Full Judgment Text
1
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.3343 OF 2020
DEBASHIS SINHA & ORS. …..APPELLANTS
VS.
M/S R.N.R. ENTERPRISE REP. BY ITS
PROPRIETOR/CHAIRMAN,KOLKATA & ORS. RESPONDENTS
O R D E R
1. This appeal under section 23 of the Consumer Protection Act,
1986 (hereafter ‘the C.P. Act’, for short) calls in question the order
st
dated 21 August, 2020 passed by the National Consumer Disputes
Redressal Commission, New Delhi, (hereafter ‘NCDRC’, for short). By
the impugned order, the NCDRC has dismissed the consumer
complaint lodged by the appellants.
2. The multiple appellants are owners of flats in different blocks
of a housing complex at 1, Kailash Ghosh Road, Kolkata – 700008
Signature Not Verified
Digitally signed by
Harshita Uppal
(hereafter ‘housing complex’, for short).
Date: 2023.02.09
15:49:20 IST
Reason:
2
3. Aggrieved by the failure of the respondents - the developers of
the housing complex - to provide services as promised, the
jurisdiction of the NCRDC was invoked by the appellants in 2008.
They alleged that despite paying full consideration amount as per
market rate and despite execution and registration of deeds of
conveyance in their favour, the respondents had failed, inter alia, to
provide the ‘Completion Certificate’, which is their statutory
obligation as per the rules of the Kolkata Municipal Corporation
(hereafter ‘KMC’, for short); and, in the absence of such a certificate,
their occupation of the respective flats has been rendered
precarious. According to the appellants, the respondents also failed
to provide them common amenities and facilities viz., playground,
community hall-cum-office room, 33-feet wide concrete road, and
supply of water from the KMC. It was their further complaint that
the respondents had adopted unfair trade practices by promising a
playground on a land which actually belonged to a local club as well
as attracted buyers by showing in the brochure/ advertisement a
‘beautified lake’, which never came into existence. Also, finding that
there were constructional defects, a valuer from the list of approved
valuers maintained by the Calcutta High Court had been engaged by
the appellants. The report of such valuer revealed constructional
defects of the nature delineated therein. Based on the complaint
that was lodged before the NCDRC, the appellants sought direction
3
to the respondents to provide the completion certificate of the
project and to set right the constructional defects as pointed out by
the valuer. Further, they claimed that direction be issued for
providing other facilities such as community hall, landscape
gardening, generator, multi-gymnasium, water filtration plant, and
gas pipeline. Additionally, compensation of Rs.1,80,00,000/- (Rupees
one crore eighty lakh only) together with litigation cost of
Rs.50,000/- (Rupees fifty thousand only) was claimed.
4. The complaint lodged by the appellants was contested by the
respondents by filing a written statement. Apart from objecting to
the maintainability of the complaint on the grounds that the same
was time barred and that a joint complaint could not have been
lodged by 36 (thirty-six) flat owners, it was contended that the
appellants have not paid the full consideration amounts, that
certain common facilities/amenities could be provided only if all the
members of the housing complex contribute for the same and that
the compensation claimed was vague and imaginary. It was also
contended in the written statement that most of the appellants had
taken possession of the flats in 2006 without raising any objection at
the material time; hence, lodging of a complaint after 2 (two) years
of possession being delivered is motivated. Insofar as the issue of
obtaining the completion certificate is concerned, it was contended
that the flats having already stood transferred to the appellants by
4
way of conveyance/sale deed(s), it was for the appellants to apply
before the KMC for obtaining such certificate. The respondents also
contended that since KMC had completed assessment of the flats of
the appellants, it was not possible for the respondents to now apply
and obtain completion certificate for the flats.
5. Considering the pleadings before it as well as upon hearing the
parties, the NCDRC returned findings that the respondents had
shown a very casual approach and were guilty of unfair trade
practice as well; yet, it was observed that the appellants had not
been able to establish their claim. It also appears from the
impugned order that the NCDRC suspected that the purpose of the
complaint was to pressurize the respondents into paying some
compensation and/or not insisting upon extra payment for the extra
facilities and amenities. Also, it was held that the respondents had
been able to successfully urge that the fault for not obtaining the
completion certificate of the project could not be attributed to them.
In this regard, the NCDRC returned a finding that reading of section
403 of the Kolkata Municipal Corporation Act, 1980 (hereafter ‘KMC
Act’, for short) makes it clear that it was incumbent on both the
respondents as well as the appellants to not occupy the premises in
the absence of the completion certificate. As a result thereof, a
finding was further returned that both the parties had violated the
law; as such, no deficiency could be attributed to the respondents
5
on this account. Based on broadly these findings, the complaint of
the appellants failed before the NCDRC.
6. We have heard Mr. Sharma, learned counsel for the appellants.
None appeared before us on behalf of the respondents on the
previous 2 (two) occasions the appeal was heard and even today.
7. We have also perused the impugned order of the NCDRC and
considered the materials on record.
8. What has struck us first is the time taken by the NCDRC to
decide the complaint after it reserved the same for passing orders. It
took the NCDRC in excess of 10 (ten) months to dismiss the
complaint. As our discussion hereafter would unfold, we are of the
clear view that the long delay in passing the order on the complaint
did have its own effect on the ultimate decision of the NCDRC.
9. The complaint of the appellants was that the respondents have
not provided playground, community hall, beautified lake, landscape
gardening, generator backup, multi-gymnasium, etc. as mentioned
in the brochure/advertisement pursuant to which they expressed
interest to purchase flats in the project and, thus, defaulted in
providing services in relation to housing construction.
10. One entire paragraph in the order has been devoted by the
NCDRC to highlight that the project was not that huge and talk of
common areas and facilities on a grand scale was quite misplaced.
6
An admission made by the appellants themselves in the complaint
has been referred to but we have not been able to trace any
admission of the complainants that the respondents promised not to
deliver substantial common areas and common facilities. Be that as
it may, what the NCDRC omitted to bear in mind was that the
appellants were allured to purchase flats of the nature and kind
together with facilities and amenities as attractively published in the
brochure/advertisement; hence, whether the project was huge or
otherwise was absolutely beside the point. It was the duty of the
NCDRC to ascertain, based on the materials on record, whether if at
all and to what extent facilities and amenities as promised were
offered and/or whether there was any deficiency of service. We
have not found any categorical findings in this regard, although
there are unambiguous findings that the NCDRC disapproved the
conduct of the respondents.
11. The conduct of the respondents, the NCDRC recorded in the
impugned order, was far too casual and on the face of it, the
respondents are guilty of “unfair trade practice” within the meaning
of section 2(1)(r) of the C.P. Act. After so recording, the NCDRC held
that this does little to rescue the complainants. The reason assigned
therefor defies logic. We have failed to comprehend as to what the
NCDRC meant when it observed that the appellants “ought to have
known what they were purchasing”. More often than not, the
7
jurisdiction of the consumer fora under the C.P. Act is invoked post-
purchase. If complaints were to be spurned on the specious ground
that the consumers knew what they were purchasing, the object and
purpose of the enactment would be defeated. Any deficiency
detected post-purchase opens up an avenue for the aggrieved
consumer to seek relief before the consumer fora. The reasoning of
the NCDRC is, thus, indefensible. Indeed, the appellants had
purchased their respective flats on payment of consideration
amounts as per market rate and there was due execution and
registration of the deeds of conveyance preceded by agreements for
sale and these instruments did indicate, inter alia, what formed part
of the common facilities/amenities; however, the matter obviously
could not have ended there. Whether the appellants had been
provided what the respondents had promised did survive for
consideration, which does not get reflected in the impugned order.
12. NCDRC, in our opinion, might have missed to appreciate the
present day realities of life. Now-a-days, flat owners seldom
purchase flats with liquid cash. Flats are purchased on the basis of
finances being advanced by banks and other financial institutions.
Once a flat is booked and the prospective flat owner enters into an
agreement for loan, instalments fall due to be paid to clear the debt
irrespective of whether the flat is ready for being delivered
possession. The usual delays that are associated with construction
8
activities result in undue anxiety, stress, and harassment for which
many a prospective flat owner, it is common knowledge, even
without the project/flat being wholly complete is left with no other
option but to take possession. Whether, upon taking possession, a
flat owner forfeits his/her right to claim such services which had
been promised but are not provided resulting in deficiency in
services is a question that the NCDRC ought to have adverted to.
Once the NCDRC arrived at a finding that the respondents were
casual in their approach and had even resorted to unfair trade
practice, it was its obligation to consider the appellants’ grievance
objectively and upon application of mind and thereafter give its
reasoned decision. If at all, the appellants had not forfeited any
right by registration of the sale deeds and if indeed the respondents
were remiss in providing any of the facilities/amenities as promised
in the brochure/advertisement, it was the duty of the NCDRC to set
things right.
13. That the appellants had genuine reasons to feel aggrieved was
th
clearly documented in the report of the valuer dated 11 July, 2008
which was even acknowledged by the NCDRC, yet, a peculiar
approach was adopted and the respondents absolved of their
obligations by an order which appears to us to be unjustified on
facts and in the circumstances.
9
14. We have found from the impugned order that it speaks of
certain facilities to be made available by the respondents on
payment of extra money. However, there is no such clear-cut
description of facilities/amenities which the respondents asserted
would be provided on payment of extra money by the appellants.
NCDRC would have done well to indicate the same with clarity.
15. Finally, we cannot resist but comment on the perfunctory
approach of the NCDRC while dealing with the appellants’ contention
that it was the duty of the respondents to apply for and obtain the
completion certificate from the KMC and that the respondents ought
to have been directed to act in accordance with law. The observation
made by the NCDRC of the respondents having successfully argued
that it was not their fault, that no completion certificate of the
project could be obtained, is clearly contrary to the statutory
provisions.
16. Sub-section (2) of section 403 of the KMC Act was referred to
by the NCDRC in the impugned order. Sub-section (1) thereof, which
finds no reference therein, requires every person giving notice
under section 393 or section 394 or every owner of a building or a
work to which the notice relates to send or cause to be delivered or
sent to the Municipal Commissioner a notice in writing of completion
of erection of building or execution of work within one month of such
completion/erection, accompanied by a certificate in the form
10
specified in the rules made in this behalf as well as to give to the
Municipal Commissioner all necessary facilities for inspection of such
building or work.
17. Section 393 mandates every person, who intends to erect a
building, to apply for sanction by giving notice in writing of his
intention to the Municipal Commissioner in such form and containing
such information as may be prescribed together with such
documents and plans. Similarly, section 394 also mandates every
person who intends to execute any of the works specified in clause
(b) to clause (m) of sub-section (1) of section 390 to apply for
sanction by giving notice in writing of his intention to the Municipal
Commissioner in such form and containing such information as may
be prescribed.
18. It is, therefore, evident on a conjoint reading of sections 403,
390, and 394 of the KMC Act that it is the obligation of the person
intending to erect a building or to execute works to apply for
completion certificate in terms of the rules framed thereunder. It is
no part of the flat owner’s duty to apply for a completion certificate.
When the respondents had applied for permission/sanction to erect,
the Calcutta Municipal Corporation Buildings Rules, 1990 (hereafter
‘1990 Rules’, for short) were in force. Rule 26 of the 1990 Rules
happens to be the relevant rule. In terms of sub-rules (1) to (3) of
rule 26 thereof, the obligation as cast was required to be discharged
11
by the respondents. Evidently, the respondents observed the
statutory provisions in the breach.
19. Curiously enough, the NCDRC referred to sub-section (2) of
section 403 of the KMC Act only to permit the respondents to
wriggle out of such obligation and arrived at a completely erroneous
finding that no deficiency in service could be attributed to the
respondents since both the respondents and the appellants had
acted in violation of law. True it is, the appellants ought not to have
taken possession without the completion certificate; however, that
was not a valid ground not to direct the respondents to apply for and
obtain the completion certificate as required by law. The mere fact
that the flat owners were being assessed by the KMC affords no
reason to the respondents for breaching section 403(1) read with
rule 26 of the 1990 Rules. Of course, once a completion certificate is
issued by the KMC upon conducting appropriate inspection and tests
of the building that has since been erected, it would stand to reason
that the same amounts to a certification that the building does not
suffer from any violation of the building plan sanctioned for the
purpose under section 390 of the KMC Act or that its constructional
quality is not of the desired level for which it is unsafe for human
habitation. We are constrained to observe that the respondents have
been let off by the NCDRC in a manner contrary to law.
12
20. For such infirmities, as noticed above, this is an appropriate
case where the complaint of the appellants ought to be remitted to
the NCDRC for taking a relook into the complaint in accordance with
law. It is ordered accordingly.
21. Since it is found that the appellants while praying for monetary
compensation of Rs.1,80,00,000.00 have failed to give detailed
particulars and/or provide the basis therefor, and undoubtedly, they
have also been on the wrong side of law by taking possession of
their respective flats without the completion certificate, whatever
might be the compulsion, we are not inclined to direct the NCDRC to
decide on the compensation component. That chapter stands
closed. The remand is directed only with a view to secure adherence
to the promises that the respondents had made in the brochure
and/or advertisement, as the case may be, and thereby cover up
deficiency in service, if any, as well as the mandatory statutory
provisions.
22. The appeal stands disposed of on terms as aforesaid, with no
orders as to costs.
23. Since the complaint is more than 15 (fifteen) years old, it
would be desirable if the NCDRC decides the same as early as
possible and preferably within a year of service of an authenticated
copy of this order.
13
………………………………J
(S. RAVINDRA BHAT)
………………………………J
(DIPANKAR DATTA)
NEW DELHI;
FEBRUARY 9, 2023.