Full Judgment Text
IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 12.10.2021
+ O.M.P. (COMM) 130/2021
M/S TOTEM-PREMCO (JV) ..... Petitioner
versus
M/S RAIL VIKAS NIGAM LIMITED ..... Respondent
Advocates who appeared in this case:
For the Petitioner : Mr Ajay Kumar Thakur, Mr Tarun Ghai
and Mr Sujeet Kumar, Advocates.
For the Respondent : Mr Udit Seth and Mr Prateek, Advocates.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1. The petitioner has filed the present petition under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereinafter the ‘A&C Act’)
impugning an Arbitral Award dated 03.06.2020 (hereinafter ‘the
impugned award’) delivered by the Arbitral Tribunal comprising of
three Arbitrators, Mr. M. Ravindra, Major General K.T. Gajria
(Retired) and Justice (Retired) Jaspal Singh, as the Presiding Arbitrator.
Whilst Justice (Retired) Jaspal Singh and Mr. M. Ravindra delivered
the impugned award by majority, Major General K.T. Gajria (Retired)
entered a dissenting opinion on 03.06.2020.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 1 of 24
2. The impugned award has been rendered in the context of disputes
that have arisen between the parties in relation to the Contract
Agreement dated 13.11.2010.
3. By the impugned award, the Arbitral Tribunal entered an award
for a sum of ₹34,43,708. The Arbitral Tribunal further allowed interest
at the rate of 10% per annum on the said amount calculated from
31.12.2015 till realisation. The Arbitral Tribunal did not accept the
petitioner’s claim for refund of the amount recovered by the respondent
by invoking the performance bank guarantee submitted by the
petitioner.
Factual Context
4. On 30.06.2010, Rail Vikas Nigam Limited (hereinafter ‘the
respondent’) issued Notice Inviting Tenders (NIT) for the
“ Construction of New Line between Dankuni-Furfura Sharif via
Jangalpara (20 KM) in Howrah Division of Eastern Railway in the
State of West Bengal, India ” (hereinafter ‘the Project’), on the terms and
conditions stipulated therein.
5. The petitioner entered is a Joint Venture (JV) between Totem
Infrastructure Limited and M/s Premco Rail Engineers Limited. The
petitioner was formed for the purpose of submitting a bid pursuant to
the aforesaid NIT.
6. Pursuant to the said NIT, the petitioner submitted its bid for
executing the project works on 17.08.2010. The petitioner’s bid was
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 2 of 24
accepted by the respondent and a contract for implementation of the
Project for an amount of ₹89,70,13,691.61 was awarded to the
petitioner by the Notification of Award dated 20.09.2010 (hereinafter
‘the NoA’)
7. In terms of the said NoA, the petitioner was called upon to furnish
a Performance Security in accordance with Clause 41.1 of Instruction
to Bidders, for an amount equivalent to 10% of the agreed contract
amount (that is, for an amount of ₹8,97,01,369.16) and further, a Bank
Guarantee in terms of Clause 35.5 of Instruction to Bidders, for an
amount of amount of ₹19,37,779.20. The same were required to be
furnished within twenty-eight days of the receipt of the said NoA. And,
the petitioner furnished the Bank Guarantees as required.
8. Thereafter, on 13.11.2010, the parties entered into an agreement
(hereinafter ‘the Agreement’), whereby the petitioner agreed to
complete the Project within a period of twenty-four months from the
date of commencement of work. The defect liability period was agreed
as six months after the completion of the works
9. By a communication dated 30.11.2010, the petitioner informed
the respondent about the various hindrances existing between “ Take off
Point to Ch:1391 from CSB of Dankuni-Region ”. The petitioner also
requested for a schedule for handing over of land as well as the drawings
for minor bridges, major bridges and station buildings. The petitioner
also stated in the letter that even after the lapse of thirty days from the
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 3 of 24
proposed date of commencement of work, no working stretch was made
available to it.
10. By several communications dated 20.12.2010, the petitioner
informed the respondent about the requisite permissions that were
required for completion of the Project.
11. On 07.06.2011, a meeting was conducted between the petitioner
and respondent to discuss the progress of the work.
12. By a letter dated 30.06.2011, the petitioner requested the
respondent to provide “ hindrance free land along with good for
construction drawings ” as more than nine months had elapsed since
issuance of the NoA and not a single working stretch had been provided
to the petitioner. Further, the petitioner stated that it was incurring huge
losses for the same.
13. By a letter dated 12.11.2011, the respondent informed the
petitioner that four kilometers of stretch of land that would be made
available commencing from the month of December, 2011 from Furfura
Sharif end of the new proposed railway line. The respondent also
indicated the list of items to be executed for the commencement of
work. The respondent requested the petitioner to mobilize equipment
and personnel to take up the work and submit its action plan within a
week’s time.
14. Thereafter, on 13.12.2011, a meeting was conducted between the
parties to discuss the mobilization of personnel and equipment by the
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 4 of 24
petitioner. The said Minutes of the Meeting recorded that the petitioner
would to take over the available site from the respondent on 15.12.2011.
15. By a letter dated 27.12.2011, the petitioner requested the
respondent to handover at least 25% of the total length of the site and
indicate the further schedule of handing over of the balance land in
order for the petitioner to plan and mobilize and start the work at the
desired pace. The respondent responded to the aforesaid letter on
06.01.2011 and requested the petitioner to start the activities at the site
immediately.
16. Thereafter, by a letter dated 06.02.2012, the respondent issued a
notice to the petitioner under Clause 15.1 of GCC, inter alia , stating
that a review would be undertaken of the progress made and based on
assessment of the same, further action, which included action under
Clause 15.2 of the GCC, would be taken.
17. On 21.02.2012, Mr. PK Biswas on behalf of S.N. Bhobde
Associates Ltd. (Project Management Consultant) informed the Chief
Project Manager of the respondent company that “ the contractor is not
willing to take up the work in right earnest and we recommend that
suitable course of action may be taken from your end ”
18. Thereafter, on 24.02.2012, the respondent issued a Notice for
Termination of the Agreement under Clause 15.2 of GCC to the
petitioner.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 5 of 24
19. The petitioner responded to the aforesaid notice on 28.02.2012.
In the said letter, the petitioner stated that due to non-handing over of
the land for complete length of the project and failure to release the due
payments, the notice issued by the respondent was improper and not
tenable. Further, the petitioner also stated that it had incurred
expenditure for the previous year due to non-handing over of the land.
20. Thereafter, on 06.03.2012, a meeting was held between the
representatives of the parties during which the parties agreed that the
work would be executed in accordance with the joint programme, as
agreed. It was also agreed that the respondent would revoke the
Termination Notice dated 24.02.2012, subject to certain agreed
conditions as recorded in the said Minutes of Meeting, which was
jointly signed by the parties.
21. In terms of the agreement between the parties, the respondent
issued a letter dated 16.03.2012, revoking the Termination Notice dated
24.02.2012; setting out the joint work programme; and the conditions
as agreed by the parties.
22. On 18.04.2012 and 02.06.2012, a meeting was conducted
between the officials of the petitioner company, the respondent
company and S.N. Bhobde Associates Ltd., to review the progress of
the work. The respondent claims that the petitioner had failed to execute
the works in accordance with the work programme as agreed.
23. By a communication dated 29.06.2012, the petitioner informed
the respondent about the costs aggregating ₹50,596,545 incurred on
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 6 of 24
account of idle machinery, manpower and equipment due to non-
availability of the site and, requested it to release the aforesaid payment.
24. On 03.10.2012 and 16.10.2012, meetings were conducted
between the parties regarding the progress of the work.
25. On 22.11.2012, the respondent issued a second Notice to Correct
under Clause 15.1 of the GCC to the petitioner. The petitioner
responded to the aforesaid notice on 28.11.2012 and stated that the
aforesaid notice was not ‘justified’ as the petitioner did not have the
required access to the site and had not received the drawings from the
respondent.
26. Thereafter, by a letter dated 12.12.2012, the petitioner informed
the respondent that it was willing to foreclose the Agreement and
requested the respondent to release all dues and eligible payments.
27. By a letter dated 22.01.2013, the respondent terminated the
Agreement in terms of Clause 15.2 of the GCC.
28. Thereafter, on 26.04.2013, the petitioner alleged that the
Agreement was illegally terminated; it claimed that the parties had
agreed to foreclose the same and release the Bank Guarantees.
29. Thereafter, the petitioner approached this Court under Section 9
of the A&C Act (being OMP COMM 68 of 2013) seeking a stay order
on the encashment of Bank Guarantees by the respondent. This Court,
by an order dated 28.01.2013, directed the parties to maintain status-
quo with regard to the Bank Guarantees. However, by an order dated
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 7 of 24
06.12.2013, this Court disposed of the aforesaid petition as the same
had become infructuous in view of the fact that the respondent had
encashed the said Bank Guarantees prior to communication of the order.
30. Since disputes had arisen between the parties, the petitioner, by a
letter dated 31.12.2015, invoked the agreement to refer the disputes to
arbitration in terms of Clause 20.3 of the Agreement and, requested the
respondent to constitute the Arbitral Tribunal within thirty days of the
receipt of this notice.
31. On 27.04.2017, the petitioner approached this Court by way of a
petition under Section 11 of the A&C Act. By an order dated
20.02.2018, this Court directed the respondent to appoint an arbitrator,
and the petitioner to select its nominee arbitrator from the list provided
by the respondent. This Court also directed the nominated arbitrators
to concur on the appointment of the presiding Arbitrator.
32. Thereafter, on 09.03.2018, M. Ravindra and Major General K.T.
Gajria (Retd.) and Justice (Retd.) Jaspal Singh entered reference.
33. The claims made by the petitioner in the Statement of Claims are
summarised as under:-
| Claim No. 1 | ₹2,50,00,000- Payment of work<br>done including the Non<br>Scheduled items |
|---|---|
| Claim No.2 | ₹20,00,000- Payment of the<br>materials lying at site at the time<br>of termination of contract |
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 8 of 24
| Claim No.3 | ₹1,25,00,000-Damages/<br>Compensation on account of<br>delay in the payment of bills |
|---|---|
| Claim No.4 | ₹25,00,000- Refund of interest<br>recovered on the mobilization<br>advance |
| Claim No.5 | ₹75,00,000- Reimbursement of<br>advance paid to the sub-<br>contractors |
| Claim No.6 | ₹25,00,000- Reimbursement of<br>expenditure incurred on<br>providing temporary works at<br>site |
| Claim No.7 | ₹8,54,49,400- Loss of profit |
| Claim No.8 | ₹9,55,40,870- Overhead<br>Expenditure incurred by the<br>Claimant. |
| Claim No. 9 | ₹2,69,10,400- Payment of<br>incentive bonus |
| Claim No. 10 | ₹5,81,000- Reimbursement of<br>Expenditure incurred on<br>payment made to idle labour and<br>idle machinery |
| Claim No.11 | ₹1,00,00,000- Refund of<br>Bidding Security |
| Claim No. 12 | ₹14,69,74,900- Claim in relation<br>to the wrongful encashment of<br>Bank Guarantees |
| Claim No. 13 | Interest at the rate of 18% per<br>annum as per Section 31 of the<br>Arbitration and Conciliation<br>Act, 1996 |
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 9 of 24
| Claim No. 14 | Cost of Arbitration |
|---|
34. The respondent filed its Statement of Defence on 27.07.2018,
however, it did not raise any counter claims.
35. Justice (Retd.) Jaspal Singh and Mr. M. Ravindra rendered the
impugned award on 03.06.2020 partly allowing the claims made by the
petitioner. Major General K.T. Gajria (Retd.) rendered a separate
dissenting opinion on 03.06.2020.
36. The Arbitral Tribunal held that the termination of the Agreement
by the respondent in terms of Clause 15.2 of the GCC could not be
faulted. The Arbitral Tribunal partly allowed the claims preferred by the
petitioner and allowed the refund of ₹49,73,514.00 on account of
mobilization advance and interest thereon; and ₹10,00,000 as refund of
the amount recovered by encashment of the additional Bank
Guarantees. The Tribunal further allowed interest at the rate of 10% per
annum from the date of invocation of arbitration, that is, from
31.12.2015
37. Major General K.T. Gajria (Retd.) dissented from the impugned
award. In his view, the termination of the Agreement by the respondent
was illegal and the petitioner was entitled to ₹25,29,806 towards refund
of interest recovered on the mobilization advance; ₹8,54,49,400 on
account of claim for loss of profit; ₹9,26,39,148 on account of claim for
wrongful encashment of the Performance Bank Guarantee; and
₹24,43,708 towards wrongful encashment of Mobilization Advance
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 10 of 24
Bank Guarantee. In addition to the above, he allowed interest at the rate
of 12% per annum on the awarded amount from 22.01.2013 till the date
of pronouncement of the award. He further directed the said payment
be made within a period of sixty days failing which a further interest of
12% per annum be paid till the date of payment.
38. On 11.06.2020, the respondent filed a petition under Section 33
of the A&C Act seeking correction of the amount awarded by the
Arbitral Tribunal towards the refund of mobilisation advance. The
Arbitral Tribunal allowed the aforesaid application and corrected the
refund due to the petitioner on account of mobilisation advance to
₹24,43,708. Accordingly, the total awarded amount stood revised to
₹34,43,708.
39. Aggrieved by the impugned award, the petitioner has filed the
present petition.
Submissions
40. Mr Thakur, learned counsel appearing for the petitioner focused
his submissions on assailing the impugned award to the extent, that the
Arbitral Tribunal had upheld the respondent’s action of enforcing the
Performance Bank Guarantee of a sum of ₹9,16,39,148/-. He pointed
out that the Arbitral Tribunal had found that the respondent had not
provided complete access to the site as the same required land
acquisition, which was not done. He submitted that the respondent was,
thus, in breach of its obligation of providing complete access within
ninety days of the commencement of the Agreement. The Arbitral
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 11 of 24
Tribunal found that even in respect of the stretch of land available from
the Dankuni Station end, no work could be smoothly executed on
account of changes contemplated in the layout of Dankuni Station.
Notwithstanding the aforesaid findings, the Arbitral Tribunal rejected
the claim of the petitioner for refund of the Performance Bank
Guarantee. He earnestly contended that to this extent, the impugned
award was vitiated on the ground of patent illegality.
41. Next, he submitted that the Arbitral Tribunal had grossly erred
in proceeding on the basis that the Agreement was novated. He stated
that neither of the parties had urged that there was any novation of the
Agreement and thus, the finding to the aforesaid effect, is patently
erroneous.
42. Lastly, he submitted that the finding of the Arbitral Tribunal that
the petitioner had abandoned the work, is also, ex facie, erroneous as
this was not the ground as mentioned in the Termination Notice dated
24.02.2012.
43. Mr Seth, learned counsel appearing for the respondent countered
the aforesaid submissions. He submitted that the respondent had
terminated the Agreement on account of failure on the part of the
petitioner to take preparatory steps for execution of the works. The said
termination was revoked as the petitioner had approached the
respondent and expressed its willingness to execute the works in terms
of an agreed programme and this was recorded in the letter dated
16.03.2012. He submitted that the respondent had specifically pleaded
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 12 of 24
that the parties had modified the Agreement in terms of the aforesaid
agreement as recorded in the Minutes of Meeting dated 06.03.2012. He
also referred to the written submissions filed on behalf of the respondent
before the Arbitral Tribunal to counter the submission that no such case
was canvassed by the respondent before the Arbitral Tribunal.
44. Lastly, Mr Seth submitted that the respondent had led evidence
to establish that the petitioner had abandoned the works and therefore,
the contention that the Arbitral Tribunal’s finding to the aforesaid effect
is without any basis, is erroneous.
Reasons and Conclusion
45. The controversy in the present case falls within a narrow
compass. The principal issue to be addressed is whether the decision of
the Arbitral Tribunal in rejecting the petitioner’s claim for refund of the
Bank Guarantees is patently erroneous as being inconsistent with its
findings.
46. The works to be executed in terms of the Agreement involved
construction of twenty kilometers of a new railway line between
Dankuni-Furfura Sharif via Jangalpara for a total consideration of
₹89,70,30,639.16/-. In terms of Clause 2.1 of the General Conditions of
the Contract (GCC), the respondent had agreed to provide the petitioner
“ right of access to, and possession of, all part of the site within the time
(or times) stated in the Contract Data ”.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 13 of 24
47. Part A of Section VII of the Special Conditions of Contract
(SCC) specified the time within which access to the site would be
provided. In terms of the SCC, the site was agreed to be progressively
handed over in ninety days. Admittedly, the respondent did not
handover the entire site, as agreed. The Arbitral Tribunal held that the
date of commencement was fixed as 01.11.2020 and therefore, the
complete site was required to be handed over by 29.01.2011. The
Tribunal found that “ this could not be achieved due to land acquisition
involved for construction of the railway line” . It further noted that the
new railway line to be constructed, in terms of the Agreement, ran
parallel to the existing railway lines for about 1400 meters taking off
from the Dankuni Railway Station. Thus, this stretch of land did not
involve any issue regarding access to the site. The petitioner was to
commence work at the above stretch of 1400 meters. However, the
Arbitral Tribunal found that the same “ could not materialise as the
layout Dankuni Station was undergoing a change by Eastern Railway
due to which the exact location from where to start the work for the new
railway line was not known ”.
48. The Arbitral Tribunal noted that in the given circumstances, the
respondent had sent a letter dated 12.11.2011 indicating that four
kilometers of stretch of land would be made available commencing
from the month of December, 2011 from Furfura Sharif end of the new
proposed railway line. Thus, access to this site was made available
thirteen months after the date of commencement.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 14 of 24
49. The Arbitral Tribunal held that the petitioner accepted “ change
in the sequence of executing the work and partial access to site being
made available after about 13 months without demur; no precondition
was laid down by it .”
50. The respondent terminated the Agreement by a Termination
Notice issued on 24.02.2012 as according to the respondent, the
petitioner was not taking the requisite steps to execute the Project.
Thereafter, on 06.03.2012, a meeting was held between the
representatives of the parties during which the parties agreed that the
work would be executed in accordance with the joint programme. It was
also agreed that the Termination Notice dated 24.02.2012 would be
revoked subject to certain agreed conditions as recorded in the Minutes
of Meeting held on 06.03.2012, which was jointly signed by the parties.
51. Admittedly, in terms of the agreement as arrived between the
parties on 06.03.2012, the respondent issued a letter dated 16.03.2012
setting out the joint programme to be executed for the initial 800 meters
and revoking the Termination Notice dated 24.02.2012, subject to the
conditions as recorded therein. The said conditions are at the centre of
the controversy in this case. The relevant extract of the said letter dated
16.03.2012, setting out the conditions as agreed between the parties, is
reproduced below:
“Total value of work = Rs.94,87,182/- say one
crore approx. The value of the Additional BG to be
submitted @ 10% = 10 lakhs in five equal instalments of
2 lakhs each as surety for achieving each months
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 15 of 24
programme. The Bank Guarantee shall be submitted by
th
9 March 2012.
M/s TOTEM PROMCO JV has also agreed for the
following conditions:
i) The Bank Guarantee shall be valid up to DDC of
the contract.
ii) In case of failure of achievement of any month
programme, one of the above additional bank
guarantee shall be encashed as penalty.
iii) The above programme is only for the initial 800m
of site from Furfura end handed over to the
contractor till date. Additional work should be done
for the additional site which will be handed over
progressively. For this RVNL reserves the right to
ask for similar time bound programme.
iv) RVNL reserves the right for issuing the termination
notice again after completion of the above period
for poor performance in the above programme.
v) Penalty imposed as defined above shall be
reviewed only on completion of the contract.
vi) The bank guarantee against mobilization advance
which may become due for extension/encashment
should be extended/deposited by the agency along
with the interest as per the contractual provision in
next 7 days time otherwise due bank guarantee
shall be encashed by RVNL.
vii) In case of the shortfall of the progress in concerned
month is made up in any of the following months,
such encashment shall be reversed by RVNL in
full.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 16 of 24
Therefore, the Termination Notice of the contract is
hereby revoked with the approval of Competent
Authority.
S/d
(Anuj Mittal)
Chief Project Manager(Barrackpur )”
52. The Arbitral Tribunal found that in view of the agreement arrived
at between the parties and as recorded in the Minutes of the Meeting
dated 06.03.2012 and the letter dated 16.03.2012, the Termination
Notice dated 24.02.2012 was withdrawn and the Agreement between
the parties underwent an ‘alteration’ or ‘novation’.
53. The Arbitral Tribunal found that the petitioner did not adhere to
the joint work programme and ceased all activities at Furfura Sharif.
The Arbitral Tribunal accepted the respondent’s contention that the
petitioner had abandoned the site and the same entitled the respondent
to terminate the Agreement. The relevant extract of the impugned
award setting out the reasoning and the conclusion of the Arbitral
Tribunal, in this regard, is reproduced below:
“The Tribunal notes that on termination of the Contract,
it was the Claimant who desired for its revival with
willingness to execute the work as per an agreed
program. Details of the commitments made by the
Claimant have been given in paragraph [29] above. The
terminated Contract was revived with effect from
16/03/2012. As would be evident, the Contract
underwent a ‘Noyation’ or ‘Alteration’ with regard to
certain stipulations, namely:
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 17 of 24
1) Commitment to execute work as per the program
detailed, failing which the additional bank guarantee
for Rs. 10 lakhs given would be forfeited. The
Performance Guarantee prescribed in the Contract
and submitted by the Claimant was for performance
of the Contract in its entirety, including the work at
Furfura Shraif. Submission of an additional bank
guarantee specifically for the work at Furfura Sharif,
which work was already covered by the Performance
Guarantee given for the Contract as a whole, is an
Amendment.
2) Obligation to make available access to site
progressively within 90 days of ‘Date of
Commencement’ as provided in Clause 2.1 of the
General Conditions of the Contract was done away
with.
3) Right of the Respondent to issue termination notice
once again if the Claimant failed to adhere to the
agreed program laid down.
[38] The Tribunal notes that while reviving the
terminated Contract with Amendments, the Claimant did
not make or put forward any claim for the delay that had
occurred in making available the site, that is, non-
adherence by the Respondent to the time limit of 90 days
prescribed.
[39] As brought out above, even after revival of the
Contract, work at Furfura Sharif did not progress as
planned. While the Claimant’s contention is that
hinderances continued to exist coming in the way of
execution, the Respondent argues that the cause lay
squarely with the Claimant. A perusal of the evidence on
record supports the Respondent on this rival contention.
Monthly Reports of the Engineer covering the relevant
period establish slowing down of execution by the
Claimant and abandonment of the site in great detail.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 18 of 24
One of the conditions accepted by the Claimant while
reviving the Contract was the right of the Respondent to
terminate the Contract if the Claimant failed to adhere to
the agreed program of execution of work at Furfura
Sharif. In other words, nonperformance at Furfura Sharif
was in itself a sufficient cause for termination of the
Contract. Any assertion that the Respondent had not
provided access to site for the entire stretch of the Project
and thus had no right to termination the Contract, being
in itself in default, would be incorrect (emphasis added).
[40] xxxx xxxx
[41] The Tribunal concludes that the termination of the
Contract by the Respondent due to cessation of all
activities by the Claimant at Furfura Sharif and then
abandoning the site was in order, the Claimant, while
reviving the Contract, having unequivocally entitled the
Respondent to do so. The right to terminate was thus
independent and not circumscribed by any consideration
of access to site being not made available by the
Respondent elsewhere; performance at Furfura Sharif
alone was the criterion. And this has been mentioned by
the Respondent in the correspondence that followed
after termination.
54. The question as to the interpretation of a contract falls squarely
within the jurisdiction of the Arbitral Tribunal. It is also settled law that
a commercial contract is required to be interpreted in the context of the
commercial understanding between the parties.
55. In the present case, the Arbitral Tribunal has interpreted the scope
of the Minutes of the Meeting dated 06.03.2012 and the letter dated
16.03.2012, in terms of which the Termination Notice dated 24.02.2012
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 19 of 24
was revoked and the Agreement was reinstated. Undisputedly, the
contract was required to be understood in accordance with the joint
work programme as agreed between the parties on 06.03.2012 and, also
recorded in the letter dated 16.03.2012. In view of the above, the
conclusion of the Arbitral Tribunal that the original terms of the
Agreement stood altered at least to the extent regarding the manner in
which the site was to be made available and the work to be executed,
cannot be faulted.
56. This Court also finds no ground to interfere with the conclusion
of the Arbitral Tribunal that in terms of the agreement as arrived at
between the parties on 06.03.2012 and as recorded in the letter dated
16.03.2012, it was no longer necessary for the respondent to
immediately make available the entire site to the petitioner. However,
that does not mean that the petitioner was absolved from performing its
obligations under the agreement. The conditions, as agreed under the
letter dated 16.03.2012, clearly provided that the joint work programme
was for the initial 800 meters of the site, from Furfura end, which was
handed over to the petitioner prior to that date. It was further specified
that further work would be done thereafter and, the site for the same
would be handed over progressively. The Arbitral Tribunal found that
the petitioner had failed to perform the work in terms of the joint work
programme as specifically agreed and set out in the letter dated
16.03.2012. Thus, the question of providing access to additional areas
of the site did not arise.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 20 of 24
57. The question of the respondent defaulting in its obligations to
provide access to further site would arise once the petitioner had
executed the works in accordance with the joint work programme.
58. In view of the above, this Court is unable to accept that the
impugned award is vitiated on account of any patent illegality or falls
foul of the public policy of India.
59. The decision of the Arbitral Tribunal to reject the petitioner’s
claim for a refund of the amount of ₹9,16,39,148/-, recovered from
encashment of its Performance Bank Guarantee, cannot be interfered
with in these proceedings. It was contended on behalf of the petitioner
that since the performance of the joint work programme was secured by
Bank Guarantees aggregating to a sum of ₹10,00,000/-, the failure to
perform the said works could result in encashment of the said Bank
Guarantees of ₹10,00,000/- and the respondent could not invoke the
Performance Bank Guarantee furnished initially.
60. The Arbitral Tribunal did not find any merit in the aforesaid
contention. The Arbitral Tribunal noted that in terms of Clause 4.2 of
the General Conditions of the Contract (GCC), the Performance
Guarantee was required to be encashed if the Agreement was terminated
under Clause 15.2 of the General Conditions of the Contract. Thus, in
terms of Clause 4.2 of the GCC, the Performance Guarantee was
required to be encashed in full. The letter dated 16.03.2012 also
expressly recorded that additional Bank Guarantees of ₹10,00,000/-
would be submitted. The word ‘additional’ indicates that the bank
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 21 of 24
guarantees to be furnished in terms of the letter dated 16.03.2012 were
in addition to the existing Performance Bank Guarantee.
61. The question whether the initial Performance Bank Guarantee
could be encashed, is a contentious one, which depends on the
interpretation of the agreed conditions as recorded in the letter dated
16.03.2012. The respondent had not invoked the Performance Bank
Guarantee after the Termination Notice dated 24.02.2012. The Arbitral
Tribunal had interpreted the agreed conditions as recorded in the
Minutes of the Meeting dated 06.03.2012 as well as the letter dated
16.03.2012 and concluded that after revival of the terminated
Agreement, the value or amount of the Performance Security increased
from ₹9,16,39,148/- to ₹9,26,39,148/-. The Arbitral Tribunal also noted
that one of the agreed conditions stipulated by the respondent was that
it reserved its right for issuing a termination notice after completion of
the period covered under the joint work programme for its poor
performance. Since the Agreement was terminated on that ground, the
encashment of the Performance Bank Guarantee was in terms of the
Agreement. However, the Arbitral Tribunal directed the release of the
additional Bank Guarantees since the Performance Security
(Performance Bank Guarantee) covered the Agreement in full. The
relevant extract of the impugned award setting out the reasoning and the
conclusion of the Arbitral Tribunal, in this regard, is reproduced below:
“(c) As brought out above, the Contract was terminated under
Clause 15.2 on 24.02.2012 for the first time for the reason the
Claimant failed to start the work at Furfura Sharif for which
site had been handed over in December, 2011, as also all the
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 22 of 24
data and drawings made available. The ‘Termination Letter’
also brought out above full mobilization advance having been
paid to the Claimant and several meetings held to commence
work.
(d) If the above termination order was not revoked, and the
Contract revived, in terms of Clause 4.2 of the General
Conditions of Contract reproduced above, the Performance
Guarantee in full (that is, Rs. 9,16,39,148/00) could have been
encashed as the Claimant was not commencing work at
Furfura Sharif though it was a part of the overall work covered
by the Contract and covered by the Performance Security
(emphasis added).
(e) However, there was no action by the Respondent to encash
the Performance Guarantee after the above termination order
due to the Claimant expressing its willingness to execute work
as per an agreed programme and terminated Contract was
revived on 16/03/2012. The agreed programme was for work
involved at Furfura Sharif for the 800 m of site made available
and covered the period March, 2012 to June, 2012. The value
of the work was assessed at Rs. 94,87,182/00.
The Claimant provided five additional Bank Guarantees, each
of Rs. 2 lakhs in value and totalling Rs. 10 lakhs, as surety for
execution and valid up to the date of completion of the
Contract. Thus, after revival of the terminated Contract, value
or amount of Performance Security got increased from Rs.
9,16,39,148/00 to Rs. 9,26,39,148/00. Work described in the
agreed programme for which the additional Bank Guarantees
of Rs. 10,00,000/00 in value was given, got covered by two
Performance Securities, one for Rs. 9,16,39,148/00 and
another for Rs. 10,00,000/00 (emphasis added).
To reiterate, as mentioned above, work mentioned in the
agreed programme was a part of the Contract and was thus
covered by the Performance Guarantee given for the Contract
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 23 of 24
as a whole earlier while executing the Contract. (emphasis
added).”
62. The view expressed by the Arbitral Tribunal is certainly a
plausible one and therefore, cannot be interfered with in these
proceedings.
63. The contention that the impugned award is required to be set
aside on the ground that the Arbitral Tribunal had erred in concluding
that the petitioner had abandoned the works, is also unpersuasive. The
finding that the petitioner had abandoned the works is a finding of fact.
The Arbitral Tribunal has returned the said finding after appreciation of
various communications and material on record. The said finding, thus,
warrants no interference in these proceedings.
64. In view of the above, the impugned award cannot be set aside
under Section 34(2A) or Section 34(2)(b)(ii) of the A&C Act. The
petition is, accordingly, dismissed.
VIBHU BAKHRU, J
OCTOBER 12, 2021
RK
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM) 130/2021 Page 24 of 24