Thareja
Committee the NDMC has undertaken to have them evicted
forthwith and in case this is not done, it will be open to
the Chaturvedi Committee to bring it to the notice of this
Court for appropriate orders, as stated earlier.
9. The NDMC in general and the Director of Estates and the
Director of Enforcement in particular will help and
implement the decisions, directions or orders of Sri V.C.
Chaturvedi. The NDMC shall also provide the other
infrastructure to Sri Chaturvedi as stated in the main body
of this order and pay his remuneration (in regard to which
we are passing separate orders in this SLP).
10. The decisions of the Chaturvedi Committee both on the
question of allotment of the kiosk/stall or the sites for
tehbazari and also as to quantum of arrears of tehbazari
shall be final as indicted in the body of this order and
shall not be questioned either by the claimants or the NDMC
before any authority. Tribunal, a Court of Law, the High
Court or in this Court. No petition shall be registered in
this behalf by the above bodies. We have only permitted the
Chaturvedi Committee to file IAs in the appeal seeking any
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 15
direction or clarification and none others. So far so orders
of NDMC in regard to change of trade, it is open to the
affected parties to resort to all appropriate remedies. We
have so permitted Sri Chaturvedi to move this court in
certain respects.
The above summary is in addition to directions
contained in the main body of this Judgment. The Civil
Appeal stands dispose of.