ESJAY INTERNATIONAL PVT. LTD.& ANR. vs. UNION OF INDIA THROUGH MINISTRY OF TEXTILES & ORS.

Case Type: NaN

Date of Judgment: 21-09-2011

Preview image for ESJAY INTERNATIONAL PVT. LTD.& ANR.  vs.  UNION OF INDIA THROUGH MINISTRY OF TEXTILES & ORS.

Full Judgment Text

2011:BHC-OS:13075-DB
KPP -1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
  ORDINARY ORIGINAL CIVIL  JURISDICTION 
WRIT PETITION  NO. 1733 OF 2001
1. Esjay International Pvt. Ltd.  )
a Company incorporated under the Indian Companies )
Act, 1956, having its office at 48­A, Laxmi Industrial  )
Estate, Shankar Rao Naram Path,  Lower Parel, )
Mumbai­400 013 )
2. Sunil G. Jhangiani, Director, )
residing at Laxmi Niwas, Bhulabhai Desai Road,  )
Mumbai­400 036  )..Petitioners
vs.
1. Union of India through Ministry of Textiles  )
2. The Textile Commissioner having his office at New CGO’s )
Building, 48, New Marine Lines, Mumbai­400 020 )
3. Apparel Export Promotion Council, having its registered )
office at 15, NBCC Tower, Bhikaji Cama Place,  )
New Delhi­110 066, and its Branch office at Bajaj )
th
Bhavan, 12  floor, Nariman Point, Mumbai­400 021 ).Respondents
Mr. Zal Andhyarujina with Mr. D. Das, instructed by Mr. Anuj N. Narula for the 
petitioners. 
Mr. Vinod Joshi for respondent Nos. 1 and 2.
Ms. K.P. Reshma Ravi for respondent No.3. 
 
   
                   CORAM :   P.B. MAJMUDAR    &
                                                                       R.M. SAVANT,   JJ.      
DATE:     SEPTEMBER 21, 2011.
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -2-
  ORAL   JUDGMENT    (Per R.M. Savant, J. )
The issue that arises for consideration in the above petition is 
as to whether the petitioners are entitled to the benefit of clause 9 of 
Government   Entitlement   Policy,1994­1996   on   account   of     “force 
majeure”.  
2. The petitioners by way of this petition under Article 226 of the 
th
Constitution of India are challenging the orders dated  20  June, 2000, 
rd th
23  June, 2000 and 13  October, 1996 passed by the Respondent Nos. 1, 
2 and 3 respectively. 
3. The  factual  matrix   involved  in  the  above  petition     can  be 
conveniently stated thus:­
3. The petitioners are exporters and have been recognised by the 
Govt. of India as such since the year 1981. The petitioners have their 
manufacturing unit at GIDC, Sarigam in the State of Gujarat which they 
th 
have established some time in the year 1993.  By notification dated 4
September, 1993, the Central Government in the Ministry of Textiles 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -3-
announced the quota policy framed for the period 1994­1996.   On the 
petitioners applying to the Gujarat Electricity Board (“GEB” for short), the 
th 
petitioners   were   given   motive   power   connection   of   80   HP   on   18
th
November, 1994 and thereafter on 16  June, 1995 the petitioners were 
given 20 KV power for lighting   in the factory and office. The GEB, it 
appears, imposed a power cut in respect of the industries at Sarigam  for a 
duration of four hours a day and 48 hours a week whereby  it is the case 
of the petitioners that the production at their factory got  directly affected 
and   as   such   was   slowed   down   considerably.     It   is   the   case   of   the 
petitioners that  the said  power cut remained in force till November,1995 
which was certified as such by the Deputy Engineer of the GEB.  In terms 
of the policy, the petitioners were to fulfil their export obligation as per 
the quota allotted to them by September,1995.  The petitioners applied 
for extension to fulfil their obligations, pursuant to which the petitioners 
st
were granted an extension as per the policy upto 31  December, 1995 on 
the petitioners giving an undertaking of 30 per cent of value of quota with 
th
remainder to be utilised after 30  September,1995.  It is the case of the 
petitioners that on account of the force majeure  condition resulting from 
the power cut so imposed by the GEB, the petitioners could manufacture 
and ship only 87.01 per cent of the allotment for the said year in respect 
of their entitlement in PPE and NQ systems. 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -4-
4. In view of the non­fulfilment of the quota obligations by the 
petitioners, the petitioners were served with a show cause notice dated 
th
10   September, 1996 addressed   by   the respondent No.3 i.e. Apparel 
Export Promotion Council (“AEPC” for short).  The show cause notice was 
to the effect that the petitioners had not utilised the allotted quantity of 
quota   and, therefore, the petitioners were liable to forfeiture   of bank 
guarantee to the extent of an amount of Rs. 16,80,352/­.  On receipt of 
the said show cause notice, the  petitioners’ Export Manager represented 
against the said show cause notice and, apart from pointing out the 
discrepancies in the show cause notice, he ventured to furnish the correct 
data of the total export effected in the year 1995.  The said show cause 
notice, it appears, was adjudicated upon by the AEPC  and by an order 
rd
dated 3  October,1996, the AEPC called upon the petitioners to pay a sum 
of Rs. 11,31,072/­   on account of the fact that the petitioners had not 
fulfilled the terms and conditions as per the policy which has resulted  in 
the breach of the undertaking in so far as the fulfilment of the export 
obligations were concerned. 
rd
5. Being aggrieved by the said order dated 3  October,1996, the 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -5-
petitioners filed an appeal   before the Respondent No.2 and the main 
rd
ground of challenge to the said order dated 3  October, 1996 was  that 
the petitioners were prevented from utilising   and entire quota and/or 
achieving 90 per cent utilisation thereof on account of the force majeure 
condition   of   the   power   cut   imposed   by   the   GEB.   It   appears   that 
respondent No.2, before whom the appeal was filed, called upon the 
petitioners to submit a certificate from the GEB in respect of the alleged 
power cut as also called upon the petitioners to submit copies of the 
electricity   bills   for   the   period   June   1995   to   December,   1995.   The 
th 
petitioners, in compliance of the said requisition, by their letter dated 9
November, 1998 furnished the details of the power consumed by them in 
their factory at Sarigam during the period  June, 1995 to December, 1995 
th
and also furnished the certificate dated 28  October,1998 issued by the 
GEB. 
6. The   appeal   of   the   petitioners   was   considered   by     the 
respondent No.2 and after taking into consideration the relevant material 
which was produced by the petitioners, the  respondent No.2 disposed of 
the said appeal by recording a finding  that the petitioners had made more 
payment  towards electricity during the latter part of the year i.e. 1995 
compared to the electricity charges paid for the period between June, 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -6-
1995 and September, 1995. The respondent No.2, therefore, concluded 
that the power cut  on which the petitioners sought to rely upon  cannot 
be said to have affected the production. The respondent No.2, therefore, 
rd
by the order dated 23  June, 2000  disposed of the said appeal  filed by 
the petitioners. 
rd
7. Being aggrieved  by  the said  order dated  23    June, 2000 
passed by the respondent No.2 herein, the petitioners filed a second 
appeal   before   the   Second   Appellate   Committee   constituted     by   the 
respondent No.1. The said Appellate Committee comprised of as many as 
four members. The substantial ground   of challenge in the appeal filed 
before the Second Appellate Committee was that the petitioners have 
been wrongly  denied the benefit of clause 9 i.e. force majeure  on the 
premise that the payment of the electricity charges during the period 
September,1995 to December, 1995 was higher than the charges paid for 
the earlier period. The petitioners challenged the said order on the ground 
that   the   respondent   No.2     had   erroneously   taken   into   account   the 
electricity charges paid for lighting provided to the office  which supply, 
according to the petitioners, was not under any power cut. It was the 
specific case of the petitioners that the respondent No.2 had erroneously 
taken into account the charges paid without considering the actual unit 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -7-
consumption of electricity  which clearly indicated that in fact less power 
had been utilised by the factory of the petitioners during September, 1995 
and December, 1995. The said appeal of the petitioners was disposed of 
th
by the Second Appellate Committee by its order dated 20  June, 2001. 
The Second Appellate Committee  confirmed the findings recorded by the 
First Appellate Committee and observed  that it had no reason to take a 
different view than the view taken by the First Appellate Committee in 
respect of the ground of force majeure  made out by the petitioners. The 
appeal filed by the petitioners was accordingly rejected by the Second 
Appellate Committee. 
8. After the  said    order was passed by  the  Second Appellate 
th
Committee, the respondent addressed a communication dated 6   July, 
2001 by which they called upon the petitioners to pay an amount of Rs. 
11,31,072/­ within a period of seven days failing which the petitioners 
were threatened  with coercive action as could be taken in terms of the 
policy.  As indicated above, the orders passed by the Respondent Nos. 1, 2 
and 3 are the subject matter of challenge in the above petition. 
9. On behalf of the respondents, an affidavit in reply, has been 
filed by one Ashok Hazra, Assistant Director in the office of the Textile 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -8-
Commissioner.  The policy as regards exports and the need for fulfilment 
of the quota by the exporters has been spelt out in the said affidavit. It has 
been averred in paragraph 6 that  non­utilisation of the export quota is a 
serious matter as it not only affects  the earning in foreign exchange  but 
if the quota remains unutilised, then it has adverse effect and impact in 
the future bilateral agreements between the countries. It is the object of 
the Ministry that no quota is wasted  and, therefore, towards that end a 
bank guarantee or a legal undertaking  is obtained by the Ministry and for 
non­fulfilment of the quota, there is a forfeiture which the exporter has to 
suffer. It is averred in paragraph 7 of the said affidavit that the petitioners 
had   given   a   Legal   Undertaking   (LUT)   to   the   AEPC   for   the   entire 
revalidated quantity. However, the petitioner Company was not able to 
utilise   the   entire   revalidated   quota   nor   the   maximum   permissible 
revalidated quantity i.e. 90 per cent  of the revalidated quantity in  all the 
st
systems till 31  December, 1995. It has further been averred in the said 
paragraph that as exporters, the petitioners were fully aware about the 
power cut imposed by the GEB since June, 1995 and it is only after 
considering the impact of such power cut the petitioners had gone for 
st
revalidation of export quota from 1  October,1995.  In so far as the order 
of the Second Appellate Committee is concerned, it has been averred in 
the said paragraph 7 that the Second Appellate Committee had gone 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -9-
through the appeal and heard  the representatives of the firm as well as 
the officers of AEPC i.e. Respondent No.3. Since the case of the petitioners 
was   the   same   as   before   the   First     Appellate   Committee,   the   Second 
Appellate   Committee     concluded   that   the   grounds   made   out   by   the 
petitioners were not valid grounds which would amount to force majeure. 
10. Heard the learned counsel appearing for the parties. 
Submissions   on   behalf   of   the   petitioners   by   learned   Counsel   Shri 
Andhyarujina.
11. The   principal   contention   of   the   learned   counsel   for   the 
petitioners   Shri   Andhyarujia     is   that   once   the   authorities     have   not 
disputed the applicability of force maejure exemption to a situation of 
power cut, the respondents thereafter have arbitrarily in the case of the 
petitioners held that the power cut in question which the petitioners were 
affected   was   not   a   force   majeure   condition.   The   learned   counsel 
submitted that in the absence of the term ‘force majeure’ in the policy, it 
was incumbent upon the respondents to uniformly interpret the force 
majeure condition under the policy and in support of the said submission 
relied upon the judgment of the Apex Court reported in AIR 1961 S.C. 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -10-
1285  in the matter of  Dhanrajmal Gobindram vs. M/s. Shamji Kalidas and 
Co .  According to the learned counsel, paragraph 9 of the said report is 
material.  That the cut imposed by the GEB was a fact and circumstance 
beyond  the   control   of   the   petitioners   and,   therefore,   constituted   and 
satisfied   the   force   majeure   condition.     That   there   was   substantial 
compliance by the petitioners of their export obligation inasmuch as  87 
st
per cent of the quota was utilised by the Petitioners on 31   December, 
1995 and, therefore, it was a fit case for the respondents to exercise the 
discretion under clause 15 of the  policy.  That the order passed by the 
Second Appellate Committee is a cryptic order and no reasons have been 
mentioned for the dismissal of the appeal. 
Submissions on behalf of the Respondents
12. That the power cut in question was known to the petitioners in 
June, 1995 itself and in spite of the same they had applied for revalidation 
of the quota in September, 1995 and, therefore, the  petitioners are now 
estopped     from   contending   that   they   were   not   able   to   fulfil   their 
obligations on account of force majeure.  That force majeure contemplates 
something happening suddenly which is not foreseen and which is beyond 
the control of the person. Such is not the case here as the petitioners were 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -11-
very well aware of the power cut.  That the circumstances were not such 
which   handicapped   the   petitioners   from   fulfilling   the   export   quota 
inasmuch as the power cut was in operation throughout the year and, 
therefore, the petitioners are disentitled to claim the benefit of clause 9 of 
the extant policy.   Reliance was placed by the learned counsel for the 
th
respondents on   an unreported judgment dated 11  November, 2002 of a 
learned single  Judge of the Delhi High Court in Civil Writ Petition No. 
7176  of 2002  wherein it has been held that if things do not turn up as 
expected and the labour problem did not get resolved, the same cannot be 
equated to a force majeure situation.   That the petitioners have been 
given the benefit of having fulfilled 90 per cent of the quota by giving a 
rebate of Rs. 5 lakhs as the original amount claimed was Rs. 16 lakhs. 
Consideration
13. At the outset, it would be apposite to refer to the judgment 
cited   by   the   learned   counsel   for   the   petitioners   in   the   case   of   M/s. 
Dhanrajmal (supra).   Paragraph 17 of the said report is material and is 
reproduced hereinunder. 
“17.     McCardie J. in Lebeaupin v. Crispin, 1920­2 KB 714 
has given an account of what is meant by “force majeure” 
with   reference   to   its   history.   The   expression   “force 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -12-
majeure”   is   not   a   mere   French   version   of   the   Latin 
expression “vis major”. It is undoubtedly a term of wider 
import. Difficulties have arisen in the past as to what could 
legitimately be included in “force majeure”. Judges have 
agreed that strikes, breakdown of machinery, which though 
normally not included   in “force major” are included in 
“force majeure”. An analysis of rulings on the subject ijnto 
which it is not necessary in this case to go, shows that 
where reference is made to “force majeure”, the intention is 
to   save   the   performing   party   from  the   consequences   of 
anything over which he has no control. This is the widest 
meaning that can be given to “force majeure”, and even if 
this be the meaning, it is obvious that the condition about 
“force majeure” in the agreement was not vague.  The use 
of   the   word   “usual”   makes   all   the   difference,   and   the 
meaning of the condition may be made certain by evidence 
about a force majeure clause, which was in contemplation 
of parties”.
A reading of the said judgment, therefore, discloses the perspective from 
which the term “force majeure” was looked at by the Apex Court.  In the 
said case the Apex Court has held that the term “force majeure” is a term 
of wider import and that difficulties had arisen in the past as to what 
could legitimately be included in force majeure.  The Supreme Court has 
referred to the fact that the Judges have agreed that strikes, breakdown of 
machinery, though normally not included in “vis major” are included in 
“force majeure”. The Supreme Court has, therefore concluded that where 
reference is   to be made to force majeure, the intention is to save the 
performing party from the consequences of anything  over which he has 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -13-
no control. This, according to the Apex court, is the widest meaning  that 
can be given to the term “force majeure”.
14. The   next   judgment   cited   by   the     learned   counsel   for   the 
petitioner is the judgment of the Apex Court reported in AIR 1976 SC 
1100 in the matter of  M/s. Northern India Iron and Steel Co. vs. The State 
of Haryana and another . Though it is not a judgment directly on the issue 
of   “force   majeure”,   the   said   judgment   was   cited   in   support   of   the 
contention that the power cut was beyond the control  of the petitioners. 
Paragraph 9 of the said report is material and is reproduced hereinder. 
“9.  We are, therefore, of the view that the inability of the 
Board to supply electric energy due to  power cut  or any 
other circumstance beyond its control as per the demand of 
the consumer according to  the contract will be reflected in 
and considered as a circumstance beyond the control of the 
consumer which prevented it from consuming electricity as 
per the contract and to the extent it wanted to consume. 
The monthly demand charge for a particular month will 
have to be assessed in accordance with sub­cl (b) of Cl. 4 of 
the tariff and therefrom a proportionate reduction will have 
to be made as per sub­cl. (f). We hope, in the light of the 
judgment, there   will be no difficulty in working out the 
figures of the proportionate  reduction in any of the cases 
and for any period. In case of any difference or dispute as to 
the quantum of the demand charge or the proportionate 
reduction, parties will be at liberty to pursue their remedy 
as may be available to them in accordance with law.”
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -14-
15. The respondents have consciously incorporated the condition 
of “force majeure” in the export policy so as to give the exporters the 
benefit, if a situation so arises that the exporter is not  able to fulfil his 
obligations for the reasons which are beyond his control. It would be 
apposite to refer to the meaning of the term “force majeure” in some of 
the legal dictionaries :
“Black’s Law Dictionary:
force majeure. [Law French “ a superior force”] An event 
or effect that can be   neither anticipated nor controlled. 
The term includes both acts of nature (e.g. Floods and 
hurricanes) and acts   of people (e.g. Riots, strikes, and 
wars) – Also termed   force majesture; vis major; superior 
force . Cf.  ACT OF GOD; VIS MAJOR. 
rd
  Webster’s 3      New International Dictionary:    
force majeure: (1) Superior or irresistible force.   (2) an 
event or effect that cannot reasonably be anticipated or 
controlled   –   Compare   ACT   OF   GOD,   INEVITABLE 
ACCIDENT, VIS MAJOR” 
It     is     in   the   said   context   that   we   would   have   to   see   whether   the 
petitioners fulfilled the said condition. As held by the Apex Court in M/s. 
Dhanrajmal case (supra), and as can be seen from the dictionaries above, 
a     “force   majeure”   condition   is   said   to   be   something   which   is 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -15-
unforeseen, unexpected and which happens suddenly and over which a 
person has no control.   Things which immediately come to mind is the 
sudden   failure   of   the   power   grid   on   account   of   which   there   is   no 
electricity or a flash strike by the workmen.  Now coming to the facts of 
the present case, it is required to be noted that the relevant time in 
question i.e. year 1995.  A judicial notice would have to be taken of the 
fact that the Electricity Boards in some states with a view to conserve 
energy and with a view to see to it that there is equitable distribution of 
energy   between   different   consumers   i.e.   Industrial,   residential   and 
commercial  adopt the method of power cuts on particular dates which is 
popularly known as “staggering supply of electricity”. A prudent business 
man, therefore, ought to have taken notice of the said aspect and ought to 
have arranged his business accordingly, more so in the case of an exporter 
who has to fulfill his export obligation so as to avail of the benefits under 
the policy of the Government.  In the instant case, the power cut was over 
a considerable period i.e. almost for a period of one year i.e. in the year 
1995.  It is not something which happened suddenly and which crippled 
the business of the petitioners for a short period of time. The power cut 
was consistently over a long period  i.e. almost for a year  and, therefore, 
the petitioners cannot be heard to say that the power cut happened so 
suddenly  and without their knowledge   so as to impact their export 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -16-
obligations.   The   Second   Appellate   Committee   therefore,   was   right   in 
observing   that   the   petitioners   could   have   been   made   alternate 
arrangements like gensets, etc. 
It is required to be noted  that though the power cut was in 
force right from January, 1995 and the  petitioners  were to fulfil their 
export   obligations   by   September,   1995,   the   petitioners   applied   for 
revalidation of their quota which was revalidated and an extension was 
st
granted   to   the   petitioners   upto   31   December,   1995.     In   the   said 
circumstances, the petitioners ought to have taken appropriate steps so as 
to fulfil their export obligations.  Having applied for revalidation in the 
teeth of the knowledge of the fact that there was a power cut, it is not 
open for the petitioners to now claim the benefit of clause 9 relating to 
“force   majeure”.     It   is   pertinent   to   note   that     though   as   per   the 
st
revalidation, the obligation was to be fulfilled by 31   December, 1995. 
The petitioners did not do so and in fact completed its quota only in 
January,1996.  In the context of the aforesaid facts, the judgment cited by 
the learned counsel for the respondents of a learned single Judge of the 
th
Delhi High Court dated 11   November, 2002  in Civil Writ Petition  No. 
7176 of 2002 is relevant. In the said case, the labour problem commenced 
in   the   year   1995   and   the   petitioner   in   the   said   case     had   sought 
revalidation   in   October,   1996.   However,   there   was   no   lock   out   or 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -17-
complete cessation of activities at any time. The petitioners in the said 
case being fully aware of the labour problem and the business risk had got 
his quota revalidated.  The learned single Judge has held that in case the 
things did not turn up as expected and the labour problem did not get 
resolved, the same cannot be equated to a force majeure situation.  The 
facts in the said case before the learned single Judge of the Delhi High 
Court was, in our view, similar to the facts of the present case inasmuch 
as   the   petitioners   were   aware   of   the   power   cut   at   the   time   of   the 
revalidation of the said quota and in spite of the same, got it revalidated 
and had not fulfilled its obligations even in the extended period.  We are, 
therefore, of the view that the ground of power cut which is sought to be 
made out by the petitioners would not constitute a “force majeure” so as 
to come within clause 9 of the extant policy. 
16. As   regards   the   submission   of   the   learned   counsel   for   the 
petitioners   Shri   Andhyarujina   that   the   order   passed   by   the   second 
Appellate Committee is a cryptic order and bereft of any reasons and is 
therefore, required to be set aside in the context of the said submission, it 
wold be relevant to note that before the First Appellate Committee the 
petitioners had produced the material in support of their case as regards 
force majeure.  The subject matter was in the form of the certificate issued 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -18-
by the GEB and the consumption of energy by the petitioners during the 
relevant    period.  The  First     Appellate  Committee,  based  on  the  said 
material and upon hearing the parties, recorded findings of fact in respect 
of the aspect of the consumption of energy by the petitioners. The matter 
was thereafter carried in appeal by the petitioners to the Second Appellate 
Committee.  The Second Appellate Committee has confirmed the findings 
recorded by the First Appellate Committee by observing that it had no 
reason to differ from the said findings.  In our view, it was not necessary 
for the Second Appellate Committee to go threadbare into the material 
produced by the petitioners before the First Appellate Committee since the 
Second Appellate Committee came to a conclusion that  it agreed with the 
findings of the First Appellate Committee.  Therefore, we do not find any 
substance in the said contention of the learned counsel for the petitioners. 
The AEPC as well as the First Appellate Committee having recorded a 
finding of fact and the same being confirmed by the Second Appellate 
Committee, the same does not warrant any interference.  
17. It is also required to be noted that in terms of the policy 
guidelines, the respondents have given the benefit of rebate of Rs. 5 lakhs 
to the petitioners as originally the amount claimed as and by way of 
forfeiture was Rs. 16 lakhs.   In that view of the matter, no case for 
::: Downloaded on - 26/06/2024 07:31:47 :::

KPP -19-
interdiction in our writ jurisdiction under Article 226 is made out. The 
writ petition is accordingly dismissed. 
18. At this stage, the learned counsel for the petitioners applies for 
stay of the order.  In the facts and circumstances of the case, we stay our 
order for a period of eight weeks on the condition that the petitioners 
keep the bank guarantee alive which has been furnished pursuant to the 
th
interim order passed by this Court on 26  November, 2001 and which is 
alive till today for a further period of 12 weeks from date. 
      P. B. MAJMUDAR, J.
                       R.M. SAVANT, J.
::: Downloaded on - 26/06/2024 07:31:47 :::