Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 4806 of 2000
PETITIONER:
K.N. Sathyapalan (Dead) By Lrs.
RESPONDENT:
State of Kerala & Anr.
DATE OF JUDGMENT: 30/11/2006
BENCH:
Dr.AR. Lakshmanan & Altamas Kabir
JUDGMENT:
J U D G M E N T
ALTAMAS KABIR,J.
The appellant entered into an agreement with the
State of Kerala on 10th October, 1985 whereunder he was
entrusted with the construction work of the Chavara
Distributory from Ch.7440M to 9440M and 10475M to
14767M. Disputes having arisen between the parties, the
matter was referred to arbitration. The Superintending
Engineer, Siruvani Project, Palghat, .the designated Arbitrator
in terms of the contract, was appointed as the sole Arbitrator.
By his award, which was published on 2nd September, 1989,
the Arbitrator awarded a total sum of Rs. 42,21,000/- with
12% interest per annum from the date of the award. Upon
the passing of the award the appellant herein filed O.P. (Arb.)
40/89 in the court below under Section 17 of the Arbitration
Act for passing a decree in terms of the award. The State of
Kerala filed a petition under Section 30 of the Act challenging
the award and for setting aside the same.
The application filed by the State was dismissed and
aggrieved thereby the State of Kerala preferred an appeal in
the High Court of Kerala at Ernakulam, being MFA No. 980 of
1990 C.
The appellant herein raised claims under 12 different
heads but the Arbitrator allowed only claims (a), (e), (g), (i) and
(k). Although, in the memorandum of appeal, the entire award
in favour of the appellant had been challenged, but the
arguments were addressed only with regard to claims under
heads (a), (g), (i) and (k). A preliminary objection was raised
in the appeal that the Superintending Engineer, who had been
appointed as the Arbitrator and had entered on the reference,
had been suspended from service for gross mal-practice, and
the Government had informed all concerned that the
Arbitrator was not to continue with the reference. The
Arbitrator retired on superannuation while he was under
suspension and the award was made after his retirement.
According to the State of Kerala, in the circumstances, the
award passed by the Arbitrator was without jurisdiction.
The aforesaid objection being preliminary in nature, the
same was taken up first for consideration and it was held by
the High Court that such an objection was without any merit.
The Arbitrator, who was working as Superintending Engineer
was placed under suspension on 31st May, 1989. As per an
agreement between the parties on 14th February, 1989, the
time for making and publishing the award was extended upto
14th June, 1989. Even after the Arbitrator was suspended
from service, both sides had agreed on 14th June, 1989 to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
extend the time further for making and publishing the award
upto 14th October, 1989. The Arbitrator retired from service
while under suspension on 30th June, 1989. In the light of
the said facts, the High Court agreed that the court below
could not revoke the authority of the Arbitrator, which could
only be done under Section 5 of the Arbitration Act, with the
leave of the Court. Accordingly, the preliminary objection
raised on behalf of the State of Kerala that the Arbitrator had
no authority to continue with the arbitration after his
suspension or retirement, was rejected by the High Court.
Claim (a) of the appellant herein involved the claimant’s
entitlement to get compensation for interruption of work by
anti-social elements and failure of the Department in removing
such miscreants from the sites which caused the claimant
heavy financial losses by way of idle men and machinery,
plant and equipment. The claim made under the aforesaid
head was for a sum of Rs.11,40,000/-. The Arbitrator was
satisfied that there was interruption of work by anti-social
elements and that the State had failed to remove such
obstruction from the site. Accordingly, the Arbitrator
awarded a sum of Rs. 7,30,000/- under this claim.
Claim (g) was confined to the question as to whether the
claimant was entitled to compensation for the losses suffered
by him on account of price escalation of materials that had
taken place during the extended period of completion when
such extension of time was necessitated by departmental
failure, although there was no provision for escalation of costs
in the contract. Under the said clause the appellant claimed
an amount of Rs.39,90,198/- but was awarded a sum of
Rs.11,70,000/- over and above the amount as per the rates in
the agreement for the work done after the original period of
contract till 9th February, 1987.
Claim (i) was confined to the question regarding the
claimant’s entitlement for compensation for the losses
purported to have been suffered by him because the
Department was unable to hand over a suitable quarry which
resulted in the claimant having to bring rubble and metal
from far off places involving additional transportation costs.
The Arbitrator came to a positive finding that the claimant had
procured rubble from quarries situated at different places.
According to the initial estimate, the quarry ought to have
been within 25 Kms. from the place of work, but from the
evidence it would be clear that the nearest quarry from which
the claimant had to procure rubble would be about 47 Km.
away from the site of the work. The other quarries were even
further away from the work site. It was the definite finding of
the Arbitrator that the average extra lead involved would be
not less than 22 Kms. and accordingly while the claimant had
claimed a sum of Rs.24,86,574/-, the Arbitrator awarded a
sum of Rs.13,35,000/- under this head for the work executed
up to 9th February, 1987.
The other claim which was pressed by the appellant was
claim (k) relating to losses suffered by him on account of
non-availability of a suitable dumping yard for dumping
excess earth. While a claim for a sum of Rs.13,72,554/- was
made in this regard, the Arbitrator awarded a sum of
Rs.6,62,000/- under this head.
The agreement relating to the handing over of the site to
the claimant was executed on 10th October, 1985 and on 25th
October, 1985, the respondents instructed the claimant to
start the work and to complete the same within the agreement
period of eleven months. However, while the period of
completion of eleven months for the whole work was to expire
on 24th September, 1986, the same could not be completed on
the scheduled dates and under clause 50 of the General
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
Conditions of Contract extension of time was sought by the
appellant for completing the work. Clause 50 of the General
Conditions of Contract provides that if failure to complete the
work was the result of delays on the part of Government in
supplying materials or equipment it had undertaken to
supply under the contract or from delays in handing over sites
or from increase in the quantity of the work to be done under
the contract or force majeure, an appropriate extension of
time would be given. Finding that the said clause was
operative, the respondents extended the time of completion
but while doing so made it conditional that such extension of
time would be subject to execution of a Supplemental
Agreement to the effect that the contractor would not be
eligible for any enhanced rate for the work done during the
extended period. According to the appellant, he had no option
but to sign the agreement, though under protest, since he had
undertaken to complete the work.
The appellant appears to have moved to the site and
commenced the work on 1st November, 1985 but he was not
allowed to proceed with the work because of external
interference involving law and order problems created by local
miscreants and anti-social elements under cover of union
activities. Although, initially such a claim was denied on
behalf of the respondents and the law and order situation was
said to be only a labour dispute between the claimant and
his workers, ultimately from the evidence the Arbitrator came
to the finding that the issue was one of law and order which
could only have been controlled by the Governmental agencies.
The Arbitrator also came to a finding that in order to
maintain peace at the work site, the claimant had to keep the
entire local work force in the muster rolls and to pay wages
when the actual work was done with bull dozers. The
Arbitrator was satisfied that although the claimant had aimed
to complete the work within the original period, he was faced
with adverse site conditions which are not usually met with at
construction sites.
The Arbitrator was also satisfied with the claimant’s
contention that adequate space had not been provided for
dumping the excess earth which had to be conveyed to
distant places for dumping. On assessment of the evidence
and the ground realities under which the claimant was
constrained to execute the Supplemental Agreement, the
Arbitrator was convinced that the claim made by the
claimant under the different heads could not be brushed
aside.
Apart from the preliminary objection taken with regard
to the competence of the Arbitrator to complete the arbitration
proceedings and to publish his award, it was also contended
before the Arbitrator that the State had no responsibility in
settling the disputes between the claimant and his employees
and it was really due to the non-cooperation of the claimant
that a settlement could not be arrived at with the workers. It
was contended that under such circumstances claim (a)
could not be granted.
It was also contended that there was no provision in the
Agreement by which the Department could be made liable to
compensate any loss sustained by the contractor because of
intervention of third parties. It was contended that it is one
thing to say that the State is responsible for maintaining law
and order and on the other hand to make the State liable
under the terms of the Agreement to compensate the
contractor for losses allegedly suffered during the period of
disturbance.
On consideration of the case made out on behalf of the
respective parties, the Arbitrator made his award in respect of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
each of the several heads of claims on the losses actually
suffered by the appellant while trying to carry out and
complete the tender work. The Arbitrator filed his award
before the Subordinate Judge, Kottarakkara, on which a
decree was passed in terms of the award but modifying the
appellant’s claim for interest. The respondents preferred an
appeal to the High Court of Kerala at Ernakulam.
The stand taken before the Arbitrator was reiterated by
the parties before the High Court of Kerala at Ernakulam in
the said appeal. In addition, arguments were addressed on
the scope of interference by the High Court in an award
passed by the Arbitrator, which award was a speaking award.
On looking into the Agreement, the High Court was of the view
that the Arbitrator had exceeded his jurisdiction in granting
claim (a). The High Court felt that the Arbitrator had travelled
outside the Agreement and had acted without jurisdiction in
granting such claim.
Even in respect of claim (g), the High Court took note of
the fact that by virtue of the Supplemental Agreement which
had to be executed for extension of the original period of
completion of the work, the appellant herein was not entitled
to enhanced rates during the extended period. In respect of
claim (g) also, the High Court found that the Arbitrator had
travelled outside the terms of the contract and had mis-
conducted himself.
Admittedly, the original Agreement did not contain a
clause for escalation of rates. On the other hand, the
Supplemental Agreement contained a specific provision that
the contractor would carry out all further works within the
extended period at the rates and in the manner agreed to in
the Agreement and would not claim any enhanced rate for
such item of work on account of the extension of time either
due to the increase in the rate of labour or materials or on
any other ground whatsoever. The High Court took the view
that although the Arbitrator had come to a finding that the
appellant had to execute the Supplemental Agreement under
the force of circumstances, there was no material before the
Arbitrator in support of such contention. On such finding
also, the High Court held that the Arbitrator had acted beyond
his jurisdiction in allowing claim (g).
The award of the Arbitrator against claim (i) also met the
same fate and the High Court held that the Arbitrator had
travelled outside the contract in granting such claim and thus
mis-conducted himself.
The only claim which was allowed by the High Court was
claim (k).
The High Court accordingly set aside the judgment and
decree of the court below to the extent it affirmed the award
as far as claims (a), (g) and (i) are concerned.
The said order of the High Court is the subject-matter of
the present appeal.
Appearing for the appellant, Mr.Dushyant Dave, learned
senior advocate, urged that the High Court while reversing
the award under claims (a), (g) and (i) had failed to take into
consideration the finding of the Arbitrator that the appellant
had suffered heavy losses on account of the law and order
problem which had been created at the work site and that he
had been compelled to complete the work under duress.
Reference was made to the letter dated 7th September, 1985
addressed by the appellant to the Superintending Engineer,
K.I.P.(RB) Circle, Kottarakkara, regarding extension of time to
complete the work under tender with the hope that the
Department would reciprocate his gesture and consider the
special circumstances under which he had given his consent
for extension of the period for completion of the work.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
Reference was also made to another letter dated 24th
September, 1986 written by the appellant to the said
Superintending Engineer informing him of the problems that
were being faced for completion of the work and requesting
that his accounts be settled and that he be freed from the
entanglements.
The last letter referred to by Mr. Dave was written by the
appellant to the said Superintending Engineer on 30th
September, 1986 indicating that he was carrying out the
work despite all the difficulties although the same was not a
solution to the genuine problems being faced by him as
indicated in the earlier letters.
It was urged that having regard to the ground realities, it
was within the powers of the Court to grant relief on account
of escalation of costs in interrupted projects, although there
may not be any specific provision for such escalation in the
contract itself.
In support of his submissions, Mr. Dave firstly referred
to the decision of this Court in P.M. Paul vs. Union of India,
1989 Supp.(1) SCC 368, wherein a dispute arose regarding
payment of escalated costs. By an order of this Court, the
dispute between the parties was referred to a retired Judge of
this Court to ascertain who was responsible for the delay in
completion of the building, what was the repercussions of the
delay and how the consequences were to be apportioned. It
had been contended therein that in the absence of any
escalation clause it was not permissible for the Arbitrator to
grant any escalation price sought by the contractor. The
Arbitrator, however, noted that the claim related to the losses
caused due to increase in prices of materials and costs of
labour and transport during the extended period of the
contract and accordingly allowed 20 per cent of the
compensation sought. The question before this Court was
whether the Arbitrator had travelled beyond his jurisdiction in
awarding escalation costs and charges. This Court came to a
finding that the Arbitrator had not mis-conducted himself in
awarding the amount as he had done. Once it was found
that there was delay in execution of the contract due to the
conduct of the respondent, respondent was liable for the
consequences of the delay, namely, increase in prices. It was
held that the claim was not outside the purview of the
contract and arose as an incidence of the contract and the
Arbitrator had jurisdiction to make such award.
Reference was then made to the decision of this Court in
T.P. George vs. State of Kerala And Anr., (2001) 2 SCC
758, where a similar situation arose and the contractor was
compelled to execute a Supplemental Agreement. Although, a
question was raised as to whether the Supplemental
Agreement debarred the contractor from pursuing his
claims, the Arbitrator allowed the claims which were however
set aside by the High Court. This Court in appeal held that
the High Court had erred in setting aside the award regarding
those claims notwithstanding the fact that the Supplemental
Agreement had been executed between the appellant and the
State Government. The grant of interest by the Arbitrator,
which had been disallowed by the High Court, was also
allowed by this Court.
Mr. Dave contended that even in the absence of any
escalation clause, if it is found that the escalation of costs
had been occasioned by circumstances which were not
anticipated at the initial stage and was attributable to the
respondents, there was no reason why the Arbitrator could
not take notice of the ground reality and to award escalation
costs. It was urged that had the respondents provided for the
rubble to be obtained for the work from the quarry at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
Mannady, the appellant would not have had to bear the extra
transportation charges for bringing such rubble from far away
quarries. The same applied to providing a suitable place for
dumping of excess earth and the failure of the respondents to
maintain the law and order problem that had been created at
the site.
The submissions advanced on behalf of the appellant
were strongly opposed on behalf of the State Government with
particular reference to the award in respect of claims (a) and
(g) since the Original Agreement did not provide for such
escalation and the Supplemental Agreement which had been
executed clearly stipulated that no extra rates would be
allowed. It was contended that the Department had never
failed to perform its contractual obligations, and, in any
event, the delay in completing the work was not on account
of any neglect on the part of the State but on account of
labour trouble involving the appellant and his workmen at
the site.
Mr. Jayant Muth Raj, who appeared for the State,
contended that as had been observed by this Court as far back
as in 1960 in M/s. Alopi Parshad & Sons Limited vs. The
Union of India, reported in (1960) 2 SCR 793, provision for
payment of charges at rates specified had been made in the
contract and the arbitrators could not ignore the express
covenants between the parties and award amounts not
agreed to be paid. It was observed further that a contract is
not frustrated merely because the circumstances in which it is
made is altered and that the Courts have no general power to
absolve a party from the performance of his part of the
contract merely because its performance has become onerous
on account of an unforeseen turn of events. According to Mr.
Muth Raj the award made in the instant case could not also
be justified on the basis of quantum meruit since such a
concept would be applicable when services are rendered but
the price thereof is not fixed by a contract.
Mr. Muth Raj also referred to various other decisions of
this Court, including the decision in State of U.P. vs. Patel
Engg. Co. Ltd. And Ors., reported in (2004) 10 SCC 566, where
a question arose as to whether on the basis of a modified
contract which specifically excluded payment of freight
charges, claims for variation in payment of such charges
could be awarded by the arbitrator. It was held that the
arbitrators had exceeded their jurisdiction in awarding freight
charges in respect of steel and handling transportation
charges and that the District Judge had rightly held that the
same was not sustainable inasmuch as the claimant was not
entitled to such freight charges. It was urged that when no
provision had been made in the contract for escalation of
costs and the Supplemental Agreement entered into between
the parties specifically provided that the contractor would not
claim any enhanced rate for the work performed during the
extended period of the contract, the Arbitrator had wrongly
allowed some of the claims made by the appellant on account
of escalation of costs and the High Court had rightly
disallowed the same.
The question which we are called upon to answer in the
instant appeal is whether in the absence of any price
escalation clause in the Original Agreement and a specific
prohibition to the contrary in the Supplemental Agreement,
the appellant could have made any claim on account of
escalation of costs and whether the Arbitrator exceeded his
jurisdiction in allowing such claims as had been found by the
High Court.
Ordinarily, the parties would be bound by the terms
agreed upon in the contract, but in the event one of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
parties to the contract is unable to fulfil its obligations under
the contract which has a direct bearing on the work to be
executed by the other party, the Arbitrator is vested with the
authority to compensate the second party for the extra costs
incurred by him as a result of the failure of the first party to
live up to its obligations. That is the distinguishing feature
of cases of this nature and M/s. Alopi Parshad’s case (supra)
and also Patel Engg.’s case (supra). As was pointed out by
Mr. Dave, the said principle was recognized by this Court in
P.M. Paul’s (supra) , where a reference was made to a retired
Judge of this Court to fix responsibility for the delay in
construction of the building and the repercussions of such
delay. Based on the findings of the learned Judge, this Court
gave its approval to the excess amount awarded by the
arbitrator on account of increase in price of materials and
costs of labour and transport during the extended period of
the contract, even in the absence of any escalation clause.
The said principle was reiterated by this Court in T.P.
George’s case (supra).
We have intentionally set out the background in which
the Arbitrator made his award in order to examine the
genuineness and/or validity of the appellant’s claim under
those heads which had been allowed by the Arbitrator. It is
quite apparent that the appellant was prevented by unforeseen
circumstances from completing the work within the stipulated
period of eleven months and that such delay could have been
prevented had the State Government stepped in to maintain
the law and order problem which had been created at the
work site. It is also clear that the rubble and metal, which
should have been available at the departmental quarry at
Mannady, had to be obtained from quarries which were
situated at double the distance, and even more, resulting in
doubling of the transportation charges. Even the space for
dumping of excess earth was not provided by the respondents
which compelled the appellant to dump the excess earth at a
place which was far away from the work site entailing extra
costs for the same.
In the aforesaid circumstances, the Arbitrator appears to
have acted within his jurisdiction in allowing some of the
claims on account of escalation of costs which was referable
to the execution of the work during the extended period. In
our judgment, the view taken by the High Court was on a rigid
interpretation of the terms of contract and the Supplemental
Agreement executed between the parties, which was not
warranted by the turn of events.
We accordingly allow the appeal and set aside the order
passed by the High Court and restore the award made by the
Arbitrator.
There will, however, be no order as to costs.