Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5865 OF 2018
UTTAR HARYANA BIJLI VITRAN
NIGAM LTD. [UHBVNL] & ANR. … APPELLANTS
VERSUS
ADANI POWER LTD. & ORS. … RESPONDENTS
WITH
CIVIL APPEAL NO. 6190 OF 2018
JUDGMENT
R.F. NARIMAN, J.
1. The appellants in Civil Appeal No. 5865 of 2018 are Uttar Haryana
Bijli Vitran Nigam Ltd. and Dakshin Haryana Bijli Vitran Nigam Ltd.
[collectively referred to as the “ Haryana Discoms ”], which are
distribution licensees in the State of Haryana. The appellant in Civil
Signature Not Verified
Appeal No. 6190 of 2018 is the Gujarat Urja Vikas Nigam Ltd.
Digitally signed by
NIDHI AHUJA
Date: 2019.02.25
16:49:56 IST
Reason:
[“ GUVNL ”], which has been assigned with the task of procuring power
1
by the State of Gujarat. The respondent, Adani Power Ltd., is a
generating company in terms of Section 2(18) of the Electricity Act,
2003 and has a 4620 MW coal-fired power plant at Mundra, District
Kutch, Gujarat. On 23.06.2005, the Special Economic Zones Act, 2005
[“ SEZ Act ”] was enacted. Section 26 of this Act provides that every
Developer shall be entitled to various exemptions, such as duty
leviable under the Customs Act, 1962, Customs Tariff Act, 1975,
Central Excise Act, 1944, etc. The Government of India approved the
respondent as a Co-Developer (which is included within the term
“Developer”). The Ministry of Commerce and Industry [“ MoC&I ”], by a
letter dated 19.12.2006, granted approval to the appellant for setting up
a power plant in the aforesaid SEZ. Thus, the appellant has
established the aforesaid power plant in four phases consisting of four
units of 330 MW in Phase I and II, two units of 660 MW in Phase III,
and three units of 660 MW in Phase IV. The respondent has entered
into various Power Purchase Agreements [“ PPAs ”] with the appellant.
We are concerned in the present case with the PPAs dated 07.08.2008
and 02.02.2007. The MoC&I, vide notification dated 06.04.2015 has
withdrawn the exemption of all duties under the Customs Act, Customs
Tariff Act, Central Excise Act, etc. on goods imported/procured by the
2
respondent for authorized operations w.e.f. 01.04.2015. Equally, vide
notification dated 16.02.2016, fiscal benefits including exemption of
service tax on power plants approved prior to 27.02.2009 was
promulgated, as a result of which, exemption from service tax, to which
the respondent was entitled, has been withdrawn. On 15.10.2015, the
respondent filed Petition No. 235/MP/2015 before the Central
Electricity Regulatory Commission [“ CERC ” or “ Commission ”],
seeking compensation for change in law by invoking Article 13 of the
respective PPAs. On 04.05.2017, the CERC allowed, as a change in
law, the added cost by way of payment of tax consequent to withdrawal
of the exemption notifications thus:
“ 35. …… However, the change in rates of custom duty,
excise duty, withholding tax and service tax on taxable
services which have been imposed pursuant to the Acts
passed by the Parliament shall be covered under
Change in Law. As regards the Green Energy Cess, it
was imposed after the cut-off date and satisfied the
requirements of Change in Law. Accordingly, the
Petitioner shall therefore be entitled for reimbursement of
custom duty, excise duty on import/procurement of any
other goods and service tax on the spares and
consumables payable by it from 1.4.2015 on account of
the withdrawal of exemption to the power plants located
in the SEZ by the Ministry of Commercial [ sic
Commerce] and Industry only to the extent of difference
in the duty or tax as on the cut-off date and as prevailing
as on 1.4.2015 and thereafter.”
3
However, the CERC followed its earlier order dated 06.02.2017 in
Petition No.156/MP/2014, in which it stated that “carrying cost” under
Article 13 of the PPA must be given to the respondent as it is to be
restored to the same economic position as if the change in law – which
is withdrawal of the exemption notifications – did not take place. After
setting out Article 13 of the PPA and distinguishing a Supreme Court
judgment in National Thermal Power Corporation Ltd. v. Madhya
Pradesh State Electricity Board , (2011) 15 SCC 580 [“ National
Thermal Power Corporation Ltd. ”], the Commission came to the
conclusion that there is no provision in the PPA for payment of carrying
cost for the period from the date of the change in law till the date of
approval by the Commission. This being the case, the Commission
held that the prayer of the respondent to grant carrying cost on
restitutionary principles from the date of change in law till the date of
decision cannot be allowed. By the impugned judgment of the
Appellate Tribunal for Electricity [“ Appellate Tribunal ”] dated
13.04.2018, the Appellate Tribunal went through the relevant provisions
of the PPAs and finally observed :
“ x. Further, the provisions of Article 13.2 i.e. restoring
the Appellant to the same economic position as if
Change in Law has not occurred is in consonance with
4
the principle of ‘restitution’ i.e. restoration of some
specific thing to its rightful status. Hence, in view of the
provisions of the PPA, the principle of restitution and
judgment of the Hon’ble Supreme Court in case of Indian
Council for Enviro-Legal Action vs. Union of India & Ors. ,
we are of the considered opinion that the Appellant is
eligible for Carrying Cost arising out of approval of the
Change in Law events from the effective date of Change
in Law till the approval of the said event by appropriate
authority. It is also observed that the Gujarat Bid-01 PPA
have no provision for restoration to the same economic
position as if Change in Law has not occurred.
Accordingly, this decision of allowing Carrying Cost will
not be applicable to the Gujarat Bid-01 PPA.”
Accordingly, carrying cost was allowed and the judgment of the
Commission was set aside.
2. Shri G. Umapathy, learned Advocate, and Shri V. Giri, learned
Senior Advocate, appearing for the appellants in these appeals have
argued before us that the judgment of the Commission was correct and
that since carrying costs are not part of the PPAs in question, any
resort to rules of equity and interest being granted on rules of equity
cannot be resorted to. For this purpose, they relied upon judgments of
this Court. According to them, therefore, the finding of the Appellate
Tribunal ought to be set aside.
5
3. On the other hand, Mr. Mukul Rohatgi, learned Senior Advocate
appearing on behalf of the respondent, supported the Appellate
Tribunal judgment and stated that the Appellate Tribunal has not gone
outside the four corners of the PPA. Since Article 13.2, in particular,
expressly provides a restitutionary principle, the respondents are
entitled to avail of the same.
4. In order to appreciate the respective contentions of the parties, it is
necessary to set out certain provisions of the PPAs. Thus, Articles
11.3.1 and 11.3.4 state as follows:
“ 11.3 Payment of Monthly Bills
11.3.1 The Procurer shall pay the amount payable under
Monthly Bill on the Due Date to such account of the
Seller, as shall have been previously notified by the
Seller to the Procurer in accordance with Article 11.3.3
below.
All payments made by the Procurer shall be appropriated
by the Seller in the following order of priority:
1. towards Late Payment Surcharge, payable
by the Procurer, if any;
2. towards earlier unpaid Monthly Bill, if any;
and
3. towards the then current Monthly Bill.”
xxx xxx xxx
“11.3.4. In the event of delay in payment of a Monthly Bill
by any procurer beyond its Due Date, a Late Payment
Surcharge shall be payable by the Procurer to the Seller
6
at the rate of two (2) percent in excess of the applicable
SBAR per annum, on the amount of outstanding
payment, calculated on a day to day basis (and
compounded with Monthly rest), for each day of the
delay.”
Articles 11.8.1 and 11.8.3 are also important and provide as follows:
“ 11.8. Payment of Supplementary Bill
11.8.1 Either Party may raise a bill on the other Party
(“Supplementary Bill”) for payment on account of:
i. Adjustments required by the Regional Energy
Account (if applicable);
ii. Tariff Payment for change in parameters,
pursuant to provisions in Schedule-5; or
iii. Change in Law as provided in Article 13
and such Bill shall be paid by the other Party.”
xxx xxx xxx
“11.8.3 In the event of delay in payment of a
Supplementary Bill by either Party beyond one month
from the date of billing, a Late Payment Surcharge shall
be payable at same terms applicable to the Monthly Bill
in Article 11.3.4.”
Article 18.17 states as follows:
“ 18.17 No Consequential or Indirect Losses
The liability of the Seller and the Procurer shall be limited
to that explicitly provided in this Agreement. Provided
that notwithstanding anything contained in this
Agreement, under no event shall the Procurer or the
Seller claim from one another any indirect or
consequential losses or damages.”
7
5. Ultimately, the result of this appeal depends upon the
interpretation of Article 13 of the PPAs which is set out in full
hereinbelow:
“ 13. ARTICLE 13 – CHANGE IN LAW
13.1 Definitions
In this Article 13, the following terms shall have the
following meanings:
13.1.1 “Change in Law” means the occurrence of any of
the following events after the date, which is seven (7)
days prior to the Bid Deadline:
(i) the enactment, bringing into effect, adoption,
promulgation, amendment, modification or
repeal, of any Law or (ii) a change in
interpretation of any Law by a Competent Court
of law, tribunal or Indian Governmental
Instrumentality provided such Court of law,
tribunal or Indian Governmental Instrumentality
is final authority under law for such
interpretation or (iii) change in any consents,
approvals or licenses available or obtained for
the Project, otherwise than for default of the
Seller, which results in any change in any cost
of or revenue from the business of selling
electricity by the Seller to the Procurer under
the terms of this Agreement;
but shall not include (i) any change in any
withholding tax on income or dividends
distributed to the shareholders of the Seller, or
(ii) change in respect of UI Charges or
frequency intervals by an Appropriate
Commission.
8
Provided that if Government of India does not
extend the income tax holiday for power
generation projects under Section 80 IA of the
Income Tax Act, upto the Scheduled
Commercial Operation Date of the Power
Station, such non-extension shall be deemed to
be a Change in Law (applicable only in case the
Seller envisaging supply from the Project
awarded the status of “Mega Power Project” by
Government of India).
13.1.2 “Competent Court” means:
The Supreme Court or any High Court, or any tribunal or
any similar judicial or quasi-judicial body in India that has
jurisdiction to adjudicate upon issues relating to the
Project.
13.2 Application and Principles for computing
impact of Change in Law
While determining the consequence of Change in Law
under this Article 13, the Parties shall have due regard to
the principle that the purpose of compensating the Party
affected by such Change in Law, is to restore through
Monthly Tariff Payments, to the extent contemplated in
this Article 13, the affected Party to the same economic
position as if such Change in Law has not occurred.
a) Construction Period
As a result of any Change in Law, the impact of
increase/decrease of Capital Cost of the Project in the
Tariff shall be governed by the formula given below:
For every cumulative increase/decrease of each
Rs.8,90,00,000 [ sic ] (Rupees eight crore ninety lakh
only) Rupees of the Contracted Capacity in the Capital
Cost over the term of this Agreement, the
increase/decrease in Quoted Capacity Charges shall be
an amount equal to zero point two two seven (0.227%)
per cent of the Quoted Capacity Charges. Provided that
the Seller provides to the Procurer documentary proof of
such increase/decrease in Capital Cost for establishing
9
the impact of such Change in Law. In case of Dispute,
Article 17 shall apply.
It is clarified that the above mentioned compensation
shall be payable to either Party, only with effect from the
date on which the total increase/decrease exceeds
amount of Rs.8,90,00,000 [ sic ] (Rupees eight crore
ninety lakh only)
b) Operation Period
As a result of Change in Law, the compensation for any
increase/decrease in revenues or cost to the Seller shall
be determined and effective from such date, as decided
by the Appropriate Commission whose decision shall be
final and binding on both the Parties, subject to rights of
appeal provided under applicable Law.
Provided that the above mentioned compensation shall
be payable only if and for increase/decrease in revenues
or cost to the Seller is in excess of an amount equivalent
to 1% of Letter of Credit in aggregate for a Contract Year.
13.3 Notification of Change in Law
13.3.1 If the Seller is affected by a Change in Law in
accordance with Article 13.2 and wishes to claim a
Change in Law under this Article it shall give notice to the
Procurer of such Change in Law as soon as reasonably
practicable after becoming aware of the same or should
reasonably have known of the Change in Law.
13.3.2 Notwithstanding Article 13.3.1, the Seller shall be
obliged to serve a notice to the Procurer under this
Article 13.3.2 if it is beneficially affected by a Change in
Law. Without prejudice to the factor of materiality or other
provisions contained in this Agreement, the obligation to
inform the Procurer contained herein shall be material.
Provided that in case the Seller has not provided such
notice, the Procurer shall have the right to issue such
notice to the Seller.
13.3.3 Any notice served pursuant to this Article 13.3.2
shall provide, amongst other things, precise details of:
10
(a) the Change in Law; and
(b) the effects on the Seller of the matters
referred to in Article 13.2
13.4 Tariff Adjustment Payment on account of
Change in Law
13.4.1 Subject to Article 13.2, the adjustment in Monthly
Tariff Payment shall be effective from:
(i) the date of adoption, promulgation,
amendment, re-enactment or repeal of the Law
or Change in Law; or
(ii) the date of order/judgment of the Competent
Court or tribunal or Indian Governmental
Instrumentality, if the Change in Law is on
account of a change in interpretation of Law.
13.4.2 The payment for Changes in Law shall be through
supplementary bill as mentioned in Article 11.8.
However, in case of any change in Tariff by reason of
Change in Law, as determined in accordance with this
Agreement, the Monthly Invoice to be raised by the
Seller after such change in Tariff shall appropriately
reflect the changed Tariff.”
6. It will be seen that Article 13.4.1 makes it clear that adjustment in
monthly tariff payment on account of change in law shall be effected
from the date of the change in law [ see sub-clause (i) of clause 4.1], in
case the change in law happens to be by way of adoption,
promulgation, amendment, re-enactment or repeal of the law or
change in law. As opposed to this, if the change in law is on account of
a change in interpretation of law by a judgment of a Court or Tribunal
11
or governmental instrumentality, the case would fall under sub-clause
(ii) of clause 4.1, in which case, the monthly tariff payment shall be
effected from the date of the said order/judgment of the competent
authority/Tribunal or the governmental instrumentality. What is
important to notice is that Article 13.4.1 is subject to Article 13.2 of the
PPAs.
7. Article 13.2 is an in-built restitutionary principle which
compensates the party affected by such change in law and which must
restore, through monthly tariff payments, the affected party to the same
economic position as if such change in law has not occurred. This
would mean that by this clause a fiction is created, and the party has to
be put in the same economic position is if such change in law has not
occurred, i.e., the party must be given the benefit of restitution as
understood in civil law. Article 13.2, however, goes on to divide such
restitution into two separate periods. The first period is the
“construction period” in which increase/decrease of capital cost of the
project in the tariff is to be governed by a certain formula. However, the
seller has to provide to the procurer documentary proof of such
increase/decrease in capital cost for establishing the impact of such
12
change in law and in the case of dispute as to the same, a dispute
resolution mechanism as per Article 17 of the PPA is to be resorted to.
It is also made clear that compensation is only payable to either party
only with effect from the date on which the total increase/decrease
exceeds the amount stated therein.
8. So far as the “operation period” is concerned, compensation for
any increase/decrease in revenues or costs to the seller is to be
determined and effected from such date as is decided by the
appropriate Commission. Here again, this compensation is only
payable for increase/decrease in revenue or cost to the seller if it is in
excess of an amount equivalent to 1% of the Letter of Credit in
aggregate for a contract year. What is clear, therefore, from a reading
of Article 13.2, is that restitutionary principles apply in case a certain
threshold limit is crossed in both sub-clauses (a) and (b). There is no
dispute that the present case is covered by sub-clause (b) and that the
aforesaid threshold has been crossed. The mechanism for claiming a
change in law is then set out by Article 13.3 of the PPA.
9. In Civil Appeal No. 6190 of 2018, the PPA contains Article 13.4 as
follows:
13
“ 13.4 Tariff Adjustment Payment on account of Change in Law
13.4.1 Subject to Article 13.2, the adjustment in Monthly
Tariff Payment shall be effective from:
(a) the date of adoption, promulgation,
amendment, re-enactment or repeal of the Law
or Change in Law; or
(b) the date of order/judgment of the
Competent Court or tribunal or Indian
Governmental Instrumentality, if the Change in
Law is on account of a change in interpretation
of Law.
(c) the date of impact resulting from the
occurrence of Article 13.1.1.
13.4.2 The payment for Changes in Law shall be through
Supplementary Bill as mentioned in Article 11.8.
However, in case of any change in Tariff by reason of
Change in Law, as determined in accordance with this
Agreement, the Monthly Invoice to be raised by the
Seller after such change in Tariff shall appropriately
reflect the changed Tariff.”
It will be seen that sub-clause (c) does not occur in the PPA in Civil
Appeal No.5865 of 2018. As we have held that the present case is
governed by sub-clause (i) of Article 13.4.1, it is obvious that sub-
clauses (b) and (c) have no application to the facts of the present case.
10. A reading of Article 13 as a whole, therefore, leads to the position
that subject to restitutionary principles contained in Article 13.2, the
adjustment in monthly tariff payment, in the facts of the present case,
has to be from the date of the withdrawal of exemption which was done
14
by administrative orders dated 06.04.2015 and 16.02.2016. The
present case, therefore, falls within Article 13.4.1(i). This being the
case, it is clear that the adjustment in monthly tariff payment has to be
effected from the date on which the exemptions given were withdrawn.
This being the case, monthly invoices to be raised by the seller after
such change in tariff are to appropriately reflect the changed tariff. On
the facts of the present case, it is clear that the respondents were
entitled to adjustment in their monthly tariff payment from the date on
which the exemption notifications became effective. This being the
case, the restitutionary principle contained in Article 13.2 would kick in
for the simple reason that it is only after the order dated 04.05.2017
that the CERC held that the respondents were entitled to claim added
costs on account of change in law w.e.f. 01.04.2015. This being the
case, it would be fallacious to say that the respondents would be
claiming this restitutionary amount on some general principle of equity
outside the PPA. Since it is clear that this amount of carrying cost is
only relatable to Article 13 of the PPA, we find no reason to interfere
with the judgment of the Appellate Tribunal.
15
11. We now come to some of the judgments cited by learned counsel
on behalf of both sides. In South Eastern Coalfields Ltd. v. State of
Madhya Pradesh and Ors. , (2003) 8 SCC 648 [“ South Eastern
Coalfields ”], this Court held that interest is payable in equity in certain
circumstances and finally concluded:
“ 24. We are, therefore, of the opinion that in the absence
of there being a prohibition either in law or in the contract
entered into between the two parties, there is no reason
why the Coalfields should not be compensated by
payment of interest for the period for which the
consumers/purchasers did not pay the amount of
enhanced royalty which is a constituent part of the price
of the mineral for the period for which it remained unpaid.
The justification for award of interest stands fortified by
the weighty factor that the Coalfields themselves are
obliged to pay interest to the State on such amount. It
will be a travesty of justice to hold that though the
Coalfields must pay the amount of interest to the State
but the consumers/purchasers in whose hands the
money was actually withheld be exonerated from liability
to pay the interest.”
What was argued by Shri Giri was that this judgment cannot be applied
to fact situations that arise under the PPA in view of Article 18.17 of the
PPA which clearly states that the liability of the seller and the procurer
shall be limited to that explicitly provided in this agreement and that, in
no event, shall either procurer or seller claim any indirect or
consequential losses or damages. Since we have found that the claim
16
for carrying costs is under Article 13 of the PPAs, this judgment would
have no application to the facts of the present case.
12. Shri Giri also relied upon National Thermal Power
Corporation Ltd. (supra), in which, South Eastern Coalfields (supra)
was distinguished in the following manner:
| “ | 25. | In this connection, it is material to note that the claim | ||||||
|---|---|---|---|---|---|---|---|---|
| in | South Eastern Coalfields | [(2003) 8 SCC 648] was | ||||||
| essentially covered under Section 61 of the Sale of | ||||||||
| Goods Act, 1930, and the interest by way of damages | ||||||||
| was payable as per this statutory provision itself. The | ||||||||
| liability had been crystallised and the interest had | ||||||||
| become payable because of the failure to pay the | ||||||||
| amount as per the liability. Besides, there was nothing in | ||||||||
| the agreement between the parties to the contrary on the | ||||||||
| issue of grant of interest. In the present matter, we have | ||||||||
| the second proviso to Regulation 79(2) of the 1999 | ||||||||
| Regulations which permitted the generating company to | ||||||||
| continue to charge the existing tariff for such period as | ||||||||
| may be specified in the notification by the Commission, | ||||||||
| and the notifications permitted continuation of the | ||||||||
| existing tariff as on 31-3-2001, until the final tariff was | ||||||||
| determined. There was no provision for payment of | ||||||||
| interest therein. The very fact that interest came to be | ||||||||
| provided subsequently by a notification under the | ||||||||
| Regulations of 2004 is also indicative of a contrary | ||||||||
| situation in the present matter viz. that interest was not | ||||||||
| payable earlier.” |
13. Article 13 of the PPAs provides for payment of carrying costs,
as held by us above. This judgment also turned on the interpretation of
Regulation 79(2) of the Central Electricity Regulatory Commission
17
(Conduct of Business) Regulations, 1999, and therefore, also has no
manner of application to the facts of the present case.
14. In Indian Council for Enviro-Legal Action v. Union of India
and Ors. , (2011) 8 SCC 161, this Court was concerned with whether a
successful party in a litigation should not be compensated by way of
restitution for deprivation of its legitimate dues. While dealing with
restitutionary principles as applicable in the context of environment
pollution, this Court laid down certain principles in paragraph 197. This
judgment, again, has no manner of application to the facts of the
present case which are confined to the interpretation of Article 13 of the
PPAs.
15. The next judgment relied upon by Shri Giri was All India Power
| Engineer Federation and Ors. v. Sasan Power Ltd. and Ors. | , (2017) |
|---|
1 SCC 487. Paragraph 31 of this judgment was relied upon to state
that in context of Section 63 of the Electricity Act, the Commission
alone can accept amended tariff that would impact consumer interest,
and therefore, public interest, and waiver of any rights of one of the
parties under the PPA, if it impacts such consumer interest, would have
to pass muster under the Commission which would look into all factors
18
and then pass a reasoned order. We fail to see how this judgment has
any application on the facts of the present case as, in the present case,
we are concerned with the interpretation of Article 13 of the PPAs.
16. Lastly, the judgment of this Court in Energy Watchdog v.
Central Electricity Regulatory Commission and Ors. , (2017) 14
SCC 80 was also relied upon. In this judgment, three issues were set
out and decided, one of which was concerned with a change in law
provision of a PPA. In holding that change in Indonesian law would not
qualify as a change in law under the guidelines read with the PPAs,
this Court referred to Clause 13.2 as follows:
“ 57. …… This being so, it is clear that so far as the
procurement of Indian coal is concerned, to the extent
that the supply from Coal India and other Indian sources
is cut down, the PPA read with these documents
provides in Clause 13.2 that while determining the
consequences of change in law, parties shall have due
regard to the principle that the purpose of compensating
the party affected by such change in law is to restore,
through monthly tariff payments, the affected party to the
economic position as if such change in law has not
occurred……”
There can be no doubt from this judgment that the restitutionary
principle contained in Clause 13.2 must always be kept in mind even
19
when compensation for increase/decrease in cost is determined by the
CERC.
17. In this view of the matter, the appeals are accordingly
dismissed.
……………………J.
(R.F. Nariman)
……………………J.
New Delhi (Navin Sinha)
February 25, 2019
20
ITEM NO.1501 COURT NO.6 SECTION XVII
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Civil Appeal No. 5865/2018
UTTAR HARYANA BIJLI VITRAN
NIGAM LTD.(UHBVNL) & ANR. Appellant(s)
VERSUS
ADANI POWER LTD. & ORS. Respondent(s)
WITH
C.A. No. 6190/2018
Date : 25-02-2019
These appeals were called on for pronouncement of judgment today.
For Appellant(s) Mr. Rakesh K. Sharma, AOR
Mr. G. Umapathy, Adv.
Mr. Nishant, Adv.
Ms. Hemantika Wahi, AOR
Mr. Anand Ganeshan, Adv.
Ms. Puja Singh, Adv.
For Respondent(s) Mr. Mukul Rohatgi, Sr. Adv.
Mr. P. S. Narsimha, Sr. Adv.
Mr. Mahesh Agarwal, Adv.
Ms. Neeha Nagpal, Adv.
Ms. Poonam Verma, Adv.
Mr. Abiha Zaidi, Adv.
Ms. Aparajita Upadhyay, Adv.
Ms. Devanshi Singh, Adv.
Mr. Malav Deliwala, Adv.
Ms. Aditi Pathak, Adv.
Mr. Arshit Anand, Adv.
Mr. E. C. Agrawala, AOR
Hon’ble Mr. Justice R. F. Nariman pronounced the
judgment of the Bench comprising His Lordship and Hon’ble
Mr. Justice Navin Sinha.
The appeals are dismissed in terms of the signed
reportable judgment.
(NIDHI AHUJA) (RENU DIWAN)
COURT MASTER (SH) ASSISTANT REGISTRAR
[Signed reportable judgment is placed on the file.]
21